ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/5/2013 BUILDING SURVEY DATE

Size: px
Start display at page:

Download "ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/5/2013 BUILDING SURVEY DATE"

Transcription

1 WEST NEVADA STREET URBANA, ILLINOIS SYSTEM CONDITION INDEX.850 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 2,286,000 LABORATORY BUILDING GROSS SQUARE FEET 29,744 NUMBER OF BUILDING STORIES 2 BUILDING SURVEY DATE CCJM: Josh Polasky (M), Stanley Panek (E) ORIGINAL YEAR OF CONSTRUCTION /5/2013 B U I L D I N G D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y TRADE E X P E C T E D R E M A I N I N G S E R V I C E L I F E FAIR ($) GOOD ($) (5-10 YEARS) (10-20 YEARS) POOR ($) (1-5 YEARS) EXCELLENT ($) (20+ YEARS) TOTAL ($) $/GSF PERCENT OF BUILDING TOTAL (%) MECHANICAL 1,141,500 1,141, PLUMBING 454, , FIRE PROTECTION 13,400 58,100 71, ELECTRICAL 308, , , COMMUNICATIONS 24, , , TOTAL % OF TOTAL CRITICAL ITEM REMEDIATION COST: $4,300 1,943, , ,500 2,286, REFER TO CRITICAL ITEM SUMMARY ON FOLLOWING PAGE. NOTE: Cost Estimates are Construction Costs are in 2013 dollars to Replace in Kind unless otherwise noted PAGE 1

2 C H I L D D E V E L O P M E N T L A B O R A T O R Y C R I T I C A L I S S U E S S U M M A R Y CODE RELATED ITEMS REPAIR COST REPLACEMENT COST REPAIR/ REPLACEMENT % REMAINING LIFE REPAIR OR REPLACE ELECTRICAL Emergency Lighting System Provide emergency lighting with battery back up or generator 4,300 19, Exceeded Replace back-up. CODE RELATED ITEMS COST 4,300 19, NOTE: Cost Estimates are Construction Costs are in 2013 dollars to remediate noted issue. CRITICAL ISSUES COST 4,300 19, Text106 M E C H A N I C A L D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y CHILLED WATER SYSTEM STEAM AND CONDENSTATE SYSTEM SUPPLY AIR SYSTEM HVAC CONTROLS SYSTEM SYSTEM/COMPONENT Cooling System Steam and Condensate System Air Handling System HVAC Controls MECHANICAL TOTAL % OF TOTAL POOR (1-5 YEARS) E X P E C T E D R E M A I N I N G S E R V I C E L I F E FAIR GOOD (5-10 YEARS) (10-20 YEARS) EXCELLENT (20+ YEARS) TOTAL 333, , , , , ,600 32,400 32,400 1,141,500 1,141, PAGE 2

3 Text6 C O O L I N G S Y S T E M A S S E S S M E N T D A T A Item ID Description This building is not attached to the chilled water loop; 3 ton window units provide the majority of cooling to the building. Overall Condition Date Installed 1956 and 1994 Recommendation Comments Room 218 is served by a Carrier split system original to the building (1956, very poor condition). 2 Trane split systems serve 2 children s play areas (rooms #117 and #122). Outdoor units are from 1993 (poor condition), indoor fan boxes appear newer (good condition). Size unavailable. Poor Remaining Useful Life Exceeded Nominal Useful Life: 30 Years Replacement Cost $333,400 Install central AHU and cooling system. Attach building to campus chilled water loop. The 1956 Carrier a/c system is barely functional PAGE 3

4 Text6 C O O L I N G S Y S T E M S U R V E Y P H O T O G R A P H S 1950s Carrier Unit Split System Interior Unit in Main Children s Play Room Trane Split System Another Trane Split System PAGE 4

5 Text6 S T E A M A N D C O N D E N S A T E S Y S T E M A S S E S S M E N T D A T A Description Campus steam serves AHUs, perimeter radiation, and domestic hot water. Piping is original to building (1956). Overall Condition Item ID Date Installed 1/1/ condensate pumps serve system: Bell & Gossett, duplex pump, 20 gpm, 2 2 HP and 2 1 hp. Pump is original (1956), motors and panels have been updated since. Poor condition for age only. Weil Pump Company, no gpm available, hp. Original (1956), poor condition. Poor Remaining Useful Life Exceeded Nominal Useful Life: 30 Years Replacement Cost $127, PAGE 5

6 Text6 S T E A M A N D C O N D E N S A T E S Y S T E M S U R V E Y P H O T O G R A P H S Steam Entry Typical Radiator Bell & Gossett Condensate Pump Weil Condensate Pump PAGE 6

7 Text6 A I R H A N D L I N G S Y S T E M A S S E S S M E N T D A T A Item ID Description 2 AHUs serve building (SF-1 and EF-1), both are original and in poor condition. Both are constant volume, single zone with interior lined ducts. EF-1 is 11,950 cfm. Cfm for SF-1 is unavailable. There are also small AHUs in basement room #11 and near the observation deck on the 2nd floor. Size unknown, poor condition. Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 30 Years Manufacturer American Blower Recommendation Install new central AHU system. Replacement Cost $648,600 Text6 A I R H A N D L I N G S Y S T E M S U R V E Y P H O T O G R A P H S SF-1 EF PAGE 7

8 Text6 H V A C C O N T R O L S A S S E S S M E N T D A T A Description Basic pneumatic controls serve building. Compressor equipment appears to be from late 1990s, fair/poor condition. Piping could be original to building (1956). Overall Condition Date Installed 1/1/1990 Recommendation Item ID Critical Issues Quincy/Pneumatech compressor system (1 HP) has 1-5 years useful life left. Poor Remaining Useful Life Exceeded Nominal Useful Life: 18 Years Replacement Cost $32,400 Install new centralized air handling system with DDCs throughout. Any building renovation should include receptionist area/desk for security purposes. Staff reports building is constantly overheated. Building lacks receptionist desk and controlled entryway PAGE 8

9 Text6 H V A C C O N T R O L S S U R V E Y P H O T O G R A P H S Pneumatic Compressor System Typical Thermostat Thermostats Quincy Compressor PAGE 9

10 Text106 P L U M B I N G D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y DOMESTIC HOT WATER SYSTEM PLUMBING FIXTURES SYSTEM SANITARY WASTE AND VENT SYSTEM SUB-SOIL DRAINAGE SYSTEM SYSTEM/COMPONENT Domestic Hot and Cold Water Plumbing Fixtures Sanitary Waste and Vent Storm and Subsoil Drainage PLUMBING TOTAL % OF TOTAL POOR (1-5 YEARS) E X P E C T E D R E M A I N I N G S E R V I C E L I F E FAIR GOOD (5-10 YEARS) (10-20 YEARS) EXCELLENT (20+ YEARS) TOTAL 125, , , , , ,300 92,200 92, , , PAGE 10

11 Text6 D O M E S T I C H O T A N D C O L D W A T E R A S S E S S M E N T D A T A Item ID Description Domestic water piping is original to building and serves bathrooms, kitchenettes, utility sinks, and a laundry room. Overall Condition Date Installed 1/1/1956 Comments Campus steam serves 2 heat exchangers and a storage tank for domestic hot water. There is a ½ HP circulation pump (poor condition). System is original to the building and in poor condition. Campus steam serves 1 small heat exchanger specifically for laundry room. System is original to building and in poor condition due to age. Poor Remaining Useful Life Exceeded Nominal Useful Life: 50 Years Replacement Cost $125,300 Poor rating is due to age only. Text6 D O M E S T I C H O T A N D C O L D W A T E R S U R V E Y P H O T O G R A P H S Domestic Hot Water Heat Exchangers and Storage Tank Circulation Pump Laundry Heat Exchanger PAGE 11

12 Text6 P L U M B I N G F I X T U R E S A S S E S S M E N T D A T A Item ID Description The building contains bathrooms, kitchenettes, a laundry room, and classroom/utility sinks. Many of the fixtures are child size and all appear original to building (1956). Overall Condition Date Installed 1/1/1956 Comments Toilets = 19 Sinks = Urinals = 1 Fountains = 3 Poor Remaining Useful Life Exceeded Nominal Useful Life: 50 Years Replacement Cost $128,000 Poor rating is due to age only, all fixtures are functional PAGE 12

13 Text6 P L U M B I N G F I X T U R E S S U R V E Y P H O T O G R A P H S Typical Fixtures Children s Toilets Typical Kitchenette Sink Children s Sinks PAGE 13

14 Text6 S A N I T A R Y W A S T E A N D V E N T A S S E S S M E N T D A T A Item ID Description 1 duplex sewage ejector pump in the basement serves the building (2 3 HP). It is original to the building (1956) and in poor condition due to age. Overall Condition Date Installed 1/1/1956 Manufacturer Comments 1 exhaust fan serves each of the 4 following building areas: mechanical room (2000 cfm), bathrooms (1835 cfm), laundry room (550 cfm), and kitchen (1000 cfm). Fans are original to building and in poor condition due to age. Poor Remaining Useful Life Exceeded Nominal Useful Life: 50 Years Recommendation Replacement Cost $109,300 Chicago Pump Company If replacing exhaust fans, kitchen will not need to be treated as full-service. Kitchen was built as full-service but is now only used as a serving space for children s snacks. Text6 S A N I T A R Y W A S T E A N D V E N T S U R V E Y P H O T O G R A P H S Sewage Ejector Pump Pump Tag PAGE 14

15 Text6 S T O R M A N D S U B S O I L D R A I N A G E A S S E S S M E N T D A T A Item ID Description Roof drains are internal. No sump pump was found. Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 50 Years Replacement Cost $92,200 Comments Poor rating is due to age no problems are reported PAGE 15

16 Text106 F I R E P R O T E C T I O N D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y FIRE ALARM SYSTEM STANDPIPE SYSTEM SYSTEM/COMPONENT Fire Alarm System Standpipe FIRE PROTECTION TOTAL % OF TOTAL POOR (1-5 YEARS) E X P E C T E D R E M A I N I N G S E R V I C E L I F E FAIR GOOD (5-10 YEARS) (10-20 YEARS) EXCELLENT (20+ YEARS) TOTAL 58,100 58,100 13,400 13,400 13,400 58,100 71, PAGE 16

17 Text6 F I R E A L A R M S Y S T E M A S S E S S M E N T D A T A Item ID Description Addressable fire arm system with pull stations, horns/strobes and smoke detection Overall Condition Good Date Installed 1/1/2008 Remaining Useful Life 15 Years Nominal Useful Life: 20 Years Manufacturer Siemens Model Number MXL-IQ Replacement Cost $58, PAGE 17

18 Text6 F I R E A L A R M S Y S T E M S U R V E Y P H O T O G R A P H S Fire Alarm Panel Horn/strobe Pull station Smoke detector PAGE 18

19 Text6 S T A N D P I P E A S S E S S M E N T D A T A Item ID Description 2.5 standpipes serve the building at city pressure. Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 50 Years Recommendation Install sprinkler system. Replacement Cost $13,400 Comments Poor rating is due to age. Text6 S T A N D P I P E S U R V E Y P H O T O G R A P H S Connection to Standpipe PAGE 19

20 Text106 E L E C T R I C A L D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y MEDIUM VOLTAGE SYSTEM LOW VOLTAGE SYSTEM EMERGENCY POWER SYSTEM INTERIOR LIGHTING EMERGENCY LIGHTING SYSTEM EXIT LIGHTING SYSTEM EXTERIOR LIGHTING SYSTEM SYSTEM/COMPONENT Substation Low Voltage Distribution System Emergency Power Interior lighting System Emergency Lighting System Exit Sign System Exterior Lighting System ELECTRICAL TOTAL % OF TOTAL POOR (1-5 YEARS) E X P E C T E D R E M A I N I N G S E R V I C E L I F E FAIR GOOD (5-10 YEARS) (10-20 YEARS) EXCELLENT (20+ YEARS) TOTAL 65,000 65, , ,000 47,100 47, , ,500 19,900 19,900 8,000 8,000 9,800 9, , , , PAGE 20

21 Text6 S U B S T A T I O N A S S E S S M E N T D A T A Item ID Description Substation with 150 KVA transformer, 600 A main breaker and (6) circuit breakers. Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 40 Years Equipment Tag Substation Manufacturer Square D Size/Capacity 600 A Voltage 4160 /120/208 V Recommendation Replacement due to age Replacement Cost $65,000 Critical Issues Testing breakers PAGE 21

22 Text6 S U B S T A T I O N S U R V E Y P H O T O G R A P H S Substation in Rm #14 Substation feeder Transformer nameplate Meter PAGE 22

23 Text6 L O W V O L T A G E D I S T R I B U T I O N S Y S T E M A S S E S S M E N T D A T A Item ID Description 120/208 V substation installed in 1956 provides power to panelboards serving lighting, receptacle load and cooling load. Overall Condition Poor Date Installed 1957/1991 Remaining Useful Life Exceeded Nominal Useful Life: 40 Years Equipment Tag - Manufacturer Square D/Federal Pacific Model Number - Serial Number - Size/Capacity 400 A HP/kW - Voltage 120/208 A Material - Recommendation Testing and replacement of 1956 equipment. Replacement Cost $159,000 Critical Issues PAGE 23

24 Text6 L O W V O L T A G E D I S T R I B U T I O N S Y S T E M S U R V E Y P H O T O G R A P H S 1956 panelboard # panelboard #2 1991panelboard # panelboard # PAGE 24

25 Text6 E M E R G E N C Y P O W E R A S S E S S M E N T D A T A Item ID Description Emergency panelboard connected ahead of main service switch provides emergency service for lighting and exit signs Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 25 Years Equipment Tag - Manufacturer Federal Pacific Model Number - Serial Number - Size/Capacity 50 A HP/kW - Voltage 120/208 A Material - Replacement Cost $47,100 Comments Provide emergency power utilizing battery or generator back- up system PAGE 25

26 Text6 E M E R G E N C Y P O W E R S U R V E Y P H O T O G R A P H S Emergency lighting switch( not utilized) PAGE 26

27 Text6 I N T E R I O R L I G H T I N G S Y S T E M A S S E S S M E N T D A T A Description Overall Condition Item ID Date Installed 12/6/2008 Equipment Tag - Manufacturer - Model Number - Serial Number - Size/Capacity - HP/kW - Material - Recommendation - Comments - Critical Issues - Majority of space illuminated by fluorescent surface mounted fixtures. Ballasts and lamps were replaced in 2008.Compact fluorescent fixtures were installed in basement in 1956 fixtures. Good Remaining Useful Life 20 Years Nominal Useful Life: 25 Years Voltage 120 V Replacement Cost $176, PAGE 27

28 Text6 I N T E R I O R L I G H T I N G S Y S T E M S U R V E Y P H O T O G R A P H S Corridor lighting Basement corridor lighting First floor corridor lighting Play room lighting PAGE 28

29 Text6 E M E R G E N C Y L I G H T I N G S Y S T E M A S S E S S M E N T D A T A Item ID Description Emergency lighting includes selected light fixtures connected to emergency circuits. Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 25 Years Replacement Cost $19,900 Comments East play area-no visible emergency lighting when room lights were switched off. Critical Issues Provide emergency lighting with battery back up or generator back-up. Critical Repair Estimate $4,300 Text6 E M E R G E N C Y L I G H T I N G S Y S T E M S U R V E Y P H O T O G R A P H S Dual head battery emergency fixtures#1 Dual head battery emergency fixtures# PAGE 29

30 Text6 E X I T S I G N S Y S T E M A S S E S S M E N T D A T A Item ID Description Original exit signs connected to emergency circuits. Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 25 Years Equipment Tag - Manufacturer - Model Number - Serial Number - Size/Capacity - HP/kW - Voltage 120 V Material - Recommendation - Replacement Cost $8,000 Comments Source of emergency circuits exceeded useful life. Critical Issues Provide exit signs with battery back up. Add signage in play rooms and galleries PAGE 30

31 Text6 E X I T S I G N S Y S T E M S U R V E Y P H O T O G R A P H S Stairway Sign Exit sign in corridor Fire Escape sign PAGE 31

32 Text6 E X T E R I O R L I G H T I N G S Y S T E M A S S E S S M E N T D A T A Item ID Overall Condition Poor Date Installed 1/1/1957 Remaining Useful Life Exceeded Nominal Useful Life: 25 Years Equipment Tag - Manufacturer - Model Number - Serial Number - Size/Capacity - HP/kW - Voltage 208 V Material - Recommendation Replace with more efficient light fixtures. Replacement Cost $9,800 Comments - Critical Issues PAGE 32

33 Text6 E X T E R I O R L I G H T I N G S Y S T E M S U R V E Y P H O T O G R A P H S Front Entry South side of the building Side Entry PAGE 33

34 Text106 C O M M U N I C A T I O N S D I S C I P L I N E R E P L A C E M E N T C O S T S U M M A R Y DATA SYSTEM SECURITY ACCESS CONTROL SYSTEM SYSTEM/COMPONENT Communication Infrastructure System Voice/Data system Access Control System COMMUNICATIONS TOTAL % OF TOTAL POOR (1-5 YEARS) E X P E C T E D R E M A I N I N G S E R V I C E L I F E FAIR GOOD (5-10 YEARS) (10-20 YEARS) EXCELLENT (20+ YEARS) TOTAL 108, ,200 24,900 24,900 24, , , PAGE 34

35 Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M A S S E S S M E N T D A T A Item ID Description The building is fed with 12 strands of single mode fiber and 100 copper pairs with each pair grounded and individually protected by a fuse/surge arrestor. Fiber and copper originate from Node #4. The building IDF is located in room 11 on the lower level. Fiber distributes radially from the building IDF to the hub room (telecommunication room) to within 100 meters of end-use equipment and lands at rack mounted fiber switch(es) within the hub room. Overall Condition There is one hub room, HA located in the lower level of the building in room 2 which serves the entire building. It contains one rack and utilizes basket cable tray for cable management. A dedicated electrical panel feeds the rack which is also connected to a dedicated ground bar to the building grounding system. Cooling is provided by a wall mounted Beckett split cooling system. Outlet standards typically have 1"C stubbed to cable management. Standard outlet consists of two network cables and two data jacks. Station cable consists of Cat 6e (Mohawk Advancenet). The building is typically equipped with WIFI throughout (coverage not noted) Good Date Installed UIUC network upgrade complete (date range 2006 to 2012) Remaining Useful Life 20 Years Nominal Useful Life: 20 Years Text6 C O M M U N I C A T I O N I N F R A S T R U C T U R E S Y S T E M S U R V E Y P H O T O G R A P H S IDF Termination Server Rack, Electrical Panel, Grounding Bar Wall Mounted Split Cooling System PAGE 35

36 Text6 V O I C E / D A T A S Y S T E M A S S E S S M E N T D A T A Item ID Description Infrastructure system includes voice/data outlets at office. Wi Fi antennas provide wireless connection. Overall Condition Fair Date Installed 1/1/2000 Remaining Useful Life 10 Years Nominal Useful Life: 20 Years Equipment Tag - Manufacturer - Model Number - Serial Number - Size/Capacity - HP/kW - Voltage - Material - Recommendation Need for an additional outlets Replacement Cost $108,200 Comments Regular phone and voice over internet has been in use. Critical Issues PAGE 36

37 Text6 V O I C E / D A T A S Y S T E M S U R V E Y P H O T O G R A P H S Typical voice/data outlet Typical Wi Fi antenna PAGE 37

38 Text6 A C C E S S C O N T R O L S Y S T E M A S S E S S M E N T D A T A Item ID Description Buildings do not have access control system Overall Condition Poor Date Installed 1/1/1956 Remaining Useful Life Exceeded Nominal Useful Life: 20 Years Recommendation Provide access/security system connected to campus security Replacement Cost $24,900 Text6 A C C E S S C O N T R O L S Y S T E M S U R V E Y P H O T O G R A P H S Back entrance Exit door PAGE 38

39 Text6 L E G A C Y A S S E T D E S C R I P T I O N : C H I L D D E V E L O P M E N T L A B O R A T O R Y The Child Development Laboratory contains two floors and a basement. The building consists of mechanical and electrical rooms, building service storage, a classroom laboratory, administrative offices, research laboratories, stack areas, a lounge, and a conference room. The Life Safety Code classifies the building as Mixed Occupancy (part Business, part Daycare). The Child Development Laboratory has a manual and automatic fire alarm system. Manual pull stations are on all floors at all exits. Automatic fire detection is located in the second floor (217A, 219A, and 203); first floor (117, 122, and 103); and basement floor (016). There exist no audible or visual devices within the building. There exists a public address system within the building. The fire alarm control panel for the building, located on the first floor east vestibule, is an unidentifiable model. The Child Development Laboratory has no observable emergency lighting or emergency power systems. The Child Development Laboratory is a non-sprinklered building with a Class II standpipe system located in all two floors and the basement. There exists no fire department connection to the building. OCCUPANT LOAD/EXITING Second Floor: 88 occupants; two exits required (3 exits provided); the exit width including stairs/doors provides capacity for 513 occupants. Door and stair widths are sufficient for occupants served. First Floor (LED): 124 occupants; 2 exits required (5 exits provided); 25" exit door width required (154" provided); door and corridor widths are sufficient for occupants served. Basement Floor: 106 occupants; two exits required (4 exits provided); the exit width including stairs/doors provides capacity for 690 occupants. Door and stair widths are sufficient for occupants served PAGE 39

40 C H I L D D E V E L O P M E N T L A B O R A T O R Y L E G A C Y A S S E S S M E N T S U M M A R Y Item ID REQUIREMENT NUMBER INSPECTION DATE IDENTIFIED ISSUE LEGACY VALUE PERCENT COMPLETE GENERAL LEGACY ITEMS ITEMS REQ /8/2002 Doors: Replace Non ADA Compliant Hardware 103, , , REQ /8/2002 ADA: Non-Compliant Kitchenette 6, ,600 6, REQ /8/2002 ADA: Threshold Too High REQ /8/2002 ADA Handrails: Non-ADA Compliant 45, ,700 45, REQ /8/2002 Canopy Ceiling: Remove Suspected Lead 10, ,500 10,500 Paint & Refinish REQ /8/2002 Interior Walls: Paint 27, REQ /8/2002 Flooring: Replace VAT 155, , , REQ /8/2002 Window Wall: Replace Aluminum Framed 78, ,500 78,500 System REQ /8/2002 Windows: Replace Aluminum Framed 95, ,500 95,500 Windows REQ /8/2002 Exterior Doors: Aged 18, ,600 18, REQ /8/2002 Vehicular Pavement: Failing 6, ,600 6,600 Driveway REQ /8/2002 Roof: Replace Built-Up With EPDM 44, ,100 44,100 POOR FAIR CODE TOTAL GENERAL LEGACY ITEMS TOTALS 593, , , ,500 MEP LEGACY ITEMS ITEMS REQ /8/2002 ADA: Restrooms ADA Non-Compliant 127, , ,100 Poor = VFA Priorities 1,2, and 3; Fair VFA Priority 4; and Code VFA Priority 5 MEP LEGACY ITEMS TOTALS 127, , ,100 TOTALS 720, , , ,600 % OF LEGACY VALUE PAGE 40

41 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Interior doors generally have knob style hardware which should be replaced with lever type hardware in accordance with ADA Section Requirement Category Requirement Name Condition Accessibility Doors: Replace Non ADA Compliant Hardware (Legacy) Critical Percent Complete 0.0 Recommendation Replace hardware on Accessible Doors in compliance with ADAAG Section Door Hardware. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 103, Estimated Remaining Cost: 103, Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description The kitchens located in 103 and 121 are not handicap accessible in accordance with UFAS (5). Requirement Category Requirement Name Condition Accessibility ADA: Non-Compliant Kitchenette (Legacy) Critical Percent Complete 0.0 Recommendation Modify kitchennette for ADAAG compliance. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 6, Estimated Remaining Cost: 6, PAGE 41

42 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition ADA section 4.1.6(d)(ii)and ADA Section requires thresholds at one-half inch and if at three-quarters of an inch to be beveled. This threshold is not beveled. Accessibility ADA: Threshold Too High (Legacy) Critical Percent Complete 0.0 Recommendation Replace threshold at indicated location. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost Estimated Remaining Cost: PAGE 42

43 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition ADAAG (11) requires that if toilet facilities are provided then each common use toilet shall be wheelchair handicapped accessible. The common restrooms are not all handicapped accessible per UFAS, ADAAG, and State of Illinois Accessibility requirements. They must be in compliance with ADA Section 4 and and Illinois Accessibility Codes Accessibility ADA: Restrooms ADA Non-Compliant (Legacy) Critical Percent Complete 0.0 Recommendation Existing fixtures in restrooms 102A, 112A, 204, 213 should be replaced with UFAS, ADAAG compliant sinks, blade faucets, toilets and grab bars. Architectural work includes space increase by demolition and reconstruction of walls, repositioning of water closetsand widening of doors to accommodate handicap accessibility. In addition, there are two ladies and one mens room in the basement. The smaller ladies room and the mens room should be combined to create one accessible mens room. The other ladies room in the basement needs to have fixture changes to comply with accessibility standards. The childrens restrooms need an additional sink and faucets that are handicap accessible. A difficulty factor of 40% has been applied to this deficiency to account for known historical data on campus mechanical installations and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 127, Estimated Remaining Cost: 127, PAGE 43

44 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition The handrails in the stairways and/or corridors do not comply with ADA Section 4.26 Figure 39 or which requires continuous railings at stairways. Accessibility ADA Handrails: Non-ADA Compliant (Legacy) Critical Percent Complete 0.0 Recommendation Install handrails to comply with ADA requirements. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 45, Estimated Remaining Cost: 45, Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition The canopy ceiling needs scraping and painting. It is a suspected lead paint finish. Appearance Canopy Ceiling: Remove Suspected Lead Paint & Refinish (Legacy) Poor Percent Complete 0.0 Recommendation Scrape, prep and repaint surface. Remove suspected lead paint A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 10, Estimated Remaining Cost: 10, Action Date 10/8/ PAGE 44

45 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Most of the interior walls and doors need painting. *UIUC Comments: Percent Complete Information _ Small Projects - AFMFA % Complete: Completed on 3/5/ TOUCH UP OR PAINT AS NECESSARY THROUGHOUT BUILDING. FOCUS IN PUBLIC AREAS. _ Small Projects - Cops Excess Earnings 19% Complete _ Small Projects - Cops Excess Earnings 39%: Substantial Completion Date: 4/2010 Total Complete to Date: 99% Requirement Category Requirement Name Condition Appearance Interior Walls: Paint (Legacy) Poor Percent Complete 98.3 Recommendation Scrape, prep and repaint surfaces, doors and trim. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 27, Estimated Remaining Cost: Action Date 10/8/ PAGE 45

46 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition During our investigation we encountered a number of areas throughout the building that may contain asbestos floor tile or linoleum. The flooring in many areas has exceeded its expected useful life and should be replaced. This flooring should be removed and replaced with UIUC approved floor covering (VCT). Asbestos Flooring: Replace VAT (Legacy) Critical Percent Complete 0.0 Recommendation Replace flooring as indicated. Approximately $2 / square foot as provided by Operations and Maintenance A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 155, Estimated Remaining Cost: 155, Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition The present window wall system utilities a single glazed aluminum framework that is original to the building. The frame and glass that have reached the end of their expected useful lives and should be replaced with new more energy efficient system. Integrity Window Wall: Replace Aluminum Framed System (Legacy) Poor Percent Complete 0.0 Recommendation Remove existing aluminum frame, single glazed glass. Install double glazed, insulated frames and glass. First floor only, remaining windows to replaced as part of another deficiency. Note: Type of window selected for budgetary purposes only. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 78, Estimated Remaining Cost: 78, Action Date 10/8/ PAGE 46

47 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition The present units are single glazed original aluminum windows that have reached the end of their expected useful lives and should be replaced with new more energy efficient models. This does not includes the front entrance facade window wall system. Integrity Windows: Replace Aluminum Framed Windows (Legacy) Poor Percent Complete 0.0 Recommendation Remove existing aluminum frame, single glazed windows. Install double glazed, insulated windows. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 95, Estimated Remaining Cost: 95, Action Date 10/8/2007 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition The exterior wood show signs of extreme wear and tear. These units have exceeded their design life expectancy and should be replaced. Integrity Exterior Doors: Aged (Legacy) Poor Percent Complete 0.0 Recommendation Replace the exterior doors (hardware, frames weatherstripping, etc.). A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 18, Estimated Remaining Cost: 18, Action Date 10/8/ PAGE 47

48 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition The asphalt-paved driveway is cracking, heaving, and failing. It needs to be replaced. Integrity Vehicular Pavement: Failing Driveway (Legacy) Poor Percent Complete 0.0 Recommendation Remove existing pavement. Recompact sub-base and base and install new bituminous paving A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 6, Estimated Remaining Cost: 6, Action Date 10/8/2005 Text6 L E G A C Y A S S E S S M E N T D A T A : R E Q Date Inspected 10/8/2002 Description Requirement Category Requirement Name Condition The existing built-up roofing on roofs above the canopies were inspected and exhibited signs of blisters, and aging. Entire roof system will require replacement. Integrity Roof: Replace Built-Up With EPDM (Legacy) Poor Percent Complete 0.0 Recommendation Replace entire existing built-up roof with an EPDM roofing system at indicated locations. A difficulty factor of 20% has been applied to represent typical costs associated with working in older buildings or confined areas, such as higher staging costs, additional demolition, addition physical and equipment resources and may not account for project specific items such as timing requirements, hidden conditions, and the organizing of multiple deficiencies corrections where issues other than costs are the prime considerations. Estimated Cost 44, Estimated Remaining Cost: 44, Action Date 10/8/ PAGE 48

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/4/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/4/2013 BUILDING SURVEY DATE 0218 504 EAST ARMORY AVENUE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.764 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 1,714,300 OFFICE BUILDING GROSS SQUARE FEET

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/19/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/19/2013 BUILDING SURVEY DATE 0154 52 EAST GREGORY DRIVE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.646 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 1,203,500 OFFICE BUILDING GROSS SQUARE FEET

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/6/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/6/2013 BUILDING SURVEY DATE 0222 54 EAST GREGORY DRIVE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.722 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 3,473,300 DISTRIBUTION BUILDING GROSS SQUARE

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/11/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/11/2013 BUILDING SURVEY DATE 0040 1402 WEST PENNSYLVANIA AVENUE URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.685 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 1,364,800 LECTURE HALL BUILDING GROSS SQUARE

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/6/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/6/2013 BUILDING SURVEY DATE 0002 1301 SOUTH GOODWIN AVENUE URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.862 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 746,400 CLASSROOMS / LIBRARY BUILDING GROSS

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/6/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/6/2013 BUILDING SURVEY DATE 0004 1103 SOUTH SIXTH STREET CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.810 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 1,831,000 CLASSROOMS / LIBRARY BUILDING GROSS

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/19/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/19/2013 BUILDING SURVEY DATE 0134 614 EAST PENNSYLVANIA AVENUE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.528 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 495,100 LABORATORY BUILDING GROSS SQUARE

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/18/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/18/2013 BUILDING SURVEY DATE 0238 URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.183 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 1,237,600 OFFICE BUILDING GROSS SQUARE FEET 18,054 NUMBER OF BUILDING

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/08/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/08/2013 BUILDING SURVEY DATE 0171 1503 SOUTH MARYLAND DRIVE URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.770 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 2,686,100 LABORATORY BUILDING GROSS SQUARE

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/17/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/17/2013 BUILDING SURVEY DATE 0039 1114 WEST NEVADA STREET URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.766 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 9,578,600 CLASSROOMS / LIBRARY BUILDING GROSS

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/3/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/3/2013 BUILDING SURVEY DATE 0006 505 EAST AVENUE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.492 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 10,114,300 BUILDING GROSS SQUARE FEET 260,748 NUMBER

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/18/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 6/18/2013 BUILDING SURVEY DATE 0358 1004 SOUTH FOURTH STREET CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.508 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 2,281,700 CLASSROOMS / LIBRARY BUILDING GROSS

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/13/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/13/2013 BUILDING SURVEY DATE 0197 1102 SOUTH GOODWIN AVENUE URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.644 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 11,554,400 LABORATORY BUILDING GROSS SQUARE

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/15/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/15/2013 BUILDING SURVEY DATE 0807 3502 SOUTH FIRST STREET CHAMPAIGN, ILLINOIS SYSTEM CONDITION INDEX.771 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 347,400 LABORATORY BUILDING GROSS SQUARE FEET 16,986

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/10/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/10/2013 BUILDING SURVEY DATE 0110 23 EAST STADIUM DRIVE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.838 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 3,161,900 LABORATORY BUILDING GROSS SQUARE FEET

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/4/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/4/2013 BUILDING SURVEY DATE 0156 504 EAST PENNSYLVANIA AVENUE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.461 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 16,618,500 CLASSROOMS / LIBRARY BUILDING

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/6/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/6/2013 BUILDING SURVEY DATE 0133 608 EAST PENNSYLVANIA AVENUE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.516 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 646,900 PARKING STRUCTURE BUILDING GROSS

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/19/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 4/19/2013 BUILDING SURVEY DATE 0220 500 EAST PEABODY DRIVE CHAMPIAGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.364 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 4,262,400 MUSEUM BUILDING GROSS SQUARE FEET

More information

Listing of Events Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School

Listing of Events Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School Building Events 2004 2005 2006 2007 2008 Total Code Repair Add ventilation to storage room $ 1,000.00 $ - $ - $ - $ - $ 1,000.00

More information

Subject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH)

Subject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH) HIP Housing In Peel Subject: Capital Reserve Expenditure Guidelines Date: August 1, 2012 Applicable To The information contained in this document applies to the following: Municipal & Private Non- Federal

More information

Anson County Early College High

Anson County Early College High NC School District/040 Anson County/High School Anson County Early College High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017

NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017 NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus

More information

Davie County Early College High

Davie County Early College High NC School District/300 Davie County/High School Davie County Early College High Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017

NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017 NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus Dashboard

More information

Pleasantdale Elementary

Pleasantdale Elementary DeKalb County School District/Elementary Schools Pleasantdale Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School

More information

Sagamore Hills Elementary

Sagamore Hills Elementary DeKalb County School District/Elementary Schools Sagamore Hills Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School

More information

Pinebrook Elementary

Pinebrook Elementary NC School District/300 Davie County/Elementary School Pinebrook Elementary Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus

More information

Laurel Hill Elementary

Laurel Hill Elementary NC School District/830 Scotland County/Elementary School Laurel Hill Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

Bob Mathis Elementary

Bob Mathis Elementary DeKalb County School District/Elementary Schools Bob Mathis Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

Social Housing Administration Directive No

Social Housing Administration Directive No Regional Municipality of Halton Social Housing Administration Directive No. 06-05 Date: August 30, 06 To: Federally-Funded Social Housing Providers subject to Operating Agreements under Section 95 of the

More information

Mountain Heritage High

Mountain Heritage High NC School District/995 Yancey County/High School Mountain Heritage High Final Campus Assessment Report March 12, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 7 Campus

More information

Stone Mountain Middle

Stone Mountain Middle DeKalb County School District/Middle Schools Stone Mountain Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

Central Davie Academy

Central Davie Academy NC School District/300 Davie County/High School Central Davie Academy Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus

More information

Anderson Creek Primary

Anderson Creek Primary NC School District/430 Harnett County/Elementary School Anderson Creek Primary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

What did they tell me?

What did they tell me? LBS Insurance Commission Oct 25, 2018 What did they tell me? Handouts from the October 25, 2018 Insurance Town Hall C R. Reynolds 1 High Level Recap of Changes for 2018-19 Deductible $5,000 -> $25,000

More information

Robert Shaw Theme Elementary

Robert Shaw Theme Elementary DeKalb County School District/Elementary Schools Robert Shaw Theme Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School

More information

Harnett Central High

Harnett Central High NC School District/430 Harnett County/High School Harnett Central High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus

More information

BUILDING PERMIT FEES

BUILDING PERMIT FEES BUILDING PERMIT FEES 1. Building Permit Fee Based on the Construction Valuation of the project excluding site work. Refer to Fee Charts below. Electrical, Mechanical and Plumbing permits are not included

More information

Lafayette Elementary

Lafayette Elementary NC School District/430 Harnett County/Elementary School Lafayette Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5

More information

NC School District/430 Harnett County/Elementary School Gentry Primary Final Campus Assessment Report March 11, 2017

NC School District/430 Harnett County/Elementary School Gentry Primary Final Campus Assessment Report March 11, 2017 NC School District/430 Harnett County/Elementary School Gentry Primary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus

More information

Facility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA

Facility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA AGENDA benefits & limitations Rod Moore, RA, LEED AP, PMP Georgia Tech Benjamin Dutton, FFB, MCIOB, MRICS Faithful+Gould GT Facilities GT Program What is GT FCA Deliverables How GT uses FCA Information

More information

Harnett Central Middle

Harnett Central Middle NC School District/430 Harnett County/Middle School Harnett Central Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus

More information

Lilesville Elementary

Lilesville Elementary NC School District/040 Anson County/Elementary School Lilesville Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus

More information

William Ellis Middle

William Ellis Middle NC School District/300 Davie County/Middle School William Ellis Middle Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus

More information

DeKalb Elementary School of the Arts at Terry Mills

DeKalb Elementary School of the Arts at Terry Mills DeKalb County School District/Elementary Schools DeKalb Elementary School of the Arts at Terry Mills Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School

More information

William Bradley Bryant Center

William Bradley Bryant Center DeKalb County School District/Education Other William Bradley Bryant Center Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School

More information

Washingtonville Central School District Building Condition Survey Five Year Plan

Washingtonville Central School District Building Condition Survey Five Year Plan Building Condition Survey Five Year Plan Project Cost Summary Building 2011 2012 2013 2014 2015 Totals 0001 Washingtonville Jr High School $38,759 $325,990 $1,882,653 $1,417,341 $1,025,559 $4,690,302 0002

More information

BUILDING SUBCODE FEES:

BUILDING SUBCODE FEES: Building Sub-code PERMIT FEES TOWNSHIP OF PENNSVILLE 2011 (A 4-2011) 1. Plan review shall be 20% of the amount to be charged for a construction permit. a. The fee for plan review for elevator devices in

More information

DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016

DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016 DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition

More information

Martin Luther King Jr. High

Martin Luther King Jr. High DeKalb County School District/High Schools Martin Luther King Jr. High Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

City School District of Albany Five Year Facilities Plan 3/14/2019

City School District of Albany Five Year Facilities Plan 3/14/2019 Bold indicates change from 3/7/19 BOE meeting Available Local Share $ 3,300,000 1 SPA Air condition gymnasium $ 267,000 1 $ 41,385 $ 41,385 $ 267,000 2 DCS Air condition gymnasium $ 221,000 1 $ 34,255

More information

Building Division Fees 2018

Building Division Fees 2018 Building Division Fees 2018 Permit Administration A permit administration fee of $45.00 shall be assessed for each permit. Staff Consultation Fee $75.00 Administration Determination $90.00 / hour; $23.00

More information

DeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016

DeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016 DeKalb County School District/High Schools Druid Hills High Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School Condition Summary

More information

Reference: The Bel-Harbour Condominium Association Reserve Study Update Kipcon Great Lakes Project No CRU

Reference: The Bel-Harbour Condominium Association Reserve Study Update Kipcon Great Lakes Project No CRU August 18, 2016 Mr. Nicholas Burbulis 420 W. Belmont Ave. Chicago, IL 60657 Reference: The Kipcon Great Lakes Dear Mr. Burbulis: Attached, please find Kipcon Great Lakes, which has been prepared for the.

More information

REPLACEMENT RESERVE GUIDE

REPLACEMENT RESERVE GUIDE CANADA MORTGAGE AND HOUSING CORPORATION REPLACEMENT RESERVE GUIDE What is the Replacement Reserve? The replacement reserve is a fund kept by each housing sponsor under the terms of its operating agreement

More information

CAPITAL RESERVE FUNDING ANALYSIS

CAPITAL RESERVE FUNDING ANALYSIS CAPITAL RESERVE FUNDING ANALYSIS FOR BROADWAY HOUSING, LLC 625 SW Jackson Portland, OR Prepared by: Capital Reserve Consultants, LLC Carson M. Horton, RS April 2014 Copyright 2014 USA / Canada 503 336

More information

TOWNSHIP OF FRANKLIN O-6-18 ORDINANCE AMENDING CHAPTER OF THE CODE OF THE TOWNSHIP OF FRANKLIN- CONSTRUCTION PERMITS

TOWNSHIP OF FRANKLIN O-6-18 ORDINANCE AMENDING CHAPTER OF THE CODE OF THE TOWNSHIP OF FRANKLIN- CONSTRUCTION PERMITS TOWNSHIP OF FRANKLIN O-6-18 ORDINANCE AMENDING CHAPTER 190-2 OF THE CODE OF THE TOWNSHIP OF FRANKLIN- CONSTRUCTION PERMITS WHEREAS, it is the desire of the Township Committee of the Township of Franklin,

More information

Questions by Vendors: District Answers are in Red. Vendor Questions are in Black.

Questions by Vendors: District Answers are in Red. Vendor Questions are in Black. Questions by Vendors: District Answers are in Red. Vendor Questions are in Black. 1. Can we receive a final Excel Sheet of all Facilities that includes physical addresses, square foot info and original

More information

S M A L L S T E P S B I G C H A N G E S

S M A L L S T E P S B I G C H A N G E S page 1 S M A L L S T E P S B I G C H A N G E S 1 CONTENTS PAGE 2 INTRODUCTION 3 SCOPE 2. INTRODUCTION 2 3. SCOPE 2 4. IDEAL LAYOUT 3 5. BASIS FOR BUDGETARY ANALYSIS 4 6. WARD LOCATIONS 5 7. WARD URBAN

More information

OVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE

OVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE MEASURE C SCHOOL SAFETY AND MODERNIZATION On November 3, 2009 the voters residing in the Mill Valley School District (MVSD) approved the Measure C Safety and Modernization Bond of 2009 (Measure C). Measure

More information

THE CLARIDGE OF POMPANO CONDOMINIUM, INC. ARCHITECTURAL REVIEW COMMITTEE REQUEST FOR MODIFICATION PART A - COMPLETED BY OWNER

THE CLARIDGE OF POMPANO CONDOMINIUM, INC. ARCHITECTURAL REVIEW COMMITTEE REQUEST FOR MODIFICATION PART A - COMPLETED BY OWNER THE CLARIDGE OF POMPANO CONDOMINIUM, INC. ARCHITECTURAL REVIEW COMMITTEE REQUEST FOR MODIFICATION PART A - COMPLETED BY OWNER I, of UNIT # request approval by the Architectural Review Committee for the

More information

Urban Heights Condominium

Urban Heights Condominium Condominium Capital 2011 2010, AssociationAnalysis, LLC Condominium Prepared For: Table of Contents Condominium Association, Inc. 1642 Maxwell Road Atlanta, GA 30012 October 19, 2010 INTRODUCTION INTRODUCTION

More information

Mocksville Elementary

Mocksville Elementary NC School District/300 Davie County/Elementary School Mocksville Elementary Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus

More information

Northern Gateway Regional Division No.10 Listing of Events

Northern Gateway Regional Division No.10 Listing of Events Building Events Maintenance Events D2020.01.03 Piping Specialties (Backflow Preventors)** David Ovans Elementary School B3989A Code Northern Gateway Regional Division No.10 Install vacuum breakers on non

More information

Ronald E. McNair Discovery Learning Academy

Ronald E. McNair Discovery Learning Academy DeKalb County School District/Elementary Schools Ronald E. McNair Discovery Learning Academy Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive

More information

Backlog Reduction Plan

Backlog Reduction Plan 2003-2013 Executive Summary proposes to achieve reductions in our facilities maintenance backlog by documenting and completing backlog projects on a priority basis and by minimizing or eliminating future

More information

Protecting your older home

Protecting your older home Protecting your older home HOMEOWNERS INSURANCE Helping you protect your biggest investment: your home At Travelers, we care about our homeowners. We want you to get the most out of the older home you

More information

Hayfield Community Schools Bond Referendum. Vote Monday, September 11, Our Schools Our Communities Our Future

Hayfield Community Schools Bond Referendum. Vote Monday, September 11, Our Schools Our Communities Our Future Hayfield Community Schools 2017 Bond Referendum Vote Monday, September 11, 2017 Our Schools Our Communities Our Future 2017 Bond Referendum What s Already Been Done? Studies and Meetings and Meetings 2014-15

More information

DEPRECIATION REPORT Strata VR 1591 The Leicester West 13th Avenue Vancouver BC V6J 2G5

DEPRECIATION REPORT Strata VR 1591 The Leicester West 13th Avenue Vancouver BC V6J 2G5 DEPRECIATION REPORT 2015 Strata VR 1591 The Leicester 1545 West 13th Avenue Vancouver BC V6J 2G5 Created by Strata Council Members Merry Meredith Tom Heise Antoine Issa The authors have compiled this report

More information

CH-UH Board of Education Meeting. June 27, 2017

CH-UH Board of Education Meeting. June 27, 2017 CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle

More information

All electrical, gas and plumbing applications, together with the fee amount, must be mailed or delivered to:

All electrical, gas and plumbing applications, together with the fee amount, must be mailed or delivered to: Application for Permit to Perform Electrical Work Massachusetts Uniform Application for a Permit to do Gas Fitting Massachusetts Uniform Application for a Permit to Perform Plumbing Work Applications and

More information

Marion County Marion Public County Works Public Building Works Inspection Division

Marion County Marion Public County Works Public Building Works Inspection Division FEE SCHEDULE The final determination of valuation, occupancy, and/or construction type under any of the provisions of this order shall be made by the Building Official. A. Structural Permits: The valuation

More information

1. The fee for plan review shall be due upon completion of subcode review.

1. The fee for plan review shall be due upon completion of subcode review. New Jersey State permit surcharge fees: Amount: This fee shall be in the amount of $0.00334 per cubic foot volume of new buildings and additions. Volume shall be computed in accordance with N.J.A.C. 5:232.28.

More information

Building Permit Fees

Building Permit Fees Permit Center 210 Lottie Street, Bellingham, WA 98225 Phone: (360) 778-8300 Fax: (360) 778-8301 TTY: (360) 778-8382 Email: permits@cob.org Web: www.cob.org/permits Building Permit Fees This handout includes

More information

Yakima County Code ~ Building and Construction ~ Title FEES

Yakima County Code ~ Building and Construction ~ Title FEES 13.24.010 AMENDED FEE TABLES AND FEE SCHEDULES The fee tables and fee schedules contained in the various codes and regulations adopted in this title shall be amended as established herein. *PLAN REVIEW

More information

Howsyth Court Condominium Corporation No. CCN Avenue SW Calgary, Alberta

Howsyth Court Condominium Corporation No. CCN Avenue SW Calgary, Alberta Entuitive Corporation Calgary + Toronto Howsyth Court Condominium Corporation No. CCN9011190 305 25 Avenue SW Calgary, Alberta Submitted By: Entuitive Corporation 209 8 th Avenue SW, Suite 300 Calgary,

More information

Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs

Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Building Bridges to Net Zero Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Evolution of HUD's Green Capital Needs Assessment, and the new CNA etool

More information

Our Focus: Your Future

Our Focus: Your Future Town of Fort Erie Infrastructure Services Our Focus: Your Future Prepared for Council-in-Committee Report No. IS-53-07 Agenda Date November 19, 2007 File No. 220102 Subject 5 YEAR FACILITY CONDITION STATUS

More information

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 Edwin Ataide Deputy Director Plant & Facilities SCH-1 School Projects All Schools Priority FY15 FY16 FY17 FY18 FY19 ADA Compliance (Handicap Accessibility)

More information

NC School District/430 Harnett County/Elementary School Coats Elementary Final Campus Assessment Report March 11, 2017

NC School District/430 Harnett County/Elementary School Coats Elementary Final Campus Assessment Report March 11, 2017 NC School District/430 Harnett County/Elementary School Coats Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus

More information

GLOBAL Solution Partners, LLC - Toll free phone and fax: (844)

GLOBAL Solution Partners, LLC - Toll free phone and fax: (844) GLOBAL Solution Partners, LLC info@globalreservestudies.com - Toll free phone and fax: (844) 477-7883 - www.globalsolutionpartners.com Funding Reserve Analysis for Oak Crest Farms November 2, 2016 Page

More information

CITY OF EL SEGUNDO SCHEDULE B-1 BUILDING & SAFETY FEE SCHEDULE BUILDING PERMIT FEES PROPOSED

CITY OF EL SEGUNDO SCHEDULE B-1 BUILDING & SAFETY FEE SCHEDULE BUILDING PERMIT FEES PROPOSED CITY OF EL SEGUNDO SCHEDULE B-1 BUILDING PERMIT FEES SERVICE PROPOSED FEE RESIDENTIAL BUILDING PERMITS Building Permit Under $500 Valuation $18.00 Building Permit $501-$2,000 Valuation $18 + $2.40 for

More information

CITY OF TAMARAC BUILDING DEPARTMENT Schedule of Permit Fees

CITY OF TAMARAC BUILDING DEPARTMENT Schedule of Permit Fees CITY OF TAMARAC BUILDING DEPARTMENT Schedule of Permit Fees SECTION I: As set forth in Section 105 of the Broward County Amendments to the 5th Edition (2014) Florida Building Code, it is unlawful for any

More information

Reserve Study Transmittal Letter

Reserve Study Transmittal Letter Reserve Study Transmittal Letter Date: January 18, 2012 To: Michael Lee, Collins Management Co. From: Richard Avelar & Associates (RA&A) Re: Bridgewater Condominium Association Attached, please find the

More information

Burlington Area School District Community Survey Results. Winter 2016

Burlington Area School District Community Survey Results. Winter 2016 Burlington Area School District Community Survey Results Winter 2016 Survey Summary The community survey was conducted in December of 2016. Residents within the District were mailed a paper survey. Each

More information

Property Assessment Form Property Data. Servicer and Loan Data

Property Assessment Form Property Data. Servicer and Loan Data Property Data Property Name: Holmead Apartments Property Address: 3435 Holmead Place NW Change from previously reported City: Washington State: DC Zip: 20010 # Units: 101 # Buildings: 1 Year Built: 1951

More information

Physical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15

Physical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15 Physical Plant Five-Year Capital Budget Plan State College Area School District November 2011 Page 1 of 15 Table of Contents Background and 2013 Projects Pages 3-5 Funding Level Pages 6-7 Existing Buildings

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM 104 Office of the President TO MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM AND APPROVAL OF EXTERNAL FINANCING

More information

Reserve Analysis Report

Reserve Analysis Report Reserve Analysis Report Parkway Towers 1155 Ash St Denver, CO 80220 Level I Study with Site Inspection Fiscal Year End Date: 12/31/2014 8597 Via Mallorca Suite E La Jolla, CA 92037 Phone: 858-764-1895

More information

Code Reference: Section , F.S. Chapter ; FS Section ; Responsible Dept.: Community Development/Building Division

Code Reference: Section , F.S. Chapter ; FS Section ; Responsible Dept.: Community Development/Building Division Building Construction Permit Fees 322100 Building Division 341910 Planning Division 341940 Harbor/Code Division 322200/322300 Surcharge Building Permit Fees The governing bodies of local governments may

More information

Educational & Performing Arts Center: Downriver Campus

Educational & Performing Arts Center: Downriver Campus Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed

More information

One and two family residences... $ Mobile Homes... $73.73 Commercial Building... $ All other miscellaneous applications... $44.

One and two family residences... $ Mobile Homes... $73.73 Commercial Building... $ All other miscellaneous applications... $44. EXHIBIT "A" BUILDING PERMITS, HOUSING CODE AND MOBILE HOME PERMIT FEES Page 1 of 9 I. APPLICATION FEES (Non-refundable) One and two family residences... $147.59 Mobile Homes... $73.73 Commercial Building...

More information

Home Buyer Pre Lending Package

Home Buyer Pre Lending Package Home Buyer Pre Lending Package Congratulations on the decision to buy a new home! The most important step in the home buying process is first obtaining a Mortgage Pre-Approval, and to understand the home

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, additions and modernizations, as well as other school related projects. For more than a decade

More information

Update With Site Visit

Update With Site Visit Update With Site Visit Le Chateau Bellevue, WA 10/28/2011 Report #1002 Phone: 253-241-8151 Fax: 360-872-8073 E-mail: jeremy@reservesolutions.net www.reservesolutions.net Le Chateau Client Info: REPORT

More information

Reserve Request Instructions: Documentation Requirements

Reserve Request Instructions: Documentation Requirements Reserve Request Instructions: Documentation Requirements These instructions specify documentation that must be submitted with requests for withdrawals from property reserve accounts held by IHDA. All requests

More information

DeKalb County School District/Middle Schools Peachtree Middle Final School Assessment Report May 20, 2016

DeKalb County School District/Middle Schools Peachtree Middle Final School Assessment Report May 20, 2016 DeKalb County School District/Middle Schools Peachtree Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition

More information

FY17 FMD Capital Budget

FY17 FMD Capital Budget FY17 FMD Capital Budget School Committee Presentation December 2, 2015 Wellesley Facilities Maintenance Department AGENDA Status Update on Capital Projects Role in Capital Planning Capital Planning & Budgeting

More information

Information for Residents of New Brunswick. Table of contents

Information for Residents of New Brunswick. Table of contents Information for Residents of New Brunswick Table of contents Page What s new for 2016?... 2 General information... 2 New Brunswick harmonized sales tax credit... 2 New Brunswick child tax benefit... 2

More information