2009 Bond Project Status Bond Oversight Commi:ee September 2009

Size: px
Start display at page:

Download "2009 Bond Project Status Bond Oversight Commi:ee September 2009"

Transcription

1 2009 Bond Project Status Bond Oversight Commi:ee September

2 ExecuIve Summary 275 total projects, 170 completed as of 9/8/ Program Budget of $150M; Final costs esimated at $ M Majority of projects completed prior to school start or can be done off- hours. ExcepIons: North High School: RenovaIon of 1911 School (May 2011) messe, Johnson, Palmer, and Samuels: New Learning Landscapes (Oct 09) 18 compleions of exising Learning Landscapes (Oct- Nov 09) messe, Henry, Kaiser, Place Bridge, Samuels: Chillers (Sep 09) Kunsmiller Storm drain system, paving (end Sep 09) McMeen and Steele: Elevators (Dec 09) George Washington HS Turf Field: Differing site condiion (Oct 09) Manual and Montebello: Stage LighIng (Oct 09) 2

3 Funding Status November 2008 bond approval $454M $990M maximum repayment cost 7.3% interest rate ceiling ParIal issuance in March 2009 $150M issued 5.1% net effecive interest rate $55M interest savings from ceiling s part of the future issuances of the remaining $304M, DPS is leveraging simulus opportuniies; currently planning two issuances: $24M of Qualified School ConstrucIon Bonds (QSCBs) in Fall 2009 Build merica Bonds (BBs), Iming and sizing yet TBD 3

4 2009 Major Projects Green Valley Ranch K-12 Campus North High School Renovation Learning Landscapes Energy Savings Shared Campus Renovations Fire Detection/Suppression Systems Regional Renovations Early Childhood Education (ECE) Lunchroom Table Replacement Non-Construction Projects 4

5 Green Valley Ranch K- 12 Project Budget: $48.5M - Design-Build Funds fully committed in 2009 Pursuing Silver Level Leadership in Energy and Environmental Design (LEED) certification; Energy consumption reduced by 2/3 Partnered with Xcel Energy for Energy Design ssistance Final bid package and full building permits in October Schedule Jan Feb Mar pr May Jun Jul ug Sep Oct Nov Dec Jan Feb Mar pr May Jun Design 1/15/09 CD 8/15/09 6/25/09 Construction FCD 6/30/10 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 5

6 Green Valley Ranch Mockup for integral color concrete tilt panel Southwest corner of Union building Geothermal piping

7 North High School Project Budget: $24.4M. 3 Phase Project: Phase 1. Relocate/rebuild criical offices; 9th Grade Summer cademy and Freshman cademy moved to Smedley. Complete Phase 2: SelecIve demoliion and asbestos abatement of main building Phase 3: DemoliIon/construcIon/rebuilding of main building and roof Schedule P R M Y J U N J U L U G S E P O C T N O V D E C J N F E B M R P R M Y J U N J U L Y U G S E P T O C T N O V D E C J N F E B M R P R M Y Design 4/15/09 CD 10/19/09 Construc4on 12/15/09 SC 4/15/11 FCD 5/15/11 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 7

8 North High School Landmark Features

9 North High School Not So Landmark Features

10 Learning Landscapes Project Budget: $4.9M 19 parials from 2003 bond; 1 complete, remainder complete o/a 11/1/09 4 new learning landscapes: Johnson, Palmer open 9/25 Samuels (DedicaIon 10/15/09); messe (10/31/09) Schedule 2009 Jan Feb Mar pr May Jun Jul ug Sept Oct Nov Dec 1/27/09 Design CD 6/30/09 School 8/19/09 ConstrucIon SC FCD 6/22/09 11/1/09 11/15/09 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 10

11 Energy Savings Project Budget: $11.9M 26 schools: Scope consists of boilers/chillers/lighing replacement sbestos abatement complete Hot water and steam boilers compleion by 9/30/09 Chiller replacement at messe, Henry, Kaiser, Place Bridge, Samuels: Temporary chillers in place, permanent chillers operaional in September LighIng replacement will coninue through the school year during off hours; Post- installaion energy measurement & verificaion 1/11/10 through 3/12/10; Expect minimum of $210,000 in energy savings per year, plus Xcel rebates Schedule Jan Feb Mar pr May Jun Jul ug Sept Oct Nov Dec Jan 6/4/09 Design CD 6/22/09 School 8/19/09 Construc4on 6/4/09 SC 12/25/10 FCD 1/8/10 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 11

12 Shared Campus RenovaIons Project Budget: $5.5M Kunsmiller, Rishel, Smiley, West renovated to accommodate OSRI programs into exising schools Building and interior renovaions completed prior to school start Punchlist items complete by October 09 ParIIoned buildings to create individual space for programs: Rishel MS, KIPP HS, Math and Science Leadership cademy (MSL) Minor renovaions of Columbine PEC completed 8/31/09 Schedule Dec Jan Feb Mar pr May June Jul ug Sept Oct Nov Design 12/1/08 CD 5/7/09 Construc4on School 8/18/09 5/29/09 SC 8/1/09 buildings FCD 9/1/09 buildings SC FCD 9/14/09 10/15/09 Kunsmiller (storm drain) Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 12

13 Fire DetecIon/Suppression Systems Project Budget: $5.8M 22 projects for replacement of fire detecion/suppression systems, fire department code enhancements 17 fire detecion and alarm control panel projects 4 fire suppression projects Barre: and University Park, Fairview: complete 9/30/09 Steele: complete by 10/9/09 1 fire alarm transmi:ers replacement project across all district faciliies (165) Schedule 2009 Jan Feb Mar pr May June Jul ug Sept Oct Nov Dec 4/21/09 Design CD 7/7/09 School 8/19/09 Construc4on 5/29/09 SC 11/15/09 FCD 12/15/09 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 13

14 Regional RenovaIons Project Budget: $17.1M 113 projects: PainIng, bathrooms, D compliance, new elevators for D access, carpet, Ile, roofing, paving, fencing, bleachers, lighing, door Schedule hardware, turf field Several projects coninuing: - George Washington HS arificial turf field, compleion 10/31/09 - Elevator work at Steele and McMeen, substanial compleion 12/31/09 - Stage lighing replacement at Manual and Montebello, compleion 10/15/ Jan Feb Mar pr May Jun Jul ug Sept Oct Nov Dec Jan Feb 1/23/09 Design CD 5/27/09 School 8/19/09 Project Closeout/Elevator Work Construc4on 5/27/09 SC 12/31/09 FCD 1/26/10 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 14

15 Regional Renovations ll City Stadium Columbine Floor and Column Tile Steele - fter Steele - Before Randolph Telco Room C

16 Early Childhood EducaIon (ECE) Project Budget: $3.1M 9 modular projects completed prior to school start ECE Center (Knight) complete Schedule Nov Dec Jan Feb Mar pril May June July ug Design School 11/15/08 CD 2/5/09 Construc4on 8/19/09 4/20/09 SC FCD 8/4/09 8/15/09 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 16

17 Lunchroom Table Replacement Project Budget: $2.0M 38 schools received new lunch tables, chairs Schedule 2009 Jan Feb Mar pril May June July ug School 8/19/09 Construc4on 6/15/09 FCD 8/14/09 Design Date () / Comple4on Date (CD) Construc4on Date () / Substan4al Comple4on Date (SC) / Final Comple4on Date (FCD) Milestone/ Key Date 17

18 Diversity Program Bond Program Performance to Date Outstanding: Professional Services: 33.2% Diverse Spend General ContracIng: 46.5% Diverse Spend

19 2009 Construction Summary Despite late start, majority of projects finished; no school openings delayed, but Need to stay on top of compleions Bidding climate excellent; expect to coninue through 2010 => move projects forward RecruiIng/training to prepare for 2010 ExecuIng a deliberate process to deliver 2010; applying 2009 lessons learned

20 Non- ConstrucIon Projects Enterprise Technology Projects InstrucIonal Management System Project budget: $2.3M 2009 project to purchase and implement Schoolnet soqware within the Teacher & dministrator portals llows access to student data, performance, curricular & instrucional resources Principal Portal launched in January 2009 Teacher Portal beta tesing underway at Gust and Steck Holm, Montclair, Place idenified as pilots for September trials Extensive roll- out begins with elementary schools in January- February 2010 Hardware and infrastructure Project budget: $450,000 Replacement of end- of life enterprise servers and storage systems Replacement of over 10,000 school based phones with VoIP phones Bids to be released in October, work to begin in January

21 Non- ConstrucIon Projects EducaIonal Technology Project budget: $4.0M Provides Promethium boards, computers, document cameras, projectors, etc, to incorporate technology into classrooms Funding allocated to schools based on enrollment and technological inventory Remaining 40 schools must submit a technology purchase plan to DoTS by 10/31/09 Schools have expended $1.65M as of 9/8/09 Hazmat/Environmental Project budget: $1.75M sbestos abatement occurs as part of work on boilers, floor and ceiling Iles, pipe insulaion, plaster, paint Soil samples on learning landscape projects Removal of hazmat items from each project Security Project budget: $1.1M Security camera interface conversion from analog to digital Replacement of site- based DVR systems to centralized network storage Replace burglar alarm phone lines with IP connecions at each school Work to begin January

22 2010 Projects (In Planning) ConInuing projects Green Valley Ranch North High School Baseline Projects InstallaIon of 13 new learning landscapes 2010 ESCO energy savings contract(s) 34 projects for installaion of energy efficient boilers, chillers, lighing and windows across 15 schools 7 fire detecion/suppression projects across 7 schools 56 facility renovaion projects across 20 schools Exploring opions to pull 39 projects forward to take advantage of favorable construcion environment 22

APPENDIX A FULL TEXT OF BOND MEASURE

APPENDIX A FULL TEXT OF BOND MEASURE APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass

More information

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017 Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By

More information

Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182

Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Operational Services/Central Services/Axtell Park School

More information

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report

ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report ORANGE UNIFIED SCHOOL DISTRICT Measure S Bond Program September 2017 Monthly Progress Report PERIOD COVERED: September 1 30, 2017 FISCAL YEAR FY 2017 2018 PROGRESS REPORT NO. PR 03 1718 003 PREPARED BY:

More information

Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...

Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... 10 Ballot Measure EXHIBIT B MEASURE Y (ABBREVIATED FORM)

More information

Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016

Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016 Campus Construction Program Report WLAC Monthly Facilities Committee Meeting February 22, 2016 1. Cost Update 2. Schedule Update 3. PreDesign Update 4. Design Update 5. Contractor Procurement Update February

More information

Ballot Measures-T Section

Ballot Measures-T Section T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and

More information

Contents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure...

Contents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure... Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 6 Impartial Analysis... 7 Statement in Favor of Measure... 8 Ballot Measure EXHIBIT A HANFORD ELEMENTARY SCHOOLS REPAIR

More information

SPACE UTILIZATION STUDY ANALYSIS November 5, 2013

SPACE UTILIZATION STUDY ANALYSIS November 5, 2013 SPACE UTILIZATION STUDY ANALYSIS November 5, 2013 Space Utilization Study Analysis Ongoing questions regarding enrollment and the use of our facilities 2010 an internal analysis was performed with no decisions

More information

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS OCTOBER 18-19, 2017 REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS Actions Requested: Consider recommending to the Board approval of the: 1. Following actions for the Knoll

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010 OVERVIEW The following is a summary of the financial highlights contained in the second quarter report for fiscal year 2010-11: Cash and Accounts

More information

Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175

Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Special Education Allocation 176 Operational Services Allocation

More information

Physical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15

Physical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15 Physical Plant Five-Year Capital Budget Plan State College Area School District November 2011 Page 1 of 15 Table of Contents Background and 2013 Projects Pages 3-5 Funding Level Pages 6-7 Existing Buildings

More information

Building and Site Sinking Fund Millage. Election Date: November 7th 2017

Building and Site Sinking Fund Millage. Election Date: November 7th 2017 Building and Site Sinking Fund Millage Election Date: November 7th 2017 How do Districts Fund Facilities and Technology Needs? General Fund - Use current operating dollars. These are limited to the amount

More information

The Beverly Middle School Flexible Learning Academy

The Beverly Middle School Flexible Learning Academy Transformative Learning Through Architecture The Beverly Middle School Flexible Learning Academy Flexible Classroom Studios FLEXIBLE ACADEMY Flexible Configurations Flexible Support Exhibits Cross Discipline

More information

Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent

Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Tumwater University School District Budget Myths Bond Project Update February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Construction Update $136,000,000 in bonds approved

More information

Budget Workshop #3

Budget Workshop #3 2018-19 Budget Workshop #3 March 22, 2018 Overview 1. Budget Gap Update 2. Projected Elementary Sections 3. Proposed Staffing 4. Remaining Preliminary Expenditures 5. Funding Sources 6. Review 2018-19

More information

Educational & Performing Arts Center: Downriver Campus

Educational & Performing Arts Center: Downriver Campus Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed

More information

Schenectady City School District

Schenectady City School District Schenectady City School District Mosaic Associates Architects Callie Gaspary, AIA Kersten Lorcher, AIA Hamlin Design Group Shawn Hamlin, AIA Turner Construction Larry Tune 19 November, 2014 CAPITAL PROJECT

More information

Ballot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools

Ballot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools Section Ballot Measures-N N Centralia Elementary School District, Building Strong Neighborhood Schools To repair/modernize aging classrooms, science labs/school facilities to keep pace with technology,

More information

JACKSON-MADISON COUNTY SCHOOL SYSTEM FUND #177 EDUCATION CAPITAL 5-YEAR PLAN (WORKING COPY)

JACKSON-MADISON COUNTY SCHOOL SYSTEM FUND #177 EDUCATION CAPITAL 5-YEAR PLAN (WORKING COPY) Elementary & K-8 Campuses Alexander 6 8 Guttering replacement 2 $ 20,000 HVAC replacement 1 $ 800,000 Remove and replace old glass block windows 3 Total for Alexander $ - $ 20,000 $ 800,000 $ - $ - $ -

More information

Community College District. Measure M

Community College District. Measure M Community College District Measure M Monthly Report October 2015 San Bernardino Community College District Program Management Measure M Monthly Report October 2015 1. Valley Campus Project Sheets 2. Crafton

More information

TROY CITY SCHOOLS. Community Advisory Team. Meeting #2, April 4th, Troy City Schools

TROY CITY SCHOOLS. Community Advisory Team. Meeting #2, April 4th, Troy City Schools TROY CITY SCHOOLS Community Advisory Team Meeting #2, April 4th, 2017 1 170404TroyCAT.key - April 5, 2017 Welcome Eric Herman, Superintendent 2 170404TroyCAT.key - April 5, 2017 Purpose: To understand

More information

Cecil County Public Schools Board of Education Proposed Budget

Cecil County Public Schools Board of Education Proposed Budget Cecil County Public Schools Board of Education Proposed Budget County Council Presentation April 12, 2016 Fiscal 2017 Operating Fund Capital Fund Debt Service Fund Budget Prioritization Survey Results

More information

Anson County Early College High

Anson County Early College High NC School District/040 Anson County/High School Anson County Early College High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018 OVERVIEW Financial highlights of the fiscal year 2018-19 1 st quarter financial report are summarized below: Cash (pages 2-3) The University

More information

Unrestricted Cash / Board Designated Cash & Investments December 2015

Unrestricted Cash / Board Designated Cash & Investments December 2015 Unrestricted Cash / Board Designated Cash & Investments December 2015 25.0 21.0 20.0 19.5 18.9 18.1 16.8 16.5 15.9 15.0 10.0 11.0 12.8 9.1 10.4 9.8 11.1 14.7 14.2 14.1 9.9 12.0 8.4 13.0 10.2 11.6 14.9

More information

Cherry Hill Board of Education

Cherry Hill Board of Education Cherry Hill Board of Education ENERGY SAVINGS PLAN (ESP) PRESENTATION JANUARY 15, 2013 Presented By: Tom Xenakis, PE - Vice President, Commercial John Marchiafava, PE - Engineering Manager, Commercial

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

FY2019 MEIF / Auxiliary Services / E&G Budget Discussion

FY2019 MEIF / Auxiliary Services / E&G Budget Discussion 1 of 20 FY2019 MEIF / Auxiliary Services / E&G Budget Discussion Kody Varahramyan Vice President for Research and Dean of the Graduate School Susan J. Hunter President Claire Strickland Chief Business

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

2019 Capital Projects Plan

2019 Capital Projects Plan Rev. 03/18 School Name Crawford County Community School Corporation County Name Crawford School No. 1300 2019 Capital Projects Plan The following plan format should be used for your 2019 Capital Projects

More information

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 Edwin Ataide Deputy Director Plant & Facilities SCH-1 School Projects All Schools Priority FY15 FY16 FY17 FY18 FY19 ADA Compliance (Handicap Accessibility)

More information

Harnett Central High

Harnett Central High NC School District/430 Harnett County/High School Harnett Central High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus

More information

Capital Projects Completed since 1988

Capital Projects Completed since 1988 Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990

More information

Ballot Measures-LL Section

Ballot Measures-LL Section LL To repair and modernize aging classrooms/school facilities at local elementary/intermediate schools, repair termite damage, dry rot, deteriorating roofs, plumbing, and electrical, improve student safety/security,

More information

OVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE

OVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE MEASURE C SCHOOL SAFETY AND MODERNIZATION On November 3, 2009 the voters residing in the Mill Valley School District (MVSD) approved the Measure C Safety and Modernization Bond of 2009 (Measure C). Measure

More information

Original Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000

Original Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000 Page 1 of 20 FACILITIES PLAN STATUS REPORT June 27, 2016 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning

More information

Central Michigan University Capital Budget

Central Michigan University Capital Budget Central Michigan University Capital Budget 1999-2000 Table of Contents Central Michigan University Capital Budget Table of Contents I. Narrative A. Overview and Process...1 B. Funding Sources...2 C. Capital

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, additions and modernizations, as well as other school related projects. For more than a decade

More information

Laurel Hill Elementary

Laurel Hill Elementary NC School District/830 Scotland County/Elementary School Laurel Hill Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

Subject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH)

Subject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH) HIP Housing In Peel Subject: Capital Reserve Expenditure Guidelines Date: August 1, 2012 Applicable To The information contained in this document applies to the following: Municipal & Private Non- Federal

More information

CH-UH Board of Education Meeting. June 27, 2017

CH-UH Board of Education Meeting. June 27, 2017 CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle

More information

Allan Hancock Joint Community College District

Allan Hancock Joint Community College District One Stop Studen Allan Hancock Joint Community College District One Stop Student Services Public S Public Safety Com Public Safety Complex Childc Childcare Addit Childcare Addition BOND MEASURE I Progress

More information

Monthly Report. April 2017

Monthly Report. April 2017 Monthly Report April 2017 El Paso ISD Bond Program Program Manager: Jacobs Table of Contents Report Date: 04/30/2017 Understanding the Monthly Report... 3 Executive Summary. 7 Program Report by Phase...

More information

Foundations of Investing

Foundations of Investing www.edwardjones.com Member SIPC Foundations of Investing 1 5 HOW CAN I STAY ON TRACK? 4 HOW DO I GET THERE? 1 WHERE AM I TODAY? MY FINANCIAL NEEDS 3 CAN I GET THERE? 2 WHERE WOULD I LIKE TO BE? 2 Develop

More information

Action Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List

Action Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List Action Item TO: PRESENTED BY: BOARD AGENDA ITEM: Board of Trustees and Superintendent of Schools Sid Albaugh, Assistant Superintendent Business Services Consideration of Approval of 2018 Measure A Facilities

More information

Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs

Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Building Bridges to Net Zero Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Evolution of HUD's Green Capital Needs Assessment, and the new CNA etool

More information

May 30, 2018 Page 2 of 2 NOTICES:

May 30, 2018 Page 2 of 2 NOTICES: 4»»scv WATER Date: May 30, 2018 To: Engineering Committee Dean Efstathiou, Chair Tom Campbell Ed Colley William Cooper Gary Martin From: Brian J. Folsom Chief Engineer The Engineering Committee is scheduled

More information

Department of Education s budget background and process for the Fiscal Biennium

Department of Education s budget background and process for the Fiscal Biennium UPDATE Department of Education s budget background and process for the 2017-2019 Fiscal Biennium BOARD OF EDUCATION Finance and Infrastructure Committee August 16, 2016 Education breeds confidence. Confidence

More information

2000 Branch Library Improvement Bond

2000 Branch Library Improvement Bond 2000 Branch Library Improvement Bond QUARTERLY REPORT Second Quarter 2011 April - June Anza Branch Library Opened June 18, 2011 Prepared by: Amber Vasché, Management Assistant Finance & Accounting, 557-4667,

More information

Hayfield Community Schools Bond Referendum. Vote Monday, September 11, Our Schools Our Communities Our Future

Hayfield Community Schools Bond Referendum. Vote Monday, September 11, Our Schools Our Communities Our Future Hayfield Community Schools 2017 Bond Referendum Vote Monday, September 11, 2017 Our Schools Our Communities Our Future 2017 Bond Referendum What s Already Been Done? Studies and Meetings and Meetings 2014-15

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 OVERVIEW Financial highlights of the 3 rd quarter financial report for fiscal year 2011-12 are summarized below: Cash The University s cash

More information

There hasn t been a bond referendum in our district since building the original facility in 1977.

There hasn t been a bond referendum in our district since building the original facility in 1977. The architect concept in this document was drawn by Howard & Helmer Architects (H&H) after several community, staff and board meetings over the last year. This concept plan was chosen after reviewing 5

More information

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. PMO Annual Update

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. PMO Annual Update Los Angeles Community College District PROGRAM MANAGEMENT SERVICES PMO Annual Update District Citizens Oversight Committee October 9, 2015 1 One Goal: Strong Program Finish ON TIME ON BUDGET NO LITIGATION

More information

Investing in Our Schools:

Investing in Our Schools: Investing in Our Schools: History of Measures A & B & Potential New Bond Facilities Workshop Special Board Meeting July 13, 2010 Cindy Cathey, Superintendent Song Chin-Bendib, Assistant Superintendent,

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 06/30/2017

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 06/30/2017 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 06/30/2017 OVERVIEW Financial highlights of the fiscal year ending June 30, 2017 financial report are summarized below: Cash (pages 2-3) The University

More information

SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S

SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S Under this measure, the Somis Union School District ( District ) is submitting a bond measure, described below, to the voters

More information

Overview of Public Schools CIP

Overview of Public Schools CIP Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, such as additions and modernizations, as well as other school-related projects. School construction

More information

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019

School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019 School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year 2018-19 February 21, 2019 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...

More information

Unrestricted Cash / Board Designated Cash & Investments December 2014

Unrestricted Cash / Board Designated Cash & Investments December 2014 Unrestricted Cash / Board Designated Cash & Investments December 2014 25.0 20.0 21.0 20.8 18.9 19.9 15.0 10.0 11.5 12.8 11.6 9.1 10.4 9.8 11.1 10.2 9.8 17.0 16.8 15.4 14.7 14.2 14.1 13.6 13.0 12.0 10.2

More information

Physical Plant. Detailed Assessment Report

Physical Plant. Detailed Assessment Report Physical Plant Detailed Assessment Report 2011-2012 Mission / Purpose The Physical Plant Department enhances the University of West Alabama's mission to provide opportunities for students to pursue a quality

More information

Anderson Creek Primary

Anderson Creek Primary NC School District/430 Harnett County/Elementary School Anderson Creek Primary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

Progress Update Identified Needs & Capital Plan

Progress Update Identified Needs & Capital Plan Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary

More information

Comprehensive Facilities Assessment School Committee

Comprehensive Facilities Assessment School Committee C A N T O N P U B L I C S C H O O L S Comprehensive Facilities Assessment 3.23.2017 School Committee A g e n d a Introductions Schedule & Process Overview Progress Update Enrollment Targets Facilities

More information

Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160

Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 - Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 Special Education Allocation 161 Operational Services

More information

Weston Public Schools PROPOSED BUDGET OF EXPENDITURES

Weston Public Schools PROPOSED BUDGET OF EXPENDITURES Weston Public Schools PROPOSED BUDGET OF EXPENDITURES 2012-2013 School Facilities 2012-2013 Budget Presentation Please refer to pages 111-117 in the Budget Binder Budget Preface The Past: Unreliable boilers

More information

FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING

FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Page 1 of 11 FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects

More information

Davie County Early College High

Davie County Early College High NC School District/300 Davie County/High School Davie County Early College High Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary

More information

Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619)

Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619) Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA 91911 (619) 691-5553 FAX (619) 420-0339 Prop O Project Summary page 1 General for CBOC Meeting of January 20, 2016 1 2 date info

More information

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016

DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

2000 Branch Library Improvement Bond

2000 Branch Library Improvement Bond 2000BranchLibraryImprovementBond QUARTERLYREPORT Thirdquarter2009 JulySeptember InglesideBranchLibrary OpenedSeptember12,2009 PhotosbyBrianWong Building better libraries for stronger communities Table

More information

4-H Financial Forms. These forms match those in the 4-H Treasurer's Manual (4H1035, rev 5/2003)

4-H Financial Forms. These forms match those in the 4-H Treasurer's Manual (4H1035, rev 5/2003) 4-H Financial Forms These forms match those in the 4-H Treasurer's Manual (4H1035, rev 5/2003) Form 6.1-4-H YDP Monthly Report Form Form 6.2 - Annual Inventory Report Form 6.3 - Annual Financial Report

More information

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017

Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017 Projections/Estimated - Unrestricted Cash / Board Designated Cash & Investments September 2017 25.0 20.0 17.1 16.9 15.0 10.0 11.7 11.0 9.1 10.1 9.7 7.7 7.0 6.8 15.1 14.8 11.5 13.1 13.8 9.9 11.4 12.2 8.4

More information

Burlington Area School District Community Survey Results. Winter 2016

Burlington Area School District Community Survey Results. Winter 2016 Burlington Area School District Community Survey Results Winter 2016 Survey Summary The community survey was conducted in December of 2016. Residents within the District were mailed a paper survey. Each

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2017

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2017 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2017 OVERVIEW Financial highlights of the fiscal year 2016-17 3 rd quarter financial report are summarized below: Cash (pages 2-3) The University

More information

Building Fund Report Inception to date, through November 15, 2018

Building Fund Report Inception to date, through November 15, 2018 1 Briargate Preschool BUDGET FF 26,950.00 25,777.66-1,172.34 95.65% TOTAL 26,950.00 25,777.66-1,172.34 95.65% Academy Calvert Online (K-5) BUDGET Academy Endeavor Elementary BUDGET FF 244,546.00 189,111.73

More information

Reserve Study Project No Prepared for Nelson Farm Homeowner Association 1771 Norwood Lane Fort Collins, Colorado

Reserve Study Project No Prepared for Nelson Farm Homeowner Association 1771 Norwood Lane Fort Collins, Colorado Reserve Study Project No. 09069 Prepared for 1771 Norwood Lane Fort Collins, Colorado Prepared by Bornengineering 1130 West 124 th Avenue, Suite 100 Westminster, Colorado 80234 January 28, 2010 1130 WEST

More information

DESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2010

DESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2010 (MEASURE B, MARCH 2004) (MEASURE B, MARCH 2004) TABLE OF CONTENTS Page Independent Auditors Report 1 Objectives... 2 Scope of the Audit.. 2 Background Information. 2-3 Procedures Performed... 3-4 Results

More information

Harnett Central Middle

Harnett Central Middle NC School District/430 Harnett County/Middle School Harnett Central Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus

More information

7th Draft Projected Adopted Proposed. Summary

7th Draft Projected Adopted Proposed. Summary Summary Central High School $ 15,700 $ 523,000 $ 363,000 $ 513,000 $ 13,000 $ 13,000 Holgate Middle School $ 44,600 $ 12 $ 10 $ $ $ Simmons Middle School $ 22,600 $ 46 $ 10 $ $ $ C.C. Lee Elementary $

More information

Interest Earned through 6/30/2018 2,013, , ,029, ,454, (3,443,911.91) 29, ,500, ,540,322.

Interest Earned through 6/30/2018 2,013, , ,029, ,454, (3,443,911.91) 29, ,500, ,540,322. STATUS OF DISTRICT RESERVES NORTH SHORE CSD Background Reserve funds are an important planning tool generally used by local governments and school districts to save for future needs and other allowable

More information

Oceanside Gateway Business Park O. A.

Oceanside Gateway Business Park O. A. Operating Budget-Final Parcel Parcel Address Parcel / Bldg / Unit Sq. Ft. % of project Total Monthly Assessment Total Quarterly Assessment PSF/Mo. 1 Hamann Co 33,100 6.78% $ 1,735 $ 5,205 $ 0.052 2-1 BP

More information

Construction Report Update

Construction Report Update NEW TRIER HIGH SCHOOL Construction Report Update September 2016 New Trier Winnetka Campus West Side Addition TABLE OF CONTENTS I. Neighbor Relations II. III. IV. Project Summary Schedule Progress Milestones

More information

NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017

NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017 NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus

More information

Fort Wayne Community Schools. Capital Projects Planning March 15, 2011

Fort Wayne Community Schools. Capital Projects Planning March 15, 2011 Fort Wayne Community Schools Capital Projects Planning March 15, 2011 District Balanced Scorecard Goal III Operate effectively with integrity and fiscal responsibility Condition scores unchanged Use of

More information

Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019

Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 PRESENTED BY Finance and Administration Florida Agricultural and Mechanical University 1 ACTION ITEM IV: Approval of

More information

(TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I

(TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I SCHOOL PROJECTS (TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I 1 Sum of Prior Years and Estimate to Complete Project Estimates: PlanningIDesign Land Construction Total 1 Sum of FY

More information

Proposition O Citizens Bond Oversight Committee Wednesday September 10, 2014 AGENDA

Proposition O Citizens Bond Oversight Committee Wednesday September 10, 2014 AGENDA Proposition O Citizens Bond Oversight Committee Wednesday September 10, 2014 AGENDA 1. Call to Order / Roll Call 2. Pledge of Allegiance Proposition O Citizens Bond Oversight Committee * Agenda * Wednesday

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

Priority #1 Request for Construction FY Priority #2 Anticipated Request for Planning FY 2019

Priority #1 Request for Construction FY Priority #2 Anticipated Request for Planning FY 2019 V. IMPLEMENTATION PLAN a) Prioritize major capital projects requested from the State, including a brief project description and estimated cost, in the format provided. (Adjust previously developed or prior

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

Bonnie Beard Agriculture Center Dedication November 29, Design & Construction Managed Projects. Monthly Report

Bonnie Beard Agriculture Center Dedication November 29, Design & Construction Managed Projects. Monthly Report Bonnie Beard Agriculture Center Dedication November 29, 2017 Design & Construction Managed Projects Monthly Report November 2017 Design & Construction Managed Projects Table of Contents Page Understanding

More information

Attachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017

Attachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017 A. Approval - New (Non-State and Other State Funds) Name (Other State) (Other State) Non-State Funds/ Undetermined 1 N/A B. Approval - Amended (Non-State and Other State Funds) 1 Coastal Carolina Main

More information

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, 2018 General Fund Actual A B C D E F WECC Fund Actual Revenue Revenue - Faith Giving 1 $ 213 $ 234 $ (22) - Tuition $ 226

More information

City School District of Albany Five Year Facilities Plan 3/14/2019

City School District of Albany Five Year Facilities Plan 3/14/2019 Bold indicates change from 3/7/19 BOE meeting Available Local Share $ 3,300,000 1 SPA Air condition gymnasium $ 267,000 1 $ 41,385 $ 41,385 $ 267,000 2 DCS Air condition gymnasium $ 221,000 1 $ 34,255

More information

Program and Project Status Update

Program and Project Status Update Program and Project Status Update Citizens Bond Oversight Committee Meeting October 14, 2014 Robert Ball, Bond Program Manager 1 Capital Improvement Program General Updates Close out of completed projects

More information

General Fund Revenue

General Fund Revenue Millions Percent of Kathy Steinert, Director of Fiscal Services Phone: 541.923.8927 145 SE Salmon Ave Redmond, OR 97756 kathy.steinert@redmond.k12.or.us Date: May 23, 2014 To: Redmond School District Board

More information

$4,701,440 $2,727,355 $2,596,419 $447,703 $11,216,598 $21,689,515

$4,701,440 $2,727,355 $2,596,419 $447,703 $11,216,598 $21,689,515 INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information