- Sharyl Poole
- 5 years ago
- Views:
Transcription
1 One Stop Studen Allan Hancock Joint Community College District One Stop Student Services Public S Public Safety Com Public Safety Complex Childc Childcare Addit Childcare Addition BOND MEASURE I Progress Report Quarterly Citizens Oversight Committee Meeting February 3, 2009 Prepared by the Project Management Team
2 Allan Hancock Joint Community College District Bond Measure I Progress Report October 2008 December 2008 PROGRAM PROGRESS SUMMARY Capital Projects During the period of October 1, 2008 through December 31, 2008, the district capital construction program reached a major milestone when the board of trustees approved the facilities site and utilities master plan. The approved master plan documents were then distributed to the design teams in December 2008 to guide their work on the various capital projects. Plan check review of the one stop student services center by the Division of the State Architect (DSA) continues on schedule. Once the project plan approval process has been completed, the district can seek approval to bid the project. The public safety complex user group meetings have continued with the development of the preliminary plans for the project focusing on site development, exterior training grounds, and additional site buildings. The childcare center addition preliminary plans continue to develop. Scheduled Maintenance Projects During this period, three (3) construction contracts were awarded for scheduled maintenance projects with a combined construction cost of $1.02M. Five (5) scheduled maintenance projects, with an estimated collective construction cost of $4.2M, continue in the planning/design phase. Technology Projects The Phoenix Project The go live date of the financial module of the new integrated financial and administration solutions (IFAS) system remains scheduled for February The kickoff of the Luminis web portal project was held and the input of catalog and admissions data has started. Technology and Instructional Equipment Modernization The technology advisory committee (TAC) recommended 41 projects in fall COC Quarterly Report 1
3 Capital Projects Construction AUDIO VISUAL SYSTEMS FOR BUILDINGS M AND S All construction and additional work was concluded during this period. The contractor is completing items noted by the design team on the punchlist walk through conducted in September. User training for the new audio visual equipment has been completed, with additional technical training for multimedia staff being scheduled for completion next month. Of the $1,580,000 budget, 63% has been committed and 95% has been expended. BFGC Architects Planners, Inc. Bachini Deferville Management Smith Electric Services Estimated budget: $ 1,580,000 Measure I funds: $ 1,580,000 Construction start: Spring 2008 Construction completion: Summer 2008 COC Quarterly Report 2
4 Capital Projects Planning/Design PUBLIC SAFETY COMPLEX MVE Institutional continued the extensive user group meetings and workshops to gather detailed input needed to complete the preliminary design for the fire tower, emergency vehicle operation course (EVOC), apparatus storage building, vehicle maintenance building, shooting range, 1/4 mile track, and other site development issues. The budget for this project is $46,163,902, with a total of 2% committed thus far. MVE Institutional Inc. Kitchell CEM, Inc. Pending Future Award Revised budget: $46,163,902 Measure I funds: $26,000,000 Measure I augmentation (2/08) $20,163,902 Design start: Fall 2007 Estimated construction start: Summer 2010 ONE STOP STUDENT SERVICES CENTER Plan check review by the Division of the State Architect (DSA) continues on schedule. Concurrent with the review process, Dovetail Decision Consultants continued with refinements to the furniture procurement specifications. Of the current project budget of $39,257,000, a total of 15% has been committed. Steinberg Architects Bachini Deferville Management Pending Future Award Revised budget: $39,257,000 Measure I funds: $ 7,800,000 Measure I augmentation (2/08) $14,900,000 Other funds: $16,557,000 Design start: Fall 2007 Estimated construction start: Fall 2009 COC Quarterly Report 3
5 Capital Projects Planning/Design CHILDCARE CENTER ADDITION The architect, MVE Institutional Inc., is nearing completion of preliminary plans based on a series of meetings with the user group to refine priorities. Of the $6,500,000 project budget, a total of 2% has been committed. MVE Institutional Inc. Pending Future Selection Pending Future Award Estimated budget: $6,500,000 Measure I funds: $6,500,000 Other funds: N/A Design start: Fall 2007 Estimated construction start: Spring 2010 FACILITIES SITE AND UTILITIES MASTER PLAN Steinberg Architects completed the final draft of the facilities site and utilities master plan report after a final planning workshop in October The final draft was presented to the board of trustees for information and input on Tuesday, November 18, The report was approved by the board of trustees on Tuesday, December 16, COC Quarterly Report 4
6 Scheduled Maintenance Projects Construction PHASE I ENERGY PROJECT This project upgrades or retrofits the existing lighting systems and fixtures in selected buildings throughout the Santa Maria campus for energy efficiency. The project was re bid in early October after a rejection of all bids at the September board meeting. Authorization to award the construction contract to Electricraft, Inc., was granted at the October 21, 2008 board meeting. The contractor is working on resolving punchlist items noted by the design team and district during a walkthrough in December Of the current $600,000 budget, a total of 93% has been committed. JMPE Electrical Engineering Lighting Design Bachini Deferville Management Electricraft, Inc. Current budget: $ 600,000 Measure I funds: $ 469,573 Other funds (CCC/IOU): $ 130,427 Construction start: Fall 2008 Construction completion: Winter 2008 BUILDING M300 HVAC UPGRADES This project addresses the replacement and modifications necessary for the M300 HVAC system; provides a master plan layout for the data center, including a UPS and HVAC for current and future needs. The contractor began construction on the data center portion of this project in October and successfully completed the installation of all components for this space. During the month of December the contractor began construction on the M300 HVAC units. The work is progressing on schedule. Of the current $450,064 budget, a total of 68% has been committed. AE Group Mechanical Engineers, Inc. Bachini Deferville Management Smith Electric Services Current budget: $ 450,064 Measure I funds: $ 450,064 Other funds: N/A Construction start: Winter 2008 Construction completion: Spring 2009 COC Quarterly Report 5
7 Scheduled Maintenance Projects Construction ROOF REPAIRS AND REPLACEMENT BUILDINGS E, F, G, AND M300 CANOPY The architect, Architect s Consulting Service, completed the design of this project in early September. This project was awarded at the October 21, 2008 board meeting to Channel Islands Roofing. Construction began during the month of November with several delays due to rain. The completion date for this project has been extended to account for the wet weather. Of the current budget of $ 1,146,116, a total of 42% has been committed. Architect s Consulting Service Kitchell CEM Channel Islands Roofing, Inc. Current budget: $1,146,116 Measure I funds: $1,146,116 Construction start: Fall 2008 Construction completion: Spring 2009 COC Quarterly Report 6
8 Scheduled Maintenance Projects Planning/Design FIRE ALARM UPGRADES BUILDINGS E, F, H, K, N AND M300 This project includes upgrades to existing fire alarm systems and devices. Originally, the scope included buildings D and M300, however, additional buildings were identified by the engineer and added to the scope of this project. The project now includes buildings E, F, H, K, and N, and the fire alarm upgrade to building D has been moved from this project to the building D roof, HVAC, and ADA upgrades project. The engineer completed preliminary design and submitted to the district for review. Of the current $140,000 budget, a total of 26% has been committed. JMPE Electrical Engineering Lighting Design Current budget: $ 140,000 Measure I funds: $ 140,000 Other funds: N/A Construction start: Summer 2009 Construction completion: Fall 2009 BUILDING C ROOF, PAINT, FLOORING AND ADA UPGRADES This project addresses the necessary repairs/replacement of roof, roof structure, ceiling tiles, and plaster damage throughout building C. It also includes interior and exterior painting, as necessary, and remodeling and upgrades for ADA compliancy. Harris Architecture and Design submitted a 90% design to the district and the Division of State Architect (DSA) for review. Comments from these reviews will be incorporated into the final bid documents. Of the current $ 878,751, a total of 17% has been committed. Harris Architect and Design Kitchell CEM Current budget: $ 878,751 Measure I funds: $ 775,000 Other funds $ 103,751 Construction start: Spring 2009 Construction completion: Fall 2009 COC Quarterly Report 7
9 Scheduled Maintenance Projects Planning/Design BUILDING D ROOF, HVAC, AND ADA UPGRADES This project addresses the necessary repairs/replacement of water lines, HVAC units, roof, ceiling tiles, and theatre catwalk. It also addresses partial interior and exterior painting of building D, along with remodeling and upgrades for ADA compliancy. Fire alarm upgrades were added to the scope of this project for coordination purposes. Design meetings were conducted to update the users on the findings regarding the existing structure and systems. The architect, Westberg + White, Inc., has been working with their consultants to design the mechanical upgrades for the project. Investigation of the existing catwalk structure continued and theatre consultants were brought in to assist in the evaluation. The architect continued design and estimate of costs to allow a final decision on the scope of work to be done. Of the current $2,076,630 budget, a total of 8% has been committed. Westberg + White Inc. Current budget: $2,182,454 Measure I funds: $2,076,630 Other funds (12/08): $ 105,824 Construction start: Winter 2009 Construction completion: Summer 2010 BUILDING M300 HVAC UPGRADES, PHASE II This project includes additional upgrades to the heating/ventilation/air conditioning (HVAC) for building M300. The engineer, AE Group Mechanical Engineers, Inc., began design of the project and submitted a preliminary design to the district for review. Of the current $248,339 budget, a total of 11% has been committed. AE Group Mechanical Engineers, Inc. Current budget: $ 248,339 Construction start: Summer 2009 Measure I funds: $ 248,339 Construction completion: Winter 2010 COC Quarterly Report 8
10 Scheduled Maintenance Projects Planning/Design PARKING LOT ONE EXPANSION, PHASE II This project expands parking lot one (located south of building C) to the west and south. The engineer, Penfield and Smith, has met with the stakeholders twice to discuss the preliminary design and has received direction on the course of the project. They will continue with the design next period. Of the current $ 975,000 budget, a total of 10% has been committed. Engineer: Penfield and Smith Current budget: $ 975,000 Construction start: Summer 2009 Measure I funds: $ 975,000 Construction completion: Winter 2009 VOICE OVER INTERNET PROTOCOL (VOIP) The new one stop student services center will demolish building B, that houses the main phone switch for the district. Since the existing phone switch is outdated, the college plans to upgrade the old phone system to a new Voice Over Internet Protocol (VOIP) system. This conversion project will be accomplished in two parts; an underground utilities phase and an equipment phase. The VOIP underground utilities phase, the first phase, will provide the necessary infrastructure for the underground utilities. In addition, the project scope of work will affect a large area of the campus north quad developing new landscape and hardscape, thus reshaping the area as outlined in the Facilities Site and Utilities Master Plan. The VOIP equipment phase, the second phase, installs all the hardware and software that will reside inside the buildings, including replacing existing phones. A design kickoff meeting with the stakeholders was held and the scope of this project was finalized, including the decision to bid this project in two phases due to scheduling requirements and implementation expertise. Steinberg Architects began the preliminary design and site investigation this period. Of the current $1,250,000 budget, a total of 21% has been committed. Steinberg Architects, Inc. Current budget: $ 1,250,000 Underground Utilities Construction start: Summer 2009 Measure I funds: $ 1,250,000 Underground Utilities Construction completion: Fall 2009 COC Quarterly Report 9
11 MAINFRAME REPLACEMENT PROJECT Technology Projects The go live date of the financial module of the new integrated financial and administration solutions (IFAS) system is scheduled for February 2009, with user training being planned for January and February For the new student Banner system, the catalog and admissions teams continued to set up tables and add data to the new system. Kickoff of the Luminis web portal project was held. Of the $6,500,000 budget, a total of 73% has been committed. Vendors: Strata Information Group (SIG) SunGard Public Sector Bi Tech (Financial and HR) SunGard Higher Education (Student) Measure I Funds: $6,500,000 SunGard Bi Tech Agreement 04/04/2007 SunGard Higher Ed Agreement 12/20/2007 Estimated Financial System live Feb 2009 Estimated Student System live June 2010 Electronic Trainer TECHNOLOGY EQUIPMENT MODERNIZATION The Technology Advisory Committee (TAC) recommended 41 technology improvements in fall This included 130 computers for student labs, classrooms, and offices. A server for the firewall logs was purchased to replace the previous server that quit working. Replacement of three 25 year old dimmer rack controls in the Marian theater was recommended along with seven GM specialized electronic training programs for the auto tech classes. Of the $11,888,795 budget, a total of 22% has been expended. Vendors: Director, Information Technology Services Associate Dean, Learning Resources Various Measure I Funds: $11,850,000 Develop process for modernization requests 12/2006 TAC complete 2006/2007 recommendations 04/2007 TAC complete 2007/2008 recommendations 05/2008 TAC complete 2008/2009 recommendations 05/2009 COC Quarterly Report 10
Allan Hancock Joint Community College District
One Stop Studen Allan Hancock Joint Community College District One Stop Student Services Public S Public Safety Com Public Safety Complex Childc Childcare Addit Childcare Addition BOND MEASURE I Progress
More informationStatus: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.
Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationStatus: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.
Page 1 of 14 FACILITIES PLAN STATUS REPORT August 24, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid
More informationAPPENDIX A FULL TEXT OF BOND MEASURE
APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass
More informationGoverning Board Bond Update. Measure G Bond Program. for. Solano Community College District
Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects
More informationBallot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools
Section Ballot Measures-N N Centralia Elementary School District, Building Strong Neighborhood Schools To repair/modernize aging classrooms, science labs/school facilities to keep pace with technology,
More informationBallot Measures-T Section
T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and
More informationCAPITAL PROJECT PROCESS
CAPITAL PROJECT PROCESS May 2009 GETTING STARTED What is a project? A project is defined as all work (maintenance & repair or renovation) that requires 5,000 or more in time and materials and/or is sufficiently
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING MAY 15, 2018
FACILITIES COMMITTEE MEETING MAY 15, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center Johnson Demolition Science Center & Building J
More informationStatus: Structural steel installation underway at primary building. Observatory construction underway.
Page 1 of 11 FACILITIES PLAN STATUS REPORT March 30, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationContents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure...
Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 6 Impartial Analysis... 7 Statement in Favor of Measure... 8 Ballot Measure EXHIBIT A HANFORD ELEMENTARY SCHOOLS REPAIR
More informationProgram and Project Status Update
Program and Project Status Update Citizens Bond Oversight Committee Meeting October 14, 2014 Robert Ball, Bond Program Manager 1 Capital Improvement Program General Updates Close out of completed projects
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018
SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center & Demolition Science Center
More informationAction Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List
Action Item TO: PRESENTED BY: BOARD AGENDA ITEM: Board of Trustees and Superintendent of Schools Sid Albaugh, Assistant Superintendent Business Services Consideration of Approval of 2018 Measure A Facilities
More informationP R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y
Measure Q Update P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y 1 5 2 0 1 5 Agenda 1. P R E L I M I N A R Y R E S P O N S E T O
More informationContents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...
Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... 10 Ballot Measure EXHIBIT B MEASURE Y (ABBREVIATED FORM)
More informationFACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING
Page 1 of 11 FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationFor. 621 Grant. Yakima, WA until: preparation. Kim Hixson Director
Yakima Valley Libraries 102 North Third Street Yakima, WA 98901 Request for Statement of Qualifications (SOQ) For Remodel of Sunnyside Community Library 621 Grant Sunnyside, WA 98944 Notice is hereby given
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More informationInformation. June 06, 2017 The Board awarded a contract to gkkworks/belli Architects.
Measure T Update Prepared by: Joseph Reyes, Executive Director Facilities Planning & Construction Management Presented to the Board: October 02, 2018 1. Measure T Implementation Plan Information June 06,
More informationCapital Project Delivery Handbook. Facilities Planning & Construction
Capital Project Delivery Handbook Facilities Planning & Construction 1 FACILITIES PLANNING & CONSTRUCTION 3/8/09 2 FACILITIES PLANNING & CONSTRUCTION 1. WELCOME TO FACILITIES PLANNING & CONSTRUCTION...
More informationSTATE CAPITAL OUTLAY PLANNING
STATE CAPITAL OUTLAY PLANNING CCC Chancellor s Office Cheryl Larry Lan Yuan San Mateo CCD Jose Nunez Karen Pinkham CCFC 2016 AGENDA Overview Eligibility Priority Review/Approval Effective Practices 1 Key
More informationUse of State and District Construction Funds
8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,
More informationProgress Update Identified Needs & Capital Plan
Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary
More informationCentral Michigan University Capital Budget
Central Michigan University Capital Budget 1999-2000 Table of Contents Central Michigan University Capital Budget Table of Contents I. Narrative A. Overview and Process...1 B. Funding Sources...2 C. Capital
More informationSchool Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year February 21, 2019
School Board of Brevard County, Florida Half-Cent Sales Surtax Round 6 Internal Audit Report Fiscal Year 2018-19 February 21, 2019 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...
More informationSanta Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013
Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013 Measure V Bond Construction Fund Year Ended June 30, 2013 Table of Contents Page Independent Auditors'
More informationSOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S
SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S Under this measure, the Somis Union School District ( District ) is submitting a bond measure, described below, to the voters
More informationBond Oversight Committee Bond program. January 7, 2016
Bond Oversight Committee 2014 Bond program January 7, 2016 Bond Oversight Committee 1 AGENDA Welcome, introductions, reminder of scope/role of BOC Stewart Jacobson, Chair Program Management: Max Cleaver
More informationBERKELEY UNIFIED SCHOOL DISTRICT
BERKELEY UNIFIED SCHOOL DISTRICT TO: Javetta Cleveland and Neil Smith, Co-Superintendents FROM: Lew Jones, Director of Facilities DATE: June 26, 2013 SUBJECT: Approval of the 2013/14 Measure H Annual Plan
More informationSanta Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015
Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015 Measure V Bond Construction Fund Year Ended June 30, 2015 Table of Contents Page Independent Auditors'
More informationMEASURE I CITIZENS' OVERSIGHT COMMITTEE MEETING AUGUST 5, 2014 QUARTERLY FINANCIAL REPORT
MEASURE I CITIZENS' OVERSIGHT COMMITTEE MEETING AUGUST 5, 214 QUARTERLY FINANCIAL REPORT Bond Income and Expenditure Summary Income Statement Projects List Project Expenditure Summary Cash Flow Report
More informationConstruction Workshop
Build United Construction Workshop 1 Agenda Welcome Overview of 2013 Bond Program Procurement Methods & Procedures for Contractors Design Build Method Construction Manager at Risk Competitive Sealed Proposals
More informationAttachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017
A. Approval - New (Non-State and Other State Funds) Name (Other State) (Other State) Non-State Funds/ Undetermined 1 N/A B. Approval - Amended (Non-State and Other State Funds) 1 Coastal Carolina Main
More informationDESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2008
(MEASURE B, MARCH 2004) (MEASURE B, MARCH 2004) TABLE OF CONTENTS Page Independent Auditors Report 1 Objectives... 2 Scope of the Audit. 2 Background Information 2-3 Procedures Performed... 3-4 Results
More informationSchool Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year February 20, 2018
School Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year 2017-18 February 20, 2018 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...
More informationCH-UH Board of Education Meeting. June 27, 2017
CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle
More informationMembers Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez, Bill Rundberg and Dennis Zheng
SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes of June 1, 2017 Meeting District Office Board Room Members Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez,
More informationGeorgia Institute of Technology Advanced Computing Technology Building. Draft Program. Mission Model Initial Program Development
Georgia Institute of Technology Advanced Computing Technology Building Draft Program Initial Program Development Issued April 2, 2001 Introduction Scope This document is a summary of the Session for the
More informationFacilities Planning & Construction Report nd Quarter Ending December 31, 2017
Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By
More informationPage Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160
- Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 Special Education Allocation 161 Operational Services
More informationRockville Science Center (P036600)
Rockville Science Center (P036600) (AAGE15) Rockville Date Last Modified 2/26/14 N/A-PS Planning, Design and Supervision 6,492 6,477 15 0 0 0 0 0 0 0 0 Construction 56,300 56,272 28 0 0 0 0 0 0 0 0 6,598
More informationPage Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182
Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Operational Services/Central Services/Axtell Park School
More informationCORPORATE SERVICES GENERAL ISSUES COMMITTEE
5.2 GENERAL ISSUES COMMITTEE February 13, 2018 Mike Zegarac General Manager OVERVIEW 2 Citizen and Customer Services 546-CITY (Customer Contact Centre) askcity@hamilton.ca (Email inquiries) Municipal Service
More informationMT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE R, NOVEMBER 2001) PERFORMANCE AUDIT.
(MEASURE R, NOVEMBER 2001) (MEASURE R, NOVEMBER 2001) CONTENTS Page Independent Auditor s Report... 1 Objectives... 2 Scope of the Audit... 2 Background Information... 3 Procedures Performed... 3 Results
More informationLOS ANGELES UNIFIED SCHOOL DISTRICT Board of Education Report
LOS ANGELES UNIFIED SCHOOL DISTRICT Board of Education Report Report Number: 246-15/16 Date: Subject: Amendment to the Facilities Services Division Strategic Execution Plan to Approve Project Definitions
More informationMeasure G Quarterly Progress Update
Measure G Quarterly Progress Update February 3, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure
More informationSacramento City College
Sacramento City College Strategic Planning System Title: Plan Type: OPR: Collaborative Group: References: Facility Management Resource Allocation Operations Division Campus Development Committee ADA Transition
More informationMeasure G Quarterly Progress Update
Measure G Quarterly Progress Update May 4, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure G is
More informationMeasure K Board Workshop December 1, 2008 Building on Success: Schools for the Next Generation
Measure K Board Workshop December 1, 2008 Building on Success: Schools for the Next Generation Workshop Items Citizens Oversight Committee Measure K Next Steps Projects in Planning Milestones Board s Vision
More informationMeasure W Bond Program Quarterly Status Report
Measure W Bond Program Hensley Creek Road Project Prepared by Bond Implementation Planning Committee Mendocino-Lake Community College District 1000 Hensley Creek Road, Ukiah, CA 95482 Telephone: (707)
More informationBarnesville Public Schools Proposed Building Program
May 6, 2016 Proposal for Submitted to: Commissioner Dr. Brenda Cassellius Minnesota Department of Education Barnesville Public Schools Proposed Building Program Barnesville Public School District Independent
More informationLocal ballot measure: B. Redding School District Bond Measure
B Redding School District Bond Measure Ballot question To improve the quality of education; repair/replace leaky roofs; modernize and construct classrooms, restrooms and school facilities; and make health,
More informationTwin Falls Urban Renewal Agency Main Street Redevelopment Project
Twin Falls Urban Renewal Agency Main Street Redevelopment Project Prepared for: Monthly Report for Board Meeting of May 9, Prepared by Owner s Representative PAGE 1 Monthly Project Progress Update May
More informationBERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee
BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee AGENDA November 17, 2011 6:00 7:30 PM 1720 Oregon Street Berkeley, CA 94703 (510) 644-6066 1. Call to Order 2. Approval of Meeting
More informationOrange Unified School District (C) Copyright March 2018 All Rights Reserved
ORANGEUNIFIED UNIFIEDSCHOOL SCHOOLDISTRICT DISTRICT ORANGE Orange Unified School District (C) Copyright March 2018 All Rights Reserved 1 The Office of the Assistant Superintendent of Business Services
More informationPROGRAM REVIEW FACILITIES PLANNING & SERVICES DIVISION
2013-14 PROGRAM REVIEW FACILITIES PLANNING & SERVICES DIVISION I. Division Purpose Plan, construct and maintain a safe, functional, clean and attractive physical environment for the users of El Camino
More informationSolano Community College District. JOINT MEASURE G and Q CITIZENS BOND OVERSIGHT COMMITTEE (CBOC) MEETING
l Solano Community College District JOINT MEASURE G and Q CITIZENS BOND OVERSIGHT COMMITTEE (CBOC) MEETING Fairfield Campus - Room 1421 Solano Community College, 4000 Suisun Valley Road, Fairfield, California
More information38 th A n n u a l C o n f e r e n c e o n S c h o o l F a c i l i t i e s
MANAGING RISK v. REWARD HOW TO BALANCE CREATIVE DESIGN WITH THE REALITIES OF PROJECT BUDGETS, SCHEDULES & SCOPE 38 th A n n u a l C o n f e r e n c e o n S c h o o l F a c i l i t i e s Panel Moderator:
More informationSacramento City College Strategic Planning System
Sacramento City College Strategic Planning System Title: Plan Type: OPR: Collaborative Groups: Resource Management and Capital Outlay Master Plan 2018 Institutional VPA Resource Allocation Groups: Budget
More informationAdministrative Services Goals / Objectives * th Quarter Review 30 June 2008 & Annual Program Review
Administrative Services Goals / Objectives * 2007-2009 4 th Quarter Review 30 June 2008 & Annual Program Review VPA MISSION STATEMENT: Facilitate and promote effective student access and success by ensuring
More informationFacilities Management and Planning Organizational Review Phase II Update
MEMORANDUM Office of College Services DATE: September 3, 2013 TO: CC: FROM: SUBJECT: President Mary Spilde, Vice President Brian Kelly Facilities Management & Planning Organizational Review Team Jennifer
More informationCapital Projects Completed since 1988
Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990
More informationANNOUNCEMENT. This request for qualifications seeks the following type of service providers:
ANNOUNCEMENT REQUEST FOR STATEMENT OF QUALIFICATIONS NOTICE FOR ENGINEERING SERVICES BY SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN AND CONSTRUCTION The San Francisco Unified School District
More informationUniversity of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus)
of Colorado Capital Project Status SUMMARY - May (accounting noted by campus) Legend On-Track Risks Approved - Adjustments Needed Awaiting $ Start-Up Phase In Bidding Phase In Closeout Project Completed
More informationRequest for Proposal City Hall Facility Space Needs Assessment City of Alexandria, MN
Request for Proposal City Hall Facility Space Needs Assessment City of Alexandria, MN Issue Date: June 11, 2018 Statement of Objectives, Goals and Tasks The City of Alexandria is seeking proposals from
More informationCONTRA COSTA COMMUNITY COLLEGE DISTRICT CAPITAL OUTLAY BOND FUND 2002 ELECTION FINANCIAL REPORT
CONTRA COSTA COMMUNITY COLLEGE DISTRICT CAPITAL OUTLAY BOND FUND 2002 ELECTION FINANCIAL REPORT CONTRA COSTA COMMUNITY COLLEGE DISTRICT CAPITAL OUTLAY BOND FUND 2002 ELECTION TABLE OF CONTENTS FINANCIAL
More informationUNIVERSITY of HOUSTON MANUAL OF ADMINISTRATIVE POLICIES AND PROCEDURES
UNIVERSITY of HOUSTON MANUAL OF ADMINISTRATIVE POLICIES AND PROCEDURES SECTION: Facilities Number: 09.04.04 AREA: Facilities Management and Maintenance Information SUBJECT: Maintenance Project Evaluation
More informationFY Capital Improvement Program City of New Bedford, Massachusetts
City of New Bedford, Massachusetts Background The Massachusetts Department of Revenue, credit agencies and the Government Accounting Standards Board recommend that localities develop a capital improvement
More informationCommunity College District. Measure M
Community College District Measure M Monthly Report October 2015 San Bernardino Community College District Program Management Measure M Monthly Report October 2015 1. Valley Campus Project Sheets 2. Crafton
More informationIn FY , the following projects will be actively under design or construction:
PASCO COUNTY FISCAL YEAR 216-22 CAPITAL IMPROVEMENT PLAN INTERNAL SERVICES The Pasco County Board of County Commissioners has a broad responsibility to provide equipment, buildings, and other facilities
More informationStockton University FY 2019 Operational and Capital Report as of January 31, 2019
Stockton University FY 2019 Operational and Capital Report Stockton University FY 2019 Operational and Capital Report Table of Contents Page Operational Budget Summary: University, Auxiliaries, and Agency
More informationFrequently asked questions on the Ridgewood Public School Budget. 2. Why does the Board approve a preliminary budget?
Over the last few weeks the Board of Education has received a number of questions regarding the proposed 2018-19 budget. We hope that the Frequently Asked Questions and our Answers below will help to shed
More informationOriginal Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000
Page 1 of 20 FACILITIES PLAN STATUS REPORT June 27, 2016 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning
More informationPurpose and Responsibility of the Committee
Manhattan Beach Unified School District Measure BB Oversight Committee Annual Report Dated March 11, 2010 I. Purpose of the Report The Manhattan Beach Unified School District ( MBUSD ) Resolution No. 2008-12
More informationDESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2010
(MEASURE B, MARCH 2004) (MEASURE B, MARCH 2004) TABLE OF CONTENTS Page Independent Auditors Report 1 Objectives... 2 Scope of the Audit.. 2 Background Information. 2-3 Procedures Performed... 3-4 Results
More information2009 Annual Report to the Board of Trustees. Bond Measure V Citizens Oversight Committee
2009 Annual Report to the Board of Trustees Bond Measure V Citizens Oversight Committee Table of Contents Letter From The Chair 3 Executive Summary 4 Bond Measure V Overview 5 The Role Of The Citizens
More informationUNLV COMBINED MAJOR CAPITAL PROJECT AND ONE-TIME PROJECT PLANNING PROCESS (COPP) FY2014 AND UPCOMING 2015 LEGISLATIVE SESSION
UNLV COMBINED MAJOR CAPITAL PROJECT AND ONE-TIME PROJECT PLANNING PROCESS (COPP) FY2014 AND UPCOMING 2015 LEGISLATIVE SESSION Included in this package are the materials for the FY2014 One-Time Project
More informationFY 2018 Stockton University Operational & Capital Report as of May 31, 2018
FY 2018 Stockton University Operational & Capital Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 Internal Capital Projects 4-5 Other Capital Projects 6 State
More informationPhysical Plant. Detailed Assessment Report
Physical Plant Detailed Assessment Report 2011-2012 Mission / Purpose The Physical Plant Department enhances the University of West Alabama's mission to provide opportunities for students to pursue a quality
More informationSOCCCD FY Basic Aid Allocation Recommendations
SOCCCD FY 2015-2016 Basic Aid Board of Trustees Meeting May 18, 2015 How did the Basic Aid allocation process come about? In February, 2011, both IVC and SC were placed on warning by ACCJC, with 6 recommendations,
More informationDepartment Chair Online Resource Center Facility Maintenance or Facility Improvement? Taking a Responsible Approach
Department Chair Online Resource Center Facility Maintenance or Facility Improvement? Taking a Responsible Approach Richard Bettega, associate vice president for facilities, Lewis and Clark College. Facility
More informationSOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM
AGENDA ITEM MEETING DATE May 16, 2018 GOVERNING BOARD AGENDA ITEM TO: SUBJECT: Members of the Governing Board RESOLUTION TO APPROVE CHANGE ORDER #01 TO SOLANO COUNTY ROOFING FOR BUILDING 1000 RE- ROOFING
More informationSOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM
AGENDA ITEM MEETING DATE February 20, 2019 SOLANO COMMUNITY COLLEGE DISTRICT GOVERNING BOARD AGENDA ITEM TO: SUBJECT: Members of the Governing Board CONTRACT AMENDMENT #1 TO DOVETAIL FOR FURNITURE, FIXTURES
More informationDRAFT. PROJECT POLICY CAPITAL AND OPERATING Approved by: History: Administrative Policy Policy Number: REYNOLDA CAMPUS CONTENTS:
REYNOLDA CAMPUS PROJECT POLICY CAPITAL AND OPERATING Approved by: History: Type: Administrative Policy Policy Number: 3.3.02 Responsible Official: Executive Vice President Related Policies: CONTENTS: I.
More informationCyber Security Risk Information Sharing Program (CRISP) Overview, Budget Projection and Proposed Funding Allocation
Cyber Security Risk Information Sharing Program (CRISP) Overview, Budget Projection and Proposed Funding Allocation Introduction and Executive Summary This document provides additional background on CRISP,
More informationJob Order Contracting Mandatory Pre-Bid Conference
County of Fresno Internal Services Department Job Order Contracting Mandatory Pre-Bid Conference FOR SOLICITATION OF BID 912-5020 JOB ORDER CONTRACT JANUARY 6 TH 2012 1 Agenda Part I: The Job Order Contracting
More informationPOJOAQUE VALLEY SCHOOL DISTRICT October 12, 2016
POJOAQUE VALLEY SCHOOL DISTRICT October 2, 206 Results from data gathered from community meeting held September 20, 206 regarding use of current bond funds and goals setting for possible 207 bond On Tuesday,
More informationPerformance Audit on 2008 and 2013 SPLOST Revenues For the Fiscal Year ended June 30, 2012
Thomas County School System Performance Audit on 2008 and 2013 SPLOST Revenues 300 Mulberry Street, Suite 300 P.O. Box 1877 Macon, Georgia 31202-1877 Phone: (800) 277-0050 Facsimile: (478) 464-8051 Web:
More informationOVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE
MEASURE C SCHOOL SAFETY AND MODERNIZATION On November 3, 2009 the voters residing in the Mill Valley School District (MVSD) approved the Measure C Safety and Modernization Bond of 2009 (Measure C). Measure
More informationFacility Condition Assessment Report. Coast Community College District
Facility Condition Assessment Report Coast Community College District February 28, 2003 Introduction To help document the need for funding the necessary replacement and upgrading of facilities within California
More informationREGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS
OCTOBER 18-19, 2017 REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS Actions Requested: Consider recommending to the Board approval of the: 1. Following actions for the Knoll
More informationPROFESSIONAL SERVICES CONSULTANT TYPE OF RETAINER AGREEMENT UNIVERSITY OF ILLINOIS
PROFESSIONAL SERVICES CONSULTANT TYPE OF RETAINER AGREEMENT UNIVERSITY OF ILLINOIS THIS AGREEMENT, made and entered into in the City of, State of Illinois, as of the date of the last signature of the parties
More informationHARTNELL COMMUNITY COLLEGE DISTRICT Salinas, California. MEASURE H GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2014
Salinas, California PERFORMANCE AUDIT June 30, 2014 Salinas, California PERFORMANCE AUDIT June 30, 2014 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE HISTORY... 2 HARTNELL COMMUNITY
More informationCapital Outlay Management Plan for the Delegation of Capital Outlay Authority For Humboldt State University
Capital Outlay Management Plan for the Delegation of Capital Outlay Authority For Humboldt State University Date submitted to Certification Review Board: March 9, 2017 Humboldt State University Page 1
More informationTumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent
Tumwater University School District Budget Myths Bond Project Update February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Construction Update $136,000,000 in bonds approved
More informationInvesting in Our Schools:
Investing in Our Schools: History of Measures A & B & Potential New Bond Facilities Workshop Special Board Meeting July 13, 2010 Cindy Cathey, Superintendent Song Chin-Bendib, Assistant Superintendent,
More informationMeasure W Bond Program Quarterly Status Report
Prepared by Bond Implementation Planning Committee Mendocino-Lake Community College District 1000 Hensley Creek Road, Ukiah, CA 95482 Tel: (707) 468-3000 www.mendocino.edu INDEX Page Number Introduction
More informationBallot Measures-LL Section
LL To repair and modernize aging classrooms/school facilities at local elementary/intermediate schools, repair termite damage, dry rot, deteriorating roofs, plumbing, and electrical, improve student safety/security,
More information