Central Michigan University Capital Budget
|
|
- Gavin Barrett
- 5 years ago
- Views:
Transcription
1 Central Michigan University Capital Budget Table of Contents
2 Central Michigan University Capital Budget Table of Contents I. Narrative A. Overview and Process...1 B. Funding Sources...2 C. Capital Expenditures...3 D. Technology Resource Allocations...4 II. Capital Budget Summary...5 III. Restricted Funds...6 IV. Unrestricted Sources of Funds...7 V. Uses of Funds...8 VI. Repayment to the Capital Budget...10 VII. Technology Summary...11 VIII. Multi-Year Projects...13
3 Capital Budget Overview and Process The capital budgeting process is designed to provide a long-term perspective of the capital needs of the university. The annual review and update of the capital budget provides a four year projection concerning capital needs in the areas of capital construction; special maintenance; renovation and remodeling; utilities and infrastructure; life, fire and handicap safety; parking; and major equipment acquisition. The capital budget is designed to present and integrate the capital expenditure needs and funding availability. The sources of funds available for the capital needs are State capital outlay, gifts, the parking services operating budget, the residences and auxiliary services operating budget, the general fund operating budget, and other miscellaneous funding sources. This budget document separates the restricted dollars which must be used for specified projects and then pools the internal revenue sources committed to the capital budget process. The resources that do not have restrictions are pooled in one account per year. A separate pooled account is used for each year of the capital budgeting process. As the President or his designee authorizes the initiation of individual projects, specific project accounts are then created for the expenses and funds are moved to the project account from the pool. Once the project is completed, any excess funds will be moved back to the pooled account to be used for other capital project priorities. 1 This budget documents the capital budget for administrative and Board approval. Approval of this document includes the projects and the multi-year projects included on page 12. The other future year projects are listed as planning information and will be revisited annually for changes in content, priorities, and funding. This comprehensive review of the capital needs and funding sources of the University allows for systematic prioritization on an institutional basis. The capital budget process is useful for documenting capital needs across the university and prioritizing projects within the funding constraints. The priorities are established based on anticipated future funding and a general categorization to do maintenance related projects before new initiatives. Many projects have been recommended but, due to limited resources, cannot be funded at this time. This document includes only items that can likely be done in the four-year future window covered by this budget. The campus has many deferred maintenance needs as documented in a detailed audit of each building that was done in Beginning with , $4,500,000 per year will be dedicated toward addressing these needs. The plan that was approved is a fifteen-year plan. Funding will be from a variety of sources, including the capital budget, general fund, the President s New Initiatives Fund, and residences and auxiliary services.
4 Part of this process involves an opportunity for divisional input regarding institutional capital needs. The process includes an annual window for requests to be presented as part of the overall documentation of needs. The annual process in which new items are brought forward for consideration is based upon the following procedures. The account director submits a project request to the individual vice president via a formal project request/authorization form. Prioritized requests supported by the respective vice president are compiled into one list of institutional priorities by the Budget and Planning Office and forwarded to the Capital Planning Committee, the Vice Presidents, and the President for review and final University prioritization. After the Capital Planning Committee, Vice Presidents, and the President have reviewed and modified the document, a final recommendation is forwarded to the Board of Trustees for approval. Board approval of this capital budget gives the President, or his designee, the authority to move forward with budgetary implementation at his discretion. Individual projects will not move forward for implementation until approved by the President or his designee. As of June 30, 1998 the value of the University facility cost was estimated to be $598,721,428. This includes over 100 buildings, some of which date back to the early part of the century. Most of the utilities link into a utility infrastructure providing heating, ventilation, and in some cases, air conditioning. A number of these facilities also include elevators. Restricted Funds Funding Sources The anticipated restricted sources of funds are coming from the State capital outlay process, bond proceeds from the bond issue in April 1997, a reserve which was set up for the Library project expansion, and gifts for the athletic projects. The State capital outlay for the Library addition and remodeling is shown, based on the approved level of $37,500,000. The project will require a twenty-five percent match or $12,500,000 from the University. Site preparation began in FY , with construction commencing in FY This project includes up to $700,000 of additional unrestricted funds for projects related to the Library addition and remodeling. This is over and above the original budget of $50,000,000. The budget for the Kelly Shorts stadium expansion and the indoor athletic facility approved in January 1997 is shown in this document. The sources of funds for this project are gifts and the bonds that were issued in April In addition, $825,000 from the Capital Budget Pool was added to this budget to raise the total to $28,825,000. 2
5 Other University Resources There are several sources of University dollars being brought together in this section of the capital budget. Sources include funding from the parking services budget, the general fund, the President s New Initiatives Fund, the residences and auxiliary budget, and unused dollars from the prior year capital budget. There are also repayments to the capital budget from items previously funded. Specific funding for deferred maintenance is as follows Capital Budget $2,200,000 $2,200,000 $2,200,000 $2,200,000 New Initiatives 500, General Fund 1,400,000 1,500,000 1,500,000 1,400,000 Auxiliary Rm & Bd 400, , , ,000 $4,500,000 $4,500,000 $4,500,000 $4,500,000 The $4.5 million funding for deferred maintenance stabilizes in with $900,000 from Auxiliary Services and $1.4 million from the general fund. The deferred maintenance expenditure detail includes a contingency of about $600,000 per year as an estimate of the flexibility needed for this new program. This amount will be revisited in the future after some experience with deferred maintenance funding at this level. The years beyond include estimates of the amount of funding that will be spent in each general deferred maintenance category. These amounts will be revised and individual projects will be identified as each year approaches. Repayment to the Capital Budget This is the fourth year that the budget includes a summary of the projects that have been funded and have a repayment to the capital budget for some or all of the dollars that were fronted for the projects. There are four projects that currently fall into this category, and the details of the amount funded and the repayment stream can be seen on the schedule provided. Capital Expenditures Individual projects to be funded by the other University resources have been identified and documented in priority order. Except for the deferred maintenance projects, this capital budget is designed to address projects of $25,000 or more. Facilities Management has been allocated $50,000 each year from this budget to address the small maintenance and emergency projects under $25,000 each. Other small projects under this threshold are to be accommodated via the departmental budgets within the University operating budget. This $25,000 threshold is increasing from $10,000 effective July 1, This change is due to the additional flexibility that centers will have under the operating budget due to Budget Restructuring. The projected carry forward surplus at the end of the four-year window is at the level indicated to allow some flexibility for unforeseen projects that may arise during the year. 3
6 Technology Resource Allocations This is the fourth year that the technology resource allocation summary is also provided in this capital budget. This document provides a summary of the funds which have been specifically approved by the Board of Trustees and committed for technology needs to provide a comprehensive view of these projects. The funding sources for these technology projects are from various areas. This list does not include the numerous individual departmental acquisitions of computer hardware or software. 4
7 CENTRAL MICHIGAN UNIVERSITY CAPITAL BUDGET SUMMARY OF REVENUE AND EXPENDITURES Prior Year Total Projects Estimate In Process REVENUE/FUNDING State Capital Outlay $37,500,000 $0 $12,700,000 $24,800,000 $0 $0 Gifts for Athletic Projects 1,000, , , ,000 59,000 0 Reserve for Library Project 800, , Bond Funds 37,000,000 27,000,000 10,000, Est Interest on Bond Funds 1,700, ,700, Parking Services 4,102, ,025,600 1,025,600 1,025,600 1,025,600 Residences and Auxiliary Services 5,782, ,120,600 1,520,600 1,520,600 1,620,600 Res and Auxiliary Services Maintenance Fund General Fund 10,506, ,064,200 2,514,200 2,514,200 2,414,200 General Fund/New Initiatives 500, , Carry Forward from Prior Years 3,788,532 3,788, Payback from Prior Projects 1,296, , , ,000 0 Est Year End Transfers of Surpluses from Oper Units $0 $0 $0 $0 $0 Total Revenue/Funding $103,976,132 $32,129,532 $31,102,400 $30,464,400 $5,219,400 $5,060,400 CAPITAL EXPENDITURES Restricted Projects $78,000,000 $28,000,000 $25,000,000 $25,000,000 $0 $0 Other Projects 24,025, ,173,870 5,626,500 5,625,300 5,600,000 Total Capital Expenditures $102,025,670 $28,000,000 $32,173,870 $30,626,500 $5,625,300 $5,600,000 Net Surplus (Deficit) $4,129,532 ($1,071,470) ($162,100) ($405,900) ($539,600) Cumulative Surplus (Deficit) $1,950,462 $4,129,532 $3,058,062 $2,895,962 $2,490,062 $1,950,462 5
8 RESTRICTED SOURCES AND USES OF FUNDS FUNDING SOURCE Prior Year Account Total Projects Number Location Estimate In Process State Capital Outlay - Library $37,500,000 $0 $12,700,000 $24,800,000 $0 $0 Bond Funds for Library 10,000, ,000, Interest on Bond Funds 1,700, ,700, Reserve for Library Project 800, , Gifts for Athletic Projects 1,000, , , ,000 59,000 0 Bond Funds for Athletic Projects 27,000,000 27,000, Total Resources $78,000,000 $28,341,000 $24,640,000 $24,960,000 $59,000 $0 USES OF FUNDS Library Project (A) Park Library $50,000,000 $0 $25,000,000 $25,000,000 $0 $0 Athletic Projects (B) 28,000,000 28,000, Total Uses $78,000,000 $28,000,000 $25,000,000 $25,000,000 $0 $0 Net Available Resources $0 $341,000 ($360,000) ($40,000) $59,000 $0 Cumulative Surplus (Deficit) $341,000 ($19,000) ($59,000) $0 $0 (A) In addition to this project budget, an additional $700,000 from unrestricted capital funds have been allocated for related work. (B) The revised budget for this project is up to $28,825,000, with the additional $825,000 advance funded from unrestricted capital funds. 6
9 Unrestricted Sources of Funds Line Account Total No Number Estimate Funding Source 1 Parking Services $4,102,400 $1,025,600 $1,025,600 $1,025,600 $1,025, General Fund ,506,800 3,064,200 2,514,200 2,514,200 2,414, General Fund/New Initiatives , , Residences and Auxiliary Services ,782,400 1,120,600 1,520,600 1,520,600 1,620, Res and Aux Services Maintenance Fund Food Court Payback from Auxiliary Services , , , , Barnard/Tate Payback from Auxiliary Serv , , Robinson Dining Payback from Auxiliary Serv , , , Mainframe Payback from Comp Serv/Util 336, , , Est year end transfers of surplus from operating units Carry Forward Funding from ,788, Total Resources $25,976,132 $6,462,400 $5,504,400 $5,160,400 $5,060,400 7
10 General Uses of Funds Line Univ Total No Project Priority Location Estimate DEFERRED MAINTENANCE PROJECTS 1 Repair and rehabilitate elevator (advance funded) 1 Anspach $65,000 $65,000 2 Replace cold water line (advance funded) 2 Barnes 50,000 50,000 3 Replace windows 3 Barnes 188, ,000 4 Replace roof connecting Bovee UC and Barnes Hall 4 UC/Barnes 16,200 16,200 5 Replace heating and cooling unit ventilators (advance funded) 5 Brooks 30,000 30,000 6 Repair exterior wall masonry, clean and seal (advance funded) 6 Calkins 97,000 97,000 7 Energy management system upgrade - Phase I 7 Campus 65,000 65,000 8 Repair/replace pipe insulation in tunnels at north end of campus 8 Campus 120, ,000 9 Replace water-cooled with air-cooled air conditioners 9 Campus 35,000 35, Resurface drive south of stadium 10 Campus 100, , Replace asphalt sidewalks with concrete walks 11 Campus 50,000 50, Replace old exterior lights with energy efficient fixtures 12 Campus 75,000 75, Replace wiring, feedboxes, etc. for lighting in Warriner Mall 13 Campus 34,500 34, Replace leaking condensate line in main tunnel (advance funded) 14 Central Ener 50,000 50, Replace switchboard panels which serve boilers 15 Central Ener 25,000 25, Replace eave trough and underground storm sewer lines 16 Finch 40,000 40, Replace east end roof 17 IET 30,000 30, Replace leaking water pipes (advance funded) 18 Larzelere 140, , Replace roof 19 Larzelere 81,500 81, Replace north hallway and entrance roof 20 Merrill Dining 36,000 36, Replace roof (advance funded) 21 Merrill 157, , Various repairs to outdoor biology facilities 22 Neithercut 17,000 17, Replace south section of roof 23 Pearce 97,000 97, Replace roof (advance funded) 24 Robinson Di 157, , Dining commons renovation 25 Robinson Di 340, , Repair plumbing (advance funded) 26 Robinson 105, , Repair/modernize elevator (advance funded) 27 Ronan 35,000 35, Repair/replace plaster and paint interior of building 28 Sloan 500, , Replace roof 29 Sloan 150, , Replace windows (advance funded) 30 Sloan 138, , Repair soffits/fascia joints/clean stonework (advance funded) 31 Thorpe 115, , Replace dome roof and replace defective water valves 32 University C 407, , Repair masonry and stonework (advance funded) 33 Warriner 47,000 47, Repair water penetration problem/basement area 34 Warriner 75,000 75, Repair/replace exterior soffits 35 Washington 36,000 36,000 8
11 General Uses of Funds Line Univ Total No Project Priority Location Estimate Replace office and first floor level roofs 36 West 10,300 10, Repair/replace roof - west end 37 Wheeler 21,800 21, Replace roof 38 Wightman 156, , Roofing $1,500,000 $0 $500,000 $500,000 $500, Masonry 900, , , , Mechanical and plumbing 1,200, , , , Electrical 5,550, ,850,000 1,850,000 1,850, Architectural 2,550, , , , Contingency 2,405, , , , , SUBTOTAL DEFERRED MAINTENANCE $18,000,000 $4,500,000 $4,500,000 $4,500,000 $4,500, OTHER PROJECTS 49 Pool of funds for small maintenance projects (<$25,000) 39 Campus $200,000 $50,000 $50,000 $50,000 $50, Annual sidewalk repairs 40 Campus 160,000 40,000 40,000 40,000 40, Annual ADA changes 41 Campus 900, , , , Annual asphalt repair - parking lots, roads 42 Campus 400, , , , , Annual utility/mechanical asbestos abatement 43 Campus 360,000 90,000 90,000 90,000 90, Annual wood floor maintenance 44 Campus 80,000 20,000 20,000 20,000 20, Upton drain, phase 2 45 Campus 78,370 26,570 26,500 25, SAP system upgrade 46 Campus 650, , Pave parking lot 62 and drive (advance funded) 47 Campus 809, , Elevator replacement 48 Ronan 165, , TEPD office move and remodel 49 Ronan 67,700 67, SASW main office remodel 50 Anspach 37,600 37, EACL classroom remodel and multi-media equipment 51 Ronan 92,500 92, Upgrade HVAC system 52 Anspach 25,000 25, Administrative student system replacement 53 Foust 2,000, , , , , SUBTOTAL OTHER PROJECTS $6,025,670 $2,673,870 $1,126,500 $1,125,300 $1,100, TOTAL PROJECTS $24,025,670 $7,173,870 $5,626,500 $5,625,300 $5,600, ANNUAL SURPLUS (DEFICIT) ($711,470) ($122,100) ($464,900) ($539,600) 67 CUMULATIVE SURPLUS (DEFICIT) * $3,077,062 $2,954,962 $2,490,062 $1,950,462 * Includes prior year carryforward plus current year sources, less current year projects. 9
12 Summary of Projects With a Repayment to the Capital Budget Amount Total Funded Project by Capital When Repayment Schedule Total Project Name Amount Budget Funded Repayment Foodcourt Renovation $ 1,600,000 $ 800, $ 114,300 $ 185,700 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 800,000 Barnard/Tate Demolition (a) 1,445,000 1,445, , , , , ,040,000 Mainframe Purchase (b) 1,359, , ,800 15, , , , ,400 Robinson Food Commons (c) 975, , , , ,000 Totals $ 5,379,500 $ 3,772,500 $ 114,300 $ 461,500 $ 375,800 $ 575,800 $ 752,000 $ 444,000 $ 100,000 $ 2,823,400 (a) The net capital budget contribution for this project equals $405,000 for the landscaping and relocation of ROTC as a result of this demolition. (b) The net capital budget contribution for this project equals $204,100 (c) The funding for this project includes $340,000 of the funds earmarked for deferred maintenance, $235,000 from Auxiliary maintenance, renovation and remodeling, and the remaining $400,000 from the general capital budget. Estimated interest charges of $20,000 will flow to the General Fund interest income account. 10
13 Technology Resource Allocation University Supported Capital Projects. Date *all figures in US Dollars Description Base One Time Dec 1995 Mainframe Purchase 1,359,300 Feb 1996 Network Workshop 75,000 Feb 1996 University Advancement Upgrade 164,550 Feb 1996 Network Completion 273,446 Feb 1996 Upgrade Electrical for Network 347,500 Feb 1996 Replace DAVOX 180,000 Apr 1996 Asst Vice Provost position 89,388 Apr 1996 Student Computer and Classroom Improvements 1,000,000 May 1996 Fund Faculty Development for Tech Learn 100,000 Sep 1996 Fund Distance Learning Coordinator 84,598 Sep 1996 Student Computer and Classroom Improvements 750,000 Sep 1996 Education Technology Grant Program 200,000 Sep 1996 Library Technology Plan 100,000 Sep 1996 Technology Teaching and Learning Center 100,000 Sep 1996 Expand Campus Network 1,300,000 Sep 1996 Sep 1996 Mar 1997 Purchase of Additional DASD for Enterprise Server Purchase of Prospect Tracking for Admissions Fund partial implementation of SAP HR and FI Systems 400, ,100 3,496,000 11
14 Apr 1997 Purchase of UNIX Upgrade for IET and Pearce 245,000 Dec 1997 Meridian SL100 Switch Upgrade 700,000 Dec 1997 Purchase Library Information System 400,000 Mar 1998 Expand Campus Network 450,000 Sep 1998 Computer Lab for SAP Systems 200,000 Dec 1998 Campus Network Security 300,000 Mar 1998 Y2K Remediation 412,000 Total $506,586 $12,669,896 12
15 MULTI-YEAR PROJECTS PROJECT APPROVAL TO BE GRANTED WITH THE APPROVAL OF THE CAPITAL BUDGET DOCUMENT Prior Year Line Total Projects No Project Location Estimate in Progress Restricted Fund Projects 3 4 Library Project Park Library $50,000,000 $0 $25,000,000 $25,000,000 $0 $0 5 Athletic Projects 28,000,000 28,000, SUBTOTAL RESTRICTED PROJECTS $78,000,000 $28,000,000 $25,000,000 $25,000,000 $0 $ Unrestricted Fund Projects Additional Library Project site demolition, Park Library $700,000 $700,000 $0 $0 $0 $0 12 relocations, landscaping 13 Dining commons renovation Robinson 975, , , $1,675,000 $1,335,000 $340,000 $0 $0 $0 15 SUBTOTAL UNRESTRICTED PROJECTS TOTAL PROJECTS $79,675,000 $29,335,000 $25,340,000 $25,000,000 $0 $0 13
APPENDIX A FULL TEXT OF BOND MEASURE
APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass
More informationPage Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182
Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Operational Services/Central Services/Axtell Park School
More informationContents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure...
Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 6 Impartial Analysis... 7 Statement in Favor of Measure... 8 Ballot Measure EXHIBIT A HANFORD ELEMENTARY SCHOOLS REPAIR
More informationBallot Measures-T Section
T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and
More informationSOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S
SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S Under this measure, the Somis Union School District ( District ) is submitting a bond measure, described below, to the voters
More informationBallot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools
Section Ballot Measures-N N Centralia Elementary School District, Building Strong Neighborhood Schools To repair/modernize aging classrooms, science labs/school facilities to keep pace with technology,
More informationPhysical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15
Physical Plant Five-Year Capital Budget Plan State College Area School District November 2011 Page 1 of 15 Table of Contents Background and 2013 Projects Pages 3-5 Funding Level Pages 6-7 Existing Buildings
More informationUNIVERSITY of HOUSTON MANUAL OF ADMINISTRATIVE POLICIES AND PROCEDURES
UNIVERSITY of HOUSTON MANUAL OF ADMINISTRATIVE POLICIES AND PROCEDURES SECTION: Facilities Number: 09.04.04 AREA: Facilities Management and Maintenance Information SUBJECT: Maintenance Project Evaluation
More informationPhysical Plant. Detailed Assessment Report
Physical Plant Detailed Assessment Report 2011-2012 Mission / Purpose The Physical Plant Department enhances the University of West Alabama's mission to provide opportunities for students to pursue a quality
More informationGoverning Board Bond Update. Measure G Bond Program. for. Solano Community College District
Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects
More informationContents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...
Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... 10 Ballot Measure EXHIBIT B MEASURE Y (ABBREVIATED FORM)
More informationCentral Michigan University Mount Pleasant, Michigan Purchasing - Facility Management Office for Sustainable Purchasing Program
Central Michigan University Mount Pleasant, Michigan Purchasing - Facility Management Office for Sustainable Purchasing Program SCHOOL Central Michigan University (CMU) is a four-year, public university,
More informationStatus: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.
Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationPage Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160
- Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 Special Education Allocation 161 Operational Services
More informationMUROC JOINT UNIFIED SCHOOL DISTRICT KERN COUNTY NORTH EDWARDS, CALIFORNIA
KERN COUNTY NORTH EDWARDS, CALIFORNIA FINANCIAL AND PERFORMANCE AUDIT JUNE 30, 2018 TABLE OF CONTENTS JUNE 30, 2018 PAGE INTRODUCTORY SECTION TABLE OF CONTENTS i FINANCIAL SECTION INDEPENDENT AUDITOR'S
More informationBacklog Reduction Plan
2003-2013 Executive Summary proposes to achieve reductions in our facilities maintenance backlog by documenting and completing backlog projects on a priority basis and by minimizing or eliminating future
More informationOceanside Gateway Business Park O. A.
Operating Budget-Final Parcel Parcel Address Parcel / Bldg / Unit Sq. Ft. % of project Total Monthly Assessment Total Quarterly Assessment PSF/Mo. 1 Hamann Co 33,100 6.78% $ 1,735 $ 5,205 $ 0.052 2-1 BP
More informationBuilding and Site Sinking Fund Millage. Election Date: November 7th 2017
Building and Site Sinking Fund Millage Election Date: November 7th 2017 How do Districts Fund Facilities and Technology Needs? General Fund - Use current operating dollars. These are limited to the amount
More informationTumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent
Tumwater University School District Budget Myths Bond Project Update February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Construction Update $136,000,000 in bonds approved
More informationRockville Science Center (P036600)
Rockville Science Center (P036600) (AAGE15) Rockville Date Last Modified 2/26/14 N/A-PS Planning, Design and Supervision 6,492 6,477 15 0 0 0 0 0 0 0 0 Construction 56,300 56,272 28 0 0 0 0 0 0 0 0 6,598
More informationPage Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175
Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Special Education Allocation 176 Operational Services Allocation
More informationTwo Ballot Proposals. August 8, 2017
Two Ballot Proposals August 8, 2017 Per-Pupil Foundation Allowance Ten-Year History for Schools* Per-Pupil Foundation Allowance Ten-Year History for Schools* FYs 2007-08 through 2016-17 FY2008 FY2009 FY2010
More informationCapital Projects Completed since 1988
Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990
More informationAttachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017
A. Approval - New (Non-State and Other State Funds) Name (Other State) (Other State) Non-State Funds/ Undetermined 1 N/A B. Approval - Amended (Non-State and Other State Funds) 1 Coastal Carolina Main
More informationORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/15/2013 BUILDING SURVEY DATE
0807 3502 SOUTH FIRST STREET CHAMPAIGN, ILLINOIS SYSTEM CONDITION INDEX.771 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 347,400 LABORATORY BUILDING GROSS SQUARE FEET 16,986
More informationCIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5
CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 Edwin Ataide Deputy Director Plant & Facilities SCH-1 School Projects All Schools Priority FY15 FY16 FY17 FY18 FY19 ADA Compliance (Handicap Accessibility)
More informationReserve Request Instructions: Documentation Requirements
Reserve Request Instructions: Documentation Requirements These instructions specify documentation that must be submitted with requests for withdrawals from property reserve accounts held by IHDA. All requests
More informationSpringfield High School
5.1 Springfield High School Springfield School District Delaware County - Pennsylvania Master Plan Presentation Town Hall Meeting 5 Project Cost Estimates/ Project Financing Strategy / Tax Impact February
More informationCAPITAL PROJECT PROCESS
CAPITAL PROJECT PROCESS May 2009 GETTING STARTED What is a project? A project is defined as all work (maintenance & repair or renovation) that requires 5,000 or more in time and materials and/or is sufficiently
More informationAction Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List
Action Item TO: PRESENTED BY: BOARD AGENDA ITEM: Board of Trustees and Superintendent of Schools Sid Albaugh, Assistant Superintendent Business Services Consideration of Approval of 2018 Measure A Facilities
More informationUNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011
UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 OVERVIEW Financial highlights of the 3 rd quarter financial report for fiscal year 2011-12 are summarized below: Cash The University s cash
More informationUNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018
UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 09/30/2018 OVERVIEW Financial highlights of the fiscal year 2018-19 1 st quarter financial report are summarized below: Cash (pages 2-3) The University
More informationCapital Projects Fund. Board Work Session August 9, 2007
Capital Projects Fund Board Work Session August 9, 2007 Presentation Objectives Building inventory Revenue sources statutory adjustments and uses Demonstrate past use of funds 2008 proposed budget Setting
More informationAllan Hancock Joint Community College District
One Stop Studen Allan Hancock Joint Community College District One Stop Student Services Public S Public Safety Com Public Safety Complex Childc Childcare Addit Childcare Addition BOND MEASURE I Progress
More informationFiscal Year (FY13) Operating Budget and Capital Budget Overview
Approved by President Rush Fiscal Year 2012-2013 (FY13) Operating Budget and Capital Budget Overview Background A university budget represents the complex interchange between revenue streams that support
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING December 12, 2012
Project Name by Phase Project # Current BOT Approved Budget Encumbrances (As of 11/28/12) Budget Phase Budgeted Funding Source(s) (s) Planning Budget Phase Ecology and Evolutionary Biology (EEB) 201583
More informationDRAFT. PROJECT POLICY CAPITAL AND OPERATING Approved by: History: Administrative Policy Policy Number: REYNOLDA CAMPUS CONTENTS:
REYNOLDA CAMPUS PROJECT POLICY CAPITAL AND OPERATING Approved by: History: Type: Administrative Policy Policy Number: 3.3.02 Responsible Official: Executive Vice President Related Policies: CONTENTS: I.
More informationTO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM
104 Office of the President TO MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM AND APPROVAL OF EXTERNAL FINANCING
More informationCMP Strategy Project Listing by Cluster (Includes Technology and SIPs. Does not include SB9-08 M&O projects)
2006-20 CMP Strategy Listing by Cluster (Includes Technology and SIPs. Does not include SB9-08 M&O projects) Architectural Research Consultants, Incorporated October, 2004 Cluster: Albuquerque 244 DOLORES
More informationUNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2013
UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT OVERVIEW Financial highlights of the Fiscal Year 2012-13 3 rd quarter financial report are summarized below: Cash (pages 2-3) The University s cash position
More informationHayfield Community Schools Bond Referendum. Vote Monday, September 11, Our Schools Our Communities Our Future
Hayfield Community Schools 2017 Bond Referendum Vote Monday, September 11, 2017 Our Schools Our Communities Our Future 2017 Bond Referendum What s Already Been Done? Studies and Meetings and Meetings 2014-15
More informationAPPENDIX E ALLOWABLE CAPITAL EXPENDITURE GUIDELINES
APPENDIX E ALLOWABLE CAPITAL EXPENDITURE GUIDELINES Introduction State capital appropriations are funded primarily through the issuance of State bonds. State bonds must be authorized by Ohio voters via
More informationMT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE R, NOVEMBER 2001) PERFORMANCE AUDIT.
(MEASURE R, NOVEMBER 2001) (MEASURE R, NOVEMBER 2001) CONTENTS Page Independent Auditor s Report... 1 Objectives... 2 Scope of the Audit... 2 Background Information... 3 Procedures Performed... 3 Results
More informationLos Angeles Unified School District Page 1 of 3
Los Angeles Unified School District 333 South Beaudry Ave, Los Angeles, CA 90017 Board of Education Report File #: Rep-201-16/17, Version: 1 Amendment to the Facilities Services Division Strategic Execution
More informationMeasure RR Bond Budget by Project. Measure RR BAN Measure RR BAN Interest Measure RR Series AB Measure RR Series AB Interest
6/30/15 15/16 Thru 6/30/15 15/16 Thru 6/30/15 15/16 Thru 6/30/15 15/16 A Library, Learning Resources and Campus Center 217,200 GSF; State Funding component; begin design est. 2015/16 771120 $ 197,529.21
More informationDeferred Maintenance Phase I Report
Ohio University Deferred Maintenance Phase I Report A Case for Addressing Deferred Maintenance Needs at Ohio University Prepared by: University Planning and Implementation and Facilities Management Ohio
More informationDESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2010
(MEASURE B, MARCH 2004) (MEASURE B, MARCH 2004) TABLE OF CONTENTS Page Independent Auditors Report 1 Objectives... 2 Scope of the Audit.. 2 Background Information. 2-3 Procedures Performed... 3-4 Results
More informationOVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE
MEASURE C SCHOOL SAFETY AND MODERNIZATION On November 3, 2009 the voters residing in the Mill Valley School District (MVSD) approved the Measure C Safety and Modernization Bond of 2009 (Measure C). Measure
More informationStatus: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.
Page 1 of 14 FACILITIES PLAN STATUS REPORT August 24, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid
More informationUNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2017
UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2017 OVERVIEW Financial highlights of the fiscal year 2016-17 3 rd quarter financial report are summarized below: Cash (pages 2-3) The University
More informationSubject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH)
HIP Housing In Peel Subject: Capital Reserve Expenditure Guidelines Date: August 1, 2012 Applicable To The information contained in this document applies to the following: Municipal & Private Non- Federal
More informationHUENEME ELEMENTARY SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE T
HUENEME ELEMENTARY SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE T Under this measure, the Hueneme Elementary School District ( District ) is submitting a bond measure, described below,
More informationCH-UH Board of Education Meeting. June 27, 2017
CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle
More informationUNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010
UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 12/31/2010 OVERVIEW The following is a summary of the financial highlights contained in the second quarter report for fiscal year 2010-11: Cash and Accounts
More informationENROLLED ACT NO. 18, HOUSE OF REPRESENTATIVES SIXTY-FOURTH LEGISLATURE OF THE STATE OF WYOMING 2018 BUDGET SESSION
AN ACT relating to school finance; modifying the formula and payment structure for major maintenance funding for public K-12 schools; revising the definition of major maintenance; amending requirements
More informationBudget Analysis Fiscal Year John A. Logan College Carterville, IL 62918
Budget Analysis Fiscal Year 2017 John A. Logan College Carterville, IL 62918 June 28, 2016 1 JOHN A. LOGAN COLLEGE TABLE OF CONTENTS BUDGET ANALYSIS FY 2017 ITEM PAGE BUDGET CALENDAR... 1 BUDGET PROCESS...
More informationFacility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA
AGENDA benefits & limitations Rod Moore, RA, LEED AP, PMP Georgia Tech Benjamin Dutton, FFB, MCIOB, MRICS Faithful+Gould GT Facilities GT Program What is GT FCA Deliverables How GT uses FCA Information
More informationUniversity of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus)
of Colorado Capital Project Status SUMMARY - May (accounting noted by campus) Legend On-Track Risks Approved - Adjustments Needed Awaiting $ Start-Up Phase In Bidding Phase In Closeout Project Completed
More informationLake Mills Area School District Community Survey Results. Spring 2018
Lake Mills Area School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in late May through mid-june of 2018. Residents within the District were mailed a paper survey.
More informationMinutes Capital Planning and Budget Committee Thursday, August 23, 2012
Minutes Capital Planning and Budget Committee Thursday, August 23, 2012 The meeting of the Capital Planning and Budget Committee was called to order at 1:00 pm by Committee Chair Regent Jeffrey Bartell
More informationSANTA ROSA JUNIOR COLLEGE
SANTA ROSA JUNIOR COLLEGE 2017-2018 BUDGET 2017-18 BUDGET Presented to the Board of Trustees for Adoption September 12, 2017 Office of Finance & Administrative Services Doug Roberts Senior Vice President,
More informationSanta Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013
Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013 Measure V Bond Construction Fund Year Ended June 30, 2013 Table of Contents Page Independent Auditors'
More informationFacilities Development and Operations
Facilities Development and Operations Dashboard/Metrics Report California State University, East Bay July 1, 2016 to June 30, 2017 1 Who We Are: Vice President Administration & Finance Division Associate
More informationFacilities Planning & Construction Report nd Quarter Ending December 31, 2017
Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By
More informationFY 2018 Stockton University Operational & Capital Report as of May 31, 2018
FY 2018 Stockton University Operational & Capital Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 Internal Capital Projects 4-5 Other Capital Projects 6 State
More informationComprehensive Reserve Fund Study and Building Condition Assessment for Wellington Standard Condominium Corporation No. 149
Comprehensive Reserve Fund Study and Building Condition Assessment for Wellington Standard Condominium Corporation No. 149 820 Gartshore Street Fergus, Ontario Report Prepared for the Board of Directors
More informationSummary Report - Texas A&M University (010366)
Page 1 of 6 Summary Report - Texas A&M University (010366) MP2&3 - Assesment of Deferred Maintenance and Demolition Needs Building Proj. Desc. Type Pri Crit? Arch HVAC P&E Safety L&M Other Project Cost
More informationBERKELEY UNIFIED SCHOOL DISTRICT
BERKELEY UNIFIED SCHOOL DISTRICT TO: Javetta Cleveland and Neil Smith, Co-Superintendents FROM: Lew Jones, Director of Facilities DATE: June 26, 2013 SUBJECT: Approval of the 2013/14 Measure H Annual Plan
More informationUNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 06/30/2017
UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 06/30/2017 OVERVIEW Financial highlights of the fiscal year ending June 30, 2017 financial report are summarized below: Cash (pages 2-3) The University
More informationIntegrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs
Building Bridges to Net Zero Integrating Green Building Measures into Capital Planning for HUD Assisted and Public Housing Programs Evolution of HUD's Green Capital Needs Assessment, and the new CNA etool
More informationListing of Events Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School
Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School Building Events 2004 2005 2006 2007 2008 Total Code Repair Add ventilation to storage room $ 1,000.00 $ - $ - $ - $ - $ 1,000.00
More informationCity School District of Albany Five Year Facilities Plan 3/14/2019
Bold indicates change from 3/7/19 BOE meeting Available Local Share $ 3,300,000 1 SPA Air condition gymnasium $ 267,000 1 $ 41,385 $ 41,385 $ 267,000 2 DCS Air condition gymnasium $ 221,000 1 $ 34,255
More informationReserve Fund Study My Condominium Plan
Reserve Fund Study My Condominium Plan 12 3456 Number of Units 36 Number of Buildings 1 Building Construction 21 Contact Ima Happy Position(s) President Contact Phone 43.555.4321 Report Date August 8,
More informationINTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationGarden City Public Schools Capital Reserve. Presentation to the Board of Education January 10, 2017
Garden City Public Schools Capital Reserve Presentation to the Board of Education January 10, 2017 Tonight s Agenda District Reserves Planning process General use Current reserves Capital Reserve Voter
More informationOur Focus: Your Future
Town of Fort Erie Infrastructure Services Our Focus: Your Future Prepared for Council-in-Committee Report No. IS-53-07 Agenda Date November 19, 2007 File No. 220102 Subject 5 YEAR FACILITY CONDITION STATUS
More informationLEE COUNTY SCHOOL DISTRICT S CAPITAL PLANNING PROCESS
LEE COUNTY SCHOOL DISTRICT S CAPITAL PLANNING PROCESS A Capital Projects Management Team has been established consisting of the Superintendent, the Chief Administrative Officer, the Chief Academic Officer,
More informationFacilities Management and Planning Organizational Review Phase II Update
MEMORANDUM Office of College Services DATE: September 3, 2013 TO: CC: FROM: SUBJECT: President Mary Spilde, Vice President Brian Kelly Facilities Management & Planning Organizational Review Team Jennifer
More informationLocal ballot measure: B. Redding School District Bond Measure
B Redding School District Bond Measure Ballot question To improve the quality of education; repair/replace leaky roofs; modernize and construct classrooms, restrooms and school facilities; and make health,
More informationMeasure G Quarterly Progress Update
Measure G Quarterly Progress Update February 3, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure
More informationUrban Heights Condominium
Condominium Capital 2011 2010, AssociationAnalysis, LLC Condominium Prepared For: Table of Contents Condominium Association, Inc. 1642 Maxwell Road Atlanta, GA 30012 October 19, 2010 INTRODUCTION INTRODUCTION
More informationPROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue
PROPOSITION FARMINGTON SCHOOLS April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS - BOND LANGUAGE Shall the Board of Education of the Farmington R-7 School District of St. Francois County, Missouri,
More informationFY 2014/ /24 CAPITAL IMPROVEMENTS PROGRAM MAINTENANCE/REPLACEMENT PROJECTS DETAIL
Year 1 Project Revenue County Category FY 14/15 Total Offset Cost I 1 AGNOR HURT HVAC Design Chiller and Exhaust Fans replacement $30,000 $0 $30,000 I 2 AGNOR HURT HVAC Design replacement of 6 RTUs $35,000
More informationAnson County Early College High
NC School District/040 Anson County/High School Anson County Early College High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary
More informationSanta Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015
Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015 Measure V Bond Construction Fund Year Ended June 30, 2015 Table of Contents Page Independent Auditors'
More informationFY 2017 Stockton University Expenditure Report as of May 31, 2017
FY 2017 Stockton University Expenditure Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 FY17 Internal Capital Projects 4 State Bond/Grants 5 STOCKTON UNIVERSITY
More informationEducational & Performing Arts Center: Downriver Campus
Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - April 26, 2017
Project Name by Construction Project # Planning Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Stamford Campus Improvements/Housing
More informationMinutes Capital Planning and Budget Committee Thursday, July 9, 2009
Minutes Capital Planning and Budget Committee Thursday, July 9, 2009 Committee Chair Regent Bartell convened the meeting of the Capital Planning and Budget Committee at 9:08 a.m. in Room 1820 of Van Hise
More informationOverview of Public Schools CIP
Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, such as additions and modernizations, as well as other school-related projects. School construction
More informationPriority #1 Request for Construction FY Priority #2 Anticipated Request for Planning FY 2019
V. IMPLEMENTATION PLAN a) Prioritize major capital projects requested from the State, including a brief project description and estimated cost, in the format provided. (Adjust previously developed or prior
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018
SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center & Demolition Science Center
More informationCAPITAL FUNDING SUMMARY
CAPITAL SUMMARY SCC (School Consolidation Capital ) CAPITAL : B19 -December 1, Specifically to address a school board s excess capacity : B11 -May 26, Opportunity to identify most urgent & pressing accommodations
More informationInformational Session for Fiscal Year Budget
Informational Session for Fiscal Year 2016-2017 Budget PRESENTED BY Angela M. Poole, CPA Acting Vice President for Finance and Administration Florida Agricultural and Mechanical University Budget and Finance
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - June 28, 2017
Planning Budget Phase Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $0
More informationSam Houston State University A Member of The Texas State University System
Finance & Operations Procurement and Business Services Policy FO-PUR-17 Purchases with Higher Education Assistance Funds (HEAF) Article VII, Section 17 of the Texas Constitution established the Higher
More informationBallot Measures-LL Section
LL To repair and modernize aging classrooms/school facilities at local elementary/intermediate schools, repair termite damage, dry rot, deteriorating roofs, plumbing, and electrical, improve student safety/security,
More informationInterest Earned through 6/30/2018 2,013, , ,029, ,454, (3,443,911.91) 29, ,500, ,540,322.
STATUS OF DISTRICT RESERVES NORTH SHORE CSD Background Reserve funds are an important planning tool generally used by local governments and school districts to save for future needs and other allowable
More informationPolicy 3-205: Remodeling and Construction Policy
Policy 3-205: Remodeling and Construction Policy I. Purpose To provide for the planning, funding, approval, design and completion of remodeling and construction projects. These policies and Procedures
More information2019 Capital Projects Plan
Rev. 03/18 School Name Crawford County Community School Corporation County Name Crawford School No. 1300 2019 Capital Projects Plan The following plan format should be used for your 2019 Capital Projects
More information