1 Program and Project Status Update Citizens Bond Oversight Committee Meeting October 14, 2014 Robert Ball, Bond Program Manager 1
2 Capital Improvement Program General Updates Close out of completed projects DSA, financial, records archiving Formal startup of new projects Tech Bond (Measure I) - $113.2M November 4 th General Election $78.9 M Measure E unsold - $60 M available now 2
3 Summary of Infrastructure Upgrades Mechanical Controls $ 50 K Domestic Water $200 K Gas Piping $200 K Exterior Lighting $270 K Sanitary Sewer $380 K Exterior Paint $400 K Security Systems $455 K Irrigation $510 K Power $510 K Storm Drain $742 K Tree Work $1.2 M Security Cameras $1.9 M HVAC $4.1 M Fire Alarm $18.3 M Total: $29.2 M 3
4 School Modernization Funding Gap Comprehensive Schools $432,233,010 Alternative Education $ 19,100,000 Infrastructure $137,800,000 Sub-total: $589,133,010 Program Overhead 10% $ 58,913,300 Total $648,046,311 4
5 Capital Improvement Program Construction Cost Escalation Economic growth is projected to continue Bay Area construction market is heating up Volume increasing 9.2% for the next three years through 2017 Expected to reach peak 2005 volume by 2016, plateau in 2017 Strained labor resources: steel erectors, welders, plumbers, pipefitters, sheet metal workers, electricians Top current and future Bay Area projects Apple Campus 2 HQ $ 5.0B Transbay Transit Center $ 4.0B Treasure Island Phase 1 $ 1.5B City Place Santa Clara $ 1.0B UC Berkeley, UCSF $ 1.4B 5
6 Capital Improvement Program Construction Cost Escalation November 2014 education bond elections California $11.3B Greater Bay Area $ 3.9B South Bay $ 1.3B Projected Annual Escalation Rates % % % % % 6
7 Capital Improvement Program Construction Cost Escalation Future Cost Projections of Funding Gap for School Modernization 2014 $648,046, $694,057, $753,052, $793,340, $829,675, $865,351, $902,562,003 7
8 Andrew Hill High School New Classroom Building 100 six art classrooms, two chemistry labs and three general education classrooms, art gallery Budget: $13.8M CM: Blach Construction Architect: Cody Anderson Wasney Contractors: George E. Masker Painting Beals Martin King s Roofing Del Monte Electric RLH Fire Protection Duran & Venables Robert A. Bothman Environmental Sys, Inc. Val s Plumbing and Heating Occupancy: January,
9 Andrew Hill High School New Classroom Building 100 9
10 Andrew Hill High School Site and Infrastructure Improvements Upgrade Quads & courtyards Install new foul ball net at Baseball field Budget: $2.3M CM: Van Pelt Construction Services Proposal for Architectural Services will be finalized and issued in upcoming weeks. Kick-off meeting completed between Facilities and CM s project teams. 10
11 Evergreen Valley High School Miscellaneous Building Improvements door locks improvements to rooms A113 and A139 Budget: $1.4M CM: Kitchell CEM Architect: IBI Group Architects Contractor: R.C. Benson & Sons, Inc. Construction Start: May, 2013 Occupancy: Fall,
12 Evergreen Valley High School Miscellaneous Building Improvements A113 BEFORE A113 AFTER A113 AFTER A139 AFTER 12
13 Evergreen Valley High School Site Improvements Increment 1 Widening of walkways into Building A, B, C, D breezeways (Completed) Budget: $852K CM: Kitchell CEM Architect: IBI Group Architects Contractor: R.C. Benson & Sons, Inc. Completion: February,
14 Evergreen Valley High School Site Improvements Increment 1I Hard court resurfacing (In process) Budget: $852K 14
15 Independence High School Modernization of Performing Arts Center Building F Lobby expansion Mechanical, Electrical, Plumbing upgrades New theater seats, flooring, curtains ADA upgrades Restrooms upgrades Dance studio upgrade Budget: $8.7M CM: Van Pelt Construction Services Architect: Cody Anderson Wasney LLB Developer: McCarthy Building Companies, Inc. Construction Start: October, 2014 Occupancy: Fall
16 : Independence High School Building B Bicentennial Hall Modernization Modernize Bld B and repair fire damage Budget: $5.3M CM: Van Pelt Construction Services Contractor: McCarthy Building Companies, Inc. In design 16
17 Independence High School Campus Site Improvement Projects Streetscape enhancements N. Jackson Ave Infrastructure upgrades Wayfinding improvements Budget: $2.1M CM: Van Pelt Construction Services Contractor: McCarthy Building Companies, Inc. 17
18 Independence High School Miscellaneous Refurbish Occupancy preparations for incoming charters schools, Downtown College Preparatory and ACE Charter School Budget: $250K CM: Strawn Construction Occupancy: Summer
19 James Lick High School Buildings 200, 300 Integrated Classrooms Merge 16 classrooms into 8 integrated classrooms Provide furniture and equipment to support innovative learning structures Budget: $976K CM: Facilities Project Management Architect: Artik Art & Architecture Construction Start: July, 2014 Occupancy: August,
20 James Lick High School Buildings 200, 300 Integrated Classrooms Before and progress photos of classrooms in 200, 300 Buildings 20
21 James Lick High School Buildings 200, 300 Integrated Classrooms ROOM 206 ROOM 308 ROOM 208 ROOM
22 Mt. Pleasant High School Mini Campus Modernization Miscellaneous improvements to create a mini campus for Summit Rainier Budget: $1.1M CM: Strawn Construction Architect: Artik Art & Architecture Contractor: Cal State Construction, Inc. Construction Start: June 2014 Occupancy: August, 2014 Completion: October,
23 Mt. Pleasant High School Mini Campus Modernization 23
24 Mt. Pleasant High School Stadium Fence Painting Remove existing paint/coating and re-paint existing approx.1250 linear feet steel fence around Stadium, due to paint failure Budget: $175K CM: Facilities Project Management Completion: November,
25 Oak Grove High School Modernization of Theater Building I Mechanical, Electrical, Plumbing upgrades New theater seats, flooring, curtains ADA upgrades Restrooms upgrades Budget: $4.2M CM: Kitchell CEM Architect: WLC Architects, Inc. Construction contract award recommendations October 16 th Board Meeting 25
26 Oak Grove High School Modernization of Classroom Building U Modernization of 20 classrooms Budget: $5.1M CM: Kitchell CEM Architect: WLC Architects, Inc. Construction contract award recommendations October 16 th Board Meeting 26
27 Santa Teresa High School Stadium Lighting and Main Electrical Switchgear New stadium lighting Upgrade main electrical switchgear Budget: $1.9M Submitted to DSA in June for review Design team is currently addressing review comments 27
28 Silver Creek High School Stadium Lighting New stadium lighting Budget: $1.4M CM: Strawn Construction Engineer of Record: Salas O Brien Contractor: Bleyco, Inc. Construction Start: May, 2014 Completion: September,
29 Silver Creek High School Stadium Lighting 29
30 W.C. Overfelt High School Modernization of Building J Modernize Special Education classroom into Life Skills classroom for Special Education students Budget: $3.5 million CM: Van Pelt Construction Services Architect: FMPO, Inc. In design 30
31 W.C. Overfelt High School Campus Improvements Repair Sanitary sewer system and irrigation system controls Upgrade controls for exterior lighting fixtures Renovate Baseball Complex East Budget: $170K CM: Van Pelt Construction Services In design 31
32 Yerba Buena High School New Student Union and Quad Modernization Demolish portion of Building 100 Construct new student union Refurbish remainder of Building 100 Modernize quad Budget: $13.5M Primary Business Partner CM and Design-Build Criteria Docs: Kitchell CEM Program and criteria documentation phase 32
33 Yerba Buena High School Miscellaneous Refurbishment Occupancy preparations for incoming charter school, Luis Valdez Leadership Academy Budget: $250K CM: Strawn Construction Occupancy: Summer
34 Districtwide Projects Asphalt Repair Multiple sites walkways, parking lots, basketball courts Budget: $800K CM: Facilities Project Management Contractors: Duran & Venables, Inc. Joseph J. Albanese, Inc. Construction Start: Summer, 2014 Completion: Fall,
35 Districtwide Projects Asphalt Repair FOOTHILL SILVER CREEK OAK GROVE PIEDMONT HILLS 35
36 Districtwide Projects Roofing Repair Roof condition assessment Re-roofing of buildings at multiple sites Budget: $748K CM: Facilities Project Management Engineer: Skyline Engineering District wide roofing assessment in progress Construction documents November 2014 Bidding December January
37 Districtwide Projects Energy Efficiency Project Program Development survey & analysis ESCO contract Budget: about $17.5M Prop 39 Energy funds: about $6.5M Measure G: $9M Deferred Maintenance: $2M CM: Swinerton Management & Consulting Energy Services Provider: OpTerra Energy Services (formerly known as Chevron Energy Services) Program Development: March 2014 Oct
38 Districtwide Projects Swimming Pool Upgrades Modernization at 7 sites Budget: $12.5M Primary Business Partner CM: Swinerton Management & Consulting : RFP in October 38
39 Districtwide Projects Exterior Door Replacement Replace selected doors and/or frames at multiple sites Budget: $861K Primary Business Partner CM: Facilities Project Management Architect: Dreiling Terrones Architecture In design 39
40 Districtwide Projects Security Camera Upgrades Upgrade cameras and infrastructure districtwide Budget: $5M Capital Facilities Fund 25: $1.0M Measure I Fund 24: $3.0M School Facility Fund 35: $1.0M CM: Swinerton Management & Consulting Engineer: The Consulting Group In design 40
41 Districtwide Projects Back End Computer Systems Upgrades : Upgrade storage and switch at District Network Center Budget: $2.4M Primary Business Partner CM: District staff Vendor: TBD District re-released RFP in October after making revisions to project scope 41
42 Questions? 42
EAST SIDE UNION HIGH SCHOOL DISTRICT 2002 MEASURE G GENERAL OBLIGATION BONDS PERFORMANCE AUDIT JUNE 30, 2011
2002 MEASURE G GENERAL OBLIGATION BONDS PERFORMANCE AUDIT 2002 MEASURE G GENERAL OBLIGATION BOND FUND TABLE OF CONTENTS Independent Auditor s Report 1 Authority for Issuance 2 Purpose of Issuance 2 Authority
More informationEAST SIDE UNION HIGH SCHOOL DISTRICT ANNUAL FINANCIAL REPORT FOR THE YEAR ENDED JUNE 30, 2014
EAST SIDE UNION HIGH SCHOOL DISTRICT ANNUAL FINANCIAL REPORT FOR THE YEAR ENDED TABLE OF CONTENTS FINANCIAL SECTION Independent Auditor s Report 2 Management's Discussion and Analysis 6 Basic Financial
More informationMembers Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez, Bill Rundberg and Dennis Zheng
SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes of June 1, 2017 Meeting District Office Board Room Members Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez,
More informationEAST SIDE UNION HIGH SCHOOL DISTRICT ANNUAL FINANCIAL REPORT FOR THE YEAR ENDED JUNE 30, 2016
EAST SIDE UNION HIGH SCHOOL DISTRICT ANNUAL FINANCIAL REPORT FOR THE YEAR ENDED TABLE OF CONTENTS FINANCIAL SECTION Independent Auditor s Report 2 Management's Discussion and Analysis 5 Basic Financial
More informationEAST SIDE UNION HIGH SCHOOL DISTRICT 2002 MEASURE G BOND FUND ANNUAL FINANICAL REPORT JUNE 30, 2012
EAST SIDE UNION HIGH SCHOOL DISTRICT ANNUAL FINANICAL REPORT TABLE OF CONTENTS FINANCIAL SECTION Independent Auditor s Report 1 2002 Measure G Bond Fund Balance Sheet 2 Statement of Revenues, Expenditures,
More informationAllan Hancock Joint Community College District
One Stop Studen Allan Hancock Joint Community College District One Stop Student Services Public S Public Safety Com Public Safety Complex Childc Childcare Addit Childcare Addition BOND MEASURE I Progress
More informationStatus: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.
Page 1 of 14 FACILITIES PLAN STATUS REPORT August 24, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid
More informationSAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes June 7, 2018 District Office Board Room
Enclosure #01 SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes June 7, 2018 District Office Board Room Members Present: James Ruigomez, Chair; Gino Gasparini, Shelley Kessler,
More informationBudget Advisory Committee Meeting MARCUS BATTLE ASSOCIATE SUPERINTENDENT, BUSINESS AND OPERATIONS & KAREN POON, DIRECTOR OF FINANCE MAY 13, 2014
1 Budget Advisory Committee Meeting MARCUS BATTLE ASSOCIATE SUPERINTENDENT, BUSINESS AND OPERATIONS & KAREN POON, DIRECTOR OF FINANCE MAY 13, 2014 Presentation Summary Key Impacts of Governor s FY 2014-15
More informationGoverning Board Bond Update. Measure G Bond Program. for. Solano Community College District
Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects
More informationProposition O Citizens Bond Oversight Committee Wednesday September 10, 2014 AGENDA
Proposition O Citizens Bond Oversight Committee Wednesday September 10, 2014 AGENDA 1. Call to Order / Roll Call 2. Pledge of Allegiance Proposition O Citizens Bond Oversight Committee * Agenda * Wednesday
More informationLos Gatos Union School District Roberts Road Los Gatos, CA 95032
Los Gatos Union School District 17010 Roberts Road Los Gatos, CA 95032 (408) 335-2000 Phone (408) 395-6481 Fax www.lgusd.k12.ca.us Dr. Diana G. Abbati, Superintendent Citizens Building Oversight Committee
More informationAPPENDIX A FULL TEXT OF BOND MEASURE
APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass
More informationCapital Projects Completed since 1988
Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990
More informationBallot Measures-T Section
T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and
More informationBERKELEY UNIFIED SCHOOL DISTRICT
BERKELEY UNIFIED SCHOOL DISTRICT TO: Javetta Cleveland and Neil Smith, Co-Superintendents FROM: Lew Jones, Director of Facilities DATE: June 26, 2013 SUBJECT: Approval of the 2013/14 Measure H Annual Plan
More informationContents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure...
Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 6 Impartial Analysis... 7 Statement in Favor of Measure... 8 Ballot Measure EXHIBIT A HANFORD ELEMENTARY SCHOOLS REPAIR
More informationAction Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List
Action Item TO: PRESENTED BY: BOARD AGENDA ITEM: Board of Trustees and Superintendent of Schools Sid Albaugh, Assistant Superintendent Business Services Consideration of Approval of 2018 Measure A Facilities
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018
SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center & Demolition Science Center
More informationStatus: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.
Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationTumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent
Tumwater University School District Budget Myths Bond Project Update February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Construction Update $136,000,000 in bonds approved
More informationBallot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools
Section Ballot Measures-N N Centralia Elementary School District, Building Strong Neighborhood Schools To repair/modernize aging classrooms, science labs/school facilities to keep pace with technology,
More informationStatus: Structural steel installation underway at primary building. Observatory construction underway.
Page 1 of 11 FACILITIES PLAN STATUS REPORT March 30, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING MAY 15, 2018
FACILITIES COMMITTEE MEETING MAY 15, 2018 1 PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center Johnson Demolition Science Center & Building J
More informationAttachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017
A. Approval - New (Non-State and Other State Funds) Name (Other State) (Other State) Non-State Funds/ Undetermined 1 N/A B. Approval - Amended (Non-State and Other State Funds) 1 Coastal Carolina Main
More informationP R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y
Measure Q Update P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y 1 5 2 0 1 5 Agenda 1. P R E L I M I N A R Y R E S P O N S E T O
More informationOriginal Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000
Page 1 of 20 FACILITIES PLAN STATUS REPORT June 27, 2016 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning
More informationContents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...
Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... 10 Ballot Measure EXHIBIT B MEASURE Y (ABBREVIATED FORM)
More informationSEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE J BOND AUDIT REPORT. August 31, 2016 * * *
SEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE J BOND AUDIT REPORT August 31, 2016 * * * CHAVAN & ASSOCIATES, LLP CERTIFIED PUBLIC ACCOUNTANTS 1475 SARATOGA AVE., SUITE 180 SAN JOSE, CA 95129
More informationReserve Analysis Report
Reserve Analysis Report Parkway Towers 1155 Ash St Denver, CO 80220 Level I Study with Site Inspection Fiscal Year End Date: 12/31/2014 8597 Via Mallorca Suite E La Jolla, CA 92037 Phone: 858-764-1895
More informationOVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE
MEASURE C SCHOOL SAFETY AND MODERNIZATION On November 3, 2009 the voters residing in the Mill Valley School District (MVSD) approved the Measure C Safety and Modernization Bond of 2009 (Measure C). Measure
More informationDESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2010
(MEASURE B, MARCH 2004) (MEASURE B, MARCH 2004) TABLE OF CONTENTS Page Independent Auditors Report 1 Objectives... 2 Scope of the Audit.. 2 Background Information. 2-3 Procedures Performed... 3-4 Results
More informationMeasure G Quarterly Progress Update
Measure G Quarterly Progress Update February 3, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure
More information2017 Bond Program Summary
2017 Bond Program Summary Middle School #3 (off Vail Divide) $ 76,225,750 Middle School #3 Off-site Utility and Road Construction $ 2,100,000 Elementary School #7 (in Rough Hollow) $ 33,130,150 Bee Cave
More informationMeasure RR Bond Budget by Project. Measure RR BAN Measure RR BAN Interest Measure RR Series AB Measure RR Series AB Interest
6/30/15 15/16 Thru 6/30/15 15/16 Thru 6/30/15 15/16 Thru 6/30/15 15/16 A Library, Learning Resources and Campus Center 217,200 GSF; State Funding component; begin design est. 2015/16 771120 $ 197,529.21
More informationOriginal Revision Total Project Budget: $52,234,000 $8,308,000 $67,358,000 District Funding Commitment: Anticipated State Match:
Page 1 of 17 FACILITIES PLAN STATUS REPORT August 21, 2017 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master
More informationProgress Update Identified Needs & Capital Plan
Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary
More informationEducational & Performing Arts Center: Downriver Campus
Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed
More informationFacilities Planning & Construction Report nd Quarter Ending December 31, 2017
Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By
More informationSOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S
SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S Under this measure, the Somis Union School District ( District ) is submitting a bond measure, described below, to the voters
More informationMeasure G Quarterly Progress Update
Measure G Quarterly Progress Update May 4, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure G is
More informationSanta Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013
Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013 Measure V Bond Construction Fund Year Ended June 30, 2013 Table of Contents Page Independent Auditors'
More informationSanta Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015
Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015 Measure V Bond Construction Fund Year Ended June 30, 2015 Table of Contents Page Independent Auditors'
More informationCommunity College District. Measure M
Community College District Measure M Monthly Report October 2015 San Bernardino Community College District Program Management Measure M Monthly Report October 2015 1. Valley Campus Project Sheets 2. Crafton
More informationCH-UH Board of Education Meeting. June 27, 2017
CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle
More informationSTATE CAPITAL OUTLAY PLANNING
STATE CAPITAL OUTLAY PLANNING CCC Chancellor s Office Cheryl Larry Lan Yuan San Mateo CCD Jose Nunez Karen Pinkham CCFC 2016 AGENDA Overview Eligibility Priority Review/Approval Effective Practices 1 Key
More informationMUROC JOINT UNIFIED SCHOOL DISTRICT KERN COUNTY NORTH EDWARDS, CALIFORNIA
KERN COUNTY NORTH EDWARDS, CALIFORNIA FINANCIAL AND PERFORMANCE AUDIT JUNE 30, 2018 TABLE OF CONTENTS JUNE 30, 2018 PAGE INTRODUCTORY SECTION TABLE OF CONTENTS i FINANCIAL SECTION INDEPENDENT AUDITOR'S
More informationLocal ballot measure: B. Redding School District Bond Measure
B Redding School District Bond Measure Ballot question To improve the quality of education; repair/replace leaky roofs; modernize and construct classrooms, restrooms and school facilities; and make health,
More informationPage Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182
Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Operational Services/Central Services/Axtell Park School
More informationConstruction Total. Subtotal: $ 863,540 $ 172,708 $ 124,350 $ 1,160,598 $ 232,120 $ 1,392,717
Page 1 of 14 Hamilton School K-8 Phase District Basic Upgrades to Schools / Code Requirements Quantity Unit /Unit Soft s at 1 ADA path of travel walkways 1 LS $ 100,000 $ 100,000 $ 20,000 $ 14,400 $ 134,400
More informationBond Update Presentation Azusa Unified School District
Bond Update Presentation by Isom Advisors, a Division of Urban Futures, Inc. June 9, 2014 1470 Maria Lane, Ste. 315 - Walnut Creek, CA 94596 Community Voter Survey (November 2013) Ballot Measure (pre-information)
More informationCMP Strategy Project Listing by Cluster (Includes Technology and SIPs. Does not include SB9-08 M&O projects)
2006-20 CMP Strategy Listing by Cluster (Includes Technology and SIPs. Does not include SB9-08 M&O projects) Architectural Research Consultants, Incorporated October, 2004 Cluster: Albuquerque 244 DOLORES
More informationPerformance Audit on 2008 and 2013 SPLOST Revenues For the Fiscal Year ended June 30, 2012
Thomas County School System Performance Audit on 2008 and 2013 SPLOST Revenues 300 Mulberry Street, Suite 300 P.O. Box 1877 Macon, Georgia 31202-1877 Phone: (800) 277-0050 Facsimile: (478) 464-8051 Web:
More informationThe SMC Associated Students recommended, student representative, Zavanna Negron, to serve on the Committee for the term of
July 20, 2016 Santa Monica Community College District Citizens Bond Oversight Committee MEETING JULY 20, 2016 AGENDA A meeting of the Santa Monica Community College District Citizens Bond Oversight Committee
More informationFACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING
Page 1 of 11 FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:
More informationFacilities Development and Operations
Facilities Development and Operations Dashboard/Metrics Report California State University, East Bay July 1, 2016 to June 30, 2017 1 Who We Are: Vice President Administration & Finance Division Associate
More information2018 Educational and Facilities Master Plan (EFMP) and Proposed Bond Projects. June 27, 2018 // Board of Trustees Meeting
2018 Educational and Facilities Master Plan (EFMP) and Proposed Bond Projects June 27, 2018 // Board of Trustees Meeting Proposed Bond Projects Overall Phasing Phase 1A Phase 1B Phase 2 Phase 3 Phase TBD
More informationBacklog Reduction Plan
2003-2013 Executive Summary proposes to achieve reductions in our facilities maintenance backlog by documenting and completing backlog projects on a priority basis and by minimizing or eliminating future
More informationHARBOR POINTE CONDOMINIUM ASSOCIATION INC CONDOMINIUM APPROVED BUDGET YEAR ENDING DECEMBER 31, 2017
210 Monthly Condominium Assessment $ 477.00 Condominium Income Assessment Income Condominium 1,202,040.00 Assessment Income: $ 1,202,040.00 Condominium Expenses General / Administrative Management Fee
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More informationTHE VINEYARDS AT DUBLIN GREENE OWNERS ASSOCIATION
THE VINEYARDS AT DUBLIN GREENE OWNERS ASSOCIATION Full Reserve Study With On-site Visual Inspection October 3, 2018 Reserve Study for Fiscal Year: 01/01/2019 through 12/31/2019 2059 Camden Ave. Suite 151
More informationSONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA
SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA YEAR ENDED TABLE OF CONTENTS PAGE Independent Auditors' Report 1 Objectives 2 Scope of
More informationBERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee
BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee AGENDA November 17, 2011 6:00 7:30 PM 1720 Oregon Street Berkeley, CA 94703 (510) 644-6066 1. Call to Order 2. Approval of Meeting
More informationInformation. June 06, 2017 The Board awarded a contract to gkkworks/belli Architects.
Measure T Update Prepared by: Joseph Reyes, Executive Director Facilities Planning & Construction Management Presented to the Board: October 02, 2018 1. Measure T Implementation Plan Information June 06,
More informationFY 2018 Stockton University Operational & Capital Report as of May 31, 2018
FY 2018 Stockton University Operational & Capital Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 Internal Capital Projects 4-5 Other Capital Projects 6 State
More information2010 MEASURE G GENERAL OBLIGATION BONDS PERFORMANCE AUDIT
2010 MEASURE G GENERAL OBLIGATION BONDS PERFORMANCE AUDIT FOR THE FISCAL YEAR ENDED JUNE 30, 2018 2010 Measure G GENERAL OBLIGATION BONDS Table of Contents June 30, 2018 Independent Auditors Report...
More informationLos Angeles Unified School District Page 1 of 3
Los Angeles Unified School District 333 South Beaudry Ave, Los Angeles, CA 90017 Board of Education Report File #: Rep-201-16/17, Version: 1 Amendment to the Facilities Services Division Strategic Execution
More informationFY 2017 Stockton University Expenditure Report as of May 31, 2017
FY 2017 Stockton University Expenditure Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 FY17 Internal Capital Projects 4 State Bond/Grants 5 STOCKTON UNIVERSITY
More informationWhy did we undertake a comprehensive Educational Facility Master Plan?
NUSD EDUCATIONAL FACILITY MASTER PLAN Why did we undertake a comprehensive Educational Facility Master Plan? Novato Unified School District (NUSD) has thirteen school sites that provide the educational
More informationAbilene Independent School District Bond Oversight Committee. Meeting Agenda
Abilene Independent School District Bond Oversight Committee Meeting Agenda May 12, 2014 12:00 noon Type of Meeting: Meeting of 2013 Bond Oversight Committee Meeting Facilitator: Cary Etter Invitees: Oversight
More informationMT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE R, NOVEMBER 2001) PERFORMANCE AUDIT.
(MEASURE R, NOVEMBER 2001) (MEASURE R, NOVEMBER 2001) CONTENTS Page Independent Auditor s Report... 1 Objectives... 2 Scope of the Audit... 2 Background Information... 3 Procedures Performed... 3 Results
More informationGAVILAN JOINT COMMUNITY COLLEGE DISTRICT Gilroy, California. MEASURE E GENERAL OBLIGATION BOND PERFORMANCE AUDIT June 30, 2013
Gilroy, California PERFORMANCE AUDIT June 30, 2013 PERFORMANCE AUDIT June 30, 2013 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE HISTORY... 2 GAVILAN JOINT COMMUNITY COLLEGE DISTRICT
More informationGRF Mutual Project Log (10/31/17)
904 Maint Svc 904 Maint Svc 904 Maint Svc 904 Maint Svc GRF Mutual Project Log (10/31/17) Priority # Type Name Description Status 1 CH 5 Commercial Appliances Replace Clubhouse 5 Dishwasher and Booster
More informationPhysical Plant. Detailed Assessment Report
Physical Plant Detailed Assessment Report 2011-2012 Mission / Purpose The Physical Plant Department enhances the University of West Alabama's mission to provide opportunities for students to pursue a quality
More informationLOS ANGELES UNIFIED SCHOOL DISTRICT Board of Education Report
LOS ANGELES UNIFIED SCHOOL DISTRICT Board of Education Report Report Number: 246-15/16 Date: Subject: Amendment to the Facilities Services Division Strategic Execution Plan to Approve Project Definitions
More informationUse of State and District Construction Funds
8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,
More informationSchool Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year February 20, 2018
School Board of Brevard County, Florida Half-Cent Sales Surtax Round 5 Internal Audit Report Fiscal Year 2017-18 February 20, 2018 TABLE OF CONTENTS Transmittal Letter... 1 Executive Summary... 2 Overview...
More informationChabot College Project List Biology Building Phase 1 $0 $0 $0 Measure B $0 $0 $0 Measure A 2016 $0 $0 $0
Chabot College Project List 552330 Biology Building Phase 1 $0 $0 $0 Measure A 2016 $0 $0 $0 562100 Library & Learning Conncetions Building Replacement 100 $57,875,000 $0 $0 Measure A 2016 $57,875,000
More informationJACKSON-MADISON COUNTY SCHOOL SYSTEM FUND #177 EDUCATION CAPITAL 5-YEAR PLAN (WORKING COPY)
Elementary & K-8 Campuses Alexander 6 8 Guttering replacement 2 $ 20,000 HVAC replacement 1 $ 800,000 Remove and replace old glass block windows 3 Total for Alexander $ - $ 20,000 $ 800,000 $ - $ - $ -
More informationCAJON PARK 18-CLASSROOM ADDITION 10-CLASSROOM ADDITION SANTEE SCHOOL DISTRICT FACILITIES COMMITTEE ANNUAL REPORT
CAJON PARK 18-CLASSROOM ADDITION 10-CLASSROOM ADDITION SANTEE SCHOOL DISTRICT FACILITIES COMMITTEE ANNUAL REPORT 2007 to 2009 The Facilities Committee is a Board Advisory Committee currently chaired by
More informationPOJOAQUE VALLEY SCHOOL DISTRICT October 12, 2016
POJOAQUE VALLEY SCHOOL DISTRICT October 2, 206 Results from data gathered from community meeting held September 20, 206 regarding use of current bond funds and goals setting for possible 207 bond On Tuesday,
More informationCITY OF GLENDALE, CALIFORNIA REPORT TO THE: Housing Authority D Successor Agency D Oversight Board D
Joint D City Council ISi CITY OF GLENDALE, CALIFORNIA REPORT TO THE: Housing Authority D Successor Agency D Oversight Board D :~ February 3, 2015 AGENDA ITEM Report: Stengel Ball Field Clubhouse & Bleacher
More informationSEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE A BOND AUDIT REPORT. For the Year Ended June 30, 2015 * * *
AUDIT REPORT * * * CHAVAN & ASSOCIATES, LLP CERTIFIED PUBLIC ACCOUNTANTS 1475 SARATOGA AVE., SUITE 180 SAN JOSE, CA 95129 Table of Contents Page No. FINANCIAL SECTION: Independent Auditor s Report... 1-2
More informationMeasure Q Quarterly Bond. Progress Update. December 1, (original issue 11/10/14)
Measure Q Quarterly Bond Progress Update December 1, 2014 (original issue 11/10/14) TABLE OF CONTENTS 1. GENERAL INFORMATION A. Executive Summary... 2 B. Project Team... 3 2. PROGRAM SUMMARY A. Current
More informationTwo Ballot Proposals. August 8, 2017
Two Ballot Proposals August 8, 2017 Per-Pupil Foundation Allowance Ten-Year History for Schools* Per-Pupil Foundation Allowance Ten-Year History for Schools* FYs 2007-08 through 2016-17 FY2008 FY2009 FY2010
More informationGeorgia Institute of Technology Advanced Computing Technology Building. Draft Program. Mission Model Initial Program Development
Georgia Institute of Technology Advanced Computing Technology Building Draft Program Initial Program Development Issued April 2, 2001 Introduction Scope This document is a summary of the Session for the
More informationCHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT Dublin, California. MEASURE B GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016
CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT MEASURE B GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2016 PERFORMANCE AUDIT June 30, 2016 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE
More information2017 Budget & Capital Improvement Plan AUGUST 29, 2017
2017 Budget & Capital Improvement Plan AUGUST 29, 2017 FY 2017 Budget Calendar May June July August September October November December Financial Forecast & Public Safety Staffing Priorities, Programs,
More informationPERRIS ELEMENTARY SCHOOL DISTRICT
PERRIS ELEMENTARY SCHOOL DISTRICT 2006 & 2014 General Obligation Bond Authorizations Measures S & C Citizens' Oversight Committee Report March 1, 2018 2006 GENERAL OBLIGATION BOND ELECTION 2006 Measure
More informationPhysical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15
Physical Plant Five-Year Capital Budget Plan State College Area School District November 2011 Page 1 of 15 Table of Contents Background and 2013 Projects Pages 3-5 Funding Level Pages 6-7 Existing Buildings
More informationReserve Fund Study My Condominium Plan
Reserve Fund Study My Condominium Plan 12 3456 Number of Units 36 Number of Buildings 1 Building Construction 21 Contact Ima Happy Position(s) President Contact Phone 43.555.4321 Report Date August 8,
More informationDepartment Report. Cultural Affairs Commission June 15, Cliff Gillespie, Business Operations Manager Office of Cultural Affairs City of Dallas
Department Report Cultural Affairs Commission June 15, 2017 Cliff Gillespie, Business Operations Manager Office of Cultural Affairs City of Dallas Agenda FY 2017-18 Budget Update 2017 Bond Program Moody
More informationSEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE A BOND AUDIT REPORT. For the Year Ended June 30, 2016 * * *
SEQUOIA UNION HIGH SCHOOL DISTRICT PROPOSITION 39/MEASURE A BOND AUDIT REPORT For the Year Ended June 30, 2016 * * * CHAVAN & ASSOCIATES, LLP CERTIFIED PUBLIC ACCOUNTANTS 1475 SARATOGA AVE., SUITE 180
More informationMeasure Q Quarterly Bond. Progress Update
Measure Q Quarterly Bond Progress Update February 9, 2015 TABLE OF CONTENTS 1. GENERAL INFORMATION A. Executive Summary... 2 B. Project Team... 3 2. PROGRAM SUMMARY A. Current Activities... 5 B. Next
More informationOriginal Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A
Page 1 of 14 FACILITIES PLAN STATUS REPORT May 21, 2018 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master Planning
More information2009 Annual Report to the Board of Trustees. Bond Measure V Citizens Oversight Committee
2009 Annual Report to the Board of Trustees Bond Measure V Citizens Oversight Committee Table of Contents Letter From The Chair 3 Executive Summary 4 Bond Measure V Overview 5 The Role Of The Citizens
More informationArt Building Addition & Renovation 04 Issue. $1,500,000 Bond Financing $2,000,000 Gift Funding $3,500,000 Total Improvements
Bond Project Recap Art Building Addition & Renovation 04 Issue $1,500,000 Bond Financing $2,000,000 Gift Funding $3,500,000 Total Improvements Eaton Hall 4 th Floor Renovation 04 Issue $1,900,000 Bond
More informationPlanning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619)
Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA 91911 (619) 691-5553 FAX (619) 420-0339 Prop O Project Summary page 1 General for CBOC Meeting of June 22, 2016 1 1 2 This report
More informationPlanning and Construction Department 1130 Fifth Avenue, Chula Vista, CA (619) FAX (619)
Planning and Construction Department 1130 Fifth Avenue, Chula Vista, CA 91911 (619) 691-5553 FAX (619) 420-0339 Prop O Project Summary page 1 General for CBOC Meeting of April 25, 2016 1 1 2 This report
More informationFacilities Management and Planning Organizational Review Phase II Update
MEMORANDUM Office of College Services DATE: September 3, 2013 TO: CC: FROM: SUBJECT: President Mary Spilde, Vice President Brian Kelly Facilities Management & Planning Organizational Review Team Jennifer
More information