next level PMP Exam Preparation Formula Guide for the PMP Exam
|
|
- George Potter
- 5 years ago
- Views:
Transcription
1 next Formula Guide for the PMP Exam January 2017
2 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to Know Expected Monetary Value (EMV) Point of Total Assumption (PTA) Communication Channels 6. Facts & Figures to Know 7. Tips for Using Formulas on the Exam 1 Earned Value Formulas CV (Cost Variance) EV - AC SV (Schedule Variance) EV - PV CPI (Cost Performance Index) EV / AC SPI (Schedule Performance Index) EV / PV < 1 below budget or schedule = 1 on budget or schedule > 1 exceeds budget or schedule
3 Page 2 1 Earned Value Formulas When project perfomance is expected to continue without deviation. When original estimate proves to be incorrect. The New ETC in this fomula is a bottom-up re-estimation of the work needing to be completed. When performance needs to be taken into account for remaining budget. BAC CPI AC + New ETC BAC - EV CPI x SPI When a one-time variance occurs. AC + (BAC - EV) ETC (Estimate to Completion) EAC - AC VAC (Variance at Completion) TCPI (To Complete Performance Index) (when you are under budget, using BAC) TCPI (To Complete Performance Index) (when you are over budget, using EAC) BAC - EAC (BAC - EV) (BAC - AC) (BAC - EV) (EAC - AC) < 1 below budget = 1 on budget > 1 exceeds budget < 1 below budget = 1 on budget > 1 exceeds budget < 1 below budget = 1 on budget > 1 exceeds budget EV (Earned Value) Percent complete x BAC
4 Page 3 2 (Program Evaluation & Review Technique) Formulas Weighted/beta distribution Signular/triangular distribution Standard deviation Variance P + 4M + O 6 P + M + O 3 P - O 6 (P - O) Float Formulas Total Float Note: This value will equal zero when an activity is on the critical path. Early Start (ES) = Earliest an activity can start given the constraints of the schedule. Early Finish (EF) = Earliest an activity can finish given the constraints of the schedule. Late Start (LS) - Early Start (ES) OR Late Finish (LF) - Early Finish (EF) Late Start (LS) = Latest an activity can start without effecting the early finish of the project. Late Finish (LF) = The latest an activity can finish without effecting the late finish of the project.
5 Page 4 4 Project Selection Formulas PV (Present Value) FV (Future Value) FV (1 + r) n PV (1 + r) n FV = future value r = interest rate n = number of time periods PV = present value r = interest rate n = number of time periods NPV (Net Present Value) Present value assets - Present value of costs IRR (Internal Rate of Return) Interest rate at which the net present value of all the cash flows (positive & negative) from a project equal zero Benfit Cost Ratio (BCR) Cost Benefit Ratio (CBR) Working Capital ROS (Return on Sales) Benfit / Cost Cost / Benefit Current assets - current liability Net income before tax Revenue
6 Page 5 5 Additional Formulas to Know EMV (Expected Monetary Value) Probability x Impact PTA (Point of Total Assumption) Ceiling Price (CP) - Targe Price (TP) Buyer s Share Ratio Target + Cost (TC) Communication Channels (N 2 - N) N = number of people 2 6 Facts & Figures to Know Estimates Rough Order of Magnitude (ROM) -25% to +75% Budget Estimate -10% to +25% Definitive Estimate -5% to +10% Standard Deviations 1 Sigma 68.27% 2 Sigma 95.45% 3 Sigma 99.73% 6 Sigma 99.99%
7 Page 6 7 Tips for Using Formulas on the Exam In addition to these s you may also need to perform basic calculations such as finding values for the mean (average), median (middle of a set of numbers) and mode (the most frequest of a set of numbers). Doing a brain-dump (writing out all s on a page) before the exam can help save time during the test. You ll be able to quickly refer to the set of s you need instead of racking your brain each time one is needed. Some question on the exam may require you to use multiple s or to solve for one value to plug into a different. As you read a question, it can help to write out the values that you are given in order to compare them with your brain-dump and identify which may be appropriate. Some exam question may also give extra information - watch out! Just because an exam question lists all of the values pertaining to a certain does not necessary mean that is the correct one to use. Beyond simply memorizing these s, refer to the PMBOK Guide for in-depth explanations to gain a greater understanding of how these s may be used on the exam. Be prepared for more than just the s. Visit for more tools to prepare for your PMP Exam. We make it easy to get the tools you need: PDF Study Guides Flashcards Books & more... Disclaimer PMI, PMP, and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not participated in the the creation of this document nor does it endorse its content. The use of this document or any of Next Level Project Management s materials does not guarantee that the user will pass the PMP certification exam and no statements, direct or indirect, are expressed as such. Next Level Project Management disclaims any liability in connection with the use of this information. Copyright 2017 Next Level Project Management
Formulas to Know for EXAM
Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for
More informationPMP Exam Prep Coaching Program
PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More informationSelf-Assessment Questions for Module 07 Project Cost Management
Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses
More informationPass PMP in 21 Days - ITTO Toolbox PROCESS MAP
PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project
More informationNEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4
NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process
More informationCAPM Exam Prep.
CAPM Exam Prep (What it really takes to prepare and pass) An ebook by Project Road Training, LLC www.project-road.com Bill Baxter Version 6-1 Project Road Training, LLC has been reviewed and approved as
More informationPROJECT MANAGEMENT BODY OF KNOWLEDGE
A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationTHE PMP EXAM PREP COURSE
THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45
More informationEarned Value Management - EVM
Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationFive-Day Schedule and Course Content
Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course
More information[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP
This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,
More informationAchieve PMP Exam Success Five-Day Course Syllabus
Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course
More informationCONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationPM tutor. Advanced Cost Theory. Presented by Dipo Tepede, PMP, SSBB, MBA. Empowering Excellence. Powered by POeT Solvers Limited
PM tutor Empowering Excellence Advanced Cost Theory Presented by Dipo Tepede, PMP, SSBB, MBA This presentation is copyright 2009 by POeT Solvers Limited. All rights reserved. This presentation is protected
More informationINTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz
INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions
More informationPerformance measurement
MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda
More informationProfessional Development Seminar Series
Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php
More informationSCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016
All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project
More informationEarned Value Management Guide
1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress
More informationCS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III
LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals
More informationPMP Exam Preparation Workshop Chapter 7 Project Cost Management
PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More informationEVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS
EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:
More informationFinal: Total 200 points (3-hour exam)
Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000
More informationLesson 7 The Project Budget
MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget
More informationJames A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)
Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com
More informationNOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:
NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM
More informationCumulative trends Problems and issues since last report
Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier
More informationCarlos Consulting Group
Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group
More informationANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?
ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1
More informationEarned Schedule schedule performance
Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should
More information4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring
More informationCost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP
Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that
More informationSAMPLE. AACE International Recommended Practice No. 80R-13
E 80R13 SA M PL ESTI MATEATCOMPLETI ON( EAC) AACE International Recommended Practice No. 80R-13 ESTIMATE AT COMPLETION (EAC) TCM Framework: 7.6 Risk Management 9.1 Project Cost Accounting 9.2 Progress
More informationUnderstanding the Differences. Accounting Practice for Measuring. Supertech Project Management
Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationeurope GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors
eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration
More informationPlanning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique
Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,
More informationCPM (College of Performance Management) Meetings have focused on this topic in the last year
June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches
More informationEarned Value Management
Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards
More informationProject Management -- Monitoring the progress
Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a
More informationLecture 3 Project Scheduling
B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?
More informationA Practical Way To Learn About EVM. ***The Deck Project***
A Practical Way To Learn About EVM ***The Deck Project*** Back to the Baseline 2 The Deck Project The product of this project is a new second-story deck in the backyard. This new deck will replace an existing
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationThomas Carlos Consulting. Simple Earned Value Management
Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,
More informationPROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana
PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING
ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationThe Four Pillars of project management
The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this
More informationEarned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC
Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context
More information9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.
Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control
More informationKey Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado
Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept
More informationBraindumps.PMI-SP.323 questions
Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for
More informationApplication of Earned Value Management (EVM) for Effective Project Control
Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge
More informationSolutions to Problems
Solutions to Problems 1. The investor would earn income of $2.25 and a capital gain of $52.50 $45 =$7.50. The total gain is $9.75 or 21.7%. $8.25 on a stock that paid $3.75 in income and sold for $67.50.
More informationEVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes
EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics
More informationFinancial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany
1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance
More informationConnecting Earned Value to the Schedule
Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned
More informationMMZG 523 PROJECT MANAGEMENT
MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable
More informationIRNOP 2017 Fuzzy Earned Value Management model for uncertain and complex projects. Leila M. Naeni Amir Salehipour
207 Fuzzy Earned Value Management model for uncertain and complex projects Leila M. Naeni Amir Salehipour Authors Leila M. Naeni Project Management lecturer at University of Technology Sydney. Research
More informationCritical Path and Earned Value Management
Critical Path and Earned Value Management Two elegantly simple metrics, both rich with meaning, have been part of project management since the very beginning of the profession: 1. Critical Path Method
More informationTechniques to Assist Delivery of Projects
Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction
More informationHomework 6 Questions and Answers
I.E. 406 PROJECT SCHEDULING AND CONTROL Fall 2012 Murat Sandikcioglu (original by Dr.Onur ÇOKGÖR) Homework 6 Questions and Answers CRITICAL CHAIN PROJECT MANAGEMENT (CCPM) & EARNED VALUE ANALYSIS (EVA)
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationAdministration. Course Aim. Introductions
Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may
More informationEarned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;
Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,
More informationValue And Earned Schedule Management
EVM World 2013 Conference IPMC 2013 Title: An Analytical Utility For Earned Value And Earned Schedule Management Gary L. Richardson and Saranya Lakshmikanthan May 29, 2013 The popular technical literature
More informationPresenting Earned Value
Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance
More informationMeasuring Time An earned value simulation study
Measuring Time An earned value simulation study Mario Vanhoucke Presentation for the Annual Earned Value Conference for the UK London - June 1-11, 28 An EVM introduction The EV terminology A case study
More informationPredicting Project Completion Date Using Earned Value Management
Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231
More informationCHAPTER 10 PROJECT CONTROL
CHAPTER 0 PROJECT CONTROL The limited objective of project control deserves emphasis. Project control procedures are primarily intended to identify deviations from the project plan rather than to suggest
More informationMonitoring System For Project Cost Control In Construction Industry
Monitoring System For Project Cost Control In Construction Industry Pramod M *, K. Phaniraj **, V. Srinivasan *** * Post graduate student: Construction Engineering and Management, Manipal Institute of
More informationPASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year
PASS4TEST IT Certification Guaranteed, The Easy Way! \ We offer free update service for one year Exam : PMI-SP Title : PMI Scheduling Professional Vendors : PMI Version : DEMO Get Latest & Valid PMI-SP
More informationObjectives of Project Cost Control System
Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final
More informationInternational Cost Estimating and Analysis Association Testable Topics List CCEA
International Cost Estimating and Association Testable Topics List CCEA Testable Topics List The Testable Topics List Cost Estimating Basics COST ESTIMATING BASICS Budgeting, Investment, and Planning of
More informationINSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.
INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E
More informationENGINEERING MANAGEMENT (GE
بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control
More informationDetailed Project Scheduling and Cost Management
Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute
More informationA Case for Project Revenue Management. Peter Varani PMP
A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach
More informationQUALITY CONTROL PROCESS
1.0 SCOPE The Enterprise Project Management Office (EPMO) established overarching Quality Policy, Quality Objectives in the 0100-0100-005-QMS EPMO QUALITY MANUAL. This procedure defines specific EPMO Information
More informationTRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA
TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L 1, Anne Ligoria S 2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor
More informationProject Management Webinar
Project Management Webinar Earned Value Basics Initiate Project Intelligence Things to Know All participants will be on mute Questions are welcome Use the question box to ask questions PM training is valid
More informationEVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities
EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP
More informationEarned Value Management. Danielle Kellogg. Hodges University
Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level
More informationA convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.
Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects
More informationThe Value of EVM. Earned Value Management
The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in
More informationA Layman s Guide to Earned Value
A Layman s Guide to Earned Value A TenStep White Paper Contact us at info@tenstep.com TenStep, Inc. 2363 St. Davids Square Kennesaw, GA. 30152 877.536.8434 770.795.9097 If you are a project manager, you
More informationPROJECT BY PROJECT MANAGEMENT T OOLS
Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationPMP (2018) PMBOK 6th Edition PMI. Project Management Professional (PMBOK 6th Edition)
PMI PMP (2018) PMBOK 6th Edition Project Management Professional (PMBOK 6th Edition) Download Full Version : https://killexams.com/pass4sure/exam-detail/pmi-001 QUESTION 903 Which process documents the
More informationETSF01: Software Engineering Process Economy and Quality
ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower
More information6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM
/7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business
More informationGate Value Method Overview document
Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person
More information