ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

Size: px
Start display at page:

Download "ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?"

Transcription

1 ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep

2 I Introduction and Contents Housekeeping Contents Definitions EAC s: Doing the Math EAC: Latest Revised Estimate and Beyond Change Management and Control Status Updates The Reality Check Independent EAC s Summation 2

3 II Definitions Things Indices People 3

4 III EAC s: Doing the Math Problem One: The Budget for your project is $3,680,549. Your cumulative Actual Cost is $2,261,004. You have been reporting the Estimate at Completion as $3,680,549, right on target. What is your Estimate to Complete? List anything else you might need to know before answering the question: 4

5 PM Tool Format Actuals Estimate to Complete: What is it? Why mind it? EAC? My budget is what it is. Direct Cost vs. Total Burdened Cost vs. Total Cost Hey, what about fee? 5

6 Earned Value Tool Format If management is the object then direct cost is most effective; Indirect Costs can be summarized and shown as a one line entry or by elements of cost. 6

7 Tripwire Metrics Tripwire because crossing thresholds automatically requires investigation, analysis, and corrective actions to bring the project back under control. Schedule Performance Index (SPI). Cost Performance Index (CPI) Critical Path Length Index (CLPI) Baseline Efficiency Index (BEI) 7

8 Schedule Performance Index- SPI Measures schedule efficiency by comparing work performed (EV) to the planned values (PV) in the PMB. In other words, what is the ratio between the work I did and the value of the work I planned to do? Earned Value SPI = Planned Value BCWP SPI = BCWS 8

9 Cost Performance Index-CPI Measures cost efficiency by comparing work performed (EV) to actual cost (AC). In other words, what is the ratio between what I did and what it cost to do it? Earned Value CPI = Actual Cost BCWP CPI = ACWP 9

10 Critical Path Length Index- CPLI Measures the decrease, or increase, in total float on the critical path over time. In other words, how much schedule cushion am I gaining or losing? CPLI from time now plus Total Float to BL contract finish. Critical Path Length+ Total Float CPLI = Critical Path Length 10

11 Baseline Efficiency Index- BEI Measures efficiency at finishing activities by comparing BL Planned Finishes to Actual Finishes. In other words, what is the ratio between the number of activities I had planned to have completed by now and the number of activities that I ve actually completed? BL Planned Finishes BEI = Actual Finishes 11

12 Tripwire Problems Problem Two, Tripwire Metrics and VAC: Calculate the following using the formulae and data shown. Schedule Variance, Cost Variance, Variance at Completion, Baseline Efficiency Index. Calculate the variances and indices. 12

13 Problem 2 -Tripwire Problem Answers: Item Data / Formulae Answer Variance At Completion VAC = EAC -BAC $215,723 Schedule Variance (SV) SV = EV - PV ($231,053) Schedule Performance Index (SPI) SPI = EV / PV 0.88 Cost Variance (CV) CV = EV -AC $554,038 Cost Performance Index (CPI) CPI = EV / AC 1.50 Baseline Efficiency Index (BEI) Actual Finishes BEI = BL Project Finishes

14 Tripwire Measurements Tripwires and Statistical Process Control Think of tripwires as Upper Control Limits Lower Control Limits Provide the visibility to see the project going out of control Before it does. Corrective action, if effective, brings the project back under control. 14

15 Questions: Actual Costs Actual Costs, AC, ACWP What do you depend upon? Where do you get actual values for labor, material, ODC? Are Labor Hours Costs? Where are the official costs? Timecards Paid Invoices Estimated Actuals The Book of Record, the General Ledger 15

16 III: Estimate At Completion What is the difference between an EAC and a Budget? What is the EAC or ETC? Is it what I m told? Technically it is the sum of cumulative actual costs from inception to date plus the estimated cost of the unfinished work before the project is done. EAC = Actual Cost + Estimate to Complete The EAC is compared to the BAC, the difference is the Variance at Completion (VAC) Is it different than a Latest Revised Estimate (LRE)? 16

17 Estimate to Complete How was it derived? A few quick tests: Can the remaining labor hours be divided by 4? Is the EAC slightly under BAC, and do other statistical data support that? Was a more devious method used to make the ETC be what someone wantsit to be? Do I believe what I was told by the responsible managers? Do the attitudes of most assigned resource indicate that things are going consistently with what the responsible manager s numbers show? 17

18 What the Numbers Tell Us Actual Cost + Estimate to Complete (Remaining hours and costs) = EAC Budget at Completion Estimate at Completion = Variance at Completion Independent EAC = Budget at Completion / Cost Performance Index 18

19 Problem 3: Calculate an IEAC and the delta to the EAC Item Formula and Data Values IEAC = BAC / CPI Estimate at Completion (EAC) $3,464,826 Budget at Completion $3,680,549 Cost Performance Index 1.50 Delta of EAC minus Independent = IEAC -EAC EAC EAC (LRE)=$3,680,549 IEAC = $2,6,453,900 Delta = $1,011,127 (41%) A significant difference. Do we believe it? 19

20 What the Numbers Tell Us What the numbers tell me? AC + ETC (Remaining hours and costs) = EAC BAC EAC = VAC This predicts what the project will cost when finished. Only as good as the inputs (actuals and ETC) Independent EAC s BAC/CPI = Straight based upon distributed budget and cumulative cost performance Others. Bases for testing the credibility of the EAC. Is our previous EAC or IEAC credible? 20

21 Best to Be Objective Work Package 21

22 The Importance of Being (Earnestly) Discrete In establishing a controlled baseline (Performance Measurement Baseline) Know what Done is. Product-based Work Breakdown Structure Technical activities have to produce something. Logical network Resource Assignments Who will perform the work? Special skills? Or any old somebody? 22

23 Eschew Surplusage Mark Twain A rule of the literary art. Be specific Require specificity Indefinite modifiers: some, many, all, most, etc. As in Say what you intend to say, not merely something near it. Mark Twain 23

24 Product-based WBS & Network WBS: Fastener Assembly Nut Make Nuts Bolt Assembly Make Bolts Assemble Product Logical Network 24

25 Estimating Base estimates on the average person. Allow for some degree of risk where it exists. Weighted Average: Best case cost x probability Worst case cost x probability Likely case cost x probability 25

26 Problem 4: Estimating Risk Problem Four: Calculate a weighted average, riskbased estimate for an activity or WBS Item Case Estimate Probability Worst Case $10,000 25% Likely Case $7,000 40% Best Case $3,000 35% Risk-based Estimate Sum of Answers: Answers: Case Estimate x Probability Answer: $ 6,350 Can be applied to: Labor hours, labor costs, material costs, and Durations. 26

27 Granularity: EVM System Criteria Objective, not subjective completion criteria. Plan & complete technical activities in 1 status period, 2 periods if weekly status. Work Packages: 1-2 month duration. Non-technical activities keep separate from technical work. 27

28 Granularity: Control Accounts Four Elements must be present for analysis and control Actual Labor Hours and Costs (AC) Remaining Cost, and Hours (ETC) Budgeted Hours and Costs in the Performance Measurement Baseline (BCWS, PV) Performance, (BCWP, EV) 28

29 Granularity: Rolling Wave What will you be doing one year from today? Work Packages: Near term work 1-6 months, or whatever work can be reasonably planned. Planning Packages: Farther term work. We know we ll need to do something, but not specifically how we will do it. Typically greater than 3 months in the future. MR Float 29

30 V Change Management and Control Definitions: Scopemeans The sum of the products, services, and results to be provided as a project. Performance Measurement Baselinemeans An approved integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance The PMB is the controlledbaseline against which project performance is measured. Controlled means only authorized and approved efforts are included. 30

31 Control Scope Tightly Have a documented process for adding work to the baseline and to the current (EAC) plan. Do not accept changes without evaluating the cost and schedule impact before acceptance. Do not start until the work is authorized by the proper customer/stakeholders. Scope can be entered into the PMB or the current plan, or both. Oops, got ya sare not baseline changes. 31

32 Change Control Process Two phase process, whether formal or informal: 1 st Phase Change Description Develop a detailed description of the change so all parties can agree on it. If allowed, estimate the effort and cost to investigate. Submit for approval of the investigation effort. 2 nd Phase Change Approval Submittal and approval or rejection of the change proposal. Agreement on the content, cost, and schedule impact resulting from implementation of the proposed change. Approved changes must be entered into the PMB. 32

33 What Needs to Be Known In Advance Was WBS Approved, Authorized Scope (SOW) Cost, Schedule, Resource Requirements Present Budget, Schedule, EAC, Deliverables, Specifications, Requirements, Risks Will Be, If Approved WBS Revised Scope (SOW), specific change Revised Cost, Schedule, Resource Requirements Revised Budget, Schedule, EAC, Deliverables, Specifications, Requirements, Risks Amount of Change 33

34 VI Status Updates 34

35 Technical Activities Objective Performance: Done or Not Done In progress activity ETC s for all resources. What material is purchased and remains unpaid? What material must still be purchased? Regular bottom up EAC s Scope rationalization Resource usage using the principles of resourcedriven scheduling. Subjective Performance 35

36 Level of Effort Overhead Activities In progress activity ETC s for all resources. (How many hours before done?) If true LOE, verify burn rate (actual hours, material, or expense costs per period) and verify that ETC s usage forecast is set accordingly, Ifthere are no known increases or decreases in the future. 36

37 Subjective Performance Anecdote Do whatever you want: You re making it up anyway. Don t blame the tool or others. Percent Complete is not Objective... 37

38 Simple Status Rules Data must be reliable and unconcerned with anything other than representing: Actual starts and finishes of activities, Completion of steps within activities, Remaining efforts, and Resource utilization (usage). Objectivemethods determine the amount of work performed. Remaining Hours and Costs must represent only the amount of effort required to complete the activity in progress. 10 PM Status, Tracking, and Analysis.ppt 01 June

39 VII The Reality Checks Resource Loading This won t happen Because that s a problem 39

40 Reality Checks Actuals are actual: They should not include estimated actuals; Checks written, timesheets approved and logged. ETC: If the CAM, PM, or Resource Manager is telling you that the activity, Control Account, WBS, or Project will be done in two months. How many hours are in the ETC for his work? If Bob, or anyone else, is essential and requires 80 hours a week to finish the work, is it reasonable to believe that it will happen? What are the choices? 40

41 ETC Balance Just as the PMB, the ETC should demonstrate balance of: 41

42 VIII Independent EAC s Testing the EAC using EV Methods Cumulative CPI Method (Problem Three) Cost/Schedule Method Cost/Schedule Weighted Factor Method Three Month Average Method 42

43 Cumulative CPI Method IEAC =(BAC/CPI) Budget at Completion divided by Cost Performance Index What s critical here? Budget at Completion Work Performed (EV) Actual Cost 43

44 Cost/Schedule Method IEAC =AC+ Budgeted Cost of Work Remaining (BCWR) Unearned Value Budget at Completion minus Earned Value then divided by Cost Performance Index multiplied by SPI What s critical here? The Budget at Completion, Budgeted Cost of Work Performed (EV) Tries to consider schedule performance as a driver of at completion cost. Again the focus is cumulative performance. 44

45 Cost/Schedule Weighted Factor Method IEAC =.. What s critical here? Budget at Completion, Budgeted Cost of Work Performed (EV) Tries to consider schedule performance as a driver of at completion cost. Weights each Index by respective contribution to overall cost history. Factors should be based on observed performance. 45

46 Three Month Average Method = + What s critical here? This IEAC method can verify a change to the rate at which value has been earned. Two periods do not a trend make; three periods may Budgeted Cost of Work Performed (EV) View this method as another in the series of EAC tests. 46

47 To Complete Performance Index (TCPI) = Tests reasonableness of the ETC by comparing to CPIcum. EAC is considered to be reasonable if the CPIcumand TCPI are within.05 of each other. 47

48 PV, EV, AC Project Periods 48

49 SPI CPI Three Periods 49

50 EAC Methods Compared 50

51 Earned Value Trend Chart 51

52 Summation Managing Cost Managing project cost means: Manage scope. Good indicators of scope issues include SPI-SV CPI-CV Start and Finish Efficiencies (Baseline Efficiency Index) 52

53 Summation Managing Cost Means Managing scope. Managing work completion (schedule). Leading resources, not managing them. Thinking things through, beginning to end. Recovery Plan, what it really means How long do we want to hide truth? 53

54 Summation Managing Cost Means In the end, the project will cost what it costs. You can make good decisions about Make/Buy Resource skills and rates Scope, what to do or not do You can manage only scope, schedule, resources, and EXPECTATIONS, While you try not to do anything stupid. 54

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

Performance Analyzer Formulas. Assumptions. Current Month Adjustments

Performance Analyzer Formulas. Assumptions. Current Month Adjustments User's Guide for PA for Windows Error! No text of specified style in document. 1 Performance Analyzer Formulas Assumptions Current Month Adjustments Current Period values (BCWS, BCWP, ACWP) are derived

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Predicting The Future

Predicting The Future Predicting The Future Peter Hayward BAE Systems Insyte 1 Predicting The Future Steve said to me that perhaps I could maybe touch on one or two main issues with forecasting the Estimate To Complete 2 Predicting

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327 Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

Earned Schedule Analysis

Earned Schedule Analysis Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

Roberta Tomasini Defense Acquisition University DSN

Roberta Tomasini Defense Acquisition University DSN $ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

Earned Schedule schedule performance

Earned Schedule schedule performance Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com 2010 ISPA/SCEA International Conference SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Ms

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

SAMPLE. AACE International Recommended Practice No. 80R-13

SAMPLE. AACE International Recommended Practice No. 80R-13 E 80R13 SA M PL ESTI MATEATCOMPLETI ON( EAC) AACE International Recommended Practice No. 80R-13 ESTIMATE AT COMPLETION (EAC) TCM Framework: 7.6 Risk Management 9.1 Project Cost Accounting 9.2 Progress

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data

Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data William Laing Technomics, Inc. wlaing@technomics.net 2011 ISPA/SCEA Joint Annual Conference & Training Workshop

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Overview of Today s Discussion. Don t Let EVM Data Mislead You. Steve Sheamer. Brief Overview of EVM Concepts. Why you can t trust BACs or EACs

Overview of Today s Discussion. Don t Let EVM Data Mislead You. Steve Sheamer. Brief Overview of EVM Concepts. Why you can t trust BACs or EACs Overview of Today s Discussion Brief Overview of EVM Concepts Don t Let EVM Data Mislead You Steve Sheamer Why you can t trust BACs or EACs Why EVM progress is often overstated Why you need to account

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1 RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0

More information

Project Management: Cost

Project Management: Cost Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

Connecting Earned Value to the Schedule

Connecting Earned Value to the Schedule Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

next level PMP Exam Preparation Formula Guide for the PMP Exam

next level PMP Exam Preparation Formula Guide for the PMP Exam next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to

More information

Project health monitoring by Earned Value Analysis

Project health monitoring by Earned Value Analysis 13th International Software Testing Conference (STC 2013) December 0-06, 2013 in Bangalore, India. Project health monitoring by Earned Value Analysis Gangadhar. B. Kallur Honeywell Technology Solutions,

More information

Earned Schedule in Action

Earned Schedule in Action Earned Schedule in Action Earned Value Analysis - 11 Conference London, United Kingdom 12-17 June 2006 Kym Henderson Education Director PMI Sydney Australia Chapter Kym.Henderson@froggy.com.au EVM Schedule

More information

Prepared by DCMA Lockheed Martin Fort Worth

Prepared by DCMA Lockheed Martin Fort Worth Joint Strike Fighter Lightning II Monthly Assessment Report Prepared by DCMA Lockheed Martin Fort Worth January 2010 THIS DOCUMENT CONTAINS CONTRACTOR INFORMATION WHICH MAY BE PROPRIETARY AND PROTECTED

More information

What we practice (Sub) consciously

What we practice (Sub) consciously Project Horoscope or PM Horrorscope What we practice (Sub) consciously Face reading: by means of variations in face and head shape. Onomancy: by names. Clairvoyance: by spiritual vision or inner sight

More information

Value And Earned Schedule Management

Value And Earned Schedule Management EVM World 2013 Conference IPMC 2013 Title: An Analytical Utility For Earned Value And Earned Schedule Management Gary L. Richardson and Saranya Lakshmikanthan May 29, 2013 The popular technical literature

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

Utilization of EVM metrics In Developing Life Cycle Cost Estimates and Cost Benefit Analyses

Utilization of EVM metrics In Developing Life Cycle Cost Estimates and Cost Benefit Analyses Utilization of EVM metrics In Developing Life Cycle Cost Estimates and Cost Benefit Analyses Prepared by Anthony Chandler & Ken Thomson Areas of Discussion Life Cycle Cost Estimation (LCCE) and Cost Benefit

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013

Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013 Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013 Introduction Why do Project Management professionals need facts? What happens when we don

More information

Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd

Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd john.chapman@touchstone.co.uk John Chapman: Publications Project and Programme Accounting The Gower Handbook

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

CPM (College of Performance Management) Meetings have focused on this topic in the last year

CPM (College of Performance Management) Meetings have focused on this topic in the last year June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

Outline. Introduction. Nicholas C. Romano, Jr., Ph.D. Project Management Graphics: An Experimental Comparison Nicholas C. Romano

Outline. Introduction. Nicholas C. Romano, Jr., Ph.D. Project Management Graphics: An Experimental Comparison Nicholas C. Romano Project Management Graphics: An Experimental Comparison Nicholas C. Romano William S. Spears School of Business Management Science and Information Systems Oklahoma State University - Tulsa Nicholas.Romano@okstate.edu

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Prof. Shervin Shirmohammadi SITE, University of Ottawa Prof. Shervin Shirmohammadi ELG

More information

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis Prof. Shervin Shirmohammadi SITE, University of Ottawa Prof. Shervin Shirmohammadi ELG

More information

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions

More information

EVM s Potential for Enabling Effective Integrated Cost-Risk Management

EVM s Potential for Enabling Effective Integrated Cost-Risk Management EVM s Potential for Enabling Effective Integrated Cost-Risk Management by David R. Graham (dgmogul1@verizon.net; 703-489-6048) Galorath Federal Systems Stove-pipe cost-risk chaos is the term I think most

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

DATA ITEM DESCRIPTION

DATA ITEM DESCRIPTION DATA ITEM DESCRIPTION Form Approved OMB NO. 0704-0188 Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions,

More information

101 Tips and Tricks for winsight Part V

101 Tips and Tricks for winsight Part V 101 Tips and Tricks for winsight Part V A compendium of tips, tricks, and helpful hints; some are well known, some are new, a few are very new, and some should probably not be mentioned at all. Eleanor

More information

Gate Value Method Overview document

Gate Value Method Overview document Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects difficul7es to have an overall visibility of risks; a lack of understanding of all the interdependencies

More information

Long Description. Figure 15-1: Contract Status. Page 1 of 7

Long Description. Figure 15-1: Contract Status. Page 1 of 7 Page 1 of 7 Figure 15-1: Contract Status A single performance report provides the status of the Program at a point in time. When combined with previous reports, a much more revealing picture of the Program

More information

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information