1 MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda Review/Questions Your mini-presentations Session content Performance measurement What to measure How to measure it How to represent it Earned Value Analysis How to communicate it Review and preparation for #5 07/06/2004 MGT/437 #4 -- Brian Smithson 2 rian Smithson 1
2 Review/Questions Homework/Grades Computer/NETg issues Individual Assignment Learning Team Assignment Assigned Reading 07/06/2004 MGT/437 #4 -- Brian Smithson 3 Performance measurement Why measure performance? if you can t measure it, you can t manage it Stakeholders want to know You want to know Nobody likes surprises on projects You, your team, and/or your project, may be getting paid based on performance Typical reports Progress since last report Actual status versus plan (or baseline) Schedule, Cost, and Scope Problems identified, action plans, results Risks identified, occurred, mitigated 07/06/2004 MGT/437 #4 -- Brian Smithson 4 rian Smithson 2
3 What to measure 07/06/2004 MGT/437 #4 -- Brian Smithson 5 How to measure Planned, baselines, and actuals Planned is the plan as originally approved Baseline is the plan with approved changes There should be few baselines Only for significant changes There should be a good reason for measuring against a new baseline instead of against the original plan Actual is the actual status at a particular date Variances Deviations from what was planned (or baselined) 07/06/2004 MGT/437 #4 -- Brian Smithson 6 rian Smithson 3
4 Representing performance Tracking Gantt charts Shows progress toward milestones Indicates original plan and/or baseline plan, plus actual progress Control charts Shows accumulated variances and overall trends Earned Value Simple cost or schedule variances don t tell you enough Earned Value accounts for the value of the work performed and the cost of performing the work at a particular date Earned Value is often a basis for progress payments on projects 07/06/2004 MGT/437 #4 -- Brian Smithson 7 Tracking Gantt chart 07/06/2004 MGT/437 #4 -- Brian Smithson 8 rian Smithson 4
5 Control chart 07/06/2004 MGT/437 #4 -- Brian Smithson 9 Earned Value Components Work packages, schedules, and budgets EV status calculations BCWS = budgeted cost of work scheduled (more modern: PV) BCWP = budgeted cost of work performed (more modern: EV) ACWP = actual cost of work performed (more modern: AC) Schedule variance SV = BCWP BCWS Cost variance CV = BCWP ACWP EV planning calculations BAC = budgeted cost at completion, total BCWS for the project EAC = estimated cost at completion (we ll talk about this) VAC = BAC EAC, variance at completion ETC = EAC = ACWP, estimated amount remaining to complete 07/06/2004 MGT/437 #4 -- Brian Smithson 10 rian Smithson 5
6 EV Charts 07/06/2004 MGT/437 #4 -- Brian Smithson 11 EV Indexes Cost Performance Index CPI = BCWP / ACWP Schedule Performance Index SPI = BCWP / BCWS Percent Complete Index PCI-B = BCWP / BAC PCI-C = ACWP / EAC 07/06/2004 MGT/437 #4 -- Brian Smithson 12 rian Smithson 6
7 Techniques for estimating AC EAC = ACWP + ETC Used when past estimates were not correct EAC = ACWP + (BAC - BCWP) Used when current variances are not typical and are not expected to continue EAC = ACWP + (BAC - BCWP)/CPI Used when current variances are typical and expected to continue 07/06/2004 MGT/437 #4 -- Brian Smithson 13 Communicating performance Have a communication plan as part of your overall project plan What information will be collected, from whom, how often, etc. What reports and analyses will be performed, by whom, how often, etc. Who will receive reports and/or have access to collected information, on what schedule, under what circumstances, etc. 07/06/2004 MGT/437 #4 -- Brian Smithson 14 rian Smithson 7
8 Closing Questions? Assignments See the Course Syllabus for assignments Individual: reading assignment Problem identification assignment (prepare a 5 minute talk) Study for final exam questions multiple choice closed book, closed notes Learning team: Part 4 of project: Project Evaluation, Reporting, and Termination Final project paper Presentation See you next week! 07/06/2004 MGT/437 #4 -- Brian Smithson 15 rian Smithson 8
Cumulative trends Problems and issues since last report
Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier
More informationEarned Value Management Guide
1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress
More information4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring
More informationJames A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)
Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com
More information9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.
Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control
More informationProject Management -- Monitoring the progress
Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals
More informationEarned Value Management - EVM
Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the
More informationTHE PMP EXAM PREP COURSE
THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45
More informationNOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:
NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationPMP Exam Prep Coaching Program
PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationEARNED VALUE MANAGEMENT. Is it worth the effort?
EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our
More informationJefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7
Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,
More informationEarned Value Management An Overview March 2014
Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More informationTHE VALUE OF EARNED VALUE MANAGEMENT
THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs
More information1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish
International Campus Kish Sharif University of Technology Session#12 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,
More informationProject Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:
Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,
More informationGPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties
More informationProject Monitoring and Control Project Closure. Week 8
Project Monitoring and Control Project Closure Week 8 Last Week MS Project Tutorial Assignment Guidelines This Week Project Monitoring and Control What is Monitoring and Control Reporting Milestone Monitoring
More informationEarned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;
Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,
More informationFinancial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany
1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance
More informationCS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III
LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date
More informationFormulas to Know for EXAM
Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for
More informationHomework 6 Questions and Answers
I.E. 406 PROJECT SCHEDULING AND CONTROL Fall 2012 Murat Sandikcioglu (original by Dr.Onur ÇOKGÖR) Homework 6 Questions and Answers CRITICAL CHAIN PROJECT MANAGEMENT (CCPM) & EARNED VALUE ANALYSIS (EVA)
More informationApplication of Earned Value Management (EVM) for Effective Project Control
Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge
More informationMMZG 523 PROJECT MANAGEMENT
MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable
More informationPROJECT MANAGEMENT BODY OF KNOWLEDGE
A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education
More informationProfessional Development Seminar Series
Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context
More informationProject Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013
Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013 Introduction Why do Project Management professionals need facts? What happens when we don
More informationAdministration. Course Aim. Introductions
Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may
More informationEarning Value From Risk
Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationDEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers
1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program
More informationWorkshop II Project Management
Workshop II Project Management UNITAR-HIROSHIMA FELLOWSHIP FOR AFGHANISTAN 2007 Introduction to Project Management 15 17 August 2007, Dehradun, India Presented by: Dr. Jobaid Kabir Fellowshop Program 2007
More informationPerformance Analyzer Formulas. Assumptions. Current Month Adjustments
User's Guide for PA for Windows Error! No text of specified style in document. 1 Performance Analyzer Formulas Assumptions Current Month Adjustments Current Period values (BCWS, BCWP, ACWP) are derived
More informationWhat is Earned Value Analysis?
What is Earned Value Analysis? 1 Earned Value Performance Measurement Time now Budget Cost Actual Good News or Bad? Time 2 Starting point Recording Progress The Plan is in place and work has started, so
More informationProject Performance Evaluation By Earned Value Method
Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *
More information[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP
This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,
More informationProject Management: Cost
Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required
More informationANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?
ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1
More informationEarned Value Management Handbook. arne. alu
Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change
More informationAnalysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh
Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS
More informationThe Mystery of Earned Value - An Oil & Gas Owner s Perspective
The Mystery of Earned Value - An Oil & Gas Owner s Perspective 15 June 2011 William Harroun Head of Programme Controls, BG Group What we are going to cover Cost and progress reporting before --- Earned
More informationRunning head: VALUE ANALYSIS REPORTING 1
Running head: VALUE ANALYSIS REPORTING 1 Value Analysis Reporting Benjamin Srock Embry-Riddle Aeronautical University Worldwide Campus Effective Communication for Managing Projects PMGT-502 Ki-Young Jeong,
More informationEarned Value Management
Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards
More informationCONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationnext level PMP Exam Preparation Formula Guide for the PMP Exam
next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to
More informationThe Value of EVM. Earned Value Management
The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in
More informationUnderstanding the Differences. Accounting Practice for Measuring. Supertech Project Management
Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php
More informationEarned Value Management. Danielle Kellogg. Hodges University
Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationEarned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd
Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd john.chapman@touchstone.co.uk John Chapman: Publications Project and Programme Accounting The Gower Handbook
More informationEARNED VALUE AS A RISK ASSESSMENT TOOL
EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at
More information5-D Integrated Earned Value Analysis
5-D Integrated Earned Value Analysis Erol Yurtseven, October 2013 Budgeting Scheduling Design Coordination Quantity Survey Technical Office 3 4 Technical Office Design Dept & Technical Office 2 5 Cost
More informationEV in a War Zone: Understanding Earned Value & How to apply it.
EV in a War Zone: Understanding Earned Value & How to apply it. 2017 CONSTRUCTION CPM CONFERENCE WED33, 2PM SPEAKER: ERIK TUMA, P.S.P Kandahar International Airport, Kandahar, Afghanistan Personal Introduction
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationObjectives of Project Cost Control System
Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final
More informationProject Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition
Project Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition Chapter Fourteen Cost Control Do Project Managers Control Costs, Monitor Costs, or Both? Cost Management
More informationINTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz
INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions
More informationKey Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado
Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept
More informationCONSTRUCTION PROJECT RISK CONTROL BASED ON EXPERTISE USING FUZZY SET THEORY
CONSTRUCTION PROJECT RISK CONTROL BASED ON EXPERTISE USING FUZZY SET THEORY Andrzej Minasowicz*, Bartosz Kostrzewa, and Jacek Zawistowski Department of Civil Engineering, Warsaw University of Technology,
More informationENGINEERING MANAGEMENT (GE
بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control
More informationeurope GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors
eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration
More informationNEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4
NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process
More informationEVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS
EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:
More informationEarned Value Management System. a system to
Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects difficul7es to have an overall visibility of risks; a lack of understanding of all the interdependencies
More informationRoberta Tomasini Defense Acquisition University DSN
$ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program
More informationPredicting The Future
Predicting The Future Peter Hayward BAE Systems Insyte 1 Predicting The Future Steve said to me that perhaps I could maybe touch on one or two main issues with forecasting the Estimate To Complete 2 Predicting
More informationEarned Value Management System. a system to
Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects where there is difficult to have an overall visibility of risks a lack of understanding of
More informationProject Controls Expo
Project Controls Expo 09/10 Nov London 2011 Integrating Risk and Earned Value Management Speaker Profile Since joining BMT in 2000, Edwina has provided Project Controls expertise to MoD Programme teams
More informationApplication of Earned Value Analysis in Analysing Project Performance
Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant
More informationeurope GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors
eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration
More informationConnecting Earned Value to the Schedule
Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned
More informationCapital Acquisition Under The President s Management Agenda. David Muzio Office of Federal Procurement Policy
Capital Acquisition Under The President s Management Agenda David Muzio Office of Federal Procurement Policy 202-395-6805 President s Message in FY 2003 Budget With all the new demands on our resources,
More informationLearning Legacy Document
PROGRAMME CONTROLS - COST Performance Measurement Procedure Current Document History: Revision: Effective Date: Document Number: CRL1-XRL-Z9-GPD-CR001_Z-50001 Author(s) Reviewed by: Approved by: Reason
More informationSMC/PMAG Control Account Manager (CAM) Notebook Evaluation
Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com 2010 ISPA/SCEA International Conference SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Ms
More informationOverview of Today s Discussion. Don t Let EVM Data Mislead You. Steve Sheamer. Brief Overview of EVM Concepts. Why you can t trust BACs or EACs
Overview of Today s Discussion Brief Overview of EVM Concepts Don t Let EVM Data Mislead You Steve Sheamer Why you can t trust BACs or EACs Why EVM progress is often overstated Why you need to account
More informationPredicting Project Completion Date Using Earned Value Management
Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231
More information!" #Resource) *"* $ $ $&& $ $+$ (+& $ $ !"( /3 "'(!", &"!"-1 "'('') (+. %& $') Data Type Entry Type. % Complete Percentage Calculated or Entered
Data Type Entry Type % Complete Percentage % Work complete Percentage Actual Cost Currency Actual Actual Finish Date Actual Overtime Cost Actual Overtime Work Currency Actual Start Date Actual Work ACWP
More informationIRNOP 2017 Fuzzy Earned Value Management model for uncertain and complex projects. Leila M. Naeni Amir Salehipour
207 Fuzzy Earned Value Management model for uncertain and complex projects Leila M. Naeni Amir Salehipour Authors Leila M. Naeni Project Management lecturer at University of Technology Sydney. Research
More informationPass PMP in 21 Days - ITTO Toolbox PROCESS MAP
PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project
More informationSelf-Assessment Questions for Module 07 Project Cost Management
Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses
More informationLesson 7 The Project Budget
MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget
More informationEarned Value Management (EVM) and the Acquisition Program
American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.
More informationCost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP
Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that
More informationThree Numbers to Measure Project Performance
Dr. Thomas Liedtke Alcatel D 70435 Stuttgart (Germany) Peter Paetzold Alcatel D 70435 Stuttgart (Germany) e_mail: TLiedtke@alcatel.de phone: +49 711 821 40346 fax.: +49 711 821 42230 e_mail: Peter.Paetzold@alcatel.de
More informationEarned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC
Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationCarlos Consulting Group
Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group
More informationWhat we practice (Sub) consciously
Project Horoscope or PM Horrorscope What we practice (Sub) consciously Face reading: by means of variations in face and head shape. Onomancy: by names. Clairvoyance: by spiritual vision or inner sight
More informationSCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016
All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project
More informationPMI - Dallas Chapter. PMP Exam Sample Questions
PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationCPM (College of Performance Management) Meetings have focused on this topic in the last year
June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches
More informationSlides copyright 1996, 2001, 2005, 2009, 2014 by Roger S. Pressman. For non-profit educational use only
Chapter 34 Project Scheduling Slide Set to accompany Software Engineering: A Practitioner s Approach, 8/e by Roger S. Pressman and Bruce R. Maxim Slides copyright 1996, 2001, 2005, 2009, 2014 by Roger
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More information