Earned Value Management

Size: px
Start display at page:

Download "Earned Value Management"

Transcription

1 Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP September 5, 2018

2 Overview EVM Background EVM Basics and Standards Variables & Metrics Integrating Cost, Schedule, Scope EVM Links Sample Questions 2

3 EVM Background 1960s PERT/Cost :- Earned value-based on Department of Defense (DoD) Cost/Schedule Control Systems Criteria (C/SCSC) 1996 DoD adopts 32 Industry Earned Value criteria 1998 ANSI/EIA 748 Issued 3

4 EVM Basics Industry definition: Use of an integrated management system that coordinates work scope, schedule, and cost objectives and employs earned value methods for program planning and control EVM is not an accounting method or financial management practice 4

5 EVM Basics Triple Constraint EVM is a tool for the Project Manager Earned Value may point to cost or schedule issues, but does not substitute for good project management. Don t Manage the Earned Value Critical Path Analysis Technical, scope control SCOPE SCHEDULE COST 5

6 EVM Standards Industry standard ANSI/EIA EVM system guidelines address nine management processes DoD contracts >$20M require EVM DoD contracts >$100M surveillance, certified EVM System (EVMS) * Not used on FFP, LoE, or T&M Contracts * 6

7 EVM Variables - PMB Performance Management Baseline (PMB); timephased budget plan. Earned Value measures progress vs. the PMB. MR for unknown unknowns Should not mask poor cost performance Planning Packages for rolling wave WBS development EVM is managed at the CA level: Roll-up for Reporting NCC AUW Undistributed Budget CBB OVERRUN Work Packages Contract Price TAB PMB OTB Control Accounts Profit / Fees Planning Packages DAU Gold Card Management Reserve Summary Level Planning Packages 7

8 Responsibility Assignment Matrix (RAM) CONTRACT WORK BREAKDOWN STRUCTURE ORGANIZATIONAL STRUCTURE LEVEL 1 LEVEL 2 LEVEL 3 FIRE CONTROL RADAR TRAINING RECEIVER SYSTEM ANTENNA C O M P A N Y T E S T E N G M F G D E S I G N LEVEL 4 MECHANICAL DESIGN Electrical DESIGN DRAFTING/ CHECKING CONTROL ACCOUNT CONTROL ACCOUNT RECEIVER CONTROL ACCOUNT CONTROL ACCOUNT PHASE SHIFTER RECEIVER CASE POWER SUPPLY APPLICATION S/W Work Packages 8

9 EV Independent Variables PV or Planned Value, BCWS Budgeted Cost of Work Scheduled EV or Earned Value, BCWP Budgeted Cost of Work Performed AC or Actual Cost, ACWP Actual Cost of Work Performed BAC Budget at Completion EAC Estimate at Completion Also Latest Revised Estimate (LRE) 9

10 Some Earned Value Techniques (Short-Term, 2-3 Periods) (Within One Period) Incremental Milestone (Long-Term) Equivalent Unit (e.g.: Road Building) Percent Complete Agile: use %Complete from agile tool and apply to high level schedule Supervisor s Estimate (Subjective) 10

11 Earned Value Metrics CV = EV AC = BCWP ACWP Cost Variance SV = EV PV = BCWP BCWS Schedule Variance (Accomplishment) in $ VAC = BAC EAC Variance at Completion Forecast Overrun or Underrun 11

12 Earned Value Metrics Cost Efficiency Cost Performance Index (CPI) = EV/AC CV% = (CV/EV)*100 Schedule Efficiency Schedule Performance Index (SPI) = EV/PV SV% = (SV/PV)*100 To Complete Performance Index (TCPI) Work Remaining / Cost Remaining (BAC EV) / (EAC AC) 12

13 Earned Value Metrics EAC Forecast Final Cost (EAC) by Projecting Future Performance based on Past Performance Estimate At Completion (EAC) oactuals to Date + [Remaining Work / Efficiency Factor] oac + [(BAC EV) / CPI] = BAC/CPI Estimate to Complete (ETC) oetc = EAC AC = BAC/CPI AC 13

14 EVM Graphical View Graphical view of baseline (PMB) showing end date and total Budget at Completion (BAC). EAC Using the past performance, CPI, as a prediction of future performance, the AC can be projected to forecast an Estimate at Completion (EAC). PV is the PMB up to the Status Date $ Management Reserve (MR) Schedule Variance AC PMB Cost Variance TAB BAC CV compares the actual cost to the budgeted cost of actual Work Performed. PV EV SV compares the Budgeted Cost of actual Work Performed with Work Scheduled up to the Status Date (Time Now). time Time Now Completion Date 14

15 Evaluating Schedule Variance SV does not tell the whole story Good News May Not Be Good 10 Day s work Scheduled by status date 10 Days work completed: Zero Schedule Variance Critical Path shows Project will be 2 days late! 3 Days 2 Days 2 Days 3 Days Critical Path Start 10 Days 2 Days 3 Days 2 Days 2 Days Time Now Days Completed Task 15

16 Evaluating Schedule Variance SV does not tell the whole story Bad News May Not Be Bad 15 Day s work Scheduled by status date Only 12 Days work completed: Negative SV Critical Path shows Project is on schedule Slipped Task has Slack Critical Path 5 Days 5 Days 5 Days 4 Days Start 10 Days 2 Days 3 Days 3 Days 2 Days Time Now Completed Task 16

17 Integrated Baseline Review Jointly Assess Planning Cost, Schedule, Technical Ensure Complete Coverage of SOW Exclude Work not in Scope Logical Scheduling Critical Path Adequate Resourcing Identify Risk 17

18 Integrating Cost, Schedule, Scope DAU 12-Step Analysis Model Highlights: Sort for CV and SV $ and %, ID WBS elements w/ most unfavorable variances Correlate w/ Technical Drivers / Key Performance Parameters (KPPs) Correlate w/ Critical Path Correlate CV & SV drivers w/ each other 18

19 Integrating Cost, Schedule, Scope Generate an EAC Based on Key Drivers Select Performance Factor (PF) for Key WBS Elements CPI for Cost Drivers SPI for Schedule Drivers CPI*SPI for both Technical Risk Factor 19

20 Validate Independent EAC Low Range EAC: CPI(cum) High Range EAC: CPI(cum)*SPI(cum) Likely EAC from Analysis Independent TCPI within 5% of CPI(cum)? Future performance is not likely to increase more than 5% over past performance based on OSD history 20

21 CPI and To-Complete 21

22 Summary EVM is one tool available to the PM Use with Critical Path analysis Integrates Cost & Schedule performance Correlate with key technical drivers Report Card on the baseline Increased focus by Federal agencies More interest by commercial sector MS Project EV table Agile: Storycard tool & sprint summary 22

23 EVM Links AT&L EVM site: DAU EVM community: DAU EVM Training: %20Center.aspx DAU Gold Card General-Reference-(Gold-Card) NDIA Guides and Resources, including EVM Intent Guide (32 Criteria) 23

24 Q&A 24

25 $ BCWS Cum EARNED VALUE MANAGEMENT GOLD CARD Total Allocated Budget Management Reserve Schedule Variance ACWP Cum Time BCWP Cum Time Now VARIANCES Positive is Favorable, Negative is Unfavorable Cost Variance CV = BCWP ACWP CV % = (CV / BCWP) * 100 Schedule Variance SV = BCWP BCWS SV % = (SV / BCWS) * 100 Variance at Completion VAC = BAC EAC VAC % = (VAC / BAC) * 100 PMB Cost Variance Projected Slip? Completion Date EFFICIENCIES Cost Efficiency CPI = BCWP / ACWP Favorable is > 1.0, Unfavorable is < 1.0 Schedule Efficiency SPI = BCWP / BCWS Favorable is > 1.0, Unfavorable is < 1.0 EAC BAC COMPLETION = ACTUALS TO DATE + [ (REMAINING WORK) / (PERFORMANCE FACTOR) ] EAC CPI = ACWP CUM + [ (BAC BCWP CUM ) / CPI CUM ] EAC Composite = ACWP CUM + [ (BAC BCWP CUM ) / (CPI CUM * SPI CUM ) ] TO COMPLETE PERFORMANCE INDEX (TCPI) # TCPI Target = Work Remaining / Cost Remaining = (BAC BCWP CUM ) / (Target ACWP CUM ) To Determine the TCPI for BAC, LRE, or EAC Substitute TARGET with BAC, LRE, or EAC # To Determine the Contract Level TCPI for EAC, You May Replace BAC with TAB OVERALL STATUS % Schedule = (BCWS CUM / BAC) * 100 % Complete = (BCWP CUM / BAC) * 100 % Spent = (ACWP CUM / BAC) * 100 BASELINE EXECUTION INDEX (BEI) & Hit Task % BEI = Total Tasks Completed / (Total Tasks with Baseline Finish On or Prior to Current Report Period) Hit Task % = 100 * (Tasks Completed ON or PRIOR to Baseline Finish / Tasks Baselined to Finish within Current Report Period) NCC AUW TAB CBB OVERRUN Undistributed Control Budget (UB) Accounts (CA) Work Packages (WP) Contract Price PMB OTB Profit / Fees Summary Level Planning Packages (SLPP) Planning Packages (PP) Management Reserve (MR) ACRONYMS ACWP Actual Cost of Work Performed Cost actually incurred in accomplishing work performed = ACTUAL COST AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized BAC Budget At Completion Total budget for total contract thru any given level BCWP Budgeted Cost for Work Performed Value of completed work in terms of the work s assigned budget = EARNED VALUE BCWS Budgeted Cost for Work Scheduled Time-phased Budget Plan for work currently scheduled = PLANNED VALUE CA Control Account Lowest CWBS element assigned to a single focal point to plan & control scope / schedule / budget CBB Contract Budget Base Sum of NCC & AUW EAC Estimate At Completion Estimate of total Cost for total contract thru any given level generated by Ktr, PMO, DCMA, etc. = EAC Ktr / PMO / DCMA LRE Latest Revised Estimate Ktr s EAC or EAC Ktr MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management NCC Negotiated Contract Cost Contract Price Minus profit or fee(s) OTB Over Target Baseline Sum of CBB + additional budget approved for remaining work PAC Price At Completion EAC Plus Adjusted Profit or Fee(s) PMB Performance Measurement Baseline Contract time-phased budget plan PP Planning Package Far-term CA activities not yet defined into WPs SLPP Summary Level Planning Package Far-term contract activities not yet defined into CAs TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB TCPI To Complete Performance Index Efficiency needed from time now to achieve a Cost Target = BAC, LRE, or EAC UB Undistributed Budget Broadly defined activities not yet distributed to CAs or SLPPs WP Work Package Near-term, detail-planned activities within a CA EVM POLICY: Interim DoDI , Enclosure 1. Table 8. EVMS in accordance with ANSI/EIA-748 is required for cost or incentive contracts, subcontracts, intra-government work agreements, & other agreements valued > $20M (TY $). Contracts > $50M (TY $) require that the EVMS be formally validated by the cognizant contracting officer. EVM is discouraged on Firm-Fixed Price, Time & Material Contracts, & LOE activities regardless of cost. Refer to the IPMR Implementation Guide for IPMR Tailoring Guidance. DoD s EVM CONTRACTING REQUIREMENTS: DFARS CLAUSES NOTICE OF EVMS FOR SOLICITATIONS EVMS FOR SOLICITATIONS & CONTRACTS CONTRACTOR BUSINESS SYSTEMS FOR SOLICITATIONS & CONTRACTS CONTRACT PERFORMANCE REPORT DI-MGMT-81466A 5 FORMATS = WBS, ORGANIZATION, BASELINE, STAFFING, EXPLANATIONS & PROB ANALYSES INTEGRATED MASTER SCHEDULE DI-MGMT MANDATORY FOR DOD EVMS CONTRACTS Integrated Program Mngt Report DI-MGMT * 7 FORMATS = WBS, OBS / IPT, BASELINE, STAFFING, EXPLANATIONS & PROB ANALYSES, IMS, HISTORY / FORECAST COST INTEGRATED BASELINE REVIEW MANDATORY FOR ALL EVMS CONTRACTS WBS For Defense Materiel Items MIL-STD-881-C * Combines & Supersedes DI-MGMT-81466A & 81650; Effective July 1, 2012 EVM CoP: Address: EVM.dau@dau.mil Revised January 2014

26 Sample PMP Earned Value Questions You are the project manager of a project to build fancy birdhouses. - You are to build two birdhouses a month for 12 months. - Each birdhouse is planned to cost $ Your project is scheduled to last for 12 months. - It is the beginning of month You have built 20 birdhouses and your CPI is How is the project performing? A. Over budget and ahead of schedule B. Under budget and ahead of schedule C. Over budget and behind schedule D. Under budget and behind schedule. 1. A Over budget & ahead of schedule. The problem tells you that your CPI is.9091, and we know that CPI = EV/AC. Applying that, a CPI less than 1 means that we aren t getting enough value for each dollar that we put into our project, so it is over budget. However, the project is ahead of schedule because we have built 20 birdhouses and after 9 months, we had expected to build only 2 birdhouses per month * 9 months = 18 birdhouses. Questions posted by Rich Rinaldi,

27 Sample PMP Earned Value Questions You are the project manager of a project to build fancy birdhouses. - You are to build two birdhouses a month for 12 months. - Each birdhouse is planned to cost $ Your project is scheduled to last for 12 months. - It is the beginning of month You have built 20 birdhouses and your CPI is What is the actual cost of the project right now? A. $1800 B. $2000 C. $2200 D. $2400 C $2200. In this problem, we need to determine the AC. In the body of the problem, you are given the CPI and can determine the EV, so you can use the CPI formula to back out the AC. EV = 20 birdhouse & $100 per birdhouse = $2000. CPI = EV/AC.9091 = $2000/AC, so multiply both sides by AC AC(.9091) = $2000, so divide both side by.9091 AC = $2200. Questions posted by Rich Rinaldi,

28 Sample PMP Earned Value Questions You are the project manager of a project to build fancy birdhouses. - You are to build two birdhouses a month for 12 months. - Each birdhouse is planned to cost $ Your project is scheduled to last for 12 months. - It is the beginning of month You have built 20 birdhouses and your CPI is Assuming that the COST variance experienced so far in the project will continue, how much more money will it take to complete the project? A. $400 B. $440 C. $2800 D. $2840 B $440. First, use the context of the problem to determine that you need the ETC when a variance exists and it is continuing. Based on that information, we know to use ETC = BAC/CPI AC. We already know the CPI from the problem and AC from the solution to #2, so let s find BAC. BAC = 2 birdhouses per month * 12 months * $100 per birdhouse BAC = $2400 ETC = EAC AC = BAC/CPI AC ETC = $2400/.9091 $2200 ETC = $440 Questions posted by Rich Rinaldi,

29 Sample PMP Earned Value Questions You are the project manager of a project to build fancy birdhouses. - You are to build two birdhouses a month for 12 months. - Each birdhouse is planned to cost $ Your project is scheduled to last for 12 months. - It is the beginning of month You have built 20 birdhouses and your CPI is If the cost variance experienced so far were to stop, what is the project s estimate at completion? A. $2400 B. $2440 C. $2600 D. $2800 C $2600. This question is asking you for the EAC if a variance that was encountered on a project is expected to stop, so use EAC = AC + BAC EV ( or AC + Budgeted Cost of Work Remaining). EAC = $ $2400 $2000 EAC = $2600 The real PMP exam doesn t have answers that build upon each other, so your steps to solving this problem on its own would be less straightforward. Instead you would first determine which equation to use, then calculate AC using the CPI (as in question #2), then BAC as in question #3, then EV as in question #2. Questions posted by Rich Rinaldi,

30 Sample PMP Earned Value Questions You are the project manager of a project to build fancy birdhouses. - You are to build two birdhouses a month for 12 months. - Each birdhouse is planned to cost $ Your project is scheduled to last for 12 months. - It is the beginning of month You have built 20 birdhouses and your CPI is What is the project s TCPI using the project s Budget At Completion? A..5 B. 1 C. 1.5 D. 2 D 2. Fortunately, PMI has to tell you which TCPI formula to use. This one says use BAC, so TCPI = (Work Remaining)/(Budget Remaining) = (BAC EV)/(BAC AC) = ( ) / ( ) = 400/200 = 2. Or, 4 birdhouses left to build and $200 of budget remaining, so we would have to complete the last four at $50 each, or double the cost efficiency of the original plan. Questions posted by Rich Rinaldi,

31 You are the project manager of a project to build fancy birdhouses. - You are to build two birdhouses a month for 12 months. - Each birdhouse is planned to cost $ Your project is scheduled to last for 12 months. - It is the beginning of month You have built 20 birdhouses and your CPI is Senior management wants to know the percentage of the project that is complete. What should you report? A. 75% B. 83% C. 92% D. 95% B 83%. Percent Complete = (EV/BAC)*100% = ($2000/$2400)*100 = 83% Sample PMP Earned Value Questions Note: 92% of the Budget has been spent but does not represent the amount of completed work. Questions posted by Rich Rinaldi,

Roberta Tomasini Defense Acquisition University DSN

Roberta Tomasini Defense Acquisition University DSN $ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

DATA ITEM DESCRIPTION. Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date:

DATA ITEM DESCRIPTION. Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date: DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date: 20150916 AMSC Number: D9583 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing

More information

Outline. Introduction. Nicholas C. Romano, Jr., Ph.D. Project Management Graphics: An Experimental Comparison Nicholas C. Romano

Outline. Introduction. Nicholas C. Romano, Jr., Ph.D. Project Management Graphics: An Experimental Comparison Nicholas C. Romano Project Management Graphics: An Experimental Comparison Nicholas C. Romano William S. Spears School of Business Management Science and Information Systems Oklahoma State University - Tulsa Nicholas.Romano@okstate.edu

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

Chapter 7 Earned Value Management

Chapter 7 Earned Value Management Chapter 7 Earned Value Management Table of Contents 7.1 Introduction 7-4 7.2 Policy and Directives 7-4 7.3 Roles and Responsibilities 7-5 7.3.1 DoD Executive Agent 7-5 EVM Center 7-5 7.3.2 Component EVMS

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

DATA ITEM DESCRIPTION

DATA ITEM DESCRIPTION DATA ITEM DESCRIPTION Form Approved OMB NO. 0704-0188 Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions,

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

CPM (College of Performance Management) Meetings have focused on this topic in the last year

CPM (College of Performance Management) Meetings have focused on this topic in the last year June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

Master Definitions List for IPMD Guides

Master Definitions List for IPMD Guides National Defense Industrial Association Integrated Program Management Division Master Definitions List for IPMD Guides Revision December 18, 2018 National Defense Industrial Association (NDIA) 2101 Wilson

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com 2010 ISPA/SCEA International Conference SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Ms

More information

Level of Effort (LOE) Replanning

Level of Effort (LOE) Replanning Level of Effort (LOE) Replanning This article discusses how to avoid Level 3 Corrective Action Requests (CARs) that can result because of a lack of attention to level of effort (LOE) planned in support

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

Contract Performance Report

Contract Performance Report Contract Performance Report Description This report consists of five formats containing cost and related data for measuring contractors' cost and schedule performance on Department of Defense (DOD) acquisition

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

Earned Value Management System

Earned Value Management System DEPARTMENT OF VETERANS AFFAIRS Office of Information and Technology Earned Value Management System Description Document VA-DI-MGMT-81466A RECORD OF CHANGES Change Number Date Reference (Page, Section,

More information

Earned Value Manager Product Guide - On Premise. Service Pack

Earned Value Manager Product Guide - On Premise. Service Pack Earned Value Manager Product Guide - On Premise Service Pack 02.0.01 This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

Utilization of EVM metrics In Developing Life Cycle Cost Estimates and Cost Benefit Analyses

Utilization of EVM metrics In Developing Life Cycle Cost Estimates and Cost Benefit Analyses Utilization of EVM metrics In Developing Life Cycle Cost Estimates and Cost Benefit Analyses Prepared by Anthony Chandler & Ken Thomson Areas of Discussion Life Cycle Cost Estimation (LCCE) and Cost Benefit

More information

EARNED VALUE MANAGEMENT SYSTEM (EVMS)

EARNED VALUE MANAGEMENT SYSTEM (EVMS) NOT MEASUREMENT SENSITIVE DOE G 413.3-10A EARNED VALUE MANAGEMENT SYSTEM (EVMS) [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents and

More information

Agile Methods with. Performance-Based Earned Value

Agile Methods with. Performance-Based Earned Value Agile Methods with Performance-Based Earned Value CMMI Technology Conference Abstract 7110 November 20, 2008 Paul Solomon, PMP Performance-Based Earned Value www.pb-ev.com 1 Agenda Customer expects valid

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

EFCOG Best Practice #174

EFCOG Best Practice #174 EFCOG Best Practice #174 Best Practice Title: CPR/DID Monthly Validation Facility: Washington River Protection Solutions, Hanford Site, Richland Washington Point of Contact: Craig Hewitt, WRPS Hanford,

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

Performance Analyzer Formulas. Assumptions. Current Month Adjustments

Performance Analyzer Formulas. Assumptions. Current Month Adjustments User's Guide for PA for Windows Error! No text of specified style in document. 1 Performance Analyzer Formulas Assumptions Current Month Adjustments Current Period values (BCWS, BCWP, ACWP) are derived

More information

Humphreys &Associates, Inc.

Humphreys &Associates, Inc. Humphreys &Associates, Inc. 3111 N. Tustin Street, Suite 250 Orange, CA 92865 (714) 685-1730 (Phone) (714) 685-1734 (Fax) Email: humphreys@humphreys-assoc.com http://www.humphreys-assoc.com No portion

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013

Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013 Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013 Introduction Why do Project Management professionals need facts? What happens when we don

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

The [Whole] Truth about ANSI Compliant EVMS

The [Whole] Truth about ANSI Compliant EVMS The [Whole] Truth about ANSI Compliant EVMS ICEAA Workshop June 2013 1 Introduction 2 EVMS that complies with ANSI/EIA 748(B) Standard often characterized as good project management Basic concepts/principles

More information

Association for Project Management 2008

Association for Project Management 2008 Earned Value Management APM Guidelines Earned Value Management APM Guidelines Association for Project Management Association for Project Management Ibis House, Regent Park Summerleys Road, Princes Risborough

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Earned Value Management (EVM)

Earned Value Management (EVM) Earned Value Management (EVM) Tracking cost and schedule performance on projects What are my chances? / Not good. / You mean, not good like one out of a hundred? / I d say more like one out of a million.

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

Downloaded from

Downloaded from Over Target Baseline and Over Target Schedule Handbook May 7, 2003 1 Authors Ivan Bembers, NIMA Melissa Boord Traci Ann Byrnes, Department of Defense, Australia Tony Finefield, Finefield Consulting Will

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

DCMA MANUAL PROGRAM SUPPORT ANALYSIS AND REPORTING

DCMA MANUAL PROGRAM SUPPORT ANALYSIS AND REPORTING DCMA MANUAL 3101-02 PROGRAM SUPPORT ANALYSIS AND REPORTING Office of Primary Responsibility: Program Support Capability Effective: November 22, 2017 Releasability: Cleared for public release New Issuance

More information

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

AIR FORCE INSTITUTE OF TECHNOLOGY

AIR FORCE INSTITUTE OF TECHNOLOGY An Analysis of the Estimate at Complete for Department of Defense Contracts THESIS Deborah B. Kim, First Lieutenant, USAF AFIT-ENC-MS-18-M-214 DEPARTMENT OF THE AIR FORCE AIR UNIVERSITY AIR FORCE INSTITUTE

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION

GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION GEIA STANDARD ANSI/EIA-748-B-2007 Approved: September 10, 2007 EIA-748-B Earned Value Management Systems EIA-748-B JUNE 2007 GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION A Sector of the

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion

Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion Stephen A. Book The Aerospace Corporation P.O. Box 92957 Los Angeles, CA 90009-2957 (310) 336-8655 stephen.a.book@aero.org Society of Cost

More information

Project health monitoring by Earned Value Analysis

Project health monitoring by Earned Value Analysis 13th International Software Testing Conference (STC 2013) December 0-06, 2013 in Bangalore, India. Project health monitoring by Earned Value Analysis Gangadhar. B. Kallur Honeywell Technology Solutions,

More information

1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish

1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#12 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

And a Great Afternoon to You All

And a Great Afternoon to You All And a Great Afternoon to You All Report Documentation Page Report Date 26032001 Report Type N/A Dates Covered (from... to) - Title and Subtitle Earned Value Management as an Implementation Tool for CAIV

More information

Contracting for Integrated Project Management (IPM)

Contracting for Integrated Project Management (IPM) Contracting for Integrated Project Management (IPM) Mr. Gordon Kranz PARCA Deputy Director for NCMA Meeting June 23, 2015 0 Agenda OSD PARCA Integrated Program Management (IPM) Earned Value Management

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

The Mystery of Earned Value - An Oil & Gas Owner s Perspective The Mystery of Earned Value - An Oil & Gas Owner s Perspective 15 June 2011 William Harroun Head of Programme Controls, BG Group What we are going to cover Cost and progress reporting before --- Earned

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

Earned Value Management Training Program

Earned Value Management Training Program Earned Value Management Training Program Course Brochure and Competency Matrix INDEX: 1. Company Introduction 2. Training Programme Description 3. Training Delivery Options 4. Course Syllabus 5. Programme

More information

What is Earned Value Analysis?

What is Earned Value Analysis? What is Earned Value Analysis? 1 Earned Value Performance Measurement Time now Budget Cost Actual Good News or Bad? Time 2 Starting point Recording Progress The Plan is in place and work has started, so

More information

Value And Earned Schedule Management

Value And Earned Schedule Management EVM World 2013 Conference IPMC 2013 Title: An Analytical Utility For Earned Value And Earned Schedule Management Gary L. Richardson and Saranya Lakshmikanthan May 29, 2013 The popular technical literature

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

Braindumps.PMI-SP.323 questions

Braindumps.PMI-SP.323 questions Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for

More information

USING PERFORMANCE INDICES TO EVALUATE THE ESTIMATE AT COMPLETION 1. David S. Christensen Southern Utah University

USING PERFORMANCE INDICES TO EVALUATE THE ESTIMATE AT COMPLETION 1. David S. Christensen Southern Utah University USING PERFORMANCE INDICES TO EVALUATE THE ESTIMATE AT COMPLETION 1 David S. Christensen Southern Utah University Christensend@suu.edu ABSTRACT The estimated final cost of a defense contract, termed the

More information