Earned Value Management - EVM

Size: px
Start display at page:

Download "Earned Value Management - EVM"

Transcription

1 Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the scope, schedule and cost. Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work More Elaborately: Earn Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. EVM technique integrates the scope, schedule and cost of a project. EVM technique answers a lot of questions to the stakeholders in a project related to the performance of the project. EVM technique can be used to show past performance of the project, current performance of the project and predict the future performance of the project by use of statistical techniques. Good planning coupled with effective use of the EVM technique will reduce a large amount of issues arising out of schedule and cost overruns. EVM emerged as a financial analysis specialty in United States Government programs in the 1960s, but it has since become a significant branch of project management. In the late 1980s and early 1990s, EVM emerged as a project management methodology to be understood and used by managers and executives, not just EVM specialists and PMI. Today EVM should become an essential part of every project s performance tracking. There are following three basic elements of EVM Planned Value (PV) Actual Cost (AC) Earned Value (EV) All the three elements are captured on a regular basis as of a reporting date. Planned Value (PV) This is also referred to as Budgeted Cost of Work Scheduled (BCWS). Planned Value (PV) or BCWS is the total cost of the work scheduled /Planned as of a reporting date. This is calculated as: PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled Prepared By: Michael McCormick Page 1

2 NOTE: Hourly Rate is the rate at which effort will be valued. Actual Cost (AC) This is also referred to as Actual Cost of Work Performed (ACWP). Actual Cost (AC) or ACWP is the total cost taken to complete the work as of a reporting date. This is calculated as: AC or ACWP = Hourly Rate * Total Hours Spent Earned Value (EV) This is also referred to as Budgeted Cost of Work Performed (BCWP). Earned Value (EV) or BCWP is the total cost of the work completed/performed as of a reporting date. This is calculated as: EV or BCWP = Baselined Cost * % Complete Actual BAC * % Complete All these three elements can be derived from Work Breakdown Structure by associating the costs to each of the tasks. For a big project it will be a tedious task to calculate these elements manually. Scheduling Software like Microsoft Project is used to calculate these three elements. NOTE: % Completed Planned and % Completed Actual are defined below % Completed Planned The percentage of work which was planned to be completed by the Reporting Date. This is calculated using the following formula % Completed Planned = PV / BAC % Completed Actual The percentage of work which was actually completed by the Reporting Date. This is calculated using the following formula % Completed Actual = AC / EAC Cost Variance (CV) is very important factor to measure project performance. Cost Variance (CV) indicates how much over or under budget the project is. Cost Variance can be calculated as using the following formula Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC) Prepared By: Michael McCormick Page 2

3 Cost Variance (CV) = BCWP - ACWP The formula mentioned above gives the variance in terms of cost which will indicate how less or more cost has been to complete the work as of date. Positive Cost Variance Indicates the project is under budget Negative Cost Variance Indicates the project is over budget Cost Variance % Cost Variance % indicates how much over or under budget the project is in terms of percentage. Cost Variance % can be calculated as using the following formula CV % = Cost Variance (CV) / Earned Value (EV) CV % = CV / BCWP The formula mentioned above gives the variance in terms of percentage which will indicate how much less or more money has been used to complete the work as planned in terms of percentage. Positive Variance % indicates % under Budget. Negative Variance % indicates % over Budget. Cost Performance Indicator (CPI) Cost Performance Indicator is an index showing the efficiency of the utilization of the resources on the project. Cost Performance Indicator can be calculated using the following formula: CPI = Earned Value (EV) /Actual Cost (AC) CPI = BCWP / ACWP The formula mentioned above gives the efficiency of the utilization of the resources allocated to the project. CPI value above 1 indicates efficiency in utilizing the resources allocated to the project is good. CPI value below 1 indicates efficiency in utilizing the resources allocated to the project is not good. The To Complete Performance Index (TCPI) TCPI is the third forecasting tool mentioned in the PMBOK Guide. This is a relatively new term which was coined by the PMI to assist project managers in calculating the future cost performance of the project. Prepared By: Michael McCormick Page 3

4 Since the concept of TCPI is new and there is not much research available on this topic, it often confuses many people. The To Complete Performance Index (TCPI) gives you the future cost performance index that you must follow for the remaining work if you want to complete it within the given budget. As per the PMBOK Guide, fifth edition: TCPI is the calculated cost performance index that is achieved on the remaining work to meet the specified management goal, such as the BAC or the EAC. Put more simply, the To Complete Performance Index (TCPI) is the estimate of the future cost performance that you may need to complete the project within the approved budget. This budget may be your initial approved budget (BAC), or a newly calculated budget/estimate at completion (EAC). You can calculate the TCPI by dividing the remaining work by the remaining funds; i.e. TCPI = (Remaining Work) / (Remaining Funds) or (BAC EV) You can calculate the remaining work by subtracting the earned value from the total budget; i.e. (BAC EV). However, there are two cases to determine the remaining funds on hand. In the first case, you determine the remaining funds when you are under budget and in the second case when you are over budget. So, in these cases, the formula to calculate the To Complete Performance Index (TCPI) formula will be different. To Complete Cost Performance Indicator (TCPI) To complete Cost Performance Indicator is an index showing the efficiency at which the resources on the project should be utilized for the remainder of the project. This can be calculated using the following formula: TCPI using Budget at Completion (BAC) TCPI (BAC) = Work Remaining ( BAC - EV ) / Funds Remaining (BAC - AC) TCPI using the Project Manager s Estimate at Completion (EAC) TCPI (EAC) = Work Remaining ( BAC - EV ) / ( EAC - AC) The formula mentioned above gives the efficiency at which the project team should be utilized for the remainder of the project. TCPI value above 1 indicates utilization of the project team for the remainder of the project can be stringent. TCPI value below 1 indicates utilization of the project team for the remainder of the project should be lenient. Schedule Variance indicates how much ahead or behind schedule the project is. Schedule Variance can be calculated as using the following formula Prepared By: Michael McCormick Page 4

5 Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV) Schedule Variance (SV) = BCWP - BCWS The formula mentioned above gives the variance in terms of cost which will indicate how much cost of the work is yet to be completed as per schedule or how much cost of work has been completed over and above the scheduled cost. Positive Schedule Variance Indicates we are ahead of schedule Negative Schedule Variance Indicates we are behind of schedule Schedule Variance % Schedule Variance % indicates how much ahead or behind schedule the project is in terms of percentage. Schedule Variance % can be calculated as using the following formula SV % = Schedule Variance (SV) / Planned Value (PV) SV % = SV / BCWS The formula mentioned above gives the variance in terms of percentage which will indicate how much percentage of work is yet to be completed as per schedule or how much percentage of work has been completed over and above the scheduled cost Positive Variance % indicates % ahead of schedule. Negative Variance % indicates % behind of schedule. Schedule Performance Indicator (SPI) Schedule Performance Indicator is an index showing the efficiency of the time utilized on the project. Schedule Performance Indicator can be calculated using the following formula: SPI = Earned Value (EV) /Planned Value (PV) SPI = BCWP / BCWS The formula mentioned above gives the efficiency of the project team in utilizing the time allocated for the project. SPI value above 1 indicates project team is very efficient in utilizing the time allocated to the project. SPI value below 1 indicates project team is less efficient in utilizing the time allocated to the project. To Complete Schedule Performance Indicator (TSPI) To Complete Schedule Performance Indicator is an index showing the efficiency at which the remaining time on the project should be utilized. This can be calculated using the following formula: Prepared By: Michael McCormick Page 5

6 TSPI = ( Total Budget - EV ) / ( Total Budget - PV ) TSPI = ( Total Budget - BCWP ) / ( Total Budget - BCWS ) The formula mentioned above gives the efficiency at which the project team should utilize the remaining time allocated for the project. TSPI value below 1 indicates project team can be lenient in utilizing the remaining time allocated to the project. TSPI value above 1 indicates project team needs to work harder in utilizing the remaining time allocated to the project. Budget At Completion (BAC) Budget At Completion (BAC) is the total budget allocated to the project. Budget At Completion (BAC) is generally plotted over time. Say like periods of reporting (Monthly, Weekly etc.) BAC is used to compute the Estimate At Completion (EAC), explained in next section. BAC is also used to compute the TCPI and TSPI BAC is calculated using the following formula BAC = Baselined Effort-hours * Hourly Rate Estimate To Complete (ETC) Estimate To Complete (ETC) is the estimated cost required to complete the remainder of the project. Estimate To Complete (ETC) is calculated and applied when the past estimating assumptions become invalid and a need for fresh estimates arises. ETC is used to compute the Estimation at Completion (EAC). ETC is calculated using the following formula ETC = EAC-AC Estimate At Completion (EAC) Estimate At Completion (EAC) is the estimated cost of the project at the end of the project. There are 5 Formulas Derived from the Generic EAC Formula based on what conditions you have with your project: Formula I EAC = AC + ETC Formula II EAC = AC + (BAC EV) Formula III EAC = AC + (BAC EV)/CPI Formula IV EAC = BAC/CPI Formula V EAC = AC + [(BAC EV)/(CPI * SPI)] There are 4 formulas listed in the PMBOK Guide 5th Edition. Most of the PMP study guides also list the Prepared By: Michael McCormick Page 6

7 same 4 formulas. But, I have listed 5 formulas here. The PMBOK Guide lists Formula II but does not list Formula III. I have listed both these formulas as Formula II is a special case of Formula III. In fact Formula IV is also a special case of Formula III. Let us take a close look at all the formulas. Let me explain each one of them in detail. Formula I Formula I is same as our Generic EAC Equation. EAC = AC + ETC In the PMBOK Guide and in some other books you will find this formula written as EAC = AC + Bottom-up ETC What is Bottom-up ETC? Refer to Scenario IV of my article on Estimate to Complete. The term Bottom-Up has no specific significance in the EAC formula. ETC can be either derived mathematically by using the ETC formulas or it can be estimated afresh. A fresh ETC can be found by estimating the cost of remaining (unfinished) work in the Work Breakdown Structure (WBS). You can re-estimate the cost of remaining (unfinished) work components (work packages and activities) and then total them Upwards in the WBS to determine a fresh ETC. Formula II Refer to my article on Estimate to Complete. By replacing ETC Formula II (project s past performance was atypical) in the EAC Equation, the EAC Equation reduces to EAC = AC + (BAC EV) Formula III Refer to my article on Estimate to Complete. By replacing ETC Formula I (project s past performance was typical) in the EAC Equation, the EAC Equation reduces to EAC = AC + (BAC EV) / CPI Note: We can also use Formula III of ETC in the EAC Equation. It will give us another formula which would be similar to EAC Formula III. However, the resulting formula would use projected future CPI instead of past CPI. Formula IV Let us mathematically solve EAC Formula III. EAC = AC + (BAC EV) / CPI EAC = AC + (BAC EV) / CPI EAC = AC + (BAC / CPI) (EV / CPI) Refer to Basics of Earned Value Analysis. Let us replace CPI in above Equation with (EV/AC). The above Prepared By: Michael McCormick Page 7

8 Equation reduces to EAC = AC + (BAC / CPI) EV/(EV/AC) EAC = AC + (BAC / CPI) AC EAC = BAC / CPI Formulas III and IV are, sometimes, also referred to as Independent Estimate at Completion or IEAC. Variance At Completion (VAC) Variance At completion (VAC) is the variance on the total budget at the end of the project. This is the difference between what the project was originally expected (baselined) to cost, versus what it is now expected to cost. VAC is calculated using the following formula VAC = BAC - EAC % Completed Planned The percentage of work which was planned to be completed by the Reporting Date. This is calculated using the following formula % Completed Planned = PV / BAC % Completed Actual The percentage of work which was actually completed by the Reporting Date. This is calculated using the following formula % Completed Actual = AC / EAC Prepared By: Michael McCormick Page 8

9 To illustrate the concept of EVM and all the formulas, assume a project that has exactly one task. The task was baselined at 8 hours, but 11 hours have been spent and the estimate to complete is 1 additional hour. The task was to have been completed already. Assume an Hourly Rate of $100 per hour. Using this information: Hourly Rate = $100 PV or BCWS = Hourly Rate * Total Hours Planned or Scheduled PV = $800 ($100 * 8 hours) AC or ACWP = Hourly Rate * Total Hours Spent AC = $1100 ($100 * 11 hours) EV or BCWP = Baselined Cost * % Complete Actual EV = $734 (baseline of $800 * 91.7% complete) (NOTE % Complete Actual (below) to get the 91.7%) BAC = Baselined Effort-hours * Hourly Rate BAC = $800 (8 hours * $100) EAC = AC + ETC EAC = $1200 ( ) VAC = BAC - EAC VAC = -$400 ($800 - $1200) % Completed Planned = PV / BAC % Complete Planned = 100% ($800 PV / $800 BAC) % Completed Actual = AC / EAC % Complete Actual = 91.7% ($1100 AC / $1200 EAC) SV = Earned Value (EV) - Planned Value (PV) SV = -$66 ($734 EV - $800 PV) SPI = Earned Value (EV) /Planned Value (PV) SPI = 0.91 ($734 EV / $800 PV) CV = Earned Value (EV) - Actual Cost (AC) CV = -$366 ($734 EV - $1100 AC) indicating a cost overrun CPI = Earned Value (EV) /Actual Cost (AC) CPI = 0.66 ($734 EV / $1100 AC) indicating over budget Prepared By: Michael McCormick Page 9

10 TCPI Example You have a project to be completed in 12 months and the total cost of the project is $100,000 USD. Six months have passed and $60,000 USD has been spent, but on closer examination you find that only 40% of the work is completed so far. Find the To Complete Performance Index (TCPI) for this project. Example: Budget at Completion (BAC) = $100,000 USD Actual Cost (AC) = $60,000 USD Planned Value (PV) = 50% of $100,000 = $50,000 USD Earned Value (EV) = 40% of $100,000 = $40,000 USD Cost Performance Index (CPI) = EV / AC = $40,000 / $60,000 = 0.67 Hence, Cost Performance Index (CPI) = 0.67 Now, Estimate at Completion (EAC) = BAC/CPI = $100,000/0.67 = $149, USD Hence, Estimate at Completion (EAC) = $149, USD From the calculation, we can see that since the CPI is less than one, you re over budget. Therefore, to calculate the To Complete Performance Index (TCPI), you will use the formula based on EAC. TCPI = (BAC EV)/(EAC AC) = (100,000 40,000)/(149, ,000) =60,000/89, =0.67 TCPI = 0.67 This means that you can continue with a Cost Performance Index of 0.67 to complete the project. Before I conclude this example, let s revisit some key points regarding the To Complete Performance Index (TCPI): Cost Performance Index (CPI) is the past performance of the project; on the other hand TCPI is the future performance of the project. If you are under budget, you will calculate the TCPI based on the BAC. If you are over budget, you will calculate the TCPI based on the EAC. If the To Complete Performance Index in less than one, you are in a comfortable position. If the To Complete Performance Index is greater than one, you have to perform with better cost performance than the past cost performance. And finally, if the To Complete Performance Index is equal to one, you can continue with the same cost performance. Prepared By: Michael McCormick Page 10

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

CPM (College of Performance Management) Meetings have focused on this topic in the last year

CPM (College of Performance Management) Meetings have focused on this topic in the last year June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Project Management: Cost

Project Management: Cost Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:

More information

A Practical Way To Learn About EVM. ***The Deck Project***

A Practical Way To Learn About EVM. ***The Deck Project*** A Practical Way To Learn About EVM ***The Deck Project*** Back to the Baseline 2 The Deck Project The product of this project is a new second-story deck in the backyard. This new deck will replace an existing

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

next level PMP Exam Preparation Formula Guide for the PMP Exam

next level PMP Exam Preparation Formula Guide for the PMP Exam next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to

More information

Application of Earned Value Analysis in Analysing Project Performance

Application of Earned Value Analysis in Analysing Project Performance Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant

More information

Estimating Cost-To-Go Without Stable EVM Data

Estimating Cost-To-Go Without Stable EVM Data PR-158 Estimating Cost-To-Go Without Stable EVM Data Peter C. Frederic, Tecolote Research Inc. Ronald K. Larson, NASA 20 March 2013 2013 Professional Development & Training Workshop New Orleans, LA June

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

CAPM Exam Prep.

CAPM Exam Prep. CAPM Exam Prep (What it really takes to prepare and pass) An ebook by Project Road Training, LLC www.project-road.com Bill Baxter Version 6-1 Project Road Training, LLC has been reviewed and approved as

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects difficul7es to have an overall visibility of risks; a lack of understanding of all the interdependencies

More information

PMP Exam Preparation Workshop Chapter 7 Project Cost Management

PMP Exam Preparation Workshop Chapter 7 Project Cost Management PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost

More information

What is Earned Value Analysis?

What is Earned Value Analysis? What is Earned Value Analysis? 1 Earned Value Performance Measurement Time now Budget Cost Actual Good News or Bad? Time 2 Starting point Recording Progress The Plan is in place and work has started, so

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects where there is difficult to have an overall visibility of risks a lack of understanding of

More information

Project health monitoring by Earned Value Analysis

Project health monitoring by Earned Value Analysis 13th International Software Testing Conference (STC 2013) December 0-06, 2013 in Bangalore, India. Project health monitoring by Earned Value Analysis Gangadhar. B. Kallur Honeywell Technology Solutions,

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd

Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd john.chapman@touchstone.co.uk John Chapman: Publications Project and Programme Accounting The Gower Handbook

More information

Connecting Earned Value to the Schedule

Connecting Earned Value to the Schedule Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned

More information

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,

More information

5-D Integrated Earned Value Analysis

5-D Integrated Earned Value Analysis 5-D Integrated Earned Value Analysis Erol Yurtseven, October 2013 Budgeting Scheduling Design Coordination Quantity Survey Technical Office 3 4 Technical Office Design Dept & Technical Office 2 5 Cost

More information

ENGINEERING MANAGEMENT (GE

ENGINEERING MANAGEMENT (GE بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

Performance Analyzer Formulas. Assumptions. Current Month Adjustments

Performance Analyzer Formulas. Assumptions. Current Month Adjustments User's Guide for PA for Windows Error! No text of specified style in document. 1 Performance Analyzer Formulas Assumptions Current Month Adjustments Current Period values (BCWS, BCWP, ACWP) are derived

More information

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

The Mystery of Earned Value - An Oil & Gas Owner s Perspective The Mystery of Earned Value - An Oil & Gas Owner s Perspective 15 June 2011 William Harroun Head of Programme Controls, BG Group What we are going to cover Cost and progress reporting before --- Earned

More information

Quantifying Damages in Construction Claims. James L McGovern

Quantifying Damages in Construction Claims. James L McGovern Quantifying Damages in Construction Claims James L McGovern Types of Claims Delay Acceleration Changed or Differing Site Conditions Defective Plans or Specs Disruption Extra Work Deletions of Work Potential

More information

Braindumps.PMI-SP.323 questions

Braindumps.PMI-SP.323 questions Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for

More information

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1 RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0

More information

Objectives of Project Cost Control System

Objectives of Project Cost Control System Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final

More information

Roberta Tomasini Defense Acquisition University DSN

Roberta Tomasini Defense Acquisition University DSN $ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program

More information

Running head: VALUE ANALYSIS REPORTING 1

Running head: VALUE ANALYSIS REPORTING 1 Running head: VALUE ANALYSIS REPORTING 1 Value Analysis Reporting Benjamin Srock Embry-Riddle Aeronautical University Worldwide Campus Effective Communication for Managing Projects PMGT-502 Ki-Young Jeong,

More information

Earned Schedule schedule performance

Earned Schedule schedule performance Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish

1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#12 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

Project Monitoring and Control Project Closure. Week 8

Project Monitoring and Control Project Closure. Week 8 Project Monitoring and Control Project Closure Week 8 Last Week MS Project Tutorial Assignment Guidelines This Week Project Monitoring and Control What is Monitoring and Control Reporting Milestone Monitoring

More information

Gate Value Method Overview document

Gate Value Method Overview document Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that

More information

Three Numbers to Measure Project Performance

Three Numbers to Measure Project Performance Dr. Thomas Liedtke Alcatel D 70435 Stuttgart (Germany) Peter Paetzold Alcatel D 70435 Stuttgart (Germany) e_mail: TLiedtke@alcatel.de phone: +49 711 821 40346 fax.: +49 711 821 42230 e_mail: Peter.Paetzold@alcatel.de

More information

A Case for Project Revenue Management. Peter Varani PMP

A Case for Project Revenue Management. Peter Varani PMP A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach

More information

Abstract. Value. Baselining a Project

Abstract. Value. Baselining a Project Earning Function Points in Software Projects Robert J. Muller, Chief Information Officer ValueStar, Inc. 1120A Ballena Blvd. Alameda, CA 94501-3682 Phone: (510) 814-7191 E-mail bmuller@valuestar.com Abstract

More information

Detailed Project Scheduling and Cost Management

Detailed Project Scheduling and Cost Management Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute

More information

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327 Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING

More information