PMP Exam Preparation Workshop Chapter 7 Project Cost Management

Size: px
Start display at page:

Download "PMP Exam Preparation Workshop Chapter 7 Project Cost Management"

Transcription

1 PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1

2 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost management processes as described in PMBOK Guide Fifth Edition How to approach PMP Exam questions on cost management 2

3 Agenda Cost Management Overview Cost Management Processes: 1. Plan Cost Management 2. Estimate Costs 3. Determine Budget 4. Control Costs Sample Exam Questions 3

4 Introduction Project Cost Management: Involves planning, estimating, budgeting, financing, funding, managing, and controlling costs. Facilitate project completion within the approved budget. Includes the following processes: Plan Cost Management Estimate Costs Determine Budget Control Costs Predicts and analyzes financial performance of the project. 4

5 Overview PMBOK V5 Ref # Fig

6 Plan Cost Management PMBOK V5 Ref # Fig 7-2 6

7 Plan Cost Management PMBOK V5 Ref # Fig 7-3 7

8 Plan Cost Management Cost Management Plan: Element of the project management plan which describes how the project costs will be planned, structured and controlled May be formal or informal, highly detailed or broadly framed, based upon the needs of the project 8

9 Plan Cost Management - Inputs Project Management Plan Scope baseline Schedule baseline Project Charter Summary budget Approval requirements Enterprise Environmental Factors Organizational culture Market conditions, currency exchange rates Published commercial information Organization Process Assets Financial controls procedures Historical information and lessons learned Financial databases, cost estimating and budgeting policies 9

10 Plan Cost Management Tools & Techniques Expert Judgment Guided by historical information Guided by expertise Analytical Techniques May involve strategic funding options Meetings Planning meetings with anyone with responsibility for project costs 10

11 Plan Cost Management - Outputs Cost Management Plan: Units of Measure Level of Precision Level of Accuracy Organizational Procedures Links Control Thresholds Rules of Performance Measurement Earned Value Management (EVM) Reporting Formats Process Descriptions Additional Details 11

12 Estimate Costs PMBOK V5 Ref # Fig

13 Estimate Costs PMBOK V5 Ref # Fig

14 Estimate Costs Determines the approximate monetary resources needed to complete project activities Cost differs from price Cost: how much is spent to complete the product or service Price: how much to charge for the product or service (i.e., a business decision) Cost estimates identify and investigate various alternatives, e.g.: Make vs buy Buy vs lease 14

15 Estimate Costs Cost estimates Generally expressed in units of currency May be expressed in work hours or days Includes all resources charged to the project, e.g.: Labour, materials, equipment, services, facilities Accuracy of estimates Order of Magnitude(ROM) estimate: -25% to +75% Preliminary estimate: -15% to + 50% Budget estimate: -10% to +25% Definitive estimate: -5% to +10% Final estimate: 0% Estimates are refined during the course of the project as additional detail becomes available 15

16 Estimate Costs Direct Costs Costs incurred directly by the project Indirect Costs Costs allocated to the project by the organization as a cost of doing business Sunk Cost Costs already expended that cannot be recovered and do not affect decision making Opportunity Costs Benefits not realized as a result of choosing a particular alternative 16

17 Estimate Costs Fixed Costs Costs that do not vary with volume of activity Variable Costs Costs that vary with project duration or volume of activity Marginal Costs Incremental cost of the last unit added (extra order) Expense Cost deducted against income for the current year Capital Costs Not an expense, depreciated over time 17

18 Estimate Costs Life Cycle Costing An estimate of all costs associated with a system/item over its useful life Elements usually included in life cycle costs include: Initial acquisition costs Replacement costs Maintenance costs Operation costs Loan & interest costs Taxes & insurance Income produced 18

19 Estimate Costs - Inputs Scope Baseline Project Schedule Human Resource Plan Risk Register Enterprise Environmental Factors Market conditions Published commercial information Organizational Process Assets Cost estimating policies and templates Historical information Lessons learned 19

20 Estimate Costs Tools & Techniques Expert Judgment Guided by historical information Provides valuable insight about the environment and experiences on similar projects Analogous Estimating Uses actual costs from similar projects as the basis for estimating the cost of the current project (top-down estimate) Parametric Estimating Statistical estimate using the relationship between historical data and other variables (e.g. $/square foot) Bottom Up Estimating Detailed cost estimate derived from the lowest level in the work breakdown structure 20

21 Estimate Costs Tools & Techniques Three-Point Estimates: Weighted average - factors in all potential cost outcomes: PERT: (Optimistic + 4 x Expected + Pessimistic) / 6 Triangular: (Optimistic + Expected + Pessimistic) / 3 Reserve Analysis Estimate of costs required to deal with uncertainty/risks (contingency reserves) Can overstate the cost estimate, should NOT be used at the schedule activity level Cost of Quality All the costs associated with achieving quality standards (costs to prevent non-conformance, appraising/inspecting product or service and in failing to meet requirements) 21

22 Estimate Costs Tools &Techniques Project Management Software Use of software to assist with cost estimating (spreadsheets, simulation, statistical tools, etc.) Vendor Bid Analysis Analysis of what the project should cost versus vendor bid Examines the price of individual deliverables to derive a cost Supports the final total project cost Group Decision Making Techniques Team based approach such as brainstorming or Delphi technique Additional information is gained and can result in more accurate estimates 22

23 Estimate Costs - Outputs Activity Cost Estimates Probable costs required to complete project work Basis of Estimates Includes supporting detail for activity cost estimates Varies by application area Project Document Updates Typically risk register, but not limited to risk register 23

24 Determine Budget PMBOK V5 Ref # Fig

25 Determine Budget PMBOK V5 Ref # Fig

26 Determine Budget Aggregate estimate cost of all work packages to create the cost baseline Used throughout the project to measure project performance Notes: Project Budget Maximum size of the budget is usually imposed Approved estimate for the project (or any WBS component or any schedule activity) Cannot be modified without approval Typically broken down into time periods and category 26

27 Determine Budget - Inputs Activity Cost Estimates Basis of Estimates Scope Baseline Scope statement Work Breakdown Structure WBS dictionary Project Schedule Resource Calendars Contracts Organizational Process Assets 27

28 Determine Budget Tools & Techniques Cost Aggregation Cost estimates are aggregated by WBS Components Assign costs to each work package and/or activity Aggregate costs to higher component levels of WBS (control accounts) Aggregate costs to get a total cost for the project Reserve Analysis Establish contingency reserve 28

29 Determine Budget Tools & Techniques Expert Judgment Historical Relationships Parametric or analogous estimates Funding Limit Reconciliation Compares (reconciles) budgeted costs with the funding limits Adjusts expenditures to smooth or regulate the expenses 29

30 Determine Budget Additional Techniques Forecasting and Financial Analysis Part of initiating processes, used as project selection tool Financial Forecasting Used for decision making Tools: Return on Investment (ROI): o Ratio of annual net profits to capital investment Payback Analysis o Time required for accumulated cash flows to equal zero Net Present Value (NPV) Internal Rate of Return (IRR) 30

31 Determine Budget Return on Investment (ROI) Measures financial change (whether positive or negative) that would result from pursuing a given project. Inflows and outflows evaluated relative to other investment opportunities in terms of: Financial Benefits Revenue introduction of/increases to revenue streams Cost savings reductions in financial obligations Cost avoidance - averting unfavourable costs - e.g. fines, overhead increases Cost protection controlling existing costs. Investment Costs Costs associated with executing the project New steady state expenditures introduced by the project e.g. maintenance obligations, headcount increases Loss of revenue e.g. erosion of market share for firm s other products 31

32 Determine Budget Payback Analysis Simple method Calculation of the number of years to pay back the initial investment Ignores the time value of money Ignores expected cash flows beyond the payback period Choose the project with the shortest payback period By interpolation, payback time is approximately 2.4 years Year Cashflow Cumulative Cash flow

33 Determine Budget Present Value Is a form of Discounted Cash Flow Represents: current value of a future some of money, given a specified rate of return Useful in comparing project investments: by assessing the amount that would need to be invested today, in order to receive x amount at x time in the future For example: For a $100,000 investment, Project A will yield $300,000 - tripling the investment in 5 years, whereas Project B will yield $400,000 quadrupling the investment in 7 years. All other things being equal, which is the better investment? 33

34 Determine Budget Present Value Present Value Formula is PV = FV / (1 + r)y. To determine which project will yield a higher return, we solve for r as r = (FV / PV)1 / Y - 1 Project A will yield a higher return, and is the better investment: Project A Project A s r = (300,000 / 100,000 ) 1 / Y - 1 Project A s r = (3) 1 / 5 1 = (3) Project A s r = = or 24.57% Project B Project B s r = (400,000 / 100,000 ) 1 / Y - 1 Project B s r = (4) 1 / 7 1 = (4) Project B s r = = or 21.90% 34

35 Determine Budget Net Present Value (NPV) Also called Discounted Cash Flow The difference between: Present value of the benefits Present value of the costs The benefit and cost cash flows are discounted by the required rate of return (also known as the hurdle rate) Positive result is favorable Negative result is undesirable Choose the project alternative with the highest net present value GO No GO 35

36 Determine Budget Internal Rate of Return (IRR) The rate of return that makes NPV = 0 Equates Present Value of expected benefit to Present Value of expected costs Value is found by trial and error, spreadsheet function, etc. IRR > Cost of Capital is acceptable, IRR < Cost of Capital is unacceptable When comparing investment opportunities, choose highest IRR that is above the Cost of Capital IRR will be between 20% and 25% for NPV to be 0 IRR found to be % 36

37 Determine Budget Depreciation The process of allocating the cost of an asset to the periods of benefit Four step process: Determine value of asset Estimate expected useful life (# of years) Estimate salvage value (at the end of its expected useful life) Evaluate the dollar value of the asset expected to be used up per year: 1. Straight-line depreciation (SLD) 2. Sum of the years digits (SYD) 3. Double declining balance (DDB) 4. Units of production 37

38 Determine Budget Straight Line Depreciation Reduce value of asset by an identical amount per period, over its expected useful life. Account for Residual Value - subtract the Residual Value from Original Cost, before determining the amount to be deducted per period. Derived as: (Original Cost Residual Value) / Useful Life For example: the following calculations show depreciation for a $500,000 asset with and without a residual value. 38

39 Determine Budget Straight Line Depreciation Straight-Line Depreciation Original cost Residual value Net cost Life Depreciation per year Straight-Line Depreciation (w/ salvage value) $ $ $ 500, , ,000 $ Original cost Residual value Net cost Life Depreciation per year Straight-Line Depreciation Year $ $ $ $ $ Beginning NBV 500, , , , ,000 Depreciation for Year $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 500,000 $ $ $ $ $ Ending NBV 400, , , ,000 - $ 500,000 $ 100,000 $ 400,000 5 $ 80,000 Straight-Line Depreciation Year $ $ $ $ $ Beginning NBV 500, , , , ,000 $ $ $ $ $ $ Depreciation for Year 80,000 80,000 80,000 80,000 80, ,000 Ending NBV $ 420,000 $ 340,000 $ 260,000 $ 180,000 $ 100,000 In this case, depreciation stops at the expected residual value of the asset 39

40 Determine Budget Sum of the Years Digits Type of accelerated depreciation Three step process: 1. Sum the digits of the number of years over which the asset is to be depreciated 2. Establish the depreciation factors Numerator = reverse order of the years Denominator = sum of the years digits (step 1) 3. Calculate each year s depreciation expense by multiplying the appropriate depreciation factor by the original cost of the asset 40

41 Determine Budget Sum of the Years Digits Cost of Fixed Asset = $8,000 Salvage Value = $0 Expected Useful Life = 5 years Sum of the Years = ( ) = 15 Year Depreciation Factor Asset Cost Annual Depreciation 1 5/15 $8,000 $2, /15 $8,000 $2, /15 $8,000 $1, /15 $8,000 $1, /15 $8,000 $533 41

42 Determine Budget Double Declining Depreciation Type of accelerated depreciation Depreciation rate is up to double the straight line depreciation rate Depreciation rate is applied to the declining balance or book value, not the depreciable balance Annual Depreciation = Depreciation Rate * Book Value at beginning of year Cannot write-off more total depreciation than the original cost 42

43 Determine Budget Double Declining Depreciation Example: Cost of the asset = $10,000 Salvage value = $2,000 Depreciable balance = $8,000 Expected useful life = 5 years Straight line depreciation rate = 1/5 * 100 = 20% Year Depreciation Factor Declining Balance (Book Value) Annual Depreciation 1 40% $10,000 $4, % $6,000 $2, % $3,600 $1, % $2,160 $160* 5 40% * Cannot write off more than the depreciable balance $2,000 $0 43

44 Determine Budget Units of Production Cost of the asset is allocated according to the number of units the capital asset is expected to produce Example: Original cost of a truck = $25,000 Expected total usage = 100,000 miles Cost per mile = $25,000 / 100,000 = $0.25 Expected useful life = 5 years Number of miles per year = 20,000 Depreciable expense = 20,000 * 0.25 = $5,000 per year 44

45 Determine Budget - Outputs Cost Performance Baseline Approved version of the time-phased budget excluding management reserves Large projects can have multiple cost baselines (e.g. each phase) PMBOK V5 Ref # Fig

46 Determine Budget - Outputs PMBOK V5 Ref # Fig

47 Determine Budget - Outputs Cost Performance Baseline Approved version of the time-phased budget excluding management reserves Project Funding Requirements Determined from the cost baseline Establish total and periodic cost objectives Total funds required include: Cost baseline Management reserves (due to risks) Project Document Updates 47

48 Control Costs PMBOK V5 Ref # Fig 7-10 PMBOK Ref # Fig

49 Control Costs PMBOK V5 Ref # Fig

50 Control Costs Influences factors that create changes to cost baseline Monitors cost performance to detect variances from the plan Ensures that all changes are recorded accurately in the cost baseline Prevents incorrect, inappropriate or unauthorized changes Informs appropriate stakeholders of authorized changes 50

51 Control Costs Accounts: Control Accounts Control point where measurement of control will occur Placed at specific component at selected levels of the WBS Chart of Accounts Numbering system used to monitor project costs Usually based upon corporate chart of accounts 51

52 Control Costs - Inputs Project Management Plan Cost performance baseline Cost management plan Project Funding Requirements Work Performance Data Organizational Process Assets 52

53 Control Costs Tools & Techniques Earned Value Management Forecasting To-Complete Performance Index (TCPI) Performance Reviews Variance Analysis Project Management Software 53

54 Control Costs Earned Value Management Earned Value Management Commonly used performance measurement method Forecasting Project s future state based on present data To-Complete Performance Index (TCPI) Cost performance that must be achieved on the remaining work to meet specified management goal Performance Reviews Variance Analysis Project Management Software 54

55 Control Costs Earned Value Management Earned value management assesses project performance by integrating scope, cost and schedule measures. Cost and schedule variance alone do not provide a complete measure of performance Benefits Early warning management tool Examines actual accomplishment Compares what was done with what was planned Uses work in progress to predict future outcomes Forecast completion date and cost 55

56 Control Costs Earned Value Management PMBOK V5 Ref # Fig

57 Control Costs Earned Value Management Planned Value (PV): Budgeted Cost of Work Scheduled Earned Value (EV): Budgeted Cost of Actual Work Performed Actual Cost (AC): Actual Cost of Actual Work Performed Schedule Variance (SV): SV = EV - PV Schedule Performance Index (SPI): SPI = EV / PV Cost Variance (CV): CV = EV - AC Cost Performance Index (CPI): CPI = EV / AC 57

58 Control Costs Earned Value Management Earned Value (EV): Budget x % Complete Methods of determining % Completed: Milestones (30, 70, 90, 100%) Detailed Evaluation Expert Judgment 58

59 Control Costs Forecasting Estimate based on information and knowledge available now Allows prediction of future costs or completion dates Is a form of trend analysis PMBOK V5 Ref # Fig

60 Control Costs Forecasting BAC - Budget at completion EAC Estimate at completion Remaining work performed at budget rate EAC = AC + BAC EV Use when variances are atypical Remaining work performed at current CPI EAC = AC + [(BAC-EV)/CPI] or EAC = BAC / CPI Use when variances are typical 60

61 Control Costs Forecasting - cont d EAC Estimate at completion Remaining work performed considers CPI & SPI EAC = AC + [(BAC-EV)/(Cumulative CPI * Cumulative SPI] ETC - Estimate to Complete ETC = EAC - AC VAC - Variance at Completion VAC = BAC - EAC 61

62 Control Costs To-Complete Performance Index Calculated projection of cost performance on remaining work to meet the specified BAC or EAC TCPI = (BAC - EV) / (BAC - AC) Based on BAC TCPI = (BAC EV ) / (EAC AC) Based on EAC Refer to Table 7-1: Earned Value Calculations Summary Table PMBOK Page

63 Control Costs To-Complete Performance Index PMBOK V5 Ref # Fig

64 Control Costs Examples For each activity: Calculate Cost Variance (CV) Calculate Schedule Variance (SV) For the project: Calculate Cost Variance (CV) Calculate Schedule Variance (SV) Calculate Estimate At Completion (EAC) Calculate TCPI (BAC) and TCPI (EAC) 64

65 Control Costs 65

66 Control Costs CV SV 66

67 Control Costs 67

68 Control Costs Example EV Problem The project: 5 software package installs on 5 existing PCs in 5 weeks for a total consulting fee of $5,000. After two weeks only 1 install has been done for a cost of $1,500. Plot PV, AC & EV Calculate SV, CV, SPI & CPI Assume the rate of progress continues and calculate EAC and forecast the completion time 68

69 Control Costs Example EV Problem Budget at Completion (BAC) = $5,000 Actual Cost (AC) = $1,500 Earned Value (EV) = $1,000 Planned Value (PV) = $2,000 Schedule Variance (SV) = EV PV = -$1,000 Cost Variance (CV) = EV AC = -$500 69

70 Control Costs Example EV Problem Schedule Performance Index (SPI) = EV / PV = 1000/2000 = 0.5 Cost Performance Index (CPI) = EV / AC = 1000/1500 = Estimate at Completion (EAC) = BAC / CPI = 5000/ = $7,500 Forecast Completion Time = Original Schedule / SPI = 5 weeks / 0.5 = 10 Weeks 70

71 Control Costs Performance Reviews Variance Analysis Compares actual to planned performance Trend Analysis Examines performance over time Determines if performance is improving or deteriorating Earned Value Performance Compares baseline plan to actual schedule and cost performance 71

72 Control Costs Variance Analysis Assesses magnitude and cause of variations to original cost baseline Use CV & CPI Allows decision on whether corrective or preventive action is required Variances tend to decrease as project progresses and more work is accomplished 72

73 Control Costs - Outputs Work Performance Measurements Cost Forecasts Organizational Process Assets Updates Change Requests Project Management Plan Updates Cost performance baseline Cost management plan Project Document Updates Cost estimates Basis of estimates Organization Process Assets Updates 73

74 PMP Exam Preparation Sample Questions Chapter 7 Project Cost Management 74

75 Question #1 The output from Plan Cost Management includes: A. Activity cost estimates B. Cost performance baseline C. Cost management plan D. Work breakdown structure Answer: 75

76 Question #2 As a project manager, you examine project results over time to determine how the project is performing. This can be done through: A.Performance Reviews B.Variance Analysis C.Trend Analysis D.Earned Value Analysis Answer: 76

77 Question #3 You have recently taken over a project when the previous project manager resigned. While studying the project information, you find out that cost variances are very severe. To provide realistic basis for performance measurement, you should recommend: A.Authorizing a budget update B.Revising the cost baseline C.Submitting a corrective action for sponsor approval D.Closing the project Answer: 77

78 Question #4 In your construction project, the CPI is 0.85 and SPI is What could be the potential reason: A.A critical resource went on sick leave for a long period of time, which had not been anticipated earlier. B.The cost of raw materials required for construction increased 10% - you had anticipated a cost increase of 12% in your project plans. C.Anticipating delays, the project had to be crashed to decrease duration. D.There was a 4 days waiting time in the curing of the cement, and work could not be done during that time. Answer: 78

79 Question #5 Your project has 4 tasks A-B-C-D performed one after the other, all on the critical path. All tasks are estimated to require a similar effort of 5 days and cost $5,000 each to accomplish. We are at the end of day 11. Tasks A and B have been completed while task C is only 50% complete. A total of $13,000 has already been spent. What is the Earned Value (EV)? A.$5,000 B.$10,000 C.$11,000 D.$12,500 Answer: 79

80 Question #6 If a project is to employ three people each for 40 hours at a labor rate of $40 per hour with overhead included and a fourth person for 30 hours during the same period, but at a loaded labor rate of $60 per hour, the Planned Value (PV) for the week is: A.$1,800 B.$6,600 C.$4,800 D.$5,600 Answer: 80

81 Question #7 If cost variance is negative, but schedule variance is positive, then this indicates: A.Cost and schedule are not dependent on each other B.The project is under budget and behind schedule C.The project is over budget and ahead of schedule D.Crashing may be recommended to make the cost variance positive Answer: 81

82 Question #8 While reviewing project performance, the project manager determines that the schedule variance is $500. What is the BEST thing to do: A.Let the sponsor know B.Determine the cost variance C.Look for activities that can be done in parallel D.Move resources from the project to the one that is not failing Answer: 82

83 Question #9 Your project has 3 tasks A-B-C performed one after the other. Task A is worth $500, is 80% complete, and actually cost $500. Task B is worth $450, is 75% complete, and actually cost $402 so far. Task C is worth $600, is 90% complete, and has cost $550 so far. The total budget is $3,000. What is the cost variance for this project? A.-$ B.$ C.$0.84 D.$ Answer: 83

84 Question #10 In your construction project, the CPI is 1.30 and SPI is What could be the potential reason? A.A critical resource went on sick leave for a long period of time, which had not been anticipated earlier B.The cost of raw materials required for construction increased 10% C.You did not take into account inflation rate which increased this year D.There was 4 days waiting time in the curing of cement, and work could not be done during that time Answer: 84

85 Question #11 Which of the following formulas shows the remaining amount to be spent on the project based on current spending efficiency? A.BAC/CPI B.EV-PV C.EAC-AC D.EV-AC Answer: 85

86 Question #12 In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the Estimate at Completion for your project if BAC = $300,000, AC = $100,000, EV=$150,000, CPI=1.2, and ETC=$120,000? A.$250,000 B.$220,000 C.$280,000 D.$300,000 Answer: 86

87 Question #13 Your project has 3-tasks A-B-C performed one after the other. Task A is worth $500, is 80% complete, and actually cost $500, Task B is worth $450, is 75% complete, and actually cost $402 so far. Task C is worth $600, is 90% complete, and has cost $550 so far. The total budget is $3,000. What is the estimate at completion for the tasks listed? A.$3, B.$1, C.$3, D.$ Answer: 87

88 Question #14 As a project manager, you examine project results over time to determine how a project is performing. This can be done through: A.Performance Reviews B.Variance Analysis C.Trend Analysis D.Earned Value Analysis Answer: 88

89 Question #15 The project team is planning an upgrade to a client s movie production studio. During planning, the team members discover that the lab where editing processes are to reside will not have sufficient space, forcing the client to lease another building. This building will also be shared with another department. What type of Cost would this be? A.Direct B.Indirect C.Variable D.Indirect Fixed Answer: 89

90 Question #16 You estimate that your project has an earned value of $80,000. Your budget at completion is $150,000. Your project accountant reports actual costs at this point to be around $95,000, while the planned value is reported by your software to be at $100,000. The last time you estimated the costs at project completion you obtained $155,000. What is the To-Complete Performance Index(TCPI) for your project: A.1.17 B.1.27 C D Answer: 90

91 Question #17 Budget forecasts, such as calculated EAC, are an output of which of the following processes? A.Estimate Costs B.Determine Budget C.Control Costs D.Control Schedule Answer: 91

92 Question #18 Which of the following tools/techniques is used in the Control Costs process? A.Analogous Estimated B.Forecasting C.Parametric Estimating D.Bottom-up Estimating Answer: 92

93 Question #19 The assumptions made during cost estimation and the constraints that would apply to those estimates can be found in: A.Activity Cost Estimates B.Basis of Estimates C.Cost Performance Baseline D.Project Funding Requirements Answer: 93

94 Question #20 An estimate that is -25% to +75% of actual is considered a(n): A.Budget estimate B.Order of magnitude estimate C.Definitive estimate D.Parametric estimate Answer: 94

95 PMP Exam Preparation End of Session Chapter 7 Project Cost Management 95

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Achieve PMP Exam Success Five-Day Course Syllabus

Achieve PMP Exam Success Five-Day Course Syllabus Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course

More information

Five-Day Schedule and Course Content

Five-Day Schedule and Course Content Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

COPYRIGHTED MATERIAL. Index

COPYRIGHTED MATERIAL. Index Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

next level PMP Exam Preparation Formula Guide for the PMP Exam

next level PMP Exam Preparation Formula Guide for the PMP Exam next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions

More information

LCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP

LCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP PMP Review Chapter 5 Developing Project Budgets Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:

More information

PMI PMI-SP. PMI Scheduling Professional. Download Full Version :

PMI PMI-SP. PMI Scheduling Professional. Download Full Version : PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

A Practical Way To Learn About EVM. ***The Deck Project***

A Practical Way To Learn About EVM. ***The Deck Project*** A Practical Way To Learn About EVM ***The Deck Project*** Back to the Baseline 2 The Deck Project The product of this project is a new second-story deck in the backyard. This new deck will replace an existing

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT Planning DETERMINE BUDGET PROCESSES BY PROCESS GROUP Monitoring and Controlling 7.1 Plan Costs Management 7.4 Control Costs 7.2 Estimate Costs 7.3 Determine Budget DETERMINE BUDGET

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Project Management: Cost

Project Management: Cost Project Management: Cost Cost Management the processes required to ensure that a project is completed within the approved budget Estimating cost of resources Forecasting: quantity when they are required

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

Project Integration Management

Project Integration Management Project Integration Management The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all of the other knowledge areas throughout a project s life cycle.

More information

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

Project Management CSC 310 Spring 2017 Howard Rosenthal

Project Management CSC 310 Spring 2017 Howard Rosenthal Project CSC 310 Spring 2017 Howard Rosenthal 1 No?ce This course is based on and includes material from the text: Effective Project - Traditional, Agile, Extreme 7TH Edition Authors: Robert K. Wysocki

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

Project Management. A Practitioner s Guide. Steven M. Bragg

Project Management. A Practitioner s Guide. Steven M. Bragg Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project

More information

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP

Cost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that

More information

Project Management. Session 5 Budgets and Estimation Andre Samuel

Project Management. Session 5 Budgets and Estimation Andre Samuel Project Management Session 5 Budgets and Estimation Andre Samuel This Session Budgets and Estimation Estimation Principles Estimation Techniques Cost Estimating Estimation Principles Prediction of project

More information

Braindumps.PMI-SP.323 questions

Braindumps.PMI-SP.323 questions Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

Chapter 7: Project Cost Management. IT Project Management, Third Edition Chapter 7

Chapter 7: Project Cost Management. IT Project Management, Third Edition Chapter 7 Chapter 7: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Project Management Certification. Multiple Choice Questions

Project Management Certification. Multiple Choice Questions Project Management Certification (PMP) Project Management Certification (PMP) Multiple Choice Questions QUESTION 1 In Project Cost Management, which input is exclusive to the Determine Budget process?

More information

CPM (College of Performance Management) Meetings have focused on this topic in the last year

CPM (College of Performance Management) Meetings have focused on this topic in the last year June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches

More information

Exam Questions PMI-SP

Exam Questions PMI-SP Exam Questions PMI-SP PMI Scheduling Professional Practice Test https://www.2passeasy.com/dumps/pmi-sp/ 1.CORRECT TEXT Fill in the blank with the appropriate word. When activities are logically linked,

More information

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project

More information

Review of Financial Analysis Terms

Review of Financial Analysis Terms Review of Financial Analysis Terms Financial Analysis Requirements Economic Evaluation of Potential TUR Techniques (310 CMR 50.46A) The TUR plan must include the discount rate, cost of capital, depreciation

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

IT Certification Exams Provider! Weofferfreeupdateserviceforoneyear! h ps://

IT Certification Exams Provider! Weofferfreeupdateserviceforoneyear! h ps:// IT Certification Exams Provider! Weofferfreeupdateserviceforoneyear! h ps://www.certqueen.com Exam: PMI-002 Title : Certified Associate in Project Management (CAPM) Certification Version : DEMO 1 / 7 1.A

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

PMI - Dallas Chapter. PMP Exam Sample Questions

PMI - Dallas Chapter. PMP Exam Sample Questions PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

Application of Earned Value Analysis in Analysing Project Performance

Application of Earned Value Analysis in Analysing Project Performance Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant

More information

Value And Earned Schedule Management

Value And Earned Schedule Management EVM World 2013 Conference IPMC 2013 Title: An Analytical Utility For Earned Value And Earned Schedule Management Gary L. Richardson and Saranya Lakshmikanthan May 29, 2013 The popular technical literature

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

Glossary of Budgeting and Planning Terms

Glossary of Budgeting and Planning Terms Budgeting Basics and Beyond, Third Edition By Jae K. Shim and Joel G. Siegel Copyright 2009 by John Wiley & Sons, Inc.. Glossary of Budgeting and Planning Terms Active Financial Planning Software Budgeting

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers 1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

Estimating Cost-To-Go Without Stable EVM Data

Estimating Cost-To-Go Without Stable EVM Data PR-158 Estimating Cost-To-Go Without Stable EVM Data Peter C. Frederic, Tecolote Research Inc. Ronald K. Larson, NASA 20 March 2013 2013 Professional Development & Training Workshop New Orleans, LA June

More information

PASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year

PASS4TEST. IT Certification Guaranteed, The Easy Way!  We offer free update service for one year PASS4TEST IT Certification Guaranteed, The Easy Way! \ We offer free update service for one year Exam : PMI-SP Title : PMI Scheduling Professional Vendors : PMI Version : DEMO Get Latest & Valid PMI-SP

More information

Performance Based Management at Raytheon Aircraft Company. Joe Kusick Raytheon Aircraft Company EVMS Manager May 18, 1998

Performance Based Management at Raytheon Aircraft Company. Joe Kusick Raytheon Aircraft Company EVMS Manager May 18, 1998 Performance Based Management at Raytheon Aircraft Company Joe Kusick Raytheon Aircraft Company EVMS Manager May 18, 1998 Raytheon Aircraft Policy for Performance Based Management EVMS is a Tool for Performance

More information

The Project Times and Costs

The Project Times and Costs The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

Investment Decision Criteria. Principles Applied in This Chapter. Disney s Capital Budgeting Decision

Investment Decision Criteria. Principles Applied in This Chapter. Disney s Capital Budgeting Decision Investment Decision Criteria Chapter 11 1 Principles Applied in This Chapter Principle 1: Money Has a Time Value. Principle 2: There is a Risk-Return Tradeoff. Principle 3: Cash Flows Are the Source of

More information

A Layman s Guide to Earned Value

A Layman s Guide to Earned Value A Layman s Guide to Earned Value A TenStep White Paper Contact us at info@tenstep.com TenStep, Inc. 2363 St. Davids Square Kennesaw, GA. 30152 877.536.8434 770.795.9097 If you are a project manager, you

More information

Earned Schedule schedule performance

Earned Schedule schedule performance Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

A Case for Project Revenue Management. Peter Varani PMP

A Case for Project Revenue Management. Peter Varani PMP A Case for Project Revenue Management Peter Varani PMP A Case for Project Revenue Management PMBOK GUIDE (4 th edition) Cost 845 Revenue 3 Unisys Annual Report (2008) Cost 174 Revenue 152 2 Balanced Approach

More information