A Practical Way To Learn About EVM. ***The Deck Project***

Size: px
Start display at page:

Download "A Practical Way To Learn About EVM. ***The Deck Project***"

Transcription

1 A Practical Way To Learn About EVM ***The Deck Project***

2 Back to the Baseline 2

3 The Deck Project The product of this project is a new second-story deck in the backyard. This new deck will replace an existing deck, stand about 10 feet off the ground, and measure 12 feet by 12 feet square. On one side, a set of stairs will lead to the ground. The structure will be attached to the house and supported with four posts resting on concrete footings. Due to city ordinances, the footings must extend below 4 feet. The homeowner and friends (when available) will construct the deck with standard materials. All supplies will be ordered from and delivered by the local home improvement center. 3

4 Schedule Baseline #1 Activity Planned Value Planned Scheduled Finish (Effort-Hours) Duration (Days) (Day) Draw plans and material lists 6 1 Day 1 Destroy old deck 12 1 Day 2 Truck off trash Day 3 Purchase materials Day 3 Dig four footing holes 8 2 Day 5 Pour concrete footings 4 1 Day 6 Construct main deck 12 3 Day 9 Constuct railings and stairs 8 2 Day 11 Clean-up 6 1 Day 12 Actual Costs (Effort-Hours) Status (Done/Started) Earned Value (Effort-Hours) Totals:

5 The Project Schedule 5

6 For our deck project, the total duration is 12 days with 64 hours of total effort. Figure 2 shows the effort hours by day (as bars) and the cumulative effort hours (as a line). The height of the line on Day 12 is 64 hours, which corresponds to our total cost. 6

7 It s Day 5, So What s The Problem? # Activity Planned Value (Effort-Hours) Planned Duration (Days) Scheduled Finish (Day) Actual Costs (Effort-Hours) Status (Done/Started) Earned Value (Effort-Hours) 1 Draw plans and material lists 6 1 Day 1 6 Done 6 2 Destroy old deck 12 1 Day 2 12 Done 12 3 Truck off trash Day 3 4 Done 4 4 Purchase materials Day 3 4 Done 4 5 Dig four footing holes 8 2 Day 5 10 Started 0 Total-To-Date Pour concrete footings 4 1 Day 6 7 Construct main deck 12 3 Day 9 8 Constuct railings and stairs 8 2 Day 11 9 Clean-up 6 1 Day 12 Totals:

8 Summary According to the schedule, we had planned to expend 34 hours of effort on the project (the sum of the planned cost for the first five activities). Those 34 hours were to complete the first five activities. However, based on actual results, we have expended 36 hours and completed the first four activities. Activity 5, Dig footings, has started, but is not yet finished and it is running over plan (the planned effort was 8 hours, recorded actuals show 10 hours so far). And since the digging is not done, we can t take any credit for Earned Value on the activity. 8

9 So what s the status? At the end of Day 5, we planned to accomplish 34 hours of work We ve expended 36 hours, yet we ve only earned 26 hours Planned Value (Cumulative) = 34 Hours Actual Costs (Cumulative) = 36 Hours Earned Value (Cumulative) = 26 Hours 9

10 Calculate CPI & SPI Group Exercise How would you explain these indexes from the perspective of this project What would the graph of this project look like? Draw a high-level graph What does this graph tell us? 10

11 Calculating EVA CPI = 26/36 = 0.72 SPI = 26/34 = 0.76 Based on our CPI, we are realizing 7.2 hours of result for every 10 hours of actual effort expended on our project. Based on our SPI, we are realizing 7.6 hours of result for every 10 hours of planned effort on our project. 11

12 2.00 Cost Performance Index (CPI) Day Schedule Performance Performance Index (SPI) 12

13 Planned Value, Actual Cost & Earned Value vs. Project Duration Through Day 5 13

14 What the graph tell us By comparing the Actual Cost line to the Planned Value line, we can see that, through Day 3 of the project, actual costs were according to plan. But on Day 4, the red jumps above the blue, showing that we ve gone over plan. Also, because no work was marked Done on Days 4 or 5, the Earned Value (green line) levels off. The gap between Actual Cost, Planned Value, and Earned Value clearly indicates project problems. 14

15 Group/Homework Exercise What is the EAC of this project? Hint: What s the assumption of the CPI at this point? Can your figure out what the new forecasted end date will be? Hint: What s the Duration at Completion [DAC]? The PMBOK forgets that EAC calculates the vertical axis, but needs an additional EAC[t] (t = time ) calculation for the horizontal axis What would the graph look like? 15

16 EAC[t]: Estimated Time At Completion In order to calculate the EAC[t], we need to add additional variables to our EVM collection: Planned Duration (PD) - The planned duration at a given status period Actual Duration (AD) The actual duration expended Earned Duration (ED) The duration earned Duration At Complete (DAC) The sum of all authorized durations allocated to the project 16

17 EAC[t] Details The EAC[t] equals the actual durations incurred, plus the estimated durations for completing all the remaining project work. The use of a particular EAC[t] should be exactly the same as the conditions for the EAC, with the exception of the assumption of the SPI, rather than the CPI, remaining constant throughout the project. Outlined in the Practice Standard for Earned Value Management published by PMI in 2005, the SPI and using what they refer to as the average PV per unit of time can be used to provide a rough estimate of when the project will complete or if the project s performance trend stays fairly constant, what the forecast end date could be. 17

18 EAC[t] Details Cont d The equation is as follows (*Note: PMI uses PD for planned duration instead of DAC. I feel that DAC is more accurate counterpart to BAC): This can equation can be simplified to: Therefore, the most likely EAC[t] is DAC SPI which is the direct counter part to formula #3 of EAC which is BAC CPI. 18

19 Where are we headed? If these ratios are accurate, we can use them to forecast completion of the project. To forecast the estimate at completion (EAC), divide the original cost by the CPI, with the assumption that the variance should stay the same. For our project, EAC = 64 / 0.72 = 88.6 or 89 hours. The estimate at completion for time (EAC[t]) is the original duration divided by the SPI. Again, for our project, the EAC[t] = DAC/SPI = 12 / 0.76 = 15.7 or 16 days (see next graph). 19

20 Forecast of Project EAC & EAC[t] 20

21 What s the implications of the data? What s happening? So after five days of work on the project, it looks like we ve added about 4 days to the schedule and 25 hours of work to the budget. Is the project really that far off track? (CPI and SPI are conservative forecasting tools each assumes that past performance is an indicator of future results.) After a review and discussion of the project s performance, our key stakeholders discovered that the original estimates for digging were based on favorable soil conditions. For three of the four holes, this was a valid assumption. However, the diggers uncovered a large boulder (more than 500 lbs) on the fourth hole. 21

22 Group Exercise Why did we only choose the EAC calculation of EAC = BAC/CPI (64/0.72)? What other EAC calculations could we have used and why? What would the graph look like if we plotted all of the scenarios and how would you present this? Hint: think of the three-option rule (Arco gas demo) What other forecasting equation would be useful to use and why? Hint: What about TCPI? What would the graph for TCPI look like? 22

23 Additional Analysis The PMBOK lists four types of EAC calculations The formula EAC = AC + Bottom-up ETC is the most accurate, but would require you to manually rebuild the work package estimates from the ground up. Who has that time! We therefore have three other EAC equations we can utilize, but why would we use them and not the one we already calculated? 23

24 Statistical EAC Comparisons Low-end over-run to date The optimistic or best case EAC = AC + BAC EV = 74 Middle range EAC The most likely case EAC = BAC/CPI 64/0.72 = 89 High-end range EAC The pessimistic or worst case EAC = AC + [(BAC EV)/(CPI x SPI)] 36 + ((64 26)/(0.72 x 0.76)) =

25 Statistical EAC[t] Comparisons (Time) Low-end over-run to date The optimistic or best case EAC[t] = AD + DAC ED = 13 Middle range EAC The most likely case EAC[t] = DAC/SPI 12/0.76 = 15.7 High-end range EAC The pessimistic or worst case EAC[t] = AD + [(DAC ED)/(CPI x SPI)] 5 + ((12 4)/(0.72 x 0.76)) = 20 25

26 Graph with three point EACs EAC = AC + [(BAC EV)/(CPI x SPI)] EAC = BAC/CPI EAC = AC + BAC EV 26

27 27

28 What about TCPI? The To Complete Performance Index (TCPI) provides the performance the CPI must maintain in order to get back to 1.0 at a particular status date At our current status day, we are more concerned with the question of is the BAC achievable? rather than is the current EAC realistic and achievable? So we use TCPI[p] = (BAC EV)/(BAC AC) or (64 26)/(64 36) = 1.36 In other words, given where we are at, we would need to maintain a CPI of 1.36 to get back to

29 Graph of TCPI[p] Sunk Costs Opportunity Costs TCPI[p] 1.00 Baseline - CPI 0.72 Day 5 Day 12 29

30 Graph of TCPI[p] & TCPI[e] Sunk Costs Opportunity Costs (CPI) TCPI[p] otcpi[e] mtcpi[e] ptcpi[e] Day 5 Day 12 30

31 What about TCPI[t]? Just as there is a counterpart to EAC with EAC[t] for time, we can compute the TCPI[t] for the horizontal axis: TCPI[t][p] = (DAC-ED) (DAC-AD) TCPI[t][e] = (DAC-ED) (EAC[t]-AD) At our current status day, we are more concerned with the question of is the DAC achievable? rather than is the current EAC[t] realistic and achievable? So we use TCPI[t][p] = (DAC ED)/(DAC AD) or (12 4)/(12 5) = 1.14 In other words, given where we are at, we would need to maintain a SPI of 1.14 to get back to

32 Graph of TCPI[t][p] Sunk Time Opportunity Time TCPI[t][p] SPI 0.76 Day 5 Day 12 Baseline 32

33 Graph of TCPI[t][p] & TCPI[t][e] Sunk Time Opportunity Time TCPI[t][p] otcpi[t][e] mtcpi[t][e] ptcpi[t][e] 0.76 (SPI) Day 5 Day 12 33

34 Group Exercise What corrective actions would you take to get the project back on track? Use the grid on the following slide to outline the possible corrective actions you would take based on product features and performance (scope), schedule and cost Hints: Re-evaluate how you would re-scope the digging of the 4 holes to get the project back on track How does this effect the CPI & SPI Does this have any effect on the EAC and the overall duration of the project? 34

35 Possible Corrective Action for the Deck Project 35

36 Possible Corrective Action for the Deck Project 36

37 Strategies to dig out way out So our project is not quite as badly off as the numbers suggest. Three of the four holes are complete, and the fourth hole would be done if not for the boulder. If we informally apply a % complete evaluation to our project, we earn 75% of the hole digging activity. This increases our Earned Value to 32 hours, and our CPI and SPI to 0.89 and 0.94 respectively. If we re-compute the EAC and schedule, our EAC forecast improves from 88 to 72 hours and we shorten our schedule estimate from 15.7 days to 12.7 days. This information will help us decide on what corrective action to take. 37

38 Re-baseline the project! After some discussion, the stakeholders decided that the key constraint is the product s features and performance. They chose to remove the bolder and place the footing where originally planned, satisfying all building codes. However, since this choice adds work to the project, the plan must be adjusted. Removing the rock involved manually excavating around it, dragging it out of the hole, and restoring the earth displaced by the rock. In total, an additional eight hours of effort and one day of schedule need to be added. 38

39 # Activity Planned Value (Effort-Hours) Planned Duration (Days) Scheduled Finish (Day) Actual Costs (Effort-Hours) Status (Done/Started) Earned Value (Effort-Hours) 1 Draw plans and material lists 6 1 Day 1 6 Done 6 2 Destroy old deck 12 1 Day 2 12 Done 12 3 Truck off trash Day 3 4 Done 4 4 Purchase materials Day 3 4 Done 4 5 Dig three footing holes 8 2 Day 5 10 Started 8 6 Remove bolder and dig footing hole 8 1 Day 6 7 Pour concrete footings 4 1 Day 7 (6) 8 Construct main deck 12 3 Day 10 (9) 9 Constuct railings and stairs 8 2 Day 12 (11) 10 Clean-up 6 1 Day 12 (13) Totals: Re-baselining the project and updating the plan reflects the added task Remove boulder. No other project activities have been changed. Also, the activity Dig footings was marked Done and the value of that work counted as Earned. 39

40 Group Exercise What would be the new baseline results? What would the new graph look like? 40

41 New baseline results The effect of the re-baseline can be evaluated quickly with CPI, SPI, and their related projections. At the end of Day 5, we have a new CPI = 34/36 = 0.94 and the new SPI = 34/34 = 1.0. The new EAC = 72/0.94 = 77 hours. The projected duration is the same as the re-baselined plan, or 13/1.0 = 13. The project is still forecasted to exceed the new budget (because CPI is less than 1.0), due to two hours of rock removal on Day 5 (two hours against the eight hours added during the re-baseline). We expect that after Day 6, CPI productivity will climb back to 1.0. Re-baselining is only legitimate when it is performed in response to a stakeholder- approved scope change. 41

42 Original Baseline and Re-Baselined Planned Value 42

43 2.00 Cost Performance Index (CPI) Day 5 Day 5 (New) Schedule Performance Performance Index (SPI) 43

44 44

45 Probabilistic EVM Modeling! 45

46 Questions? 46

An Earned Value Tutorial

An Earned Value Tutorial 500 Thoreau Street Concord, MA 01742 USA +978.369.9009 info@newleafpm.com When you are ready to earn your PDUS: Please return to www.newleafpm.com Click on the White Papers tab. Select White Paper Power

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

Project Management -- Monitoring the progress

Project Management -- Monitoring the progress Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

CPM (College of Performance Management) Meetings have focused on this topic in the last year

CPM (College of Performance Management) Meetings have focused on this topic in the last year June 13, 2016 1 PMI - (PMI-ACP Exam tests using EVM with Agile) PMI: EVM should be used on all projects, in all industries, no matter how simple or complex Federal Government is asking for the two approaches

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project. Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

CAPM Exam Prep.

CAPM Exam Prep. CAPM Exam Prep (What it really takes to prepare and pass) An ebook by Project Road Training, LLC www.project-road.com Bill Baxter Version 6-1 Project Road Training, LLC has been reviewed and approved as

More information

PMP Exam Preparation Workshop Chapter 7 Project Cost Management

PMP Exam Preparation Workshop Chapter 7 Project Cost Management PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost

More information

Earned Schedule schedule performance

Earned Schedule schedule performance Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

next level PMP Exam Preparation Formula Guide for the PMP Exam

next level PMP Exam Preparation Formula Guide for the PMP Exam next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

Braindumps.PMI-SP.323 questions

Braindumps.PMI-SP.323 questions Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

Project Assessment Exercise

Project Assessment Exercise Project Assessment Exercise www.spmbook.com We have been assigned the task of assessing the project status of a project, whose Gantt chart is presented in Illustration 1, where: 1. we are currently at

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

Earned Schedule Analysis

Earned Schedule Analysis Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

PMI Long Island Chapter s Tools and Techniques Series PM101

PMI Long Island Chapter s Tools and Techniques Series PM101 PMI Long Island Chapter s Tools and Techniques Series PM101 Project Metrics & KPIs Agenda Overview Why Metrics and KPIs important Source of Metrics and KPIs Common PM Metrics and KPIs Other PM Metrics

More information

Long Description. Figure 15-1: Contract Status. Page 1 of 7

Long Description. Figure 15-1: Contract Status. Page 1 of 7 Page 1 of 7 Figure 15-1: Contract Status A single performance report provides the status of the Program at a point in time. When combined with previous reports, a much more revealing picture of the Program

More information

30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering. sete2018.com.au BRETT THIELE

30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering. sete2018.com.au BRETT THIELE 30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering BRETT THIELE A Standardised Data Set to Support Research on Earned Value and Earned Schedule Management Techniques Motivation

More information

Application of Earned Value Analysis in Analysing Project Performance

Application of Earned Value Analysis in Analysing Project Performance Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant

More information

Predicting The Future

Predicting The Future Predicting The Future Peter Hayward BAE Systems Insyte 1 Predicting The Future Steve said to me that perhaps I could maybe touch on one or two main issues with forecasting the Estimate To Complete 2 Predicting

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

Price Hedging and Revenue by Segment

Price Hedging and Revenue by Segment Price Hedging and Revenue by Segment In this lesson, we're going to pick up from where we had left off previously, where we had gone through and established several different scenarios for the price of

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

FAQ: Estimating, Budgeting, and Controlling

FAQ: Estimating, Budgeting, and Controlling Question 1: Why do project managers need to create a budget? Answer 1: The budget is designed to tell how much the total project should cost and when these costs will occur. This information is beneficial

More information

Critical Path and Earned Value Management

Critical Path and Earned Value Management Critical Path and Earned Value Management Two elegantly simple metrics, both rich with meaning, have been part of project management since the very beginning of the profession: 1. Critical Path Method

More information

Basic Project Management

Basic Project Management PDHonline Course P103H (8 PDH) Basic Project Management Instructor: William J. Scott, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions

More information

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327 Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING

More information

Humphreys &Associates, Inc.

Humphreys &Associates, Inc. Humphreys &Associates, Inc. 3111 N. Tustin Street, Suite 250 Orange, CA 92865 (714) 685-1730 (Phone) (714) 685-1734 (Fax) Email: humphreys@humphreys-assoc.com http://www.humphreys-assoc.com No portion

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Estimating Cost-To-Go Without Stable EVM Data

Estimating Cost-To-Go Without Stable EVM Data PR-158 Estimating Cost-To-Go Without Stable EVM Data Peter C. Frederic, Tecolote Research Inc. Ronald K. Larson, NASA 20 March 2013 2013 Professional Development & Training Workshop New Orleans, LA June

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects difficul7es to have an overall visibility of risks; a lack of understanding of all the interdependencies

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

Techniques to Assist Delivery of Projects

Techniques to Assist Delivery of Projects Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:

More information

+44 (0) The first annual earned value conference for continental Europe

+44 (0) The first annual earned value conference for continental Europe Measuring Integral Earned Schedule (IES) and Predicting the Project's Final Completion Duration: The Application of Kinematics Approach to Earned Value Management Metrics Mojtaba Zarei-Kesheh Moj.ZareiKesheh@gmail.com

More information

MMZG 523 PROJECT MANAGEMENT

MMZG 523 PROJECT MANAGEMENT MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable

More information

QUALITY CONTROL PROCESS

QUALITY CONTROL PROCESS 1.0 SCOPE The Enterprise Project Management Office (EPMO) established overarching Quality Policy, Quality Objectives in the 0100-0100-005-QMS EPMO QUALITY MANUAL. This procedure defines specific EPMO Information

More information

SAMPLE. AACE International Recommended Practice No. 80R-13

SAMPLE. AACE International Recommended Practice No. 80R-13 E 80R13 SA M PL ESTI MATEATCOMPLETI ON( EAC) AACE International Recommended Practice No. 80R-13 ESTIMATE AT COMPLETION (EAC) TCM Framework: 7.6 Risk Management 9.1 Project Cost Accounting 9.2 Progress

More information

Connecting Earned Value to the Schedule

Connecting Earned Value to the Schedule Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned

More information

Earned Value Project Management Fourth Edition

Earned Value Project Management Fourth Edition EARNED VALUE PROJECT MANAGEMENT FOURTH EDITION PDF - Are you looking for earned value project management fourth edition Books? Now, you will be happy that at this time earned value project management fourth

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics

More information

The Cost Monitoring of Construction Projects Through Earned Value Analysis

The Cost Monitoring of Construction Projects Through Earned Value Analysis 211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Monitoring System For Project Cost Control In Construction Industry

Monitoring System For Project Cost Control In Construction Industry Monitoring System For Project Cost Control In Construction Industry Pramod M *, K. Phaniraj **, V. Srinivasan *** * Post graduate student: Construction Engineering and Management, Manipal Institute of

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1 RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

Performance measurement

Performance measurement MGT/437 Project Management Session #4 Managing Projects to Achieve Optimal Results University of Phoenix, San José Learning Center 07/06/2004 Brian Smithson 07/06/2004 MGT/437 #4 -- Brian Smithson 1 Agenda

More information

Earned Value Management System. a system to

Earned Value Management System. a system to Earned Value Management System a system to MANAGE - - - and help resolve control problems in running projects where there is difficult to have an overall visibility of risks a lack of understanding of

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

Quality Project Management

Quality Project Management Quality Project Management By James N. Salapatas, PE, PMP www.suncam.com Copyright 2014 James N. Salapatas Page 1 of 44 Table of Contents Title Page LIST OF CHARTS 2 LIST OF FIGURES 3 ABOUT THE COURSE

More information

Learning Legacy Document

Learning Legacy Document PROGRAMME CONTROLS - COST Performance Measurement Procedure Current Document History: Revision: Effective Date: Document Number: CRL1-XRL-Z9-GPD-CR001_Z-50001 Author(s) Reviewed by: Approved by: Reason

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

Measuring Time An earned value simulation study

Measuring Time An earned value simulation study Measuring Time An earned value simulation study Mario Vanhoucke Presentation for the Annual Earned Value Conference for the UK London - June 1-11, 28 An EVM introduction The EV terminology A case study

More information