+44 (0) The first annual earned value conference for continental Europe

Size: px
Start display at page:

Download "+44 (0) The first annual earned value conference for continental Europe"

Transcription

1 Measuring Integral Earned Schedule (IES) and Predicting the Project's Final Completion Duration: The Application of Kinematics Approach to Earned Value Management Metrics Mojtaba Zarei-Kesheh +44 (0) Presentation for the EVA Europe Geneva 2009 CERN, Geneva - 25Nov2009 The first annual earned value conference for continental Europe

2 Objective Traditional and Current EVM methodologies Introduce the Integral Earned Schedule (IES) Concept Develop the Schedule Performance Indicators and Predictors Comparison of Different Methods 2

3 TIME IS NOT MONEY On the whole complex construction projects are likely to be finished more than six months late, due to poor time control. ( Managing the Risk of Delayed Completion in the 21st Century, CIOB research 2008) Money: if you leave it, it might actually accumulate. Time: expires at a regular and consistent rate whether you use it or not. (Keith Pikavance, President of CIOB, conference 2008). 3

4 CPM or EVA? CPM: The most reliable method to predict the project s time dimension (Fleming & Koppelman) CP analysis as a predictor: too time-consuming & incapable of providing early warning signal due to its retrospective nature. C/SCSC & ANSI/EIA 748: These standards do not define the analysis to be performed on EVM other than to state cost and schedule variances need to be computed. 4

5 Traditional EVM Data Relationship Physical % Complete In current project Activity Duration In project baseline (PMB) Data Date (DD) Performance % Complete BAC Schedule % Complete AC EV PV BAC = Budget at Completion PV = Planned Value EV = Earned Value AC = Actual Cost CV CPI SV SPI CV = Cost Variance CPI = Cost Performance Index SV = Schedule Variance SPI = Schedule Performance Index BASIC INPUT DATA DERIVED DATA 5

6 SV & SPI in Primavera P6! SV = EV - PV 6 SPI = EV / PV

7 Two Different EV Camps THE BUDGET-BASED CAMP (Traditional EV Schedule Metrics: Budget-based) THE TIME-BASED CAMP (21 st Century EV Schedule Metrics: Time-based) SPI( ) = EV / PV SV( ) = EV PV =? At completion (For late finish project): SPI( ) ends up at 1! SV( ) ends up at 0! Schedule Variance in units of budget make no sense! They behave erratically for projects behind schedule. SPI(t) = ES / AT SV(t) = ES AT = Time delay At completion (For late finish project): SPI(t) does not creep toward 1 SV(t) does not creep toward 0 Schedule Variance in time units 7

8 Integral Earned Schedule (IES) Camp Integration of Time & Cost The idea is to identify the point in time where the area under planned value curve (AUPV) equals the current area under earned value curve (AUEV). Integral Earned Schedule (IES) looks at when the current AUEV was to be accomplished. The area under PV and EV curves can be computed using integral approach (trapezoidal rule). 8

9 Integral Approach (Trapezoidal Rule) EV % or PV% EV(ATn-1)% EV(ATn) % ATn-1 ATn Time (Periods) ATn% -ATn-1% 9

10 IES Metrics and Indicators calculation Calculate cumulative values of AUPV% and AUEV% using Integral Approach (Trapezoidal Rule) Now other calculations is similar to ES calculation! In Lipke s ES Calculator: Substitute PVcum with AUPV%cum Substitute EVcum with AUEV%cum Substitute ES with IES Substitute SV(t) with SV(IES) Substitute SPI(t) with SPI(IES) 10

11 Integral Earned Schedule (IES) Formula IES cumulative = Whole time (months or periods) completed for ΣAUEV% Σ AUPV% + Fractional Time Completed (I) IEScum = X + [(ΣAUEV%t Σ AUPV%x) / (Σ AUPV%x+1 Σ AUPV%x)] (x = whole time (month, period,..) earned ; x+1 = month or period following; t = Time Now) Indicators: Schedule Variance (IES): SV(IES) = IES AT Schedule Performance Index (IES): SPI(IES) = IES / AT where: AT: Actual Time 11

12 Prediction Terminology Prediction Method Anbari Jacob Lipke Zarei Planned Value Rate Earned Duration Earned Schedule Integral Earned Schedule P.F. = 1 IEAC(t)ED1 = PD + AT (1 -SPI) IEAC(t)PV1 = PD - (SV/(BAC/PD)) After PCD: IEAC(t)ED1 = AT (2 - SPI) IEAC(t)ES1 = IEAC(t)IES1 = AT + (PD - ES) AT + (PD - IES) IEAC(t)ED2 = PD / SPI P.F. = SPI IEAC(t)PV2 = PD / SPI After PCD: IEAC(t)ED2 = AT / SPI IEAC(t)ES2 = PD / SPI(t) IEAC(t)IES2 = PD / SPI(IES) 12

13 Analogous ways to think of integration of time and money (IES) For labor-intensive projects IES (our integration of time and money) is analogous to estimating work in terms of staff-hours; Thus: the work duration is estimated by the number of staff available More people-less time, less people-more time; So the value of the work is the product. IES: the same approach in EVA analysis; The product of time and money (PV, staff) defines work scope; The product of EV and time is the work completed. 13

14 Real-life Project Data The Real-life Project: Reporting 100% complete as of Jul ,208 million pounds contract Planned Completion Date = Feb09 Actual Completion Date = Jul09 5 Periods Slip 14

15 Schedule Variance Comparison Periods SV(t)cum SV(EAS)cum SV(IES)cum Target SV SV( )cum Zarei Time (Periods) The SV(t) starts to show the real final delay from 97% completion point! Incapability in providing the real final delay in early / middle stage of project. At period 30, or the 50% completion point, the SV(IES) shows the more reliable and consistent SV trend, it correlates very well. SV(IES) predict also the final delay at this point reliably! SV(IES): always normal & consistent trend SV(t): upward and downward trends! inconsistent trend 15

16 Schedule Performance Index Comparison 1.20 SPI(t)cum SPI(EAS)cum SPI(IES)cum SPI( )cum Target SPI Zarei Index Value Time (Periods) SPI(IES): always overall normal & consistent trend SPI(t): always overall abnormal & inconsistent trend: Look at the upward and downward trends! Ooops! So confusing for PM! 16

17 Schedule Variance SV( ): SV(t): SV(IES): Expressed in pounds units; in the vertical direction Expressed in time units in the horizontal direction Expressed in time units Consider both vertical and horizontal direction (integration of time and cost together), then looks at horizontal direction 17

18 Final Duration Predicting Comparison Duration (Periods) P.F. = IEAC(t)PV1 Anbari IEAC(t)EAS1 IES1 Zarei IEAC(t)ED1 Jacob Planned Duration IEAC(t)ES1 Lipke Final Duration Look at the upward and downward trends! So confusing for PM! 48 0% 20% 40% 60% 80% 100% Physical Percent Complete From 30% Completion point, IEAC(IES1): higher accuracy than others, consistent Early Warning Signal behavior / trend, correct final duration Other methods: abnormal, aberrant and inconsistent behavior / trend 18

19 Durat tion (Periods) Final Duration Predicting Comparison P.F. = SPI, SPI(t), SPI(IES) IEAC(t)PV2 Anbari IEAC(t)EAS2 IES2 Zarei IEAC(t)ED2 Jacob Planned Duration Look at the upward and downward trends! No consistency! IEAC(t)ES2 Lipke Final Duration Seeing is believing! 0% 20% 40% 60% 80% 100% Physical Percent Complete From 13% Completion point (early stage), IEAC(IES2): begins to show accurate and reliable prediction; consistent behavior and trend, the most accurate result, correct final duration. This is consistent and reliable EARLY WARNING SIGNAL! Other methods: abnormal, aberrant and inconsistent behavior / trend specially in early stage. 19

20 IES Summary Time & Cost Integration for assessing and measuring schedule performance and predicting final duration; IES: Integration of both time and cost together; Unique characteristics of the area Under Planned Value curve (AUPV) and area under EV curve (AUEV) in Real Projects (not applicable for artificial and unrealistic projects); SV(IES): normal & consistent trend from early stage of project; capability to predict real final delay of project (Early Warning Signal); CONSISTENCY AND ACCURACY IES method: consistent, stabilized and correct predictive behaviour from the early stage of project (Early Warning Signal). 20

21 Project Managers do not need the predictive results at the late stage of project At the late stage, PM cannot take corrective action; everybody is aware of delay IES method claims to predict correct final duration from early stage. Useful info for PMs! That is called: Early Warning Signal! IES method: IES Summary provide consistent results (real final delay, final duration) from early stage; CONSISTENCY AND ACCURACY advance programme control; give opportune time to project planners and PMs to take corrective action. The other methods do not have this capability! 21

22 Thank you to... Mr. Ray Stratton PMP, EVP for his book that motivated me to walk in EVM world; also for his technical advice during my research on EVM/IES; Prof. Mario Vanhoucke for his constant encouragement during my IES research; Mr. Walt Lipke for his technical advice during my work on ES implementation in Thameslink Programme (London) and for use of ES Calculator. 22

23 Thank you to... EVA Europe Geneva 2009, CERN L to R: Kym Henderson, Walt Lipke, Mojtaba Zarei-Kesheh, Stephan Vandevoorde, Prof. Mario Vanhoucke, Prof. Pierre Bonnal 23

24 References Anbari F. (2003) Earned value method and extension. Project Management Journal Fleming, Q. et al. (2005) Earned value project management, 3 rd ed, PMI Jacob, D. (2003) Forecasting project schedule completion with earned value metrics. The Measurable News (March) Jacob, D. et al. (2004) Forecasting project schedule completion with earned value metrics revisited. The Measurable News (Summer) Lipke, W. (2003) Schedule is different. The Measurable News (March) Lipke, W. (2009) Project duration forecasting a comparison of earned value management methods to earned schedule. The Measurable News (Issue 2) PMI-EVM Practice Standard, (2005), PMI Vanhoucke, M. et al. (2006) A simulation and evaluation of earned value metrics to forecast project duration. J Oper Res Soc Vanhoucke, M. et al. (2006) comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management 24 24

25 25

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Earned Schedule schedule performance

Earned Schedule schedule performance Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should

More information

Earned Schedule in Action

Earned Schedule in Action Earned Schedule in Action Earned Value Analysis - 11 Conference London, United Kingdom 12-17 June 2006 Kym Henderson Education Director PMI Sydney Australia Chapter Kym.Henderson@froggy.com.au EVM Schedule

More information

Earned Schedule Analysis

Earned Schedule Analysis Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI

More information

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia Schedule Analysis and Predictive Techniques Using Earned Schedule 16 th IPM Conference Tysons Corner, Virginia 17 th November 2004 Walt Lipke OC-ALC/MAS Tinker AFB OK walter.lipke@tinker.af.mil 405-736-3341

More information

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327 Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING

More information

Connecting Earned Value to the Schedule

Connecting Earned Value to the Schedule Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned

More information

Monitoring System For Project Cost Control In Construction Industry

Monitoring System For Project Cost Control In Construction Industry Monitoring System For Project Cost Control In Construction Industry Pramod M *, K. Phaniraj **, V. Srinivasan *** * Post graduate student: Construction Engineering and Management, Manipal Institute of

More information

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context

More information

Earned Schedule Training

Earned Schedule Training Earned Schedule Training Instructors Walt Lipke waltlipke@cox.net (405) 364-1594 Kym Henderson Education Director PMI Sydney, Australia Chapter kym.henderson@froggy.com.au 61 414 428 537 Copyright Lipke

More information

PROJECT BY PROJECT MANAGEMENT T OOLS

PROJECT BY PROJECT MANAGEMENT T OOLS Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring

More information

Not Your Father's Earned Value

Not Your Father's Earned Value Not Your Father's Earned Value Ray Stratton (February 24, 2005) Reprint from Projects @ Work: http://www.projectsatwork.com Sure, for 30-some years earned value management has helped project managers estimate

More information

Measuring Time An earned value simulation study

Measuring Time An earned value simulation study Measuring Time An earned value simulation study Mario Vanhoucke Presentation for the Annual Earned Value Conference for the UK London - June 1-11, 28 An EVM introduction The EV terminology A case study

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php

More information

30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering. sete2018.com.au BRETT THIELE

30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering. sete2018.com.au BRETT THIELE 30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering BRETT THIELE A Standardised Data Set to Support Research on Earned Value and Earned Schedule Management Techniques Motivation

More information

Application of Data Mining Tools to Predicate Completion Time of a Project

Application of Data Mining Tools to Predicate Completion Time of a Project Application of Data Mining Tools to Predicate Completion Time of a Project Seyed Hossein Iranmanesh, and Zahra Mokhtari Abstract Estimation time and cost of work completion in a project and follow up them

More information

Predicting The Future

Predicting The Future Predicting The Future Peter Hayward BAE Systems Insyte 1 Predicting The Future Steve said to me that perhaps I could maybe touch on one or two main issues with forecasting the Estimate To Complete 2 Predicting

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

Project Performance Evaluation By Earned Value Method

Project Performance Evaluation By Earned Value Method Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *

More information

Does Project Performance Stability Exist? A Re-examination of CPI and Examination of SPI(t) Stability

Does Project Performance Stability Exist? A Re-examination of CPI and Examination of SPI(t) Stability Does Project Performance Stability Exist? A Re-examination of CPI and Examination of SPI(t) Stability Earned Value Analysis - 13 Conference London, United Kingdom 12-17 June 2008 Kym Henderson Vice President

More information

Statistical Methods Applied to Project

Statistical Methods Applied to Project Statistical Methods Applied to Project Management Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net www.earnedschedule.com Abstract An objective of project management is to have

More information

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James

More information

Does Project Performance Stability Exist? a re-examination of CPI and evaluation of SPI(t) stability

Does Project Performance Stability Exist? a re-examination of CPI and evaluation of SPI(t) stability Does Project Performance Stability Exist? a re-examination of CPI and evaluation of SPI(t) stability Kym Henderson Vice President, Research and Standards PMI College of Performance Management * Dr. Ofer

More information

Improving the Practical Application for Monitoring Project Progress Using the Earned Value Method

Improving the Practical Application for Monitoring Project Progress Using the Earned Value Method CSCE 2010 General Conference - Congrès générale 2010 de la SCGC Winnipeg, Manitoba June 9-12, 2010 / 9 au 12 juin 2010 Improving the Practical Application for Monitoring Project Progress Using the Earned

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

EXAMINATION OF THE THRESHOLD FOR THE TO COMPLETE INDEXES By Walt Lipke, PMI Oklahoma City Chapter

EXAMINATION OF THE THRESHOLD FOR THE TO COMPLETE INDEXES By Walt Lipke, PMI Oklahoma City Chapter THE MEASURABLE NEWS 2016.01 EXAMINATION OF THE THRESHOLD FOR THE TO COMPLETE INDEXES By Walt Lipke, PMI Oklahoma City Chapter ABSTRACT From time to time in the Earned Value Management literature a claim

More information

FACULTEIT ECONOMIE EN BEDRIJFSKUNDE. HOVENIERSBERG 24 B-9000 GENT Tel. : 32 - (0) Fax. : 32 - (0)

FACULTEIT ECONOMIE EN BEDRIJFSKUNDE. HOVENIERSBERG 24 B-9000 GENT Tel. : 32 - (0) Fax. : 32 - (0) FACULTEIT ECONOMIE EN BEDRIJFSKUNDE HOVENIERSBERG 24 B-9000 GENT Tel. : 32 - (0)9 264.34.61 Fax. : 32 - (0)9 264.35.92 WORKING PAPER A Comparison of Different Project Duration Forecasting Methods using

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

Earned Value Management An Overview March 2014

Earned Value Management An Overview March 2014 Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process

More information

PROJECT REGULARITY: DEVELOPMENT AND EVALUATION OF A NEW PROJECT CHARACTERISTIC

PROJECT REGULARITY: DEVELOPMENT AND EVALUATION OF A NEW PROJECT CHARACTERISTIC J Syst Sci Syst Eng DOI: 10.1007/s11518-016-5312-6 ISSN: 1004-3756 (Paper) 1861-9576 (Online) CN11-2983/N PROJECT REGULARITY: DEVELOPMENT AND EVALUATION OF A NEW PROJECT CHARACTERISTIC Jordy Batselier

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What

More information

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561) Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com

More information

Lesson 7 The Project Budget

Lesson 7 The Project Budget MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget

More information

Earned Value Management - EVM

Earned Value Management - EVM Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the

More information

Optimization on Earned Value Method Combined with Critical Path

Optimization on Earned Value Method Combined with Critical Path Optimization on Earned Value Method Combined with Critical Path Qi-bin Zheng and Xing Bi Abstract When calculating the schedule performance using the traditional earned value method, the earned value in

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals

More information

Politecnico di Torino. Porto Institutional Repository

Politecnico di Torino. Porto Institutional Repository Politecnico di Torino Porto Institutional Repository [Article] An earned schedule-based regression model to improve cost estimate at completion Original Citation: Narbaev T.; De Marco A. (2014). An earned

More information

Value And Earned Schedule Management

Value And Earned Schedule Management EVM World 2013 Conference IPMC 2013 Title: An Analytical Utility For Earned Value And Earned Schedule Management Gary L. Richardson and Saranya Lakshmikanthan May 29, 2013 The popular technical literature

More information

AIR FORCE INSTITUTE OF TECHNOLOGY

AIR FORCE INSTITUTE OF TECHNOLOGY A Comparison of Earned Value Management and Earned Schedule as Schedule Predictors on DoD ACAT I Programs THESIS Kevin T. Crumrine, Captain, USAF AFIT-ENV-13-M-36 DEPARTMENT OF THE AIR FORCE AIR UNIVERSITY

More information

PMP Exam Prep Coaching Program

PMP Exam Prep Coaching Program PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to

More information

Project regularity: Development and evaluation of a new project characteristic

Project regularity: Development and evaluation of a new project characteristic Project regularity: Development and evaluation of a new project characteristic Jordy Batselier a, Mario Vanhoucke a,b,c, a Faculty of Economics and Business Administration, Ghent University, Tweekerkenstraat

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs

A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs Calhoun: The NPS Institutional Archive Theses and Dissertations Thesis Collection 2012-09 A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense

More information

Presenting Earned Value

Presenting Earned Value Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

an accuracy study and improvement of a time-dependent earned value model using monte carlo simulation

an accuracy study and improvement of a time-dependent earned value model using monte carlo simulation universiteit gent faculteit economie en bedrijfskunde Academiejaar 2012 2013 an accuracy study and improvement of a time-dependent earned value model using monte carlo simulation Masterproef voorgedragen

More information

APPLICATION OF THE EVM METHOD AND ITS EXTENSIONS IN THE IMPLEMENTATION OF CONSTRUCTION OBJECTS

APPLICATION OF THE EVM METHOD AND ITS EXTENSIONS IN THE IMPLEMENTATION OF CONSTRUCTION OBJECTS ENGINEERING STRUCTURES AND TECHNOLOGIES ISSN 2029-882X / eissn 2029-8838 2015 7(4): 189 196 doi:10.3846/2029882x.2016.1152168 APPLICATION OF THE EVM METHOD AND ITS EXTENSIONS IN THE IMPLEMENTATION OF CONSTRUCTION

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

Project Risk and CPI Why Should CPI = 1?

Project Risk and CPI Why Should CPI = 1? Project Risk and CPI Why Should CPI = 1? Walt Lipke PMI - Oklahoma City +1 405 364 1594 waltlipke@cox.net www.earnedschedule.com Abstract The expectation when applying Earned Value Management is to control

More information

EARNED VALUE MANAGEMENT. Is it worth the effort?

EARNED VALUE MANAGEMENT. Is it worth the effort? EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our

More information

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS

EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:

More information

Administration. Course Aim. Introductions

Administration. Course Aim. Introductions Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may

More information

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process

More information

Thomas Carlos Consulting. Simple Earned Value Management

Thomas Carlos Consulting. Simple Earned Value Management Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,

More information

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

Earned Value Management Guide

Earned Value Management Guide 1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Carlos Consulting Group

Carlos Consulting Group Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE

EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE Mr. Divyesh Joshi 1, Mr. Vyom B. Pathak 2, Ms. Neetu B. Yadav 3 M.E. Student, Civil Eng. Dept., SNPIT &RC, Umrakh

More information

Journal of Project Management

Journal of Project Management Journal of Project Management 1 (2016) 41 54 Contents lists available at GrowingScience Journal of Project Management homepage: www.growingscience.com A modified earned value management using activity

More information

Cumulative trends Problems and issues since last report

Cumulative trends Problems and issues since last report Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier

More information

Alternative Project Management Practices in Earned Value and Black-Scholes. Xinlei Zhang

Alternative Project Management Practices in Earned Value and Black-Scholes. Xinlei Zhang Alternative Project Management Practices in Earned Value and Black-Scholes Xinlei Zhang A thesis in fulfilment of the requirements for the degree of Masters by Research The University of New South Wales

More information

An Analysis of Stability Properties in Earned Value Management s Cost Performance Index and Earned Schedule s Schedule Performance Index

An Analysis of Stability Properties in Earned Value Management s Cost Performance Index and Earned Schedule s Schedule Performance Index Air Force Institute of Technology AFIT Scholar Theses and Dissertations 3-14-2014 An Analysis of Stability Properties in Earned Value Management s Cost Performance Index and Earned Schedule s Schedule

More information

A Practical Way To Learn About EVM. ***The Deck Project***

A Practical Way To Learn About EVM. ***The Deck Project*** A Practical Way To Learn About EVM ***The Deck Project*** Back to the Baseline 2 The Deck Project The product of this project is a new second-story deck in the backyard. This new deck will replace an existing

More information

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors eva europe GENEVA 2009 2009, CERN, HEG, Authors - This material is provided courtesy of EVA Europe 2009, the European organisation for nuclear research(cern), the Geneva School of Business administration

More information

Detailed Project Scheduling and Cost Management

Detailed Project Scheduling and Cost Management Detailed Project Scheduling and Cost Management A Case Study on Dhaaruni Commercial Complex Bengaluru Lathan B.S 1, Dr.Srinath Shetty.K 2 1 P.G Student, 2 Professor & Head Civil Engineering NMAM Institute

More information

next level PMP Exam Preparation Formula Guide for the PMP Exam

next level PMP Exam Preparation Formula Guide for the PMP Exam next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to

More information

Homework 6 Questions and Answers

Homework 6 Questions and Answers I.E. 406 PROJECT SCHEDULING AND CONTROL Fall 2012 Murat Sandikcioglu (original by Dr.Onur ÇOKGÖR) Homework 6 Questions and Answers CRITICAL CHAIN PROJECT MANAGEMENT (CCPM) & EARNED VALUE ANALYSIS (EVA)

More information

PM World Today March 2011 (Vol XIII, Issue III) PM WORLD TODAY FEATURED PAPER MARCH Why Should CPI = 1? By Walt Lipke PMI Oklahoma City Chapter

PM World Today March 2011 (Vol XIII, Issue III) PM WORLD TODAY FEATURED PAPER MARCH Why Should CPI = 1? By Walt Lipke PMI Oklahoma City Chapter PM WORLD TODAY FEATURED PAPER MARCH 2011 Why Should CPI = 1? By Walt Lipke PMI Oklahoma City Chapter Abstract The expectation when applying Earned Value Management is to control performance such that CPI

More information

AIR FORCE INSTITUTE OF TECHNOLOGY

AIR FORCE INSTITUTE OF TECHNOLOGY An Analysis of the Estimate at Complete for Department of Defense Contracts THESIS Deborah B. Kim, First Lieutenant, USAF AFIT-ENC-MS-18-M-214 DEPARTMENT OF THE AIR FORCE AIR UNIVERSITY AIR FORCE INSTITUTE

More information

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L 1, Anne Ligoria S 2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists. International authors and editors

We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists. International authors and editors We are IntechOpen, the world s leading publisher of Open Access books Built by scientists, for scientists 3,500 108,000 1.7 M Open access books available International authors and editors Downloads Our

More information

ESTIMATINGCOST AT COMPLETION THROUGH EARNED VALUE TECHNIQUE IN BYPASS ROAD OF NORTH EAST OF AHVAZ

ESTIMATINGCOST AT COMPLETION THROUGH EARNED VALUE TECHNIQUE IN BYPASS ROAD OF NORTH EAST OF AHVAZ ESTIMATINGCOST AT COMPLETION THROUGH EARNED VALUE TECHNIQUE IN BYPASS ROAD OF NORTH EAST OF AHVAZ Farokh Tavakoli Shoushtari and *Mehdi Mahdavi Adeli Department of Civil Engineering, College of Engineering,

More information

The First Steps in Implementing a Simplified Earned Value Management System

The First Steps in Implementing a Simplified Earned Value Management System 2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface

More information

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,

More information

Roberta Tomasini Defense Acquisition University DSN

Roberta Tomasini Defense Acquisition University DSN $ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program

More information

Monitoring and Controlling RCC Work in Delayed Construction Projects

Monitoring and Controlling RCC Work in Delayed Construction Projects Monitoring and Controlling RCC Work in Delayed Construction s Nimesh Gujarati, Dr. B S Balapgol Post Graduate Student (Construction and Management), DYPCOE, Akurdi, Pune-44, Maharashtra, India Principal,

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Critical Path and Earned Value Management

Critical Path and Earned Value Management Critical Path and Earned Value Management Two elegantly simple metrics, both rich with meaning, have been part of project management since the very beginning of the profession: 1. Critical Path Method

More information

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions

More information

An Automated Framework for the Integration between EVM and Risk Management

An Automated Framework for the Integration between EVM and Risk Management Journal of Information Systems Engineering & Management, 2018, 3(1), 03 ISSN: 2468-4376 An Automated Framework for the Integration between EVM and Risk Management Anabela Tereso 1 *, Pedro Ribeiro 1, Manuel

More information

The Cost Monitoring of Construction Projects Through Earned Value Analysis

The Cost Monitoring of Construction Projects Through Earned Value Analysis 211 International Conference on Economics and Finance Research IPEDR vol.4 (211) (211) IACSIT Press, Singapore The Cost Monitoring of Construction Projects Through Earned Value Analysis Mohd Faris Khamidi

More information

ievm (INTEGRATED EARNED VALUE MANAGEMENT) AN APPROACH FOR INTEGRATING QUALITY WITH TRADITIONAL EVM FOR EFFECTIVE PROGRAM AND PROJECT MANAGEMENT

ievm (INTEGRATED EARNED VALUE MANAGEMENT) AN APPROACH FOR INTEGRATING QUALITY WITH TRADITIONAL EVM FOR EFFECTIVE PROGRAM AND PROJECT MANAGEMENT ievm (INTEGRATED EARNED VALUE MANAGEMENT) AN APPROACH FOR INTEGRATING QUALITY WITH TRADITIONAL EVM FOR EFFECTIVE PROGRAM AND PROJECT MANAGEMENT Vanshika T Department of Information Technology Barkatullah

More information

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

The Value of EVM. Earned Value Management

The Value of EVM. Earned Value Management The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in

More information

Application of Earned Value Management (EVM) for Effective Project Control

Application of Earned Value Management (EVM) for Effective Project Control Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge

More information

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ; Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

The Mystery of Earned Value - An Oil & Gas Owner s Perspective The Mystery of Earned Value - An Oil & Gas Owner s Perspective 15 June 2011 William Harroun Head of Programme Controls, BG Group What we are going to cover Cost and progress reporting before --- Earned

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado Pradip Mehta, PMP, CCE, PSP, EVP, PMI-SP, RMP Vice President, Project Controls AECOM Corporation Agenda 1. Earned Value Concept

More information