Measuring Time An earned value simulation study
|
|
- Joanna O’Connor’
- 5 years ago
- Views:
Transcription
1 Measuring Time An earned value simulation study Mario Vanhoucke Presentation for the Annual Earned Value Conference for the UK London - June 1-11, 28
2 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software Cover might be subject to change upon publication
3 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software
4 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software
5 EVM metrics Earned Value Key Parameters Planned Value (PV) Actual Cost (AC) Earned Value (EV) Earned Schedule (ES) Earned Value Performance Measures Cost Performance Index (CPI) Cost Variance (CV) Schedule Performance Index (SPI) Schedule Variance (SV) Schedule Performance Index (SPI(t)) Schedule Variance (CV(t)) Translation to time units Time Variance (TV) Earned Duration (ED) Earned Value Forecasting Indicators Cost Estimate At Completion (EAC) Duration Estimate At Completion (EAC(t)) Duration Estimate At Completion (EAC(t))
6 delay over budget 225 delay under budget W W1 W2 W3 W4 W5 W6 W7 W8 W9 W W1 W2 W3 W4 W5 W6 W7 W8 W9 4 3 ahead over budget ahead under budget W W1 W2 W3 W4 W5 W6 W7 W8 W9 W W1 W2 W3 W4 W5 W6 W7 W8 W9 PV AC EV
7 Earned Schedule ES (new!) Find t such that EV > PVt and EV < PVt +1 ES = t + (EV - PVt) / (PVt+1 - PVt) PVt+1 EV 75 PVt W W1 W2 W3 W4 W5 W6 W7 W8 W9 Planned Value Earned Value ES AT
8 Earned Schedule ES Find t such that EV > PVt and EV < PVt +1 ES = t + (EV - PVt) / (PVt+1 - PVt) Behind schedule (in monetary terms!) 75 W W1 W2 W3 W4 W5 W6 W7 W8 W9 Planned Value Earned Value ES AT Behind schedule (in a time dimension!)
9 Earned Schedule ES ES measures time in hours, days, weeks or months! Find t such that EV > PVt and EV < PVt +1 ES = t + (EV - PVt) / (PVt+1 - PVt) Behind schedule (in monetary terms!) 75 W W1 W2 W3 W4 W5 W6 W7 W8 W9 Planned Value Earned Value ES AT Behind schedule (in a time dimension!)
10 Performance Planned Duration PC PV AC EV W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11.% 2.67% 1.% 18.33% 26.67% 4.% 5.% 75.% 8.% 87.% 95.% 1.% Late! ES SPI SPI(t) CPI W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11 PV AC EV
11 Performance Cost performance: cost overrun! Correct measure PC PV AC EV W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11.% 2.67% 1.% 18.33% 26.67% 4.% 5.% 75.% 8.% 87.% 95.% 1.% ES SPI SPI(t) CPI Cost Performance Budget overrun!.5.25 W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11 CPI
12 Performance Time performance: quirky behavior! PC PV AC EV W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11.% 2.67% 1.% 18.33% 26.67% 4.% 5.% 75.% 8.% 87.% 95.% 1.% ES SPI SPI(t) CPI Schedule Performance On time?.85 Late! W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11 SPI SPI(t)
13 Performance ES measures real time performance until the end of the project! Time performance: quirky behavior! PC PV AC EV W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11.% 2.67% 1.% 18.33% 26.67% 4.% 5.% 75.% 8.% 87.% 95.% 1.% ES SPI SPI(t) CPI Schedule Performance On time?.85 Late! W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11 SPI SPI(t)
14 SPI = EV / PV End of project: EV = PV SPI = 1 (always!) SPI(t) = ES / AD End of project: ES = PD ES > AD (early) ES = AD (on time) SPI(t) = 1 ES < AD (late) 1. Schedule Performance On time?.85 Late! W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11 SPI SPI(t)
15 Unreliable region for performance measurement! Inaccurate time forecast! 1. Schedule Performance On time?.85 Late! W W1 W2 W3 W4 W5 W6 W7 W8 W9 W1 W11 SPI SPI(t)
16 Forecasting General idea: based on current performance Forecasting methods Traditional methods (PV, AC and EV) Novel method (ES) Planned Value Method Earned Duration Method Earned Schedule Method Current Project Performance PF = 1 Future follows the schedule EAC(t)PV1 EAC(t)ED1 EAC(t)ES1 PF = SPI or SPI(t) PF = SCI or SCI(t) Future time performance = Current time performance Future time performance = Current time/cost performance EAC(t)PV2 EAC(t)ED2 EAC(t)ES2 EAC(t)PV3 EAC(t)ED3 EAC(t)ES3
17 Forecasting ES predicts the future in a better way? General idea: based on current performance Forecasting methods Traditional methods (PV, AC and EV) Novel method (ES) Planned Value Method Earned Duration Method Earned Schedule Method Current Project Performance PF = 1 Future follows the schedule EAC(t)PV1 EAC(t)ED1 EAC(t)ES1 PF = SPI or SPI(t) PF = SCI or SCI(t) Future time performance = Current time performance Future time performance = Current time/cost performance EAC(t)PV2 EAC(t)ED2 EAC(t)ES2 EAC(t)PV3 EAC(t)ED3 EAC(t)ES3
18 Forecasting ES predicts the future in a better way? General idea: based on current performance Forecasting methods Traditional methods (PV, AC and EV) Novel method (ES) Planned Value Method Earned Duration Method Earned Schedule Method Current Project Performance PF = 1 Future follows the schedule EAC(t)PV1 EAC(t)ED1 EAC(t)ES1 PF = SPI or SPI(t) PF = SCI or SCI(t) Future time performance = Current time performance Future time performance = Current time/cost performance EAC(t)PV2 EAC(t)ED2 EAC(t)ES2 EAC(t)PV3 EAC(t)ED3 EAC(t)ES3
19 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software
20 Research project General conclusions instead of often subjective case study statements! Research topic 1: Static forecast accuracy drivers Research topic 2: Dynamic forecast accuracy drivers Research topic 3: Guide the corrective action decision making process Study 1 Determinants of forecast accuracy Study 2 Project structure (topological indicators) Baseline schedule (activity criticality) Schedule adherence (p-factor) Review period (percentage completed) Concept Project definition Project scheduling Project execution Project control Project termination Forecast accuracy Study 3 Feedback loop (earned value performance management) Management s attention (activity or project based) Corrective action decision making
21 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software
22 Methodology Network indicators (4) Project network Generate project networks with a pre-defined structure Project schedule Construct an earliest start schedule (ESS) using forward calculations Planned Value (PV) Simulation scenarios (9) Project execution Monte-Carlo simulation for each activity s duration and cost Actual Cost (AC) Earned Value (EV) Project monitoring Measure the forecasting accuracy at each review period
23 Project network Topological structure of a network Number of activities, precedence relations, Influence on risk of delay, computer speed, schedule quality, resource consumption, etc... Wide and diverse set of project networks Idea: span the full range of complexity Parameter: SP indicator to measure the degree between a serial/parallel network
24 Baseline schedule Construction of baseline schedule Critical path method: ESS Planned Value PV S-curve Point-of-reference: The real purpose of a project schedule is to act as a predictive model of a team of resources and the project work destined for that team
25 Simulation scenarios Critical activities Non-critical activities SPI(t) = Legend: SPI(t): average project early warning performance signal > 1: average positive signal (ahead of schedule) < 1: average negative signal (schedule delay) RD: Real project duration
26 Simulation scenarios The true scenarios Critical activities Non-critical activities SPI(t) =
27 Simulation scenarios The true scenarios Critical activities Report: Project ahead Reality: Project ahead Non-critical activities SPI(t) =
28 Simulation scenarios The true scenarios Critical activities Report: Project ahead Reality: Project ahead Non-critical activities SPI(t) = Report: Project delay Reality: Project delay +
29 Simulation scenarios The true scenarios Critical activities Report: Project ahead Reality: Project ahead Non-critical activities SPI(t) = Report: Project delay Reality: Project delay + Report: Project on time Reality: Project on time
30 Simulation scenarios The misleading scenarios Critical activities Non-critical activities SPI(t) =
31 Simulation scenarios The misleading scenarios Critical activities - + Report: Project ahead Reality: Project on time Non-critical activities SPI(t) =
32 Simulation scenarios The misleading scenarios Critical activities - + Report: Project ahead Reality: Project on time Non-critical activities SPI(t) = Report: Project delay Reality: Project on time
33 Simulation scenarios The false scenarios Critical activities Non-critical activities SPI(t) =
34 Simulation scenarios The false scenarios Critical activities - + Non-critical activities SPI(t) = Report: Project ahead Reality: Project delay +
35 Simulation scenarios The false scenarios Critical activities - + Report: Project delay Reality: Project ahead Non-critical activities SPI(t) = Report: Project ahead Reality: Project delay
36 Forecast accuracy Project schedule and real-life execution: Murphy strikes! Real project duration Forecast accuracy = quality of average EAC(t) prediction = difference between average EAC(t) and RD 35 PV AC EV SPI(t) per period EAC(t) per period Average EAC(t) over complete horizon
37 Results (1) The earned schedule method outperforms, on average, the more traditional method (planned value method and earned duration method) EAC(t) estimate is too low EAC(t) estimate is too high Scenario 1 Scenario 2 True scenarios (1, 2, 5, 8, 9) ES >> PV and ED Scenario 3 Scenario 4 Scenario 5 Scenario 6 Misleading scenarios (4, 6) ES < PV and ED Scenario 7 Scenario 8 Scenario 9 Planned Value Earned Duration Earned Schedule False scenarios (3, 7) ES << PV and ED -2.% -1.%.% 1.% 2.% 3.% 4.%
38 Results (2) The network structure has a clear influence on the forecast accuracy 2 16 Early project 7.5 Late project SP low (parallel networks) Low accuracy SP high (serial networks) High accuracy Planned Value Earned Duration Earned Schedule From a parallel to a serial network From a parallel to a serial network
39 Results (3) Accuracy along the completion stage (beginning, middle or late) All forecasting methods have a relatively low accuracy at the project start. So what? The earned schedule method outperforms the other methods from the beginning of the project All other methods make the quirky mistake from the 5% à 6% percentage completed Early project Late project Early stage Middle stage Late stage Early stage Middle stage Late stage Planned Value Earned Duration Earned Schedule
40 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software
41 Earned Value Management = project based tracking approach Project Objective Item Item Item Item Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity
42 Earned Value Management = project based tracking approach Project Objective SPI or SPI(t) below a critical threshold? Item Item Item Item Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity In danger! Watch out! No problem Requires action Requires attention Under control
43 EVM: when? Project based vs. activity based project tracking approach Activity based tracking SPI(t) is unreliable EAC(t) is inaccurate Project based tracking SPI(t) is reliable EAC(t) is accurate 1% parallel network 1% serial network
44 Schedule Risk Analysis = activity based tracking approach Project Objective Positive effect on project objective? Item Item Item Item Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Individual activity control as a trigger for corrective actions = Obtain with the minimal effort the maximal return!
45 Simulation study Input Simulation run Output Project data Run simulation Measure activity sensitivity Action threshold Run simulation with corrective actions % Control Measure improvement Unit contribution Total contribution
46 Management s focus Action threshold as a function of activity sensitivity Determines the %Control Sensitivity Chart Sensitivy Action threshold Full control ( th percentile) Action threshold No control (1 th percentile)
47 Results Activity based tracking SPI(t) is unreliable EAC(t) is inaccurate Project based tracking SPI(t) is reliable EAC(t) is accurate low SP - low action threshold high SP - low action threshold ? CI SI CRI SSI CI SI CRI SSI low SP - high action threshold high SP - high action threshold ? CI SI CRI SSI CI SI CRI SSI %C TC
48 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software
49 Ideal WBS level? WBS levels EVM: top-down SRA: bottom-up Project Project performance problem! Negative effect on project performance? item Project Objective Project Objective Item Item Item Item Item Item Item Item Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activities Which activities are critical and responsible for the problem? Highly sensitive activities in trouble!
50 Construct baseline schedule Measure activity sensitivity Start project execution (t = ) Increase review period (t = t + 1) Measure project performance (SPI and SPI(t)) Simulate activity time/cost variation at current time t Determine set of activities in progress Top-down project monitoring no no Below project performance threshold? yes Delays in critical activities? yes Take corrective actions yes Above activity sensitivity thresholds? yes Delay in sensitive activities? no no Bottom-up project monitoring (a) (b) Project finished? no yes Measure efficiency
51 Results 5% 4% Tracking Efficiency 3% 2% 1% % Parallel networks Serial networks TD-SPI TD-SPI(t) BU-SRA Top-down project tracking using EVM with SPI(t) is particularly useful for serial networks - Bottom-up project tracking using SRA is particularly useful for parallel networks
52 An EVM introduction The EV terminology A case study The research project Static drivers of forecast accuracy Dynamic drivers of forecast accuracy Time sensitivity and corrective actions Top-down or bottom-up project tracking The software
53 ProTrack CRITERIA ProTrack ProTrack ProTrack ProTrack Standard Sensitivity Scan Time Shuttle Smart Version Project Planning CPM based planning Network visualization Automatic Project Creation yes yes yes yes - yes yes yes - yes yes yes Project simulation options Activity Time/Cost Simulation Schedule Risk Analysis EVM forecast accuracy Analysis - Advanced module Standard Module Standard/Advanced modules - yes - yes - - yes yes Project Tracking Earned Value and Earned Schedule Earned Value Forecasting** Automatic Tracking Generation p-factor calculation yes yes yes yes yes yes yes yes - - yes yes - - yes yes Book Measuring Time Price yes
54 General conclusions References Future research avenues
55 General conclusion Activity based project tracking (bottom-up time sensitivity) Project based project tracking (Top-down earned value) Parallel project networks Yes! Focus on a subpart of activity set No! Inaccurate time forecasts Serial project networks No! Focus not possible Yes! Accurate time forecasts using Earned Schedule
56 Contact Research Faculty of Economics, Ghent University, Tweekerkenstraat 2, 9 Gent (Belgium) mario.vanhoucke@ugent.be Vlerick Leuven Gent Management School, Reep 1, 9 Gent (Belgium) mario.vanhoucke@vlerick.be Publications Cover might be subject to change upon publication 2 published: International Journal of Project Management, Journal of the Operational Research Society 4 research manuscripts under submission (June 28) Book: Measuring time (to appear) Software (coming soon) OR-AS, Operations Research - Applications and Solutions, Hoorndriesstraat 1, 982 Merelbeke (Belgium) Web: info@or-as.be
57
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationEarned Schedule schedule performance
Earned Schedule schedule performance analysis from EVM measures Walt Lipke PMI - Oklahoma City Chapter +1 405 364 1594 waltlipke@cox.net $$ The idea is to determine the time at which h the EV accrued should
More informationPROJECT REGULARITY: DEVELOPMENT AND EVALUATION OF A NEW PROJECT CHARACTERISTIC
J Syst Sci Syst Eng DOI: 10.1007/s11518-016-5312-6 ISSN: 1004-3756 (Paper) 1861-9576 (Online) CN11-2983/N PROJECT REGULARITY: DEVELOPMENT AND EVALUATION OF A NEW PROJECT CHARACTERISTIC Jordy Batselier
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php
More information+44 (0) The first annual earned value conference for continental Europe
Measuring Integral Earned Schedule (IES) and Predicting the Project's Final Completion Duration: The Application of Kinematics Approach to Earned Value Management Metrics Mojtaba Zarei-Kesheh Moj.ZareiKesheh@gmail.com
More informationProject regularity: Development and evaluation of a new project characteristic
Project regularity: Development and evaluation of a new project characteristic Jordy Batselier a, Mario Vanhoucke a,b,c, a Faculty of Economics and Business Administration, Ghent University, Tweekerkenstraat
More informationProject Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:
Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,
More informationPredicting Project Completion Date Using Earned Value Management
Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231
More informationManaging Product Innovation
Managing Product Innovation A study of product innovation in project management Astrid De Keyzer Jolien Dobbelaere Shana Raes Lisa Vandevoorde Dorien Van Steenberge Project Fictitious product innovation
More informationCS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III
LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III Earned Value Management Earned value management (EVM) is a way of measuring your performance (and the performance of your project team) at any given date
More informationI declare that the content of this Masters Dissertation may be consulted and/or reproduced, provided that the source is referenced.
III CONFIDENTIALITY AGREEMENT PERMISSION I declare that the content of this Masters Dissertation may be consulted and/or reproduced, provided that the source is referenced. Students name: Pieter Van Nevel
More informationan accuracy study and improvement of a time-dependent earned value model using monte carlo simulation
universiteit gent faculteit economie en bedrijfskunde Academiejaar 2012 2013 an accuracy study and improvement of a time-dependent earned value model using monte carlo simulation Masterproef voorgedragen
More informationPROJECT MANAGEMENT BODY OF KNOWLEDGE
A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education
More informationMonitoring System For Project Cost Control In Construction Industry
Monitoring System For Project Cost Control In Construction Industry Pramod M *, K. Phaniraj **, V. Srinivasan *** * Post graduate student: Construction Engineering and Management, Manipal Institute of
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationAnalysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh
Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS
More informationPROJECT BY PROJECT MANAGEMENT T OOLS
Earned Schedule Tejas Sura Joint M.D., Conart Engineers Limited V.P.-President President PMI Mumbai Chapter We are here to know HOW TO GUIDE OUR PROJECT BY PROJECT MANAGEMENT TOOLS Project Monitoring Monitoring
More informationPMP Exam Prep Coaching Program
PMP Exam Prep Coaching Program Project Part 1 Presented by Vinai Prakash, PMP 1 Project Plan Estimate s Determine Budget 2 Vinai Prakash, PMCHAMP.COM 1 Process of monitoring the status of the project to
More informationEarned Schedule Analysis
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI
More informationEARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION
EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY Dr David Hillson PMP FAPM FIRM, Director, Risk Doctor & Partners david@risk-doctor.com www.risk-doctor.com INTRODUCTION In today s uncertain
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals
More informationProject Performance Evaluation By Earned Value Method
Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *
More informationApplication of Data Mining Tools to Predicate Completion Time of a Project
Application of Data Mining Tools to Predicate Completion Time of a Project Seyed Hossein Iranmanesh, and Zahra Mokhtari Abstract Estimation time and cost of work completion in a project and follow up them
More informationNot Your Father's Earned Value
Not Your Father's Earned Value Ray Stratton (February 24, 2005) Reprint from Projects @ Work: http://www.projectsatwork.com Sure, for 30-some years earned value management has helped project managers estimate
More informationEarned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING
More informationEarned Value Management. Danielle Kellogg. Hodges University
Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level
More informationEarned Schedule in Action
Earned Schedule in Action Earned Value Analysis - 11 Conference London, United Kingdom 12-17 June 2006 Kym Henderson Education Director PMI Sydney Australia Chapter Kym.Henderson@froggy.com.au EVM Schedule
More informationResearch on the Impact of Project Network Topology on Project Control
Research on the Impact of Project Network Topology on Project Control GeDi Ji a, YiDan Wang a School of Economics and Management, Inner Mongolia University of Technology, Hohhot 010051, China. a 862003786@qq.com
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationApplication of Earned Value Management (EVM) for Effective Project Control
Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge
More informationAPPLICATION OF THE EVM METHOD AND ITS EXTENSIONS IN THE IMPLEMENTATION OF CONSTRUCTION OBJECTS
ENGINEERING STRUCTURES AND TECHNOLOGIES ISSN 2029-882X / eissn 2029-8838 2015 7(4): 189 196 doi:10.3846/2029882x.2016.1152168 APPLICATION OF THE EVM METHOD AND ITS EXTENSIONS IN THE IMPLEMENTATION OF CONSTRUCTION
More informationSelf-Assessment Questions for Module 07 Project Cost Management
Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses
More informationPlanning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique
Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,
More informationValue And Earned Schedule Management
EVM World 2013 Conference IPMC 2013 Title: An Analytical Utility For Earned Value And Earned Schedule Management Gary L. Richardson and Saranya Lakshmikanthan May 29, 2013 The popular technical literature
More informationLesson 7 The Project Budget
MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget
More informationConnecting Earned Value to the Schedule
Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned
More informationEarned Value Management An Overview March 2014
Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More informationApplication of Earned Value Analysis in Analysing Project Performance
Application of Earned Value Analysis in Analysing Project Performance Shyama Salikuma P.G Student (Structural Engg & CM) Dept. of Civil Engg, IIET Nellikuzhy, Kothamangalam Ms. Minu Anna Johny Assistant
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More informationNEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4
NEW HORIZONS ONLINE LIVE Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4 2 3 4 5 6 Other PMP Topics Cost Ranges Rough Order of Magnitude (ROM) (often done in the initiating process
More informationEarned Value Management - EVM
Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationFACULTEIT ECONOMIE EN BEDRIJFSKUNDE. HOVENIERSBERG 24 B-9000 GENT Tel. : 32 - (0) Fax. : 32 - (0)
FACULTEIT ECONOMIE EN BEDRIJFSKUNDE HOVENIERSBERG 24 B-9000 GENT Tel. : 32 - (0)9 264.34.61 Fax. : 32 - (0)9 264.35.92 WORKING PAPER A Comparison of Different Project Duration Forecasting Methods using
More informationEARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE
EARNED VALUE FEASIBILITY ANALYSIS FOR SOUTH GUJARAT REGION TO ENHANCE PROJECT PERFORMANCE Mr. Divyesh Joshi 1, Mr. Vyom B. Pathak 2, Ms. Neetu B. Yadav 3 M.E. Student, Civil Eng. Dept., SNPIT &RC, Umrakh
More informationJames A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)
Earned Value Management Results in Early Visibility and Management Opportunities March 21, 2007 James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL 33412 (561) 694-1646 E-mail: wrisley@pmassoc.com
More information30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering. sete2018.com.au BRETT THIELE
30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering BRETT THIELE A Standardised Data Set to Support Research on Earned Value and Earned Schedule Management Techniques Motivation
More informationCumulative trends Problems and issues since last report
Project Progress Report Format Progress since last report Current status of project 1. Schedule 2. Cost 3. Scope Cumulative trends Problems and issues since last report 1. Actions and resolution of earlier
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationProject health monitoring by Earned Value Analysis
13th International Software Testing Conference (STC 2013) December 0-06, 2013 in Bangalore, India. Project health monitoring by Earned Value Analysis Gangadhar. B. Kallur Honeywell Technology Solutions,
More informationMMZG 523 PROJECT MANAGEMENT
MMZG 523 PROJECT MANAGEMENT BITS Pilani Pilani Campus ARUN MAITY BITS Pilani Pilani Campus PROGRESS & PERFORMANCE MANAGEMENT AND EVALUATION CHAPTER NO 13 TEXTBOOK T1 Need Control holds people accountable
More informationEarned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC
Earned Schedule James C. Blair, PhD, PMP Project Management Institute May 19, 2010 2010 Paladin Project Management Consultants, LLC Earned Schedule Agenda Earned Value Management Background and Context
More information4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13) Unit 7 Slide 7.2.1 Lectures of 19/20/21 April 2017 Structure of a Project Monitoring
More informationEarned Value Management Guide
1 Earned Value Management Guide Earned Value Management (EVM) is a project management technique that objectively tracks physical accomplishment of work. More elaborately: EVM is used to track the progress
More informationMonitoring and Controlling RCC Work in Delayed Construction Projects
Monitoring and Controlling RCC Work in Delayed Construction s Nimesh Gujarati, Dr. B S Balapgol Post Graduate Student (Construction and Management), DYPCOE, Akurdi, Pune-44, Maharashtra, India Principal,
More information9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.
Project Management Progress and Performance Measurement and Evaluation Haeryip Sihombing 12 Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 McGraw-Hill/Irwin 13 2 Project Monitoring System for Control
More informationSchedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia
Schedule Analysis and Predictive Techniques Using Earned Schedule 16 th IPM Conference Tysons Corner, Virginia 17 th November 2004 Walt Lipke OC-ALC/MAS Tinker AFB OK walter.lipke@tinker.af.mil 405-736-3341
More informationPerformance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods
EPPM, Singapore, 20-21 Sep 2011 Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic Meghdad Attarzadeh 1 and David K H Chua 2 Abstract Estimation and
More informationCost Management Mock Exam. Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP
Cost Management Mock Exam Lab for PMP Exam Prep Course Part 2 #347 Instructor: Neal L. Rowland, PMP 10 Practice Questions Move at Your Own Pace Question 1 You are project manager for a $2.3M project that
More informationJefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7
Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationProject Management -- Monitoring the progress
Project Management -- Monitoring the progress Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 2 Structure of a
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationMohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators
Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience
More informationThe Mystery of Earned Value - An Oil & Gas Owner s Perspective
The Mystery of Earned Value - An Oil & Gas Owner s Perspective 15 June 2011 William Harroun Head of Programme Controls, BG Group What we are going to cover Cost and progress reporting before --- Earned
More informationnext level PMP Exam Preparation Formula Guide for the PMP Exam
next Formula Guide for the PMP Exam January 2017 n e x t l e v e l Page 1 What s Included: 1. Earned Value Formulas 2. Formulas 3. Float Formulas 4. Project Selection Formulas 5. Additional Formulas to
More information5-D Integrated Earned Value Analysis
5-D Integrated Earned Value Analysis Erol Yurtseven, October 2013 Budgeting Scheduling Design Coordination Quantity Survey Technical Office 3 4 Technical Office Design Dept & Technical Office 2 5 Cost
More informationNOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:
NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM
More informationEVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities
EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP
More informationPresenting Earned Value
Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What
More informationPass PMP in 21 Days - ITTO Toolbox PROCESS MAP
PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project
More informationEarned Value Management (EVM) and the Acquisition Program
American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.
More informationpm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationTRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA
TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L 1, Anne Ligoria S 2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor
More informationENGINEERING MANAGEMENT (GE
بسم هللا الرحمن الرحيم ENGINEERING MANAGEMENT (GE 404) 1 L E C T U R E # 12 Project Cost-Control Contents Objectives of the present lecture Integration of cost and schedule Aim of project cost control
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationHomework 6 Questions and Answers
I.E. 406 PROJECT SCHEDULING AND CONTROL Fall 2012 Murat Sandikcioglu (original by Dr.Onur ÇOKGÖR) Homework 6 Questions and Answers CRITICAL CHAIN PROJECT MANAGEMENT (CCPM) & EARNED VALUE ANALYSIS (EVA)
More informationProject Management Certification. Multiple Choice Questions
Project Management Certification (PMP) Project Management Certification (PMP) Multiple Choice Questions QUESTION 1 In Project Cost Management, which input is exclusive to the Determine Budget process?
More informationINTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz
INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ Introducing Project Cost Management Exercises & Quiz EXERCIS 1: Describe what activities are involved in resource planning EXERCIS 2: Answer the questions
More informationEARNED VALUE MANAGEMENT. Is it worth the effort?
EARNED VALUE MANAGEMENT Is it worth the effort? Session Objectives Examples of earned value in use. Why don t more Project Managers use EMV? Road Map to EVA Maturity? What you need to know? How is our
More information[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP
This template is downloaded from project-management.magt.biz [Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 19, 2015 [Ref. number] Marc Arnecke, PMP [Sub-Project,
More informationPresenting Earned Value
Successfully Presenting Earned Value Your guide to Earned Value Management What is Earned Value Management? Earned Value Management (EVM) is a project management system which combines schedule performance
More informationCarlos Consulting Group
Carlos Consulting Group Earned Value Management Building A Playhouse Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP June 20, 2007 Carlos Consulting Group
More informationEarned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;
Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,
More informationOptimization on Earned Value Method Combined with Critical Path
Optimization on Earned Value Method Combined with Critical Path Qi-bin Zheng and Xing Bi Abstract When calculating the schedule performance using the traditional earned value method, the earned value in
More informationA Study on Risk Analysis in Construction Project
A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------
More informationAdministration. Course Aim. Introductions
Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may
More informationProfessional Development Seminar Series
Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context
More informationUnderstanding the Differences. Accounting Practice for Measuring. Supertech Project Management
Understanding the Differences Between Earned Value and Accounting Practice for Measuring and Reporting Performance YOUR PRESENTER Roland Horat Managing Director Global Business, Substituting for James
More informationRETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1
RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0
More informationObjectives of Project Cost Control System
Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationDo Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion
Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion Stephen A. Book The Aerospace Corporation P.O. Box 92957 Los Angeles, CA 90009-2957 (310) 336-8655 stephen.a.book@aero.org Society of Cost
More informationThomas Carlos Consulting. Simple Earned Value Management
Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,
More informationThe Value of EVM. Earned Value Management
The Value of EVM Earned Value Management Good decisions are based on knowledge and not on numbers. - Plato What is EVM? A project management technique for measuring project performance and progress, in
More informationEVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS
EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:
More informationVanguard Global Capital Markets Model
Vanguard Global Capital Markets Model Research brief March 1 Vanguard s Global Capital Markets Model TM (VCMM) is a proprietary financial simulation engine designed to help our clients make effective asset
More informationANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?
ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING? KANSAS CITY CHAPTER PMI PROFESSIONAL DEVELOPMENT DAYS SEPTEMBER 2012 Glenn Meyer (c) Glenn Meyer, except as noted. 10 Sep 2012 1
More information