Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Size: px
Start display at page:

Download "Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management"

Transcription

1 Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

2 Slide 1 Looking Glass Development, LLC (303) / (888) S. Ulster St. #150 Denver, CO information@lookingglassdev.com

3 Slide 2 All the processes required to ensure timely completion of the project The major output of these processes is the project schedule Planning Process Group 6. Project Time Management 6.1 Plan Schedule Management Monitoring and Controlling Process Group 6. Project Time Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.7 Control Schedule 6.6 Develop Schedule v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/2013 2

4 Slide Plan Schedule Management Defines the rules for developing & managing the schedule. The benefit of this process is that it provides guidance & direction on how the schedule will be managed. Planning Process Group 6. Project Time Management 6.2 Define Activities 6.1 Plan Schedule Management 6.4 Estimate Activity Resources 6.3 Sequence Activities 6.5 Estimate Activity Durations 6.6 Develop Schedule v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/2013 3

5 Slide Plan Schedule Management Inputs.1 Project management plan.2 Project charter.3 Enterprise environmental factors.4 Organizational process assets Tools & Techniques.1 Expert judgment.2 Analytical techniques.3 Meetings Outputs.1 Schedule Management plan v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/2013 4

6 Slide Define Activities Creating a list of all the work that needs to be done to produce the project deliverables Work packages are decomposed into schedule activities These schedule activities provide a basis for estimating, scheduling, executing, and monitoring and controlling Planning Process Group 6. Project Time Management 6.2 Define Activities 6.3 Sequence Activities 6.1 Plan Schedule Management 6.6 Develop Schedule 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/2013 5

7 Slide 6 Rolling Wave Planning Less Details Project Initiation Analyze Existing Situation Define New System Requirements Purchase And Install Package Construct & Test & Test System Implement Components System Planning Details More Details Project Start Time v Copyright and all rights reserved 2013 Looking Glass Development, LLC.

8 Slide Define Activities Inputs.1 Schedule management plan.2 Scope baseline.3 Enterprise environmental factors.4 Organizational process assets Tools & Techniques.1 Decomposition.2 Rolling wave planning.3 Expert judgment Outputs.1 Activity list.2 Activity attributes.3 Milestone list v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/2013 7

9 Slide Sequence Activities Ordering the activities that have been defined and assigning logical dependencies Planning Process Group 6. Project Time Management 6.1 Plan Schedule Management 6.2 Define Activities 6.4 Estimate Activity Resources 6.3 Sequence Activities 6.5 Estimate Activity Durations 6.6 Develop Schedule v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/2013 8

10 Slide 9 Finish to Start Start to Start Finish to Finish Start to Finish A S - S B C PDM F - S D E S F is not common F G H F - F v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 9/18/2013 9

11 Slide 10 Conditional Diagramming GERT is most common Allows for probability Allow for looping 20% Eyeball Diagram 80% A B C v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/

12 Slide 11 Types of Dependencies Mandatory (hard logic) inherent in the work Discretionary (soft logic) from best practices or as desired External v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/

13 Slide 12 Other Terms Lead Time Dependency relationship which allows the second task to start prior to the completion of the first. Lag Time Dependency relationship which requires the second task to wait. One-Point Estimate A single value estimate. Regression Analysis a graphic analysis to track if two variables are related. Heuristic A rule of thumb. Learning Curve The improvement achieved by doing an activity more than once. Monte Carlo Simulation A computer model which allows the analyst to simulate an activity 1,000 or more times to achieve a probability of a result. v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/

14 Slide Sequence Activities Inputs.1 Schedule management plan.2 Activity list.3 Activity attributes.4 Milestone list.5 Project scope statement.6 Enterprise environmental factors.7 organizational process assets Tools & Techniques.1 Precedence diagramming method (PDM).2 Dependency determination.3 Applying leads and lags Outputs.1 Project schedule network diagrams.2 Project document updates v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/

15 Slide Estimate Activity Resources Inputs.1 Schedule management plan.2 Activity list.3 Activity attributes.4 Resource calendars.5 Risk register.6 Activity cost estimates.7 Enterprise environmental factors.8 Organizational process assets Tools & Techniques.1 Expert judgment.2 Alternatives analysis.3 Published estimating data.4 Bottom-up estimating.5 Project management software Outputs.1 Activity resource requirements.2 Resource breakdown structure.3 Project document updates v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/

16 Slide Estimate Activity Durations Compilation (not the sum) of activity duration estimates results in the project duration All supporting data is documented Uses identified risks & cost estimates Accuracy improves over time Ranges, e.g. 280 days 10% Planning Process Group 6. Project Time Management 6.1 Plan Schedule Management 6.2 Define Activities 6.4 Estimate Activity Resources 6.3 Sequence Activities 6.5 Estimate Activity Durations 6.6 Develop Schedule v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/

17 Slide Estimating Activity Duration Inputs.1 Schedule management plan.2 Activity list.3 Activity attributes.4 Activity resource requirements.5 Resource calendars.6 Project scope statement.7 Risk register.8 Resource breakdown structure.9 Enterprise environmental factors.10 Organizational process assets Tools & Techniques.1 Expert judgment.2 Analogous estimating.3 Parametric estimating.4 Three point estimating.5 Group decision-making techniques.6 Reserve analysis Outputs.1 Activity duration estimates.2 Project document updates v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 7/31/

18 Slide 17 Project Evaluation & Review Technique (PERT) v Copyright and all rights reserved 2013 Looking Glass Development, LLC.

19 Slide 18 Project Evaluation & Review Technique (PERT) 4X Most PERT Optimistic + Likely + Pessimistic Weighted = 6 Average PERT Pessimistic - Optimistic Standard = 6 Deviation v Copyright and all rights reserved 2013 Looking Glass Development, LLC.

20 Slide Develop Schedule Iterative Determines planned start and end dates for activities and the whole project. Baseline for measuring progress. Planning Process Group 6. Project Time Management 6.1 Plan Schedule Management 6.2 Define Activities 6.4 Estimate Activity Resources 6.3 Sequence Activities 6.5 Estimate Activity Durations 6.6 Develop Schedule v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 1/29/

21 Slide 20 CPM The Critical Path is the project path which will be the longest duration or where all activities have zero float The Critical Path does not necessarily have the greatest risk The Critical Path determines the earliest completion of the project v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 1/29/

22 Slide 21 The Critical Path Method EF = ES + DUR LS = LF DUR Float = LF EF or LS - ES Deliverable A Deliverable C Deliverable D Deliverable B Deliverable E ES DUR EF Deliverable LS Float LF Deliverable F v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 1/29/

23 Slide 22 Resource Optimization After CPM. Redistribute resource assignments where a resource is needed on more than one task in the same time period. Can change the critical path. v Copyright and all rights reserved 2016 Looking Glass Development, LLC.

24 Slide 23 Critical Chain Method Critical Chain = Longest chain of dependent tasks with zero slack taking into consideration resource constraints. Progress equal burn rate of the buffers vs. work complete v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 1/29/

25 Slide 24 Inputs.1 Schedule management plan.2 Activity list.3 Activity attributes.4 Project schedule network diagram.5 Activity resource requirements.6 Resource calendars.7 Activity duration estimates.8 Project scope statement.9 Risk register.10 Project staff assignments.11 Resource breakdown structure.12 Enterprise environmental factors.13 Organizational process assets 6.6 Develop Schedule Tools & Techniques.1 Schedule network analysis.2 Critical path method.3 Critical chain method.4 Resource optimization techniques.5 Modeling techniques.6 Leads and lags.7 Schedule compression.8 Scheduling tool Outputs.1 Schedule baseline.2 Project schedule.3 Schedule data.4 Project calendars.5 Project management plan updates.6 Project document updates v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 1/29/

26 Slide Control Schedule Part of Integrated Change Control Determine the current status of the project schedule Influence the factors that create schedule changes. Determine that the project schedule has changed. Manage the changes as they occur. Monitoring and Controlling Process Group 6. Project Time Management 6.7 Control Schedule v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 1/29/

27 Slide 26 Inputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data.6 Organizational process assets 6.7 Control Schedule Tools & Techniques.1 Performance reviews.2 PM software.3 Resource optimization techniques.4 Modeling techniques.5 Leads & lags.6 Schedule compression.7 Scheduling tool Outputs.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan updates.5 Project documents updates.6 Organizational process assets updates v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 26

28 Slide 27 Project Time Management Summary Seven (7) processes PERT, GERT, PDM, CPM, CCPM Crashing, fast tracking Decomposition, baseline, float or slack Schedule development is iterative v Copyright and all rights reserved 2013 Looking Glass Development, LLC. 27

29

30 Review Questions Part 1: 1. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

31 2. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

32 3. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

33 4. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D 5. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

34 6. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

35 7. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

36 8. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

37 9. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

38 10. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

39 11. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

40 12. Which of the following diagrams best represents the diagram described in the image using PDM? A. Option A B. Option B C. Option C D. Option D

41 Review Questions Part 2: 1. If a resource gives you a pessimistic estimate of 10 days and an optimistic estimate of 6 days. What is the standard deviation? A B. 4 C D If a resource gives you a pessimistic estimate of 9 days and an optimistic estimate of 4 days. What is the standard deviation? A B C D If a resource gives you a pessimistic estimate of 5 days and an optimistic estimate of 2 days. What is the standard deviation? A B. 0.5 C D If a resource gives you a pessimistic estimate of 15 days and an optimistic estimate of 6 days. What is the standard deviation? A. 8.0 B C. 9.5 D If a resource gives you a pessimistic estimate of 17 days and an optimistic estimate of 8 days. What is the standard deviation? A B C. 1.5 D If a resource gives you a pessimistic estimate of 25 days and an optimistic estimate of 15 days. What is the standard deviation? A B C D

42 7. If a resource gives you a pessimistic estimate of 28 days and an optimistic estimate of 17 days. What is the standard deviation? A B C D If a resource gives you a pessimistic estimate of 21 days and an optimistic estimate of 12 days. What is the standard deviation? A B C. 14 D If a resource gives you a pessimistic estimate of 54 days and an optimistic estimate of 36 days. What is the standard deviation? A. 3.0 B C D If a resource gives you a pessimistic estimate of 31 days and an optimistic estimate of 19 days. What is the standard deviation? A B. 2.0 C D Your boss comes into your office and wants the schedule estimate for your project in which you have 99% confidence. If your worst case estimate is 10 months, your best case estimate 6 months and your most likely case estimate is 7 months what do you provide him? A to 8.67 months B. 6 to 10 months C to 9.33 months D. approximately 10 months

43 Review Questions Part 3: 1. Using the included table what is the critical path for the project? A. B, C, D, F, G, H B. A, C, D, E, G, H C. A, B, C, D, E, F, G, H D. A, B, C, D, F, G, H 2. Using the included table what is the project duration using CPM? A. 35 B. 38 C. 34 D. 4) 37

44 3. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. A B. B C. D D. F 4. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. B B. E C. F D. H

45 5. What is the critical path for the included table? A. 1, 2, 6, 8, 11 B. 1, 3, 5, 7, 11 C. 1, 4, 9, 7, 11 D. 1, 4, 9, 10, Using CPM and the included table, what is the project duration? A. 44 B. 42 C. 45 D. 51

46 7. Based upon the included table and CPM, which of the following tasks is not critical? A. 1 B. 2 C. 4 D Based upon the included table and CPM, which of the following tasks is not critical? A. 4 B. 9 C. 6 D. 10

47 9. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 8 B. 4 C. 9 D What is the critical path for the included table? A. A, C, F, H, K, M B. A, D, G, L, M C. A, B, E, H, K, M D. A, B, E, I, J, M

48 11. Using the included table, what is the project duration using CPM? A. 59 B. 63 C. 67 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. A B. B C. C D. J

49 13. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. F B. E C. I D. J 14. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. A B. H C. E D. J

50 15. Using the included table what is the critical path for the project? A. 1, 3, 6, 7, 9, 10 B. 1, 3, 6, 7, 8, 10 C. 1, 2, 5, 7, 8, 10 D. 1, 2, 5, 7, 9, Using the included table what is the project duration using CPM? A. 66 B. 51 C. 48 D. 62

51 17. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 2 B. 5 C. 3 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 2 B. 4 C. 5 D. 7

52 19. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 6 B. 7 C. 9 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 2 B. 5 C. 8 D. 7

53 21. Using the included table what is the critical path for the project? A. A, B, C, F, G, H B. A, B, D, F, G, H C. A, B, C, D, E, H D. A, B, D, E, H 22. Using the included table what is the project duration using CPM? A. 38 B. 36 C. 42 D. 40

54 23. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. D B. B C. C D. E 24. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. B B. F C. D D. E

55 25. Using the included table what is the critical path for the project? A. 2, 4, 8, 9 B. 1, 3, 5, 6, 9 C. 2, 4, 8, 7, 9 D. 1, 3, 5, 7, Using the included table what is the project duration using CPM? A. 45 B. 43 C. 44 D. 46

56 27. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 2 B. 3 C. 5 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 3 B. 4 C. 5 D. 6

57 29. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 3 B. 5 C. 6 D Using the included table, what is the critical path for the project? A. A, B, D, G, J, L, M B. A, C, E, H, I, L, M C. A, C, E, G, J, L, M D. A, B, F, G, K, L, M

58 31. Using the included table, what is the project duration using CPM? A. 52 B. 49 C. 50 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. E B. G C. J D. B

59 33. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. E B. G C. D D. L 34. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. F B. C C. G D. J

60 35. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. C B. H C. E D. J 36. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. I B. E C. G D. L

61 37. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. E B. K C. J D. G 38. Using the included table, what is the critical path for the project? A. 1, 3, 7, 10, 12, 13 B. 1, 3, 7, 9, 12, 13 C. 1, 3, 6, 10, 12, 13 D. 1, 2, 5, 8, 11, 13

62 39. Using the included table, what is the project duration using CPM? A. 46 B. 43 C. 47 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 2 B. 3 C. 6 D. 10

63 41. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 3 B. 4 C. 10 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 3 B. 6 C. 7 D. 10

64 43. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. 10 B. 12 C. 6 D Using the included table, what is the critical path for the project? A. A, B, C, F, I, K, M B. A, B, C, E, I, K, M C. A, B, D, G, I, K, M D. A, B, D, G, J, L, M

65 45. Using the included table, what is the project duration using CPM? A. 61 B. 60 C. 58 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. D B. F C. G D. I

66 47. Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. G B. I C. J D. K 48. Using the included table, what is the critical path for the project? A. A, B, E, G, J, M. O B. A, C, D, F, I, K, L, N, O C. A, C, D, F, H, I, K, N, O D. A, C, D, F, I, K, N, O

67 49. Using the included table, what is the project duration using CPM? A. 51 B. 48 C. 53 D Using CPM to evaluate the project represented by the included table, which of the following tasks are not on the critical path? A. I B. G C. K D. N

68 51. Using CPM to evaluate the project represented by the included table, which of the following tasks is not on the critical path? A. F B. K C. L D. N

69 Review Questions Part 4: 1. When comparing the critical chain to the critical path which of the following is true? A. The critical path accounts for resource limitations B. The critical chain accounts for resource limitations C. The critical path uses aggressive estimates D. The critical chain uses pessimistic estimates 2. The critical chain methodology schedules each activity to: A. Occur as late as possible B. Occur as soon as possible C. Occur with the middle schedule D. Any of the above 3. The critical chain method focuses on managing what? A. Total project float B. The critical path C. Buffers D. Specific network paths 4. What is the major difference between the critical path and the critical chain? A. The critical path takes into account resources B. The critical path is always longer C. The critical chain is always longer D. The critical chain takes into account resources 5. Which of the following statements about the critical chain is true? A. Critical path management does not allow multi-tasking B. Critical chain management uses bar charts C. Critical chain management does not allow multi-tasking D. All of the above are true

70 6. Which of the following statements about critical chain management is true? A. It is a methodology that creates an optimized project schedule that considers resource limitations B. It is a methodology that works best when resources are unlimited but schedule milestones are restricted C. It makes extensive use of PERT D. It is used primarily with agile methodologies in information technology projects. 7. Which of the following is not a step in the theory of constraints? A. Identify the constraint B. Identify the next systems constraint C. Exploit the constraint D. Subordinate everything to the constraint 8. According to the TOC most current management philosophies focus on what? A. Throughput management B. Schedule management C. Cost management D. Balancing all of the above 9. According to the TOC, what is the only way to achieve good cost performance? A. Achieve good local performance everywhere B. Manage costs throughout the system C. Have visibility to all costs D. Have all project team members know the project costs

71 10. Using the table above, what is the project's critical chain excluding feed buffers and assuming 30% for all other buffers? A. 1, 3, 5, 7, 10 B. 1, 2, 6, 8, 10 C. 1, 2, 6, 8, 10 D. 1, 2, 5, 7, Using the table above, what is the project's critical chain excluding feed buffers and assuming 30% for other all buffers? A. 41 B. 28 C. 52 D. 44

72 12. Using the included table and CCPM, what is the project's expected duration assuming project and feeder buffers of 30%? A. 52 B. 71 C. 74 D After which of the following tasks which you place a feed buffer using CCPM to analyze the include task list? A. 8 B. 4 C. 9 D. 3

73 14. After which of the following tasks which you place a feed buffer using CCPM to analyze the include task list? A. 7 B. 8 C. 9 D After which of the following tasks which you place a resource buffer using CCPM to analyze the include task list? A. 2 B. 3 C. 5 D. 7

74 16. After which of the following tasks which you place a resource buffer using CCPM to analyze the include task list? A. 7 B. 5 C. 9 D Using CCPM to evaluate the included table of tasks, what is the project's critical chain? A. A, C, F, H, K, M B. A, B, E, I, J, M C. A, D, G, F, H, K, M D. A, B, E, E, F, H, K, M

75 18. Using the table above, what is the project's critical chain excluding feed buffers and assuming 30% for all other buffers? A. 73 B. 62 C. 95 D What is the length of the project buffer represented by the included table using CCPM and assuming a 30% rate for all other buffers? A. 29 B. 19 C. 22 D. 16

76 20. What is the overall project duration (excluding feed buffers) for the project represented by the included table using CCPM and assuming a buffer rate of 30% for all buffers? A. 95 B. 73 C. 91 D Using the included table and CCPM, after which of the following tasks would you place a feed buffer? A. D B. A C. H D. C

77 22. Using the included table and CCPM, after which of the following tasks would have a feed buffer? A. B B. J C. D D. G 23. Using the included table and CCPM, after which of the follow tasks would you place a feed buffer? A. H B. L C. K D. B

78 24. Using the included table and CCPM and assuming a 30% rate for all buffers, what is the project's critical chain? A. 1, 3, 6, 7, 8, 10, 11 B. 1, 3, 4, 6, 7, 8, 10, 11 C. 1, 2, 5, 7, 8, 11 D. 1, 2, 5, 9, 7, 10, Based on the included table and using CCPM what is the length of the critical chain? A. 77 B. 100 C. 81 D. 86

79 26. Using the included table, CCPM, and assuming 30% for all buffers, what is the length of the project buffer? A. 77 B. 24 C. 19 D What is the overall project duration (excluding feed buffers) for the project represented by the included table using CCPM and assuming a buffer rate of 30% for all buffers? A. 77 B. 81 C. 92 D. 100

80 28. Based upon the included table and CCPM, what is the critical chain for the project? A. 1, 3, 5, 8, 9 B. 2, 4, 6, 8, 9 C. 2, 4, 5, 7, 9 D. 1, 3, 6, 8, Based upon the included table and CCPM what is the project's critical chain length excluding buffers? A. 42 B. 43 C. 45 D. 59

81 30. Based upon the included table, CCPM, and assuming a buffer rate of 30% what is the length of the project buffer? A B C D What is the overall project duration (excluding feed buffers) for the project represented by the included table using CCPM and assuming a buffer rate of 30% for all buffers? A B C D. 76.7

82 32. Using the included table and CCPM, after which of the following tasks would you place a feed buffer? A. 1 B. 2 C. 6 D Using the included table and CCPM, after which task would you place a feed buffer? A. 7 B. 5 C. 3 D. 1

83 34. Using the included table and CCPM, what is the project's critical chain excluding feed buffers? A. A, B, D, F, G, H B. A, B, C, D, F, G, H C. A, B, D, E, H D. A, B, C, E, G, H 35. Using the included table and CCPM, what is the critical chain length? A. 54 B. 60 C. 62 D. 70

84 36. Using the included table, CCPM and assuming a 30% buffer rate, what is the project buffer? A. 14 B C. 16 D What is the overall project duration (excluding feed buffers) for the project represented by the included table using CCPM and assuming a buffer rate of 30% for all buffers? A. 64 B. 65 C D. 70

85 38. Using the included table and CCPM, after which of the following tasks would you place a feed buffer? A. B B. E C. D D. G

86 Review Questions Part 5: 1. Which of the following is the last process found in Time Management? A. Define activities B. Estimate activity durations C. Develop schedule D. Control schedule 2. Which of the following is not a process found in Time Management? A. Create WBS B. Estimate activity resources C. Develop schedule D. Estimate activity durations 3. Which of the following is the first process found in Time Management? A. Estimate activity durations B. Develop schedule C. Define activities D. Plan schedule management 4. What is the variance of a project that has a best case estimate of 6, most likely case estimate of 7, and a worst case estimate of 10? A B C D What is the variance of a project that has a best case estimate of 15, most likely case estimate of 19, and a worst case estimate of 25? A B C D What is the variance of a project that has a best case estimate of 17, most likely case estimate of 21, and a worst case estimate of 28? A B C D. 3.36

87 7. What is the variance of a project that has a best case estimate of 12, most likely case estimate of 15, and a worst case estimate of 21? A B C D What is the variance of a project that has a best case estimate of 36, most likely case estimate of 41, and a worst case estimate of 54? A B C D What is the variance of a project that has a best case estimate of 19, most likely case estimate of 24, and a worst case estimate of 31? A B C D Your project is significantly over budget and behind schedule. It is critical that you determine your projected duration. To gain a better understanding of the project you analyze the sequence of deliverables, activities or tasks to find the ones with the least amount of schedule flexibility. What technique are you using? A. GERT B. CPM C. PERT D. PDM 11. A project manager is discussing her project with her boss. They are concerned that the project might be falling behind schedule and decide they must determine the project's likely completion date and where any flexibility exists. Which of the following tools would best provide this information? A. AOA B. PDM C. CPM D. Network Diagramming

88 12. You are the project manager for a new product. You are in the planning phase of your project and have just been told by one of your senior resources that they require the completed schematics before they can begin to build the product prototype. This is an example of what kind of dependency? A. Mandatory B. Discretionary C. Internal D. External 13. You are the project manager at a major pharmaceuticals company. You are planning the release of a new drug and must wait for regulatory approval before you can begin manufacture of the drug. This is an example of what kind of dependency? A. Discretionary B. Mandatory C. Internal D. External 14. Which of the following is a type of bar chart? A. Gaussian distribution B. Scatter plot C. Gantt Chart D. Logit model 15. As a general rule, which of the following is better illustrated by network diagrams than bar charts? A. Project progress B. Logical relationships between activities C. The project's critical chain D. Resource needs 16. Which of the following is not correct about PDM? A. The critical path always has dummy tasks B. Every network has at least one critical path C. The network displays all task interdependencies D. Tasks not on the critical path has slack or float

89 17. Which of the following is not an input to the define activities process? A. Milestone lists B. Scope baseline C. Enterprise environmental factors D. Organizational process assets 18. A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Fifth Edition, Project Management Institute, Inc., Which of the following is an input to the define activities process? A. Activity attributes B. Precedence diagram C. Rolling wave plan D. Scope baseline 19. Which of the following is not a tool or technique used in the define activities process? A. Decomposition B. Precedence Diagramming C. Rolling wave plan D. Expert judgment 20. Which of the following is a tool or technique for the define activities process? A. PDM B. Rolling wave plan C. GERT D. Dependency determination 21. Which of the following is a tool or technique for the define activities process? A. Expert judgment B. Schedule network templates C. Milestone management D. Activity attribute development 22. Which of the following is not an output of defining activities? A. Activity lists B. Activity attributes C. Project network diagrams D. Milestone lists

90 23. Which of the following is not an output of the define activities process? A. Activity attributes B. Activity list C. Milestone list D. Activity list updates 24. Which of the following is not an input to the sequence activities process? A. WBS B. Project scope statement C. Activity list D. Activity attributes 25. Which of the following is not an input to sequence activities? A. Organizational process assets B. Milestone list C. WBS D. Project scope statement 26. Which of the following is an input to sequence activities? A. Organizational process assets B. WBS dictionary C. Scope baseline D. Work breakdown structure 27. Which of the following is not a tool or technique for sequence activities? A. Precedence diagramming method B. Decomposition C. Applying leads & lags D. Dependency determination 28. Which of the following is not a tool or technique for activity sequencing? A. Precedence diagramming method B. Dependency determination C. Project schedule network diagrams D. Applying leads and lags

91 29. Which of the following is a tool or technique for activity sequencing? A. Dependency determination B. Decomposition C. WBS D. GERT 30. Which of the following is a tool or technique for activity sequencing? A. Expert Judgment B. Applying leads and lags C. Alternatives analysis D. Decomposition 31. Which of the following is not an output from activity sequencing? A. Schedule network diagrams B. Milestone list C. Project document updates D. All of the above are outputs 32. Which of the following is an output from activity sequencing? A. RBS B. PERT estimate C. Network diagrams D. Approved changes 33. Which of the following is not an input to estimate activity resources? A. WBS dictionary B. Activity list C. Resource calendars D. Organizational process assets 34. Which of the following is an input to estimate activity resources? A. Precedence diagrams B. Requested changes C. Milestone lists D. Resource calendars

92 35. Which of the following is a tool or technique used to estimate activity resources? A. Alternatives analysis B. Precedence diagramming method C. GERT D. Dependency determination 36. Which of the following is a tool or technique used to estimate activity resources? A. Resource breakdown structure B. Planning component C. Published estimating data D. Rolling wave plan 37. Which of the following is not a tool or technique used to estimate activity resource? A. Expert Judgment B. Templates C. Alternatives analysis D. Bottom-up estimating 38. Which of the following is not an output to estimate activity resource? A. Requested changes B. RBS C. Activity resource requirements D. Project schedule network diagrams 39. Which of the following is an output of the estimate activity resources process? A. Activity list B. RBS C. Milestone list D. Required changes 40. Which of the following is not an input to the estimate activity durations process? A. Milestone list B. Project scope statement C. Organizational process assets D. Resource calendars

93 41. Which of the following is not an input to the estimate activity durations process? A. Expert judgment B. Enterprise environmental factors C. Organizational process assets D. Activity attributes 42. Which of the following is not a tool or technique used in the estimate activity durations process? A. PDM B. Expert judgment C. Reserve analysis D. Parametric estimating 43. Which of the following is not a tool or technique used in the estimate activity durations process? A. Analogous estimating B. PERT Analysis C. Three-point estimating D. Parametric estimating 44. Which of the following is an output from the estimate activity durations process? A. Activity list updates B. Requested changes C. Milestone updates D. Activity duration estimates 45. Which of the following is not an input to the develop schedule process? A. Requested changes B. Resource calendars C. Project schedule network diagrams D. Activity attributes 46. Which of the following is not a tool or technique used in the develop schedule process? A. Critical Path Method B. Critical Chain Method C. Precedence Diagramming Method D. Resource leveling

94 47. Which of the following is not a tool or technique used in the develop schedule process? A. Schedule network analysis B. Project schedule modeling C. Lead and lags D. Resource optimization techniques 48. Which of the following is a tool or technique used in the develop schedule process? A. Project schedule modeling B. GERT C. Schedule compression D. RBS 49. Which of the following is not an output from the develop schedule process? A. Project schedule B. Schedule data C. Schedule baseline D. Activity list updates 50. Which of the following is not an output from the develop schedule process? A. Project schedule B. Project document updates C. Activity cost estimates D. Schedule data 51. Which of the following is an output from the develop schedule process? A. Activity cost estimate updates B. Project document updates C. Approved changes D. Activity duration estimates 52. Which of the following is not an input to the control schedule process? A. Project schedule B. Work performance data C. Organizational process assets D. Schedule management plan

95 53. Which of the following is not an input to the control schedule process? A. Performance reports B. Project schedule C. Project management plan D. Organizational process assets 54. Which of the following is not a tool or technique used for the control schedule process? A. Resource optimization techniques B. Schedule management C. Modeling techniques D. Schedule compression 55. Which of the following is not a tool or technique used in the control schedule process? A. Scheduling tool B. Schedule compression C. Project document updates D. Leads and lags 56. Which of the following is not an output from the control schedule process? A. Work performance information B. Change requests C. Project management plan updates D. What-if scenario updates 57. Which of the following is an output from schedule control? A. Recommended preventive actions B. Change requests C. Approved changes D. Project schedule updates 58. Which of the following terms represents a method of problem solving that relies of inductive reasoning from past experience or expert judgment when there is no relevant mathematical algorithm available? A. A heuristic B. A logit C. GERT D. Analogous estimating

96 59. Which of the following best describe the amount of time one activity can be delayed without impacting the early start of its succeeding task or activity? A. Lead time B. Float C. Lag time D. None of the above 60. Which of the following terms best represents the amount of time one activity can begin prior to the completion of its preceding dependent task? A. Lag time B. Lead time C. Float D. None of the above 61. Which of the following statements is correct? A. A network diagram allows you to determine the shortest time the project can take. B. A WBS allows you to determine the longest chain of dependent tasks. C. Changing the end date of the project will cause the network diagram to change. D. The critical path will always contain dummy tasks. 62. Which of the follow statements about a milestone is true? A. A milestone can have any duration B. A milestone has the same duration as the task, activity or deliverable it represents C. A milestone always has zero duration D. None of the above 63. Your boss asks you to use Monte Carlo Analysis to evaluate your project. For what purpose was this request most likely made? A. To create an activities estimated length B. To gain an indication of the risk in the project C. To define the order in which activities occur D. Define project resource requirement

97 64. On Monday morning your boss comes into your office and asks about the amount of slack you have on a specific activity in your project. This is determined by: A. Performing a PERT analysis B. Estimating the task or activity length C. Creating a PDM diagram D. Determining the total amount of time that a schedule activity may be delayed without impacting the project delivery. 65. Your boss enters your office and is concerned that a particular activity will delay the delivery of the project. What is the best thing to do: A. Determine if the activity is on the critical path B. Explain why your boss should not worry C. Perform a GERT analysis D. Examine the activity's risk triggers 66. You and your project team have obtained estimates for your project, assigned resources, and developed a precedence diagram of the project. Several of your resources are very concerned that two of the activities are not being focused on enough and will end up delaying the project as they are critical components of the project's end product. What is the best thing to do? A. Sit down with the resources to discuss the project Gantt chart B. Determine if the activities in question are on the critical path C. Examine the project's risk register D. Evaluate alternative project 67. Which of the following best describes the impact of multiple critical paths on a project? A. The project takes longer to complete B. The project is more expensive C. The project takes more resources to manage D. The project risk increases 68. You and your project team have just completed the development of your PDM diagram. The current diagram shows there are three (3) critical paths in your project. What is the best thing to do next? A. Re-evaluate the network for errors B. Develop the project schedule C. Examine the project risk register D. Discuss alternative networks with your team

98 69. In discussing your project with management you determine that the project schedule is the most flexible and the project scope is the least flexible. If the allowable monthly project expenditures are fixed what is the best thing to do? A. Level the resources B. Examine the project's critical path C. Analyze the project's life cycle costs D. Crash the project 70. Your manager asks you to produce a report on your project for management. Which of the following would best meet the request? A. Bar chart B. PERT chart C. Milestone chart D. Gantt chart 71. You and your project team have just completed the development of your project schedule. Based on constraints provided by the project sponsor, the project is scheduled to be completed after the project deadline. Assuming that costs are the least important constraint and scope is the most important which of the following is the best thing to do? A. Fast track the project B. Crash the project C. Reassess the critical path D. Develop a critical chain model for the project 72. You and your project team have just completed the development of your project schedule. Based on constraints provided by the project sponsor, the project is scheduled to be completed after the project deadline. Assuming that costs are the most important constraint and scope is the least important which of the following is the best thing to do? A. Crash the project B. Reassess the critical path C. Develop a new project schedule D. Fast track the project

99 73. Your manager comes to you and demands that you complete your project three (3) weeks early. What is the best thing to do? A. Meet with your project team to examine alternatives for crashing and fast tracking. B. Tell your boss the project critical path does not allow for a three week early completion C. Ask the project to work overtime D. Ask your manager if you can reduce the scope of the project. 74. When evaluating the impact on your project of crashing, which of the following should be included in the evaluation? A. The project sponsor's interest B. Risks associated with the schedule changes C. The amount of overtime to be worked D. The impact of a reduction in project scope 75. Which of the following PM processes requires the project manager to reach an agreement with the activity resources on the calendar date for each activity? A. Sequence activities B. Estimate activity durations C. Estimate activity resources D. Develop schedule 76. It is late Friday afternoon when your project sponsor informs you that the project schedule has been reduced by two (2) weeks. What is the best thing to do? A. Meet with your project team to determine options for schedule compression B. Cut the project scope C. Crash the project D. Inform management that the date cannot be met

100 77. As the project manager you estimate the time that will be needed for each activity, assign tasks to specific resources and then add the estimates to create the project estimate. You then use this value to establish the project delivery date which you provide to the project sponsor. What is incorrect with this process? A. The project manager created the estimates without the team. Additionally, summing the tasks will lead to a significantly longer project duration. B. Project duration estimates should be developed by the project sponsor C. The project manager created the estimates without the project resources and did not use a network diagram to define the critical path D. The project completion date should be derived from an evaluation of the triple constraints 78. You are the project manager for a large construction project. It is early in the project lifecycle and you have completed the activity definition. In analyzing the activities you see a number of activities that are dependent on each other but can start at the same time. To properly evaluate this project which methodology is best? A. CPM B. PDM C. AOA D. GERT 79. You are the project manager for a US $250,000 software development project. You are working with your project team and determine that the project has a number of project tasks that are dependent on each other. However, one of your team members also points out that the tasks can finish at the same time. Which of the following is the best technique to understand this situation? A. Critical path method B. Activity on arrow method C. Precedence diagramming method D. Program evaluation and review technique

101 80. You are the project manager for a large consulting company leading a process improvement project for your organization's largest client. The project currently has a CPI of 1.04 and SPI of.98. Your customer has just asked if you can produce a diagram the shows probabilistic project paths. Which of the following tools would be best in this situation? A. Graphical evaluation and review technique B. Program evaluation and review technique C. Critical path method D. Precedence diagramming method 81. Which of the following is best suited to define a project network that has potential looping of the activities, deliverables or tasks? A. PERT B. CPM C. GERT D. PDM 82. You are the project manager for a software development project with an estimated budget of US $650,000. You have just completed the duration estimates, and activity sequencing for your project. Which of the following do you still need to complete the initial project schedule? A. Approved change request B. Contingency reserves C. Recommended change requests D. Schedule management plan 83. You are just taking over for a project manager who was forced to take a medical leave of absence. Your project has a CPI of 93 and an SPI of 89. To gain a better understanding of how the previous project manager was managing schedule changes to which of the following would you turn? A. The project plan B. The project schedule C. The schedule management plan D. The project Gantt chart

102 84. You are taking over for a project manager who was terminated. The previous project manager was using weighted average duration estimates to develop the schedule network. What type of modeling are you using? A. Monte Carlo analysis B. Program evaluation and review technique analysis C. Critical chain analysis D. Critical path analysis 85. You are the project manager for a large mechanical engineering project. You have completed your scope statement, the WBS, the resource estimate, duration estimates, and the network diagram. Which of the following is the thing you should do next? A. Create the schedule B. Complete the cost estimates C. Define the project budget D. Solicit purchase 86. You are working as a project manager and have completed the scope statement, resource estimates, and the WBS. You have just received the activity duration estimates. Which of the following is your best course of action? A. Finalize the schedule B. Compress the schedule C. Complete the risk register D. Develop RFPs 87. One of your resources comes into your office to discuss their task. The project has a CPI of.89 and an SPI of.92. The resource's task has an early start of week 14, a late start of week 17. What do you know about this activity? A. It is ahead of schedule B. It is behind schedule C. It is on the critical path D. It is not on the critical path

103 88. You have an activity that has an ES of 12 weeks, a LS of 15 weeks, an EF of 21 weeks, and a LF of 24 weeks. What do you know about this activity? A. It is not on the critical path B. It is ahead of schedule C. It is behind schedule D. It is on the critical path 89. You are leading a project that you have just learned is 3 weeks behind schedule. The dependencies are discretionary. The project has an SPI of.81 and a CPI of.83. Due to cost overruns you cannot add more resources. What is the best thing to do? A. Move resources from tasks with discretionary dependencies B. Complete activities in parallel where possible C. Reduce resources D. Reduce project scope 90. You are the project manager for a project that you have just learned is 30 days behind schedule. You do not have any additional resources that may be engaged. The project has a CPI of.84 and an SPI of.79. The BCR is 1.45 and only a few of the project tasks have mandatory dependencies. What is the best thing to do? A. Meet with the project sponsor to inform them of the delay B. Reduce the project scope to meet the deadline C. Crash the project D. Make more activities concurrent 91. Sally is a brand new project manager within her company that manufactures household products. She has just taken over a project that is seriously over budget and behind schedule. Originally, the project was slated to have spent US $135,000 and they have already spent US $170,000. It appears that most of the overage is because of flawed original estimates. This project is critical to the organization's success so who has primary responsibility to solve these issues? A. The project sponsor B. The project manager C. The project team D. Senior management

104 92. You have been brought into the organization because senior management is struggling to get a strong understanding of the state of all the projects within the organization. You only have a week to prepare a 30 minute presentation on the status of all projects. Which of the following would best help senior management understand the current portfolio status? A. Project management plan executive summaries B. Detailed cost and schedule analysis C. Milestone reports D. Gantt charts 93. Rearranging dependent tasks or activities so they are done in parallel is called what? A. Fast tracking B. Leveling C. Paralleling D. Crashing 94. Rearranging resources and resource workloads so that the amount of work done in each month or specified time period is constant is called what? A. Fast tracking B. Paralleling C. Leveling D. Crashing 95. Adding additional resources to reduce the schedule time a task or activity is called what? A. Fast tracking B. Crashing C. Paralleling D. Leveling 96. Which of the following is a benefit of a three point project estimate? A. It shows a better understanding of the task B. It allows the project manager to better manage stakeholder expectations C. It helps determine if the project will meet the schedule D. It provides a probabilistic estimate

105 97. Which of the following is a benefit of analogous project estimates? A. It helps to raise questions about expectations B. The estimates will more accurately reflect actuals C. It helps the project resources understand their obligations D. It helps senior management feel better about the estimates 98. Which of the following is an advantage of parametric estimating? A. It accounts for estimating uncertainty B. It provides for improved communication C. It provides a quantifiable deterministic estimate D. It provides estimates at the lowest possible level 99. You are the project manager for a very large and important project within your organization. Your project has been progressing very well until the last couple of weeks when you began to experience a large number of scope changes. Your current CPI is 1.02 and your SPI is.98. As the project manager, what should you do? A. Maintain the baseline and make approved changes B. Maintain the baseline and resist all changes C. Make only the changes approved by the project sponsor D. Initiate a discussion with management about the level of changes 100. Which of the following is best defined as a heuristic? A. Rule of thumb B. A logistic algorithm C. A planning tool D. A control tool

106 Answer Key Part 1: 1. A PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 2. B PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 3. C PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 4. D PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages.

107 5. A PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 6. B PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 7. C PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 8. D PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 9. A PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages.

108 10. B PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 11. C PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages. 12. A PDM stands for Precedence Diagramming Method. In this method there are four (4) potential methods to relate tasks to one and other: Finish to Start (FS) (the most common), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) (seldom used). Before you can used the Critical Path Method (CPM) you must be able to create the correct network diagram for a list of tasks, activities, deliverables or work packages.

109 Answer Key Part 2: 1. A The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 10-6 = 4 and then 4/6 = C The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 9-4 = 5 and then 5/6 = B The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 5-2 = 3 and then 3/6 =.5 4. D The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 15-6 = 9 and then 9/6 = C The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals 17-8 = 9 and then 9/6 = A The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 10 and then 10/6 = C The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 11 and then 11/6 = 1.83

110 8. D The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 9 and then 9/6 = A The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 18 and then 18/6 = B The standard deviation in this case is the PERT standard deviation. The formula for the PERT standard deviation is Pessimistic - optimistic / 6. For this question that equals = 12 and then 12/6 = C This is a PERT problem. To calculate the answer you must first determine the PERT weighted average and the PERT standard deviation. You must then both add and subtract the standard deviation from the weighted average to come up with the range used for 99% confidence (3 Sigma).

111 Answer Key Part 3: 1. A The critical path is the longest path of dependent tasks with no slack or float. It requires you to first do a forward pass and then a backward pass. Any task where the late start early start or late finish early finish equal zero is on the critical path. 2. B Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 3. A Task A has slack or float of 3. By definition, any task or deliverable with float greater than zero is not on the critical path.

112 4. B Task E has slack or float of 10. By definition, any task or deliverable with float greater than zero is not on the critical path. 5. D Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path.

113 6. C Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. Summing this time provides the project duration. 7. B Task 2 has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path.

114 8. C Task 6 has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path. 9. A Task 8 has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path. 10. D Determining the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path.

115 11. B Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 12. C Task C has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path. 13. A Task F has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path.

116 14. B Task H has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path. 15. D Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path.

117 16. A Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 17. C Task 3 has slack or float of 4. By definition, any task or deliverable with float greater than zero is not on the critical path. 18. B Task 4 has slack or float of 5. By definition, any task or deliverable with float greater than zero is not on the critical path.

118 19. A Task 6 has slack or float of 4. By definition, any task or deliverable with float greater than zero is not on the critical path. 20. C Task 8 has slack or float of 3. By definition, any task or deliverable with float greater than zero is not on the critical path. 21. D Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path.

119 22. A Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 23. C Task C has slack or float of 2. By definition, any task or deliverable with float greater than zero is not on the critical path. 24. B Task F has slack or float of 2. By definition, any task or deliverable with float greater than zero is not on the critical path.

120 25. B Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 26. C Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 27. A Task 2 has slack or float of 4. By definition, any task or deliverable with float greater than zero is not on the critical path.

121 28. B Task 4 has slack or float of 4. By definition, any task or deliverable with float greater than zero is not on the critical path. 29. D Task 7 has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path. 30. C Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path.

122 31. A Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 32. D Task B has slack or float of 3. By definition, any task or deliverable with float greater than zero is not on the critical path. 33. C Task D has slack or float of 5. By definition, any task or deliverable with float greater than zero is not on the critical path.

123 34. A Task F has slack or float of 8. By definition, any task or deliverable with float greater than zero is not on the critical path. 35. B Task H has slack or float of 3. By definition, any task or deliverable with float greater than zero is not on the critical path. 36. A Task I has slack or float of 2. By definition, any task or deliverable with float greater than zero is not on the critical path.

124 37. B Task K has slack or float of 6. By definition, any task or deliverable with float greater than zero is not on the critical path. 38. C Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path.

125 39. C Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 40. A Task 2 has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path.

126 41. B Task 4 has slack or float of 3. By definition, any task or deliverable with float greater than zero is not on the critical path. 42. C Task 7 has slack or float of 2. By definition, any task or deliverable with float greater than zero is not on the critical path. 43. D Task 11 has slack or float of 1. By definition, any task or deliverable with float greater than zero is not on the critical path.

127 44. C Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 45. A Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 46. B Task F has slack or float of 3. By definition, any task or deliverable with float greater than zero is not on the critical path.

128 47. C Task J has slack or float of 3. By definition, any task or deliverable with float greater than zero is not on the critical path. 48. D Calculating the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path. 49. A Calculating the duration of the critical path is done by first building the Precedence Diagram. Once that is done enter the task durations and complete the forward and backward pass. By evaluating the differences between the late and early start or the late and early finish. The longest chain of dependent tasks with zero slack or float is the critical path.

129 50. B Task G has slack or float of 2. By definition, any task or deliverable with float greater than zero is not on the critical path. 51. C Task L is a special case because of its finish to finish relationship with K. K in this case is the driving task and therefore on the critical path.

130 Answer Key Part 4: 1. B The critical chain is the longest chain of dependent tasks with zero slack or float taking into consideration resource constraints. The difference between the critical path and the critical chain is the resource considerations. When using the critical chain methodology it is important that you use true most likely case estimates without safety. 2. A The critical chain method requires the creation of a PDM diagram and then, scheduling from the late finish date for each activity asks the project manager to add in resource, feeder and project buffers. 3. C Critical chain management focuses on managing the three different types of project buffers: Project, feeder, and resource. 4. D While in most cases the critical chain will be longer, there is no set rule guaranteeing it. However, it is true that the critical chain does take into account resource limitations while the critical path does not. 5. C Because CCPM focuses on the longest chain of dependent tasks taking into account resource constraints, it specifically excludes multi-tasking. 6. A The core argument of critical chain management is that most projects fail because they do not consider the limitations of resources. This means one resource cannot be doing two tasks at the same time. When this happens, the resource in question becomes the bottleneck and will delay the project.

131 7. B The Theory of Constraints has five major steps: Identify the system constraint Exploit the constraint Subordinate everything to the constraint Elevate the systems constraints Repeat the process 8. C According to the Theory of Constraints, most current management philosophies focus on either cost or throughput management. However, most are focused on cost management. 9. A According to the Theory of Constraints, the only way to achieve good cost performance is to achieve good cost performance at each local or independent stage of the process. This localizing factor becomes a major problem for overall project performance as this can be very different from good overall project cost performance as sometimes a local step needs to be sacrificed to ensure good overall performance. 10. B The critical chain is the longest chain of dependent tasks with zero slack or float taking into consideration resource constraints. Tasks 2 and 5 as well as 6 and 8 are done by the same resource and must be leveled to create the critical chain.

132 11. C CCPM requires you to calculate the longest chain of dependent tasks with zero slack or float taking into consideration resource constraints. In this case the critical chain is 1, 2, 6, 8, 10. These values are summed without adding any buffer values to get the critical chain length. 12. D The expected duration of a project using critical chain project management is calculated using the sum of the critical chain (52) plus a value of 30% of that for the project buffer (16) for a total of B Feed buffers are placed anywhere a non critical chain feeding into the critical chain. Task 4 is not on the critical chain, but it does feed task 8 which is on the critical chain. A feed buffer is placed between the two to ensure a cushion exists.

133 14. A Feed buffers are placed anywhere a non critical chain feeding into the critical chain. Task 3 & 5 are not on the critical chain, but they do feed task 7 which is on the critical chain. A feed buffer is placed between the two to ensure a cushion exists. 15. A Tasks 2 and 5 are done by the same resource and are sequentially right next to each other. To ensure that task 5 is not delayed if task 2 is held up a resource buffer is necessary immediately after task D Tasks 6 and 8 are done by the same resource and are sequentially right next to each other. To ensure that task 8 is not delayed if task 6 is held up a resource buffer is necessary immediately after task 6.

134 17. C The critical chain is the longest chain of dependent tasks with zero slack or float taking into consideration resource constraints. Tasks F and G, B and D, and I and L are done by the same resource and must be leveled to create the critical chain. 18. A The project's critical chain is determined by first determining the project's network using PDM. Then resources and durations are assigned to each task. Tasks are then leveled to account for resource limitations. The longest chain of dependent tasks taking into consideration resource limitations is then determined. This path is summed to provide the time of the project's critical chain which does not include buffers of any kind. 19. C The project buffer for a project using the Critical Chain Project Management methodology is calculated by determining the project's critical chain and then multiplying that value by the buffer rate. In this case, the critical chain is 73. The 30% rate is given to you in the question. Therefore, the correct answer is 22.

135 20. A The overall project duration for a project using CCPM is determined by first determining the project's critical chain length and the length of the project buffer, which is a percentage of the critical chain length. These two values are then added together. In this case 73 and D Feed buffers are placed anywhere a non critical chain feeding into the critical chain. Task C is not on the critical chain, but it does feed task F which is on the critical chain. A feed buffer is placed between the two to ensure a cushion exists. 22. B Feed buffers are placed anywhere a non critical chain feeding into the critical chain. Task J is not on the critical chain, but it does feed task M which is on the critical chain. A feed buffer is placed between the two to ensure a cushion exists. 23. B Feed buffers are placed anywhere a non critical chain feeding into the critical chain. Task L is not on the critical chain, but it does feed task M which is on the critical chain. A feed buffer is placed between the two to ensure a cushion exists.

136 24. C The project's critical chain is determined by first determining the project's network using PDM. Then resources and durations are assigned to each task. Tasks are then leveled to account for resource limitations. The longest chain of dependent tasks taking into consideration resource limitations is then determined. 25. C The project's critical chain is determined by first determining the project's network using PDM. Then resources and durations are assigned to each task. Tasks are then leveled to account for resource limitations. The longest chain of dependent tasks taking into consideration resource limitations is then determined. This path is summed to provide the time of the project's critical chain which does not include buffers of any kind. 26. D The project buffer for a project using the Critical Chain Project Management methodology is calculated by determining the project's critical chain and then multiplying that value by the buffer rate. In this case, the critical chain is 77. The 30% rate is given to you in the question. Therefore, the correct answer is 23.

137 27. D The overall project duration for a project using CCPM is determined by first determining the project's critical chain length and the length of the project buffer, which is a percentage of the critical chain length. These two values are then added together. In this case 77 and A The project's critical chain is determined by first determining the project's network using PDM. Then resources and durations are assigned to each task. Tasks are then leveled to account for resource limitations. The longest chain of dependent tasks taking into consideration resource limitations is then determined. 29. C The project's critical chain is determined by first determining the project's network using PDM. Then resources and durations are assigned to each task. Tasks are then leveled to account for resource limitations. The longest chain of dependent tasks taking into consideration resource limitations is then determined. This path is summed to provide the time of the project's critical chain which does not include buffers of any kind.

138 30. A The project buffer for a project using the Critical Chain Project Management methodology is calculated by determining the project's critical chain and then multiplying that value by the buffer rate. In this case, the critical chain is 45. The 30% rate is given to you in the question. Therefore, the correct answer is B The overall project duration for a project using CCPM is determined by first determining the project's critical chain length and the length of the project buffer, which is a percentage of the critical chain length. These two values are then added together. In this case 45 and C Feed buffers are placed anywhere a non critical chain feeding into the critical chain. Task 6 is not on the critical chain, but it does feed task 8 which is on the critical chain. A feed buffer is placed between the two to ensure a cushion exists.

139 33. A Feed buffers are placed anywhere a non critical chain feeding into the critical chain. Task 7 is not on the critical chain, but it does feed task 9 which is on the critical chain. A feed buffer is placed between the two to ensure a cushion exists. 34. B The project's critical chain is determined by first determining the project's network using PDM. Then resources and durations are assigned to each task. Tasks are then leveled to account for resource limitations. The longest chain of dependent tasks taking into consideration resource limitations is then determined. 35. A The project's critical chain is determined by first determining the project's network using PDM. Then resources and durations are assigned to each task. Tasks are then leveled to account for resource limitations. The longest chain of dependent tasks taking into consideration resource limitations is then determined. This path is summed to provide the time of the project's critical chain which does not include buffers of any kind.

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

COPYRIGHTED MATERIAL. Index

COPYRIGHTED MATERIAL. Index Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

Five-Day Schedule and Course Content

Five-Day Schedule and Course Content Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course

More information

PMI PMI-SP. PMI Scheduling Professional. Download Full Version :

PMI PMI-SP. PMI Scheduling Professional. Download Full Version : PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Achieve PMP Exam Success Five-Day Course Syllabus

Achieve PMP Exam Success Five-Day Course Syllabus Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

u w 1.5 < 0 These two results imply that the utility function is concave.

u w 1.5 < 0 These two results imply that the utility function is concave. A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Exam Questions PMI-SP

Exam Questions PMI-SP Exam Questions PMI-SP PMI Scheduling Professional Practice Test https://www.2passeasy.com/dumps/pmi-sp/ 1.CORRECT TEXT Fill in the blank with the appropriate word. When activities are logically linked,

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management Project Management Professional (PMP) Exam Prep Course 11 - Project Slide 1 Project Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

PASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year

PASS4TEST. IT Certification Guaranteed, The Easy Way!  We offer free update service for one year PASS4TEST IT Certification Guaranteed, The Easy Way! \ We offer free update service for one year Exam : PMI-SP Title : PMI Scheduling Professional Vendors : PMI Version : DEMO Get Latest & Valid PMI-SP

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

MS Project 2007 Page 1 of 18

MS Project 2007 Page 1 of 18 MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

Poor Man s Approach to Monte Carlo

Poor Man s Approach to Monte Carlo Poor Man s Approach to Monte Carlo Based on the PMI PMBOK Guide Fourth Edition 20 IPDI has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI).

More information

ETSF01: Software Engineering Process Economy and Quality

ETSF01: Software Engineering Process Economy and Quality ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

Systems Engineering. Engineering 101 By Virgilio Gonzalez

Systems Engineering. Engineering 101 By Virgilio Gonzalez Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results

More information

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

LCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP

LCS International, Inc. PMP Review. Chapter 5 Developing Project Budgets. Presented by David J. Lanners, MBA, PMP PMP Review Chapter 5 Developing Project Budgets Presented by David J. Lanners, MBA, PMP These slides are intended to be used only in settings where each viewer has an original copy of the Sybex PMP Study

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

The Project Times and Costs

The Project Times and Costs The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45

More information

Teori Pengambilan Keputusan. Week 12 Project Management

Teori Pengambilan Keputusan. Week 12 Project Management Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM

More information

Project Management. Session 5 Budgets and Estimation Andre Samuel

Project Management. Session 5 Budgets and Estimation Andre Samuel Project Management Session 5 Budgets and Estimation Andre Samuel This Session Budgets and Estimation Estimation Principles Estimation Techniques Cost Estimating Estimation Principles Prediction of project

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities

More information

Project Management. A Practitioner s Guide. Steven M. Bragg

Project Management. A Practitioner s Guide. Steven M. Bragg Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project

More information

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur

More information

70-632_formatted. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0

70-632_formatted.   Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0 70-632_formatted Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ Microsoft EXAM 70-632 TS:Microsoft Office Project 2007. Managing Projects Total Questions:

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

PMP Exam Preparation Workshop Chapter 7 Project Cost Management

PMP Exam Preparation Workshop Chapter 7 Project Cost Management PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

Braindumps.PMI-SP.323 questions

Braindumps.PMI-SP.323 questions Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Unit 9: Risk Management (PMBOK Guide, Chapter 11) (PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should

More information

PMI - Dallas Chapter. PMP Exam Sample Questions

PMI - Dallas Chapter. PMP Exam Sample Questions PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

PROJECT MANAGEMENT: PERT AMAT 167

PROJECT MANAGEMENT: PERT AMAT 167 PROJECT MANAGEMENT: PERT AMAT 167 PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time

More information

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM /7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business

More information

WHY ARE PROJECTS ALWAYS LATE?

WHY ARE PROJECTS ALWAYS LATE? WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,

More information

COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING

COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING ISSN: 0976-3104 Lou et al. ARTICLE OPEN ACCESS COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING Ashkan Khoda Bandeh Lou *, Alireza Parvishi, Ebrahim Javidi Faculty Of Engineering,

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Project Management Certification. Multiple Choice Questions

Project Management Certification. Multiple Choice Questions Project Management Certification (PMP) Project Management Certification (PMP) Multiple Choice Questions QUESTION 1 In Project Cost Management, which input is exclusive to the Determine Budget process?

More information

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

PROJECT MANAGEMENT CPM & PERT TECHNIQUES PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

Quality Project Management

Quality Project Management Quality Project Management By James N. Salapatas, PE, PMP www.suncam.com Copyright 2014 James N. Salapatas Page 1 of 44 Table of Contents Title Page LIST OF CHARTS 2 LIST OF FIGURES 3 ABOUT THE COURSE

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

Management Management

Management Management Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently

More information

MGMT 627 SOLVED MCQs

MGMT 627 SOLVED MCQs MGMT 627 SOLVED MCQs Question # 1 of 15 ( Start time: 07:53:55 PM ) Total Marks: 1 All of the following are the characteristics of a project, EXCEPT: A start and an end A multi-disciplinary team brought

More information

Techniques to Assist Delivery of Projects

Techniques to Assist Delivery of Projects Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction

More information

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices

More information

DC Program and Project Managers Meeting #2

DC Program and Project Managers Meeting #2 + Trevor Lowing Trevor.Lowing@gmail.com DC Program and Project Managers Meeting #2 Session 1: Planning projects with MS Project Session 2: Workshop: Generating Reports with MS Project and Visual Basic

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

Outline. Project Management. Introduction. What is a Project?

Outline. Project Management. Introduction. What is a Project? Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction

More information

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1 A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,

More information

Project Theft Management,

Project Theft Management, Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com

More information

IE 102 Spring Project Management

IE 102 Spring Project Management IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and

More information

Project Management. Basic Definitions: Project and Project Plan

Project Management. Basic Definitions: Project and Project Plan Project Management Basic Definitions: Project and Project Plan Software Project: All technical and managerial activities required to deliver the deliverables to the client. A software project has a specific

More information

KERN COMMUNITY COLLEGE DISTRICT BAKERSFIELD COLLEGE INDA B132 COURSE OUTLINE OF RECORD

KERN COMMUNITY COLLEGE DISTRICT BAKERSFIELD COLLEGE INDA B132 COURSE OUTLINE OF RECORD Status: Final Last Revised: February 11, 2016 Proposal Type: New Course Start Term: Fall 2017 TOPS Code: 0935.00 CIP Code: 15.0406 (updated 6/1/16) KERN COMMUNITY COLLEGE DISTRICT BAKERSFIELD COLLEGE INDA

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT Planning DETERMINE BUDGET PROCESSES BY PROCESS GROUP Monitoring and Controlling 7.1 Plan Costs Management 7.4 Control Costs 7.2 Estimate Costs 7.3 Determine Budget DETERMINE BUDGET

More information

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project. INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E

More information