Project Management -- Developing the Project Plan

Size: px
Start display at page:

Download "Project Management -- Developing the Project Plan"

Transcription

1 Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1

2 Where We Are Now 6 2

3 Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies, and start and finish times of the project job plan of activities that is the critical path through the network. 6 3

4 Developing the Project Plan Provides the basis for scheduling labor and equipment. Enhances communication among project participants. Provides an estimate of the project s duration. Provides a basis for budgeting cash flow. Identifies activities that are critical. Highlights activities that are critical and can not be delayed. Help managers get and stay on plan. 6 4

5 WBS/Work Packages to Network FIGURE

6 WBS/Work Package to Network (cont d) FIGURE 6.1 (cont d) 6 6

7 Constructing a Project Network Terminology Activity: an element of the project that requires time. Merge Activity: an activity that has two or more preceding activities on which it depends. Parallel (Concurrent) Activities: Activities that can occur independently and, if desired, not at the same time. A B D C 6 7

8 Constructing a Project Network (cont d) Terminology Path: a sequence of connected, dependent activities. Critical path: the longest path through the activity network that allows for the completion of all project-related activities; the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project. 6 8

9 Constructing a Project Network (cont d) C A B D (Assumes that minimum of A + B > minimum of C in length of times to complete activities.) 6 9

10 Constructing a Project Network (cont d) Terminology Event: a point in time when an activity is started or completed. It does not consume time. Burst Activity: an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it). A B C D 6 10

11 Constructing a Project Network (cont d) Two Approaches Activity-on-Node (AON) Uses a node to depict an activity. Activity-on-Arrow (AOA) Uses an arrow to depict an activity. A B C D 6 11

12 Basic Rules to Follow in Developing Project Networks 1. Networks typically flow from left to right. 2. An activity cannot begin until all preceding connected activities are complete. 3. Arrows indicate precedence and flow and can cross over each other. 4. Each activity must have a unique identify number that is greater than any of its predecessor activities. 6 12

13 Basic Rules to Follow in Developing Project Networks 5. Looping is not allowed. 6. Conditional statements are not allowed. 7. Use common start and stop nodes. 6 13

14 Activity-on-Node Fundamentals 6 14

15 Activity-on-Node Fundamentals (cont d) FIGURE 6.2 (cont d) 6 15

16 Network Information TABLE

17 Automate Warehouse Partial Network FIGURE

18 Automated Warehouse Complete Network FIGURE

19 Network Computation Process Forward Pass Earliest Times How soon can the activity start? (early start ES) How soon can the activity finish? (early finish EF) How soon can the project finish? (expected time ET) 6 19

20 Network Computation Process Backward Pass Latest Times How late can the activity start? (late start LS) How late can the activity finish? (late finish LF) Which activities represent the critical path? How long can activity be delayed? (slack or float SL) 6 20

21 Network Information TABLE

22 Activity-on-Node Network FIGURE

23 Activity-on-Node Network Forward Pass FIGURE

24 Forward Pass Computation Add activity times along each path in the network (ES + Duration = EF). Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected. 6 24

25 Activity-on-Node Network Backward Pass FIGURE

26 Backward Pass Computation Subtract activity times along each path in the network (LF - Duration = LS). Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected. 6 26

27 Determining Free Slack (or Float) Free Slack (or Float) Is the amount of time an activity can be delayed after the start of a longer parallel activity or activities. Is how long an activity can exceed its early finish date without affecting early start dates of any successor(s). Allows flexibility in scheduling scarce resources. 6 27

28 Determining Free Slack (or Float) Sensitivity The likelihood the original critical path(s) will change once the project is initiated. The critical path is the network path(s) that has (have) the least slack in common. 6 28

29 Forward and Backward Passes Completed with Slack Times FIGURE

30 Practical Considerations Network Logic Errors Activity Numbering Use of Computers to Develop Networks Calendar Dates Multiple Starts and Multiple Projects 6 30

31 Network Logic Errors: Illogical Loop FIGURE

32 Automated Warehouse Order Picking System Network FIGURE

33 Automated Order Warehouse Picking System Bar Chart FIGURE

34 Extended Network Techniques to Come Close to Reality Laddering Activities are broken into segments so the following activity can begin sooner and not delay the work. 6 34

35 Lags Extended Network Techniques to Come Close to Reality The minimum amount of time a dependent activity must be delayed to begin or end. Lengthy activities are broken down to reduce the delay in the start of successor activities. Lags can be used to constrain finish-to-start, start-tostart, finish-to-finish, start-to-finish, or combination relationships. 6 35

36 Example of Laddering Using Finish-to-Start Relationship FIGURE

37 FIGURE 6.14 Use of Lags Finish-to-Start Relationship Start-to-Start Relationship FIGURE 6.13

38 Use of Lags Cont d Use of Lags to Reduce Project Duration FIGURE

39 New Product Development Process FIGURE

40 Use of Lags (cont d) Finish-to-Finish Relationship FIGURE 6.17 Start-to-Finish Relationship FIGURE 6.18 Combination Relationship FIGURE 6.19

41 Network Using Lags FIGURE

42 Hammock Activities ( 吊床活動 ) Hammock Activity Spans over a segment of a project. Has a duration that is determined after the network plan is drawn. Is used to aggregate sections of the project to facilitate getting the right amount of detail for specific sections of a project. Is very useful in assigning and controlling indirect project costs. 6 42

43 Hammock Activity Example FIGURE

44 Common Elements of Project Plan 1. Scope Statement, Charter, or SOW 2. Detailed requirements 3. Detailed work definition (WBS and work package details) 4. Responsibility for work tasks 5. Detailed schedules and milestones 1. Gantt charts 2. Networks 6. Project budget and cost accounts 44

45 Gantt Chart 45

46 Tasks Gantt Chart A B C D E F G H What is affect of Time C starting 2 weeks late? C starting 6 weeks late? E taking 3 weeks instead of 2 weeks? E finishing a week early? 46

47 Network Diagrams: Scheduling Using Network Methods AON method: Activity on Node Each activity (work package or task) in project is represented by a node (a circle or box) Activity A A or A A project is represented by a network of nodes connected with arrows arranged in sequence as specified by immediate predecessors 47

48 Network Diagrams: AON Example Activity Immediate Time A B Gantt Chart Predecessors A -- 1 B A 2 C B 3 D C E D B 1 E C, D 2 F F E Time

49 Network Diagrams: AON (cont d) Example Activity Immediate Predecessors A -- B A C B D B E C, D F E A B 49

50 Network Diagrams: AON (cont d) Example Activity Immediate Predecessors A -- B A C B D B E C, D F E A B C D 50

51 AON (cont d) Example Activity Immediate Predecessors C A -- A B E F B C A B D D B E C, D F E 51

52 Network Diagrams: AON (cont d) When a network has dangling nodes at the start or end of the project, cannot tell where project starts or ends. A C B H I D F G J K E L 52

53 Network Diagrams: AON (cont d) The network should have one start node and one end node B A I start C H D G K end J F E L 53

54 Network Diagrams: Activities in the network should be based upon work packages from the WBS 54

55 Network Diagrams: Computer generated network diagrams 55

56 Network Diagrams: Scheduling Using a Network How do we schedule activities on the network? C, 3 A, 1 B, 2 E, 2 F, 3 D, 1 56

57 The Critical Path: Creating the Schedule Assume project starts at time 0. Start at first node, work left-to-right, adding duration times. Project start start = 3 finish = 6 C, 3 A, 1 B, 2 E, 2 F, 3 start = 0 finish = 1 start = 1 finish = 3 D, 1 start =? start = 3 finish = 4 57

58 The Critical Path: Creating the Schedule If an activity has multiple immediate predecessors (activity E), must wait until all are finished before starting. start = 3 finish = 6 C, 3 A, 1 B, 2 E, 2 F, 3 start = 0 finish = 1 start = 1 finish = 3 D, 1 start = 3 finish = 4 start = 6 finish = 8 start = 8 finish = 11 58

59 The Critical Path: Creating the Schedule Note: Here, ignore fact that in reality an activity will finish on one day or week and the next activity will start on following day or week. To simplify, assume that when an activity is finished, its successors start immediately. 59

60 Tasks The Critical Path: Creating the Schedule start = 3 finish = 6 C, 3 A, 1 B, 2 E, 2 F, 3 start = 0 finish = 1 A start = 1 finish = 3 B C D, 1 start = 3 finish = 4 start = 6 finish = 8 start = 8 finish = 11 Note: Results are same if had created a Gantt chart. D E F

61 The Critical Path: Creating the Schedule -- Early Times These times are called Early Times the earliest activities can be started and finished Early times give only half the time information needed to create a realistic, feasible schedule Early times do not consider potential constraints 61

62 The Critical Path: Creating the Schedule -- Early Times (cont d) Suppose 1. Contractor for D cannot start in week (has prior commitment); must wait until week 5 2. E cannot be completed in 2 weeks (shortage of personnel); will require 3 weeks to complete What affect will these have on project? start = 3 finish = 6 C, 3 A, 1 B, 2 E, 2 F, 3 start = 0 finish = 1 start = 1 finish = 3 D, 1 start = 3 finish = 4 start = 6 finish = 8 start = 8 finish = 11 62

63 Tasks The Critical Path: Creating the Schedule -- Early Times (cont d) A B D C E F Answers No affect. However, if D s start were delayed until week 6, it would delay project completion date. 2. If E exceeds 2 week duration by any amount, project will be delayed 12 63

64 The Critical Path: Creating the Schedule -- Early Times (cont d) To quickly answer questions like these, need to know more than Early Times Need also to know Late Times 64

65 The Critical Path: Late Times Late times: latest times activities must be started or finished in order to complete project by target date To compute late times, start at last node in project, specify target completion, and work backwards finish = 6 start = 3 Start here: Target Completion = 11 finish =? C, 3 finish = 8 start = 6 finish = 11 start = 8 A, 1 B, 2 E, 2 F, 3 D, 1 finish = 6 start = 5 65

66 The Critical Path: Late Times (cont d) Notice, the late finish for an activity is based on late start for its successor. If an activity has more than one successor, late finish is based on earliest of its successors. Hence, late finish for B is 3, which is late start for earliest of its successors, C. Were B to finish any later than 3, C would be delayed, as would E and F finish = 1 start = 0 finish = 3 start = 1 finish = 6 start = 3 C, 3 finish = 8 start = 6 finish = 11 start = 8 A, 1 B, 2 E, 2 F, 3 D, 1 finish = 6 start = 5 66

67 The Critical Path: Early and Late Times To simplify presentations from here on use Where ES EF LS LF ES = early start EF = early finish LS = late start LF = late finish 67

68 The Critical Path: Early and Late Times (cont d) ACTIVITY, TIME ES LS EF LF C, A, 1 B, 2 E, 2 F, 3 D,

69 The Critical Path: Early and Late Times (cont d) Another example ES EF LS LF C, 2 A, 1 E, 2 G, 6 Start B, 3 D, 7 F, 3 H, 1 End 69

70 The Critical Path: Early and Late Times (cont d) 1 3 ES EF LS LF 0 1 C, 2? A, E, 2 G, 6 Start D, 7 End B, F, 3? H, 1 70

71 The Critical Path: Early and Late Times (cont d) 1 3 ES EF LS LF 0 1 C, A, E, 2 G, 6 Start D, 7 End B, F, 3 H,

72 The Critical Path: Early and Late Times (cont d) Suppose target date is 16 weeks C, A, 1 D, 7 Start B, E, 2 ES EF LS LF G, 6 F, 3 H, End 72

73 The Critical Path: Early and Late Times (cont d) Start 0 1 A, 1 1 3? C, 2 1 8? D, 7 B, 3 0 3? E, G, 6 F, 3 H, ES EF LS LF End 73

74 The Critical Path: Early and Late Times (cont d) Start 0 1? A, C, D, 7 B, E, G, 6 F, 3 H, ES EF LS LF End 74

75 The Critical Path: Early and Late Start Times (cont d) C, A, D, 7 B, E, G, 6 F, 3 H, ES EF LS LF End In project management software this information is displayed in tabular form 75

76 The Critical Path: Early and Late Times (cont d) Start Finish Late Start Late Finish 76

77 The Critical Path: Project Duration -- How Long Will the Project Take? Quick way to determine duration of project: Identify longest path through network from the start node to the end node 77

78 The Critical Path: Project Duration (cont d) A, C, ES EF LS LF E, 2 (Can ignore these!) G, 6 Start D, 7 End B, F, 3 H,

79 The Critical Path: Project Duration (cont d) C, 2 A, 1 E, 2 G, 6 Start D, 7 End B, 3 F, 3 H, 1 Longest path is A-D-E-G, 16 weeks, thus, project duration is 16 weeks 79

80 The Critical Path: Slack Times Difference between early and late times represent slack (or float ) of an activity LS ES = slack or LF EF = slack 80

81 The Critical Path: Slack Times Start m = slack time How much activity can exceed expected duration C, A, E, 2 G, 6 D, 7 End B, Slack represents scheduling flexibility How much an activity can be delayed F, 3 H,

82 The Critical Path: Slack Times Start Activities F and H both have slack of 4 weeks. However, both are on same sub-path, hence, 4 weeks represents combined slack for both activities. (If F is delayed 1 week, H has 3 weeks of slack remaining) C, A, E, 2 D, B, G, 6 F, 3 H, End 82

83 The Critical Path: Early and Late Times (cont d) Start Finish Late Start Late Finish Slack 83

84 The Critical Path: Critical Path Notice the path with 0 total slack This path is also the Critical Path Start C, A, E, 2 D, B, Critical Path CP = A-D-E-G G, 6 F, 3 H, End 84

85 The Critical Path: Critical Path (cont d) CP has least slack Also, CP is the Longest Path C, 2 Start A, 1 B, 3 D, 7 E, 2 F, 3 G, 6 H, 1 End Activities on CP are called critical activities Activities not on CP are called non critical activities Any delay on any activity on CP will delay project. 85

86 The Critical Path: Critical Path (cont d) CP has least slack in project (though not always 0. If, e.g., target of project is 18 weeks, slack on CP will be 2, but 2 more everywhere else). Start A, C, D, 7 B, E, 2 F, CP = A-D-E-G G, H, Target Date = 18End 86

87 The Critical Path: Free Slack Free slack is the time an activity can be delayed without delaying the start of any successor activity. Free slack for a activity = ES - EF 87

88 Management Schedule Reserve: PDM Networks AON presumes a finish-to-start relationship (immediate predecessors must finish before successors can start) PDM (Precedence Diagramming Method) shows kinds of relationships in projects Start activity when predecessors are only partially completed Start activity n days after start of predecessor Start activity n days after predecessors are completed Finish activity n days after finished predecessor With Lags. 88

89 Network Diagrams: PDM Networks Examples A FS = 1 Start B 1 day after finish A B A FF = 5 B Finish B 5 days after finish A A SS = 3 B Start B 3 days after start A With most project management software, you can schedule using PDM method 89

90 Sample problem Specify ES, EF, LS, LF, critical path, and slack times ES EF LS LF D, 3 F, 5 C, 1 L, 2 J, 3 Q, 6 M, 3 Assume LF = EF R, 2 90

91 Early times ? 0 2 L, 2 D, 3 F, Q, 6 J, R, C, 1 M, 3 91

92 Early times D, 3 F, 5 C, 1? 5 11 L, 2 M, 3 Q, 6 J, R,

93 Early times D, 3 F, 5 C, ? L, 2 M, 3 Q, 6 J, R,

94 Late times L, 2 D, 3 F, C, M, 3 Q, 6 J, R, 2?

95 Late times L, 2? D, 3 F, C, M, 3 Q, 6 J, R,

96 Critical path? L, 2 D, 3 F, C, M, 3 Q, 6 J, R,

97 Critical path, slack times L, 2 0 D, 3 F, C, M, 3 0 Q, 6 J, R,

98 Scheduling with Resource Constraints So far have assumed all resources required for project will be available. Q: Will they be available? What happens if they are not? 98

99 Scheduling with Resource Constraints: Resource Loading Resource Loading: amount of a specified resource required throughout a project Assume have a well-defined project Have defined the kinds of resources and amount or number of resources for every work package 99

100 Scheduling with Resource Constraints: Resource Loading Analysis -- apply to constrained resources Example: Work Package D resource requirements: Programmer 160 hrs. Systems Analyst 40 hrs. Mainframe Computer 10 hrs. Suppose Systems Analyst time and Mainframe Computer time, no problem. Hence, ignore these in resource loading analysis. Programmers are very busy and in short supply. Hence, focus on this in resource loading analysis 100

101 Scheduling with Resource Constraints: Resource Loading Analysis (cont d) Assume Work Package D must be completed in 2 weeks Each programmer can devote at most 20 hrs per week. Thus, the required programmers for Work Package D: 160 hrs 2 wks hrs = 80 hrs. 80 wk = 4 programmers wk hrs wk 20 programmer Work Package D will require 4 programmers for two weeks Similar estimates are made for number of programmers for every work package in the project 101

102 Scheduling with Resource Constraints: Project Network A E End B H Start C D Activity F G Immediate Predecessors Time (weeks) Resource (Programmers) A B C D E A 4 9 F C 2 7 G D, F 3 2 H B, G

103 Scheduling with Resource Constraints: Resource Loading Analysis Questions: According to the schedule, how many programmers will be needed each week for the project? Given the shortage of programmers, will there be enough programmers for the project? 103

104 Scheduling with Resource Constraints: Gantt Chart, early times According to the schedule, how many programmers will be needed each week for the project? A, 3 E, 9 B, 8 C, 6 F, 7 G, 2 H, 1 D, 4 e.g., Activity D requires 4 programmers Key: CP /57

105 Gantt Chart A, 3 E, 9 B, 8 C, 6 F, 7 G, 2 H, 1 D, Resource Loading Diagram Early Times For example, during weeks 1 and 2 F D 16 Activities A, B, C, and D are scheduled So, number of programmers needed is C F = 21 E 11 In week 3 G Activities E, B, and F are scheduled So, = 24 B E B 2 H 1 A G (Most project management software perform this kind of analysis) 105

106 Resource Leveling What happens if required resources exceed the available amount? Use resource leveling technique 106

107 Resource Leveling (cont d) D C 24 F E Resource Loading using Early Event Times 16 F G B E A B 2 G H week Suppose maximum number of programmers available for project in any given week = 12 The schedule is infeasible since weeks 1-4 require more than 12 programmers 107/57

108 Resource Leveling (cont d) Many activities are scheduled early in the project Not all of these have to be scheduled then They can be delayed Delaying activities defers need for resources 108

109 Use trial and error, delay activities along their slack ties, check impact on total required resources. *For example, delay A by 2 weeks B by 4 weeks E by 5 weeks A* E* B* C F G H D /57

110 Programmers Resource Leveling Viola! Project can be completed in 11 weeks with no more than 10 programmers per week B* C F G H D A* E* D A* B* E* C F G *Resource loading after rescheduling A, B, and E H 110

111 Resource Leveling (cont d) Method is called resource leveling because it results in leveling of peak requirements Notice in example, if constraint on programmers had been less than 10, project would not be able to complete project in 11 weeks D A* B* E* C F G H

112 Resource Leveling (cont d) When project has multiple constrained resources, Repeat same analysis for each All resources must be leveled simultaneously so no resource exceeds constraints This is one application in which project management software that is invaluable When PM does not have direct authority over resources Speak to managers of resources. Try to get suggestions about how to meet schedule with limited resources. 112

113 Tasks Multi-Project Scheduling Use similar approach to schedule multiple projects that share constrained resources Create resource loadings for projects scheduled at same time. Combined to yield multi-project loading. A B D C E Project A A B TimeD Project B C E F F Time 113

114 Multi-Project Scheduling Project A Project B If loading exceeds constraints, tasks within projects are delayed along their slack times. If that fails, then tasks in lower-priority projects are delayed further or (lower priority projects are delayed in their entirety) Software for multi-project planning and scheduling have this capability 114

115 Key Terms Activity Activity-on-arrow (AOA) Activity-on-node (AON) Burst activity Concurrent engineering Critical path Early and late times Free slack Gantt chart Hammock activity Lag relationship Merge activity Parallel activity Sensitivity Total slack 6 115

116 Greendale Stadium Case TABLE

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001 Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique

More information

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

Lecture 3 Project Scheduling

Lecture 3 Project Scheduling B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING Planning of Works Contract Form of contract by which one party undertakes to the other to perform certain work, for a price. Corresponds to the execution of a

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

The Project Times and Costs

The Project Times and Costs The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

IE 102 Spring Project Management

IE 102 Spring Project Management IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and

More information

POLYTECHNIC OF NAMIBIA

POLYTECHNIC OF NAMIBIA POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project. INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E

More information

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques

More information

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION 1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and

More information

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

PROJECT MANAGEMENT CPM & PERT TECHNIQUES PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a

More information

Teori Pengambilan Keputusan. Week 12 Project Management

Teori Pengambilan Keputusan. Week 12 Project Management Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM

More information

Outline. Project Management. Introduction. What is a Project?

Outline. Project Management. Introduction. What is a Project? Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction

More information

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT Programme BA (Hons) Fashion and Textiles (Top-Up) BA (Hons) Graphic Design with Animation (Top-Up) BA (Hons) Interior Design Cohort FDI- BFT(TP)/14B/PT FDI- BGDA(TP)/14B/PT FDI-BAID/13B/FT Examinations

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

06IP/IM74 OPERATIONS RESEARCH

06IP/IM74 OPERATIONS RESEARCH 06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this

More information

MS Project 2007 Page 1 of 18

MS Project 2007 Page 1 of 18 MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems

More information

Project Planning. Planning is an important step in project execution. Planning means:

Project Planning. Planning is an important step in project execution. Planning means: Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving

More information

SECTION PROJECT SCHEDULE 08/08

SECTION PROJECT SCHEDULE 08/08 SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM /7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

ETSF01: Software Engineering Process Economy and Quality

ETSF01: Software Engineering Process Economy and Quality ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower

More information

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,

More information

Final: Total 200 points (3-hour exam)

Final: Total 200 points (3-hour exam) Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1 A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

PROJECT MANAGEMENT DIPLOMA COURSE

PROJECT MANAGEMENT DIPLOMA COURSE PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a

More information

Ins. Luay Dwaikat Fall 2013/2014

Ins. Luay Dwaikat Fall 2013/2014 An-Najah National University Faculty of Engineering Civil/Building Engineering Dept. Construction Management - 6147 Ins. : Luay Dwaikat Course Outline Introduction to project management Project Work breakdown

More information

The Critical Path Method

The Critical Path Method The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico "I believe that this nation should commit

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

DC Program and Project Managers Meeting #2

DC Program and Project Managers Meeting #2 + Trevor Lowing Trevor.Lowing@gmail.com DC Program and Project Managers Meeting #2 Session 1: Planning projects with MS Project Session 2: Workshop: Generating Reports with MS Project and Visual Basic

More information

Management Management

Management Management Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Lecture 5: Project Management

Lecture 5: Project Management Lecture 5: Management organization structure ritical path method (PM) Time/cost tradeoff PM with three activity it time estimates t Readings: hapter 10 Management series of related jobs usually directed

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Chapter 2 The PERT/CPM Technique

Chapter 2 The PERT/CPM Technique Chapter The PERT/CPM Technique Abstract Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects

More information

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities

More information

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2 UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle

More information

u w 1.5 < 0 These two results imply that the utility function is concave.

u w 1.5 < 0 These two results imply that the utility function is concave. A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices

More information

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center

More information

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:

More information

WHY ARE PROJECTS ALWAYS LATE?

WHY ARE PROJECTS ALWAYS LATE? WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

Project Management Techniques (PMT)

Project Management Techniques (PMT) Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.

More information

Chapter16Project Management and. Scheduling Project management

Chapter16Project Management and. Scheduling Project management Chapter6Project Management and Scheduling Figure 6. On completion of this chapter, you should be able to identify key components of projects and the issues associated with them, and you should be able

More information

If you have a question during any portion of this exam, raise your hand and speak to the proctor. Write legibly.

If you have a question during any portion of this exam, raise your hand and speak to the proctor. Write legibly. CE167: Engineering Project Management Spring 2007 Professor William Ibbs MIDTERM 2 SOLUTION Date: April 26, 2007 General Instructions All work is to be completed in a bluebook answers not recorded in a

More information

Managing Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost

Managing Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost Managing Projects As Investments: The Benefits Of Computing Critical Path Drag And Drag Cost ***** A Presentation for PMI Westchester County Chapter by Stephen A. Devaux 6/13/2017 1 The History of PM and

More information

Tip and Trick Bulletins 2/1/04

Tip and Trick Bulletins 2/1/04 IN THIS ISSUE Primavera Project Planner (P3) Version 3.1 Survival Guide for Using Constraints by Eric Chou, PE A constraint is a restriction imposed on the schedule to control the results (such as Start

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

But is it on the critical path?

But is it on the critical path? But is it on the critical path? Notes from an evening seminar held on the 12 May 2005 for the Adjudication Society Seminar in the London office of Ove Arup Speaker Peter Curtis Ladymead Projects Ltd Agenda

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE [---Section 01315A should be used for contracts for which a fully-developed computergenerated critical path method is appropriate for managing

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017

More information

SCM 301 (Solo) Exam 1 Practice Exam Solutions

SCM 301 (Solo) Exam 1 Practice Exam Solutions 1. D $118,000 www.liontutors.com SCM 301 (Solo) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

56:171 Operations Research Midterm Examination Solutions PART ONE

56:171 Operations Research Midterm Examination Solutions PART ONE 56:171 Operations Research Midterm Examination Solutions Fall 1997 Answer both questions of Part One, and 4 (out of 5) problems from Part Two. Possible Part One: 1. True/False 15 2. Sensitivity analysis

More information

Project Management and Cost Control

Project Management and Cost Control Project Management and Cost Control What is Project Management Build A A Done Build B B Done Build C JAN FEB MAR APR MAY JUN C Done Build D On time! Ship Unique, one-time operations designed to accomplish

More information

JAYARAM COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF INFORMATION TECHNOLOGY

JAYARAM COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF INFORMATION TECHNOLOGY JAYARAM COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF INFORMATION TECHNOLOGY Two Mark Question for Student s Reference 1. Define software project management. Software Project Management has key ideas

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

Techniques to Assist Delivery of Projects

Techniques to Assist Delivery of Projects Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

Quality Project Management

Quality Project Management Quality Project Management By James N. Salapatas, PE, PMP www.suncam.com Copyright 2014 James N. Salapatas Page 1 of 44 Table of Contents Title Page LIST OF CHARTS 2 LIST OF FIGURES 3 ABOUT THE COURSE

More information

CHAPTER 5. Project Scheduling Models

CHAPTER 5. Project Scheduling Models CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

How to Satisfy GAO Schedule Best Practices

How to Satisfy GAO Schedule Best Practices By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

Scheduling Resources and Costs

Scheduling Resources and Costs CHAPTER EIGHT Scheduling Resources and Costs Copyright 2014 McGraw-Hill Education. All Rights Reserved. PowerPoint Presentation by Charlie Cook Where We Are Now 8 2 Overview of the Resource Scheduling

More information

Project Management with Brief Information regarding CPM and PERT Methods

Project Management with Brief Information regarding CPM and PERT Methods 99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract

More information

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project

More information