CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri
|
|
- Allan Richardson
- 5 years ago
- Views:
Transcription
1 CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri
2 Introduction Planning & Scheduling Principles Techniques Work breakdown structure Gantt Chart & S-Curve Critical Path Method Successor/ predecessor relationship Arrow Diagram Method and Precedence Diagram Method
3 THE INTEGRATION OF TIME & SUSTAINABLE CONSTRUCTION Our focus!! Traditional Project s Critical Components (time, cost, & quality); in relation with sustainable construction concept
4 Introduction Project planning Process of identifyingall the activities necessary to successfully complete the project. Provides map to guide where to go and focused on how to get there Planned in early stage of Project life Cycle or also before site activities start.
5
6 Introduction Importance of planning Reduce mistake and rework Avoid wastage minimize unnecessary in time and cost scheduling better quality control Effective project progress control Effective usage resources
7 Introduction Project scheduling Process of determining the sequential order of the planned activities, assigning realistic durationsto each activity and determining the start and finish dates for each activities. it can be used to manage, coordinate, control and report. Depending on the sophistication of the user, the schedule can take different forms.
8
9 Introduction Purpose of project scheduling Claim Project time and cost control Allocate project resources more efficiently As a monitoring tool Material delivery at site Storage all material cannot put in the site (confined space) Avoid delay of the work and activity. Minimize the cash flow as min as possible such as order material stage by stage depend on the work needed. Control human resources and machinery To improve the efficiency of the operation through the efficient use of resources and cost control. Project planning is prerequisite to project planning!
10 Desired results of planning and scheduling Finish the project on time. Continuous (uninterrupted) flow of work (no delays) Reduced amount of rework (least amount of changes) Minimized confusion on misunderstandings. Increase knowledge of status of project by everyone. Meaningful and timely reports to management. You run the project instead the project running you. Knowledge of scheduled times of key parts of the project. Knowledge of the distributions of costs of the project Accountability of people, define responsibility/authority. Clear understanding of who does what, when & how much. Integration of all work to ensure a quality project for the owner.
11 What are the different? Planning is more difficult to accomplish than scheduling. The term planning and scheduling are often used synonymously. Planning is first step to project scheduling. Tools used for planning and scheduling are different!
12 Principles of planning and scheduling Begin planning before starting work, rather than after starting work. Involve people who will actually do the work in the planning and scheduling process. Includes all aspects of the project: scope, budget, schedule & quality. Build flexibility into the plan, include allowance for changes and time for reviews and approvals. Remember the schedule is the plan for doing the work, and it will never be precisely correct. Keep the plan simple, eliminate irrelevant details that prevent the plans from being readable. Communicating the plan to all parties; any plan is worthless unless it is known.
13 COST RESOURCES TIME SCOPE QUALITY The Collection of Project s Critical Components (should be in equilibrium)
14 Steps in planning and scheduling Scope definition Activity Sequencing Time & Resource Management Create WBS Activity resource planning Activity Duration Estimation Schedule development Scope Management Cost Estimating Cost Budgeting Cost Management
15 Steps in planning and scheduling 1. Develop a work breakdown structure (WBS) 2. Prepare a drawing (network diagram). Determine the time, cost and resources required. Compute the schedule to determine start, finish and float times. Analyze costs and resources for the project 6. Communicate the results of the plan and schedule
16 Work breakdown structure (WBS) Identifies the tasks and activities that must be performed. It divides the project into identifiable parts that can be managed. Concept of WBS: in order to manage a whole project, one must manage and control each of its parts. It defines: The work to be performed The need of expertise Assist in selection of project team Establish a base of project scheduling and control
17 Work breakdown structure (WBS) WBS is display as a graphical or outline method that shows thedivision of work in a multi level system. In developing WBS, we should consider: Activities that require time Activities that require cost Activities that need to arrange Activities that need to monitor
18 Work Breakdown Structure (Graphical) Level 1 Construction of one block office building Level 2 Start Project Preliminaries Block A Testing & Commissioning Project complete Level Performance bond Earthwork Establish and removal of site office Structure Work Architecture Work M&E work
19 Work Breakdown Structure (Outline) Construction of one block office building Start Project Preliminaries Performance bond Establish and removal of site office Block A Earthwork Structure Work Architecture Work M&E work Testing and Commissioning Project complete
20 Work breakdown structure (WBS) Importance of WBS Overall program can be explain in summary according to each sub-element divided. Planning could execute. Cost and budget could estimate more accurately. Time, Cost and Performance of each element could be monitor from time to time. Objective could be relate directly with the available resources in the company. Network diagram and control planning could be prepared in early stages. Responsibilities for each parties involve in every element could be identify and assign.
21 Work breakdown structure (WBS) Example: You are the Project Manager for a Construction of Proposed Construction and Completion of a Double Storey Bungalow House And Related Works For Messrs. Dato'Kamal Jaafar. Develop a preliminary graphical work breakdown structure (up to level ) for the project given. Your WBS should complete with all works needs in completing a one unit bungalow.
22 Example (WBS-Graphical Method) Level 1 Proposed Construction and Completion of A Double Storey Bungalow House and Related Works for Messrs. Dato'Kamal Jaafar. Level 2 Preliminary works Building works External works Level Performance bond Structure Architecture M&E Sewerage Progress Report Foundation Wall Wiring Road and drainage Level Ground level 1 st floor level Floor Roof Fittings installation Landscape 2 nd floor level Fittings
23 Exercise (Outline Method) Proposed Construction and Completion of A Double Storey Bungalow House and Related Works for Messrs. Dato'Kamal Jaafar.
24 Techniques for scheduling Techniques used will vary depending on: Project s size Complexity Duration Personnel Owner requirements Two general methods commonly used : Bar chart (Gantt chart) Critical path method (CPM/ network analysis system)
25 Develop by Henry L.Gantt Is a graphical time-scale of the schedule, length represent the duration of activity.
26 Advantages Easy to interpret Simplicity & ease of preparation and understanding (Simple graphical). No theory or complicated calculation involved (Easy for general comprehension). Time-scaled (the length of the bar representing certain activity is proportional to the duration of that activity. Appeal to persons who do not have a technical background Wide spread used in industry Mostly used in small project Fairly broad planning and scheduling tools, so they require less revision and updating than more sophisticated systems Disadvantages Difficult to update Very cumbersome as the number of line activities, or bars increases Does not integrate costs or resources with the schedule Limited application for detail construction work Difficult to use it for forecasting the effects that changes in a particular activity will have on the overall schedule
27 Bar chart (Gantt Chart) No. Description Month Mobilization 2 Foundation Excavation Diversion Stage Foundation Grouting Dam Concrete 6 Install Outlet Gates 7 Install Trash Racks 8 Prestress 9 Radial Gates 10 Spillway Bridge 11 Curtain Grout 12 Dismantle Plant, Clean Up Actual progress Original Schedule Bar chart basically use x-axis only (to depict time). The y-axis is use to show individual activities, to represent a variable across time (e.g.: man-hours, budget, % complete and so forth.
28 Bar chart (Gantt Chart) + S curve No. Description Month 1 Mobilization 2 Foundation Excavation Diversion Stage Foundation Grouting Dam Concrete 6 Install Outlet Gates 7 Install Trash Racks 8 Prestress 9 Radial Gates 10 Spillway Bridge 11 Curtain Grout 12 Dismantle Plant, Clean Up Actual progress Original Schedule Bar chart basically use x-axis only (to depict time). The y-axis is use to show individual activities, to represent a variable across time (e.g.: man-hours, budget, % complete and so forth. The variables usually shown as a curve superimposed on the bar chart. 100 Cumulative progress (%) 0
29 Bar chart (Gantt Chart) Example 1: A project consist of five activities that should be done in a period of time. Try to create a bar chart to ease the project planning and scheduling. * consider 1 week as 7 days Activity A : 1 week, starting from 1 Jun 201 Activity B : 2 week, starting from 8 Jun 201 Activity C : week, starting from 1 Jun 201 Activity D : 2 week, starting from 22 Jun 201 Activity E : 2 week, starting from 29 Jun 201
30 Bar chart (Gantt Chart)-Example 1 Step 1: identify start date and finish date for each activity Activity A : 1 week, starting from 1 Jun 201 (1/6-7/6) Activity B : 2 week, starting from 8 Jun 201 (8/6-21/6) Activity C : week, starting from 1 Jun 201 (1/6-/7) Activity D : 2 week, starting from 22 Jun 201 (22/6-/7) Activity E : 2 week, starting from 29 Jun 201 (29/6-12/7)
31 Bar chart (Gantt Chart)-Example 1 Step 2: Draw outline of bar chart Activity Duration (week) Week 1 Week 2 Week Week Week Week 6 1/6 8/6 1/6 22/6 29/6 6/7 Act. A 1 Act. B 2 Act. C Act. D 2 Act. E 2
32 Activity Bar chart (Gantt Chart)-Example 1 Step : Draw the activity bars Duration (week) Act. A 1 Act. B 2 Act. C Act. D 2 Act. E 2 Activity A : 1 week, starting from 1 Jun 201 (1/6-7/6) Activity B : 2 week, starting from 8 Jun 201 (8/6-21/6) Activity C : week, starting from 1 Jun 201 (1/6-/7) Activity D : 2 week, starting from 22 Jun 201 (22/6-/7) Activity E : 2 week, starting from 29 Jun 201 (29/6-12/7) Week 1 Week 2 Week Week Week Week 6 1/6 8/6 1/6 22/6 29/6 6/7
33 Bar chart (Gantt Chart)-Example 2 Num Activity Duration (days) Start Date Cost (RM) Resources/ day (person) Work progress percentage (%) 1 Activity A //201 1, Activity B 7//201 2, Activity C 7 10//201, Activity D 1//201 6, Activity E 17//201, Activity F 6 19//201 12, ,
34 Bar chart (Gantt Chart)-Example 2 Step 1: identify start date and finish date for each activity Activity A : days, starting from May 201 (/-6/) Activity B : days, starting from 7 May 201 (7/-11/) Activity C : 7 days, starting from 10 May 201 (10/-16/) Activity D : days, starting from 1 May 201 (1/-19/) Activity E : days, starting from 17 May 201 (17/-20/) Activity F : 6 days, starting from 19 May 201 (19/-2/)
35 Bar chart (Gantt Chart)-Example 2 Step 2: Draw outline of bar chart / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Act. A Act. B Act. C 7 Act. D Act. E Act. F 6
36 Bar chart (Gantt Chart)-Example 2 Step : Draw the activity bars Activity A :(/-6/) Activity B :(7/-11/) Activity C :(10/-16/) Activity D :(1/-19/) Activity E :(17/-20/) Activity F :(19/-2/) Activity Duration (days) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A Act. B Act. C 7 Act. D Act. E Act. F 6
37 An S-curveis defined as: "A display of cumulative costs, labor hours or other quantities plotted against time. The name derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the middle, which is typical of most projects. The beginning represents a slow, deliberate but accelerating start, while the end represents a deceleration as the work runs out."
38 S-Curve Type of S-Curve Physical S-Curve Financial S-Curve Both S-curve can be in Baseline (planned) or actual S-curve
39 Num Activity Duration (days) S-Curve (Example) Start Date Cost (RM) Resources/ day (person) Work progress percentage (%) 1 Activity A //201 1, Activity B 7//201 2, Activity C 7 10//201, Activity D 1//201 6, Activity E 17//201, Activity F 6 19//201 12, , Based on bar chart in Example 2, construct S-curve (daily basis) for this project: 1. Financial S-Curve 2. Physical S-curve (resources vstime & work vstime)
40 Financial S-Curve
41 Financial S-Curve STEP 1: DRAW BAR CHART (from Example 2), include Cost of each activity Activity Duration (days) Cost (RM) Cost/day (RM) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A 1,00 Act. B 2,700 Act. C 7,00 Act. D 6,000 Act. E,700 Act. F 6 12,600 Cost/day Cumulative cost/day
42 Financial S-Curve STEP 2: Calculate COST/ DAY = Cost / duration Activity Duration (days) Cost (RM) Act. A 1,00 Act. B 2,700 Act. C 7,00 Act. D 6,000 Act. E,700 Act. F 6 12,600 Cost/day Cost/day (RM) =1,00/ 67 =2,700/ 0 =,00/7 00 =6,000/ 1200 =,700/ 117 =12,600/ / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Cumulative cost/day
43 Financial S-Curve STEP 2: Calculate COST/ DAY = Cost / duration Activity Duration (days) Cost (RM) Cost/day (RM) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A 1,00 Act. B 2,700 Act. C 7,00 Act. D 6,000 Act. E,700 Act. F 6 12, Cost/day Cumulative cost/day
44 Financial S-Curve STEP : Calculate the TOTAL COST of each DAY / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Cost (RM) Cost/day (RM) Act. A 1,00 67 Act. B 2,700 Act. C 7, Act. D 6, Act. E, Act. F 6 12, Cost/day Cumulative cost/day
45 Financial S-Curve STEP : Calculate the CUMULATIVE COST of each DAY / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Cost (RM) Cost/day (RM) Act. A 1,00 67 Act. B 2,700 0 Act. C 7,00 00 Act. D 6, Act. E, Act. F 6 12, Cost/day Cumulative Cumulative cost cost (previous) (previous) + current + current cost/day cost/day = 67 = Cumulative cost/day
46 Financial S-Curve STEP : Plot graph base on cumulative cost / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Cost (RM) Act. A 1,00 Act. B 2,700 Act. C 7,00 Act. D 6,000 Act. E,700 Act. F 6 12,600 Start from 0 Cost/day Cost/da y (RM) Total cumulative cost Get the medium (0900 /2) Start from Cumulative cost/day
47 Financial S-Curve STEP : Plot graph base on cumulative cost / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Cost (RM) Act. A 1,00 Act. B 2,700 Act. C 7,00 Act. D 6,000 Act. E,700 Act. F 6 12,600 Cost/day Cost/da y (RM) Cumulative cost/day
48 Physical S-Curve (resources VS time)
49 Num Activity Duration (days) Start Date Cost (RM) Resources/ day (person) Work progress percentage (%) 1 Activity A //201 1, Activity B 7//201 2, Activity C 7 10//201, Activity D 1//201 6, Activity E 17//201, Activity F 6 19//201 12, ,
50 Physical S-Curve (resources VS time) STEP 1: DRAW BAR CHART (from Example 2), include resource/day for each activity Activity Duration (days) Resource/ day / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A 2 Act. B Act. C 7 2 Act. D Act. E Act. F 6 Resource/day Cumulative resource/day
51 Physical S-Curve (resources VS time) STEP 2: Calculate the CUMULATIVE resource of each DAY / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Resource/ day Act. A 2 Act. B Act. C 7 2 Act. D Act. E Act. F 6 2Resource/day Cumulative resource (previous) + current resource/day = Cumulative resource/day
52 Physical S-Curve (resources VS time) STEP : Plot graph base on cumulative resource / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Resource/ day Act. A 2 Act. B Act. C 7 2 Act. D Act. E Act. F 6 2Resource/day Cumulative resource/day
53 Physical S-Curve (resources VS time) STEP : Plot graph base on cumulative resource / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Resource/ day Act. A 2 Total cumulative resource Act. B Act. C 7 2 Act. D Act. E Act. F 6 102/6 x 2 = 102/6 = 17 Start from 0 2Resource/day Cumulative resource/day
54 Physical S-Curve (resources VS time) STEP : Plot graph base on cumulative resource / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Activity Duration (days) Resource/ day Act. A 2 Act. B Act. C 7 2 Act. D Act. E Act. F 6 2Resource/day Cumulative resource/day
55 Physical S-Curve (work VS time)
56 Num Activity Duration (days) Start Date Cost (RM) Resources/ day (person) Work progress percentage (%) 1 Activity A //201 1, Activity B 7//201 2, Activity C 7 10//201, Activity D 1//201 6, Activity E 17//201, Activity F 6 19//201 12, ,
57 Physical S-Curve (work VS time) STEP 1: DRAW BAR CHART (from Example 2), include work progress percentage/day for each activity Activity Duration (days) Work progress percentage (%) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A 12 Act. B 0 Act. C 7 21 Act. D 10 Act. E 12 Act. F 6 1 Work progress/day Cumulative work progress/day
58 Physical S-Curve (work VS time) STEP 2: Calculate work progress percentage of each day for every activities Activity Duration (days) Work progress percentage (%) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A 12 12% / days = %/ day Act. B % / days = 6%/ day Act. C 7 Act. D Act. E Act. F 6 Work progress/day Cumulative work progress/day
59 Physical S-Curve (work VS time) STEP 2: Calculate work progress percentage of each day Activity Duration (days) Work progress percentage (%) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A Act. B Act. C 7 Act. D Act. E Act. F 6 Work progress/day Cumulative work progress/day
60 Physical S-Curve (work VS time) STEP : Calculate cumulative work progress percentage of each day Activity Duration (days) Work progress percentage (%) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A 12 Act. B Act. C 7 Act. D Act. E Act. F 6 Work progress/day Cumulative work progress/day
61 Physical S-Curve (work VS time) STEP : Calculate cumulative work progress percentage of each day Activity Duration (days) Work progress percentage (%) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A 12 Act. B Act. C 7 Act. D Act. E Act. F 6 Work progress/day Cumulative work progress/day
62 Physical S-Curve (work VS time) STEP : Plot S-curve Activity Duration (days) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ Act. A Work progress percentage (%) 12 Act. B Act. C 7 21 Act. D Act. E 12 Act. F Work progress/day Cumulative work progress/day
63 Physical S-Curve (work VS time) STEP : Plot S-curve Activity Duration (days) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 100 Act. A Work progress percentage (%) 12 7 Act. B Act. C Act. D Act. E 12 Act. F Work progress/day Cumulative work progress/day
64 Physical S-Curve (work VS time) STEP : Plot S-curve Activity Duration (days) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 100 Act. A Work progress percentage (%) 12 7 Act. B Act. C Act. D Act. E 12 Act. F Work progress/day Cumulative work progress/day
65 Physical S-Curve (work VS time) STEP : Plot S-curve Activity Duration (days) / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 100 Act. A Work progress percentage (%) 12 7 Act. B Act. C Act. D Act. E 12 Act. F Work progress/day Cumulative work progress/day
66 Planning VS Actual S-curve?? Before this, we just create a planning bar chart. What if, the real activities has started? How to create actual S-curve?
67 Planning VS Actual S-curve (Example 2) Physical S-Curve (work vs time) Num. Activity Duration (days) Start Date Actual Start Date Actual Finish Date Cost (RM) Resources (person) 1 Activity A //201 //201 6//201 1, Activity B 7//201 7//201 12//201 2, Activity C 7 10//201 11//201 17//201, Activity D 1//201 17//201 21//201 6, Activity E 17//201 18//201 22//201, Activity F 6 19//201 21//201 26//201 12, ,900.00
68 Activity Duration (days) Planning VS Actual S-curve STEP 1: DRAW BAR CHART (planning and actual) Start Date Actual Start Date Actual Finish Date Act. A //1 //1 6//1 Act. B 7//1 7//1 12//1 / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 2/ 26/ Planning Actual Act. C 7 10//1 11//1 17//1 Act. D 1//1 17//1 21//1 Act. E 17//1 18//1 22//1 Act. F 6 19//1 21//1 26//1 Planning cumulative work / day Actual cumulative work/ day
69 Activity Duration (days) Planning VS Actual S-curve STEP 2: Calculate cumulative for both planning & actual work/day Start Date Actual Start Date Actual Finish Date Act. A //1 //1 6//1 / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 2/ 26/ Act. B 7//1 7//1 12//1 Act. C 7 10//1 11//1 17//1 Act. D 1//1 17//1 21//1 Act. E 17//1 18//1 22//1 Act. F 6 19//1 21//1 26//1 Planning cumulative work / day Actual cumulative work/ day
70 Planning VS Actual S-curve STEP 2: Calculate cumulative for both planning & actual work/day Activity Duration (days) Start Date Actual Start Date Actual Finish Date Act. A //1 //1 6//1 / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 2/ 26/ Act. B 7//1 7//1 12//1 Act. C 7 10//1 11//1 17//1 Act. D 1//1 17//1 21//1 Act. E 17//1 18//1 22//1 Act. F 6 19//1 21//1 26//1 Planning cumulative work / day Actual cumulative work/ day
71 Planning VS Actual S-curve STEP : Plot the S -curves Activity Duration (days) Start Date Actual Start Date Actual Finish Date / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 2/ 26/ Act. A //1 //1 6//1 Act. B 7//1 7//1 12//1 Act. C 7 10//1 11//1 17//1 Act. D 1//1 17//1 21//1 Act. E 17//1 18//1 22//1 Act. F 6 19//1 21//1 26//1 Planning cumulative work / day Actual cumulative work/ day
72 Planning VS Actual S-curve STEP : Plot the S -curves Activity Duration (days) Start Date Actual Start Date Actual Finish Date / / 6/ 7/ 8/ 9/ 10/ 11/ 12/ 1/ 1/ 1/ 16/ 17/ 18/ 19/ 20/ 21/ 22/ 2/ 2/ 2/ 26/ Act. A //1 //1 6//1 Planning Act. B 7//1 7//1 12//1 Act. C 7 10//1 11//1 17//1 Actual Act. D 1//1 17//1 21//1 Act. E 17//1 18//1 22//1 Act. F 6 19//1 21//1 26//1 Planning cumulative work / day Actual cumulative work/ day
73 Arrow Diagram Method (ADM) -Activity-on-Arrow (AOA) Network Precedence Diagram Method (PDM) - Activity-on-Nodes (AON) Network
74 Network Diagram Activity on Arrow (AOA)/ Arrow Diagram Method (ADM) In arrow diagram project task or activities are represented by the arrow and connected by the node to express their logical relationship Node represents an event. An activity starts or ends at a node. Activity A Activity B Node Node Node
75 ADM Diagram for construction of pad footing Fabricated rebar Excavate trench Fixed fwk Fixed rebar Pour concrete Fabricated formwork
76 Network Diagram Activity on Node (AON)/ Precedence Diagram Method (PDM) activity is place on the node The arrow used to connect between project task to show their logical relationship Act. A Act. B Node Node
77 Network Diagram Diagram for construction of pad footing Arrow - Logical Node - Activity Logical Show the relationship between activities -Sequences of interrelated activity
78 Basic definition in network diagram Activity-the performance of a task required to complete the project. An activity require time, cost, or both. Network-a diagram to represent the relationship of activities to complete a project. The network may be drawn as ADM or PDM. Duration-the estimated time required to perform an activity.
79 Activity Sequencing Understand the order of how the job to be accomplished in the field. The planner must understand how various activities of the project related to each other in term of their logical sequence. Example preparing formwork before reinforcement could be place & than pouring concrete.
80 Activity Sequencing Predecessor A task whose start or finish date determines the start or finish date of its successor task. Successor A task whose start or finish date is driven by its predecessor task.
81 ADM vs. PDM Item ADM PDM Activity Activities shown as an arrow or sometimes as a line. A ES LS D A TF ES: Early Start LS: Late Start EF: Early Finish LF: Late Finish D : Duration TF: Total Float Activities shown on node. EF LF Event/ Node 1 ES LS A 2 EF LF ES LS D A TF EF LF 1 ES LS D B TF EF LF 2 events / nodes 1 event
82 ADM vs. PDM ADM PDM Early Start (ES) is the earliest possible time an activity Early can start. Finish (EF) is the earliest possible time an activity can finish if it is start on Early Start Time (ES) and finish within the planned duration. Late Finish (LF) is the latest *D = duration possible time an activity can finish without extending the completion date of the project. Late Start (LS) is the latest possible time an activity can start without extending the completing date of the project. LS = LF -D Total float (TF)- the amount of time an activity may be delayed without delaying the completion date of the project. TF = LF ES D or TF = LS ES EF = ES + D or TF = LF EF Free float (FF)- the amount of time an activity may be delayed without delaying the early start time of the immediately following activity. FF(i) = ES(j) EF(i) ; i-preceding activity, j-following activity
83 ADM vs. PDM ADM -A and B are activities. 1, 2 and are events -Activity A has ID or label 1-2 ; Activity B has ID or label 2- -Activity A precedes activity B A 1 2 B PDM Activity Nodes ES LS D A TF EF LF Predecessor Activity 1 ES LS D B TF EF LF Current Activity 2 ES LS D B TF EF LF Successor Activity
84 ADM vs. PDM Item ADM PDM Relationshi p F S ADM only shows finish-tostart relationships, meaning that each activity is completed before the successor activity starts. F S F F S S S - F Critical path - Critical Path - A series of interconnected activities through the network diagram, with each activity having zero total float time. The critical path determines the minimum time to complete the project. 1. ES X = LS X, or 2. LF X = EF X, or. Total Float (TF) = 0 - Possible to have more than one critical path - Activities which lay on critical path cannot suffer any delay
85 ADM vs. PDM Item ADM PDM Dummy Activity or D Definition An activity that indicates any activity following the dummy cannot be started until the activity(ies) preceding the dummy are completed. Activity which has not duration. It is only used to show any relationship between activities. Function If there is a situation where one event is used to show relationship more than one activity. To show a complicated relationship clearly Dummy activity is not used in Precedence Diagram Method (PDM)
86 ADM
87 Item Dummy Activity D or Activity A & B have the same ID A: 1-2 False B: 1-2 A 1 2 If C is to follow A & B, but D is to follow only B. (not fulfill) A B C ADM ID for Activity A & B are not same. A: 1-2 True B: B A If C is to follow A & B, but D is to follow only B. (use dummy) A C B D B D
88 Item ADM If P, Q and R follow A, and B follows P, Q and R. The following diagram is not the correct representation of the same. P False Dummy Activity A 1 2 Q R B D or Reason: Activities P, Q and R have the same ID (2-). True A 1 2 P Q B Activities P has the ID (2-), Q (2-) and R (2-6). R 6
89 Item ADM 1. D is preceded by A only 2. E is preceded by A and B. F is preceded by B and C Dummy Activity False True D A D A D or B E B E C F C F Statement not fulfill where F is preceded by A, B and C.
90 ADM vs. PDM Item ADM PDM Estimating duration - FORWARD PASS : To establish the earliest expected start and finish times for each activity in the network. - BACKWARD PASS : To establish the latest allowable start and finish times for each activity in the network. FORWARD PASS Early Start Early Finish Late Start Late Finish BACKWARD PASS 90
91 Arrow Diagram Method 91 Note A 1 a b 2 c d X Backward pass Forward pass c = a + X e = c + Y B Y d = f Y e f a : Early Start (ES) A b : Late Start (LS) A c : Early Finish (EF) A = (ES) B d : Late Finish (LF) A = (EF) B e : Early Finish (EF) B f : Late Finish (LF) B X : Duration of activity A Y : Duration of activity B Forward pass Backward pass a = 0 f = e c = a + X d = f Y e = c + Y b = d - X
92 ACTIVITY DURATION(DAY) PREDECESSOR A - B A C B D - E A F 10 E,D G 9 C,F
93 1 A 2 B E D F 10 C ACTIVITY G 9 DURATION (DAY) 6 PREDECESSOR A - B A C B D - E A F 10 E,D G 9 C,F
94 0+= Early Finish Box Early Start at node 1 is zero Early Start Box 1 0 A B 2 E D F 10 C G 9 6 Make forward pass through the network by adding duration times.
95 Early Start Box Early Finish Box 1 0 A 2 B 8 E D F 10 C +=8 G 9 6 Make forward pass through the network by adding duration times.
96 1 0 A B 2 8 C +=7 E D F 7 10 Larger=7 0+= G 9 6 If two or more activities terminate at a junction node, place the larger sum at ES box.
97 1 0 A B 2 8 E D F 7 10 C 17 G
98 1 0 A B 2 8 E D F 7 10 C 17 G Early finish of activity G in the node 6 =26 days. That s means it will take 26 days to complete the project. Therefore, 26days represents Late Finishof the project. Enter 26into Late Finish box at the node 6, and make a backward pass to establish LF for each activity by deducting the durations.
99 1-=9 Smaller= A B E 7-= D F C 17 G =17 In the case of junction nodes (with two or more activities), place the smaller value in the LF box of that node.
100 1 0 0 A B E D F C 17 G
101 TF A = LF-D-ES =--0 =0 TF A = TF B =6 B A E TF E =0 D F 7 10 TF D = 7 TF F =0 C TF C =6 TF B = LF-D-ES =1-- =6 17 G TF G =0 Total Float (TF) =LF-D-ES
102 TF B =6 TF A = B A E TF E =0 D F 7 10 TF D = 7 TF F =0 C TF C =6 17 G TF G =0 Activities on critical path : A,E,F and G.
103 ACTIVITY DURATION(DAY) ES EF LS LF TF A 0 0 0* B C D E 7 7 0* F * G * * Critical Activity Total Float (TF) =LF-D-ES
104 ACTIVITY DURATION (DAY) ES EF LS LF TF A 0 0 0* B BAR CHART C D E 7 7 0* F * G * Activity Duration (days) A B C D E F 10 G
105 Example 2 (ADM) Activity Duration (day) Predecessor (s) Act. A 2 - Act. B - Act. C A Act. D B Act. E C,D Act. F 2 C,D Act. G E Act. H F 1. Develop an arrow diagram for the project. 2. Identify critical activity and critical path for the project.
106 Activity Duration (day) Predecessor (s) Act. A 2 - Act. B - Act. C A Act. D B Act. E C,D Act. F 2 C,D Act. G E Act. H F 1 A 2 B 2 C D E F 2 6 G H 7
107 Forward pass 1 0 A 2 B 2 2 C D 7 E F G H 7 1
108 Backwardpass A 2 B 2 2 C D 7 7 E F G H 7 1 1
109 Total Float Activity Duration (day) ES EF LS LF TF Act. A Act. B 0 0 0* Act. C Act. D 7 7 0* Act. E * Act. F Act. G * Act. H * Critical Activity Total Float (TF) =LF-D-ES
110 Critical Path A 2 B 2 2 C D 7 7 E F G H Activities on critical path : B,D,E and G. Critical path
111 Exercise (ADM) Activity Duration (day) Predecessor (s) Act. A 2 - Act. B A Act. C A Act. D A Act. E 2 B,C Act. F C Act. G C,D Act. H 2 E,F,G Prepare a arrow diagram for the project. Identify critical path for the project.
112 Exercise Forward pass B 7,7 1 0 A 2 2 C 7 2 F 9,10,11 H D 6,7 7
113 Exercise Backward pass B A C ,2, 7 7 9,8,7 F H D 7 7
114 Exercise (ADM-Solution) B A C 7 7 F H Activities on critical path : A,C,G and H. D 7 7 Critical path
115 Link (Relationship) Finish to Start (FS) Activity B cannot start until Activity A finish Act. A Act. B Start to Start (SS) Activity B cannot start until Activity A start Act. A Act. B
116 Link (Relationship) Finish to Finish (FF) Activity B cannot finish until Activity A finish. Act. A Act. B Start to Finish (SF) Activity B cannot finish until Activity A start. Act. A Act. B
117 Lead time & lag time Lead time Overlap between dependent activity Eg: FS d Act. A Act. B Lag time Delay between dependent activity Eg: FS + 2 d Act. A d Act. B 2d
118 ACTIVITY DURATION(DAY) PREDECESSOR A 2 START B 6 A C 6 B D 1 B E A F D,E G 2 C(+2),F
119 ACTIVITY DURATION (DAY) PREDECESSOR ES D LS A 2 START B 6 A EXAMPLE 1 LS Activity TF LF C 6 B D 1 B E A F D,E 2 A 6 B 6 C G 2 C(+2),F 1 D E FS +2 F 2 G
120 EXAMPLE 1 FORWARD PASS A B C 16, D 2 E,9 FS F G
121 EXAMPLE 1 BACKWARD PASS A B C 16, D 2 E,9 FS F G 16 18
122 EXAMPLE 1 BACKWARD PASS A B C ,10 8, D E 10 1,9 FS F , G 16 18
123 EXAMPLE 1 BACKWARD PASS A B C ,10 8, D E 10 1,9 FS F , G 16 18
124 EXAMPLE 1 COMPLETED A B C ,12 2,10 8,12 FS D 12 1, F 16 G 18 2 E
125 EXAMPLE 1 12 TOTAL FLOAT A B C TF C = LF-EF =1-1 =0 TF G =0 = LF-EF = TF A = LF-EF =2-2 =0 TF B = LF-EF =8-8 = D FS G 0 18 TF D = LF-EF =1-9 = E F 1 TF E = LF-EF =1- =8 16 TF F = LF-EF =16-12 =
126 EXAMPLE FREE FLOAT A B C FF C = ES SUCC -EF- Lag = =0 FS FF A = ES SUCC -EF- Lag =2-2-0 =0 FF B Lag = ES SUCC -EF- =8-8-0 =0 FF D = ES SUCC -EF- Lag =9-9-0 = D E FF F = ES SUCC -EF- Lag = = 9 12 F G 0 18 FF A = ES SUCC - EF- Lag = =
127 EXAMPLE 1 CRITICAL PATH A B C ,12 2,10 8,12 FS D 12 1, F 16 G E
128 Example 2 (PDM) Activity Duration (day) Predecessor (s) Act. A 10 - Act. B 11 A Act. C B Act. D B Act. E 12 A Act. F C,D Act. G 7 F Act. H 11 E Act. I G,H 1. Develop a precedence diagram for the project. 2. Identify critical activity and critical path for the project.
129 Example 2 (PDM) 11 C 7 B F G 10 A D I 12 E 11 H ES LS D Activity TF LS LF
130 Example 2 (PDM-forward pass) C B F G A D 6 0 I E H ES LS D Activity TF LS LF
131 Example 2 (PDM-backward pass) B C F G D A 10 6 I E H ES D LS Activity LS TF LF
132 Example 2 (PDM-Total float) C B F G D A I E 1 2 H 2 TF = LF ES D or TF = LS ES or TF = LF EF Critical path 6 ES D LS Activity LS TF LF
133 Example (PDM) Activity Duration (week) Predecessor (s) Act. A 2 - Act. B A (FS+2), C (FF+1), D(FF) Act. C 2 A Act. D 1 C (SS) 1. Develop a precedence diagram for the project. 2. Identify critical activity and critical path for the project.
134 Example (PDM-forward pass) +2 7 B A 2 2 C D
135 Example (PDM-backward pass) +2 7 B A C Total Float = LF ES D TF(A) = = 0 TF(B) = 7-- = 0 TF(C) = = 2 TF(D) = = 1 2 D 6 7 Critical path
136 Exercise (PDM) Activity Duration (day) Predecessor (s) Act. A 2 - Act. B A Act. C A Act. D A Act. E 2 B,C Act. F C Act. G C,D Act. H 2 E,F,G Prepare a precedence diagram for the project. Identify critical path for the project.
137 Exercise (PDM-Solution) 2 B E A C F H D G
138 BUT WAIT!! Are there any other type of Scheduling method?? How if the Gantt Chart and CPM did not actually work/represent well with the nature/requirement of the particular construction project?? So, actually we have LINEAR SCHEDULING METHOD (LSM) / LINE OF BALANCE (LOB)
139 This method is actually appropriate for a project that: Progress linearly (straight without major fluctuation of activities), Highly repetitive works, Have fixed starting point and end, Such as; highways, airfields, pipelines, multiple housing units, high-rise buildings, etc.
140 LINEAR SCHEDULING METHOD (LSM) (cont.) Take for example; a highway construction project:
141 LINEAR SCHEDULING METHOD (LSM) (cont.) Kilometer(km) We have linear activities: 1. Clear & strip 2. Drainage. Subgrade. Base course. Pave Width of B: At 0km, the subgrade works will starts at week. until week. Height of A: At week, subgrade works from 1km to 21km. LSM Diagram for highway project (adopted from Nunnally, 201) Distance of C: It is a time lag / time float for 10km; between subgradeworks and base course works. 1. weeks to be exact.
142 THANK YOU
Project Management -- Developing the Project Plan
Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationIns. Luay Dwaikat Fall 2013/2014
An-Najah National University Faculty of Engineering Civil/Building Engineering Dept. Construction Management - 6147 Ins. : Luay Dwaikat Course Outline Introduction to project management Project Work breakdown
More informationProject Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams
Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able
More informationMnDOT use of Calendars in Primavera P6
MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be
More informationMnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationIntroduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES
Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and
More informationProject Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark
Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale
More informationTextbook: pp Chapter 11: Project Management
1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use
More informationConstruction Management
Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationProject Management Chapter 13
Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling
More informationCISC 322 Software Architecture
CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service
More informationCHAPTER 9: PROJECT MANAGEMENT
CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized
More informationAfter complete studying this chapter, You should be able to
Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics
More informationProgram Evaluation and Review Techniques (PERT) Critical Path Method (CPM):
Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the
More informationUNIT-II Project Organization and Scheduling Project Element
UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite
More informationINSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.
INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E
More informationA Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1
A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,
More informationGPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationAssistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationIE 102 Spring Project Management
IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and
More informationCONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING
CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING Planning of Works Contract Form of contract by which one party undertakes to the other to perform certain work, for a price. Corresponds to the execution of a
More informationProbabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4
Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center
More informationA convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.
Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects
More informationProject Management Fundamentals
Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)
More informationPROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana
PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce
More informationManagement Management
Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently
More informationPROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan
PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationProject Management Techniques (PMT)
Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.
More informationTeori Pengambilan Keputusan. Week 12 Project Management
Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM
More informationLecture 3 Project Scheduling
B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?
More informationChapter16Project Management and. Scheduling Project management
Chapter6Project Management and Scheduling Figure 6. On completion of this chapter, you should be able to identify key components of projects and the issues associated with them, and you should be able
More informationOutline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling
Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:
More informationSSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION
1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and
More information1 of 14 4/27/2009 7:45 AM
1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake
More informationSAMPLE. ANALYZING S-CURVES TCM Framework: 10.1 Project Performance Assessment. AACE International Recommended Practice No. 55R-09
E 55R09 SA M PL ANAL YZI NGSCURVES AACE International Recommended Practice No. 55R-09 ANALYZING S-CURVES TCM Framework: 10.1 Project Performance Assessment Rev. Note: As AACE International Recommended
More informationIf you have a question during any portion of this exam, raise your hand and speak to the proctor. Write legibly.
CE167: Engineering Project Management Spring 2007 Professor William Ibbs MIDTERM 2 SOLUTION Date: April 26, 2007 General Instructions All work is to be completed in a bluebook answers not recorded in a
More informationSECTION PROJECT SCHEDULE 08/08
SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationPROJECT MANAGEMENT CPM & PERT TECHNIQUES
PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a
More informationFinal: Total 200 points (3-hour exam)
Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000
More informationTechniques to Assist Delivery of Projects
Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction
More informationSECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)
SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment
More informationSECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES
SECTION 01 32 16.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES PART 1- GENERAL 1.1 DESCRIPTION: The Architect/Engineer of Record (A/E) shall develop a Critical Path Method (CPM Schedule) plan and schedule
More informationProject Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.
Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,
More informationThe Project Times and Costs
The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step
More informationPROJECT MANAGEMENT DIPLOMA COURSE
PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a
More informationPOLYTECHNIC OF NAMIBIA
POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:
More information06IP/IM74 OPERATIONS RESEARCH
06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this
More informationProgramme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001
Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique
More informationLine Of Balance. Dr. Ahmed Elyamany
Line Of Balance Dr. Ahmed Elyamany Intended Learning Outcomes Define the principles ofline of Balance (LOB) Demonstrate the application of LOB Understand the importanceof LOB Understand the process ofapplying
More informationThe Critical Path Method
The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico "I believe that this nation should commit
More informationAppendix A Decision Support Analysis
Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated
More informationVIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS
S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted
More informationBut is it on the critical path?
But is it on the critical path? Notes from an evening seminar held on the 12 May 2005 for the Adjudication Society Seminar in the London office of Ove Arup Speaker Peter Curtis Ladymead Projects Ltd Agenda
More informationProject planning and creating a WBS
37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and
More informationETSF01: Software Engineering Process Economy and Quality
ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower
More informationPROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA
This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract
More informationResearch Methods Outline
: Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research
More informationCHAPTER 7 PROJECT CONTROL
CHAPTER 7 PROJECT CONTROL The limited objective of project control deserves emphasis. Project control procedures are primarily intended to identify deviations from the project plan rather than to suggest
More informationAllocate and Level Project Resources
Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both
More informationAppendix B: Glossary of Project Management Terms
Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances
More informationQuality Project Management
Quality Project Management By James N. Salapatas, PE, PMP www.suncam.com Copyright 2014 James N. Salapatas Page 1 of 44 Table of Contents Title Page LIST OF CHARTS 2 LIST OF FIGURES 3 ABOUT THE COURSE
More informationMODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT
Programme BA (Hons) Fashion and Textiles (Top-Up) BA (Hons) Graphic Design with Animation (Top-Up) BA (Hons) Interior Design Cohort FDI- BFT(TP)/14B/PT FDI- BGDA(TP)/14B/PT FDI-BAID/13B/FT Examinations
More information6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM
/7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business
More informationReal-World Project Management. Chapter 15
Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,
More informationCHAPTER 5 STOCHASTIC SCHEDULING
CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration
More informationProject Planning. Planning is an important step in project execution. Planning means:
Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving
More informationVIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT
SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent
More informationChapter 2 The PERT/CPM Technique
Chapter The PERT/CPM Technique Abstract Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects
More informationMS Project 2007 Page 1 of 18
MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems
More informationCHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM
CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities
More informationOutline. Project Management. Introduction. What is a Project?
Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction
More informationPlan Implementation. Pushpa Lal Shakya
Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application
More informationSCM 301 (Solo) Exam 1 Practice Exam Solutions
1. D $118,000 www.liontutors.com SCM 301 (Solo) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network
More informationACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.
Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur
More informationVALLIAMMAI ENGINEERING COLLEGE
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE C&T:JTL 1 of 6 C&T:APPR:JDC:PAL:07-24-02 FHWA:APPR:06-01-11 a. Description. In addition to the progress
More informationINSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.
. Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your
More informationVIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS
S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted
More informationNetwork Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana
Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices
More informationDC Program and Project Managers Meeting #2
+ Trevor Lowing Trevor.Lowing@gmail.com DC Program and Project Managers Meeting #2 Session 1: Planning projects with MS Project Session 2: Workshop: Generating Reports with MS Project and Visual Basic
More informationHow to Satisfy GAO Schedule Best Practices
By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document
More informationFredric L. Plotnick, Ph.D., Esq., P.E. Engineering & Property Management Consultants, Inc.
Introduction of Relationship Diagramming Method (RDM) Variant of the Critical Path Method of Planning & Scheduling Analysis to Primavera Pertmaster Fredric L. Plotnick, Ph.D., Esq., P.E. Engineering &
More informationChapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
More informationAnswer Assignment # 3. ENGR 301 Lecture 12. Examples. Examples
NGR Lecture Midterm Revision Answer Assignment #. Table # represent a project on its th month. Calculate the V for each activity and for the total project. Calculate also the following. Cost and schedule
More information11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?
PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides
More informationSCM 301 (Lutz) Exam 1 Practice Exam Solutions
1. D $118,000 www.liontutors.com SCM 301 (Lutz) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network
More informationTip and Trick Bulletins 2/1/04
IN THIS ISSUE Primavera Project Planner (P3) Version 3.1 Survival Guide for Using Constraints by Eric Chou, PE A constraint is a restriction imposed on the schedule to control the results (such as Start
More informationDOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS
DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:
More informationSUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES
March 1, 2007 SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES General This supplemental specification addresses the Critical Path Method (CPM) construction schedule requirements
More informationProject Management with Brief Information regarding CPM and PERT Methods
99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract
More informationUNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018
ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018
More informationOptimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT
Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More information