1 Introduction of Relationship Diagramming Method (RDM) Variant of the Critical Path Method of Planning & Scheduling Analysis to Primavera Pertmaster Fredric L. Plotnick, Ph.D., Esq., P.E. Engineering & Property Management Consultants, Inc

2 Origin of the Problem

3 Evolution of CPM

4 Evolution of CPM 950 s 90 s 970 s 980 s 990 s 000 s

5 In the early days of CPM, computing capability was at a premium. Rooting out inconsistencies in scheduling data had to be left completely to the planner. In practice, this meant deliberately limiting the use of the "flexibility" features. Today, the desktop computer I'm using to compose this letter has far more capability than the UNIVAC we used for our first CPM calculations. Thus, there is no reason why the computer cannot be programmed to tell me that my scheduling input is inconsistent and why.

6 Scheduling Resources is Not CPM Notice to Proceed 0 Foundation Excavation 5 Resources FS FS FS FS Foundation Backfill

7 Plan then Schedule Notice to Proceed Foundation Excavation Cure 0 5 Cure Cure Cure Foundation Backfill Notice to Proceed 0 Foundation Excavation 5 FS FS FS FS Foundation Backfill

8 Plan then Schedule Notice to Proceed Foundation Excavation Cure 0 5 Cure Cure Cure Foundation Backfill Notice to Proceed 0 Foundation Excavation 5 FS FS FS FS Foundation Backfill

9 What can we do? Maths of 50s watered down to 50s computers PCs provide tools (but not skills) to the masses More powerful PCs benefit glitz not maths GUI and WYSIWYG i/o favors bar charting Wizards further reduce need for skills Where is the logic?

10 Proposed Solution RDM Relationship Diagramming Method

11 Introduction by James J. O Brien Improving CPM Restoring the Original Promise Video on next slide Kelley expected more from CPM but was limited by early computers free and independent float RDM created ~ 003 to 005 amazing grasp of the obvious what Kelley was looking for

12 Relationship Diagramming Method more about RDM requires you to record the relationships between activities and allows the computer to recalculate the impact of changes made reducing the 40%+ rework effort to that of a keystroke

13 Relationship Diagramming Method Five classes of new coding: The Event Code The Duration Code The Reason Why Code The Expanded Lead Lag Code The Relationship Code

14 Reason/Why Codes Record the reason why the restraint exists physical how important description resource crew/craft/equipment/forms/materials/etc. Excav 000 feet - 0 days P st / last 50 feet Stone 000 P st / last 50 feet Pave 000 P Required Open Section SS & FF feet - 0 days SS & FF feet - 0 days of Highway R Move Machine Type of restraint P=physical, R=resource and reason for restraint and duration between activities Pave Next Location Check for: physical open ends duplicative resource logic What if: add crews/equip/forms? add falsework/relax code?

15 Reason/Why Codes Special reason why codes physical just-in-time or subordinate support calculate latest dates to not delay early start of successor to restraint Survey P Excavate P Fdn P P P Fdn Fdn Rig & Set J = Just-in-Time P P P P Procure Submit Approve Fabricate Deliver

16 Additional code data on restraints Just-in-Time Physical Restraint distinguish prevent delaying project / prevent delaying work crew calculate new attributes JLS, JLF, JTF Rig/Set Steel is Critical Equipment has float Legend Top Line (Green) is Early Dates, Middle Line (Yellow) is Junior Dates, Bottom Line (Purple) is Late Dates

17 Just-in-Time Date & Float Attribute Legend Top Line (Green) is Early Dates, Middle Line (Yellow) is Junior Dates, Bottom Line (Purple) is Late Dates

18 Relationship Codes Restraint v Relationship Codes resource codes user defined activity codes Calculation on the fly? conduit cable connections energize rig pump pipe to pump run wire to pump Highlight the Handoff mechanical to electrical subcontractor crew movement between job area locations is there a handoff or demob/remob duration?

19 Put it all together event codes & text duration codes reason/why codes & text expanded lead/lag codes relationship codes 440i 440 Main Bldg - Install Roofing 0 C R RF A S3 440i0 at 500 SY of 5000 SY Crew Roofers FS RF Physical -- FS 0 -- Physical Penetrations at 50% PS 50% 440i 450i 40i Building Watertight 440 Garage Install Roofing 5 C R RF A5 S3 450 Main Bldg Studs & Drywall 0 I M 4 CP S0 S07 40 Main Bldg Roof HVAC 4 I M 4 SM S3 M4

20 Notice to Proceed Foundation Excavation Cure 0 5 Cure ADM Cure Cure Foundation Backfill Notice to Proceed 0 Foundation Excavation 5 FS PDM FS FS FS Foundation Backfill Notice to Proceed Foundation Excavation CP Crew 3 Rod Crew Cure FS Conc Crew Labor Crew Physical RDM Physical Physical 5 8 s # CP Crew Rod Crew 3 Cure FS Conc Crew Cure FS Labor Crew Physical Physical s # CP Crew Rod Crew Conc Crew Labor Crew Physical Cure FS Foundation Backfill 3

21 Industry Adoption

22 RDM is now in Primavera s Pertmaster v8.

23 Hailey Burton Cartwright Construction Company v. Macaw Casino Company

24 what s new on the screen? restraints have different colors two late start/finish bars reference to link category reference to ignore link

25 Reason/Why Codes Steel required before elev floor slabs

26 Relationship Codes

27 Relationship Codes A 0 - SiteG0 Notice to Proceed B SiteG0 Mobilize C fs D No LINKTYPE 0 LINKTITLE 0[fs] 000 G H I J K ACT 0 SUC 000 ACRTY SCRTY ALOC S SLOC S ALOC G0 SLOC G0 unknown craft unknown reason/why EDIT <C:> TRIAL07P Rec: /08 A 30 - West0 / Elev 7 B West09 / Slab C fs D No LINKTYPE 3 LINKTITLE 30[fs] 300 G H I J K ACT 30 SUC 300 ACRTY CP same crew different floor SCRTY CP ALOC W SLOC W ALOC 0 SLOC 09 EDIT <C:> TRIAL07P Rec: 5/08 A 5 - WestGS Erect, Bolt, Plumb Steel to Elev 77 B 0 - WestCL / Casino Level C fs D No LINKTYPE LINKTITLE 5[fs] 0 G H I J K ACT 5 SUC 0 ACRTY IW SCRTY CP change craft physical reason/why ALOC W SLOC W ALOC GS SLOC CL EDIT <C:> TRIAL07P Rec: 7/08 A 0 - WestGS / Footers B 0 - EastGS / Footers C fs D No LINKTYPE 4 LINKTITLE 0[fs] 0 G H I J K ACT 0 SUC 0 ACRTY CP SCRTY CP ALOC W SLOC E ALOC GS SLOC GS same crew different building EDIT <C:> TRIAL07P Rec: /08

28 Who asked for RDM?

29 Who asked for RDM? You Did!!! 59

30 Just-in-Time Date & Float Attribute As Early as Possible As Late as Possible w/o delay to Project As Late as Possible w/o delay to Production Just In Time LinkType

31 How accurate is the CPM calculation? Risk and Monte Carlo Simulation A 0± B 0± C 0± D 0± 40 Estimating A 0± Scheduling B 0± D 0± C 0± Project Duration 3⅔ % % DAY LATEST DATE 5 JUN MC0MPRJ.MC Sheet of Excerpt from page 4 of CPM in Construction Management EXPECTED DATE 3 MAY EARLIEST DATE MAY TARGET DATE 30 MAY 0 Plot Date 0FEB0 (c) Primavera Systems, Inc. MONTE CARLO TEST # Title Finish Date of Project Date Revision Checked Approved

32 Risk Analysis Features of Pertmaster v8.5

33 Risk Analysis 000 Iterations

34 Risk Analysis 000 Iterations

35 Risk Analysis with RDM 000 Iterations

36 Risk Analysis with RDM 000 Iterations

37 Better Specifications CPM is a Shop Drawing Purpose = Further Assurances Owner does not want CPM to show timely completion Owner wants CPM to assure timely completion Contractor shall provide a CPM: that indicates an 80% likelihood of completion on or before June 30, 009 prepared in the RDM format to separately show physical planning restraints from resource scheduling restraints coded to indicate sub, craft, location Updates to the CPM shall include additional reports that incorporate: trend analysis starting at 30% for any classification of work or subcontractor dynamic re-leveling with up to 5% additional resources if the likelihood of timely project completion falls below 80% a cost analysis if resources are to be increased involuntarily beyond 5%

38 The Road Ahead

39 Reason/Why Codes Special reason why codes resource leveling must suppress (ignore) R reason coded restraints for same resource R code temporarily replaced with S code for reporting and analysis L code restraints track actual resource deployment by leveling routine L coded restraints are deleted each time the leveling routine is re-run

40 Trend Durations for ACTIVITIES based upon any common resource based upon any user defined activity code for progress style RESTRAINTS based upon reference activity for passage style RESTRAINTS based upon any common resource based upon any user defined restraint code

41 Split Activities Distinguish Passage v Progress Activity A 0 days Activity B 5 days versus 3 days 3 days Activity A 0 days Activity B 5 days

42 Split Activity Mimics SS v PS

43 Split Activity Mimics SS v PS SS PS event between split activities distinguishes start Wall A Wallpaper days after starting Plaster Walls, and start Wall A Wallpaper when days of Plaster Walls completed (Wall A)

44 Relationship Diagramming Critical Path Method CT Contiguous representing a Finish-to-Start restraint where the preceding activity may not start until a contiguous and continuous flow of work may occur from the start of the predecessor to the finish of the successor The lag portion of this Lead/Lag code represents the longest weekend permitted between activities The use of this restraint code will be similar to assigning a Zero Free Float constraint to the predecessor affecting the successor activity of THIS restraint only Activity A Activity B

45 Relationship Diagramming Critical Path Method CC Concurrent representing the two activities must be performed in lock-step this is more than saying two activities joined with SS+FF or PS+FR

46 Relationship Diagramming Critical Path Method CC Concurrent representing the two activities must be performed in lock-step this is more than saying two activities joined with SS+FF or PS+FR Examples include: erecting a MSE wall and backfilling during placement pouring a concrete slab with embedded electrical conduit coordination of surgeon and anesthesiologist during an operation in each instance possibly being performed by separate subcontractors but under the daily control of only one individual the proper logical means to depict the combination is by only one activity, however the needs for separate rollups by subcontractors and the general desire for such a splitting of this ONE activity indicate a need for this type of restraint code

47 Relationship Diagramming Critical Path Method DS Duplicate SS+FF restraints sharing the same lag duration the MSCS program of the 90s and 970s included a popular Z code = combination of SS+FF indicates that the early (but not necessarily the late) start of the two activities would start together or that the two activities (if having the same duration) would be staggered note predecessor and successor activities should have the same duration and calendar An error code should be generated for violations. DP Duplicate PS+FR restraints sharing the same lag duration Similar to the DS restraint, except the successor activity will be calculated to start after the remaining duration of the predecessor has been reduced by Lag units of time. DR Duplicate RS+FP restraints sharing the same lag duration Similar to the DS restraint, except the successor activity will be calculated to finish after the remaining duration of the predecessor has been reduced to Lag units of time.

48 Other Contributions

49 performance of projects is measured by activities performance of projects is driven by relationships

50 Q&A

Working in Unexplored Territory. Technology, Project Delivery & Sustainable Design: Liability and Emerging Standards of Practice

Working in Unexplored Territory. Technology, Project Delivery & Sustainable Design: Liability and Emerging Standards of Practice Working in Unexplored Territory Technology, Project Delivery & Sustainable Design: Liability and Emerging Standards of Practice Introducing Fredric L. Plotnick, PhD., Esq., P.E. Moderator Co-Author CPM

More information

Ins. Luay Dwaikat Fall 2013/2014

Ins. Luay Dwaikat Fall 2013/2014 An-Najah National University Faculty of Engineering Civil/Building Engineering Dept. Construction Management - 6147 Ins. : Luay Dwaikat Course Outline Introduction to project management Project Work breakdown

More information

30 Sample CPM Specification: A Guideline for Preparing Your Own Specification

30 Sample CPM Specification: A Guideline for Preparing Your Own Specification Chapter 30 Sample CPM Specification: A Guideline for Preparing Your Own Specification This 8th edition is taking a new approach to writing a sample specification. Previous editions included language and

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES March 1, 2007 SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES General This supplemental specification addresses the Critical Path Method (CPM) construction schedule requirements

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Tip and Trick Bulletins 2/1/04

Tip and Trick Bulletins 2/1/04 IN THIS ISSUE Primavera Project Planner (P3) Version 3.1 Survival Guide for Using Constraints by Eric Chou, PE A constraint is a restriction imposed on the schedule to control the results (such as Start

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CRITICAL PATH METHOD NETWORK SCHEDULE C&T:JTL 1 of 6 C&T:APPR:JDC:PAL:07-24-02 FHWA:APPR:06-01-11 a. Description. In addition to the progress

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment

More information

How to Satisfy GAO Schedule Best Practices

How to Satisfy GAO Schedule Best Practices By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document

More information

SECTION PROJECT SCHEDULE 08/08

SECTION PROJECT SCHEDULE 08/08 SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

How to Properly Demonstrate Delays in a P3 Schedule to Support a Delay Claim. Michael E. Stone

How to Properly Demonstrate Delays in a P3 Schedule to Support a Delay Claim. Michael E. Stone How to Properly Demonstrate Delays in a P3 Schedule to Support a Delay Claim Michael E. Stone Construction Delays & CPM Schedules Recognize different types of delays Understand how to use P3 to measure

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE [---Section 01315A should be used for contracts for which a fully-developed computergenerated critical path method is appropriate for managing

More information

SECTION NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY)

SECTION NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) SECTION 01 32 16.16 NETWORK ANALYSIS SCHEDULES (DESIGN-BUILD ONLY) PART 1- GENERAL 1.1 DESCRIPTION: SPEC WRITER NOTES: 1. Coordinate this Design-Build Specification with FAR 52.232, VAAR 852.236 and Section

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

Is your Schedule Ready for the 14-Point DCMA Assessment?

Is your Schedule Ready for the 14-Point DCMA Assessment? Is your Schedule Ready for the 14-Point DCMA Assessment? By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 Copyright 2010 EyeDeal Tech. All rights reserved. This document and translations

More information

Plan Implementation. Pushpa Lal Shakya

Plan Implementation. Pushpa Lal Shakya Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application

More information

2. Briefly discuss the factors that contribute to the improvement of the contractor s cash flow?

2. Briefly discuss the factors that contribute to the improvement of the contractor s cash flow? Part 1: Short Answers 1. Discuss the effect of the following contract types on the owner s risk? Unit price Lump sum Cost plus sliding fees Cost plus percentage of cost 2. Briefly discuss the factors that

More information

THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM

THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM COST THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM November/December 2012 ENGINEERING www.aacei.org INTEGRATED COST-SCHEDULE RISK ANALYSIS ESTIMATE ACCURACY: DEALING WITH

More information

CHAPTER 5 STOCHASTIC SCHEDULING

CHAPTER 5 STOCHASTIC SCHEDULING CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration

More information

Chapter16Project Management and. Scheduling Project management

Chapter16Project Management and. Scheduling Project management Chapter6Project Management and Scheduling Figure 6. On completion of this chapter, you should be able to identify key components of projects and the issues associated with them, and you should be able

More information

SECTION PROGRESS SCHEDULE

SECTION PROGRESS SCHEDULE NOTE: Review this section carefully. If Project Scope is complex this Specification is to be used. If project is relatively simple and straightforward use Section 01310. SECTION 01311 PART 1 GENERAL 1.1

More information

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23 P6 Data Dictionary Version 17 July 2017 Contents Cloud or On-Premises Content... 19 Introduction... 21 Data Dictionary... 23 % Allocation... 23 Access Level... 23 Access Time... 23 Accounting Variance...

More information

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1 A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,

More information

70-632_formatted. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0

70-632_formatted.   Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0 70-632_formatted Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ Microsoft EXAM 70-632 TS:Microsoft Office Project 2007. Managing Projects Total Questions:

More information

AACE International Recommended Practices

AACE International Recommended Practices AACE International Recommended Practice No. 49R-06 IDENTIFYING THE CRITICAL PATH TCM Framework: 7.2 Schedule Planning and Development, 9.2 Progress and Performance Measurement, 10.1 Project Performance

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568

David T. Hulett, Ph.D, Hulett & Associates, LLC # Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 David T. Hulett, Ph.D, Hulett & Associates, LLC # 27809 Michael R. Nosbisch, CCC, PSP, Project Time & Cost, Inc. # 28568 Integrated Cost-Schedule Risk Analysis 1 February 25, 2012 1 Based on AACE International

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

Direct labour 8 Direct material 50 Variable production overhead 8 Fixed production overhead 12 Administration overhead 5

Direct labour 8 Direct material 50 Variable production overhead 8 Fixed production overhead 12 Administration overhead 5 1. Anderson Ltd. manufacture gearboxes for use in cars. At the start of the year, the management of Anderson Ltd. estimated that its costs would be: % of sales value Direct labour 8 Direct material 50

More information

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett (RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice Dr. David T. Hulett Author Biography David T. Hulett, Hulett & Associates, LLC Degree: Ph.D. University: Stanford

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

Improving workflow and resource usage in construction schedules through location-based

Improving workflow and resource usage in construction schedules through location-based Construction Management and Economics ISSN: 044-693 (Print) 466-433X (Online) Journal homepage: http://www.tandfonline.com/loi/rcme20 Improving workflow and resource usage in construction schedules through

More information

This contract shall be known as PGC-LGF-18-02

This contract shall be known as PGC-LGF-18-02 All bids must be submitted electronically @ the website www.pasupplierportal.state.pa.us before the deadline of 2:00 PM on April 10, 2019 to be eligible for consideration. This contract shall be known

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018

More information

SPECIFICATION NO.1197S Addendum No.5 Attachment B. New and Revised Specification Sections. Page 1 of 2 Specification No. 1197S Addendum No.

SPECIFICATION NO.1197S Addendum No.5 Attachment B. New and Revised Specification Sections. Page 1 of 2 Specification No. 1197S Addendum No. SPECIFICATION NO.1197S Addendum No.5 Attachment B New and Revised Specification Sections Page 1 of 2 Specification No. 1197S Addendum No. 5 ATTACHMENT B TABLE OF CONTENTS New Specification Sections or

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

Time and Cost Optimization Techniques in Construction Project Management

Time and Cost Optimization Techniques in Construction Project Management Time and Cost Optimization Techniques in Construction Project Management Mr.Bhushan V 1. Tatar and Prof.Rahul S.Patil 2 1. INTRODUCTION In the field of Construction the term project refers as a temporary

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

TEXAS A&M UNIVERSITY FACILITIES SERVICES SUPPLEMENTAL GENERAL CONDITIONS

TEXAS A&M UNIVERSITY FACILITIES SERVICES SUPPLEMENTAL GENERAL CONDITIONS TEXAS A&M UNIVERSITY FACILITIES SERVICES SUPPLEMENTAL GENERAL CONDITIONS These Texas A&M University Supplemental General Conditions amend and supplement the Uniform General and Supplementary Conditions

More information

Brown hamburger and assemble tacos (including cheese)

Brown hamburger and assemble tacos (including cheese) 19.1 An Introduction to PERT PERT is an acronym for the Program Evaluation Review Technique. The Special Projects Office in the Department of the Navy created this project management tool in 1958. It was

More information

CITY OF FORT PIERCE BUILDING DEPARTMENT

CITY OF FORT PIERCE BUILDING DEPARTMENT CITY OF FORT PIERCE BUILDING DEPARTMENT APPLICATION FOR DETERMINATION OF SUBSTANTIAL IMPROVEMENT This is a request for determination by the City s Floodplain Administrator as to whether or not the project

More information

This paper proposes contractual language intended to

This paper proposes contractual language intended to CDR.14 Proposed Specification Language Regarding Pacing Mr. Kenji P. Hoshino PSP This paper proposes contractual language intended to specify and predetermine rules for applying the pacing concept to delays

More information

CHAPTER 6 PROJECT CASH FLOW

CHAPTER 6 PROJECT CASH FLOW CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter deals with project cash

More information

PML Analysis of Construction Models

PML Analysis of Construction Models PML Analysis of Construction Models The United States case 8 October, 2015 Bruce Cliff, The Travelers Companies, Inc. Agenda Surety & Fidelity Association of America (SFAA) Terminology Background Results

More information

Electric Service Information Sheet Georgia Power Company

Electric Service Information Sheet Georgia Power Company Electric Service Information Sheet Georgia Power Company Project: Location: Developer: (Name of S/D or Customer) (Street Address or road Name) (Developer s Name) Georgia Power Company (the Company) will

More information

VDOT Dashboard 4.0 Projects User Guide DRAFT

VDOT Dashboard 4.0 Projects User Guide DRAFT VDOT Dashboard 4.0 Projects User Guide DRAFT March 2018 Table of Contents INTRODUCTION... 1 About this Guide...1 Purpose of the Guide... 1 Audience for the Guide... 1 About Dashboard...1 VDOT Dashboard...

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 1 T100 PROJECT LOCATION MAP Scale: NTS N Revisions: No. Date: Description: Scale As Indicated

More information

SCM 301 (Solo) Exam 1 Practice Exam Solutions

SCM 301 (Solo) Exam 1 Practice Exam Solutions 1. D $118,000 www.liontutors.com SCM 301 (Solo) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

SCM 301 (Lutz) Exam 1 Practice Exam Solutions

SCM 301 (Lutz) Exam 1 Practice Exam Solutions 1. D $118,000 www.liontutors.com SCM 301 (Lutz) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

Kala, Tanmaya; Mouflard, Christopher; Seppänen, Olli Production Control using Location-Based Management System on a Hospital Construction Project

Kala, Tanmaya; Mouflard, Christopher; Seppänen, Olli Production Control using Location-Based Management System on a Hospital Construction Project Powered by TCPDF (www.tcpdf.org) This is an electronic reprint of the original article. This reprint may differ from the original in pagination and typographic detail. Kala, Tanmaya; Mouflard, Christopher;

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Project Delays and Extensions of Time. Dr Tony Farrow

Project Delays and Extensions of Time. Dr Tony Farrow Project Delays and Extensions of Time Dr Tony Farrow Topics 1. Why Extensions of Time? 2. Methods of Analysis and examples 3. Schedule Float 4. Concurrent Delay 5. Exercise 6. Questions Construction Contracts

More information

DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VIRGINIA

DEPARTMENT OF TRANSPORTATION 1401 EAST BROAD STREET RICHMOND, VIRGINIA Charles A. Kilpatrick, P.E. Commissioner May 11, 2016 DEPARTMENT OF TRANSPORTATION 1401 ST BROAD STREET RICHMOND, VIRGINIA 23219-2000 Order No.: J88 Project: (NFO) 0095-043-848, M501 FHWA: HSIP-0951(351)

More information

GOPHER STATE ONE CALL

GOPHER STATE ONE CALL 1110 Centre Pointe Curve, Mendota Heights, MN 55120 OFFICE HOURS: 6:00 a.m. - 6:00 p.m. April thru October 7:00 a.m. - 5:00 p.m. November thru March (excluding weekends and holidays) REFER TO THE HANDBOOK

More information

ROWLAND UNIFIED SCHOOL DISTRICT

ROWLAND UNIFIED SCHOOL DISTRICT UNIFORM CONSTRUCTION COST ACCOUNTING; INFORMAL BIDDING PRE-QUALIFICATION APPLICATION (Public Contract Code 22030 et seq. for Projects Valued Between $45,000 and $175,000) FOR THE CALENDAR YEAR PRE-QUALIFICATION

More information

NOTE: ONLY FULLY COMPLETED ORIGINAL APPLICATIONS INCLUDING ALL ADDITIONAL INFORMATION REQUESTED WILL BE CONSIDERED.

NOTE: ONLY FULLY COMPLETED ORIGINAL APPLICATIONS INCLUDING ALL ADDITIONAL INFORMATION REQUESTED WILL BE CONSIDERED. Tribal Employment Rights Commission Poarch Band of Creek Indians 5811 Jack Springs Road Atmore, Alabama 36502 Location: 3480 Highway 21 Phone: (251) 368-0606 Ext. 07 Fax: (251) 368-9312 TRIBAL EMPLOYMENT

More information

NETWORK ANALYSIS QUESTION BANK

NETWORK ANALYSIS QUESTION BANK NETWORK ANALYSIS QUESTION BANK 1. Explain the terms : Total elapsed time, idle time. 2. What do you mean by dummy activity and successor activity. 3. Write four advantages of network analysis. 4. Explain

More information

Final: Total 200 points (3-hour exam)

Final: Total 200 points (3-hour exam) Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000

More information

Project orie:nta.teci pla.:n:ni:ng, scheduling a.:nci controlling technique

Project orie:nta.teci pla.:n:ni:ng, scheduling a.:nci controlling technique Project orie:nta.teci pla.:n:ni:ng, scheduling a.:nci controlling technique By Ha ilu Yemanu, Chief Engineer, Awash Valley Authority In the past several years, 1/iere has been an explosive growth of management

More information

Status: Structural steel installation underway at primary building. Observatory construction underway.

Status: Structural steel installation underway at primary building. Observatory construction underway. Page 1 of 11 FACILITIES PLAN STATUS REPORT March 30, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

But is it on the critical path?

But is it on the critical path? But is it on the critical path? Notes from an evening seminar held on the 12 May 2005 for the Adjudication Society Seminar in the London office of Ove Arup Speaker Peter Curtis Ladymead Projects Ltd Agenda

More information

Project Management Techniques (PMT)

Project Management Techniques (PMT) Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

SAN LUIS OBISPO COUNTY COMMUNITY COLLEGE DISTRICT

SAN LUIS OBISPO COUNTY COMMUNITY COLLEGE DISTRICT SAN LUIS OBISPO COUNTY COMMUNITY COLLEGE DISTRICT UNIFORM CONSTRUCTION COST ACCOUNTING; INFORMAL BIDDING PREQUALIFICATION APPLICATION (Public Contract Code 22030 et seq. for Projects Valued Up to $200,000)

More information

CE 167 Exam #2 Fall 2003 Prof. C.W. Ibbs

CE 167 Exam #2 Fall 2003 Prof. C.W. Ibbs CE 167 Exam #2 Fall 2003 Prof. C.W. Ibbs Directions: Put your name on this exam. This exam is to be completed on these pages answers not recorded in this exam will not be graded. Read the question thoroughly

More information

u w 1.5 < 0 These two results imply that the utility function is concave.

u w 1.5 < 0 These two results imply that the utility function is concave. A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that

More information

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule Presented to the 2013 ICEAA Professional Development & Training Workshop June 18-21, 2013 David T. Hulett, Ph.D. Hulett & Associates,

More information

USER GUIDE - simple steps for 360 sourcing GET POSITIVE BE POSITIVE STAY POSITIVE

USER GUIDE - simple steps for 360 sourcing GET POSITIVE BE POSITIVE STAY POSITIVE USER GUIDE - simple steps for 360 sourcing GET POSITIVE BE POSITIVE STAY POSITIVE Simple steps to sourcing your 360 user guide STEP 1: Login /register / edit your account details go to > STEP 3: Refine

More information

Cost Reduction: Planning & Control. Impacting the Bottom Line

Cost Reduction: Planning & Control. Impacting the Bottom Line Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,

More information

Line Of Balance. Dr. Ahmed Elyamany

Line Of Balance. Dr. Ahmed Elyamany Line Of Balance Dr. Ahmed Elyamany Intended Learning Outcomes Define the principles ofline of Balance (LOB) Demonstrate the application of LOB Understand the importanceof LOB Understand the process ofapplying

More information

Humphreys &Associates, Inc.

Humphreys &Associates, Inc. Humphreys &Associates, Inc. 3111 N. Tustin Street, Suite 250 Orange, CA 92865 (714) 685-1730 (Phone) (714) 685-1734 (Fax) Email: humphreys@humphreys-assoc.com http://www.humphreys-assoc.com No portion

More information

P6 Data Dictionary Release 8.3

P6 Data Dictionary Release 8.3 P6 Data Dictionary Release 8.3 March 2013 Legal Notices Oracle Primavera P6 Data Dictionary Copyright 1999, 2013, Oracle and/or its affiliates. All rights reserved. Oracle and Java are registered trademarks

More information

Lecture 3 Project Scheduling

Lecture 3 Project Scheduling B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?

More information

Rock Chalk Park - Infrastructure Report. July 2013

Rock Chalk Park - Infrastructure Report. July 2013 Rock Chalk Park Infrastructure Report July 2013 The following report is the first monthly report for the construction of infrastructure at Rock Chalk Park. The format follows the sections outlined in the

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

BUILDING PERMIT-GENERAL INFORMATION

BUILDING PERMIT-GENERAL INFORMATION Inc. Village of New Hyde Park BUILDING PERMIT-GENERAL INFORMATION THIS INFORMATION IS FOR BUILDING PERMITS ONLY. PLUMBING PERMITS MUST ALSO BE APPLIED FOR ALL PLUMBING WORK 1. Fee MUST be paid at time

More information

SECTION 7 - PROSECUTION OF THE WORK TABLE OF CONTENTS

SECTION 7 - PROSECUTION OF THE WORK TABLE OF CONTENTS SECTION 7 - PROSECUTION OF THE WORK TABLE OF CONTENTS Section Page 7-1 BEGINNING OF WORK... 7.1 7-2 AMOUNT OF WORK UNDER CONSTRUCTION... 7.1 7-3 PRECONSTRUCTION CONFERENCE AND PROGRESS MEETINGS... 7.1

More information

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,

More information

Construction Report Update

Construction Report Update NEW TRIER HIGH SCHOOL Construction Report Update September 2016 New Trier Winnetka Campus West Side Addition TABLE OF CONTENTS I. Neighbor Relations II. III. IV. Project Summary Schedule Progress Milestones

More information

THIS IS AN APPLICATION FOR A BUILDING PERMIT

THIS IS AN APPLICATION FOR A BUILDING PERMIT THIS IS AN APPLICATION FOR A BUILDING PERMIT 1. Read these instructions and carefully complete the application. 2. No building or structure shall be erected, added to or structurally altered or the use

More information