UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

Size: px
Start display at page:

Download "UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018"

Transcription

1 ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018 Time: INSTRUCTIONS TO CANDIDATES: This paper contains two sections: section A and section B Section A contains one question: you must answer this question. It is worth 40 marks. Section B contains four questions: you should answer any three questions from these four questions. Each of these questions is worth 20 marks. Marks for parts of questions are shown in brackets. This examination paper carries a total of 100 marks. All working must be shown. A numerical solution to a question obtained by programming an electronic calculator will not be accepted.

2 Section A Compulsory Question Question One The information provided in Table Q1 represents the activity dependencies to be followed for a major road-bridge project. List of Duration Activity Dependencies Activities (weeks) A 4 A starts the project. B 8 B can begin once A has completed. C 6 C can start on completion of both D and B. D 3 D can begin 2 weeks after the start of A (SS2). E 5 E can only commence 1 week after the completion of F (FS1) F 2 F starts on completion of A. G 6 G begins no sooner than 3 weeks from the start of A (SS3) H 3 H can commence once F and G are complete. J 2 J can begin 7 weeks after the start of C (SS7). J also starts when E has ended. K 4 K follows H and also commences 2 weeks after the start of E (SS2). L 2 L follows both J & C. However, L may only start 2 weeks after C is finished (FS2). L finishes the project. M 3 M commences upon completion of K. M finishes the project. Complete the following tasks: Table Q1 (a) Draw a network diagram for the above activities using precedence diagram. (b) Carry out forward and backward passes to determine earliest & latest times and earliest & latest finish times for each activity and the network critical path. (c) Calculate the Total Float (TF), Total Time Available (TTA) and Free Float (FF) for all non-critical activities Page 2 of 7 Question 1 continues overleaf

3 Question 1 continued (d) If the contractor has detected the following two mistakes: The duration of Activity E should be 15 weeks not 5 weeks. Activity L follows J (as before) but should begin 8 weeks after the completion of C not 2 weeks. The Client is anxious not to exceed 26 weeks for this project. Review the precedence diagram, examine the effect of the above changes and any change in the free float for activities F, E and M, then advise the Client of the consequences. Section B Answer any three questions Question Two Page 3 of 7 Total 40 marks (a) Critically discuss the six main steps of value engineering, and the main tasks and outcomes of each stage. (b) Critically evaluate the process of Project Risk Management and how each stage of risk analysis and risk response could be conducted including the techniques/tools used in each stage. Question Three Total 20 marks (a) Appraise the roles and responsibilities of a project manager, and critically discuss the skills and attributes required to be an effective project manager. (b) Critically discuss the five key stages through which groups or teams pass (Tuckman s Model) and relate that to the nature of the construction industry. Total 20 marks

4 Question Four (a) Discuss the main objective of resources aggregation in a construction project and mention some of the techniques used to achieve it. 4 marks (b) The network diagram in Figure Q4 represents a planning programme for construction activities in a project as viewed by the construction manager. Activities duration are given in weeks. (i) Analyse the network and determine the earliest start and latest finish times for each activity together with the network critical path. (8 marks) (ii) If all project activities in Figure Q4 require continuous craneage. The contractor owns one crane costing 1575/week and the cheapest crane hire would cost 1980/week. Determine the minimum cost of craneage to the contractor. (8 marks) Total 20 marks Figure Q4 Page 4 of 7

5 Question Five A graduate engineer prepared a plan for construction activities to bid for a building project. The plan included ten activities that need to be performed to carry out the project. To convince his manager that the project could be finished in 36 weeks, the engineer used the PERT three-estimate approach, to estimate accurate duration for each activity as laid in Table Q5. Estimated Times (Weeks) Activity O M P Precedence (Optimistic) (Most Likely) (Pessimistic) A B A C A D A E B F C G D H E I F & G J H & I Table Q5 The manager had a look at the numbers above and made his own calculation, then told the engineer that there is a 99:1 chance of completing the project in the duration that he has in his mind. (a) Construct the network diagram for this project and determine the mean critical path. (b) What is the chance that the engineer would complete the project by 36 weeks? 5 marks (c) What was the project duration the manager had in his mind when he talked to the engineer? 5 marks Total 20 Marks END OF QUESTIONS Page 5 of 7

6 PERT Equations Useful Formulae t e = a + 4m + b 6 ; 2 b a v e = ( 6 ) n T = t e i i=1 d T Z = S ; n S = v e i ; P(d T) = 1 P(T > d) i where, te ve a m = expected mean duration of activity = variance of activity duration = optimistic estimate for activity duration = most likely estimate for activity duration b = pessimistic estimate for activity duration, (a < m < b) = project mean duration T S d n P(d T) Z = standard deviation of project duration = project required deadline duration = number of activities along the critical path = probability of project required duration less than or equal project expected duration = standard normal random variable Page 6 of 7

7 Page 7 of 7

Project Management Techniques (PMT)

Project Management Techniques (PMT) Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2015/2016 PROJECT MANAGEMENT

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2015/2016 PROJECT MANAGEMENT TW74 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2015/2016 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: Monday 11 th January 2016 Time: 14:00

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

Final: Total 200 points (3-hour exam)

Final: Total 200 points (3-hour exam) Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

CHAPTER 5 STOCHASTIC SCHEDULING

CHAPTER 5 STOCHASTIC SCHEDULING CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration

More information

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION 1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

PROJECT MANAGEMENT CPM & PERT TECHNIQUES PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a

More information

ETSF01: Software Engineering Process Economy and Quality

ETSF01: Software Engineering Process Economy and Quality ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower

More information

PROJECT MANAGEMENT: PERT AMAT 167

PROJECT MANAGEMENT: PERT AMAT 167 PROJECT MANAGEMENT: PERT AMAT 167 PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

Diploma in Financial Management with Public Finance

Diploma in Financial Management with Public Finance Diploma in Financial Management with Public Finance Cohort: DFM/09/FT Jan Intake Examinations for 2009 Semester II MODULE: STATISTICS FOR FINANCE MODULE CODE: QUAN 1103 Duration: 2 Hours Reading time:

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No. E 32R04 SA M PL DETERMI NI NGACTI VI TY DURATI ONS AACE International Recommended Practice No. 32R-04 DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development Rev. Note: As AACE

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

Teori Pengambilan Keputusan. Week 12 Project Management

Teori Pengambilan Keputusan. Week 12 Project Management Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM

More information

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

Lecture 3 Project Scheduling

Lecture 3 Project Scheduling B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?

More information

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM /7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business

More information

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project. INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E

More information

WHY ARE PROJECTS ALWAYS LATE?

WHY ARE PROJECTS ALWAYS LATE? WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,

More information

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001 Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique

More information

Project Management with Brief Information regarding CPM and PERT Methods

Project Management with Brief Information regarding CPM and PERT Methods 99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

06IP/IM74 OPERATIONS RESEARCH

06IP/IM74 OPERATIONS RESEARCH 06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this

More information

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

Plan Implementation. Pushpa Lal Shakya

Plan Implementation. Pushpa Lal Shakya Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta Contemporary Engineering Sciences, Vol. 10, 2017, no. 7, 317-333 HIKARI Ltd, www.m-hikari.com https://doi.org/10.12988/ces.2017.712 Optimization of Rescheduling and Economy Analysis of the Implementation

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices

More information

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT Programme BA (Hons) Fashion and Textiles (Top-Up) BA (Hons) Graphic Design with Animation (Top-Up) BA (Hons) Interior Design Cohort FDI- BFT(TP)/14B/PT FDI- BGDA(TP)/14B/PT FDI-BAID/13B/FT Examinations

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

Programme Evaluation and Review Technique

Programme Evaluation and Review Technique 15 Programme Evaluation and Review Technique LEARNING OBJECTIVES : After studying this chapter, you will be able to : l l l l l l l l l Explain generic term network analysis and such related terms as Critical

More information

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H XRIS. What do you mean by network analysis? xplain with counter examples.. What are the basic differences between PM and PRT analysis of project work?. State the rule of constructing the network diagram..

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center

More information

Haeryip Sihombing 1. Risk. Risk Management

Haeryip Sihombing 1. Risk. Risk Management Project Management Managing Risk 7 Haeryip Sihombing Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 1 2 Risk Management Process The Risk Event Graph Risk Uncertain or chance events that planning

More information

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

Project Planning. Planning is an important step in project execution. Planning means:

Project Planning. Planning is an important step in project execution. Planning means: Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

UNIVERSITY OF BOLTON ENGINEERING, SPORTS AND SCIENCES. BSc(HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2014/2015 SEMESTER ONE

UNIVERSITY OF BOLTON ENGINEERING, SPORTS AND SCIENCES. BSc(HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2014/2015 SEMESTER ONE For Faculty Use UNIVERSITY OF BOLTON ENGINEERING, SPORTS AND SCIENCES BSc(HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2014/2015 SEMESTER ONE PROJECT AND ENVIRONMENTAL MANAGEMENT MODULE NO: BLT3026

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7 Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Managing Risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by

More information

NETWORK ANALYSIS QUESTION BANK

NETWORK ANALYSIS QUESTION BANK NETWORK ANALYSIS QUESTION BANK 1. Explain the terms : Total elapsed time, idle time. 2. What do you mean by dummy activity and successor activity. 3. Write four advantages of network analysis. 4. Explain

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities

More information

u w 1.5 < 0 These two results imply that the utility function is concave.

u w 1.5 < 0 These two results imply that the utility function is concave. A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that

More information

Comparison between Deterministic and Stochastic Time Estimating Techniques

Comparison between Deterministic and Stochastic Time Estimating Techniques Comparison between Deterministic and Stochastic Time Estimating Techniques Daketima G. Briggs, Ph.D, PMP Management Department, Faculty of Business, University of Botswana ABSTRACT: This paper started

More information

COPYRIGHTED MATERIAL. Index

COPYRIGHTED MATERIAL. Index Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria

More information

How to Satisfy GAO Schedule Best Practices

How to Satisfy GAO Schedule Best Practices By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

UNIVERSITY OF SWAZILAND FACULTY OF COMMERCE DEPARTMENT OF BUSINESS ADMINISTRATION FINAL EXAMINATION PAPER MAY 2016 ROJECT MANAGEMENT THREE [3] HOURS

UNIVERSITY OF SWAZILAND FACULTY OF COMMERCE DEPARTMENT OF BUSINESS ADMINISTRATION FINAL EXAMINATION PAPER MAY 2016 ROJECT MANAGEMENT THREE [3] HOURS UNIVERSITY OF SWAZILAND FACULTY OF COMMERCE DEPARTMENT OF BUSINESS ADMINISTRATION FINAL EXAMINATION PAPER MAY 2016 TITLE OF PAPER ROJECT MANAGEMENT COURSE CODE BA303 FULL TIME STUDENTS TIME ALLOCATED TOTAL

More information

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015 Logistics Lecture notes Maria Grazia Scutellà Dipartimento di Informatica Università di Pisa September 2015 These notes are related to the course of Logistics held by the author at the University of Pisa.

More information

Gurukripa s Guideline Answers to Nov 2011 Final Exam Questions Advanced Management Accounting

Gurukripa s Guideline Answers to Nov 2011 Final Exam Questions Advanced Management Accounting Gurukripa s Guideline Answers to Nov 2011 Final Exam Questions Advanced Management Accounting Question No.1 is compulsory (4 X 5 = 20 Marks). Answer any five questions from the remaining six questions

More information

56:171 Operations Research Midterm Exam Solutions October 22, 1993

56:171 Operations Research Midterm Exam Solutions October 22, 1993 56:171 O.R. Midterm Exam Solutions page 1 56:171 Operations Research Midterm Exam Solutions October 22, 1993 (A.) /: Indicate by "+" ="true" or "o" ="false" : 1. A "dummy" activity in CPM has duration

More information

Program Evaluation and Review Technique (PERT) in Construction Risk Analysis Mei Liu

Program Evaluation and Review Technique (PERT) in Construction Risk Analysis Mei Liu Applied Mechanics and Materials Online: 2013-08-08 ISSN: 1662-7482, Vols. 357-360, pp 2334-2337 doi:10.4028/www.scientific.net/amm.357-360.2334 2013 Trans Tech Publications, Switzerland Program Evaluation

More information

Line Of Balance. Dr. Ahmed Elyamany

Line Of Balance. Dr. Ahmed Elyamany Line Of Balance Dr. Ahmed Elyamany Intended Learning Outcomes Define the principles ofline of Balance (LOB) Demonstrate the application of LOB Understand the importanceof LOB Understand the process ofapplying

More information

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING Planning of Works Contract Form of contract by which one party undertakes to the other to perform certain work, for a price. Corresponds to the execution of a

More information

If you have a question during any portion of this exam, raise your hand and speak to the proctor. Write legibly.

If you have a question during any portion of this exam, raise your hand and speak to the proctor. Write legibly. CE167: Engineering Project Management Spring 2007 Professor William Ibbs MIDTERM 2 SOLUTION Date: April 26, 2007 General Instructions All work is to be completed in a bluebook answers not recorded in a

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2 UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle

More information

DUE DATE : 3pm Tuesday 16 March MATERIAL REQUIRED : ANSWER SHEET Refer to page 7

DUE DATE : 3pm Tuesday 16 March MATERIAL REQUIRED : ANSWER SHEET Refer to page 7 Page 1 of 7 ASSIGNMENT 1 st SEMESTER : FINANCIAL MANAGEMENT (FM) STUDY UNITS COVERED : MODULES 1-10 DUE DATE : 3pm Tuesday 16 March 2010 TOTAL MARKS : 100 MATERIAL REQUIRED : ANSWER SHEET Refer to page

More information

NPV Method. Payback Period

NPV Method. Payback Period 1. Why the payback method is often considered inferior to discounted cash flow in capital investment appraisal? A. It does not take account of the time value of money B. It does not calculate how long

More information

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:

More information

Systems Engineering. Engineering 101 By Virgilio Gonzalez

Systems Engineering. Engineering 101 By Virgilio Gonzalez Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

BSc (Hons) Software Engineering BSc (Hons) Computer Science with Network Security

BSc (Hons) Software Engineering BSc (Hons) Computer Science with Network Security BSc (Hons) Software Engineering BSc (Hons) Computer Science with Network Security Cohorts BCNS/ 06 / Full Time & BSE/ 06 / Full Time Resit Examinations for 2008-2009 / Semester 1 Examinations for 2008-2009

More information

Project Management. A Practitioner s Guide. Steven M. Bragg

Project Management. A Practitioner s Guide. Steven M. Bragg Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project

More information

MANAGEMENT ACCOUNTING TECHNIQUES AS AID IN DECISION-MAKING ACN306Y

MANAGEMENT ACCOUNTING TECHNIQUES AS AID IN DECISION-MAKING ACN306Y MANAGEMENT ACCOUNTING TECHNIQUES AS AID IN DECISION-MAKING ACN306Y 1 PROGRAMME: GROUP DISCUSSION 2010 14:30-15:30 COST VOLUME PROFIT, REGRESSION, LEARNING CURVES, OPTIMISATION (CHAPTERS 5, 6, 7, 8) 15:30-15:45

More information

MINI GUIDE. Project risk analysis and management

MINI GUIDE. Project risk analysis and management MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques

More information

2. Briefly discuss the factors that contribute to the improvement of the contractor s cash flow?

2. Briefly discuss the factors that contribute to the improvement of the contractor s cash flow? Part 1: Short Answers 1. Discuss the effect of the following contract types on the owner s risk? Unit price Lump sum Cost plus sliding fees Cost plus percentage of cost 2. Briefly discuss the factors that

More information

SCM 301 (Solo) Exam 1 Practice Exam Solutions

SCM 301 (Solo) Exam 1 Practice Exam Solutions 1. D $118,000 www.liontutors.com SCM 301 (Solo) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network

More information

SCM 301 (Lutz) Exam 1 Practice Exam Solutions

SCM 301 (Lutz) Exam 1 Practice Exam Solutions 1. D $118,000 www.liontutors.com SCM 301 (Lutz) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

Bsc (Hons) Tourism and Hospitality Management. Cohort: BTHM/16A/FT. Examinations for 2016/2017 Semester I. & 2016 Semester II

Bsc (Hons) Tourism and Hospitality Management. Cohort: BTHM/16A/FT. Examinations for 2016/2017 Semester I. & 2016 Semester II Bsc (Hons) Tourism and Hospitality Management Cohort: BTHM/16A/FT Examinations for 2016/2017 Semester I & 2016 Semester II MODULE: COST AND MANAGEMENT ACCOUNTING MODULE CODE: ACCF 1104A Duration: 2 Hours

More information