1 of 14 4/27/2009 7:45 AM

Size: px
Start display at page:

Download "1 of 14 4/27/2009 7:45 AM"

Transcription

1 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake are large and complex. A builder putting up an office building, for example, must complete thousands of activities costing millions of dollars. NASA must inspect countless components before it launches a rocket. Avondale shipyards in New Orleans requires tens of thousands of steps in constructing an ocean-going tugboat. Almost every industries worries about how to manage similar large-scale, complicated projects effectively. It is a difficult problem, and the stakes are high. Millions of dollars in coast overruns have been wasted due to poor planning of projects. Unnecessary delays have occurred due to poor scheduling. How can such problems be solved? The first step in planning and scheduling a project is to develop the work breakdown structure. This involves identifying the activities that must be performed in the project. There may be varying levels of detail, and each activity may be broken in to its most basic components. The time, cost, resource requirements, predecessors and person(s) responsible are identified for each activity. When this has been done, a schedule for the project can be developed. The program evaluation and review technique (PERT) and the critical path method (CPM) are two popular quantitative analysis techniques that help managers plan, schedule, monitor, and control large and complex projects. They were developed because there was a critical need for a better way to manage. FRAMEWORK OF PERT AND CPM There are six steps common to both PERT and CPM. The procedure follows: Six Steps of PERT and CPM 1. Define the project and all of its significant activities or tasks. 2. Develop the relationships among the activities. Decide which activities must precede others Draw the network connecting all of the activities. Assign time and /or cost estimates to each activity. 5. Compute the longest time path through the network; this is called the critical path. 6. Use the network to help plan, schedule, monitor, and control the project. Finding the critical path is a major part of controlling a project. The activities on the critical path represent tasks that will delay the entire project if they are delayed. Managers drive flexibility by identifying non critical activities and replanning, rescheduling, and reallocating resources such as personnel and finances. Although PERT and CPM are similar in their basic approach, they do differ in the way activity times are estimated. For every PERT activity, three times estimates are combined to determine the expected activity completion time and its variance. Thus, PERT is a probabilistic technique; it allows us to find the probability that the entire project will be completed by any given date. On the other hand, CPM is called a deterministic approach. It uses to times estimates,

2 2 of 14 4/27/2009 7:45 AM PERT other hand, CPM is called a deterministic approach. It uses to times estimates, the normal time and the crash time, for each activity. The normal completion time is the time we estimate it will take under normal conditions to complete the activity. The crash completion time is the shortest time it would take to finish an activity if additional funds and resources were allocated to the task. In this chapter we investigate not only PERT and CPM, but also the technique called PERT/cost that combines the benefits of both PERT and CPM. Almost any large project can be sub divided into a series of smaller activities or tasks that can be analyzed with PERT. When you recognize that projects can have thousands of specific activities, you see why it is important to be able to answer such questions as the following: 1. When will the entire project be completed? 2. What are the critical activities or tasks in the project, that is, the ones that will delay the entire project if they are late? 3. Which are the noncritical activities, that is, the ones that can run late without delaying the entire project s completion? 4. What is the probability that the project will be completed by a specific date? 5. At any particular date, is the project on schedule, behind schedule, or ahead of schedule? 6. On any given date, is the money spent equal to, less than, or greater than the budgeted amount? 7. Are there enough resources available to finish the project on time? 8. If the project is to be finished in a shorter amount of time, what is the best way to accomplish this at the least cost? PERT (or PERT/Cost) can help answer each of these questions. The first step is to define the project and all project activities. When the project begins, the building of the internal components for the device (activity A) and the modifications that are necessary for the floor and roof (activity B) can be started. The construction of the collection stack (activity C) can begin once the internal components are completed, and pouring of the new concrete floor and installation of the frame (activity D) can be completed as soon as the roof and floor have been modified. After the collection stack has been constructed, the high-temperature burner can be built (activity E), and the installation of the pollution control system (activity F) can begin. The air pollution device can be installed (activity G) after the high-temperature burner has been built, the concrete floor has been poured, and the frame has been installed. Finally, after the control system and pollution device have been installed, the system can be inspected and tested (activity H). All of these activities seem rather confusing and complex until they are placed in a network. First, all of the activities must be listed. This information is shown in Table 7.1. We see in the table that before the collection stack can be constructed (activity C), the internal components must be built (activity A). Thus, activity A is the immediate predecessor of activity C. Similarly, both

3 3 of 14 4/27/2009 7:45 AM activities D and E must be performed just prior to installation of the air pollution device (activity G). Table 7.1 Activities and Immediate Predecessors for General Foundry, Inc. Activity Times The next step in the PERT procedure is to assign estimates of the time required to complete each activity. Time is usually given in units of weeks. For one-of-a-kind projects or for new jobs, providing activity time estimates is not always an easy task. Without solid historical data, managers are often uncertain as to activity times. For this reason, the developers of PERT employed a probability distribution based on three time estimates for each activity: Optimistic time (a) = time an activity will take if everything goes as well as possible. There should be only a small probability (say, 1/100) of this occurring. Pessimistic time (b) = time an activity would take assuming very unfavorable conditions. There should also be only a small probability that the activity will really take this long. Most likely time (m) = most realistic time estimate to complete the activity. PERT often assumes that time estimates follow the beta probability distribution (see Figure 7.1). This continuous distribution has been found to be appropriate, in many cases, for determining an expected value and variance for activity completion times. To find the expected activity time (t), the beta distribution weights the estimates as follows: t = To compute the dispersion or variance of activity completion time, we use this formula1: Variance =

4 4 of 14 4/27/2009 7:45 AM Figure 7.1 Beta Probability Distribution with Three Time Estimates This formula is based on the statistical concept that from one end of the beta distribution to the other is 6 standard deviations (±3 standard deviations from the mean). Because (b-a) is 6 standard deviations, one standard deviation is (b a)/6. Thus the variance is [(b a)/6] 2. Table 7.2 Time Estimates (Weeks) for General Foundry, Inc Table 7.2 shows General Foundry s optimistic, most likely, and pessimistic time estimates for each activity. It also reveals the expected time (t) and variance for each of the activities, as computed with Equations 7.1 and 7.2. HOW TO FIND THE CRITICAL PATH Once the expected completion time for each activity has been determined, we accept it as the actual time of that task. Although Table 7.2 indicates that the total expected time for all eight of

5 5 of 14 4/27/2009 7:45 AM Although Table 7.2 indicates that the total expected time for all eight of General Foundry s activities is 25 weeks, it is obvious in Figure 13.3 that several of the tasks can be taking place simultaneously. To find out just how long the project will take, we perform the critical path analysis for the network. The critical path is the longest time path route through the network. If Lester Harky wants to reduce the total project time for General Foundry, he will have to reduce the length of some activity on the critical path. Conversely, and delay of an activity on the critical path will delay completion of the entire project. Figure 7.2 General Foundry s Network with Excepted Activity Times To find the critical path, we need to determine the following quantities for each activity in the network: 1. Earliest start time (ES): the earliest time an activity can begin without violation of immediate predecessor requirements. 2. Earliest finish time (EF): the earliest time at which an activity can end. 3. Latest start time (LS): the latest time an activity can begin without delaying the entire project. 4. Latest finish time (LF): the latest time an activity can end without delaying the entire project. In the network, we represent these times as well as the activity times (t) in the nodes, as seen here: We first show how to determine the earliest times. When we find these, the latest times can be computed. Earliest Times There are two basic rules to follow when computing ES and EF times. The first rule is for the earliest finish time, which is computed as follows: activity time Earliest finish time = earliest start time + expected

6 6 of 14 4/27/2009 7:45 AM EF = ES + t Also, before any activity can be started, all of its predecessor activities must be completed. In other words, we search for the largest EF for all of the immediate predecessors in determining ES. The second rule is for the earliest start time, which is computed as follows: Earliest start = largest of the earliest finish times of immediate predecessors ES = largest EF of immediate predecessors. The start of the whole project will be set at time zero. Therefore, any activity that has no predecessors will have an earliest start time of zero. So ES = 0 for both A and B in the General Foundry problem, as seen here: The rest of the earliest times for General Foundry are shown in Figure 7.4. These are found using a forward pass through the network. At each step, EF = ES + t, and ES is the largest EF of the predecessors. Notice that activity G has an earliest start time of 8, since both D (with EF = 7) and E (with EF = 8) are immediate predecessors. Activity G cannot start until both predecessors are finished, and so we choose the larger of the earliest finish times for these. Thus, G has ES = 8. The finish time for the project will be 15 weeks, which is the EF for activity H. Figure 7.3 General Foundry s Earliest Start (ES) and Earliest Finish (EF) Times Latest Times The next step in finding the critical path is to compute the latest start time (LS) and the latest finish time (LF) for each activity. We do this by making a

7 7 of 14 4/27/2009 7:45 AM backward pass through the network, that is, starting at the finish and working backward. There are two basic rules to follow when computing the latest times. The first rule involves the latest start time, which is computed as Latest start time = latest finish time activity time LS = LF t Also, since all immediate predecessors must be finished before an activity can begin, the latest start time for an activity determines the latest finish time for its immediate predecessors. If an activity is the immediate predecessor for two or more activities, it must be finished so that all following activities can begin by their latest start times. Thus, the second rule involves the latest finish time, which is computed as Latest finish time = smallest of latest start times for following activities, or LF = smallest LS of following activities To compute the latest times, we start at the finish and work backwards. Since the finish time for the General Foundry project is 15, activity H has LF = 15. The latest start for activity H is LS = LF t = 15 2 = 13 weeks Continuing to work backward, this latest start time of 13 becomes the latest finish time for immediate predecessors F and G. All of the latest times are shown in Figure Notice that for activity C, which is the immediate predecessor for two activities (E and F), the latest finish time is the smaller of the latest start times (4 and 10) for activities E and F. Concept of Slack in Critical Path Computations When ES, LS, EF, and LF have been determined, it is a simple matter to find the amount of slack time, or free time, that each activity has. Slack is the length of time an activity can be delayed without delaying the whole project. Mathematically, Slack = LS ES or slack = LF EF Figure 7.4 General Foundry s Latest Start (LS) and Latest Finish (LF) Times

8 8 of 14 4/27/2009 7:45 AM Table 7.3 summarizes the ES, EF, LS, LF, and slack times for all of General Foundry s activities. Activity B, for example, has 1 week of slack time since LS ES = 1 0 = 1 (or, similarly, LF EF = 4 3 = 1). This means that it can be delayed up to 1 week without causing the project to run any longer than expected. Table 7.3 General Foundry s Schedule and Slack Times On the other hand, activities A, C, E, G, and H have no slack time; this means that none of them can be delayed without delaying the entire project. Because of this, they are called critical activities and are said to be on the critical path. Lester Harky s critical path is shown in network form in Figure 7.5. The total project completion time, 15 weeks, is seen as the largest number in the EF or LF columns of Table 7.3. Industrial managers call this a boundary timetable. Figure 7.5 General Foundry s Critical Path (A-C-E-G-H) PROBABILITY OF PROJECT COMPLETION The critical path analysis helped us determine that the foundry s expected project completion time is 15 weeks. Harky knows, however, that if the project is not completed in 16 weeks, General Foundry will be forced to close by

9 9 of 14 4/27/2009 7:45 AM is not completed in 16 weeks, General Foundry will be forced to close by environmental controllers. He is also aware that there is significant variation in the time estimates for several activities. Variation in activities that are on the critical path can affect overall project completion possibly delaying it. This is one occurrence that worries Harky considerably. PERT uses the variance of critical path activities to help determine the variance of the overall project. If the activity times are statistically independent, the project variance is computed by summing the variances of the critical activities. Project variance = variances of activities on the critical path From Table 7.2 we know that Hence, the project variance is Project variance = 4/36 + 4/ / /36 + 4/36 = 112/36 = Figure 7.6 Probability Distribution for Project Completion Times We know that the standard deviation is just the square root of the variance, so Project standard deviation = = = 1.76 weeks How can this information be used to help answer questions regarding the probability of finishing the project on time? In addition to assuming that the activity times are independent, we also assume that total project completion time follows a normal probability distribution. With these assumptions, the bell-shaped curve shown in Figure 7.7 can be used to represent project

10 10 of 14 4/27/2009 7:45 AM bell-shaped curve shown in Figure 7.7 can be used to represent project completion dates. It also means that there is a 50% chance that the entire project will be completed in less than the expected 15 weeks and a 50% chance that it will exceed 15 weeks.2 For Harky to find the probability that his project will be finished on or before the 16-week deadline, he needs to determine the appropriate area under the normal curve. The standard normal equation can be applied as follows: Z = Where = = 0.57 Z is the number of standard deviations the due date or target date lies from the mean or expected date. Referring to the normal table in Appendix A, we find a probability of Thus, there is a 71.6% chance that the pollution control equipment can be put in place in 16 weeks or less. This is shown in Figure You should be aware that non-critical activities also have variability (as seen in Table 7.2). In fact, a different critical path can evolve because of the probabilistic situation. Figure 7.7 Probability of general Foundry s Meeting the 16-Week Deadlines WHAT PERT WAS ABLE TO PROVIDE PERT has thus far been able to provide Lester Harky with several valuable pieces of management information: 1. The project s expected completion data is 15 weeks. 2. There is a 71.6% chance that the equipment will be in place within the 16-week deadline. PERT can easily find the probability of finishing by any date Harky is interested in. 3. Five activities (A, C, E, G, H) are on the critical path. If any one of them is delayed for any reason, the entire project will be delayed. 4. Three activities (B, D, F) are not critical but have some slack time built in. This means that Harky can borrow from their resources, if needed, possibly to speed up the entire project.

11 11 of 14 4/27/2009 7:45 AM 5. A detailed schedule of activity starting and ending dates has been made available (see Table 7.3). SHORTEST-ROUTE TECHNIQUE The shortest-route technique finds how a person or item can travel from one location to another while minimizing the total distance traveled. In other words, it finds the shortest route to a series of destinations. Every day, Ray Design, Inc., must transport beds, chairs, and other furniture items from the factory to the warehouse. This involves going through several cities. Ray would like to find the route with the shortest distance. The road network is shown in figure 7.8 Figure 7.8 Roads from Ray s Plant to Warehouse STEPS OF THE SHORTEST-ROUTE TECHNIQUE Find the nearest node to the origin (plant). Put the distance in a box by the node. Find the next-nearest node to the origin (plant), and put the distance in a box by the node. In some cases, several paths will have to be checked to find the nearest node. Repeat this process until you have gone through the entire network. The last distance at the ending node will be the distance of the shortest route. You should note that the distance placed in the box by the each node is the shortest route to this node. These distances are used as intermediate results in finding the next-nearest node. Looking Figure 7.8, we can see that the nearest node to the plant is node 2, with a distance of 100 miles. Thus we will connect these two nodes. This first iteration is shown in Figure 7.9 Figure 7.9 Roads from Ray s Plant to Warehouse

12 12 of 14 4/27/2009 7:45 AM Now we look for the next-nearest node to the origin. We check nodes 3, 4 and 5. Node 3 is the nearest, but there are two possible paths. Path is nearest to the origin, with a total distance of 150 miles (See Figure 7.10) Figure 7.10 Roads from Ray s Plant to Warehouse

13 13 of 14 4/27/2009 7:45 AM We repeat the process. The next-nearest node is either node 4 or node 5. Node 4 is 200 miles from node 2, and node 2 is 100 miles from node 1. Thus, node 4 is 300 miles from the origin. There are two paths for node 5, 2-5 and 3-5, to the origin. Note that we don t have to go all the way back to the origin because we already know the shortest route from node 2 and node 3 to the origin. The minimum distances are placed in boxes by these nodes. Path 2-5 is 100 miles, and node 2 is 100 miles from the origin. Thus the total distance is 200 miles. In a similar fashion, we can determine that the path from node 5 to the origin through node 3 is 190 (40 miles between node 5 and 3 plus 150 miles from node 3 to the origin). Thus, we pick node 5 going through node 3 to the origin (See Figure 7.11). Figure 7.11 Roads from Ray s Plant to Warehouse The next-nearest node will be either node 4 or node 6, as the last remaining nodes. Node 4 is 300 miles from the origin (300=200 from node 4 to node 2 plus100 from node 2 to the origin). Node 6 is 290 miles from the origin (290= ). Node 6 has the minimum distance, and because it is the ending node, we are done (refer to Figure 7.12). The shortest route is path , with a minimum distance of 290 miles. Figure 7.12 Roads from Ray s Plant to Warehouse

14 14 of 14 4/27/2009 7:45 AM

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

Teori Pengambilan Keputusan. Week 12 Project Management

Teori Pengambilan Keputusan. Week 12 Project Management Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

IE 102 Spring Project Management

IE 102 Spring Project Management IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and

More information

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM /7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business

More information

CHAPTER 5 STOCHASTIC SCHEDULING

CHAPTER 5 STOCHASTIC SCHEDULING CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

PROJECT MANAGEMENT CPM & PERT TECHNIQUES PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a

More information

Project Management Techniques (PMT)

Project Management Techniques (PMT) Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.

More information

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001 Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

CHAPTER 5. Project Scheduling Models

CHAPTER 5. Project Scheduling Models CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION 1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

Deterministic Dynamic Programming

Deterministic Dynamic Programming Deterministic Dynamic Programming Dynamic programming is a technique that can be used to solve many optimization problems. In most applications, dynamic programming obtains solutions by working backward

More information

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL Abstract: Crashing is a process of expediting project schedule

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

06IP/IM74 OPERATIONS RESEARCH

06IP/IM74 OPERATIONS RESEARCH 06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this

More information

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN: International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, 2017 http://ijaemr.com/ ISSN: 2456-3676 CPM AND PERT COMPARISON ANALYSIS IN PROJECT PLANNING ABSTRACT Talatu Muhammad

More information

WHY ARE PROJECTS ALWAYS LATE?

WHY ARE PROJECTS ALWAYS LATE? WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,

More information

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT E. Newby, F. D. Fomeni, M. M. Ali and C. Musingwini Abstract The standard methodology used for estimating the cost and

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

MS Project 2007 Page 1 of 18

MS Project 2007 Page 1 of 18 MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems

More information

56:171 Operations Research Midterm Examination Solutions PART ONE

56:171 Operations Research Midterm Examination Solutions PART ONE 56:171 Operations Research Midterm Examination Solutions Fall 1997 Answer both questions of Part One, and 4 (out of 5) problems from Part Two. Possible Part One: 1. True/False 15 2. Sensitivity analysis

More information

POLYTECHNIC OF NAMIBIA

POLYTECHNIC OF NAMIBIA POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:

More information

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2 UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle

More information

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No. E 32R04 SA M PL DETERMI NI NGACTI VI TY DURATI ONS AACE International Recommended Practice No. 32R-04 DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development Rev. Note: As AACE

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

Handout 4: Deterministic Systems and the Shortest Path Problem

Handout 4: Deterministic Systems and the Shortest Path Problem SEEM 3470: Dynamic Optimization and Applications 2013 14 Second Term Handout 4: Deterministic Systems and the Shortest Path Problem Instructor: Shiqian Ma January 27, 2014 Suggested Reading: Bertsekas

More information

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,

More information

Lecture 3 Project Scheduling

Lecture 3 Project Scheduling B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018

More information

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015 Logistics Lecture notes Maria Grazia Scutellà Dipartimento di Informatica Università di Pisa September 2015 These notes are related to the course of Logistics held by the author at the University of Pisa.

More information

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project. INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E

More information

PROJECT MANAGEMENT DIPLOMA COURSE

PROJECT MANAGEMENT DIPLOMA COURSE PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a

More information

Brown hamburger and assemble tacos (including cheese)

Brown hamburger and assemble tacos (including cheese) 19.1 An Introduction to PERT PERT is an acronym for the Program Evaluation Review Technique. The Special Projects Office in the Department of the Navy created this project management tool in 1958. It was

More information

Chapter 21. Dynamic Programming CONTENTS 21.1 A SHORTEST-ROUTE PROBLEM 21.2 DYNAMIC PROGRAMMING NOTATION

Chapter 21. Dynamic Programming CONTENTS 21.1 A SHORTEST-ROUTE PROBLEM 21.2 DYNAMIC PROGRAMMING NOTATION Chapter 21 Dynamic Programming CONTENTS 21.1 A SHORTEST-ROUTE PROBLEM 21.2 DYNAMIC PROGRAMMING NOTATION 21.3 THE KNAPSACK PROBLEM 21.4 A PRODUCTION AND INVENTORY CONTROL PROBLEM 23_ch21_ptg01_Web.indd

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Modelling cash flow in construction projects in countries in transition

Modelling cash flow in construction projects in countries in transition Modelling cash flow in construction projects in countries in transition Mladen Raduj kovic Faculty of Civil Engineering, University of Zagreb, Zagreb, Croatia Summary The paper describes the modelling

More information

DISCLAIMER. The Institute of Chartered Accountants of India

DISCLAIMER. The Institute of Chartered Accountants of India DISCLAIMER The Suggested Answers hosted in the website do not constitute the basis for evaluation of the students answers in the examination. The answers are prepared by the Faculty of the Board of Studies

More information

Outline. Project Management. Introduction. What is a Project?

Outline. Project Management. Introduction. What is a Project? Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction

More information

Plan Implementation. Pushpa Lal Shakya

Plan Implementation. Pushpa Lal Shakya Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application

More information

Project Management with Brief Information regarding CPM and PERT Methods

Project Management with Brief Information regarding CPM and PERT Methods 99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract

More information

u w 1.5 < 0 These two results imply that the utility function is concave.

u w 1.5 < 0 These two results imply that the utility function is concave. A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast

More information

NPV Method. Payback Period

NPV Method. Payback Period 1. Why the payback method is often considered inferior to discounted cash flow in capital investment appraisal? A. It does not take account of the time value of money B. It does not calculate how long

More information

Management Management

Management Management Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

Chapter 15: Dynamic Programming

Chapter 15: Dynamic Programming Chapter 15: Dynamic Programming Dynamic programming is a general approach to making a sequence of interrelated decisions in an optimum way. While we can describe the general characteristics, the details

More information

Comparison between Deterministic and Stochastic Time Estimating Techniques

Comparison between Deterministic and Stochastic Time Estimating Techniques Comparison between Deterministic and Stochastic Time Estimating Techniques Daketima G. Briggs, Ph.D, PMP Management Department, Faculty of Business, University of Botswana ABSTRACT: This paper started

More information

Crashing the Schedule An Algorithmic Approach with Caveats and Comments

Crashing the Schedule An Algorithmic Approach with Caveats and Comments ing the Schedule An Algorithmic Approach with Caveats and Comments Gilbert C. Brunnhoeffer, III PhD, P.E. and B. Gokhan Celik PhD LEED AP Roger Williams University Bristol, Rhode Island and Providence

More information

Programme Evaluation and Review Technique

Programme Evaluation and Review Technique 15 Programme Evaluation and Review Technique LEARNING OBJECTIVES : After studying this chapter, you will be able to : l l l l l l l l l Explain generic term network analysis and such related terms as Critical

More information

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta Contemporary Engineering Sciences, Vol. 10, 2017, no. 7, 317-333 HIKARI Ltd, www.m-hikari.com https://doi.org/10.12988/ces.2017.712 Optimization of Rescheduling and Economy Analysis of the Implementation

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

ETSF01: Software Engineering Process Economy and Quality

ETSF01: Software Engineering Process Economy and Quality ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower

More information

Line Balancing S K Mondal Chapter 3

Line Balancing S K Mondal Chapter 3 Line Balancing S K Mondal Chapter 3 Solution: J G 10 K I 7 L J, H 10 M K 6 N L, M 9 [10-Marks] 6 8 7 10 A D G J 5 B 5 6 E H L 10 9 N Work station number 1 3 4 5 6 4 10 7 4 C F I K M 6 Precedence diagram

More information

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H XRIS. What do you mean by network analysis? xplain with counter examples.. What are the basic differences between PM and PRT analysis of project work?. State the rule of constructing the network diagram..

More information

56:171 Operations Research Midterm Examination Solutions PART ONE

56:171 Operations Research Midterm Examination Solutions PART ONE 56:171 Operations Research Midterm Examination Solutions Fall 1997 Write your name on the first page, and initial the other pages. Answer both questions of Part One, and 4 (out of 5) problems from Part

More information

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 01, January 2019, pp. 825-832, Article ID: IJCIET_10_01_075 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=10&itype=01

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017

More information

56:171 Operations Research Midterm Exam Solutions October 22, 1993

56:171 Operations Research Midterm Exam Solutions October 22, 1993 56:171 O.R. Midterm Exam Solutions page 1 56:171 Operations Research Midterm Exam Solutions October 22, 1993 (A.) /: Indicate by "+" ="true" or "o" ="false" : 1. A "dummy" activity in CPM has duration

More information

M G T 2251 Management Science. Exam 3

M G T 2251 Management Science. Exam 3 M G T 2251 Management Science Exam 3 Professor Chang November 8, 2012 Your Name (Print): ID#: Read each question carefully before you answer. Work at a steady pace, and you should have ample time to finish.

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

Cost Reduction: Planning & Control. Impacting the Bottom Line

Cost Reduction: Planning & Control. Impacting the Bottom Line Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,

More information

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:

More information

Final: Total 200 points (3-hour exam)

Final: Total 200 points (3-hour exam) Final: Total 200 points (3-hour exam) [Engineering Economics] IRR Calculation [15 points] One alternative for improving a company s operations is to do nothing for the next 2 years and then spend $10,000

More information

The Critical Path Method

The Critical Path Method The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico "I believe that this nation should commit

More information

Essays on Some Combinatorial Optimization Problems with Interval Data

Essays on Some Combinatorial Optimization Problems with Interval Data Essays on Some Combinatorial Optimization Problems with Interval Data a thesis submitted to the department of industrial engineering and the institute of engineering and sciences of bilkent university

More information

VALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke

VALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke VALUE MANAGEMENT Snehal Salunke Post Graduate Student, Civil Engg. Department, SSJCET, Asangaon, Thane -----------------------------------------------------------------------------***------------------------------------------------------------------

More information

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques

More information

8.6 FORMULATION OF PROJECT REPORT. 160 // Management and Entrepreneurship

8.6 FORMULATION OF PROJECT REPORT. 160 // Management and Entrepreneurship 160 // Management and Entrepreneurship (9) Raw material: List of raw material required by quality and quantity, sources of procurement, cost of raw material, tie-up arrangements, if any for procurement

More information

Chapter 2 The PERT/CPM Technique

Chapter 2 The PERT/CPM Technique Chapter The PERT/CPM Technique Abstract Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects

More information