Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Size: px
Start display at page:

Download "Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall"

Transcription

1 Project Management Chapter

2 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of resources

3 What is Project Management? Project Management A systemized, phased approach to defining, organizing, planning, monitoring, and controlling projects

4 Defining and Organizing Projects Defining the Scope and Objectives Selecting the Project Manager and Team Recognizing Organizational Structure

5 Planning Projects Defining the Work Breakdown Structure Diagramming the network Developing the schedule Analyzing cost-time trade-offs Assessing risks

6 Work Breakdown Structure Work Breakdown Structure A statement of all the work that has to be completed. Activity The smallest unit of work effort consuming both time and resources that can be planned and controlled

7 Work Breakdown Structure Relocation of St. John s Hospital Level 0 Organizing and Site Preparation Physical Facilities and Infrastructure Level 1 Select administration staff Purchase and deliver equipment Site selection and survey Construct hospital Select medical equipment Develop information system Level 2 Prepare final construction plans Install medical equipment Bring utilities to site Train nurses and support staff Interview applicants for nursing and support staff Copyright 2013 Pearson Education, Inc. Publishing as

8 Diagramming the Network Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) Activity-on-Node approach 02-08

9 Establishing Precedence Relationships Precedence Relationships Determining the sequence for undertaking activities

10 Example

11 Example 2.1 Immediate Predecessor I A B C A D B E B F A G C H D I A J E,G,H K F,I,J Start A B F C D G H K J Finish E 02-11

12 Application 2.1 The following information is known about a project Activity Activity Time (days) Immediate Predecessor(s) A 7 B 2 A C 4 A D 4 B, C E 4 D F 3 E G 5 E Draw the network diagram for this project 02-12

13 Application 2.1 Activity Activity Time (days) Immediate Predecessor(s) A 7 B 2 A C 4 A D 4 B, C E 4 D F 3 E G 5 E B 2 F 3 Start A 7 D 4 E 4 Finish C 4 G

14 Developing the Schedule Path The sequence of activities between a project s start and finish. Critical Path The sequence of activities between a start and finish that takes the longest time to complete

15 Developing the Schedule Earliest start time (ES) - the latest earliest finish time of any immediately preceding activities Earliest finish time (EF) - the earliest start time plus its estimated duration EF = ES + t Latest finish time (LF) the earliest of the latest start times of any of the immediately following activities. Latest start time (LS) - the latest finish time minus its estimated duration LS = LF t Activity Slack - the maximum length of time an activity can be delayed without delaying the entire project LF-EF or LS-ES 02-15

16 Developing the Schedule Activity Earliest start time 0 A 12 Earliest finish time Latest start time Latest finish time Duration 02-16

17 Example 2.2 Paths are the sequence of activities between a project s start and finish. I A F K Path Time (wks) Start C G Finish A-I-K 33 A-F-K 28 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 B D E H J 02-17

18 Example 2.2 Earliest start time I Earliest finish time 0 A 12 F K Start C G Finish B D H J E

19 Example 2.2 I The Critical Path takes 69 weeks A F K Start C G Finish B D H J E

20 Example 2.2 Latest start time I Latest finish time A K 12 F Start C G Finish 0 B D H J E

21 Example 2.2 S = I S = 2 A S = 0 S = 41 F K S = 2 Start S = 2 12 C G Finish S = 0 0 B S = 0 S = 0 9 D H J S = 0 S = 26 9 E

22 Developing a Schedule Gantt chart 02-22

23 Application 2.2 Calculate the four times for each activity in order to determine the critical path and project duration for the diagram in Application Problem 1. Activity Duration Earliest Start (ES) Latest Start (LS) Earliest Finish (EF) Latest Finish (LF) Slack (LS- ES) On the Critical Path? A =0 Yes B 2 C 4 D 4 E 4 F 3 G 5 The critical path is A C D E G with a project duration of 24 days

24 Application 2.2 Calculate the four times for each activity in order to determine the critical path and project duration. Activity Duration Earliest Start (ES) Latest Start (LS) Earliest Finish (EF) Latest Finish (LF) Slack (LS- ES) On the Critical Path? A =0 Yes B 2 C 4 D 4 E 4 F 3 G =2 No =0 Yes =0 Yes =0 Yes =2 No =0 Yes 02-24

25 Application 2.2 The critical path is A C D E G with a project duration of 24 days. B 2 F 3 Start A 7 D 4 E 4 Finish C 4 G

26 Analyzing Cost-Time Trade-Offs Project Crashing Shortening (or expediting) some activities within a project to reduce overall project completion time. Project Costs Direct Costs Indirect Costs Penalty Costs 02-26

27 Analyzing Cost-Time Trade-Offs Project Costs Normal time (NT) is the time necessary to complete an activity under normal conditions. Normal cost (NC) is the activity cost associated with the normal time. Crash time (CT) is the shortest possible time to complete an activity. Crash cost (CC) is the activity cost associated with the crash time. Cost to crash per period = CC NC NT CT 02-27

28 Direct cost (dollars) Cost-Time Relationships Crash cost (CC) Linear cost assumption Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks Figure (Crash time) (Normal time) Time (weeks) Copyright 2013 Pearson Education, Inc. Publishing as. Normal cost (NC) 02-28

29 Analyzing Cost-Time Trade-Offs Determining the Minimum Cost Schedule: 1. Determine the project s critical path(s). 2. Find the activity or activities on the critical path(s) with the lowest cost of crashing per week. 3. Reduce the time for this activity until a. It cannot be further reduced or b. Until another path becomes critical, or c. The increase in direct costs exceeds the savings that result from shortening the project (which lowers indirect costs). 4. Repeat this procedure until the increase in direct costs is larger than the savings generated by shortening the project

30 Example 2.3 Activity DIRECT COST AND TIME DATA FOR THE ST. JOHN S HOSPITAL PROJECT Normal Time (NT) (weeks) Normal Cost (NC)($) Crash Time (CT)(weeks) Crash Cost (CC)($) Maximum Time Reduction (week) Cost of Crashing per Week ($) A 12 $12, $13, ,000 B 9 50, , ,000 C 10 4, , D 10 16, , ,000 E , , ,000 F 10 10, , ,500 G , , ,000 H 40 1,200, ,260, ,000 I 15 40, , ,500 J 4 10, , ,000 K 6 30, , ,000 Totals $1,992,000 $2,209,

31 Example 2.3 Determine the minimum-cost schedule for the St. John s Hospital project. Project completion time =69 weeks. Project cost = $2,624,000 Direct = $1,992,000 Indirect = 69($8,000) = $552,000 Penalty = (69 65)($20,000) = $80,000 A I K 33 weeks A F K A C G J K B D H J K B E J K 28 weeks 67 weeks 69 weeks 43 weeks 02-31

32 Example 2.3 STAGE 1 Step 1. The critical path is B D H J K. Step 2. The cheapest activity to crash per week is J at $1,000, which is much less than the savings in indirect and penalty costs of $28,000 per week. Step 3. Crash activity J by its limit of three weeks because the critical path remains unchanged. The new expected path times are A C G J K: 64 weeks B D H J K: 66 weeks The net savings are 3($28,000) 3($1,000) = $81,000. The total project costs are now $2,624,000 - $81,000 = $2,543,

33 Example 2.3 STAGE 1 I 15 A 12 F 10 K 6 Start C 10 G 35 Finish B 9 D 10 H 40 J 1 E

34 Example 2.3 STAGE 2 Step 1. The critical path is still B D H J K. Step 2. The cheapest activity to crash per week is now D at $2,000. Step 3. Crash D by two weeks. The first week of reduction in activity D saves $28,000 because it eliminates a week of penalty costs, as well as indirect costs. Crashing D by a second week saves only $8,000 in indirect costs because, after week 65, no more penalty costs are incurred. Updated path times are A C G J K: 64 weeks and B D H J K: 64 weeks The net savings are $28,000 + $8,000 2($2,000) = $32,000. Total project costs are now $2,543,000 $32,000 = $2,511,

35 Example 2.3 STAGE 2 I 15 A 12 F 10 K 6 Start C 10 G 35 Finish B 9 D 8 H 40 J 1 E

36 Example 2.3 STAGE 3 Step 1. The critical paths are B D H J K and A-C-G-J-K Step 2. Activities eligible to be crashed: (A, B); (A, H); (C, B); (C, H); (G, B); (G, H) or to crash Activity K We consider only those alternatives for which the costs of crashing are less than the potential savings of $8,000 per week. We choose activity K to crash 1 week at $4,000 per week. Step 3. Updated path times are: A C G J K: 63 weeks and B D H J K: 63 weeks Net savings are $8,000 - $4,000 = $4,000. Total project costs are $2,511,000 $4,000 = $2,507,

37 Example 2.3 STAGE 3 I 15 A 12 F 10 K 5 Start C 10 G 35 Finish B 9 D 8 H 40 J 1 E

38 Example 2.3 STAGE 4 Step 1. The critical paths are still B D H J K and A C G J K. Step 2. Activities eligible to be crashed: $7,600 per week. Step 3. Crash activities B and C by two weeks. Updated path times are A C G J K: 61 weeks and B D H J K: 61 weeks The net savings are 2($8,000) 2($7,600) = $800. Total project costs are now $2,507,000 $800 = $2,506,

39 Example 2.3 STAGE 4 I 15 A 12 F 10 K 5 Start C 8 G 35 Finish B 7 D 8 H 40 J 1 E

40 Example 2.3 Stage Crash Activity Time Reduction (weeks) Resulting Critical Path(s) Project Duration (weeks) Project Direct Costs, Last Trial ($000) Crash Cost Added ($000) Total Indirect Costs ($000) Total Penalty Costs ($000) Total Project Costs ($000) 0 B-D-H-J- K 1 J 3 B-D-H-J- K 2 D 2 B-D-H-J- K A-C-G-J- K 3 K 1 B-D-H-J- K A-C-G-J- K 4 B, C 2 B-D-H-J- K A-C-G-J- K 69 1, , , , , , , , , ,

41 Application 2.3 Indirect project costs = $250 per day Penalty cost = $100 per day past day 14. Activity Normal Time (days) Project Activity and Cost Data Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 5 1, ,200 B ,000 C A, B D 3 1, ,000 B E ,200 C, D F 2 1, ,400 E G E H G 02-41

42 Application C ES LS ID DUR EF LF 0 A 5 13 F Start 8 8 E Finish 0 B 5 5 D 8 13 G H

43 Application 2.3 Project Activity and Cost Data Activity Crash Cost/Day Maximum Crash Time (days) A B C D E F G 0 0 H Normal Total Costs = Total Indirect Costs = $7,500 $250 per day 21 days = $5,250 Penalty Cost = $100 per day 7 days = $700 Total Project Costs = $13,

44 Application 2.3 Step 1: The critical path is B D E G H, and the project duration is 21 days. Step 2: Activity E on the critical path has the lowest cost of crashing ($150 per day). Note that activity G cannot be crashed. Step 3: Reduce the time (crashing 2 days will reduce the project duration to 19 days) and re-calculate costs: Normal Costs Last Trial = Crash Cost Added = Total Indirect Costs = Penalty Cost = Total Project Cost = $7,500 $150 2 days = $300 $250 per day 19 days = $4,750 $100 per day 5 days = $500 $13,

45 Application 2.3 Step 4: Repeat until direct costs greater than savings (step 2) Activity H on the critical path has the next lowest cost of crashing ($200 per day). (step 3) Reduce the time (crashing 2 days will reduce the project duration to 17 days) and re-calculate costs: Costs Last Trial = $7,500 + $300 (the added crash costs) = $7,800 Crash Cost Added = $200 2 days = $400 Total Indirect Costs = $250 per day 17 days = $4,250 Penalty Cost = $100 per day 3 days = $300 Total Project Cost = $12,

46 Application 2.3 (step 4) Repeat (step 2) Activity D on the critical path has the next lowest crashing cost ($500 per day). (step 3) Reduce the time (crashing 1 day will reduce the project duration to 16 days) and re-calculate costs: Costs Last Trial = $7,800 + $400 (the added crash costs) = $8,200 Crash Cost Added = $500 1 day = $500 Total Indirect Costs = $250 per day 16 days = $4,000 Penalty Cost = $100 per day 2 days = $200 Total Project Cost = $12,900 which is greater than the last trial. Hence we stop the crashing process

47 Application 2.3 The recommended completion date is day 17. Trial Crash Activity Resulting Critical Paths Reduction (days) Project Duration (days) Costs Last Trial Crash Cost Added Total Indirect Costs Total Penalty Costs Total Project Costs 0 B-D-E-G-H 21 $7,500 $5,250 $700 $13,450 1 E B-D-E-G-H 2 19 $7,500 $300 $4,750 $500 $13,050 2 H B-D-E-G-H 2 17 $7,800 $400 $4,250 $300 $12,750 Further reductions will cost more than the savings in indirect costs and penalties. The critical path is B D E G H and the duration is 17 days

48 Assessing Risks Risk-management Plans Strategic Fit Service/Product Attributes Project Team Capability Operations 02-48

49 Assessing Risks Statistical Analysis Optimistic time (a) Most likely time (m) Pessimistic time (b) 02-49

50 Statistical Analysis Area under curve between a and b is 99.74% a m Mean b Time Beta distribution a 3σ m 3σ b Mean Time Normal distribution 02-50

51 Statistical Analysis The mean of the beta distribution can be estimated by t e = a + 4m + b 6 The variance of the beta distribution for each activity is σ 2 = b a

52 Example 2.4 Suppose that the project team has arrived at the following time estimates for activity B (site selection and survey) of the St. John s Hospital project: a = 7 weeks, m = 8 weeks, and b = 15 weeks a. Calculate the expected time and variance for activity B. b. Calculate the expected time and variance for the other activities in the project

53 Example 2.4 a. The expected time for activity B is 7 + 4(8) t e = = = 9 weeks 6 6 The variance for activity B is σ 2 = = =

54 Example 2.4 b. The following table shows the expected activity times and variances for this project. Activity Optimistic (a) Time Estimates (week) Most Likely (m) Pessimistic (b) Activity Statistics Expected Time (t e ) Variance (σ 2 ) A B C D E F G H I J K

55 Application 2.4 The director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administrative assistant identified the various activities that must be done and their relationships to each other: 02-55

56 Application 2.4 The Network Diagram is: A D G J Start B E I Finish C F H 02-56

57 Application 2.4 For the Bluebird University sales training seminar activities, calculate the means and variances for each activity. Activity Immediate Predecessor(s) Optimistic (a) Most Likely (m) Pessimistic (b) A B C D A E B F C, E G D H F I G, H J G Expected Time (t) Variance (σ) 02-57

58 Application 2.4 For the Bluebird University sales training seminar activities, calculate the means and variances for each activity. Activity Immediate Predecessor(s) Optimistic (a) Most Likely (m) Pessimistic (b) A B C D A E B F C, E G D H F I G, H J G Expected Time (t) Variance (σ)

59 Analyzing Probabilities Because the central limit theorem can be applied, the mean of the distribution is the earliest expected finish time for the project Expected activity times T E = on the critical path = Because the activity times are independent Mean of normal distribution σ p2 = (Variances of activities on the critical path) Using the z-transformation z = T T E σ p where T = due date for the project 02-59

60 Example 2.5 Calculate the probability that St. John s Hospital will become operational in 72 weeks, using (a) the critical path and (b) path A C G J K. a. The critical path B D H J K has a length of 69 weeks. From the table in Example 2.4, we obtain the variance of path B D H J K: σ 2 = = Next, we calculate the z-value: z

61 Example 2.5 Using the Normal Distribution appendix, we find a value of Thus the probability is about 0.81 the length of path B D H J K will be no greater than 72 weeks. Because this is the critical path, there is a 19 percent probability that the project will take longer than 72 weeks. Length of critical path Probability of meeting the schedule is Normal distribution: Mean = 69 weeks; σ = 3.45 weeks Probability of exceeding 72 weeks is Project duration (weeks) 02-61

62 Example 2.5 b. The sum of the expected activity times on path A C G J K is 67 weeks and that σ 2 = = The z-value is z The probability is about 0.90 that the length of path A C G J K will be no greater than 72 weeks

63 Application 2.5 The director of the continuing education at Bluebird University wants to conduct the seminar in 47 working days from now. Using the activity data from Application 2.4, what is the probability that everything will be ready in time? T = 47 days T E is: days And the sum of the variances for the critical activities is: ( ) = 8.63 The critical path is A D G I, and the expected completion time is days

64 Application 2.5 The Network Diagram is: A D G J Start B E I Finish C F H The critical path is A-D-G-I 02-64

65 Application 2.5 T = 47 days T E = days And the sum of the variances for the critical activities is: 8.63 z = T T E σ = = = Assuming the normal distribution applies, we use the table for the normal probability distribution. Given z = 1.30, the probability that activities A D G I can be completed in 47 days or less is

66 Monitoring and Controlling Projects Monitoring Project Status Open Issues and Risks Schedule Status Monitoring Project Resources 02-66

67 Solved Problem 2.1 Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the thirteenth day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedent relationships are given in Table 2.2. a. Draw the project network diagram. b. What completion date would you recommend? 02-67

68 Solved Problem 2.1 Acti vity Normal Time (days) ELECTRIC MOTOR PROJECT DATA Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 4 1, ,300 None B 7 1, ,000 None C 5 2, ,700 None D 6 1, ,400 A E ,100 B F 11 2, ,750 C G ,450 D, E H F, G 02-68

69 Solved Problem 2.1 a. The network diagram is shown in Figure Keep the following points in mind while constructing a network diagram. A 4 D 6 G 4 Finish Start B 7 E 3 H 3 C 5 F

70 Solved Problem 2.1 b. With these activity times, the project will be completed in 19 days and incur a $700 penalty. Using the data in Table 2.2, you can determine the maximum crash-time reduction and crash cost per day for each activity. For activity A Maximum crash time = Normal time Crash time = 4 days 3 days = 1 day Crash cost per day Crash cost Normal cost = = Normal time Crash time = = $300 $1,300 $1,000 4 days 3 days CC NC NT CT 02-70

71 Solved Problem 2.1 Activity Crash Cost per Day ($) Maximum Time Reduction (days) A B C D E F G H

72 Solved Problem 2.1 PROJECT COST ANALYSIS Stage Crash Activity Time Reduction (days) Resulting Critical Path(s) Project Duration (days) Project Direct Costs, Last Trial ($) Crash Cost Added ($) Total Indirect Costs ($) Total Penalty Costs ($) Total Project Costs ($) 0 C-F-H 19 10,100 3, ,600 1 H 2 C-F-H 17 10, , ,200 2 F 2 A-D-G-H 15 10, , ,100 B-E-G-H C-F-H 02-72

73 Solved Problem 2.1 The critical path is C F H at 19 days, which is the longest path in the network. The cheapest activity to crash is H which, when combined with reduced penalty costs, saves $300 per day. Crashing this activity for two days gives A D G H: 15 days, B E G H: 15 days, and C F H: 17 days Crash activity F next. This makes all activities critical and no more crashing should be done as the cost of crashing exceeds the savings

74 Solved Problem 2.2 An advertising project manager developed the network diagram in Figure 2.11 for a new advertising campaign. In addition, the manager gathered the time information for each activity, as shown in the accompanying table. a. Calculate the expected time and variance for each activity. A D E Finish b. Calculate the activity slacks and determine the critical path, using the expected activity times. Start B C F G c. What is the probability of completing the project within 23 weeks? 02-74

75 Solved Problem 2.2 Time Estimate (weeks) Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s) A B C B D A E A, C F B G E, F 02-75

76 Solved Problem 2.2 a. The expected time and variance for each activity are calculated as follows t e = a + 4m + b 6 Activity Expected Time (weeks) Variance A B C D E F G

77 Solved Problem 2.2 b. We need to calculate the earliest start, latest start, earliest finish, and latest finish times for each activity. Starting with activities A and B, we proceed from the beginning of the network and move to the end, calculating the earliest start and finish times. Activity Earliest Start (weeks) Earliest Finish (weeks) A = 4.0 B = 5.5 C = 9.0 D = 16.0 E = 15.5 F = 14.5 G =

78 Solved Problem 2.2 Based on expected times, the earliest finish date for the project is week 20, when activity G has been completed. Using that as a target date, we can work backward through the network, calculating the latest start and finish times Activity Latest Start (weeks) Latest Finish (weeks) G F E D C B A

79 Solved Problem D Finish 0.0 A E Start 5.5 C B F G

80 Solved Problem 2.2 Start (weeks) Finish (weeks) Activity Earliest Latest Earliest Latest Slack Critical Path A No B Yes C Yes D No E Yes F No G Yes Path Total Expected Time (weeks) Total Variance A D = = 2.78 A E G = = 3.94 B C E G = = 3.88 B F G = =

81 Solved Problem 2.2 The critical path is B C E G with a total expected time of 20 weeks. However, path B F G is 19 weeks and has a large variance. c. We first calculate the z-value: T T E z = = = 1.52 σ Using the Normal Distribution Appendix, we find the probability of completing the project in 23 weeks or less is Because the length of path B F G is close to that of the critical path and has a large variance, it might well become the critical path during the project 02-81

82 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

Teori Pengambilan Keputusan. Week 12 Project Management

Teori Pengambilan Keputusan. Week 12 Project Management Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

PROJECT MANAGEMENT CPM & PERT TECHNIQUES PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a

More information

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM /7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

SCM 301 (Solo) Exam 1 Practice Exam Solutions

SCM 301 (Solo) Exam 1 Practice Exam Solutions 1. D $118,000 www.liontutors.com SCM 301 (Solo) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network

More information

SCM 301 (Lutz) Exam 1 Practice Exam Solutions

SCM 301 (Lutz) Exam 1 Practice Exam Solutions 1. D $118,000 www.liontutors.com SCM 301 (Lutz) Exam 1 Practice Exam Solutions The first thing we need to do here is use the information given in the table to create a network diagram. Once we have a network

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities

More information

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project. INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001 Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique

More information

POLYTECHNIC OF NAMIBIA

POLYTECHNIC OF NAMIBIA POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center

More information

Project Management Techniques (PMT)

Project Management Techniques (PMT) Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.

More information

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices

More information

Lecture 3 Project Scheduling

Lecture 3 Project Scheduling B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?

More information

IE 102 Spring Project Management

IE 102 Spring Project Management IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and

More information

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive

More information

06IP/IM74 OPERATIONS RESEARCH

06IP/IM74 OPERATIONS RESEARCH 06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this

More information

WHY ARE PROJECTS ALWAYS LATE?

WHY ARE PROJECTS ALWAYS LATE? WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

Reducing Project Duration

Reducing Project Duration CHAPTER NINE Reducing Project Duration McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs

More information

CHAPTER 5. Project Scheduling Models

CHAPTER 5. Project Scheduling Models CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

Lecture 5: Project Management

Lecture 5: Project Management Lecture 5: Management organization structure ritical path method (PM) Time/cost tradeoff PM with three activity it time estimates t Readings: hapter 10 Management series of related jobs usually directed

More information

CHAPTER 5 STOCHASTIC SCHEDULING

CHAPTER 5 STOCHASTIC SCHEDULING CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta Contemporary Engineering Sciences, Vol. 10, 2017, no. 7, 317-333 HIKARI Ltd, www.m-hikari.com https://doi.org/10.12988/ces.2017.712 Optimization of Rescheduling and Economy Analysis of the Implementation

More information

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL Abstract: Crashing is a process of expediting project schedule

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

The Critical Path Method

The Critical Path Method The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico "I believe that this nation should commit

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

Project Management and Cost Control

Project Management and Cost Control Project Management and Cost Control What is Project Management Build A A Done Build B B Done Build C JAN FEB MAR APR MAY JUN C Done Build D On time! Ship Unique, one-time operations designed to accomplish

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

Management Management

Management Management Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently

More information

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H XRIS. What do you mean by network analysis? xplain with counter examples.. What are the basic differences between PM and PRT analysis of project work?. State the rule of constructing the network diagram..

More information

ETSF01: Software Engineering Process Economy and Quality

ETSF01: Software Engineering Process Economy and Quality ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower

More information

Outline. Project Management. Introduction. What is a Project?

Outline. Project Management. Introduction. What is a Project? Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction

More information

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 01, January 2019, pp. 825-832, Article ID: IJCIET_10_01_075 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=10&itype=01

More information

A SINGLE STEP CPM TIME-COST TRADEOFF ALGORITHM. In Mathematics and Computing. Under the guidance of Dr. Mahesh Kumar Sharma

A SINGLE STEP CPM TIME-COST TRADEOFF ALGORITHM. In Mathematics and Computing. Under the guidance of Dr. Mahesh Kumar Sharma A SINGLE STEP CPM TIME-COST TRADEOFF ALGORITHM Thesis submitted in partial fulfillment of the requirement for The award of the degree of Master of Science In Mathematics and Computing Submitted by Gurpreet

More information

Line Balancing S K Mondal Chapter 3

Line Balancing S K Mondal Chapter 3 Line Balancing S K Mondal Chapter 3 Solution: J G 10 K I 7 L J, H 10 M K 6 N L, M 9 [10-Marks] 6 8 7 10 A D G J 5 B 5 6 E H L 10 9 N Work station number 1 3 4 5 6 4 10 7 4 C F I K M 6 Precedence diagram

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

56:171 Operations Research Midterm Exam Solutions October 22, 1993

56:171 Operations Research Midterm Exam Solutions October 22, 1993 56:171 O.R. Midterm Exam Solutions page 1 56:171 Operations Research Midterm Exam Solutions October 22, 1993 (A.) /: Indicate by "+" ="true" or "o" ="false" : 1. A "dummy" activity in CPM has duration

More information

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION 1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and

More information

Handout 4: Deterministic Systems and the Shortest Path Problem

Handout 4: Deterministic Systems and the Shortest Path Problem SEEM 3470: Dynamic Optimization and Applications 2013 14 Second Term Handout 4: Deterministic Systems and the Shortest Path Problem Instructor: Shiqian Ma January 27, 2014 Suggested Reading: Bertsekas

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

NPV Method. Payback Period

NPV Method. Payback Period 1. Why the payback method is often considered inferior to discounted cash flow in capital investment appraisal? A. It does not take account of the time value of money B. It does not calculate how long

More information

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,

More information

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015 Logistics Lecture notes Maria Grazia Scutellà Dipartimento di Informatica Università di Pisa September 2015 These notes are related to the course of Logistics held by the author at the University of Pisa.

More information

Project Management with Brief Information regarding CPM and PERT Methods

Project Management with Brief Information regarding CPM and PERT Methods 99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract

More information

Programme Evaluation and Review Technique

Programme Evaluation and Review Technique 15 Programme Evaluation and Review Technique LEARNING OBJECTIVES : After studying this chapter, you will be able to : l l l l l l l l l Explain generic term network analysis and such related terms as Critical

More information

Chapter 2 The PERT/CPM Technique

Chapter 2 The PERT/CPM Technique Chapter The PERT/CPM Technique Abstract Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects

More information

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques

More information

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT Programme BA (Hons) Fashion and Textiles (Top-Up) BA (Hons) Graphic Design with Animation (Top-Up) BA (Hons) Interior Design Cohort FDI- BFT(TP)/14B/PT FDI- BGDA(TP)/14B/PT FDI-BAID/13B/FT Examinations

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

NETWORK ANALYSIS QUESTION BANK

NETWORK ANALYSIS QUESTION BANK NETWORK ANALYSIS QUESTION BANK 1. Explain the terms : Total elapsed time, idle time. 2. What do you mean by dummy activity and successor activity. 3. Write four advantages of network analysis. 4. Explain

More information

Cost Slope Analysis 1

Cost Slope Analysis 1 Cost Slope Analysis 1 Running head: Cost Slope Analysis Cost Slope Analysis Technique Summary Su-Cheng Wu Cost Slope Analysis 2 Abstract: Cost Slope Analysis considers the following: direct, indirect cost,

More information

Project Management. Chapter 2 DISCUSSION QUESTIONS

Project Management. Chapter 2 DISCUSSION QUESTIONS hapter Project Management ISUSSION QUSTIONS 1. Software is an essential element for successful management of complex projects. It can provide information on completion performance of critical activities,

More information

56:171 Operations Research Midterm Examination Solutions PART ONE

56:171 Operations Research Midterm Examination Solutions PART ONE 56:171 Operations Research Midterm Examination Solutions Fall 1997 Answer both questions of Part One, and 4 (out of 5) problems from Part Two. Possible Part One: 1. True/False 15 2. Sensitivity analysis

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

Decision Support Tool for Project Time-Cost Trade-off

Decision Support Tool for Project Time-Cost Trade-off Decision Support Tool for Project Time-Cost Trade-off Fikri Dweiri Industrial Engineering and Engineering Management Department University of Sharjah Sharjah, UAE, 27272 fdweiri@sharjah.ac.ae Abstract

More information

M G T 2251 Management Science. Exam 3

M G T 2251 Management Science. Exam 3 M G T 2251 Management Science Exam 3 Professor Chang November 8, 2012 Your Name (Print): ID#: Read each question carefully before you answer. Work at a steady pace, and you should have ample time to finish.

More information

PROJECT MANAGEMENT: PERT AMAT 167

PROJECT MANAGEMENT: PERT AMAT 167 PROJECT MANAGEMENT: PERT AMAT 167 PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time

More information

PASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year

PASS4TEST. IT Certification Guaranteed, The Easy Way!  We offer free update service for one year PASS4TEST IT Certification Guaranteed, The Easy Way! \ We offer free update service for one year Exam : PMI-SP Title : PMI Scheduling Professional Vendors : PMI Version : DEMO Get Latest & Valid PMI-SP

More information

Poor Man s Approach to Monte Carlo

Poor Man s Approach to Monte Carlo Poor Man s Approach to Monte Carlo Based on the PMI PMBOK Guide Fourth Edition 20 IPDI has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI).

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Comparison between Deterministic and Stochastic Time Estimating Techniques

Comparison between Deterministic and Stochastic Time Estimating Techniques Comparison between Deterministic and Stochastic Time Estimating Techniques Daketima G. Briggs, Ph.D, PMP Management Department, Faculty of Business, University of Botswana ABSTRACT: This paper started

More information

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1 A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,

More information

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2 UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle

More information

DEBITS AND CREDITS: ANALYZING AND RECORDING BUSINESS TRANSACTIONS

DEBITS AND CREDITS: ANALYZING AND RECORDING BUSINESS TRANSACTIONS DEBITS AND CREDITS: ANALYZING AND RECORDING BUSINESS TRANSACTIONS 2-1 Chapter 2 Learning Objectives 1. Setting up and organizing a chart of accounts. 2. Recording transactions in T accounts according to

More information

UNIVERSITY OF SWAZILAND FACULTY OF COMMERCE DEPARTMENT OF BUSINESS ADMINISTRATION FINAL EXAMINATION PAPER MAY 2016 ROJECT MANAGEMENT THREE [3] HOURS

UNIVERSITY OF SWAZILAND FACULTY OF COMMERCE DEPARTMENT OF BUSINESS ADMINISTRATION FINAL EXAMINATION PAPER MAY 2016 ROJECT MANAGEMENT THREE [3] HOURS UNIVERSITY OF SWAZILAND FACULTY OF COMMERCE DEPARTMENT OF BUSINESS ADMINISTRATION FINAL EXAMINATION PAPER MAY 2016 TITLE OF PAPER ROJECT MANAGEMENT COURSE CODE BA303 FULL TIME STUDENTS TIME ALLOCATED TOTAL

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

56:171 Operations Research Midterm Examination Solutions PART ONE

56:171 Operations Research Midterm Examination Solutions PART ONE 56:171 Operations Research Midterm Examination Solutions Fall 1997 Write your name on the first page, and initial the other pages. Answer both questions of Part One, and 4 (out of 5) problems from Part

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information