Textbook: pp Chapter 11: Project Management

Size: px
Start display at page:

Download "Textbook: pp Chapter 11: Project Management"

Transcription

1 1 Textbook: pp Chapter 11: Project Management

2 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use of PERT and CPM. Determine earliest start, earliest finish, latest start, latest finish, and slack times for each activity, along with the total project completion time and total project cost. Reduce total project time at the least total cost by crashing the network using manual or linear programming techniques. Understand the important role of software in project management.

3 3 Introduction (1 of 2) Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high o The first step in planning and scheduling a project is to develop the work breakdown structure (WBS) o Identify activities that must be performed and their beginning and ending events o Identify time, cost, resource requirements, predecessors, and people responsible for each activity o A schedule for the project then can be developed

4 4 Introduction (2 of 2) The programme evaluation and review technique (PERT) and the critical path method (CPM) are two popular quantitative analysis techniques for complex projects o PERT uses three time estimates to develop a probabilistic estimate of completion time o CPM is a more deterministic technique o They are so similar they are commonly considered as one technique, PERT/CPM

5 5 Six Steps of PERT/CPM 1. Define the project and all of its significant activities or tasks. 2. Develop the relationships among the activities. Decide which activities must precede others. 3. Draw the network connecting all of the activities. 4. Assign time and/or cost estimates to each activity. 5. Compute the longest time path through the network; this is called the critical path. 6. Use the network to help plan, schedule, monitor, and control the project. The critical path is important since any delay in these activities can delay the completion of the project!

6 6 Programme evaluation and review technique (PERT) PERT/CPM (1 of 2) Questions answered by PERT: 1. When will the entire project be completed? 2. What are the critical activities or tasks in the project that is, the ones that will delay the entire project if they are late? 3. Which are the noncritical activities that is, the ones that can run late without delaying the entire project s completion? 4. If there are three time estimates, what is the probability that the project will be completed by a specific date?

7 7 PERT/CPM (2 of 2) Questions answered by PERT: 5. At any particular date, is the project on schedule, behind schedule, or ahead of schedule? 6. On any given date, is the money spent equal to, less than, or greater than the budgeted amount? 7. Are there enough resources available to finish the project on time?

8 8 General Foundry Example (1 of 2) General Foundry, Inc. has long been trying to avoid the expense of installing air pollution control equipment The local environmental protection group has recently given the foundry 16 weeks to install a complex air filter system on its main smokestack General Foundry was warned that it will be forced to close unless the device is installed in the allotted period They want to make sure that installation of the filtering system progresses smoothly and on time

9 9 General Foundry Example (2 of 2) Activities and Immediate Predecessors for General Foundry, Inc.:

10 10 Drawing the PERT/CPM Network (1 of 2) Two common techniques for drawing PERT networks: o Activity-on-node (AON) nodes represent activities o Activity-on-arc (AOA) arcs represent the activities o The AON approach is easier and more commonly found in software packages o One node represents the start of the project, one node for the end of the project, and nodes for each of the activities o The arcs are used to show the predecessors for each activity

11 11 Drawing the PERT/CPM Network (2 of 2) Network for General Foundry, Inc.:

12 12 Activity Times (1 of 6) In some situations, activity times are known with certainty o CPM assigns just one time estimate to each activity and this is used to find the critical path In many projects there is uncertainty about activity times o PERT employs a probability distribution based on three time estimates for each activity, and a weighted average of these estimates is used for the time estimate and this is used to determine the critical path

13 13 Activity Times (2 of 6) The time estimates in PERT are: Optimistic time (a) = time an activity will take if everything goes as well as possible. There should be only a small probability (say, 1/100) of this occurring. Pessimistic time (b) = Most likely time (m) = time an activity would take assuming very unfavourable conditions. There should also be only a small probability that the activity will really take this long. most realistic time estimate to complete the activity.

14 14 Activity Times (3 of 6) PERT often assumes time estimates follow a beta probability distribution! Beta Probability Distribution with Three Time Estimates:

15 15 Activity Times (4 of 6) To find the expected activity time (t), the beta distribution weights the estimates as follows t = a + 4 m + b 6 To compute the dispersion or variance of activity completion time Variance = b 6 a 2

16 16 Activity Times (5 of 6) Time Estimates (Weeks) for General Foundry, Inc.:

17 17 Activity Times (6 of 6) General Foundry s Network with Expected Activity Times:

18 18 How to Find the Critical Path (1 of 11) We accept the expected completion time for each task as the actual time The total of 25 weeks does not take into account that some of the tasks could be taking place at the same time To find out how long the project will take we perform the critical path analysis for the network The critical path is the longest path through the network

19 19 How to Find the Critical Path (2 of 11) To find the critical path, determine the following quantities for each activity: 1. Earliest start (ES) time: the earliest time an activity can begin without violation of immediate predecessor requirements 2. Earliest finish (EF) time: the earliest time at which an activity can end 3. Latest start (LS) time: the latest time an activity can begin without delaying the entire project 4. Latest finish (LF) time: the latest time an activity can end without delaying the entire project

20 20 How to Find the Critical Path (3 of 11) Activity times are represented in the nodes Earliest times are computed as Earliest finish time = Earliest start time + Expected activity time EF = ES + t Earliest start = Largest of the earliest finish times of immediate predecessors ES = Largest EF of immediate predecessors

21 21 How to Find the Critical Path (4 of 11) At the start of the project we set the time to zero Thus ES = 0 for both A and B

22 22 How to Find the Critical Path (5 of 11) General Foundry s Earliest Start (ES) and Earliest Finish (EF) Times:

23 23 How to Find the Critical Path (6 of 11) General Foundry s Earliest Start (ES) and Earliest Finish (EF) Times: Use a forward pass through the network!

24 24 How to Find the Critical Path (7 of 11) Compute latest start (LS) and latest finish (LF) times for each activity by making a backward pass through the network. Latest start time = Latest finish time Expected activity time LS = LF t Latest finish time = Smallest of latest start times for following activities LF = Smallest LS of following activities For activity H LS = LF t = 15 2 = 13 weeks

25 25 How to Find the Critical Path (8 of 11) General Foundry s Latest Start (LS) and Latest Finish (LF) Times:

26 26 How to Find the Critical Path (9 of 11) Once ES, LS, EF, and LF have been determined, find the amount of slack time for each activity Slack = LS ES, or Slack = LF EF Activities A, C, E, G, and H have no slack time These are called critical activities and they are said to be on the critical path The total project completion time is 15 weeks Industrial managers call this a boundary timetable

27 27 How to Find the Critical Path (10 of 11) General Foundry s Schedule and Slack Times:

28 28 How to Find the Critical Path (11 of 11) General Foundry s Critical Path (A C E G H):

29 29 Probability of Project Completion (1 of 6) The critical path analysis helped determine the expected project completion time of 15 weeks o Variation in activities on the critical path can affect overall project completion o If the project is not complete in 16 weeks, the foundry will have to close PERT uses the variance of critical path activities to help determine the variance of the overall project Project variance = variances of activities on the critical path

30 30 Probability of Project Completion (2 of 6) From Table 11.2 we know Hence, the project variance is Project variance

31 31 Probability of Project Completion (3 of 6) We know the standard deviation is the square root of the variance, so Project standard deviation T Project variance weeks We assume activity times are independent and that total project completion time is normally distributed A bell-shaped curve can be used to represent project completion dates

32 32 Probability of Project Completion (4 of 6) Probability Distribution for Project Completion Times:

33 33 Table --- Appendix A (pp ) Probability of Project Completion (5 of 6) The standard normal equation can be applied as follows Z Due date Expected date of completion 16 weeks 15 weeks weeks T From Appendix A we find the probability of associated with this Z value That means the probability this project can be completed in 16 weeks or less is 0.716

34 34 Probability of Project Completion (6 of 6) Probability of General Foundry s Meeting the 16-Week Deadline:

35 35 What PERT Was Able to Provide 1. The project s expected completion date is 15 weeks 2. There is a 71.6% chance that the equipment will be in place within the 16-week deadline 3. Five activities (A, C, E, G, H) are on the critical path 4. Three activities (B, D, F) are not critical but have some slack time built in 5. A detailed schedule of activity starting and ending dates has been made available

36 38 Sensitivity Analysis and Project Management (1 of 3) The time required to complete an activity can vary from the projected or expected time: o If the activity is on the critical path, the completion time of the project will change o This will also have an impact on ES, EF, LS, and LF times for other activities o Exact impact depends on the relationship between the various activities

37 39 Sensitivity Analysis and Project Management (2 of 3) A predecessor activity is one that must be accomplished before the given activity can be started A successor activity is one that can be started only after the given activity is finished A parallel activity is one that does not directly depend on the given activity o Once these have been defined, we can explore the impact that an increase (decrease) in an activity time for a critical path activity would have on other activities in the network

38 40 Sensitivity Analysis and Project Management (3 of 3) Impact of an Increase (Decrease) in an Activity Time for a Critical Path Activity:

39 41 PERT/COST PERT is an excellent method of monitoring and controlling project length but it does not consider the very important factor of project cost PERT/Cost is a modification of PERT that allows a manager to plan, schedule, monitor, and control cost as well as time

40 42 Four Steps of the Budgeting Process (1 of 2) Step 1: Identify all costs associated with each of the activities. Then add these costs together to get one estimated cost or budget for each activity. Step 2: If you are dealing with a large project, several activities can be combined into larger work packages. A work package is simply a logical collection of activities. Since the General Foundry project we have been discussing is small, each activity will be a work package.

41 43 Four Steps of the Budgeting Process (2 of 2) Step 3: Convert the budgeted cost per activity into a cost per time period. To do this, we assume that the cost of completing any activity is spent at a uniform rate over time. Thus, if the budgeted cost for a given activity is $48,000 and the activity s expected time is 4 weeks, the budgeted cost per week is $12,000 ($48,000/4 weeks). Step 4: Using the earliest and latest start times, find out how much money should be spent during each week or month to finish the project by the date desired.

42 44 Budgeting for General Foundry (1 of 6) The Gantt chart below illustrates this process Determine how much will be spent on each activity during each week and fill these amounts into a chart in place of the bars Gantt Chart for General Foundry Example:

43 45 Budgeting for General Foundry (2 of 6) Activity Cost for General Foundry, Inc.:

44 46 Budgeting for General Foundry (3 of 6) Budgeted Cost ($1,000s) for General Foundry, Inc., Using Earliest Start Times:

45 47 Budgeting for General Foundry (4 of 6) Budgeting using the earliest start time gives a result that resembles the Gantt chart shown previously If latest start times and used expenditures are delayed until the latest possible time Any budget between these two ranges may be chosen

46 48 Budgeting for General Foundry (5 of 6) Budgeted Cost ($1,000s) for General Foundry, Inc., Using Latest Start Times:

47 49 Budgeting for General Foundry (6 of 6) Budget Ranges for General Foundry:

48 50 Monitoring and Controlling Project Costs (1 of 3) Ensure the project is progressing on schedule Cost overruns are kept to a minimum Status of the entire project should be checked periodically o Is the project on schedule? o What is the value of work completed? o Are there any overruns?

49 51 Monitoring and Controlling Project Costs (2 of 3) The value of work completed, or the cost to date for any activity Value of work completed = (Percentage of work complete) (Total activity budget) The activity difference Activity difference = Actual cost Value of work completed

50 52 Monitoring and Controlling Project Costs (3 of 3) Monitoring and Controlling Budgeted Cost:

51 53 Project Crashing (1 of 2) Projects will sometimes have deadlines that are impossible to meet using normal procedures By using exceptional methods, it may be possible to finish the project in less time Costs usually increase Reducing a project s completion time is called crashing

52 54 Project Crashing (2 of 2) Start by using the normal time to create the critical path The normal cost is the cost for completing the activity using normal procedures If the project will not meet the required deadline, extraordinary measures must be taken o The crash time is the shortest possible activity time and will require additional resources o The crash cost is the price of completing the activity in the earlier-than-normal time

53 55 Four Steps to Project Crashing (1 of 2) Step 1: Find the normal critical path and identify the critical activities. Step 2: Compute the crash cost per week (or other time period) for all activities in the network using the formula. Crash cost /Time period = Crash cost Normal cost Normal time Crash time

54 56 Four Steps to Project Crashing (2 of 2) Step 3: Select the activity on the critical path with the smallest crash cost per week. Crash this activity to the maximum extent possible or to the point at which your desired deadline has been reached. Step 4: Check to be sure that the critical path you were crashing is still critical. Often, a reduction in activity time along the critical path causes a noncritical path or paths to become critical. If the critical path is still the longest path through the network, return to step 3. If not, find the new critical path and return to step 3.

55 57 General Foundry (1 of 3) Suppose: o General Foundry has been given 14 weeks instead of 16 weeks to install the new equipment o A bonus was on the line if equipment is installed in 12 weeks or less The critical path for the project is 15 weeks What options does the firm have?

56 58 General Foundry (2 of 3) Normal and Crash Data for General Foundry, Inc.:

57 59 General Foundry (3 of 3) Crash and Normal Times and Costs for Activity B:

58 60 Project Crashing with Linear Programming (1 of 5) Linear programming can be used to find the best project crashing schedule Decision variables for General Foundry: X A = EF for activity A X B = EF for activity B X C = EF for activity C X D = EF for activity D X E = EF for activity E X F = EF for activity F X G = EF for activity G X H = EF for activity H X start = start time for project (usually 0) X finish = earliest finish time for the project Y = the number of weeks that each activity is crashed Y A = the number of weeks activity A is crashed and so forth up to Y H

59 61 Project Crashing with Linear Programming (2 of 5) General Foundry s Network with Activity Times:

60 62 Project Crashing with Linear Programming (3 of 5) Objective function: Minimise crash cost = 1,000Y A + 2,000Y B + 1,000Y C + 1,000Y D + 1,000Y E + 500Y F + 2,000Y G + 3,000Y H Crash Time Constraints: Project Completion Constraint: Y A 1 Y E 2 X finish 12 Y B 2 Y F 1 Y C 1 Y G 3 Y D 1 Y H 1

61 63 Project Crashing with Linear Programming (4 of 5) Constraints Describing the Network: EF time EF time for predecessor + Activity time EF EF predecessor + (t Y), or X X predecessor + (t Y) For activity A, X A X start + (2 Y A ) or X A X start + Y A 2 For activity B, X B X start + (3 Y B ) or X B X start + Y B 3 For activity C, X C X A + (2 Y C ) or X C X A + Y C 2 For activity D, X D X B + (4 Y D ) or X D X B + Y D 4 For activity E, X E X C + (4 Y E ) or X E X C + Y E 4 For activity F, X F X C + (3 Y F ) or X F X C + Y F 3 For activity G, X G X D + (5 Y G ) or X G X D + Y G 5 For activity G, X G X E + (5 Y G ) or X G X E + Y G 5 For activity H, X H X F + (2 Y H ) or X H X F + Y H 2 For activity H, X H X G + (2 Y H ) or X H X G + Y H 2 H finished X finish X H

62 65 Other Topics in Project Management Subprojects o For extremely large projects, an activity may be made of several smaller sub-activities Milestones o Major events in a project are often referred to as milestones Resource Levelling o Software o o Adjusts the activity start away from the early start so that resource utilisation is more evenly distributed over time Numerous project management software packages They can be used to develop budget schedules, adjust future start times, and level resource utilisation

63 66 Homework --- Chapter 11 End of chapter self-test 1-18 (pp. 432) Compile all answers into one document and submit at the beginning of the next lecture! On the top of the document, write your Pinyin-Name and Student ID. Please read Chapter 12!

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

Teori Pengambilan Keputusan. Week 12 Project Management

Teori Pengambilan Keputusan. Week 12 Project Management Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM /7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive

More information

IE 102 Spring Project Management

IE 102 Spring Project Management IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center

More information

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path? PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

PROJECT MANAGEMENT CPM & PERT TECHNIQUES PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

CHAPTER 5. Project Scheduling Models

CHAPTER 5. Project Scheduling Models CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project

More information

Project Management Techniques (PMT)

Project Management Techniques (PMT) Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.

More information

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project. INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E

More information

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION 1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

ETSF01: Software Engineering Process Economy and Quality

ETSF01: Software Engineering Process Economy and Quality ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower

More information

Outline. Project Management. Introduction. What is a Project?

Outline. Project Management. Introduction. What is a Project? Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction

More information

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

06IP/IM74 OPERATIONS RESEARCH

06IP/IM74 OPERATIONS RESEARCH 06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this

More information

Chapter 2 The PERT/CPM Technique

Chapter 2 The PERT/CPM Technique Chapter The PERT/CPM Technique Abstract Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

POLYTECHNIC OF NAMIBIA

POLYTECHNIC OF NAMIBIA POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:

More information

MS Project 2007 Page 1 of 18

MS Project 2007 Page 1 of 18 MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems

More information

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001 Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique

More information

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations

More information

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT E. Newby, F. D. Fomeni, M. M. Ali and C. Musingwini Abstract The standard methodology used for estimating the cost and

More information

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015 Logistics Lecture notes Maria Grazia Scutellà Dipartimento di Informatica Università di Pisa September 2015 These notes are related to the course of Logistics held by the author at the University of Pisa.

More information

Management Management

Management Management Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently

More information

Lecture 3 Project Scheduling

Lecture 3 Project Scheduling B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?

More information

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL Abstract: Crashing is a process of expediting project schedule

More information

WHY ARE PROJECTS ALWAYS LATE?

WHY ARE PROJECTS ALWAYS LATE? WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,

More information

Making sense of Schedule Risk Analysis

Making sense of Schedule Risk Analysis Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years

More information

u w 1.5 < 0 These two results imply that the utility function is concave.

u w 1.5 < 0 These two results imply that the utility function is concave. A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project

More information

Comparison between Deterministic and Stochastic Time Estimating Techniques

Comparison between Deterministic and Stochastic Time Estimating Techniques Comparison between Deterministic and Stochastic Time Estimating Techniques Daketima G. Briggs, Ph.D, PMP Management Department, Faculty of Business, University of Botswana ABSTRACT: This paper started

More information

Decision Support Tool for Project Time-Cost Trade-off

Decision Support Tool for Project Time-Cost Trade-off Decision Support Tool for Project Time-Cost Trade-off Fikri Dweiri Industrial Engineering and Engineering Management Department University of Sharjah Sharjah, UAE, 27272 fdweiri@sharjah.ac.ae Abstract

More information

CHAPTER 5 STOCHASTIC SCHEDULING

CHAPTER 5 STOCHASTIC SCHEDULING CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration

More information

M G T 2251 Management Science. Exam 3

M G T 2251 Management Science. Exam 3 M G T 2251 Management Science Exam 3 Professor Chang November 8, 2012 Your Name (Print): ID#: Read each question carefully before you answer. Work at a steady pace, and you should have ample time to finish.

More information

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast

More information

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018

More information

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 01, January 2019, pp. 825-832, Article ID: IJCIET_10_01_075 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=10&itype=01

More information

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN: International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, 2017 http://ijaemr.com/ ISSN: 2456-3676 CPM AND PERT COMPARISON ANALYSIS IN PROJECT PLANNING ABSTRACT Talatu Muhammad

More information

Project Planning. Planning is an important step in project execution. Planning means:

Project Planning. Planning is an important step in project execution. Planning means: Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Project Controls Expo 16 th Nov 2016

Project Controls Expo 16 th Nov 2016 Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan

More information

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2 UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle

More information

PROJECT MANAGEMENT DIPLOMA COURSE

PROJECT MANAGEMENT DIPLOMA COURSE PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a

More information

Project Management with Brief Information regarding CPM and PERT Methods

Project Management with Brief Information regarding CPM and PERT Methods 99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract

More information

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta Contemporary Engineering Sciences, Vol. 10, 2017, no. 7, 317-333 HIKARI Ltd, www.m-hikari.com https://doi.org/10.12988/ces.2017.712 Optimization of Rescheduling and Economy Analysis of the Implementation

More information

Unit 5 Slide Lectures of 04/05/06 April 2017

Unit 5 Slide Lectures of 04/05/06 April 2017 PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT SCHEDULING, PROJECT DURATION AND PROJECT COMMUNICATION PLAN (CH. 8-9) Unit 5 Slide 5.2.1 Lectures of 04/05/06 April 2017 Overview of

More information

70-632_formatted. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0

70-632_formatted.   Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0 70-632_formatted Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ Microsoft EXAM 70-632 TS:Microsoft Office Project 2007. Managing Projects Total Questions:

More information

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur

More information

Plan Implementation. Pushpa Lal Shakya

Plan Implementation. Pushpa Lal Shakya Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application

More information

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

Exam Questions PMI-SP

Exam Questions PMI-SP Exam Questions PMI-SP PMI Scheduling Professional Practice Test https://www.2passeasy.com/dumps/pmi-sp/ 1.CORRECT TEXT Fill in the blank with the appropriate word. When activities are logically linked,

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

Formulas to Know for EXAM

Formulas to Know for EXAM Formulas to Know for EXAM Activity & Project Duration Formulas In order to calculate Estimated Activity Duration (EAD) of an activity, Optimistic (O), Most Likely (M) and Pessimistic (P) estimates for

More information

SECTION PROJECT SCHEDULE 08/08

SECTION PROJECT SCHEDULE 08/08 SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No. E 32R04 SA M PL DETERMI NI NGACTI VI TY DURATI ONS AACE International Recommended Practice No. 32R-04 DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development Rev. Note: As AACE

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017

More information

Risk Video #1. Video 1 Recap

Risk Video #1. Video 1 Recap Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive

More information

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

Line Balancing S K Mondal Chapter 3

Line Balancing S K Mondal Chapter 3 Line Balancing S K Mondal Chapter 3 Solution: J G 10 K I 7 L J, H 10 M K 6 N L, M 9 [10-Marks] 6 8 7 10 A D G J 5 B 5 6 E H L 10 9 N Work station number 1 3 4 5 6 4 10 7 4 C F I K M 6 Precedence diagram

More information

Project Management. Basic Definitions: Project and Project Plan

Project Management. Basic Definitions: Project and Project Plan Project Management Basic Definitions: Project and Project Plan Software Project: All technical and managerial activities required to deliver the deliverables to the client. A software project has a specific

More information

Modelling cash flow in construction projects in countries in transition

Modelling cash flow in construction projects in countries in transition Modelling cash flow in construction projects in countries in transition Mladen Raduj kovic Faculty of Civil Engineering, University of Zagreb, Zagreb, Croatia Summary The paper describes the modelling

More information

Cost Reduction: Planning & Control. Impacting the Bottom Line

Cost Reduction: Planning & Control. Impacting the Bottom Line Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,

More information

The Critical Path Method

The Critical Path Method The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico "I believe that this nation should commit

More information

PASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year

PASS4TEST. IT Certification Guaranteed, The Easy Way!  We offer free update service for one year PASS4TEST IT Certification Guaranteed, The Easy Way! \ We offer free update service for one year Exam : PMI-SP Title : PMI Scheduling Professional Vendors : PMI Version : DEMO Get Latest & Valid PMI-SP

More information