1 UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite start date and stop date. One Accountable Entity. Unlike operational work, where separate managers are accountable for different parts of the work, projects have only one accountable entity.
2 Project Element Definitive Prioritization of the TradeOffs When doing the work of projects most people are aware of what has been termed the "triple constraints" of project management.(time, quality, and resource expenditures) Agreement The final element is having agreement between the sponsor and the project manager 2
3
4
5
6
7 Types of WBS Process WBS It partitions a large process into smaller & smaller processes. Each process is eventually decomposed into tasks that can be assigned to individuals for accomplishment. Product WBS It partitions a large entity into its components. Each component & interfaces are identified, resulting in a clearer identification of the larger system. Hybrid WBS A WBS that includes both process & product elements of a project into one WBS. Project Life Cycle Project Life Cycle ModelsWaterfall model Prototyping Model Spiral Model 7
8 Product Life cycle Product development. Product Introduction. Product Growth. Product Maturity. Product Decline. Ways To Organize Personnel Flat Staffing Some of the developers can be assigned to the analysis activities with system analysts. While others may already start other activities such as technology review & trainings. Gradual Staffing The project work is gradually carried out by hiring people as required. It is motivated by saving resources in the early part of the project. 8
9 What should be the Team Size??? Team Size (n) Positive Impact. Three Members 2. Four Members Even if one member leaves, others continues to work.. Five & Six Members It is an ideal size for a team. Single roles may be given to each member. Members meet face to face. Every member has chance to speak. Negative Impact One member can dominate the other two. One member may perform many roles. Resolving issues like tie during voting can be more time consuming. No negative effects.. Seven Members Effective team size. Team meetings tend to become long. Sub teams formation is necessary. Reviewing the status requires more than half an hour.. Eight & more members Results are usually satisfactory. Too difficult to manage. More competition rather than cooperation of team members. Internal structure starts to break down into sub teams. Stages of Team Development Forming Storming These conflicts are settled & a group feeling should emerge. Performing Various team members try to show their leadership that may result in conflicts. Norming Introduction between team members. Some rules are also setup about behavior. Tasks are decided finally. Adjourning The group is dispersed. 9
10 Project Scheduling and Control Techniques Gantt Chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule 0
11 History of CPM/PERT Critical Path Method (CPM) E I Du Pont de Nemours & Co. (97) for construction of new chemical plant and maintenance shut-down Deterministic task times Activity-on-node network construction Repetitive nature of jobs Project Evaluation and Review Technique (PERT) U S Navy (98) for the POLARIS missile program Multiple task time estimates (probabilistic nature) Activity-on-arrow network construction Non-repetitive jobs (R & D work) Project Network Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects Use of nodes and arrows Arrows An arrow leads from tail to head directionally Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes A node is represented by a circle Indicate EVENT, a point in time where one or more activities start and/or finish. Activity A task or a certain amount of work required in the project Requires time to complete Represented by an arrow Dummy Activity Indicates only precedence relationships Does not require any time of effort
12 Event Project Network Signals the beginning or ending of an activity Designates a point in time Represented by a circle (node) Network Shows the sequential relationships among activities using nodes and arrows Activity-on-node (AON) nodes represent activities, and arrows show precedence relationships Activity-on-arrow (AOA) arrows represent activities and nodes are events for points in time AOA Project Network for House Lay foundation 2 Design house and obtain financing 2 Dummy 0 Order and receive materials Select paint Build house Finish work 7 Select carpet AON Project Network for House Lay foundations Build house 2 2 Start Finish work 7 Design house and obtain financing Order and receive materials Select carpet Select paint 2
13 Situations in network diagram B A A must finish before either B or C can start C A C both A and B must finish before C can start B A C B A D B both A and C must finish before either of B or D can start A must finish before B can start Dummy both A and C must finish before D can start C D Network example Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project?
14 For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time". Questions to prepare activity network Is this a Start Activity? Is this a Finish Activity? What Activity Precedes this? What Activity Follows this? What Activity is Concurrent with this?
15 CPM calculation Path Critical Path A connected sequence of activities leading from the starting event to the ending event The longest path (time); determines the project duration Critical Activities All of the activities that make up the critical path Forward Pass Earliest Start Time (ES) earliest time an activity can start ES = maximum EF of immediate predecessors Earliest finish time (EF) earliest time an activity can finish earliest start time plus activity time EF= ES + t Backward Pass Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors
16 CPM analysis Draw the CPM network Analyze the paths through the network Determine the float for each activity Compute the activity s float float = LS - ES = LF - EF Find the critical path is that the sequence of activities and events where there is no slack i.e.. Zero slack Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project Longest path through a network Find the project duration is minimum project completion time CPM Example: CPM Network f, h, 9 g, 7 a, i, b, 8 d, j, 2 c, e, 9
17 CPM Example ES and EF Times f, h, 9 g, 7 a, 0 i, b, d, j, 2 c, 0 e, 9 CPM Example ES and EF Times f, 2 h, 9 g, 7 a, 0 2 i, b, c, 0 d, j, e, 9 7
18 CPM Example ES and EF Times f, 2 g, 7 a, 0 2 i, 2 29 h, b, d, 8 2 c, e, 9 0 j, 2 2 Project s EF = CPM Example LS and LF Times a, 0 b, c, 0 f, 2 g, 7 2 d, 8 2 i, h, j, e, 9 8
19 CPM Example LS and LF Times a, 0 0 b, c, Float f, g, d, i, h, j, e, CPM Example a, 0 0 b, c, f, g, d, h, i, j, e,
20 CPM Example Critical Path f, h, 9 g, 7 a, i, b, 8 d, j, 2 c, e, 9 PERT PERT is based on the assumption that an activity s duration follows a probability distribution instead of being a single value Three time estimates are required to compute the parameters of an activity s duration distribution: pessimistic time (tp ) - the time the activity would take if things did not go well most likely time (tm ) - the consensus best estimate of the activity s duration optimistic time (to ) - the time the activity would take if things did go well t + tm + to Mean (expected time): te = p 2 Variance: Vt = 2 = tp - to 20
21 PERT analysis Draw the network. Analyze the paths through the network and find the critical path. The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum Probability computations can now be made using the normal distribution table. Probability computation Determine probability that project is completed within specified time x- Z= where = tp = project mean time = project standard mean time x = (proposed ) specified time 2
22 PERT Example Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A - 8 B -. C A D A E A 0.. F B,C G B,C. H E,F 7 I E,F 2 8 J D,H K G,I 7 PERT Example PERT Network D A E H J C B I F K G 22
23 PERT Example Activity A B C D E F G H I J K Expected Time 2 Variance /9 /9 0 /9 / /9 /9 /9 /9 /9 PERT Example Activity ES EF LS LF A B C D E F G H I J K Slack 0 *critical 0* 9 0* * 0* 2
24 PERT Example.7 Vpath = VA + VC + VF + VI + VK = / /9 + + /9 = 2 path =. z = (2-2)/ (2-2)/. = From the Standard Normal Distribution table: P(z <.7) = =.72 PROJECT COST 2
25 Cost consideration in project Project managers may have the option or requirement to crash the project, or accelerate the completion of the project. This is accomplished by reducing the length of the critical path(s). The length of the critical path is reduced by reducing the duration of the activities on the critical path. If each activity requires the expenditure of an amount of money to reduce its duration by one unit of time, then the project manager selects the least cost critical activity, reduces it by one time unit, and traces that change through the remainder of the network. As a result of a reduction in an activity s time, a new critical path may be created. When there is more than one critical path, each of the critical paths must be reduced. If the length of the project needs to be reduced further, the process is repeated. Project Crashing Crashing Crash time an amount of time an activity is reduced Crash cost reducing project time by expending additional resources cost of reducing activity time Goal reduce project duration at minimum cost 2
26 Activity crashing Crash cost Crashing activity Slope = crash cost per unit time Normal Activity Normal cost Normal time Crash time Activity time Time-Cost Relationship Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff Min total cost = optimal project time Total project cost Indirect cost Direct cost time 2
27 Project Crashing example Time Cost data Activit Norm Norm y al time al cost Rs Crash Crash Allowabl time cost e crash Rs time slope
28 R00 R Project duration = R R00 To.. R000 From.. R200 R200 R00 R R Project duration = Additional cost = R2000 R00 R000 R200 R200 Benefits of CPM/PERT Useful at many stages of project management Mathematically simple Give critical path and slack time Provide project documentation Useful in monitoring costs CPM/PERT can answer the following important questions: How long will the entire project take to be completed? What are the risks involved? Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? Is the project on schedule, behind schedule or ahead of schedule? If the project has to be finished earlier than planned, what is the best way to do this at the least cost? 28
29 Limitations to CPM/PERT Clearly defined, independent and stable activities Specified precedence relationships Over emphasis on critical paths Deterministic CPM model Activity time estimates are subjective and depend on judgment PERT assumes a beta distribution for these time estimates, but the actual distribution may be different PERT consistently underestimates the expected project completion time due to alternate paths becoming critical To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias Computer Software for Project Management Microsoft Project (Microsoft Corp.) MacProject (Claris Corp.) PowerProject (ASTA Development Inc.) Primavera Project Planner (Primavera) Project Scheduler (Scitor Corp.) Project Workbench (ABT Corp.) 29
30 Practice Example A social project manager is faced with a project with the following activities: Activity Description Duratio n w 2w w w Social work team to live in village Social research team to do survey Analyse results of survey Establish mother & child health program Establish rural credit program w Carry out immunization of under fives w Draw network diagram and show the critical path. Calculate project duration. Practice problem Activit y Description Social work team to live in village Social research team to do survey Analyse results of survey Establish mother & child health program Establish rural credit programme Carry out immunization of under fives Duratio n w 2w w w w w 2 0
31 Project Scheduling and Tracking What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much will it cost?
32 Scheduling Principles - Compartmentalization Interdependency the product and process must be decomposed into a manageable number of activities and tasks tasks that can be completed in parallel must be separated from those that must completed serially Time allocation every task has start and completion dates that take the task interdependencies into account Scheduling Principles - 2 Effort validation project manager must ensure that on any given day there are enough staff members assigned to completed the tasks within the time estimated in the project plan Defined Responsibilities every scheduled task needs to be assigned to a specific team member 2
33 Scheduling Principles - Defined outcomes every task in the schedule needs to have a defined outcome (usually a work product or deliverable) Defined milestones a milestone is accomplished when one or more work products from an engineering task have passed quality review Total Float Time
34
35 QUESTIONS-
36 What do you mean by a dummy activity? Why it is used in networking?
37 Pert Question- Pert Question 7
Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams
Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able
More informationCISC 322 Software Architecture
CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service
More informationAfter complete studying this chapter, You should be able to
Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics
More informationPROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana
PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce
More informationPROJECT MANAGEMENT CPM & PERT TECHNIQUES
PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a
More informationManagement Management
Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently
More informationTextbook: pp Chapter 11: Project Management
1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use
More informationA convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.
Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects
More informationNetwork Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana
Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationCHAPTER 9: PROJECT MANAGEMENT
CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationTeori Pengambilan Keputusan. Week 12 Project Management
Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM
More information06IP/IM74 OPERATIONS RESEARCH
06IP/IM74 OPERATIONS RESEARCH UNIT - 6: PROJECT MANAGEMENT USING NETWORK ANALYSIS (By Dr.G.N.MOHAN BABU, Prof & HOD (I&P Engg), MCE, Hassan 573 021) LEARNING OBJECTIVES OF THE MODULE: By the end of this
More informationIntroduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES
Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and
More informationProject Management Chapter 13
Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling
More informationProject Management -- Developing the Project Plan
Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing
More informationOutline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling
Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:
More informationAppendix A Decision Support Analysis
Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated
More informationCHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM
CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities
More informationGPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationProject Management Techniques (PMT)
Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.
More informationReal-World Project Management. Chapter 15
Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,
More informationProject Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark
Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale
More informationSSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION
1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and
More information6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM
/7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business
More informationIE 102 Spring Project Management
IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and
More informationProject Management Fundamentals
Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)
More informationProgramme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001
Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique
More informationOptimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT
Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis
More informationProgram Evaluation and Review Techniques (PERT) Critical Path Method (CPM):
Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the
More information1 of 14 4/27/2009 7:45 AM
1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake
More informationConstruction Management
Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect
More informationINSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.
INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E
More informationPROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan
PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive
More informationMS Project 2007 Page 1 of 18
MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems
More informationProject planning and creating a WBS
37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and
More informationUNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2
UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle
More informationINSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.
. Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your
More informationWHY ARE PROJECTS ALWAYS LATE?
WHY ARE PROJECTS ALWAYS LATE? (what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations Introduction PM Basics FIO GID KISS (Figure it out) (Get it done) (Keep it simple,
More informationResearch Methods Outline
: Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research
More informationPOLYTECHNIC OF NAMIBIA
POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:
More informationA UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL
A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL Abstract: Crashing is a process of expediting project schedule
More informationAllocate and Level Project Resources
Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both
More informationOptimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta
Contemporary Engineering Sciences, Vol. 10, 2017, no. 7, 317-333 HIKARI Ltd, www.m-hikari.com https://doi.org/10.12988/ces.2017.712 Optimization of Rescheduling and Economy Analysis of the Implementation
More informationAppendix B: Glossary of Project Management Terms
Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances
More informationETSF01: Software Engineering Process Economy and Quality
ETSF01: Software Engineering Process Economy and Quality Dietmar Pfahl Lund University 1. Identify project objectives 0.Select project 2. Identify project infrastructure Project planning steps Review Lower
More informationCOPYRIGHTED MATERIAL. Index
Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria
More information11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?
PERT / CPM BSD Dave Novak Fall Overview Introduce Discuss what a critical path is Discuss critical path algorithm Example Source: nderson et al., 1 Quantitative Methods for Business 1 th edition some slides
More informationThe Project Times and Costs
The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step
More informationProject Management with Brief Information regarding CPM and PERT Methods
99 INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, VOLUME 9, ISSUE, JULY-8 Project Management with Brief Information regarding CPM and PERT Methods Rohan Agarwal Guide: Sheetal Patel Abstract
More informationProbabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4
Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center
More informationOutline. Project Management. Introduction. What is a Project?
Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction
More informationProject Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.
Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,
More informationPROJECT MANAGEMENT: PERT AMAT 167
PROJECT MANAGEMENT: PERT AMAT 167 PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time
More informationThe Critical Path Method
The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 2, 22 San Juan, Puerto Rico "I believe that this nation should commit
More informationCHAPTER 5. Project Scheduling Models
CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More informationVALLIAMMAI ENGINEERING COLLEGE
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017
More informationA METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT
A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT E. Newby, F. D. Fomeni, M. M. Ali and C. Musingwini Abstract The standard methodology used for estimating the cost and
More informationCost Reduction: Planning & Control. Impacting the Bottom Line
Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,
More informationProject Management and Cost Control
Project Management and Cost Control What is Project Management Build A A Done Build B B Done Build C JAN FEB MAR APR MAY JUN C Done Build D On time! Ship Unique, one-time operations designed to accomplish
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationPlan Implementation. Pushpa Lal Shakya
Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application
More informationSCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016
All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project
More informationECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING
ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING Software Project Management d_sinnig@cs.concordia.ca Department of Electrical and Computer Engineering 08-Jan-14 What is a project? Some dictionary definitions:
More informationAssistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net
More informationMnDOT use of Calendars in Primavera P6
MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be
More informationCHAPTER 5 STOCHASTIC SCHEDULING
CHPTER STOCHSTIC SCHEDULING In some situations, estimating activity duration becomes a difficult task due to ambiguity inherited in and the risks associated with some work. In such cases, the duration
More informationADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS
ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations
More informationImpacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)
Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/13) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,
More informationSystems Engineering. Engineering 101 By Virgilio Gonzalez
Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results
More informationChapter 2 The PERT/CPM Technique
Chapter The PERT/CPM Technique Abstract Completing a project on time and within budget is not an easy task. The project scheduling phase plays a central role in predicting both the time and cost aspects
More informationMODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT
Programme BA (Hons) Fashion and Textiles (Top-Up) BA (Hons) Graphic Design with Animation (Top-Up) BA (Hons) Interior Design Cohort FDI- BFT(TP)/14B/PT FDI- BGDA(TP)/14B/PT FDI-BAID/13B/FT Examinations
More informationProject Management. A Practitioner s Guide. Steven M. Bragg
Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project
More informationMINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD
International Journal of Advanced Research and Review www.ijarr.in MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD Shifat Ahmed Lecturer, Southeast
More informationu w 1.5 < 0 These two results imply that the utility function is concave.
A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that
More informationUNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018
ENG026 UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018 PROJECT MANAGEMENT MODULE NO: CPM7002 Date: 15 January 2018
More informationA Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1
A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling By Gunnar Lucko 1 1 Assistant Professor, Department of Civil Engineering, The Catholic University of America, Washington, DC 20064,
More informationProject Management. Basic Definitions: Project and Project Plan
Project Management Basic Definitions: Project and Project Plan Software Project: All technical and managerial activities required to deliver the deliverables to the client. A software project has a specific
More informationProgramme Evaluation and Review Technique
15 Programme Evaluation and Review Technique LEARNING OBJECTIVES : After studying this chapter, you will be able to : l l l l l l l l l Explain generic term network analysis and such related terms as Critical
More informationMaking sense of Schedule Risk Analysis
Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years
More informationChapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
More informationEXERCISE Draw the network diagram. a. Activity Name A B C D E F G H
XRIS. What do you mean by network analysis? xplain with counter examples.. What are the basic differences between PM and PRT analysis of project work?. State the rule of constructing the network diagram..
More informationLine Balancing S K Mondal Chapter 3
Line Balancing S K Mondal Chapter 3 Solution: J G 10 K I 7 L J, H 10 M K 6 N L, M 9 [10-Marks] 6 8 7 10 A D G J 5 B 5 6 E H L 10 9 N Work station number 1 3 4 5 6 4 10 7 4 C F I K M 6 Precedence diagram
More informationVALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke
VALUE MANAGEMENT Snehal Salunke Post Graduate Student, Civil Engg. Department, SSJCET, Asangaon, Thane -----------------------------------------------------------------------------***------------------------------------------------------------------
More informationDecision Support Tool for Project Time-Cost Trade-off
Decision Support Tool for Project Time-Cost Trade-off Fikri Dweiri Industrial Engineering and Engineering Management Department University of Sharjah Sharjah, UAE, 27272 fdweiri@sharjah.ac.ae Abstract
More informationFull Monte. Looking at your project through rose-colored glasses? Let s get real.
Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays
More informationCHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri
CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques
More informationRisk Video #1. Video 1 Recap
Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive
More informationChapter16Project Management and. Scheduling Project management
Chapter6Project Management and Scheduling Figure 6. On completion of this chapter, you should be able to identify key components of projects and the issues associated with them, and you should be able
More informationDC Program and Project Managers Meeting #2
+ Trevor Lowing Trevor.Lowing@gmail.com DC Program and Project Managers Meeting #2 Session 1: Planning projects with MS Project Session 2: Workshop: Generating Reports with MS Project and Visual Basic
More informationInternational Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:
International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, 2017 http://ijaemr.com/ ISSN: 2456-3676 CPM AND PERT COMPARISON ANALYSIS IN PROJECT PLANNING ABSTRACT Talatu Muhammad
More informationLecture 3 Project Scheduling
B10 Lecture Project Scheduling Omar El-Anwar, PhD, PMP Network alculations The purpose of conducting network calculations is to know more about the scheduling of activities: When will each activity start?
More informationPass PMP in 21 Days - ITTO Toolbox PROCESS MAP
PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project
More informationMnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationComparison between Deterministic and Stochastic Time Estimating Techniques
Comparison between Deterministic and Stochastic Time Estimating Techniques Daketima G. Briggs, Ph.D, PMP Management Department, Faculty of Business, University of Botswana ABSTRACT: This paper started