1 PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a strategy framework Explain the uses and key features of a PERT chart. Introduction A project plan can be described as a road map which shows the route for completing specific objectives and alternative ways from their start to their finish. However, it is usually the case that anyone starting to plan a project is almost always unclear about the important or relevant aspects of such a project. Subsequently, once a project need has been identified and considered feasible then a detailed strategy must be drawn up. This framework or plan is essential for implementing a project by ensuring mat what is needed is accounted for and that the correct steps are taken. The key approach to project planning is to identify and determine the planning parameters of a project. Planning parameters Correct planning involves a number of activities which have to be carefully thought out before a project can be implemented. These include: Working out the necessary resource requirements, Defining each task s objectives, and Determining a set of performance measures to evaluate progress. Project Management Diploma Course Unit Three Page 1

2 The main project parameters that need to be defined beforehand in order to complete these activities involve: Quality planning, Time planning, and Expense planning. A description of each planning parameter follows. Planning quality To plan the quality of a project is to refine the tasks broadly defined during the Project Identification phase (Lesson 1). Part of quality planning is to prioritise the order of tasks into a sequence which best fits the project s progress. It is important to remember that the quality dimension is the crucial linchpin between resources required and the time and cost dimension which is discussed further on. Quality planning outlines the standards of performance expected by project management and provides a useful guide for monitoring project progress. Key quality planning elements are: Determining the quality and types of resources needed (human and material), Setting the performance standards desired, and Verifying output quality. The latter two elements (performance standards and the verification of output quality) is performed by comparing the actual progress of the project during the Project Implementation phase with the planned progress as defined by the project schedule or the project Strategy Framework (described in the following section). The former element (determining the quality and types of resources needed) is developed within this Strategy Framework and, more specifically, within a Project Breakdown Structure. Developing a Strategy Framework A Strategy Framework breaks a project down into tasks and reduces the possibility of overlooking essential steps or sub-objectives which must be completed during a project cycle. Each task is listed as a specific activity which project management must undertake in order to complete the project. Tasks can be prioritised according to how essential they are. Categories of essentiality include: essential not so essential, non-essential, and not necessary. This does not mean that tasks which fall within the last category (not necessary) are unnecessary but rather that if budget, time or other unpredictable constraints occur and the Strategy Framework needs to be changed then these tasks can be left out altogether without any lasting disruption to the project. Project Management Diploma Course Unit Three Page 2

3 A Strategy Framework should broadly incorporate the following qualities: The goal and sub-objectives of each task, General resource commitments, and A general layout of planned schedules. Table 3A illustrates a sample Strategy Framework. A more detailed breakdown of the task schedules and requirements is often necessary when planning quality. This is accomplished by a Project Breakdown Structure. Developing a Project Breakdown Structure A Project Breakdown Structure is an analysis of the tasks listed in the Strategy Framework. Each task is broken down into sub-tasks and all the relevant activities identified. Therefore the Project Breakdown Structure goes further than the Strategy Framework by detailing the process required to complete each task of the project. In particular, the Project Breakdown Structure identifies the necessary resources and standards or output quality to be fulfilled. Useful questions to ask when developing a Project Breakdown Structure include: What is the overall goal to be accomplished? What has to be done to meet this goal? How can it be done? Table 3B illustrates a sample Project Breakdown Structure. Planning time Another critical planning parameter is the time limits set for each task so that the project is finished by a planned completion date. When planning for time, the following considerations must be taken into account: The duration or time that should be spent on each step, The earliest time when a task should start, and The latest time a task should start. However, it is difficult to finalise a specific time period for each task. Some approaches include reviewing the time periods required for other projects of a similar nature and considering their breakdowns or simply by guestimating guessing and estimating the start and completion dates! Project Management Diploma Course Unit Three Page 3

4 A time scheduler is often applied to estimate these dates. Table 3C illustrates the time scheduler. A practical method for planning time visually is by charts. Two ways to display planned task times or the project schedule are the Gantt Chart and PERT Chart. The Gantt Chart The Gantt Chart displays projects where tasks are largely independent of each other. The Gantt Chart shows the tasks in a horizontal bar chart format which is a line representation of the activities which must be completed during a project s lifespan. A Gantt Chart is created by the following steps: 1. Listing the tasks required to complete a project 2. Estimating the time needed for each task 3. Creating a table with the lifespan time of the project displayed (horizontal) and the list of tasks in order of priority (vertical) 4. Drawing a line for each task starting at the planned beginning date and ending with the expected completion date, and 5. Where task dates can be flexible, then drawing a dotted line to show the leeway for start and end dates. Table 3D illustrates a Gantt Chart. Gantt Charts are useful for simple projects when tasks are not interlinked. More complex and interdependent activities are better displayed by a PERT Chart. Project Management Diploma Course Unit Three Page 4

5 The PERT Chart The Programme Evaluation and Review Technique or PERT, as it is more commonly known, is useful for projects which involve a number of complex and interdependent tasks. PERT charts are represented by three key features: 1. Events or the launch and end dates of each activity, 2. Activities or the tasks, and 3. Non-activities or interdependent events where no activity is required. Events and activities are therefore the actions (or tasks) of a project, while non-activities symbolise non-actions and link dependencies between two actions. As with Gantt Charts, the dotted lines represent the slack time or extra time that can be afforded to complete a particular task. A PERT Chart is created by the following steps: 1. Listing the steps required to complete a project, 2. Estimating the time required for each step, 3. Linking the activities by non-activity lines, 4. Numbering each task in order of priority, 5. Drawing separate paths for steps that are undertaken at the same time, and 6. Remembering that the length of the line arrow joining activities indicates the time required A critical path can be included to show the essential steps required in order of priority. A critical path is calculated by: 1. Establishing the sequence of tasks that best fit the time and money constraints, and 2. Identifying the tasks most critical for the completion of each stage of the project. A critical path is useful in the case of limited time or scarce resources. Table 3E illustrates a PERT chart. Planning expense The costs of resources such as supplies, materials and wages, must be accounted for. Planning costs should not stop once the project is launched but should continue throughout a project s lifespan in order to keep track of expenses and avoid overspending. However, estimating a project s costs is not easy as many unexpected costs can be incurred during a project cycle. Project Management Diploma Course Unit Three Page 5

6 To calculate a budget, cost estimates should involve the items listed in the Project Breakdown Structure which typically include labour costs, material costs, travel costs, and administrative costs. An estimate of a project s costs should consider: The knowledge, expertise or skills are required (the greater the expertise, the higher the probable cost), and The types and amount of specific materials, supplies and facilities needed. These costs can be displayed in a budget worksheet. Details of how to prepare a budget are given in Lesson 6. Table 3F illustrates a budget worksheet. Delegating responsibilities Project personnel should hold clearly assigned responsibilities within the project schedule. If considering the nature of such responsibilities, some useful questions to ask are: What kind of knowledge or expertise is required for each task? Who best suites the demands of the task? Once the project has been planned by detailing its quality, costs and time, then the project can be implemented. Review The Project Planning phase is the second phase of the project cycle. Good planning depends on the usefulness of the information applied, being able to identify key start and completion dates, budgeting realistically, and maintaining a steady supply of essential resources (materials, skills and the suchlike). Planning project parameters determines a project s quality, time and costs. Planning project parameters also ensures that a clear project strategy is drawn up and a logical sequence of steps is followed by means of pre-defined tasks and activities. Once the Project planning phase is complete then a project can be implemented. Project Management Diploma Course Unit Three Page 6

7 END OF UNIT: Well done of completing your third unit of this course. The tables related to during the course are found after this page. Keep up all your good work. All that remains for you to do is move on and complete your question paper relating to this unit. Copyright Reserved Learn to listen. Opportunity could be knocking at your door very softly. Anonymous Table 3A Table 3A: Sample Strategy Framework CASE STUDY: BUILDING A HOUSE GOAL Build a house TASKS Plan design Prepare resources Construct houses ACTIVITIES Investigate idea and detail plan Investigate funding, human and material resources Draw up relevant contracts Build foundations Build exterior Build interior and finish Project Management Diploma Course Unit Three Page 7

8 Table 3B Table 3B: Sample Project Breakdown Structure CASE STUDY: BUILDING A HOUSE PROJECT DEFINITION: Build a house within three (3) months at a cost of 20,000 before moving in. Project Management Diploma Course Unit Three Page 8

9 Table 3C Table 3C: Time Scheduler The Time Scheduler The following symbols indicate certain values which need to be calculated by the formula shown below. A = The amount of time you think is needed to complete the project B = The least amount of time you think is needed to complete the project C = The most amount of time you think is needed to complete the project D = Time scheduler s amount of time needed to complete the project B+ C+ D= 6 ( 4 A) In the Time scheduler above you must being with an idea of self-estimation of how long your project can take before it s completed. Once you have established a rough figure then the following time spans should be considered: the least possible time and the most possible time your project could take. You then apply the above calculation to get the Time scheduler s suggestion of how long your project should take to be completed. Extra time should also be added to the Time scheduler s figure to provide insurance against unforeseeable events such as missing materials or a labour strike. Extra time is calculated by the following formula: C B 2 Extra time= 6 The following page illustrates how these formulae can be used. Project Management Diploma Course Unit Three Page 9

10 Table 3C Example: The proposed amount of time for a project is 90 days A = 90 days (amount of time the project manager thinks the project can be completed in) B = 60 days (the shortest amount of time the project manager thinks the project can be completed in) C = 180 days (the longest amount of time that the project manager thinks the project will take) D = Answer: The amount of time the Time Scheduler proposes What amount of time should the project manager plan for? Therefore: ( 4 90) 60 days+ 180 days+ D = days+ D = 6 ( 360 days) 600 days D = 6 D = 100 days (the project should finish after 100 days) However, extra time should be added to the proposed schedule (100 days) in case of unexpected events. 180 days 60 days Extra time= days Extra time= 2 6 Project Management Diploma Course Unit Three Page 10

11 Extra time = 20 days x 2 Extra time = 40 days Therefore, the final project schedule should be: 100 days + 40 days Time required for the project = 140 days Table 3D Table 3D: Sample Gantt Chart CASE STUDY: BUILDING A HOUSE PROJECT DEFINITION: Build a house within 140 days (see Table 3C) at the cost of 20,000 before moving in. Project steps and estimated time The time needed for each activity should be added to the list of activities. 1. Develop idea (13 days) 2. Discuss idea with architect and quantity surveyor (13 days) 3. Draw up plan (13 days) 4. Obtain funding (4 days) 5. Organise builders and materials (8 days) 6. Complete contracts and building (9 days) 7. Lay foundation (10 days) 8. Build walls (10 days) 9. Build roof (7 days) 10. Install windows (6 days) 11. Paint exterior (3 days) 12. Install electrical fixtures (5 days) 13. Install plumbing (5 days) 14. Put in doors (5 days) 15. Paint inside (3 days) 16. Cleanup and finish (26 days) The Gantt Chart is displayed on the following page. Project Management Diploma Course Unit Three Page 11

12 Table 3D Project Management Diploma Course Unit Three Page 12

13 Table 3E Table 3E: Sample PERT Chart CASE STUDY: BUILDING A HOUSE PROJECT DEFINITION: Build a house within 140 days (see Table 3C) at the cost of 20,000 before moving in. Project steps and estimated time 1. Start project ( days) 2. Plan completed (39 days) 3. Funding obtained (4 days) 4. Builders and material organised (8 days) 5. Contracts and building permit completed (9 days) 6. Foundation laid (10 days) 7. Walls built (10 days) 8. Roof built (7 days) 9. Windows installed (6 days) 10. Exterior of house painted (3 days) 11. Electrical fixtures installed (5 days) 12. Plumbing installed (5 days) 13. Doors finished (5 days) 14. Inside of house painted (3 days) 15. Cleanup completed (26 days) 16. Project finished ( days) The PERT Chart is displayed on the following page. Project Management Diploma Course Unit Three Page 13

14 Table 3E Activities (Please note that Days do not have to be included in such a diagram) Table 3F Table 3F: Sample Budget Worksheet CASE STUDY: BUILDING A HOUSE PROJECT DEFINITION: Build a house within 140 days (see Table 3C) at the cost of 20,000 before moving in. For selected steps refer to the Gantt Chart (Table 3D) or PERT Chart (Table 3E). Project Management Diploma Course Unit Three Page 14

15 PART I Project Budget: Itemised Item Step Rate/quantity Cost Labour Architect per hour 250 Quantity surveyor per hour 250 Builders per hour 4,500 Sub-Total 5,000 Materials Bricks bricks 2,200 Cement kg 1,500 Timber meters 500 Doors 14 5 doors 450 Roof tiles tiles 1,200 Piping meters 600 Electrical fixtures 12 Wiring and sockets 300 Paint 11, litres 450 Glass pieces 425 Sub-Total 7,625 General and Administrative Contracts 6 Legal fees (indirect) 350 Building permit 6 Revenue stamp 50 Stationary 1-3 Paper, pencils, etc. 120 Travel 1-16 Car allowance 300 Building equipment rental 7-16 Cement mixer, etc. 2,075 Overheads (spare money) 1-16 Extra or reserved 2,000 Sub-Total 4,895 TOTAL COST = 5, , ,895 = 17,520 (Please note that quoted prices are fictional and do not reflect real costs in any way) Project Management Diploma Course Unit Three Page 15

16 Table 3F PART II The Project Budget Schedule calculates the estimated cost of each activity or step in the project plan. Figures are divided over the applicable steps, as itemised under Step. For instance, the final Item Overheads budgets for steps 1-16 for 2,000. This means that in PART II the 2,000 is evenly split over the 16 steps and 125 is added to each step. Project Budget Schedule Activity or Step Calculation Total Cumulative Develop idea Stationary ( 40) + Overheads ( 125) Meet Architect and Quantity Surveyor + Travel ( 18.75) Stationary ( 40) + Overheads ( 125) + Rate 1 ( 125) + Rate 2 ( 125) + Travel ( 18.75) Draw up plan Stationary ( 40) + Overheads ( 125) + Rate 1 ( 125) + Rate 2 ( 125) + Travel ( 18.75) Obtain funding Overheads ( 125) + Travel ( 18.75) Organise builders and materials Complete contracts and building permit Overheads ( 125) + Travel ( 18.75) Contracts ( 350) + Building permit ( 50) + Overheads ( 125) + Travel ( 18.75) Lay foundation Builders ( 450) + Cement ( 750) + Building equipment rental ( ) + Overheads ( 125) + Travel ( 18.75) Build walls Bricks ( 2200) + Cement ( 750) + Builders ( 45) + Building Equipment rental ( ) + Overheads ( 125) + Travel ( 18.75) Build roof Roof tiles ( 1200) + Timber ( 250) + Builders ( 450) + Travel ( 18.75) + Building equipment rental ( ) + Overheads ( 125) Install windows Glass ( 425) + Builders ( 450) + Timber ( 250) + Travel ( 18.75) + Building equipment rental ( ) + Overheads ( , Project Management Diploma Course Unit Three Page 16

17 Table 3F PART II (cont.) Paint exterior Pain ( 225) + Builder ( 450) + Travel 18.75) + Building equipment rental ( ) + Overheads ( 125) Install electrical Wiring and sockets ( 300) + Builders fixtures ( 450) + Travel ( 18.75) + Building equipment rental ( ) + Overheads ( 125) Install plumbing Piping ( Builders ( 450) + Travel ( 18.75) + Building equipment rental ( ) + Overheads ( 125) Put in doors 5 doors ( 450) + Builders ( 450) + Travel ( 18.75) + Building Equipment rental ( ) + Overheads ( 125) Paint interior Paint ( 225) + Builder ( 450) + Travel ( 18.75) + Building equipment rental ( ) + Overheads ( 125) Cleanup and finish Builders ( 450) + Travel ( 18.75) + Building equipment rental ( ) + Overheads ( 125) , , , , , Project Management Diploma Course Unit Three Page 17

18 STUDENT NOTES: Please use the space below for recording what you consider to be any pertinent information or notes. You may find it helpful to refer back to it later on! Project Management Diploma Course Unit Three Page 18

19 STUDENT NOTES: Please use the space below for recording what you consider to be any pertinent information or notes. You may find it helpful to refer back to it later on! Project Management Diploma Course Unit Three Page 19

20 STUDENT NOTES: Please use the space below for recording what you consider to be any pertinent information or notes. You may find it helpful to refer back to it later on! Project Management Diploma Course Unit Three Page 20

PROJECT MANAGEMENT DIPLOMA COURSE

PROJECT MANAGEMENT DIPLOMA COURSE PROJECT MANAGEMENT DIPLOMA COURSE UNIT FOUR PROJECT IMPLEMENTATION TUTOR TALK: The Learning Outcomes for this assignment are: Evaluate how a project is prepared for implementation. Analyse the following

More information

Assistance with University Projects? Research Reports? Writing Skills? We have got you covered! www.assignmentstudio.net WhatsApp: +61-424-295050 Toll Free: 1-800-794-425 Email: contact@assignmentstudio.net

More information

CISC 322 Software Architecture

CISC 322 Software Architecture CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service

More information

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM): A Rough Guide by Andrew Scouller PROJECT MANAGEMENT Project Managers can use project management software to keep track of the

More information

Project Planning. Planning is an important step in project execution. Planning means:

Project Planning. Planning is an important step in project execution. Planning means: Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,

More information

Research Methods Outline

Research Methods Outline : Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

After complete studying this chapter, You should be able to

After complete studying this chapter, You should be able to Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Earned Value Management Tutorial Module 4: Budgeting. Prepared by:

Earned Value Management Tutorial Module 4: Budgeting. Prepared by: Earned Value Management Tutorial Module 4: Budgeting Prepared by: Module 4: Budgeting Welcome to Module 4. The objective of this module is to introduce you to Budgeting Concepts and Definitions. The Topics

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project

More information

1 of 14 4/27/2009 7:45 AM

1 of 14 4/27/2009 7:45 AM 1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake

More information

Chapter16Project Management and. Scheduling Project management

Chapter16Project Management and. Scheduling Project management Chapter6Project Management and Scheduling Figure 6. On completion of this chapter, you should be able to identify key components of projects and the issues associated with them, and you should be able

More information

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING Planning of Works Contract Form of contract by which one party undertakes to the other to perform certain work, for a price. Corresponds to the execution of a

More information

Plan Implementation. Pushpa Lal Shakya

Plan Implementation. Pushpa Lal Shakya Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

Ready to take the next step? Owning a home step by step. Talk to your Scotiabank Mortgage Specialist. Move into affordable homeownership.

Ready to take the next step? Owning a home step by step. Talk to your Scotiabank Mortgage Specialist. Move into affordable homeownership. Ready to take the next step? Owning a home step by step Talk to your Scotiabank Mortgage Specialist. Move into affordable homeownership. For answers to all of your homeownership questions, connect with

More information

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive

More information

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4 1 Department of Mathematics and Statistics, Universiti Tun Hussein Onn Malaysia 2 Center

More information

Project Management. Basic Definitions: Project and Project Plan

Project Management. Basic Definitions: Project and Project Plan Project Management Basic Definitions: Project and Project Plan Software Project: All technical and managerial activities required to deliver the deliverables to the client. A software project has a specific

More information

A Project Management Guide for Researchers

A Project Management Guide for Researchers A Project Management Guide for Researchers Prepared by: Research Grant and Contract Services January 2018 Copyright 2018 Memorial University of Newfoundland Table of Contents 1.0 Introduction... 4 2.0

More information

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce

More information

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur

More information

IE 102 Spring Project Management

IE 102 Spring Project Management IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

Impacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)

Impacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate) Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/13) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

POLYTECHNIC OF NAMIBIA

POLYTECHNIC OF NAMIBIA POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT OF MANAGEMENT PROJECT MANAGEMENT BACHELOR OF BUSINESS ADMINISTRATION 07BBMA SUBJECT CODE: PRM422S DATE: DURATION: MARKS: EXAMINERS: MODERATOR:

More information

Cost Reduction: Planning & Control. Impacting the Bottom Line

Cost Reduction: Planning & Control. Impacting the Bottom Line Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,

More information

Quality Project Management

Quality Project Management Quality Project Management By James N. Salapatas, PE, PMP www.suncam.com Copyright 2014 James N. Salapatas Page 1 of 44 Table of Contents Title Page LIST OF CHARTS 2 LIST OF FIGURES 3 ABOUT THE COURSE

More information

Cost Volume Profit Analysis

Cost Volume Profit Analysis 4 Cost Volume Profit Analysis Cost Volume Profit Analysis 4 LEARNING OUTCOMES After completing this chapter, you should be able to: explain the concept of contribution and its use in cost volume profi

More information

DC Program and Project Managers Meeting #2

DC Program and Project Managers Meeting #2 + Trevor Lowing Trevor.Lowing@gmail.com DC Program and Project Managers Meeting #2 Session 1: Planning projects with MS Project Session 2: Workshop: Generating Reports with MS Project and Visual Basic

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001 Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay August 2001 Participatory Research In Asia Introduction Programme Evaluation and Review Technique

More information

CHAPTER 9: PROJECT MANAGEMENT

CHAPTER 9: PROJECT MANAGEMENT CHAPTER 9: PROJECT MANAGEMENT The aim is to coordinate and plan a single job consisting lots of tasks between which precedence relationships exist Project planning Most popular planning tools are utilized

More information

JKUAT RESEARCH GUIDELINES Format and Guidelines for Writing a Research Proposal ANNEX IV

JKUAT RESEARCH GUIDELINES Format and Guidelines for Writing a Research Proposal ANNEX IV 36 JKUAT RESEARCH GUIDELINES Format and Guidelines for Writing a Research Proposal ANNEX IV 1.0 Cover Page The project document must bear the standard official cover page for JKUAToriginated research proposals.

More information

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2 UNIT 5 PROJECT ANALYSIS MODULE - 2 UNIT 5 PROJECT ANALYSIS Structure 5.0 Introduction 5.1 Unit Objectives 5.2 Definitions of Project and Project Management 5.3 Characteristics of a Project 5.4 Life Cycle

More information

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of

More information

Management Management

Management Management Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently

More information

Work Breakdown Structure. Managing an Efficient Construction Workflow

Work Breakdown Structure. Managing an Efficient Construction Workflow Work Breakdown Structure Managing an Efficient Construction Workflow Managing an Efficient Construction Workflow The purpose of this whitepaper is to define an operational process that creates an efficient

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

PROJECT CYCLE MANAGEMENT & LOGICAL FRAMEWORK MATRIX TRAINING CYPRIOT CIVIL SOCIETY IN ACTION V INNOVATION AND CHANGES IN EDUCATION VI

PROJECT CYCLE MANAGEMENT & LOGICAL FRAMEWORK MATRIX TRAINING CYPRIOT CIVIL SOCIETY IN ACTION V INNOVATION AND CHANGES IN EDUCATION VI PROJECT CYCLE MANAGEMENT & LOGICAL FRAMEWORK MATRIX TRAINING CYPRIOT CIVIL SOCIETY IN ACTION V INNOVATION AND CHANGES IN EDUCATION VI Objectives of the training Understand the definition of project and

More information

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:

More information

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION 1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

CHAPTER 6 PROJECT CASH FLOW

CHAPTER 6 PROJECT CASH FLOW CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter deals with project cash

More information

MANAGEMENT ACCOUNTING TECHNIQUES AS AID IN DECISION-MAKING ACN306Y

MANAGEMENT ACCOUNTING TECHNIQUES AS AID IN DECISION-MAKING ACN306Y MANAGEMENT ACCOUNTING TECHNIQUES AS AID IN DECISION-MAKING ACN306Y 1 PROGRAMME: GROUP DISCUSSION 2010 14:30-15:30 COST VOLUME PROFIT, REGRESSION, LEARNING CURVES, OPTIMISATION (CHAPTERS 5, 6, 7, 8) 15:30-15:45

More information

Teori Pengambilan Keputusan. Week 12 Project Management

Teori Pengambilan Keputusan. Week 12 Project Management Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM

More information

Chapter 11: PERT for Project Planning and Scheduling

Chapter 11: PERT for Project Planning and Scheduling Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex

More information

Scheduling Resources and Costs

Scheduling Resources and Costs CHAPTER EIGHT Scheduling Resources and Costs Copyright 2014 McGraw-Hill Education. All Rights Reserved. PowerPoint Presentation by Charlie Cook Where We Are Now 8 2 Overview of the Resource Scheduling

More information

Project Management Fundamentals

Project Management Fundamentals Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

Unemployment Role Play Activity

Unemployment Role Play Activity FEDERAL RESERVE BANK OF ST. LOUIS ECONOMIC EDUCATION Standards and Benchmarks (see page 14) Activity Description This activity is designed to demonstrate the impact that unemployment and reduced consumer

More information

JKUAT RESEARCH GUIDELINES. Format and Guidelines for Writing a Research Proposal ANNEX IV

JKUAT RESEARCH GUIDELINES. Format and Guidelines for Writing a Research Proposal ANNEX IV JKUAT RESEARCH GUIDELINES Format and Guidelines for Writing a Research Proposal ANNEX IV 1.0 Cover Page The project document must bear the standard official cover page for JKUAT-originated research proposals.

More information

Real-World Project Management. Chapter 15

Real-World Project Management. Chapter 15 Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,

More information

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis

More information

EAN.UCC Project Management Framework Handbook. Issue Version 3.0

EAN.UCC Project Management Framework Handbook. Issue Version 3.0 EAN.UCC Project Management Framework Handbook Issue Version 3.0 Document Information Document Summary Document Item Document Title (auto, from properties) File Name (auto) PMFH Issue Version 3 Template

More information

Unit 5 Slide Lectures of 04/05/06 April 2017

Unit 5 Slide Lectures of 04/05/06 April 2017 PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT SCHEDULING, PROJECT DURATION AND PROJECT COMMUNICATION PLAN (CH. 8-9) Unit 5 Slide 5.2.1 Lectures of 04/05/06 April 2017 Overview of

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

Estimate Considerations. Estimate Considerations

Estimate Considerations. Estimate Considerations Estimate Considerations Estimate Considerations Every estimate, whether it is generated in the conceptual phase of a project or at bidding time, must consider a number of issues Project Size Project Quality

More information

ENM102 Introduction to Industrial Engineering

ENM102 Introduction to Industrial Engineering Res. Asis. Dr. Gulcin Dinc Yalcin ENM102 Introduction to Industrial Engineering Project Management What is a project? https://www.itpro.co.uk/strategy/28489/project-management-everything-you-need-to-know

More information

Systems Engineering. Engineering 101 By Virgilio Gonzalez

Systems Engineering. Engineering 101 By Virgilio Gonzalez Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results

More information

DISCLAIMER. The Institute of Chartered Accountants of India

DISCLAIMER. The Institute of Chartered Accountants of India DISCLAIMER The Suggested Answers hosted in the website do not constitute the basis for evaluation of the students answers in the examination. The answers are prepared by the Faculty of the Board of Studies

More information

Construction to Permanent Loan Forms

Construction to Permanent Loan Forms Construction to Permanent Loan Forms Table of Contents Form A - Builder Acceptance Checklist and Questionnaire Form completed by builder for Builder Acceptance by the Lender. Form B - Builder s Letter

More information

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

PROJECT MANAGEMENT CPM & PERT TECHNIQUES PROJECT MANAGEMENT CPM & PERT TECHNIQUES FLOW OF PRESENTATION INTRODUCTION NETWORK PLANNING ESTIMATING TIME CPM PERT Project Management Project A project is an interrelated set of activities that has a

More information

THE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL

THE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL EXAMINATION NO. THE PUBLIC ACCOUNTANTS EXAMINATION COUNCIL OF MALAWI 2014 EXAMINATIONS ACCOUNTING TECHNICIAN PROGRAMME PAPER TC9: COSTING AND BUDGETARY CONTROL MONDAY 2 JUNE 2014 TIME ALLOWED: 3 HOURS

More information

70-632_formatted. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0

70-632_formatted.   Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0 70-632_formatted Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ Microsoft EXAM 70-632 TS:Microsoft Office Project 2007. Managing Projects Total Questions:

More information

How to Satisfy GAO Schedule Best Practices

How to Satisfy GAO Schedule Best Practices By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

NETWORK ANALYSIS QUESTION BANK

NETWORK ANALYSIS QUESTION BANK NETWORK ANALYSIS QUESTION BANK 1. Explain the terms : Total elapsed time, idle time. 2. What do you mean by dummy activity and successor activity. 3. Write four advantages of network analysis. 4. Explain

More information

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:

More information

COPYRIGHTED MATERIAL. Index

COPYRIGHTED MATERIAL. Index Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria

More information

Prince2 Foundation.exam.160q

Prince2 Foundation.exam.160q Prince2 Foundation.exam.160q Number: Prince2 Foundation Passing Score: 800 Time Limit: 120 min PRINCE2 Foundation PRINCE2 Foundation written Exam Sections 1. Volume A 2. Volume B Exam A QUESTION 1 Which

More information

Presenting and Understanding Project Management

Presenting and Understanding Project Management The best source of information and training on Aboriginal finance and management The Aboriginal Finance and Management Capacity Development Series Presenting and Understanding Project Management A Practical

More information

Development Cooperation Development Education Partnership Fair. Writing a successful co financing application

Development Cooperation Development Education Partnership Fair. Writing a successful co financing application Development Cooperation Development Education Partnership Fair Writing a successful co financing application 3 sessions to guide project preparation Session 1: Deciding on stakeholders and defining problems/issues.

More information

Project Planning Unveiled

Project Planning Unveiled Project Planning Unveiled Mark Norman Oxford University Computing Services 16 November 2006 1 An introduction? Me a project manager? You?? This isn't a technical course! Although we will have a look at

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment

More information

Mock One. Performance Management F5PM-MK1-Z16-A. Answers & Marking Scheme. Becker Study School DeVry/Becker Educational Development Corp.

Mock One. Performance Management F5PM-MK1-Z16-A. Answers & Marking Scheme. Becker Study School DeVry/Becker Educational Development Corp. Mock One Performance Management F5PM-MK-Z6-A Answers & Marking Scheme 206 DeVry/Becker Educational Development Corp. Question Answer Mark Question Answer Mark Section A Section B D 6 A 2 C 7 A 3 C 8 A

More information

Basic Introduction to Project Cycle. Management Using the. Logical Framework Approach

Basic Introduction to Project Cycle. Management Using the. Logical Framework Approach Basic Introduction to Project Cycle Management Using the Logical Framework Approach Developed and Presented by: Umhlaba Development Services Umhlaba Development Services Noswal Hall, Braamfontein, Johannesburg,

More information

Marginal and. this chapter covers...

Marginal and. this chapter covers... 7 Marginal and absorption costing this chapter covers... This chapter focuses on the costing methods of marginal and absorption costing and compares the profit made by a business under each method. The

More information

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri CHAPTER SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT UWB10202 Effective Communication by Norazmi Danuri (norazmi@uthm.edu.my) Introduction Planning & Scheduling Principles Techniques

More information

Code No. : Sub. Code : R 3 BA 52/ B 3 BA 52

Code No. : Sub. Code : R 3 BA 52/ B 3 BA 52 (8 pages) Reg. No. :... Sub. Code : R 3 BA 52/ B 3 BA 52 B.B.A. (CBCS) DEGREE EXAMINATION, NOVEMBER 2014. Fifth Semester Business Administration Main MANAGEMENT ACCOUNTING (For those who joined in July

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

Technical note: Project cost contingency

Technical note: Project cost contingency Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Technical note: Project cost contingency Project cost contingency setting is an important

More information

CHAPTER 5. Project Scheduling Models

CHAPTER 5. Project Scheduling Models CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project

More information

Working With The Numbers & Thinking Outside The Numbers

Working With The Numbers & Thinking Outside The Numbers Business, Investor & SMSF Specialists Working With The Numbers & Thinking Outside The Numbers DISCLAIMER GENERAL INFORMATION ONLY DOES NOT CONSTITUTE ADVICE DISCLAIMER TODAY S PRESENTATION PLEASE CONSULT

More information

Part 1 Examination Paper 1.2. Section A 10 C 11 C 2 A 13 C 1 B 15 C 6 C 17 B 18 C 9 D 20 C 21 C 22 D 23 D 24 C 25 C

Part 1 Examination Paper 1.2. Section A 10 C 11 C 2 A 13 C 1 B 15 C 6 C 17 B 18 C 9 D 20 C 21 C 22 D 23 D 24 C 25 C Answers Part 1 Examination Paper 1.2 Financial Information for Management June 2007 Answers Section A 1 B 2 A 3 A 4 A 5 D 6 C 7 B 8 C 9 D 10 C 11 C 12 A 13 C 14 B 15 C 16 C 17 B 18 C 19 D 20 C 21 C 22

More information