1 STAFF REPORT MEETING DATE: June 9, 2015 TO: City Council FROM: Petr Skala, Engineer II PRESENTER: Russ Thompson, Public Works Director 922 Machin Avenue Novato, CA (415) FAX (415) SUBJECT: AWARD CONSTRUCTION CONTRACT FOR NAVE DRIVE MULTI USE PATH (MUP) AND ADOPT A RESOLUTION AMENDING CIP BUDGET REQUEST Consider 1.) Awarding the construction contract for Nave Drive Multi Use Path, CIP Project No for the base bid plus additive alternate bid item 2A (Substitute Wooden Split-Rail Fence) in the total amount of $617, to Maggiora & Ghilotti, Inc. as the lowest responsible bidder submitting the lowest responsive bid and 2.) Adopting a resolution amending the CIP Budget in the amount of $222,370 for the Nave Drive Multi Use Path, CIP Project No RECOMMENDATION Award construction contract and adopt resolution. DISCUSSION This proposed project will construct a 1,590 lineal feet class I multi-use path along Nave Drive between Main Gate Road and Bolling Drive and a new left turn pocket in southbound Nave Drive. The work to be done includes construction of a retaining wall, pathway lighting, bioretention facility, wooden split-rail fence between the path and street, upgrade to shoulder parking, removal and construction of concrete curb, gutter and sidewalk, removal and replacement of (9) trees, hot mix asphalt road widening, roadway signs installation and pavement striping and markings as shown on the Nave Drive Multi Use Path, CIP project No plans. On April 14, 2015 City Council authorized the advertising for construction bids and staff subsequently advertised the project for public bids. A public bid opening was held on May 19, 2015 and a total of three (3) bids were received. After examination of the same, Maggiora & Ghilotti, Inc. was determined to be the lowest responsible bidder, with a bid amount of $573, The low bid is higher than the engineer s estimate of $486, Received bids are summarized below: cc15_
2 1 2 3 BIDDER Maggiora & Ghilotti, Inc. Team Ghilotti, Inc. W.R. Forde Associates LOCATION BASE BID ($) ALT - 1A ($) ALT - 2A ($) RECOMMENDED AWARD (BASE BID + ALT-2A) San Rafael, CA 573, , , $617, Petaluma, CA 601, , , Richmond, CA 654, , , The attached Bid Abstract shows the bid details. Two alternate bid items were considered for this project. Alternate Bid Item 1A Substitute Solar LED Lighting consists of substituting solar powered luminaires in lieu of the electrically powered luminaires. After a detailed evaluation it was determined that substituting the proposed solar powered LED luminaires for the specified base bid lighting would not be cost effective. Alternate Bid Item 2A Substitute Wooden Split-Rail Fence consists of substituting wooden split rail fencing in lieu of the Landscape Berms. Staff is recommending inclusion of the alternate bid item 2A in the contract. Additional cost for wooden split-rail fence will be offset by eliminating future maintenance needs including the cost of irrigation. The low bidder was determined by the base bid only and not the base bid with Alternates. Staff reviewed the received bids and although the low bid exceeds the engineer s estimate, does not find the low bid to be unreasonably high, and is of the opinion that rebidding the project would not yield a lower bid. Due to the time limit on use of the BAAQMD Grant funds, and the potential cost and uncertainty of rebidding, staff recommends that the City Council allocate additional local funds to the project and award the construction contract to Maggiora & Ghilotti Inc. ENVIRONMENTAL ASSESSMENT This project has been determined to be Categorically Exempt from CEQA as detailed in the staff report presented at the April 14, 2015 City Council meeting. FISCAL IMPACT The Nave Drive Multi Use Path (CIP Project No ) is funded by BAAQMD Grant funds (283), and Gas Tax (272) funds. This project is included in the City of Novato Adopted Capital Improvement Program Budget for 2014/2015. There are insufficient funds in the Construction (430) account to award a contract based on the low bid, inclusive of the alternate bid item 2A and allowing for the standard 10% contingency allowance. Current accounting shows that the Project Development (410) account is $12,000 underfunded, compared with expended funds. cc15_
3 Adoption of a budget resolution is required to cover the Project Development (410) increase and the anticipated Construction (430) cost based on low bid and allowing for 10% contingency. There are no available supplemental funds from the granting agency, and without transferring already allocated local funds designated for pavement rehabilitation there are limited gap fund sources. Staff is proposing an allocation of General Fund (101) in the total amount of $222,370 to fill the funding gap. The specific allocations are as follows. 1. Allocate General Fund (101) in the amount of $12,000 to Project Development (410) account of CIP Project No , Nave Drive Multi-Use Path and 2. Allocate General Fund (101) in the amount of $210,370 to Construction (430) account of CIP Project No , Nave Drive Multi-Use Path. ALTERNATIVES 1. Take no action at this time; direct staff as to action requested. 2. Award base bid only. 3. Award base bid plus Alternate Bid Item 1A Substitute Solar LED Lighting. 4. Award base bid plus Alternate Bid Item 2A Substitute Wooden Split-Rail Fence. 5. Award base bid plus Alternate Bid Item 1A and Alternate Bid Item 2A. ATTACHMENTS 1. Bid Abstract 2. Resolution 3. Vicinity Map 4. CIP Budget Excerpt cc15_
4 CITY OF NOVATO ABSTRACT OF BIDS AND AWARD OF CONTRACT PROJECT NAME : Nave Drive Multi Use Path (MUP) BID NO. : PROJECT NO. : CIP DATE : 19-May-2015 BID OPENING : 2:00 pm BIDDERS Engineer's Estimate Maggiora & Ghilotti, Inc Team Ghilotti, Inc W.R. Forde Associates Item TOTAL BID $486, $573, $601, $654, No. DESCRIPTION Unit Qty Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount 1 Temporary Water Pollution Control ( ) LS 1 $ 5, $ 5, $ 1, $ 1, $ 2, $ 2, $ 10, $ 10, Removal of Existing Portland Cement Concrete "LF" ( ) LF 690 $ 6.00 $ 4, $ 7.50 $ 5, $ $ 6, $ $ 6, Removal of Existing Portland Cement Concrete "SF" ( ) SF 600 $ 5.00 $ 3, $ 4.75 $ 2, $ 2.00 $ 1, $ 8.00 $ 4, Removal of Existing Asphalt Concrete ( ) SF 2,200 $ 4.00 $ 8, $ 2.25 $ 4, $ 2.00 $ 4, $ 2.00 $ 4, Temporary Removal and Replacement of Bus Shelter ( ) LS 1 $ 2, $ 2, $ 3, $ 3, $ 5, $ 5, $ 6, $ 6, Removal of Existing Pavement Markings and Striping ( ) LS 1 $ 1, $ 1, $ $ $ $ $ $ Construction Area Signs ( ) LS 1 $ 1, $ 1, $ 1, $ 1, $ 2, $ 2, $ 4, $ 4, Maintaining Traffic ( ) LS 1 $ 5, $ 5, $ 3, $ 3, $ 1, $ 1, $ 15, $ 15, Traffic Control System for Lane Closure ( ) LS 1 $ 10, $ 10, $ 2, $ 2, $ 2, $ 2, $ 25, $ 25, Clearing and Grubbing ( ) LS 1 $ 15, $ 15, $ 14, $ 14, $ 25, $ 25, $ 30, $ 30, Tree Removal ( ) EACH 9 $ $ 7, $ $ 4, $ $ 5, $ $ 4, Tree Stump Removal ( ) EACH 1 $ $ $ $ $ $ $ $ Common Excavation (Cut and Fill) ( ) CY 500 $ $ 10, $ $ 42, $ $ 50, $ $ 32, Landscape - Berm ( ) LF 955 $ $ 14, $ $ 11, $ $ 19, $ $ 14, Final Stabilization - Hydroseeding ( ) LS 1 $ 5, $ 5, $ 2, $ 2, $ 2, $ 2, $ 2, $ 2, Class 2 Aggregate Base ( ) TON 530 $ $ 31, $ $ 31, $ $ 59, $ $ 18, Class 2 Aggregate Base - Shoulder Parking ( ) TON 60 $ $ 3, $ $ 9, $ $ 12, $ $ 2, Concrete Sidewalk ( ) SF 332 $ $ 5, $ $ 4, $ $ 3, $ $ 3, Type "A" Curb ( ) LF 41 $ $ 2, $ $ 2, $ $ 1, $ $ 1, Type "E" Curb ( ) LF 555 $ $ 30, $ $ 16, $ $ 13, $ $ 19, Concrete Driveway Approach ( ) SF 360 $ $ 7, $ $ 5, $ $ 9, $ $ 5, Concrete Bus Pad ( ) SF 106 $ $ 2, $ $ 7, $ $ 5, $ $ 2, Remove and Construct Concrete Stairs ( ) LS 1 $ 7, $ 7, $ 5, $ 5, $ 9, $ 9, $ 11, $ 11, Structural Excavation (Retaining Wall) ( ) CY 230 $ $ 8, $ $ 31, $ $ 14, $ $ 14, Structural Concrete (Retaining Wall - Footing) ( ) CY 30 $ $ 19, $ 1, $ 30, $ $ 20, $ 1, $ 30, Page 41 of 2
5 CITY OF NOVATO ABSTRACT OF BIDS AND AWARD OF CONTRACT PROJECT NAME : Nave Drive Multi Use Path (MUP) BID NO. : PROJECT NO. : CIP DATE : 19-May-2015 BID OPENING : 2:00 pm BIDDERS Engineer's Estimate Maggiora & Ghilotti, Inc Team Ghilotti, Inc W.R. Forde Associates Item TOTAL BID $486, $573, $601, $654, No. DESCRIPTION Unit Qty Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount 26 Structural Concrete (Retaining Wall) ( ) CY 40 $ $ 32, $ 1, $ 54, $ 1, $ 56, $ 2, $ 104, Pervious Backfill (Retaining Wall) ( ) CY 130 $ $ 3, $ $ 23, $ $ 16, $ $ 11, Bioretention Facility ( ) LS 1 $ 25, $ 25, $ 20, $ 20, $ 20, $ 20, $ 35, $ 35, Self-Retaining Area ( ) LS 1 $ 7, $ 7, $ 10, $ 10, $ 12, $ 12, $ 10, $ 10, Road Widening Deep Lift HMA ( ) TON 200 $ $ 40, $ $ 50, $ $ 38, $ $ 60, HMA Base Course ( ) TON 55 $ $ 9, $ $ 8, $ $ 10, $ $ 11, Plane Existing AC Pavement 0.15' ( ) SY 390 $ 7.00 $ 2, $ $ 8, $ $ 5, $ $ 5, Pavement Reinforcing Fabric ( ) SY 440 $ 4.00 $ 1, $ 8.50 $ 3, $ 8.50 $ 3, $ 5.00 $ 2, HMA Surface Course (0.15') ( ) TON 180 $ $ 23, $ $ 36, $ $ 27, $ $ 27, Thermoplastic Pavement Stripe Detail 22 ( ) LF 385 $ 2.00 $ $ 1.80 $ $ 1.75 $ $ 2.00 $ Thermoplastic Pavement Stripe Detail 29 ( ) LF 530 $ 3.50 $ 1, $ 3.50 $ 1, $ 3.50 $ 1, $ 3.50 $ 1, Thermoplastic Pavement Stripe Detail 38 ( ) LF 330 $ 2.00 $ $ 1.50 $ $ 1.50 $ $ 1.50 $ Thermoplastic Pavement Stripe Detail 39 ( ) LF 1,700 $ 1.25 $ 2, $ 0.75 $ 1, $ 0.75 $ 1, $ 0.75 $ 1, Thermoplastic Pavement Stripe Detail 39A ( ) LF 144 $ 1.25 $ $ 0.50 $ $ 0.45 $ $ 0.50 $ Thermoplastic Pavement Marking - White ( ) SF 90 $ 4.00 $ $ 4.00 $ $ 4.00 $ $ 4.00 $ MUP Marking - 4" Retroreflective Yellow Stripe ( ) LF 320 $ 2.00 $ $ 1.25 $ $ 1.25 $ $ 1.35 $ Roadway Signs ( ) EACH 10 $ $ 3, $ $ 2, $ $ 2, $ $ 2, Chain Link Railing ( ) LF 125 $ $ 3, $ $ 6, $ $ 11, $ $ 6, Fixed Bollard ( ) EACH 11 $ $ 4, $ $ 3, $ $ 6, $ $ 3, Removable Bollard ( ) EACH 6 $ $ 3, $ 1, $ 7, $ 1, $ 8, $ 1, $ 7, Replacement Tree - 15 Gallon ( ) EACH 9 $ $ 4, $ $ 7, $ $ 4, $ $ 7, Construct MUP Lighting Trench (10-3) LF 1,590 $ $ 23, $ $ 31, $ $ 23, $ $ 31, MUP Lighting (10-3) EACH 21 $ 3, $ 69, $ 2, $ 42, $ 2, $ 60, $ 2, $ 42, Extra Work Allowance ( ) LS 1 $ 10, $ 10, $ 10, $ 10, $ 10, $ 10, $ 10, $ 10, TOTAL BASE BID $486, $573, $601, $654, Alternate Bid Items 1A Substitute Solar LED Lighting ( ) EACH $6, , $95, , $62, , $84, A Substitute Wooden Split-Rail Fence ( ) LF $31, $43, $53, $38, RECOMMENDATION : OTHER INFORMATION : Award contract to Maggiora Ghilotti, Inc. Verified By : Julian Skinner Submitted By : Petr Skala as the lowest responsible bidder for the Base Bid in the amount of $573, Page 2 of 2
6 CITY COUNCIL OF THE CITY OF NOVATO RESOLUTION NO. RESOLUTION AMENDING BUDGET RESOLUTION ALLOCATING GENERAL FUND (101) IN TOTAL AMOUNT OF $222,370 TO NAVE DRIVE MULTI USE PATH, CIP PROJECT NO WHEREAS, the City Council of the City of Novato has adopted a final Capital Improvement Program (CIP) budget for fiscal Year 2014/2015; and WHEREAS, the Project Development (410) account for CIP project , Nave Drive Multi Use Path is underfunded compared with expended funds; and WHEREAS, there are insufficient funds in the Construction (430) account for CIP project , Nave Drive Multi Use Path to award a contract based on the apparent low bid and allowing for 10% contingency; and WHEREAS, adoption of a budget resolution is required to cover the Project Development (410) increase and anticipated Construction (430) cost based on low bid and allowing for 10% contingency; and WHEREAS, there is funding available as an allocation of General Fund (101); and WHEREAS, it is necessary to revise Resolution to amend the budget amounts for CIP Project No , Nave Drive Multi Use Path. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Novato hereby approves this budget amendment for CIP project , Nave Drive Multi Use Path and providing for the revised appropriations as follows: 1. Allocate General Fund (101) in the amount of $12,000 to Project Development (410) account of CIP Project No , Nave Drive Multi-Use Path and 2. Allocate General Fund (101) in the amount of $210,370 to Construction (430) account of CIP Project No , Nave Drive Multi-Use Path. * * * * * * I HEREBY CERTIFY that the foregoing resolution was duly and regularly adopted by the City Council of the City of Novato, Marin County, California, at a meeting thereof, held on the 9 th day of June, 2015, by the following vote, to wit: AYES: NOES: ABSTAIN: ABSENT: Councilmembers Councilmembers Councilmembers Councilmembers res
7 City Clerk of the City of Novato Approved as to form: City Attorney of the City of Novato res
8 GRAPHIC SCALE PROJECT LOCATION SCALE: 1:24,000 PROJECT NAME: Nave Multi Use Path; CIP No: PROJECT LOCATION: Nave Drive between Main Gate Road and Bolling Drive. LOCATION MAP 8
9 Nave Drive Multi Use Path Project No.: R1 Base Code: 431 Funded Project Objective: To improve Nave Drive from Main Gate Road to Bolling Drive to include a multi-use path along the east side and a dedicated left turn lane for southbound traffic entering the Hamilton School/ Gym parking lot. Project Description and Background: In 2013 staff started receiving requests from residents in the Hamilton area for improved pedestrian facilities along Nave Drive in the vicinity of the Hamilton Meadows school and new gym. Staff applied for and recieved two consecutive rounds of Transportation for Clean Air (TFCA) grant through the Bay Area Air Quality Management District, that provide the majority of the funding. Since the filing of the first TFCA grant, an additional improvement (left turn lane) has been identified as a benefit, increasing the proposed cost. Basis for Cost Estimate: The costs are based on the engineer's estimate, which is based on preliminary plans only. Basis for Schedule: Construction is tentatively scheduled to take place in summer of 2015; The first round of TFCA funding has a November 2015 deadline for expenditure. Revenue Considerations: being funded with Gas Tax. Partial funding has been secured through the TFCA grant, and the gap closure is Sub Prior to Project Expenditure Objects 14/15 14/15 15/16 16/17 17/18 18/19 Total Proj Develop ,000 70,000 Construction , ,883 Construction Mgt ,000 47,000 TOTAL 585, ,883 Sub Prior to Funding Source Objects 14/15 14/15 15/16 16/17 17/18 18/19 Total Gas Tax (272) ,000 29,000 Gas Tax (272) ,050 65,050 Gas Tax (272) ,554 12,554 Grant BAAQMD (283) ,000 41,000 Grant BAAQMD (283) , ,833 Grant BAAQMD (283) ,446 34,446 TOTAL 0 585, ,883 CARRYOVER 0 PROPOSED E-41 10/20/2014 9
Both bids are substantially higher than the engineer s estimate of $362, The attached Bid Abstract shows the bid details.
STAFF REPORT MEETING DATE: September 12, 2017 TO: FROM: City Council David Dammuller, Senior Engineer Chris Blunk, Deputy Public Works Director 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/
More informationPRESENTER: Christopher J. Blunk, Deputy Public Works Director / City Engineer
G-7 STAFF REPORT MEETING DATE: November 27, 2018 TO: FROM: City Council Petr Skala, Associate Engineer 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/ 899-8213 www.novato.org PRESENTER: Christopher
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 4.g Meeting Date: March 6, 2017 Department: Public Works SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Director of Public Works TOPIC: ADA-DOJ CURB RAMPS 2016-2017 City
More informationPRESENTER: Christopher Blunk, Deputy Public Works Director/City Engineer
G-6 STAFF REPORT MEETING DATE: June 12, 2018 TO: FROM: City Council Petr Skala, Assistant Engineer 922 Machin Avenue Novato, CA 94945 (415) 899-8900 FAX (415) 899-8213 www.novato.org PRESENTER: Christopher
More informationPetr Skala, Engineer II Christopher J. Blunk, Deputy Public Works Director/City Engineer
STAFF REPORT MEETING DATE: March 28, 2017 TO: FROM: City Council Petr Skala, Engineer II Christopher J. Blunk, Deputy Public Works Director/City Engineer 922 Machin Avenue Novato, CA 94945 415/ 899-8900
More informationBIDDER'S PROPOSAL TO THE HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
Bidders submitting proposals shall be very careful to follow all requirements in connection therewith. A checklist has been attached for guidance in complying with all phases of the bid process and project.
More informationPRESENTER: Chris Blunk, Deputy Public Works Director/City Engineer
STAFF REPORT MEETING DATE: July 11, 2017 TO: City Council FROM: Chris Blunk, Deputy Public Works Director/City Engineer PRESENTER: Chris Blunk, Deputy Public Works Director/City Engineer 922 Machin Avenue
More informationMVMCC CAPITAL IMPROVEMENT PROGRAM (CIP) UPDATE AND ADOPTING A RESOLUTION APPROVING A MVMCC CAPITAL BUDGET ALLOCATION AMENDMENT
STAFF REPORT MEETING DATE: October 20, 2015 TO: FROM: City Council Cathy Capriola, Assistant City Manager Matt Greenberg, Park General Manager Tony Williams, Senior Civil Engineer 922 Machin Avenue Novato,
More informationADDENDUM NO. 1 PUBLIC WORKS CONSTRUCTION PROJECT NO
ADDENDUM NO. 1 10 th STREET WEST GAP CLOSURE This addendum forms a part of the contract documents for the above identified project and modifies the original specifications, plans, and contract documents
More informationHeather Hafer, Senior Management Analyst Kate Whan, Public Works Administrative Manager SAN PABLO SUBDIVISION LANDSCAPE & LIGHTING DISTRICT A-03
I-10 STAFF REPORT MEETING DATE: May 22, 2018 TO: City Council FROM: Heather Hafer, Senior Management Analyst Kate Whan, Public Works Administrative Manager 922 Machin Avenue Novato, CA 94945 (415) 899-8900
More informationCrushed Surfacing Base Course, per ton. Pages 8-8, Special Provisions Section , Materials. This Section is supplemented with the following:
Crushed Surfacing Base Course, per ton. The unit contract price per ton for Crushed Surfacing Top Course and Crushed Surfacing Base Course shall include the cost for all labor, materials, equipment and
More information69889/AV/lm. Recipients of C-TRAN ITB # Fourth Plain BRT Maintenance Facility Expansion. DATE: June 25, SUBJECT: Addendum #11
69889/AV/lm TO: Recipients of C-TRAN ITB #2015-04 Fourth Plain BRT Maintenance Facility Expansion DATE: June 25, 2015 SUBJECT: Addendum #11 C-TRAN has revised the following sections of the Invitation to
More informationDORAN STREET AND BROADWAY/BRAZIL SAFETY AND ACCESS PROJECT PROJECT STUDY REPORT (EQUIVALENT) Appendix I Cost Estimates
DORAN STREET AND BROADWAY/BRAZIL SAFETY AND ACCESS PROJECT PROJECT STUDY REPORT (EQUIVALENT) Appendix I Cost Estimates (Alternative 1 - Doran Overpass) PROJECT DESCRIPTION Limits Doran Street from Commercial
More informationCITY OF YUBA CITY STATE OF CALIFORNIA PUBLIC WORKS DEPARTMENT NOTICE TO CONTRACTORS
CITY OF YUBA CITY STATE OF CALIFORNIA PUBLIC WORKS DEPARTMENT NOTICE TO CONTRACTORS Sealed proposals will be received at the City Clerk s Office, City of Yuba City, located at City Hall, 1201 Civic Center
More informationJANUARY 18, Reference Specifications, Attachment to Form 96 (BID FORM), Bid Proposal: Respectfully submitted,
ADDENDUM NO. 3 TO THE PLANS AND SPECIFICATIONS for STREET AND STORM SEWER IMPROVEMENTS ON HANCOCK AND WASHINGTON STREETS for the FRENCH LICK REDEVELOPMENT COMMISSION ORANGE COUNTY, INDIANA MEI PROJECT
More informationDOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER ADVERTISEMENT FOR BIDS FOR THE MOFFETT DRIVE ( CIP 70224)
AGENDA REPORT Agenda Item 9 Reviewed City Manager Finance Director N/ A MEETING DATE: APRIL 21, 2015 TO: JEFFREY C. PARKER, CITY MANAGER FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER
More informationCITY OF CHINO ENGINEERING COST ESTIMATE. Quantity Unit Item Unit Total Cost Price Per Item. LS Traffic Control (5% of construction cost) 5% $
RESOLUTION NO 2015078 STREETS LS Traffic Control (5% of construction cost) 5% $ LS Clear & Grub Site (5% of construction cost) 5% $ EA Tree Removal $ 800.00 $ CY Concrete Removal $ 300.00 $ CY AC Pavement
More informationCITY OF DEERFIELD BEACH Request for City Commission Agenda
Item: CITY OF DEERFIELD BEACH Request for City Commission Agenda Agenda Date Requested: 7/10/2012 Contact Person: Charles DaBrusco, P.E., Director of Environmental Services Description: Award of contract
More informationEngineer's Preliminary Estimate - 100% Submittal
EA 284700 1 070010 PROGRESS SCHEDULE (CRITICAL PATH) LS 1 $ 15,000 $ 15,000 2 071325 TEMPORARY FENCE (TYPE ESA) M 1250 $ 10 $ 12,500 3 074019 PREPARE STORM WATER POLLUTION PREVENTION PLAN LS 1 $ 7,000
More informationRock Chalk Park - Infrastructure Report. July 2013
Rock Chalk Park Infrastructure Report July 2013 The following report is the first monthly report for the construction of infrastructure at Rock Chalk Park. The format follows the sections outlined in the
More informationBID TABULATION REPORT ABRAM STREET (SH CITY LIMITS) PROJECT No. PWST09016 BID OPENED : April 22, 2014 at 1:30 p.m.
PAVING IMPROVEMENTS 101 Mobilization and Bonds, LS 1 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 $ 225,000.00 102 Right-of-way Preparation LS 1 $ 365,500.00
More informationENGINEER'S ESTIMATE OF PROBABLE COST CCTA I 680 NORTH EXPRESS LANE PROJECT (SOUTHBOUND ONLY) EA 04 4H % PS&E Submittal
Page: 1 of 8 (F) Description 1 050000A CONTRACTOR STAKING LS 1 $ $ 2 070030 LEAD COMPLIANCE PLAN LS 1 $ $ 3 080000A POTHOLING LS 1 $ 50,000.00 $ 50,000.00 4 080050 PROGRESS SCHEDULE (CRITICAL PATH METHOD)
More informationRECEIVE A REPORT AND APPROVE PROPOSED PUBLIC ENGAGEMENT POLICIES AND PRACTICES FOR THE PUBLIC
J-17 STAFF REPORT MEETING DATE: October 24, 2017 TO: City Council FROM: Russ Thompson, Public Works Director PRESENTER: Russ Thompson, Public Works Director SUBJECT: RECEIVE A REPORT AND APPROVE PROPOSED
More informationCarla Hansen, Management Analyst II Peggy Flynn, Public Communications Coordinator Cathy Capriola, Assistant City Manager
STAFF REPORT MEETING DATE: October 27, 2015 TO: FROM: City Council Carla Hansen, Management Analyst II Peggy Flynn, Public Communications Coordinator Cathy Capriola, Assistant City Manager 922 Machin Avenue
More informationDepartment of Public Works Engineering
Department of Public Works Engineering DATE: January 27, 2016 TO: Honorable Chairman and Public Utility Authority Members FROM: Cynthia M. Herrera, MMC, Interim Executive Director/ City Clerk BY: Nathan
More informationRANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO Item Description Est. Qty. Units Unit Price
2. BID SCHEDULE RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO. 7046 To the Honorable Mayor and City Council of the City of Hesperia: Schedule of prices to construct the Ranchero Road and BNSF
More informationReviax Constracting Corp. DeSantis Construction
Denise Piszkowski, Q.P.A., Purchasing Agent Bid Results for: 2016-B08 Reconstrucion of Preston Drive Submitted By: JTG Construction Black Rock Enterprises Top Line Construction Reviax Constracting Corp.
More informationCITY ENGINEER'S ESTIMATE ITEM DESCRIPTION UNIT QTY. UNIT PRICE ITEM TOTAL UNIT PRICE ITEM TOTAL UNIT PRICE ITEM TOTAL REMOVALS
1 2 3 4 5 6 MOBILIZATION per the General Requirements, Sections 01292 and 01721 ALLOWANCE for Differing Site Condition per the General Requirements, Sections 01212 and 01253 ALLOWANCE for Participating
More informationFALCON FIELD RELOCATE PARALLEL TAXIWAY 'E' (B II SM.) ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST
FALCON FIELD RELOCATE PARALLEL TAXIWAY 'E' (B II SM.) 1 Contractor Quality Control 1 LS $50,000.00 $50,000.00 2 Mobilization 1 LS $100,000.00 $100,000.00 3 Location of Underground Utilities 1 LS $25,000.00
More information2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE IV SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD BID PROPOSAL
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationREVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO OF THE CITY OF SAN JACINTO
REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO. 2003-1 OF THE CITY OF SAN JACINTO December 11, 2003 REVISED ENGINEER'S REPORT ASSESSMENT DISTRICT NO. 2003-1 CITY OF SAN JACINTO Prepared for CITY OF SAN
More information19th & Barker Roundabout / Waterline Improvement Project No. 56-CP12-901(C) Cost Breakdown
19th & Barker Roundabout / Waterline Improvement Project No. 56CP12901(C) Cost Breakdown Engineering Fees: Original Contract $ 71,861.00 Additional Services $ 8,744.00 Waterline Contract $ 17,500.00 TOTAL
More informationSUBDIVISION IMPROVEMENTS AGREEMENT
SUBDIVISION IMPROVEMENTS AGREEMENT THIS AGREEMENT, made between GLEN DEVELOPMENT COMPANY, hereinafter called the "Subdivider," and El Paso County by and through the Board of County Commissioners of El
More information2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction)
2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) Project Information The Glen at Widefield Filing No. 9 PDD File: SF-185 9/25/2018 Project Name Section 1 - Grading and Erosion
More informationBID TABULATION BID REQUEST NO
BID TABULATION BID REQUEST NO. 13-1046 1 LOWEST RESPONSIVE BIDDER Dakota Contracting Bidder: Corporation D & G Concrete Bidder: Construction, Inc. Carl V. Carlson Bidder: Company Address: 431 NORTH PHILLIPS
More informationNOVATO GENERAL PLAN 2035 ENVIRONMENTAL IMPACT REPORT CONSULTANT SERVICES AGREEMENT AMENDMENT
G-3 STAFF REPORT MEETING DATE: September 26, 2017 TO: FROM: City Council Steve Marshall, Planning Manager 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/ 899-8213 www.novato.org SUBJECT: NOVATO
More informationCONSULTANT SERVICES AGREEMENT AMENDMENT NO. 2 WITH RINCON CONSULTANTS FOR WORK ON THE NOVATO GENERAL PLAN 2035 ENVIRONMENTAL IMPACT REPORT
STAFF REPORT MEETING DATE: January 9, 2018 TO: City Council FROM: Steve Marshall, Planning Manager PRESENTER: N/A 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/ 899-8213 www.novato.org SUBJECT:
More information2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD
AGENDA ITEM NO. 2. fl Concord REPORT TO MAYOR AND COUNCIL/AGENCY BOARD TO THE HONORABLE MAYOR AND COUNCIL: DATE: June 22, 2009 Subiect: ADOPTING RESOLUTION NO. 09-53, APPROVING THE CITY'S REVISED PROPOSITION
More informationCITY OF NEWCASTLE COUNCIL MEETING CITY HALL COUNCIL CHAMBERS NEWCASTLE WAY, SUITE 200 DECEMBER 18, CALL TO ORDER
CITY OF NEWCASTLE COUNCIL MEETING CITY HALL COUNCIL CHAMBERS 12835 NEWCASTLE WAY, SUITE 200 DECEMBER 18, 2012 SPECIAL MEETING 12:00 P.M. 1. CALL TO ORDER 2. GENERAL BUSINESS a. AB 12 077 Resolution Authorizing
More information2012 WATER & SEWER ALLEY CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD
BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and
More informationNE WEST KINGSTON ROAD CULVERT REPLACEMENT
NE WEST KINGSTON ROAD CULVERT REPLACEMENT KITSAP COUNTY MILE POST 1.28 TO 1.44 PUBLIC WORKS BID TABULATION SECTION PREPARED: BLB LENGTH: 0.16 Mile REVISED: DATE: March 7, 2017 SCHEDULE A - ROADWAY IMPROVEMENTS
More informationFor Reference Only - Not for the Purpose of Bidding BP-1. Azucena Street 30-Inch Sewer Project Job No Solicitation No.
Job 11-4518 Solicitation B-12-059-DD PROPOSAL of BID PROPOSAL, a corporation a partnership consisting of an individual doing business as TO THE SAN ANTONIO WATER STEM: Pursuant to Instructions Invitation
More informationAddendum 1 13 TH Street Streetscape. September 1, 2017
Addendum 1 13 TH Street Streetscape September 1, 2017 ACKNOWLEDGEMENT OF RECEIPT OF THIS ADDENDUM IS NOT REQUIRED. ADDENDUMS ARE POSTED ON THE CITY WEB SITE AND PROPOSER IS RESPONSIBLE TO CHECK THIS SITE
More informationAppendix B Example Project Designs and Engineers Opinion of Costs
Appendix B Example Project Designs and Engineers Opinion of Costs 32 nd Street from E. 2 nd to Main Avenue CR 251 and CR 250 9 th Street Sidewalk Improvements 15 th Street Improvements Intermodal Facility
More informationSUTTER BUTTER FLOOD CONTROL AGENCY FEATHER RIVER WEST LEVEE PROJECT PROJECT C, CONTRACT NO C BID TABULATION
Bid Schedule A - Feather River West Levee Project C Improvements No. Item Description Quantity Unit Nordic/Magnus Pacific JV Engineer's Estimate Unit Price Total Price Unit Price Total Price A1 Injury
More informationRegular. NECESSARY RESOURCES/IMPACTS (OTHER) n/a. Fiscal Impact
CITY COUNCIL AGENDA Meeting Date: 09/16/2013 TITLE: Hatley Way Sidewalk Improvements 2013 Bid Award Responsible Staff: Ron Crumley Backup Material: Backup material attached Digital Presentation: Yes Other
More informationI. J~ /.. RrECE~VfEfD 9J7J:. 13~ 7b 1/1~ COUNCIL. ~ 1-j r-(lk. 1 1-'> lft:; WHATCOM COUNTY COUNCIL AGENDA BILL
WHATCOM COUNTY COUNCIL AGENDA BILL NO. 2016-248 CLEARANCES Initial Date Date Received in Council Office AxendaDate Assixned to: Originator: James Karcher, P.E. 9J7J:. 1 1-'> lft:; RrECE~VfEfD Division
More informationCITY OF SAN MARCOS ENGINEERING DIVISION
AN APPLICANT S GUIDE TO PROCEDURES FOR: CITY OF SAN MARCOS ENGINEERING DIVISION 1 Civic Center Dr., San Marcos, CA 92069-2918 (760) 744-1050 FAX (760) 591-4135 FEE SCHEDULE FOR GRADING & IMPROVEMENT PLAN
More informationCITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA
CITY OF SIGNAL HILL 2175 Cherry Avenue Signal Hill, CA 90755-3799 AGENDA ITEM TO: FROM: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL STEVE MYRTER, P.E. DIRECTOR OF PUBLIC WORKS SUBJECT: RESOLUTION DECLARING
More informationSTRAIGHT STRIPE PAINTING, INC. 22b Remove Pavement Markings with Sand Blasting Per Hour 1 $ $ $ $
PAVEMENT MARKING STRAIGHT STRIPE PAINTING, AMERICAN PAVEMENT MARKING, LLC ITEM UNIT TOTAL UNIT TOTAL NUMBER DESCRIPTION UNIT QUANTITY COST AMOUNT COST AMOUNT 1 Mobilization L.S. 3 $ 400.00 $ 1,200.00 $
More informationSAN RAFAEL CITY COUNCIL AGENDA REPORT
Agenda Item No: 6.b Meeting Date: April 3, 2017 Department: Public Works Prepared by: Bill Guerin, Director of Public Works TOPIC: SAN RAFAEL CITY COUNCIL AGENDA REPORT City Manager Approval: File No.:
More informationREPLACEMENT OF MERCER COUNTY BRIDGE
ADDENDUM NO. ONE Notice is hereby given that on April 26, 2019 at 11:00 AM (Prevailing time), sealed proposals will be opened and read in public by the Purchasing Department in the Mercer County McDade
More informationCITY OF PALM DESERT PUBLIC WORKS DEPARTMENT
BEFORE YOU CAN PERFORM ANY CONSTRUCTION OR MAINTENANCE WORK IN THE PUBLIC RIGHT-OF-WAY, YOU MUST HAVE A VALID ENCROACHMENT PERMIT ISSUED BY THIS DEPARTMENT This work includes but is not limited to driveway
More informationBID TABULATION. Engineer's Estmated Opinion of Costs
Street Resurfacing Project - 2018 Rank Vendor Name Total Bid % of Low Bid % of Estimate File 2018-004 Engineer's $ 5,032,397.47 102.11% 100.00% Bid 4529 1 Ajax Paving Industries, Inc $ 4,928,322.54 100.00%
More information(b) Approve a ten percent contingency in the amount of $304,024; and
COUNCIL AGENDA: 6/9/15 ITEM:
More informationADDITIONS, MODIFICATIONS, AND/OR DELETIONS TO THE PROPOSAL
II. ADDITIONS, MODIFICATIONS, AND/OR DELETIONS TO THE PROPOSAL ITEM NO. 1: Page P-1, Proposal DELETE the Proposal (pages P-1 through P-9) in its entirety and REPLACE with the attached Proposal (pages P-1R
More informationTown of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562
Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 1 T100 PROJECT LOCATION MAP Scale: NTS N Revisions: No. Date: Description: Scale As Indicated
More informationBob Brown, Community Development Director Annette Chavez, Chief Building Official Gail Papworth, Principal Human Resources Analyst
STAFF REPORT MEETING DATE: September 12, 2017 TO: FROM: City Council Bob Brown, Community Development Director Annette Chavez, Chief Building Official Gail Papworth, Principal Human Resources Analyst 922
More informationExhibit 4 Page 1 of 8
Page 1 of 8 Price Analysis Summary Bid #C2113975C1, Construction of Davie Road Extension Agency: Highway Construction and Engineering Division Bid Submittals: 4 Purchasing Agent: Cara M. Leisy, J.D. Declinations:
More informationSTAFF REPORT. MEETING October 24, City Council. Regan M. Candelario, City Manager Jessica Deakyne, Senior Management Analyst
J-18 STAFF REPORT MEETING DATE: October 24, 2017 TO: City Council FROM: Regan M. Candelario, City Manager Jessica Deakyne, Senior Management Analyst 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX
More informationMEETING NOTICE. City Council will be held at 5:30 p.m. in the City Council Chambers. located at 305 Third Avenue East.
CITY OF TWIN FALLS, IDAHO MEETING NOTICE * * * * The Monday, November 19, 2012, regular meeting of the Twin Falls City Council will be held at 5:30 p.m. in the City Council Chambers located at 305 Third
More informationAPPROVAL OF AGREEMENTS AUTHORIZING A NEW DEPOSITORY BANKING RELATIONSHIP WITH UMPQUA BANK
STAFF REPORT MEETING DATE: January 27, 2015 TO: FROM: City Council Michael Frank, City Manager Cathy Capriola, Assistant City Manager Brian Cochran, Finance Manager Maureen Chapman, Accounting Supervisor
More informationSUBJECT: ADOPT RESOLUTIONS TO APPROVE STREET RESURFACING, CITY PROJECT NO :
Agenda Item No: 6.b Meeting Date: April 16, 2018 SAN RAFAEL CITY COUNCIL AGENDA REPORT Department: Public Works Prepared by: Bill Guerin, Director of Public Works City Manager Approval: File No.: 16.06.87
More informationCANTON COMMUNITY REQUEST FOR BOARD ACTION
CANTON COMMUNITY REQUEST FOR BOARD ACTION MEETING DATE: March 22, 2016 AGENDA ITEM #G-10 ITEM: Consider Approval of a Budget Amendment & Award of a Contract Asphalt Repairs to Hutch Paving, Inc. the Wayne
More informationPavlick, Kenneth - DEN Date: :26:57-07'00'
November 21, 2018 PIKES PEAK PARKING RESTORATION CONTRACT NO. 201845783 ADDENDUM NUMBER ONE This Addendum Number One supersedes and/or supplements all portions of the Contract Documents with which it conflicts.
More informationPreliminary Budget Cost Estimate-Raft Island RIIA Roads 26952 SY Construction Items Budget Preliminary Temporary Erosion Control/Miscellaneous Work $ 18,500.00 Traffic Control $ 10,000.00 Pulverizing $
More informationTOTAL QUANTITY UNIT COST UNIT
BASE BID DIVISION 1 - GENERAL 1 1070-206-A-0 TRAFFIC CONTROL LS 1 $ 10,000 $ 10,000 $3,000.00 $3,000.00 $5,600.00 $5,600.00 2 2010-108-B-0 CLEARING AND GRUBBING AC 5 $ 9,000 $ 45,000 $7,192.50 $35,962.50
More informationADDENDUM #1 March 12, 2019 BID FORM. Moore, Oklahoma DATE: PROJECT:
ADDENDU #1 arch 12, 2019 BID FOR PLACE DATE: PROJECT: oore, Oklahoma 34 th Street, Telephone Rd to Santa Fe Ave Roadway Widening Proposal of (hereinafter called BIDDER ), doing business as a Corporation
More information2011 PUBLIC PARKING LOT & ALLEY IMPROVEMENTS Village of Whitefish Bay Project No March 17, 2011 ITEM DESCRIPTION UNIT QTY.
ALLEY: 5600 BLOCK OF N. LAKE DRIVE 1 Remove concrete pavement 800 SY $ 11.07 $ 8,856.00 $ 5.31 $ 4,248.00 $ 12.70 $ 10,160.00 $ 6.20 $ 4,960.00 $ 9.27 $ 7,416.00 $ 16.75 $ 13,400.00 2 6" Aggregate Dense
More informationCertified Bid Tabulation Southeast Residential Community Parking Development South Dakota State University
Base Bid - Parking Lot Construction Number Grading and Surfacing Items Quantity Unit C-1 Mobilization 1 LS $ 60,000.00 $ 60,000.00 $ 82,000.00 $ 82,000.00 $ 18,255.59 $ 18,255.59 C-2 Traffic Control 1
More informationSECTION BID. Valley Court Force Main Replacement Contract No. BE17-029
SECTION 00300 - BID BID TO: THE CITY AND BOROUGH OF JUNEAU 1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with the OWNER in the form included in the
More informationAVERAGE OF BID ITEMS ENGINEERS ESTIMATE
ROADWAY 1 Mobilization 1 LS $ 990,048.50 $ 80,000.00 $ 880,000.00 $ 880,000.00 $ 950,000.00 $ 950,000.00 $ 967,510.00 $ 967,510.00 $ 1,162,684.00 $ 1,162,684.00 2 Maintenance of Traffic ( incl. Pedestrian
More informationSubject: Addendum No. 1 Project #C CCE Parking Lot Replacement Phase 2 Robert Bishop Drive 4380 Richmond Road, Highland Hills, Ohio 44122
Addendum No. 1 Page One To: From: All Plan Holders of Record CT Consultants, Inc. Gene E. Arters, P.E. on behalf of Cuyahoga Community College Subject: Addendum No. 1 Project #C20166009 CCE Parking Lot
More informationCOUNTY OF SAN MATEO STATE OF CALIFORNIA NOTICE TO CONTRACTORS
COUNTY OF SAN MATEO STATE OF CALIFORNIA NOTICE TO CONTRACTORS NOTICE IS HEREBY GIVEN, that Sealed bids will be received at the office of the County Manager/Clerk of the Board of Supervisors, Hall of Justice
More informationALVAREZ ENGINEERS, INC. July 27, 2017 a) Evaluation Criteria PROJECT: ROADWAY IMPROVEMENTS TO DOLPHIN MALL OUTER RING ROAD for BEACON TRADEPORT COMMUN
ALVAREZ ENGINEERS, INC. July 27, 2017 a) Evaluation Criteria PROJECT: ROADWAY IMPROVEMENTS TO DOLPHIN MALL OUTER RING ROAD for BEACON TRADEPORT COMMUNITY DEVELOPMENT DISTRICT CITY OF SWEETWATER, FLORIDA
More informationSubmitted by: Jeffrey Egeberg, Secretary, Public Works Commission. Street Repair Policy Update and Permeable Paver Trial Project
Public Works Commission ACTION CALENDAR July 14, 2009 To: From: Honorable Mayor and Members of the City Council Public Works Commission Submitted by: Jeffrey Egeberg, Secretary, Public Works Commission
More informationFailure to acknowledge all addenda in the BID may cause rejection of the BID. See Instructions to Bidders.
Addendum #1 409 22nd Ave So PO Box 298 Brookings, SD 57006 Toll Free 1-855-323-6342 www.bannerassociates.com Project: Viborg Utility Improvements - 2017 Bid Date: 11:00 A.M., Local Time, March 15, 2017
More informationCITY OF ELK GROVE CITY COUNCIL STAFF REPORT
AGENDA ITEM NO. 8.11 CITY OF ELK GROVE CITY COUNCIL STAFF REPORT AGENDA TITLE: Adopt resolution approving the Rural Roads Shoulder Backing Improvements Project (WRM001) (Re-bid), authorizing the City Manager
More informationJob No Wastewater Collection System Small Main Rehabilitation at Focus Areas Pipebursting Method BID PROPOSAL. Dollars Cents $ $ Dollars
BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of an individual doing business as TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instructions and Invitations to Bidders, the undersigned
More informationFuel Adjustment Allowance USD 50,000 $ 1.00 $ 50, $ 1.00 $ 50, $ 1.00 $ 50, $ 1.00 $ 50, $ 1.00 $
SOLICITATION NO. 147850: VALENCIA ROAD: WADE ROAD TO MARK ROAD Achen Gardner Granite Hunter Borderland KE&G ITEM NO. ITEM DESCRIPTION UNIT QTY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT
More informationCITY OF ELKO BID TABULATION * RE-BID* FOR Sports Complex April 4, 2018
CITY OF ELKO BID TABULATION * RE-BID* FOR Sports Complex 2017-2018 April 4, 2018 Great Basin Engineering CLEARING EARTHWORK 1 337.01200 Mobilization @ Per Lump Sum 1 LS $445,350.00 $ 445,350.00 $481,768.00
More informationNew Jersey Department of Transportation DATE : 06/22/10 PAGE : TABULATION OF BIDS
PAGE : 107-1 CONTRACT TIME : 01/24/11 COMPLETION DATE CONTRACT DESCRIPTION : URBAN PROJECT(S) : FS-0022(105) ROUTE 37 FROM ROUTE 70 TO GARDEN STATE PARKWAY RESURFACING CONTRACT NO. 000103080 TOWNSHIP OF
More informationCA: RMM: rmd254/hpca City Council Meeting Santa Monica, California RESOLUTION NUMBER 7231(CCS) (City Council Series)
CA: RMM: rmd254/hpca City Council Meeting 6-10-86 Santa Monica, California RESOLUTION NUMBER 7231(CCS) (City Council Series) A RESOLUTION OF THE CITY COUNCIL OF CITY OF SANTA MONICA ADOPTING THE PERCENT
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 22, 2008 DATE: July 15, 2008 SUBJECT: Approval of Resolutions and Questions to include in the 2008 Bond Referenda C. M. RECOMMENDATION:
More informationNorth Baker Ave - City Limits to 23rd St NE CRP 949 PROPOSAL
North Baker Ave. - City Limits to 23rd St. NE Bid Documents BD-1 To the Board of County Commissioners Douglas County, Washington Gentlemen: North Baker Ave - City Limits to 23rd St NE CRP 949 PROPOSAL
More information2017/2018 OPERATING BUDGET AMENDMENT REQUEST FOR LIEB PROPERTY (1519 / 1521 / 1525 HILL ROAD, APNs , , -033, NOVATO)
J-15 STAFF REPORT MEETING DATE: September 26, 2017 TO: FROM: City Council Russ Thompson, Public Works Director 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/ 899-8213 www.novato.org SUBJECT:
More informationADDENDUM No. 1 January 29, Paving Program Village of Milford
ADDENDUM No. 1 2018 Paving Program Village of Milford The following changes, additions, and/or clarifications to the Contract Documents shall be incorporated in said documents and shall be allowed for
More informationEXHIBIT A CITY OF OLDSMAR PERMIT, INSPECTION AND PLANS EXAMINATION FEE SCHEDULE
1. Building Permit EXHIBIT A CITY OF OLDSMAR PERMIT, INSPECTION AND PLANS EXAMINATION FEE SCHEDULE a. This fee schedule is applicable to all building permits issued by the City of Oldsmar, Building Division
More informationBID PROPOSAL ANNUAL PATHWAY & MINOR CONSTRUCTION CONTRACT PBC PROJECT #
ENGINEERS Wynn & Sons Envir. ESTIMATE Construction, Inc. 1 Emergency Response, Less than 6 Hours 10 EA $ 50.00 $ 50.00 $ 500.00 2 Emergency Response, 6 Hours to 24 Hours 20 EA $ 50.00 $ 50.00 $ 1,000.00
More informationMunilla Construction HOOD RD., E. OF FLORIDA'S TURNPIKE TO W. OF CENTRAL BLVD. AND HOOD RD. & CENTRAL
JW Cheatham, ROADWAY 1 MOBILIZATION 1.0 LS $ 1,350,116.25 $ 906,000.00 $ 1,233,000.00 $ 1,233,000.00 $ 1,159,208.36 $ 1,159,208.36 $ 1,451,835.00 $ 1,451,835.00 $ 1,556,421.65 $ 1,556,421.65 2 MAINTENANCE
More informationBid No.: PO Box Cone Rd Asphalt Ave th Ave. E. Dunedin, FL Tampa, FL Tampa, FL Palmetto, FL 34221
Bid : 7379 GENERAL 1 2 3 4 @ unit $ total $ @ unit $ total $ @ unit $ total $ @ unit $ total $ G-1.1 Mobilization 1 LS $ 450,000.00 $ 450,000.00 $ 720,000.00 $ 720,000.00 $ 750,000.00 $ 750,000.00 $ 530,000.00
More informationCITY OF DEERFIELD BEACH Request for City Commission Agenda
Item: CITY OF DEERFIELD BEACH Request for City Commission Agenda Agenda Date Requested: 6/5/2012 Contact Person: Charles DaBrusco, P.E., Director of Environmental Services Description: Award of contract
More informationRFB Addendum 3
Yes GENERAL CONDITIONS 1.00 MOBLIZATION AND DEMOBILIZATION 1 LS $ 293,750.00 $ 293,750.00 1.01 STORMWATER POLLUTION PREVENTION PLAN (INCLUDES EROSION CONTROL AND SEDIMENT IMPLEMATION PLAN) 1.02 STORMWATER
More informationLETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY
LETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY January 5, 205 2 Partially Completed Single Family Lots (65' x 5' typical) 46 Completed Townhome Pads (22' x 50' typical) Sale. This letter of intent outlines
More informationPART A ROADWAY - BASE BID
May 10, 2016 HEB-MC-61 PART A ROADWAY - BASE BID 202(A) - UNCLASSIFIED EXCAVATION - CY 34,946.00 $ 6.00 209,676.00 $ 7.98 $ 278,869.08 205(A) - TYPE A-SALVAGED TOPSOIL - LSUM 1.00 $ 22,500.00 $ 22,500.00
More informationAppendix E: Revenues and Cost Estimates
Appendix E: Revenues and Cost Estimates Photo Source: Mission Media Regional Financial Plan 2020-2040 Each metropolitan transportation plan must include a financial plan. In this financial plan, the region
More informationCITY COUNCIL Quasi-Judicial Matter
SUMMARY REPORT CITY COUNCIL Quasi-Judicial Matter c:::::t f Agenda No. Key Words: Landscaping Lighting District Meeting Date: July 12, 2016 PREPARED BY: ~ Janet Koster, Public Works Operations Manager~
More informationOKLAHOMA TURNPIKE AUTHORITY
PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 250,000.00 $250,000.00 $ 240,978.56 $ 240,978.56 260,000.00 $ 260,000.00 201(A) CLEARING & GRUBBING LSUM 1.00 $ 30,000.00 $30,000.00 $ 17,188.20
More informationBID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012
Page 1 BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO. 87786 BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012 ROADWAY 1 201 CLEARING AND GRUBBING 1 LUMP $4,500.00 $4,500.00 $10,016.00
More informationRESOLUTION NO A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARSON, CALIFORNIA, REAFFIRMING RESOLUTION
RESOLUTION NO. 17-111 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CARSON, CALIFORNIA, REAFFIRMING RESOLUTION NO. 17-079 AND DECLARING A FISCAL EMERGENCY PURSUANT TO ARTICLE XIII C SECTION 2( b) OF
More information