Conducting a Facilities Condition Assessment as Part of Your Capital Planning. FEFPA July 5, 2011
|
|
- Ellen Moody
- 5 years ago
- Views:
Transcription
1 Conducting a Facilities Condition Assessment as Part of Your Capital Planning FEFPA July 5, 2011
2 Agenda Introduction History and Goals Process Physical Condition Analysis and Ranking Educational Adequacy Analysis and Ranking Technology Survey Room Use Survey
3 History and Goals Clermont Umatilla MS
4 Process Physical Condition Ranking Educational Adequacy Ranking Technology Survey
5 Building Envelope Site HVAC Roofing Age PHYSICAL CONDITION ASSESSMENT
6 Physical Condition Assessment School Name: Beverly Shores ES School ID: 0031 Building Envelope Building Exterior Windows Condition Value Exterior Doors Condition Value Exterior Walls Condition Value Condition Value Average 3 Poor 4 Poor 4 Good Fair 3 Fair 3 Good Fair 3 Poor 4 Good Fair 3 Fair 3 Good Poor 4 Poor 4 Good Fair 3 Fair 3 Good Good 2 Good 2 Good Good 2 Good 2 Good Good 2 Good 2 Good 2 2.0
7 Grading Criteria LCSB Condition Assessment Guidelines Condition Value Recommended Action 1. Very Good 1 = Very Good (Asset has no defect; appearance is as new) A. Clean Remove debris, stains, surface rust 2. Good 2 = Good (Asset exhibits superficial wear and tear, minor defects, minor signs of deterioration to surface finishes; but does not require major maintenance; no major defects exist.) B. Adjust Tighten system components, align doors 3. Fair 3 = Fair (Asset services are functional, but require attention; uncorrected, will result in premature failure or accelerated deterioration of component or system.) C. Remove Graffiti, inoperable systems 4. Poor 4 = Poor (Asset is in poor condition; critical deficiencies affecting function; requires significant attention; services are functional but falling often.) D. Repair Return components back to service 5. Unacceptable 5 = Unacceptable (Asset has deteriorated badly; serious structural problems; elements are broken, services are not performing; significant major defects exist.) E. Replace Deteriorated beyond repair, repaint F. No Action Leave as is
8 Physical Condition Assessment School Name: Fruitland Park ES 2/23/10 HVAC Building Unit Type of Equipment MFG MFG Date Condition Value Recommend Action Estimated Life Cycle Remaining Replacement Year 1 Chiller Trane F AHU-1 CW air handler Trane E AHU-2 CW air handler Trane E Package unit Carrier E Package unit Carrier E MAV 1 Package unit Weather King E Package unit Carrier E Package unit Carrier E Package unit Carrier E Package unit Carrier E Package unit Trane F
9 Elementary Schools Facility Condition Score School Average Age Building Envelope Roofs HVAC Site FCI Clermont Seminole Springs Cypress Ridge Eustis Eustis Heights Fruitland Park Groveland Beverly Shores Spring Creek Treadway Astatula Rimes Early Learning Center Lost Lake Triangle Villages Leesburg Round Lake Umatilla Pine Ridge Tavares Mascotte Minneola Grassy Lake Sawgrass Bay Total Average
10 Building Age EUSTIS HIGH SCHOOL BUILDING SQUARE FEET YEAR BUILT AGE AVERAGE BUILDING AGE = 25.7 YEARS CAMPUS BUILDING STUDENT MAJOR % VALUE STATIONS RENOVA- TION ADJUSTED BUILDING AGE 1 44, % , % , % , % , % , % , % TOTAL 155, %
11 Middle Schools School Average Age Building Envelope Roofs HVAC Site Facility Condition Score FCI Clermont Umatilla Tavares Eustis Oak Park Mount Dora Windy Hill Carver East Ridge Total Average High Schools School Type Average Age Building Envelope Roofs HVAC Site Facility Condition Score Eustis Curtright 9th South Lake HS East Ridge HS Tavares HS Leesburg HS Eustis HS Mount Dora HS Umatilla HS Total Average FCI
12 Building Analysis School Name Build Design Use Building Envelope HVAC Roofing Site Sum of CVs Rank Build Age Beverly Shores 3 Primary Classroom (K-3) Teacher Resource Rooms Clermont MS Eustis ES 5 7 Primary Classroom (K-3) Intermediate Classroom (4-8) Classrooms, Grades 1-2, Teacher Planning Classrooms, Grade 3, PE Coach Office, Math Book Storage Administration Administration/ Main Office Dining Area Dining Jr High Gymnasium Gymnasium Eustis Heights ES 8 Intermediate Science Demo Primary Classroom (K-3) Group Restrooms Intermediate Classroom (4-8) Science Classrooms w/ Labs Classrooms, K & Grade Boys & Girls Restrooms Classrooms, Grade
13 Square Feet Comparison - 75% Safety and Security 5% Site 5% Performance Indicators 10% Furniture and Equipment 5% EDUCATIONAL ADEQUACY ASSESSMENT
14 Educational Adequacy Assessment Capacity Total Facilities Capacity List NSF FISH Actual NSF % of Desired STANDARD CLASSROOMS 24 Primary Classroom , ,813 39,944 84% Classroom/Academic 24 Storage, Material 100 2, Storage, Outside 50 1, Storage, Student Toilet, Student 60 1,440 Subtotal 1,132 27,168 8 Intermediate Classroom 858 6, Storage, Material Storage, Outside Toilet, Student-Male Toilet, Student-Female Subtotal 1,078 8,624 MUSIC 1 Elementary Music 1,000 1, Reference Storage, Material Practice, Music Subtotal 1,270 1,270
15 Educational Adequacy Assessment Safety and Security - Single Point of Entry, fencing, cameras, circulation management Site Parking, vehicular/pedestrian separation, fields and play areas Performance Indicators - Lighting (natural and artificial) Temperature/ ventilation Acoustics Finishes (floors, carpet, worn-out ) Furniture and Equipment
16 Elementary Schools Summary % of the State Guidelines Other Criteria 2009 FISH 2014 Enrol Proj Proposed Capacity * * Media Center Dining Admin Weighed total (SF)* Safety/ Security Site Classrooms Performance Furn & Equip Educ adeq score Clermont ES % 56% 46% 44% 41% 2% 1% 6% 3% 53% Eustis ES % 31% 73% 100% 46% 4% 1% 6% 3% 60% Cypress Ridge % 84% 41% 66% 46% 3% 5% 6% 5% 65% Eustis Heights / % 59% 50% 65% 48% 4% 5% 6% 3% 66% Treadway % 82% 71% 87% 52% 2% 5% 6% 5% 70% Rimes % 100% 100% 92% 50% 3% 5% 8% 5% 71% Beverly Shores % 100% 100% 96% 66% 4% 5% 2% 2% 78% Fruitland Park % 73% 64% 100% 63% 3% 4% 4% 4% 78% Grassy Lake % 70% 90% 55% 56% 5% 5% 8% 5% 79% * Percent X.75 ** 1: Capacity exceeds projected enrollment : Capital Plan includes an addition 3: Other
17 Middle Schools Summary % of the State Guidelines Other Criteria FISH 2014 Proposed * EnrolProj Capacity * Media Weighed Safety/S Center Dining PE Admin total (SF) ecurity Site Classrooms Performance Furn & Equip Educ adeq score Umatilla MS % 85% 42% 88% 58% 53% 4% 3% 4% 3% 67% Mt Dora MS % 99% 87% 82% 68% 52% 3% 4% 6% 5% 70% Oak Park % 94% 65% 100% 92% 62% 3% 5% 4% 2% 76% Windy Hill MS % 86% 81% 95% 100% 58% 4% 5% 8% 5% 80% Clermont MS % 98% 100% 100% 84% 69% 2% 3% 4% 3% 81% Eustis MS % 89% 75% 79% 97% 64% 5% 5% 4% 5% 83% Tavares MS % 89% 81% 87% 98% 66% 5% 5% 6% 3% 85% East Ridge MS % 92% 99% 100% 77% 62% 5% 5% 10% 5% 87% Carver MS % 88% 100% 100% 100% 70% 5% 5% 10% 5% 95%
18 High Schools Summary % of the State Guidelines Other Criteria FISH 2014 Proposed EnrolProj Capacity * * Media Weighed Safety/S Center Dining PE Admin total (SF) ecurity Site Classrooms Performance Furn & Equip Educ adeq score Curtwright Ct % 78% 100% 100% 96% 60% 4% 5% 4% 1% 74% Tavares HS % 56% 86% 100% 100% 66% 4% 5% 4% 4% 83% Umatilla HS % 77% 74% 100% 100% 59% 4% 5% 10% 5% 83% Leesburg HS % 58% 86% 100% 100% 67% 4% 5% 8% 3% 87% Eustis HS % 82% 100% 100% 100% 68% 4% 4% 8% 4% 88% South Lake HS % 77% 100% 100% 100% 70% 5% 5% 6% 3% 89% Mt Dora % 88% 100% 93% 100% 70% 4% 5% 10% 5% 94% East Ridge HS % 66% 100% 100% 100% 70% 5% 5% 10% 4% 95%
19 TECHNOLOGY SURVEY
20 Technology Survey Elementary Schools Classrooms Document Cameras Units % LCD Projectors Units % Interactive Slate or Airliner Units % Interactive White Boards (SMART, Mimio, etc.) Units % Student Response Systems (Clickers) Units % Sound Enhancement Units % Astatula % 8 18% 0 0% 0 0% 0 0% 1 2% 0 Beverly Shores % 20 51% 0 0% 6 15% 0 0% 4 10% 0 Clermont % 26 87% 0 0% 9 30% 0 0% 12 40% 0 Cypress Ridge % % 0 0% 3 9% 1 3% 14 42% 0 Eustis % 20 80% 1 4% 1 4% 1 4% 3 12% 0 Eustis Heights % 35 81% 3 7% 3 7% 2 5% 2 5% 0 Computer on Wheels (COW) Fruitland Park % 22 56% 0 0% 11 28% 0 0% 0 0% 5-12 unit Grassy Lake % % 0 0% 2 4% 0 0% % 0 Groveland % % % 0 0% 0 0% % 1-24 unit
21 Technology Survey High Schools Classrooms Document Cameras LCD Projectors Interactive Slate or Airliner Interactive White Boards (SMART, Mimio, etc.) Student Response Systems (Clickers) Sound Enhancement Computer on Wheels (COW) Units % Units % Units % Units % Units % Units % East Ridge % % 0 0% 11 11% 0 0% 42 42% 2-25 units Eustis % 36 72% 1 2% 5 10% 1 2% 0 0% 2-24 unit Eustis Annex- Curtright % 18 82% 2 9% 1 5% 1 5% 4 18% 2-12 unit Leesburg % % 4 4% 16 16% 6 6% % 4-10 unit; 5-24 unit Mount Dora % % 0 0% 14 22% 0 0% % unit; 2-10 South Lake % 64 66% 2 2% 5 5% 0 0% 22 23% unit Tavares % 55 83% 0 0% 4 6% 6 9% 4 6% 3-24 unit Umatilla % 25 56% 0 0% 4 9% 0 0% 0 0% 0
22 ROOM USE SURVEY
23 Actual vs. FISH Room Use
24 Questions/ Next Steps
Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent
Tumwater University School District Budget Myths Bond Project Update February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Construction Update $136,000,000 in bonds approved
More informationINTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationOrlando Regional REALTOR Association Monday Morning Quarterback - 06/19/ /25/2011 Lake, Orange, Osceola & Seminole Counties
Monday Morning Quarterback - /9/ - /5/ Sales Total 87 Under $5k Single Family Homes $K to $K 95 $K to $5K Short Sales / Bank Owned 8 7 7 5 8 Active Listings Short Sales / Bank Owned Months of Inventory,,98
More informationOrlando Regional REALTOR Association Monday Morning Quarterback - 12/26/ /01/2011 Lake, Orange, Osceola & Seminole Counties
Sales Monday Morning Quarterback - /6/ - // Total 47 Under $k,68 Single Family Homes 9 6 $K to $4K,6 $4K to $K Short Sales / Bank Owned 69 6 Active Listings,67 9 $K to $K Short Sales / Bank Owned 4,87,8
More informationProgress Update Identified Needs & Capital Plan
Progress Update Identified Needs & Capital Plan May 29, 2012 Buena Park School District Facilities Assessment & Implementation Plan 0 Facilities Planning, Public Finance, Program Administration Summary
More informationINTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationCOMMUNITY INVESTMENT PLAN FOR FISCAL YEARS 2016 TO 2021
COMMUNITY INVESTMENT PLAN FOR FISCAL YEARS 2016 TO 2021 PUBLIC SCHOOLS: New Construction, Additions, Modernizations Fiscal Year 2016 2017 2018 2019 2020 2021 Allocation Complete Project Cost Career and
More informationMonday Morning Quarterback Summary
Summary May, Single-family existing homes Sales of single-family homes decreased to 55 during the week of May, from 5 the week prior The median price of single family homes decreased to $,, a change of
More informationINVITATION TO BID SCHOOL BOARD OF LAKE COUNTY PURCHASING DEPARTMENT COUNTY ROAD 561 TAVARES, FLORIDA
INVITATION TO BID SCHOOL BOARD OF LAKE COUNTY PURCHASING DEPARTMENT 29529 COUNTY ROAD 561 TAVARES, FLORIDA 32778-2496 The School Board of Lake County, located in Tavares, Florida, solicits your company
More informationCH-UH Board of Education Meeting. June 27, 2017
CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle
More informationWest Bend School District Community Survey Results. Spring 2018
West Bend School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in June of 2018. Residents within the District were mailed a paper survey. Each survey included a
More informationCIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5
CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 Edwin Ataide Deputy Director Plant & Facilities SCH-1 School Projects All Schools Priority FY15 FY16 FY17 FY18 FY19 ADA Compliance (Handicap Accessibility)
More informationPublic Presentation Capital Bond November 27, 2017
Public Presentation Capital Bond November 27, 2017 Capital Bond The Board of Education facilities committee working in concert with building administration, central administration, and the district architect
More informationFACILITIES EVALUATIONS BACKGROUND REPORT
for DRAFT FACILITIES EVALUATIONS BACKGROUND REPORT March 30, 2016 TABLE of CONTENTS PURPOSE. 2 SCOPE of the. 2 CAPACITY / UTILIZATION ANALYSIS UPDATE.. 4 FACILITIES EVALUATIONS :: BACKGROUND DATA REPORTS
More informationMonday Morning Quarterback Summary
Summary Feb 8, 8 Single-family existing homes Sales of single-family homes increased to 56 during the week of Feb 8, from the week prior The median price of single family homes decreased to $5,, a change
More informationOverview of Public Schools CIP
Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, such as additions and modernizations, as well as other school-related projects. School construction
More informationPhysical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15
Physical Plant Five-Year Capital Budget Plan State College Area School District November 2011 Page 1 of 15 Table of Contents Background and 2013 Projects Pages 3-5 Funding Level Pages 6-7 Existing Buildings
More informationFACILITIES PLANNING COMMITTEE
Marble Falls ISD FACILITIES PLANNING COMMITTEE Meeting 2 April 26, 2018 Love and Inspire WELCOME! Agenda Welcome Co-Chairs School Finance 101 MFISD Financial Overview Aging Facilities Small Group and Large
More informationMonday Morning Quarterback Summary
Summary Mar 8, 8 Single-family existing homes Sales of single-family homes decreased to 8 during the week of Mar 8, from 79 the week prior The median price of single family homes decreased to $9,, a change
More informationPROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue
PROPOSITION FARMINGTON SCHOOLS April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS - BOND LANGUAGE Shall the Board of Education of the Farmington R-7 School District of St. Francois County, Missouri,
More informationWAYLAND PUBLIC SCHOOLS BUDGET HEARING
+ WAYLAND PUBLIC SCHOOLS BUDGET HEARING School Committee Recommended FY13 Operating Budget March 12, 2012 + AGENDA Proposed Goals and Priorities FY13 Operating Budget Budget Process Enrollment & Staffing
More informationBurlington Area School District Community Survey Results. Winter 2016
Burlington Area School District Community Survey Results Winter 2016 Survey Summary The community survey was conducted in December of 2016. Residents within the District were mailed a paper survey. Each
More informationBob Mathis Elementary
DeKalb County School District/Elementary Schools Bob Mathis Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationMonday Morning Quarterback Summary
Summary Apr 6, 7 Single-family existing homes Sales of single-family homes increased to during the week of Apr 6, from 9 the week prior The median price of single family homes decreased to $,, a change
More informationStone Mountain Middle
DeKalb County School District/Middle Schools Stone Mountain Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationOverview of Public Schools CIP
Overview of Public Schools CIP The Public Schools Community Investment Plan (CIP) includes school construction, additions and modernizations, as well as other school related projects. For more than a decade
More informationBond 2018 Referendum
1 Bond 2018 Referendum November 6, 2018 Election $992.6 million bond plan Projected tax rate of $1.35 3 pennies higher than current tax rate $1.32 1 penny higher than 2016 tax rate $1.34 Three year plan
More informationBarnesville Public Schools Proposed Building Program
August 1, 2018 Proposal for Submitted to: Commissioner Dr. Brenda Cassellius Minnesota Department of Education Barnesville Public Schools Proposed Building Program Barnesville Public School District Independent
More informationBallot Measures-T Section
T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and
More informationAnderson Creek Primary
NC School District/430 Harnett County/Elementary School Anderson Creek Primary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary
More informationPleasantdale Elementary
DeKalb County School District/Elementary Schools Pleasantdale Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School
More informationBid #:4290DG Bid Name: Elevator Preventative Maintenance and Repair Service Vendor Name: Located in: Item # Qty. Manufacturer Location State ID Description Rise/Length Openings Emergency Elevator Phone
More informationOverview of Public Schools CIP
Overview of Public Schools CIP The Board of Education CIP includes public school construction, addition and modernization projects as well as other school related projects. The primary sources of funding
More informationBallot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools
Section Ballot Measures-N N Centralia Elementary School District, Building Strong Neighborhood Schools To repair/modernize aging classrooms, science labs/school facilities to keep pace with technology,
More informationAdopted Tentative Budget. Final Public Hearing
2013-14 Adopted Tentative Budget Final Public Hearing September 5, 2013 Presentation Outline Proposed Millage Budget Information Enrollment Projections vs. State Recalibration Proposed Employee Positions
More informationPage Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175
Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Special Education Allocation 176 Operational Services Allocation
More informationBarnesville Public Schools Proposed Building Program
May 6, 2016 Proposal for Submitted to: Commissioner Dr. Brenda Cassellius Minnesota Department of Education Barnesville Public Schools Proposed Building Program Barnesville Public School District Independent
More informationRonald E. McNair Discovery Learning Academy
DeKalb County School District/Elementary Schools Ronald E. McNair Discovery Learning Academy Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive
More informationSagamore Hills Elementary
DeKalb County School District/Elementary Schools Sagamore Hills Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School
More informationBALTIMORE COUNTY PUBLIC SCHOOLS
Exhibit B BALTIMORE COUNTY PUBLIC SCHOOLS DATE: TO: FROM: SUBJECT: ORIGINATOR: RESOURCE PERSON(S): BOARD OF EDUCATION Dr. Joe A. Hairston, Superintendent PROPOSED FY 2008 STATE AND COUNTY CAPITAL BUDGET
More informationINTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationLos Angeles Unified School District Page 1 of 3
Los Angeles Unified School District 333 South Beaudry Ave, Los Angeles, CA 90017 Board of Education Report File #: Rep-201-16/17, Version: 1 Amendment to the Facilities Services Division Strategic Execution
More informationCAPITAL BUDGET FY 2020 & CAPITAL IMPROVEMENT PROGRAM FY REQUEST
CAPITAL BUDGET FY 22 & CAPITAL IMPROVEMENT PROGRAM FY 221-225 REQUEST Board of Education 1/1/218 BOARD OF EDUCATION Bob E. Lord, President Donna M. Sivigny, Vice-President Virginia R. Harrison, Member
More informationDeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016
DeKalb County School District/Elementary Schools Dunwoody Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition
More informationContents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...
Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure... 10 Ballot Measure EXHIBIT B MEASURE Y (ABBREVIATED FORM)
More informationFY 2014/ /24 CAPITAL IMPROVEMENTS PROGRAM MAINTENANCE/REPLACEMENT PROJECTS DETAIL
Year 1 Project Revenue County Category FY 14/15 Total Offset Cost I 1 AGNOR HURT HVAC Design Chiller and Exhaust Fans replacement $30,000 $0 $30,000 I 2 AGNOR HURT HVAC Design replacement of 6 RTUs $35,000
More informationComprehensive Facilities Assessment School Committee
C A N T O N P U B L I C S C H O O L S Comprehensive Facilities Assessment 3.23.2017 School Committee A g e n d a Introductions Schedule & Process Overview Progress Update Enrollment Targets Facilities
More informationMontville Township Public Schools
Montville Township Public Schools PRELIMINARY BUDGET PRESENTATION 2017-2018 SCHOOL YEAR Presented to the: Montville Township Board of Education February 21, 2017 Dr. Rene Rovtar, Superintendent of School
More informationSECOND EXTENSION TO AGREEMENT FOR CONTRACTOR SERVICES WITNESSETH:
SECOND EXTENSION TO AGREEMENT FOR CONTRACTOR SERVICES This Second Extension is made as of the~ day of ~, 2016, between the School Board of Lake of County, Florida ("SCHOOL BOARD"), and WC Fire Safety,
More informationOrlando Regional REALTOR Association Monday Morning Quarterback - 05/13/ /19/2012 Lake, Orange, Osceola & Seminole Counties
Monday Morning Quarterback - // - // Sales Total Under $k Single Family Homes $K to $K $K to $K 7 $K to $M Short Sales / Bank Owned 6 6 6 Active Listings,7,6 6 7 7 Short Sales / Bank Owned,7 7, 6 7 7 7
More informationINTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationHarnett Central High
NC School District/430 Harnett County/High School Harnett Central High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus
More information2017 Bond Program Summary
2017 Bond Program Summary Middle School #3 (off Vail Divide) $ 76,225,750 Middle School #3 Off-site Utility and Road Construction $ 2,100,000 Elementary School #7 (in Rough Hollow) $ 33,130,150 Bee Cave
More informationClinton Public Schools Proposed Budget. Maryann O Donnell Superintendent of Schools January 29, 2018
Clinton Public Schools 2018-2019 Proposed Budget Maryann O Donnell Superintendent of Schools January 29, 2018 Budget Packet Cover Sheet Mission, Strategic Priorities, & Goals Foundation Skills & Competencies
More informationAPPENDIX A FULL TEXT OF BOND MEASURE
APPENDIX A FULL TEXT OF BOND MEASURE INTRODUCTION To repair aging classrooms / leaky roofs / old facilities, and provide a safe, quality learning environment for current and future students, shall Grass
More informationCapital Projects Fund. Board Work Session August 9, 2007
Capital Projects Fund Board Work Session August 9, 2007 Presentation Objectives Building inventory Revenue sources statutory adjustments and uses Demonstrate past use of funds 2008 proposed budget Setting
More information$12,893,799 $6,260,719 $6,074,226 $137,544 $0 $25,366,288
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationWilliam Bradley Bryant Center
DeKalb County School District/Education Other William Bradley Bryant Center Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School
More information$4,701,440 $2,727,355 $2,596,419 $447,703 $11,216,598 $21,689,515
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationFY20 Capital Budget and FY21-FY25 Capital Improvement Program Request
Agenda Item #: 4.c ITEM TYPE: Report BOARD AGENDA ITEM TITLE: FY2 Capital Budget and FY21-FY25 Capital Improvement Program Request DATE: September 12, 218 OVERVIEW: The attached FY2 Capital Budget and
More informationSPACE UTILIZATION STUDY ANALYSIS November 5, 2013
SPACE UTILIZATION STUDY ANALYSIS November 5, 2013 Space Utilization Study Analysis Ongoing questions regarding enrollment and the use of our facilities 2010 an internal analysis was performed with no decisions
More informationBond Oversight Committee Bond program. January 7, 2016
Bond Oversight Committee 2014 Bond program January 7, 2016 Bond Oversight Committee 1 AGENDA Welcome, introductions, reminder of scope/role of BOC Stewart Jacobson, Chair Program Management: Max Cleaver
More informationINTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationPinebrook Elementary
NC School District/300 Davie County/Elementary School Pinebrook Elementary Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus
More informationMaterials, Services, Facilities and Technology Fee Fiscal Year Budget Request Form*
Channr-I Islands Materials, Services, Facilities and Technology Fee Fiscal Year 2014-2015 Budget Request Form* DUE: Friday, February 14, 2014 @ 5:00 P M. Please return completed requests via email to gina.matibag@csuci.edu
More informationUse of State and District Construction Funds
8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,
More informationLaurel Hill Elementary
NC School District/830 Scotland County/Elementary School Laurel Hill Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary
More information2019 Capital Projects Plan
Rev. 03/18 School Name Crawford County Community School Corporation County Name Crawford School No. 1300 2019 Capital Projects Plan The following plan format should be used for your 2019 Capital Projects
More informationBoard of Trustees Proposition Summary Table of Contents
Table of Contents Table of Contents... ii 1 Facilities Condition Assessment... 2 1.1 Priority One... 2 1.2 Priority Two... 5 1.3 Priority Three... 7 1.4 Priority Four... 9 2 Major Projects... 10 2.1 Facility
More informationTotal Revenues $27,158,867 $1,800,000 $2,400,000 $2,600,000 $3,600,000 $37,558,867
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationTHE STATE OF THE SYSTEM
THE STATE OF THE SYSTEM Alamance-Burlington School System Dr. Lillie Cox, Superintendent March 2013 R E A C H Rigorous Instruction Engagement in 21 st Century Learning Opportunities Achievement in Support
More informationSOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S
SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S Under this measure, the Somis Union School District ( District ) is submitting a bond measure, described below, to the voters
More informationLAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES
1 LAKE CENTRAL SCHOOL CORPORATION USE OF SCHOOL FACILITIES Lake Central Priority for Use of Facilities: Group I: Direct School-related Activities (100% Lake Central employees) e.g. classes, school clubs,
More informationLake Mills Area School District Community Survey Results. Spring 2018
Lake Mills Area School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in late May through mid-june of 2018. Residents within the District were mailed a paper survey.
More informationFY 2017 Stockton University Expenditure Report as of May 31, 2017
FY 2017 Stockton University Expenditure Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 FY17 Internal Capital Projects 4 State Bond/Grants 5 STOCKTON UNIVERSITY
More informationREQUEST FOR PROPOSALS CONSTRUCTION MANAGER AS CONSTRUCTOR
REQUEST FOR PROPOSALS CONSTRUCTION MANAGER AS CONSTRUCTOR Addendum No. 1 1. A preliminary Project Budget which includes all anticipated work items is included for reference in preparing a response to this
More informationPlainedge Public Schools Budget Presentation
Plainedge Public Schools 2016-2017 Budget Presentation Budget Overview Final Draft Presentation to the Board of Education Peter Porrazzo, Assistant Superintendent for Business April 5 th, 2016 BUDGET PLANNING
More informationDeKalb Elementary School of the Arts at Terry Mills
DeKalb County School District/Elementary Schools DeKalb Elementary School of the Arts at Terry Mills Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School
More informationBuilding and Site Sinking Fund Millage. Election Date: November 7th 2017
Building and Site Sinking Fund Millage Election Date: November 7th 2017 How do Districts Fund Facilities and Technology Needs? General Fund - Use current operating dollars. These are limited to the amount
More informationEducational & Performing Arts Center: Downriver Campus
Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed
More informationSTATE OF THE SYSTEM. Alamance Burlington School System. Dr. Lillie Cox, Superintendent. March 2013
THE STATE OF THE SYSTEM Alamance Burlington School System Dr. Lillie Cox, Superintendent March 2013 Rigorous Instruction Engagement in 21 st Century Learning Opportunities Achievement in Support of College
More informationRobert Shaw Theme Elementary
DeKalb County School District/Elementary Schools Robert Shaw Theme Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School
More informationMonday Morning Quarterback Summary
Summary Oct, 8 Single-family existing homes Sales of single-family homes increased to 85 during the week of Oct, from the week prior The median price of single family homes increased to $55,, a change
More informationORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/15/2013 BUILDING SURVEY DATE
0807 3502 SOUTH FIRST STREET CHAMPAIGN, ILLINOIS SYSTEM CONDITION INDEX.771 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 347,400 LABORATORY BUILDING GROSS SQUARE FEET 16,986
More informationDeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016
DeKalb County School District/Middle Schools Chapel Hill Middle Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 3 School Condition
More informationFort Wayne Community Schools. Capital Projects Planning March 15, 2011
Fort Wayne Community Schools Capital Projects Planning March 15, 2011 District Balanced Scorecard Goal III Operate effectively with integrity and fiscal responsibility Condition scores unchanged Use of
More informationNC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017
NC School District/520 Jones County/Elementary School Trenton Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus
More informationFacility Condition Assessments (FCA)
Facility Condition Assessments (FCA) Is it time for a third party review of your facility? Greg Ruberto, P.E. November 11, 2015 PSFEI Overview Penn State Facilities Engineering Institute was founded in
More informationConstruction Total. Subtotal: $ 863,540 $ 172,708 $ 124,350 $ 1,160,598 $ 232,120 $ 1,392,717
Page 1 of 14 Hamilton School K-8 Phase District Basic Upgrades to Schools / Code Requirements Quantity Unit /Unit Soft s at 1 ADA path of travel walkways 1 LS $ 100,000 $ 100,000 $ 20,000 $ 14,400 $ 134,400
More information$12,769,962 $15,919,892 $9,184,256 $9,491,206 $0 $47,365,316
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationThis workbook is designed as a supplement to the 2018 Department memo labeled "Capital Projects Plan Template and Notices for Budget Year 2019.
Capital Projects Plan Template and Notices for Budget Year 2019 Amended August 21, 2018 Pursuant to IC 20-40-18-6 and IC 20-40-18-7 and in conjunction with the implementation of HEA 1009-2017 and HEA 1167-2018,
More informationPROPOSED TEN-YEAR CAPITAL IMPROVEMENT PLAN
2017/2018 YEAR 1 ESTIMATED FUND BALANCE 7/1/17 $ 1,795,000 $ - $ 209,000 $ 117,861 $ (333,878) $ (240,844) $ 642,513 $ (113,143) EXPECTED REVENUE ACTIVITY $ 1,014,000 $ 33,473 $ 49,500 $ - $ - $ - $ -
More information(TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I
SCHOOL PROJECTS (TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I 1 Sum of Prior Years and Estimate to Complete Project Estimates: PlanningIDesign Land Construction Total 1 Sum of FY
More informationGuaranteed Energy Savings
Guaranteed Energy Savings Mark J. Gallick Account Manager Shayne Homan, P.E., C.E.M. - Director of Energy Services Brian Moore, LEED GA, CIPE Engineering Operations Manager Michael Grochalski, E.I.T.,
More informationWeston Public Schools PROPOSED BUDGET OF EXPENDITURES
Weston Public Schools PROPOSED BUDGET OF EXPENDITURES 2012-2013 School Facilities 2012-2013 Budget Presentation Please refer to pages 111-117 in the Budget Binder Budget Preface The Past: Unreliable boilers
More informationLafayette Elementary
NC School District/430 Harnett County/Elementary School Lafayette Elementary Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5
More informationAction Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List
Action Item TO: PRESENTED BY: BOARD AGENDA ITEM: Board of Trustees and Superintendent of Schools Sid Albaugh, Assistant Superintendent Business Services Consideration of Approval of 2018 Measure A Facilities
More informationINTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION
INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local
More informationHarnett Central Middle
NC School District/430 Harnett County/Middle School Harnett Central Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus
More informationMocksville Elementary
NC School District/300 Davie County/Elementary School Mocksville Elementary Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus
More information