BRIDGE ALTERNATE STUDY No. 1

Size: px
Start display at page:

Download "BRIDGE ALTERNATE STUDY No. 1"

Transcription

1 BRIDGE ALTERNATE STUDY No. 1 RURAL STREAM CROSSING Prepared for U. S. Bridge Cambridge, Ohio Prepared by RICHLAND ENGINEERING LIMITED 29 North Park Street, Mansfield, Ohio / FAX 419/ January 2011

2 This page intentionally left blank.

3 BRIDGE ALTERNATE STUDY No. 1 RURAL STREAM CROSSING Content Page INTRODUCTION...1 EXISTING CONDITIONS...2 Existing Structure and Site Description...2 Site Geology and Subsurface Conditions...2 Bridge Hydraulics...2 PROPOSED WORK...3 Roadway and Drainage...3 Bridge Hydraulics...3 Structure Type Study...4 Scope Variations...8 LIFE CYCLE COST ANALYSIS...11 Maintenance Schedules for Alternatives...11 Economic Analysis...11 EVALUATION...13 Evaluation Matrix...14 Evaluation of Alternatives...15 Evaluation Matrix non-federal Aid Alternatives...17 Evaluation of Net Present Value of Alternatives...19 CONCLUSIONS...20 SUMMARY...21 i

4 APPENDICES Appendix A Attached Drawings Alternative 1 Three-span continuous concrete slab Site Plan Transverse Section Alternative 2 One-span precast concrete I-beam Site Plan Transverse Section Alternative 3 One-span steel half-through truss Site Plan Transverse Section Alternative 4 Three-span continuous composite box beam Site Plan Transverse Section Alternative 3A One-span steel half-through truss (LPA) Site Plan Transverse Section Alternative 4A Three-span non-composite box beam Site Plan Transverse Section Appendix B Construction Cost Estimates Appendix C Maintenance Schedules Appendix D Residual Values Appendix E Net Present Value Calculations Appendix F Life Cycle Costs Summaries ii

5 RICHLAND ENGINEERING LIMITED 29 North Park Street, Mansfield, Ohio / FAX 419/ BRIDGE ALTERNATE STUDY No. 1 RURAL STREAM CROSSING INTRODUCTION Due to the constraints of funding and the need to minimize costs, the initial construction cost of a project will always be the primary evaluation criterion for the owner. For many projects, that may be sufficient, but at times other criteria should also be considered. For this project, a number of evaluation criteria are available for comparing the proposed structures, including: Project Cost includes construction cost estimate based on the major cost drivers for each proposed structure, a contingency for project engineering costs, and right-of-way cost. Life-Cycle Cost includes all inspection, maintenance, construction, and right-of-way costs over the structure s 75-year design life. Bridge Hydraulics based on analysis of existing bridge opening and proposed (improved) bridge opening. Profile Grade includes existing vertical alignment, project length, proposed structure depth, and minimum clearance over the river. Right of Way a qualitative assessment of additional permanent right of way needed. Environmental Impacts changed or additional impacts due to construction methods. Construction Methods equipment and staging driven by the characteristics of the proposed structure. This study will develop alternatives for a rural stream crossing and evaluate them using these criteria. These evaluation criteria are further developed within this study. 1

6 EXISTING CONDITIONS Existing Structure and Site Description The existing structure was a three-span simple steel beam bridge with an asphalt-filled corrugated steel deck on steel capped-pile piers and abutments. The structure was 24 feet wide, face to face of railing, and 103 feet long. It was originally constructed as a temporary bridge. At the time of its replacement, the structure was 30 years old, and was in poor condition. The bridge and approach roadways are on a tangent alignment. The vertical alignment is rolling, with a rise over the bridge. There are flood plains and possible wetlands adjacent to the river and the approaches. An open ditch runs parallel to the forward (north) approach, and outlets into the river immediately downstream of the bridge. The average daily traffic was 350 vehicles per day, in two lanes about 10 feet wide. Site Geology and Subsurface Conditions The project site is located on a glaciated, gently rolling plain. Two different glaciers passed over the area and left variable but medium thickness of drift materials, 20 to 60 feet thick. The soils comprise sandy silt (A-4) and silt and clay (A-6). The underlying bedrock in the area shale or sandstone, at depths estimated at 90 to 100 feet below grade. Test borings through the approach roadway indicate 7.0 feet (test boring S-2) to 10.2 feet (test boring S-1) of fill. The predominantly cohesive soils between 10 and 45 feet deep (S-1) and between 10 and 65 feet deep (S-2) presented with relatively low density or consistency. Bedrock was not encountered in either of the borings, which were terminated at depths of 80 feet (S-1) to 90 feet (S-2). Because of relatively low density materials encountered in the upper 45 to 65 feet of soils, shallow foundations constructed on these strata could not provide sufficient load-bearing capacity to the proposed bridge structures. A deep foundations system should be used to support the bridge substructure loads. Bridge Hydraulics The existing structure is skewed approximately parallel to the river. The end slopes encroach on the waterway, constricting the flow through the bridge opening. The river flows in a well-defined channel across a wide flood plain. The banks of the river are wooded and not maintained. Large branches regularly catch on the piers, trapping other debris and restricting flow through the bridge opening. The state Drainage Design policy states that, bridges (low chord) will generally clear the water surface profile of the design year frequency flood. For highways with less than 2000 vehicles per day, the design year frequency is 10 years. The 100-year frequency flood is also evaluated to assure that the backwater caused by the structure does not exceed one foot. 2

7 The hydraulic analysis indicates that for the design year frequency flood, the velocity of the flow through the bridge opening is about five times greater than the velocity of the flow approaching the bridge opening. Increasing the bridge opening will reduce the velocity of the stream flow through the bridge opening, and will reduce the backwater elevation upstream of the structure. For the 100-year frequency flood, the existing approach roadway is overtopped, which reduces the flow through the bridge opening. PROPOSED WORK Roadway and Drainage The proposed horizontal alignment will match the existing alignment. The proposed vertical alignment will be about the same as existing, increased as needed to maintain clearance over the 10-year (design) high water elevation. The projected design year average daily traffic is about 500 vehicles per day. Based on the design year traffic, the required bridge width is two lanes 11 feet wide with two shoulders four feet wide, for a total bridge width of 30 feet, face to face of railing. The proposed typical pavement section comprises two, 11-foot lanes with four-foot shoulders, to match the bridge opening. At the ends of the project, the pavement will taper to the existing roadway width. Approach slabs provide a transition between the bridge and the approach roadway, and serve to span the backfill behind the abutments. They are generally required on DOT projects, but may be omitted on local projects. Approach guardrail will be installed at each corner of the bridge, with transitions to the railing on the bridge. Drainage will flow from the embankment to the adjacent flood plain, and make its way to the river. Structure drainage will be over the side. Steel drip edges will deflect the drainage from the railing posts and at the abutments. The ditch along the right forward approach will be relocated to the east to accommodate the improvements to the roadway. New rock channel protection will be placed on the end slopes at the rear and forward abutments, and at the outlet of new or relocated ditches. Bridge Hydraulics The existing abutments will be removed and the end slopes graded to 2H:1V normal to the skew of the new abutments. The end slope grading will begin at Elevation , just above the normal water elevation, and will not involve the placement of any new material below the 3

8 ordinary high water elevation (Elevation ), nor any excavation from below the normal water elevation. New spill-through abutments will be located at the top of the end slopes, which will enlarge the hydraulic opening somewhat. The low chord elevation on the proposed bridge will not be less than Elevation , the water surface profile of the design year frequency flood for the modified bridge opening. Given the tendency for large branches and other debris to collect on the existing piers, the owner s preference is for a clear-span structure. For a multi-span structure, the new piers will be capped-pile units kept as close to the river banks as possible. Structure Type Study Four structure types are considered for the replacement structure: three-span continuous concrete slab, one-span precast concrete I-beam, one-span half-through truss, and three-span continuous composite box beam. Each of these potential replacement structures, and their impact on the project length, approach roadway, river and hydraulics, right of way, environment, and construction, will be presented. Because the project was programmed as a Federal Aid project, each of the alternative structures will be designed to meet State standards. As such, each will include a reinforced-concrete deck, twin steel-tube railings, a 60psf allowance for future wearing surface, and will be designed for the AASHTO HS20-44 truck. A site plan and transverse section is provided for each of the alternative structures in Appendix A Attached Drawings. An estimate of the project cost for the initial construction project is provided for each alternative. The construction cost estimate is based on the major cost drivers for the proposed structure, as well as non-structure items that vary significantly between alternatives. Assuming that the major items comprise 80 percent of the construction cost, the cost based on those items, increased by 25 percent, provides a reasonable estimate of the construction cost. The construction cost estimates are based on 2002 state DOT bid tabulations, multiplied by 135 percent to account for inflation and approximate construction in The project cost estimates include the construction cost, a project engineering contingency of 15 percent of the construction cost, and an estimate of the cost for permanent and temporary right of way. The alternative structures are more fully described on the following pages. 4

9 Alternative 1 Three-span continuous concrete slab. The first alternative is a three-span continuous reinforced concrete slab bridge on capped-pile piers and abutments. To fit the local orientation of the river, the bridge will be skewed 18 degrees (left forward). The proposed superstructure spans are 36 feet, 45 feet, and 36 feet, center to center of bearings. The overall length of the bridge will be feet. The reinforced concrete slab will be 22 inches thick. The structure depth from the profile grade line will be 2.07 feet. The bridge will maintain about the same vertical alignment as the existing bridge, with a smooth curve fit over the bridge to fit smoothly into the approach pavement. The project work limits (end to end of new full-depth pavement) will be 450 feet. The low chord elevation of the bridge is Elevation , clearing the design year flood by 1.9 feet. Foundation recommendations The bridge superstructure will be integral with the capped-pile abutments. The abutments and wingwalls will be founded on a single row of 12-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the abutment piles is 90 feet. The piers will be founded on 16-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the pier piles is 135 feet. Initial construction project costs The initial construction cost for this structure is estimated to be $753,000 (2010). Project engineering costs (design engineering, construction engineering, and construction administration) are estimated at $113,000. Right of way acquisition for this project is estimated to cost $10,000. The total project cost for the initial construction project is estimated to be $876,000 (2010). 5

10 Alternative 2 One-span precast concrete I-beam. The second alternative is a one-span precast concrete I-beam bridge on spill-through capped-pile abutments. To fit the local orientation of the river, the bridge will be skewed 18 degrees (left forward). The proposed superstructure will span 114 feet, center to center of bearings. The overall length of the bridge will be feet. The reinforced concrete deck will be 8½ inches thick. Four AASHTO Type 4 beams, 72 inches tall, will support the span. The structure depth from the profile grade line will be 7.07 feet. To maintain clearance over the design year flood, the bridge will be at the crest of a vertical curve 700 feet long. The roadway grade will be raised about 3.3 feet in the vicinity of the bridge. The project work limits (end to end of new full-depth pavement) will be 1350 feet. The low chord elevation of the bridge is Elevation , clearing the design year flood by 0.3 feet. Foundation recommendations The bridge superstructure will be semi-integral with the capped-pile abutments. The abutments and wingwalls will be founded on two rows of 14-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the abutment piles is 90 feet. Initial construction project costs The initial construction cost for this structure is estimated to be $972,000 (2010). Project engineering costs are estimated at $145,800. Right of way acquisition for this project is estimated to cost $25,000. The total project cost for the initial construction project is estimated to be $1,142,800 (2010). 6

11 Alternative 3 One-span steel half-through truss. The third alternative is a one-span galvanized steel half-through truss bridge on capped-pile abutments. Because the skew is too much for offset trusses (skewed floorbeams) but not enough for offset (square) floorbeams, the bridge will be made square and extended to span the additional distance. The proposed superstructure span is 116 feet center to center of bearings. The overall length of the bridge will be 120 feet. The reinforced concrete slab will be 8½ inches thick. To minimize the superstructure depth, the steel stringers will frame into the floorbeams. The floorbeams will be raised (framed between the trusses) to eliminate framing below the low chord elevation. The structure depth from the profile grade line will be 3.56 feet. The bridge will maintain about the same vertical alignment as the existing bridge, and will be level across the length of the bridge. The project work limits (end to end of new full-depth pavement) will be 450 feet. The low chord elevation of the bridge is Elevation , clearing the design year flood by 0.3 feet. The joint between the bridge deck and the abutment backwall will be armored with structural steel and sealed with an elastomeric strip seal. Foundation recommendations The bridge superstructure will be supported on capped-pile abutments. The abutments and wingwalls will be founded on two rows of 14-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the abutment piles is 90 feet. Initial construction project costs The initial construction cost for this structure is estimated to be $835,000 (2010). Project engineering costs are estimated at $104,400. Right of way acquisition for this project is estimated to cost $10,000. The total project cost for the initial construction project is estimated to be $949,400 (2010). 7

12 Alternative 4 Three-span continuous composite box beam. The fourth alternative is a three-span continuous composite box-beam bridge on capped-pile piers and abutments. To fit the local orientation of the river, the bridge will be skewed 18 degrees (left forward). The proposed superstructure spans are 37.5 feet, 40.5 feet, and 37.5 feet, center to center of substructure units. The overall length of the bridge will be feet. The prestressed concrete box beams will be 17 inches thick. The cast-in-place reinforced concrete deck will be 6 inches thick. The structure depth from the profile grade line will be 2.16 feet. The bridge will maintain about the same vertical alignment as the existing bridge, with a smooth curve fit over the bridge to fit smoothly into the approach pavement. The project work limits (end to end of new full-depth pavement) will be 450 feet. The low chord elevation of the bridge is Elevation , clearing the design year flood by 1.8 feet. Foundation recommendations The bridge superstructure will be integral with the capped-pile abutments. The abutments and wingwalls will be founded on a single row of 12-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the abutment piles is 90 feet. The piers will be founded on 16-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the pier piles is 135 feet. Initial construction project costs The initial construction cost for this structure is estimated to be $729,000 (2010). Project engineering costs are estimated at $109,400. Right of way acquisition for this project is estimated to cost $10,000. The total project cost for the initial construction project is estimated to be $848,400 (2010). Scope Variations Variations on two of the alternatives are also presented. These variations do not meet the requirements for a Federal Aid project, but are often used on local roads due to their lower costs. Each of the variations a one-span steel half-through truss with asphalt-filled corrugated metal deck, and a three-span non-composite box beam with asphalt wearing surface includes deepbeam railing, a 60psf allowance for future wearing surface, and is designed for the AASHTO HS20-44 truck. No approach slabs are included in these variations. 8

13 Alternative 3A One-span steel half-through truss. A variation on the third alternative is a one-span steel half-through truss bridge on capped-pile abutments designed to local standards. Similar to the Federal Aid truss alternative, the bridge will be made square and extended to span the additional distance. The proposed superstructure span is 116 feet center to center of bearings. The overall length of the bridge will be 120 feet. In lieu of the reinforced concrete slab, the deck will comprise galvanized corrugated flooring with asphalt fill and wearing surface. The flooring and wearing surface thickness will be will be 5 inches at the deck edge and 8 inches at the centerline. To minimize the superstructure depth, the steel stringers will frame into the floorbeams. The floorbeams will be raised (framed between the trusses) to eliminate framing below the low chord elevation. This will reduce the structure depth from the profile grade line by 0.36 feet, for a depth of 3.20 feet. The bridge will maintain about the same vertical alignment as the existing bridge, and will be level across the length of the bridge. The project work limits (end to end of new full-depth pavement) will be 450 feet. The low chord elevation of the bridge is Elevation , clearing the design year flood by 0.6 feet. In lieu of the twin steel-tube railing on the bridge, standard guardrail will be mounted to the truss verticals and diagonals. The joint between the bridge deck and the abutment backwall will be open. Foundation recommendations The bridge superstructure will be supported on capped-pile abutments. The abutments and wingwalls will be founded on two rows of 14-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the abutment piles is 90 feet. Initial construction project costs The initial construction cost for this structure is estimated to be $673,000 (2010). Project engineering costs are estimated at $101,000. Right of way acquisition for this project is estimated to cost $10,000. The total project cost for the initial construction project is estimated to be $784,000 (2010). 9

14 Alternative 4A Three-span non-composite box beam. A variation on the fourth alternative is a three-span non-composite box-beam bridge on capped-pile piers and abutments, designed to local standards. This is presented for a separate comparison. To fit the local orientation of the river, the bridge will be skewed 18 degrees (left forward). The proposed superstructure is three spans of 38.5 feet, center to center of substructure units. The overall length of the bridge will be feet. The prestressed concrete box beams will be 17 inches thick. In lieu of the reinforced concrete slab, the bridge will have waterproofing membrane and an asphalt wearing surface applied directly to the box beams. The asphalt wearing surface will be a minimum of 3 inches thick at mid-span to about 4 inches thick at the piers and abutments. The structure depth from the profile grade line will be 2.00 feet. The bridge will maintain about the same vertical alignment as the existing bridge, with a smooth curve fit over the bridge to fit smoothly into the approach pavement. The project work limits (end to end of new full-depth pavement) will be 450 feet. The low chord elevation of the bridge is Elevation , clearing the design year flood by 2.0 feet. In lieu of the twin steel-tube railing on the bridge, standard guardrail will be mounted posts attached to the fascia box beams. The joint between the bridge deck and the abutment backwall will be sealed with an elastomeric compression seal set below the asphalt wearing surface. Foundation recommendations The bridge superstructure will be supported on capped-pile abutments. The abutments and wingwalls will be founded on a single row of 12-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the abutment piles is 90 feet. The piers will be founded on 16-inch diameter cast-in-place reinforced concrete piles. The estimated pay length of the pier piles is 135 feet. Initial construction project costs The initial construction cost for this structure is estimated to be $574,000 (2010). Project engineering costs are estimated at $86,100. Right of way acquisition for this project is estimated to cost $10,000. The total project cost for the initial construction project is estimated to be $670,100 (2010). 10

15 LIFE CYCLE COST ANALYSIS The life-cycle cost includes all inspection, repair, construction, and right-of-way costs over 75- year time period. The 75-year period was selected as the normal design life of a structure. The study year of 2010 was selected as the initial construction project year. Maintenance Schedules for Alternatives The life-cycle cost analysis is based on maintaining the bridge in fair condition. A repair or rehabilitation project would be performed to improve the condition before or just after a coding item falls below the minimum fair condition level. The following are estimated maintenance intervals and work activities required to maintain the minimum condition levels: A bare concrete deck wearing surface should be sealed at 10-year intervals between overlays. Patch concrete deck surface at 10-year intervals with the patching area increasing with the age of the deck. Asphalt wearing surfaces should be milled and overlaid at 10-year intervals. A superplasticized dense concrete (SDC) overlay should be placed at 20-year intervals on any concrete deck. Any previous overlay would be removed. Asphalt-filled corrugated steel decks should be replaced at 20-year intervals. Replace the steel stringers with deck replacement. Asphalt overlays should be removed, waterproofing replaced, and new overlay placed at 20- year intervals. Minor structure rehabilitation and repair work should be performed at 20-year intervals at the same time as the deck overlay work. The work may include steel deterioration repair, replacing joint seals, erosion repair, concrete patching, and concrete sealing. A reinforced concrete deck should be replaced after 50 years in service. (Does not apply to concrete slab bridges.) Prestressed concrete beams composite with reinforced concrete decks are assumed be replaced with the deck replacement. Steel trusses should be disassembled, cleaned and re-galvanized, and re-erected after 40 to 50 years (coinciding with deck replacement). New floorbeams and stringers should be installed with the re-used trusses. Maintenance Timelines Maintenance schedule timelines are presented included in Appendix C Maintenance Schedules for the different alternative bridge replacement projects. Economic Analysis Inspection and Maintenance Costs The economic analysis used $500 per year for annual bridge inspection costs for personnel for the concrete bridge alternatives, and $700 per year for the steel truss alternatives. The multi-span bridges include an annual maintenance cost of $2,500 for clearing debris from the piers to maintain the channel opening. 11

16 Construction Costs Preliminary designs were developed for each construction or maintenance project, and quantities estimated. Unit costs were based on 2002 state DOT bid tabulations, previous similar bid tabulations, and judgment, and were multiplied by 135 percent to account for inflation and approximate construction in Each construction project cost includes contingency, design engineering, right-of-way acquisition, construction engineering, and construction administration costs. Opinions of probable project costs for the initial and interim construction projects are included in Appendix B Construction Cost Estimates. Residual Value The residual value is the value of the constructed project at the end of the 75- year study period. This 75-year period represents the end of life for the three-span slab bridge. For the other three concrete-decked bridges, the 75-year point is halfway through the service life of the replacement deck or superstructure, so the residual value of the superstructure is 50 percent of its construction cost. For the scope-variation structures, the 75-year point is 35 years into the 40-year service life of the replacement superstructure, so the residual value of the superstructure is 12.5 percent of its construction cost. The residual value of the substructure is 25 percent of the substructure construction cost for each alternative. Opinions of residual values are included in Appendix D Residual Values. Time Value of Money Capital investment decisions usually involve comparison of benefits. However, money paid at two different points of time has different values. This difference in value is accounted for by comparing the net present value (NPV) of alternative projects using an appropriate discount rate. Discount Rate The annual discount rate used in the analysis is 2.7 percent. The value is from the December 2009 Office of Management and Budget (OMB) Circular No A-94, Appendix C, real discount rate. FHWA literature and several life-cycle cost analyses reference OMB Circular No. A-94. The December 2009 data is the latest available information. Net Present Value The net present value (NPV), or present worth, analysis method was used to compare the mutually exclusive alternatives at the study year NPV = n t = RCFt 0 ( 1+ i) t RCF t = Real Cash Flow i = Annual Discount Rate n = 75 years The NPV is independent of inflation rate. Calculations of the NPV for each of the alternatives are presented in Appendix E Net Present Value Calculations. 12

17 EVALUATION Matrices on the following pages present the evaluation criteria applied to the proposed structures (and separately to their non-federal Aid variations) in a tabular format. A narrative following each matrix highlights the advantages and disadvantages of each alternative. 13

18 Criterion Alternative 1 3-span slab Proposed Structures Alternative 2 1-span precast I-beam Alternative 3 1-span half-through truss Alternative 4 3-span composite Box Beam Initial Project Cost $876,000 $1,143,000 $949,400 $848,400 Life-Cycle Cost (NPV) $1,124,000 $1,432,000 $1,212,000 $1,189,000 Project Length 450 feet 1350 feet 450 feet 450 feet Foundations 4680 ft of driven piles 5760 ft of driven piles 3960 ft of driven piles 4770 ft of driven piles Bridge Hydraulics Profile Grade Right of Way Environmental Impact Construction Method Clears design year flood by 1.9' Clears 100-year flood 100-year flood overtops approach roadway Piers in river Similar to existing Structure depth 2.07 Strip take on one side at bridge Pier construction in river 404 permit required for temporary causeway Temporary causeway required for pier construction Temporary shoring or significant falsework required for slab construction Susceptible to flooding Increased risk Clears design year flood by 0.3' 100-year flood forced through bridge opening Increased backwater Increased velocity No piers to trap debris Increased by over 3.3 feet Structure depth 7.07 Strip take required on both sides of roadway Additional embankment construction for approach roadway 404 permit required for temporary work area Long beams difficult to transport to remote sites Heavy beams (60 tons) require heavy crane (500+ tons ) for beam erection Temporary work area along river required for beam erection Clears design year flood by 0.3' 100-year flood overtops approach roadway No piers to trap debris Similar to existing Structure depth 3.56 Strip take on one side at bridge No work in river Truss shipped in multiple units for field assembly and erection Medium crane (250 tons) needed for erection Crane works from approach roadway Clears design year flood by 1.8' Clears 100-year flood 100-year flood overtops approach roadway Piers in river Similar to existing Structure depth 2.16 Strip take on one side at bridge Pier construction in river 404 permit required for temporary causeway Temporary causeway required for pier construction and beam erection Medium crane (250 tons) needed for erection Susceptible to flooding Increased risk 14

19 Evaluation of Alternatives Advantages and disadvantages of the various proposed structure alternatives include: Alternative 1 Three-span continuous concrete slab Advantages Second-lowest initial construction cost for concrete-decked bridge Lowest life-cycle cost for concrete-decked bridge Clears design year and 100-year floods Maintains similar vertical alignment Least structure depth Least right-of-way take Disadvantages Piers in the river can trap debris and increase flood risk Pier construction requires temporary causeway and work areas in the river Work in the river requires 404 permit from Army Corps of Engineers Significant falsework and/or temporary shoring required for slab construction Work in river is susceptible to flooding Alternative 2 One-span precast concrete I-beam Advantages No piers to trap debris Disadvantages Highest initial construction cost for concrete-decked bridge Highest life-cycle cost for concrete-decked bridge Substantial rise in vertical alignment Greatest structure depth Raised approach roadway forces 100-year flood through bridge opening (not over approach roadway), increasing velocity Increased backwater, and flood risk Greatest amount right-of-way impact Temporary right of way required for staging area for work area for crane for beam erection Beam erection requires temporary work area along the river Work in the river requires 404 permit from Army Corps of Engineers Length of beams (116 feet) difficult to transport to remote sites Heavy beams (60 tons/beam) may damage local roads Heavy crane (500 tons or more) required for beam erection Longest construction time 15

20 Alternative 3 One-span steel half-through truss Advantages No piers to trap debris Maintains similar vertical alignment Moderate structure depth Least right-of-way take No work required in the river Truss shipped in sections for field assembly Medium crane (250 tons) required for truss erection from behind abutment Staging can be accomplished in approach roadway Life-cycle cost about the same as for Alternative 4 Disadvantages Second highest initial construction cost for concrete-decked bridge Alternative 4 Three-span continuous composite box beam Advantages Lowest initial construction cost for concrete-decked bridge Second-lowest life-cycle cost for concrete-decked bridge Clears design year and 100-year floods Maintains similar vertical alignment Second-least structure depth Least right-of-way take Disadvantages Piers in the river can trap debris and increase flood risk Pier construction requires temporary causeway and work areas in the river Work in the river requires 404 permit from Army Corps of Engineers Work in river is susceptible to flooding 16

21 Criterion Alternative (LPA) Structures Alternative 3A 1-span half-through truss Alternative 4A 3-span non-composite box beam Construction Cost $784,000 $670,100 Life-Cycle Cost (NPV) $1,175,000 $962,000 Project Length 450 feet 450 feet Foundations 3600 ft of driven piles 4590 ft of driven piles Bridge Hydraulics Clears design year flood by 0.6' 100-year flood overtops approach roadway No piers to trap debris Profile Grade Similar to existing Structure depth 3.20 Right of Way Strip take on one side at bridge Clears design year flood by 2.0' Clears 100-year flood 100-year flood overtops approach roadway Piers in river Similar to existing Structure depth 2.00 Strip take on one side at bridge Environmental Impact No work in river Pier construction in river 404 permit required for temporary causeway Construction Method Truss shipped in multiple units for field assembly and erection Medium crane (250 tons) needed for erection Crane works from approach roadway No cure time for asphalt bridge deck Temporary causeway required for pier construction and beam erection Medium crane (250 tons) needed for erection Susceptible to flooding Increased risk 17

22 Alternative 3A One-span steel half-through truss (LPA) Advantages No piers to trap debris Maintains similar vertical alignment Moderate structure depth Least right-of-way take No work required in the river Truss shipped in sections for field assembly Medium crane (250 tons) required for truss erection from behind abutment Staging can be accomplished in approach roadway Asphalt wearing surface on corrugated metal bridge deck needs no cure time Shortest construction time Disadvantages Higher initial construction cost for non-federal Aid bridge No approach slab can develop dip at ends of the bridge Asphalt wearing surface on corrugated metal bridge deck likely needs replaced before concrete bridge deck Without a concrete deck, railing must be attached to stringers (which requires additional diaphragms) or to the truss itself (which may not meet minimum railing requirements) Alternative 4A Three-span non-composite box beam (LPA) Advantages Lowest initial construction cost Lowest life-cycle cost Clears design year and 100-year floods Maintains similar vertical alignment Low structure depth Least right-of-way take Disadvantages Piers in the river can trap debris and increase flood risk Pier construction requires temporary causeway and work areas in the river Work in the river requires 404 permit from Army Corps of Engineers Work in river is susceptible to flooding No approach slab can develop dip at ends of the bridge Not significantly faster to construct than the concrete-decked alternatives 18

23 Evaluation of Net Present Value of Alternatives For the Federal Aid alternatives, the alternative with the lowest life-cycle cost is the three-span continuous concrete slab. The low life-cycle cost reflects the fact that the slab bridge is the only alternative that does not see a major rehabilitation in its lifetime. The Federal Aid alternative with the second-lowest life-cycle cost is the three-span continuous composite box beam. The life-cycle cost of the one-span steel half-through truss is about 3 percent higher than the composite box beam. Since the initial construction of the truss is about 12 percent higher than the box beam, the reduced difference in costs largely reflects the difference in maintenance costs (to keep the piers free of debris). In addition, the truss has a salvage value beyond the end of the service life for the existing deck, in that the truss could be reused in another application or sold for the scrap value, while the box beam structure only has no value beyond its current service. Between the two scope variation alternatives, the three-span non-composite box beam has the lower life-cycle cost. It should be noted that the life-cycle cost for the one-span steel half-through truss with a concrete deck is only about three percent greater than for the one-span steel half-through truss with an asphalt-filled corrugated steel deck. This indicates that the additional initial cost of a concrete deck affords lower maintenance costs and defers rehabilitation costs, which significantly lowers the life-cycle costs for the structure. 19

24 CONCLUSIONS Four structure types have been evaluated for the replacement structure: a three-span continuous concrete slab, a one-span precast concrete I-beam, a one-span half-through truss, and a threespan continuous composite box beam. Each of these structures was designed to meet AASHTO design criteria, and to similar levels of detail, to allow them to be compared on a number of criteria. Each structure, in particular, included a reinforced concrete deck (or superstructure), reinforced concrete approach slabs, and bridge railings meeting NCHRP Level TL-4. Scope variations on the truss bridge and the three-span composite box beam bridge a similar half-through truss span and a three-span box non-composite beam bridge were also designed, but to lesser specifications, as a bridge replacement using entirely local monies might be designed. The primary differences from the Federal Aid alternatives are no concrete bridge deck, no approach slabs, and deep-beam guardrail on the bridge (NCHRP Level TL-2). The four concrete-decked structures, and their impact on the project length, approach roadway, river and hydraulics, right of way, environment, and construction, are presented and compared to each other: The structure with the lowest initial construction cost is the three-span composite box beam (Alternative 4), which also has the second-lowest life-cycle cost. This structure, however, does not satisfy the owner preference for a clear-span structure. The structure with the second-lowest initial construction cost (and the lowest life-cycle cost) is the three-span reinforced concrete slab (Alternative 1). This structure also does not satisfy the owner preference for a clear-span structure. The initial construction cost of the one-span truss structure (Alternative 3) is estimated to be about 12 percent higher than the cost of the three-span composite box beam, and about 8 percent higher than the cost of the three-span slab. The life-cycle cost is estimated to be about 8 percent higher than the three-span slab. This structure is the lowest-cost Federal Aid (both initial construction and life-cycle) which meets the owner preference for a clear-span, and maintains the existing vertical and horizontal alignment, minimizing the amount of approach roadway work and right-of-way acquisition needed. The precast concrete I-beam structure (Alternative 2) has the highest estimated initial construction cost, about 20 percent higher than the truss (Alternative 3) and about 35 percent higher than the lowest-cost alternative. The structure itself, however, has the second-lowest construction cost per square foot, indicating that cost of raising the approach roadway has a significant impact on the total cost of construction. This structure also has the highest lifecycle cost, about 27 percent higher than that of the three-span slab bridge. 20

25 The two scope variations are also presented and compared to each other: The three-span non-composite box-beam structure (Alternative 4A) has the lowest initial construction cost (and life-cycle cost) of any of the alternatives or variations. This structure, however, does not satisfy the owner preference for a clear-span structure. The initial construction cost for the one-span truss variation (Alternative 3A) is about 17 percent higher than that of the three-span non-composite box beam (Alternative 4A) and 8-12 percent less than that of the three-span concrete-decked structures (Alternatives 1 and 4). The clear-span structure improves bridge hydraulics when compared to a multi-span structure. The time of construction can be reduced, since there is no deck concrete to form, place, and cure. The life-cycle cost for the one-span truss variation (Alternative 3A) is about 22 percent higher than that of the three-span non-composite box beam (Alternative 4A), and only slightly (3 percent) less than that of the one-span concrete-decked truss (Alternative 3). The clear-span structure improves bridge hydraulics when compared to a multi-span structure. The initial time of construction can be reduced, since there is no deck concrete to form, place, and cure. However, the multiple deck replacements (three vs. one) over the lifetime of the variation would nullify the initial reduction in detour time. SUMMARY Based on the owner preference for a clear-span bridge, the lowest cost one-span bridge is the half-through steel truss bridge. This is, in fact, what the owner selected, and the structure was constructed in

26

27 APPENDICES

28

29 Appendix A Attached Drawings

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55 Appendix B Construction Cost Estimates

56 SUMMARY OF CONSTRUCTION PROJECT COSTS Project Costs Project Construction Project Engineering Right of Way Total Cost Year 1-A $ 753,000 $ 113,000 $ 10,000 $ 876, B $ 7,000 $ 1,100 $ - $ 8, C $ 72,000 $ 10,800 $ - $ 82, D $ 23,000 $ 3,500 $ - $ 26, E $ 162,000 $ 24,300 $ - $ 186, D $ 23,000 $ 3,500 $ - $ 26, F $ 87,000 $ 13,100 $ - $ 100, D $ 23,000 $ 3,500 $ - $ 26, Total $ 1,332,800 2-A $ 972,000 $ 145,800 $ 25,000 $ 1,142, B $ 8,000 $ 1,200 $ - $ 9, C $ 79,000 $ 11,900 $ - $ 90, D $ 25,000 $ 3,800 $ - $ 28, E $ 95,000 $ 14,300 $ - $ 109, F $ 582,000 $ 87,300 $ 5,000 $ 674, B $ 8,000 $ 1,200 $ - $ 9, C $ 79,000 $ 11,900 $ - $ 90, Total $ 2,155,400 3-A $ 835,000 $ 104,400 $ 10,000 $ 949, B $ 7,000 $ 900 $ - $ 7, C $ 73,000 $ 9,100 $ - $ 82, D $ 23,000 $ 2,900 $ - $ 25, E $ 87,000 $ 10,900 $ - $ 97, F $ 563,000 $ 70,400 $ - $ 633, B $ 7,000 $ 900 $ - $ 7, C $ 73,000 $ 9,100 $ - $ 82, Total $ 1,886,600 4-A $ 729,000 $ 109,400 $ 10,000 $ 848, B $ 7,000 $ 1,100 $ - $ 8, C $ 72,000 $ 10,800 $ - $ 82, D $ 23,000 $ 3,500 $ - $ 26, E $ 86,000 $ 12,900 $ - $ 98, F $ 524,000 $ 78,600 $ 5,000 $ 607, B $ 7,000 $ 1,100 $ - $ 8, C $ 72,000 $ 10,800 $ - $ 82, Total $ 1,763,200

57 SUMMARY OF CONSTRUCTION PROJECT COSTS Project Costs Project Construction Project Engineering Right of Way Total Cost Year 3A-A $ 673,000 $ 101,000 $ 10,000 $ 784, A-B $ 13,000 $ 2,000 $ - $ 15, A-C $ 206,000 $ 30,900 $ - $ 236, A-B $ 13,000 $ 2,000 $ - $ 15, A-D $ 432,000 $ 64,800 $ - $ 496, A-B $ 13,000 $ 2,000 $ - $ 15, A-C $ 206,000 $ 30,900 $ - $ 236, A-B $ 13,000 $ 2,000 $ - $ 15, Total $ 1,814,600 4A-A $ 574,000 $ 86,100 $ 10,000 $ 670, A-B $ 13,000 $ 2,000 $ - $ 15, A-C $ 45,000 $ 6,800 $ - $ 51, A-B $ 13,000 $ 2,000 $ - $ 15, A-D $ 358,000 $ 53,700 $ 5,000 $ 416, A-B $ 13,000 $ 2,000 $ - $ 15, A-C $ 45,000 $ 6,800 $ - $ 51, A-B $ 13,000 $ 2,000 $ - $ 15, Total $ 1,250,400

58 Alternative 1-3-span Concrete Slab Cost Project Description Quantity Unit Unit Extended 1-A 6" Bituminous Aggregate Base 124 Cu Yd $ $ 12,400 6" Aggregate Base 129 Cu Yd $ $ 4,515 6" Stabilized Crushed Aggregate 45 Cu Yd $ $ " Intermediate Course 35 Cu Yd $ $ 5, " Surface Course 25 Cu Yd $ $ 4,375 Sediment & Erosion Control 1 Each $ 7, $ 7,400 Approach Guardrail Ft $ $ 3,375 12" CIP RC Piling, Driven 2520 Ft $ 7.50 $ 18,900 12" CIP RC Piling, Furnished 2800 Ft $ 8.50 $ 23,800 16" CIP RC Piling, Driven 2160 Ft $ $ 48,600 16" CIP RC Piling, Furnished 2400 Ft $ $ 48,000 Reinforcing Steel Pound $ 0.55 $ 24,750 Superstructure Concrete 241 Cu Yd $ $ 180,750 Abutment Concrete 53 Cu Yd $ $ 21,200 Pier Cap Concrete 15 Cu Yd $ $ 12,000 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 12" thick 100 Sq Yd $ $ 11,000 Subtotal $ 445,965 Design Contingency Add 25% $ 111,491 Total (2002) $ 557,456 1-A Total (2010) $ 753,000

59 Alternative 1-3-span Concrete Slab Cost Project Description Quantity Unit Unit Extended 1-B Structure Sealing Concrete Surfaces 495 Sq Yd $ 8.00 $ 3,960 Incidentals Mobilization Lump Sum $ - $ - Subtotal $ 3,960 Design Contingency Add 35% $ 1,386 Total (2002) $ 5,346 1-B Total (2010) $ 7,000

60 Alternative 1-3-span Concrete Slab Cost Project Description Quantity Unit Unit Extended 1-C Structure New SDC Overlay 495 Sq Yd $ $ 12,375 Surface Preparation 495 Sq Yd $ $ 17,325 SDC Overlay (Variable Thick, 5%) 2.1 Cu Yd $ $ 315 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 39,515 Design Contingency Add 35% $ 13,830 Total (2002) $ 53,345 1-C Total (2010) $ 72,000

61 Alternative 1-3-span Concrete Slab Cost Project Description Quantity Unit Unit Extended 1-D Structure Patching Concrete Deck (5%) 25 Sq Yd $ $ 6,250 Sealing Concrete Surfaces 495 Sq Yd $ 8.00 $ 3,960 Incidentals Maintaining Traffic Lump Sum $ 2, $ 2,500 Mobilization Lump Sum $ - $ - Subtotal $ 12,710 Design Contingency Add 35% $ 4,449 Total (2002) $ 17,159 1-D Total (2010) $ 23,000

62 Alternative 1-3-span Concrete Slab Cost Project Description Quantity Unit Unit Extended 1-E Structure Approach Slab Removed 100 Sq Yd $ $ 2,200 Rebuild Deck Edge 240 Sq Ft $ $ 8,400 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 12" thick 100 Sq Yd $ $ 11,000 New SDC Overlay 395 Sq Yd $ $ 9,875 Surface Preparation 395 Sq Yd $ $ 13,825 SDC Overlay (Variable Thick, 10%) 3.3 Cu Yd $ $ 495 Remove Existing Overlay 395 Sq Yd $ $ 5,925 Incidentals Maintaining Traffic Lump Sum $ 10, $ 10,000 Field Office 2 Month $ 2, $ 4,200 Mobilization Lump Sum $ 4, $ 4,000 Subtotal $ 88,670 Design Contingency Add 35% $ 31,035 Total (2002) $ 119,705 1-E Total (2010) $ 162,000

63 Alternative 1-3-span Concrete Slab Cost Project Description Quantity Unit Unit Extended 1-F Structure New SDC Overlay 495 Sq Yd $ $ 12,375 Surface Preparation 495 Sq Yd $ $ 17,325 SDC Overlay (Variable Thick, 20%) 8.3 Cu Yd $ $ 1,245 Remove Existing Overlay 495 Sq Yd $ $ 7,425 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 47,870 Design Contingency Add 35% $ 16,755 Total (2002) $ 64,625 1-F Total (2010) $ 87,000

64 Alternative 2-1-span Precast I-beam Cost Project Description Quantity Unit Unit Extended 2-A Embankment Construction 7500 Cu Yd $ 4.00 $ 30,000 6" Bituminous Aggregate Base 554 Cu Yd $ $ 55,400 6" Aggregate Base 578 Cu Yd $ $ 20,230 6" Stabilized Crushed Aggregate 193 Cu Yd $ $ 3, " Intermediate Course 155 Cu Yd $ $ 23, " Surface Course 111 Cu Yd $ $ 19,425 Sediment & Erosion Control 1 Each $ 7, $ 7,400 Approach Guardrail 1200 Ft $ $ 12,000 14" CIP RC Piling, Driven 5760 Ft $ 9.00 $ 51,840 14" CIP RC Piling, Furnished 6400 Ft $ $ 70,400 Reinforcing Steel Pound $ 0.55 $ 26,950 Superstructure Concrete 181 Cu Yd $ $ 95,025 Abutment Concrete 135 Cu Yd $ $ 50,625 Draped Strand Beams, AASHTO Type 4 (Mod) 4 Each $ 17, $ 70,000 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 15" thick 167 Sq Yd $ $ 20,875 Subtotal $ 576,030 Design Contingency Add 25% $ 144,008 Total (2002) $ 720,038 2-A Total (2010) $ 972,000

65 Alternative 2-1-span Precast I-beam Cost Project Description Quantity Unit Unit Extended 2-B Structure Sealing Concrete Surfaces 558 Sq Yd $ 8.00 $ 4,464 Incidentals Mobilization Lump Sum $ - $ - Subtotal $ 4,464 Design Contingency Add 35% $ 1,562 Total (2002) $ 6,026 2-B Total (2010) $ 8,000

66 Alternative 2-1-span Precast I-beam Cost Project Description Quantity Unit Unit Extended 2-C Structure New SDC Overlay 558 Sq Yd $ $ 13,950 Surface Preparation 558 Sq Yd $ $ 19,530 SDC Overlay (Variable Thick, 5%) 2.3 Cu Yd $ $ 345 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 43,325 Design Contingency Add 35% $ 15,164 Total (2002) $ 58,489 2-C Total (2010) $ 79,000

67 Alternative 2-1-span Precast I-beam Cost Project Description Quantity Unit Unit Extended 2-D Structure Patching Concrete Deck (5%) 28 Sq Yd $ $ 7,000 Sealing Concrete Surfaces 558 Sq Yd $ 8.00 $ 4,464 Incidentals Maintaining Traffic Lump Sum $ 2, $ 2,500 Mobilization Lump Sum $ - $ - Subtotal $ 13,964 Design Contingency Add 35% $ 4,887 Total (2002) $ 18,851 2-D Total (2010) $ 25,000

68 Alternative 2-1-span Precast I-beam Cost Project Description Quantity Unit Unit Extended 2-E Structure New SDC Overlay 558 Sq Yd $ $ 13,950 Surface Preparation 558 Sq Yd $ $ 19,530 SDC Overlay (Variable Thick, 10%) 4.7 Cu Yd $ $ 705 Remove Existing Overlay 558 Sq Yd $ $ 8,370 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 52,055 Design Contingency Add 35% $ 18,219 Total (2002) $ 70,274 2-E Total (2010) $ 95,000

69 Alternative 2-1-span Precast I-beam Cost Project Description Quantity Unit Unit Extended 2-F Approach Sediment & Erosion Control 1 Each $ 7, $ 7,400 Structure Portions of Structure Removed Lump Sum $ 50, $ 50,000 Approach Slab Removed 167 Sq Yd $ $ 3,674 Reinforcing Steel Pound $ 0.55 $ 22,550 Superstructure Concrete 181 Cu Yd $ $ 95,025 Draped Strand Beams, AASHTO Type 4 4 Each $ 17, $ 70,000 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 15" thick 167 Sq Yd $ $ 20,875 Incidentals Maintaining Traffic Lump Sum $ 15, $ 15,000 Field Office 3 Month $ 2, $ 6,300 Mobilization Lump Sum $ 10, $ 10,000 Subtotal $ 319,574 Design Contingency Add 35% $ 111,851 Total (2002) $ 431,425 2-F Total (2010) $ 582,000

70 Alternative 3-1-span Half-through truss Cost Project Description Quantity Unit Unit Extended 3-A 6" Bituminous Aggregate Base 124 Cu Yd $ $ 12,400 6" Aggregate Base 129 Cu Yd $ $ 4,515 6" Stabilized Crushed Aggregate 45 Cu Yd $ $ " Intermediate Course 35 Cu Yd $ $ 5, " Surface Course 25 Cu Yd $ $ 4,375 Sediment & Erosion Control 1 Each $ 3, $ 3,700 Approach Guardrail Ft $ $ 3,375 14" CIP RC Piling, Driven 3960 Ft $ 9.00 $ 35,640 14" CIP RC Piling, Furnished 4400 Ft $ $ 48,400 Reinforcing Steel Pound $ 0.55 $ 24,200 Superstructure Concrete 112 Cu Yd $ $ 70,000 Abutment Concrete 148 Cu Yd $ $ 55,500 Strip Sealed Expansion Joint 60 Ft $ $ 12,000 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 12" thick 100 Sq Yd $ $ 11,000 Steel Truss, FBs, Stringers, etc. 1 Each $ 185, $ 185,000 Subtotal $ 495,005 Design Contingency Add 25% $ 123,751 Total (2002) $ 618,756 3-A Total (2010) $ 835,000

71 Alternative 3-1-span Half-through truss Cost Project Description Quantity Unit Unit Extended 3-B Structure Sealing Concrete Surfaces 500 Sq Yd $ 8.00 $ 4,000 Incidentals Mobilization Lump Sum $ - $ - Subtotal $ 4,000 Design Contingency Add 35% $ 1,400 Total (2002) $ 5,400 3-B Total (2010) $ 7,000

72 Alternative 3-1-span Half-through truss Cost Project Description Quantity Unit Unit Extended 3-C Structure New SDC Overlay 500 Sq Yd $ $ 12,500 Surface Preparation 500 Sq Yd $ $ 17,500 SDC Overlay (Variable Thick, 5%) 2.1 Cu Yd $ $ 315 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 39,815 Design Contingency Add 35% $ 13,935 Total (2002) $ 53,750 3-C Total (2010) $ 73,000

73 Alternative 3-1-span Half-through truss Cost Project Description Quantity Unit Unit Extended 3-D Structure Patching Concrete Deck (5%) 25 Sq Yd $ $ 6,250 Sealing Concrete Surfaces 500 Sq Yd $ 8.00 $ 4,000 Incidentals Maintaining Traffic Lump Sum $ 2, $ 2,500 Mobilization Lump Sum $ - $ - Subtotal $ 12,750 Design Contingency Add 35% $ 4,463 Total (2002) $ 17,213 3-D Total (2010) $ 23,000

74 Alternative 3-1-span Half-through truss Cost Project Description Quantity Unit Unit Extended 3-E Structure New SDC Overlay 500 Sq Yd $ $ 12,500 Surface Preparation 500 Sq Yd $ $ 17,500 SDC Overlay (Variable Thick, 10%) 4.2 Cu Yd $ $ 630 Remove Existing Overlay 500 Sq Yd $ $ 7,500 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 47,630 Design Contingency Add 35% $ 16,671 Total (2002) $ 64,301 3-E Total (2010) $ 87,000

75 Alternative 3-1-span Half-through truss Cost Project Description Quantity Unit Unit Extended 3-F Structure Portions of Structure Removed Lump Sum $ 25, $ 25,000 Approach Slab Removed 100 Sq Yd $ $ 2,200 Reinforcing Steel Pound $ 0.55 $ 13,750 Superstructure Concrete 112 Cu Yd $ $ 70,000 Structural Steel (FB& Stringers) Lb $ 1.00 $ 50,000 Strip Sealed Expansion Joint 60 Ft $ $ 12,000 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 12" thick 100 Sq Yd $ $ 11,000 Remove/Galvanize/Replace Steel Truss Lump Sum $ 75, $ 75,000 Incidentals Maintaining Traffic Lump Sum $ 15, $ 15,000 Field Office 3 Month $ 2, $ 6,300 Mobilization Lump Sum $ 10, $ 10,000 Subtotal $ 309,000 Design Contingency Add 35% $ 108,150 Total (2002) $ 417,150 3-F Total (2010) $ 563,000

76 Alternative 4-3-span Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4-A 6" Bituminous Aggregate Base 124 Cu Yd $ $ 12,400 6" Aggregate Base 129 Cu Yd $ $ 4,515 6" Stabilized Crushed Aggregate 45 Cu Yd $ $ " Intermediate Course 35 Cu Yd $ $ 5, " Surface Course 25 Cu Yd $ $ 4,375 Sediment & Erosion Control 1 Each $ 7, $ 7,400 Approach Guardrail Ft $ $ 3,375 12" CIP RC Piling, Driven 2880 Ft $ 7.50 $ 21,600 12" CIP RC Piling, Furnished 3200 Ft $ 8.50 $ 27,200 16" CIP RC Piling, Driven 1890 Ft $ $ 42,525 16" CIP RC Piling, Furnished 2100 Ft $ $ 42,000 Reinforcing Steel Pound $ 0.55 $ 15,400 Superstructure Concrete 74 Cu Yd $ $ 40,700 Abutment Concrete 62 Cu Yd $ $ 24,800 Pier Cap Concrete 22 Cu Yd $ $ 17,600 Precast Composite Box Beam, CB17 24 Each $ 5, $ 132,000 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 12" thick 100 Sq Yd $ $ 11,000 Subtotal $ 431,790 Design Contingency Add 25% $ 107,948 Total (2002) $ 539,738 4-A Total (2010) $ 729,000

77 Alternative 4-3-span Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4-B Structure Sealing Concrete Surfaces 495 Sq Yd $ 8.00 $ 3,960 Incidentals Mobilization Lump Sum $ - $ - Subtotal $ 3,960 Design Contingency Add 35% $ 1,386 Total (2002) $ 5,346 4-B Total (2010) $ 7,000

78 Alternative 4-3-span Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4-C Structure New SDC Overlay 495 Sq Yd $ $ 12,375 Surface Preparation 495 Sq Yd $ $ 17,325 SDC Overlay (Variable Thick, 5%) 2.1 Cu Yd $ $ 315 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 39,515 Design Contingency Add 35% $ 13,830 Total (2002) $ 53,345 4-C Total (2010) $ 72,000

79 Alternative 4-3-span Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4-D Structure Patching Concrete Deck (5%) 25 Sq Yd $ $ 6,250 Sealing Concrete Surfaces 495 Sq Yd $ 8.00 $ 3,960 Incidentals Maintaining Traffic Lump Sum $ 2, $ 2,500 Mobilization Lump Sum $ - $ - Subtotal $ 12,710 Design Contingency Add 35% $ 4,449 Total (2002) $ 17,159 4-D Total (2010) $ 23,000

80 Alternative 4-3-span Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4-E Structure New SDC Overlay 495 Sq Yd $ $ 12,375 Surface Preparation 495 Sq Yd $ $ 17,325 SDC Overlay (Variable Thick, 10%) 4.1 Cu Yd $ $ 615 Remove Existing Overlay 495 Sq Yd $ $ 7,425 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ 2, $ 2,000 Subtotal $ 47,240 Design Contingency Add 35% $ 16,534 Total (2002) $ 63,774 4-E Total (2010) $ 86,000

81 Alternative 4-3-span Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4-F Approach Sediment & Erosion Control 1 Each $ 7, $ 7,400 Structure Portions of Structure Removed Lump Sum $ 35, $ 35,000 Approach Slab Removed 100 Sq Yd $ $ 2,200 Reinforcing Steel Pound $ 0.55 $ 9,158 Superstructure Concrete 74 Cu Yd $ $ 40,700 Precast Composite Box Beam, CB17 24 Each $ 5, $ 132,000 Bridge Railing - TST 250 Ft $ $ 18,750 Approach Slab, 12" thick 100 Sq Yd $ $ 11,000 Incidentals Maintaining Traffic Lump Sum $ 15, $ 15,000 Field Office 3 Month $ 2, $ 6,300 Mobilization Lump Sum $ 10, $ 10,000 Subtotal $ 287,508 Design Contingency Add 35% $ 100,628 Total (2002) $ 388,135 4-F Total (2010) $ 524,000

82 Alternative 3A - 1-span Half-through truss (LPA) Cost Project Description Quantity Unit Unit Extended 3A-A 6" Bituminous Aggregate Base 124 Cu Yd $ $ 12,400 6" Aggregate Base 129 Cu Yd $ $ 4,515 6" Stabilized Crushed Aggregate 45 Cu Yd $ $ " Intermediate Course 35 Cu Yd $ $ 5, " Surface Course 25 Cu Yd $ $ 4,375 Sediment & Erosion Control 1 Each $ 3, $ 3,700 Approach Guardrail Ft $ $ 3,375 Asphalt Wearing Surface 55 Cu Yd $ $ 12,375 14" CIP RC Piling, Driven 3600 Ft $ 9.00 $ 32,400 14" CIP RC Piling, Furnished 4000 Ft $ $ 44,000 Reinforcing Steel Pound $ 0.60 $ 12,000 Abutment Concrete 147 Cu Yd $ $ 55,125 Corrugated Steel Flooring 3600 Sq Ft $ $ 47,340 Bridge Railing - Deep Beam 250 Ft $ $ 6,250 Steel Truss, FBs, Stringers, etc. 1 Each $ 155, $ 155,000 Subtotal $ 399,005 Design Contingency Add 25% $ 99,751 Total (2002) $ 498,756 3A-A Total (2010) $ 673,000

83 Alternative 3A - 1-span Half-through truss (LPA) Cost Project Description Quantity Unit Unit Extended 3A-B Structure Asphalt Mill & Fill 400 Sq Yd $ $ 7,000 Incidentals Mobilization Lump Sum $ - $ - Subtotal $ 7,000 Design Contingency Add 35% $ 2,450 Total (2002) $ 9,450 3A-B Total (2010) $ 13,000

84 Alternative 3A - 1-span Half-through truss (LPA) Cost Project Description Quantity Unit Unit Extended 3A-C Structure Portions of Structure Removed Lump Sum $ 10, $ 10,000 Asphalt Wearing Surface 55 Cu Yd $ $ 12,375 Structural Steel (Stringers) Lb $ 1.00 $ 25,000 Corrugated Steel Flooring 3600 Sq Ft $ $ 47,340 Incidentals Maintaining Traffic Lump Sum $ 10, $ 10,000 Field Office 2 Month $ 2, $ 4,200 Mobilization Lump Sum $ 4, $ 4,000 Subtotal $ 112,915 Design Contingency Add 35% $ 39,520 Total (2002) $ 152,435 3A-C Total (2010) $ 206,000

85 Alternative 3A - 1-span Half-through truss (LPA) Cost Project Description Quantity Unit Unit Extended 3A-D Structure Portions of Structure Removed Lump Sum $ 15, $ 15,000 Asphalt Wearing Surface 55 Cu Yd $ $ 12,375 Structural Steel (FB& Stringers) Lb $ 1.00 $ 50,000 Corrugated Steel Flooring 3600 Sq Ft $ $ 47,340 Bridge Railing - Deep Beam 250 Ft $ $ 6,250 Remove/Galvanize/Replace Steel Truss Lump Sum $ 75, $ 75,000 Incidentals Maintaining Traffic Lump Sum $ 15, $ 15,000 Field Office 3 Month $ 2, $ 6,300 Mobilization Lump Sum $ 10, $ 10,000 Subtotal $ 237,265 Design Contingency Add 35% $ 83,043 Total (2002) $ 320,308 3A-D Total (2010) $ 432,000

86 Alternative 4A - 3-span Non-Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4A-A 6" Bituminous Aggregate Base 124 Cu Yd $ $ 12,400 6" Aggregate Base 129 Cu Yd $ $ 4,515 6" Stabilized Crushed Aggregate 45 Cu Yd $ $ " Intermediate Course 35 Cu Yd $ $ 5, " Surface Course 25 Cu Yd $ $ 4,375 Sediment & Erosion Control 1 Each $ 7, $ 7,400 Approach Guardrail Ft $ $ 3, " Intermediate Course 25 Cu Yd $ $ 3, " Surface Course 14 Cu Yd $ $ 2,450 12" CIP RC Piling, Driven 2700 Ft $ 7.50 $ 20,250 12" CIP RC Piling, Furnished 3000 Ft $ 8.50 $ 25,500 16" CIP RC Piling, Driven 1890 Ft $ $ 42,525 16" CIP RC Piling, Furnished 2100 Ft $ $ 42,000 Reinforcing Steel Pound $ 0.55 $ 6,600 Superstructure Concrete 4 Cu Yd $ $ 2,000 Abutment Concrete 62 Cu Yd $ $ 24,800 Pier Cap Concrete 22 Cu Yd $ $ 17,600 Precast Box Beam, B17 24 Each $ 4, $ 108,000 Bridge Railing - Deep Beam 250 Ft $ $ 6,250 Subtotal $ 339,940 Design Contingency Add 25% $ 84,985 Total (2002) $ 424,925 4A-A Total (2010) $ 574,000

87 Alternative 4A - 3-span Non-Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4A-B Structure Asphalt Mill & Fill 395 Sq Yd $ $ 6,913 Incidentals Mobilization Lump Sum $ - $ - Subtotal $ 6,913 Design Contingency Add 35% $ 2,419 Total (2002) $ 9,332 4A-B Total (2010) $ 13,000

88 Alternative 4A - 3-span Non-Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4A-C Structure Wearing Course Removed 395 Sq Yd $ $ 3,950 Waterproofing 395 Sq Yd $ $ 7, " Intermediate Course 25 Cu Yd $ $ 3, " Surface Course 14 Cu Yd $ $ 2,450 Incidentals Maintaining Traffic Lump Sum $ 7, $ 7,500 Mobilization Lump Sum $ - $ - Subtotal $ 24,760 Design Contingency Add 35% $ 8,666 Total (2002) $ 33,426 4A-C Total (2010) $ 45,000

89 Alternative 4A - 3-span Non-Composite Box Beam Cost Project Description Quantity Unit Unit Extended 4A-D Approach Sediment & Erosion Control 1 Each $ 7, $ 7,400 Structure Portions of Structure Removed Lump Sum $ 35, $ 35, " Intermediate Course 25 Cu Yd $ $ 3, " Surface Course 14 Cu Yd $ $ 2,450 Reinforcing Steel 1000 Pound $ 0.55 $ 550 Superstructure Concrete 4 Cu Yd $ $ 2,000 Precast Box Beam, B17 24 Each $ 4, $ 108,000 Bridge Railing - Deep Beam 250 Ft $ $ 6,250 Incidentals Maintaining Traffic Lump Sum $ 15, $ 15,000 Field Office 3 Month $ 2, $ 6,300 Mobilization Lump Sum $ 10, $ 10,000 Subtotal $ 196,700 Design Contingency Add 35% $ 68,845 Total (2002) $ 265,545 4A-D Total (2010) $ 358,000

90

91 Appendix C Maintenance Schedules

92 MAINTENANCE SCHEDULE Alternative 1 Three-span continuous concrete slab End of Life Project 1-A Project 1-C Project 1-E Project 1-F New Bridge Minor Rehab Major Rehab Minor Rehab Patch Deck Patch Deck Patch Deck Overlay Deck Edge Repair Overlay Minor Repairs Overlay Minor Repairs Minor Repairs Project 1-B Project 1-D Project 1-D Project 1-D Minor Repairs Minor Repairs Minor Repairs Minor Repairs Seal Deck Patch Deck Patch Deck Patch Deck Seal Deck Seal Deck Seal Deck

93 MAINTENANCE SCHEDULE Alternative 2 One-span precast concrete I-beam End of Study Project 2-A Project 2-C Project 2-E Project 2-B New Bridge Minor Rehab Minor Rehab Minor Repairs Patch Deck Patch Deck Seal Deck Overlay Overlay Minor Repairs Minor Repairs Project 2-B Project 2-D Project 2-F Project 2-C Minor Repairs Minor Repairs Major Rehab Minor Rehab Seal Deck Patch Deck New Superstructure Patch Deck Seal Deck Overlay Minor Repairs

94 MAINTENANCE SCHEDULE Alternative 3 One-span steel half-through truss End of Study Project 3-A Project 3-C Project 3-E Project 3-B New Bridge Minor Rehab Minor Rehab Minor Repairs Patch Deck Patch Deck Seal Deck Overlay Overlay Minor Repairs Minor Repairs Project 3-B Project 3-D Project 3-F Project 3-C Minor Repairs Minor Repairs Major Rehab Minor Rehab Seal Deck Patch Deck New Deck Patch Deck Seal Deck New Floor System Overlay Galvanize Truss Minor Repairs

95 MAINTENANCE SCHEDULE Alternative 4 Three-span continuous composite box beam End of Study Project 4-A Project 4-C Project 4-E Project 4-B New Bridge Minor Rehab Minor Rehab Minor Repairs Patch Deck Patch Deck Seal Deck Overlay Overlay Minor Repairs Minor Repairs Project 4-B Project 4-D Project 4-F Project 4-C Minor Repairs Minor Repairs Major Rehab Minor Rehab Seal Deck Patch Deck New Superstructure Patch Deck Seal Deck Overlay Minor Repairs

96 MAINTENANCE SCHEDULE Alternative 3A One-span steel half-through truss End of Study Project 3A-A Project 3A-C Project 3A-D Project 3A-C New Bridge Major Rehab Major Rehab Major Rehab New Deck New Deck New Deck New Stringers New Floor System New Stringers Minor Repairs Galvanize Truss Minor Repairs Project 3A-B Project 3A-B Project 3A-B Project 3A-B Minor Repairs Minor Repairs Minor Repairs Minor Repairs Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill

97 MAINTENANCE SCHEDULE Alternative 4A Three-span non-composite box beam End of Study Project 4A-A Project 4A-C Project 4A-D Project 4A-C New Bridge Minor Rehab Major Rehab Minor Rehab New Waterproofing New Superstructure New Waterproofing New Wearing Surface New Wearing Surface Minor Repairs Minor Repairs Project 4A-B Project 4A-B Project 4A-B Project 4A-B Minor Repairs Minor Repairs Minor Repairs Minor Repairs Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill

98

99 Appendix D Residual Values

100 Alternative 1-3-span Concrete Slab Residual Value Cost Description Quantity Unit Unit Extended Substructure 12" CIP RC Piling, Driven 2520 Ft $ 7.50 $ 18,900 12" CIP RC Piling, Furnished 2800 Ft $ 8.50 $ 23,800 16" CIP RC Piling, Driven 2160 Ft $ $ 48,600 16" CIP RC Piling, Furnished 2400 Ft $ $ 48,000 Reinforcing Steel 9000 Pound $ 0.55 $ 4,950 Abutment Concrete 53 Cu Yd $ $ 21,200 Pier Cap Concrete 15 Cu Yd $ $ 12,000 Substructure (25%) 25 % $ 177, $ 44,363 Superstructure Reinforcing Steel Pound $ 0.55 $ 19,800 Superstructure Concrete 241 Cu Yd $ $ 180,750 Superstructure (0%) 0 % $ 200, $ - Subtotal $ 44,363 Design Contingency Add 25% $ 11,091 Total (2002) $ 55,453 Total (2010) $ 75,000

101 Alternative 2-1-span Precast I-beam Residual Value Cost Description Quantity Unit Unit Extended Substructure 14" CIP RC Piling, Driven 5760 Ft $ 9.00 $ 51,840 14" CIP RC Piling, Furnished 6400 Ft $ $ 70,400 Reinforcing Steel Pound $ 0.55 $ 7,150 Abutment Concrete 135 Cu Yd $ $ 50,625 Substructure (25%) 25 % $ 180, $ 45,004 Superstructure Reinforcing Steel Pound $ 0.55 $ 19,800 Superstructure Concrete 181 Cu Yd $ $ 95,025 Draped Strand Beams, AASHTO Type 4 (Mod 4 Each $ 17, $ 70,000 Superstructure (50%) 50 % $ 184, $ 92,413 Subtotal $ 137,416 Design Contingency Add 25% $ 34,354 Total (2002) $ 171,770 Total (2010) $ 232,000

102 Alternative 3-1-span Half-through truss Residual Value Cost Description Quantity Unit Unit Extended Substructure 14" CIP RC Piling, Driven 3960 Ft $ 9.00 $ 35,640 14" CIP RC Piling, Furnished 4400 Ft $ $ 48,400 Reinforcing Steel Pound $ 0.55 $ 10,175 Abutment Concrete 148 Cu Yd $ $ 55,500 Substructure (25%) 25 % $ 149, $ 37,429 Superstructure Reinforcing Steel Pound $ 0.55 $ 14,025 Superstructure Concrete 112 Cu Yd $ $ 70,000 Strip Sealed Expansion Joint 60 Ft $ $ 12,000 Steel Truss, FBs, Stringers, etc. 1 Each $ 185, $ 185,000 Superstructure (50%) 50 % $ 281, $ 140,513 Subtotal $ 177,941 Design Contingency Add 25% $ 44,485 Total (2002) $ 222,427 Total (2010) $ 300,000

103 Alternative 4-3-span Composite Box Beam Residual Value Cost Description Quantity Unit Unit Extended Substructure 12" CIP RC Piling, Driven 2880 Ft $ 7.50 $ 21,600 12" CIP RC Piling, Furnished 3200 Ft $ 8.50 $ 27,200 16" CIP RC Piling, Driven 1890 Ft $ $ 42,525 16" CIP RC Piling, Furnished 2100 Ft $ $ 42,000 Reinforcing Steel Pound $ 0.55 $ 6,050 Abutment Concrete 62 Cu Yd $ $ 24,800 Pier Cap Concrete 22 Cu Yd $ $ 17,600 Substructure (25%) 25 % $ 181, $ 45,444 Superstructure Reinforcing Steel Pound $ 0.55 $ 9,350 Superstructure Concrete 74 Cu Yd $ $ 40,700 Precast Composite Box Beam, CB17 24 Each $ 5, $ 132,000 Superstructure (50%) 50 % $ 182, $ 91,025 Subtotal $ 136,469 Design Contingency Add 25% $ 34,117 Total (2002) $ 170,586 Total (2010) $ 230,000

104 Alternative 3A - 1-span Half-through truss (LPA) Residual Value Cost Description Quantity Unit Unit Extended Substructure 14" CIP RC Piling, Driven 3600 Ft $ 9.00 $ 32,400 14" CIP RC Piling, Furnished 4000 Ft $ $ 44,000 Reinforcing Steel Pound $ 0.60 $ 12,000 Abutment Concrete 147 Cu Yd $ $ 55,125 Substructure (25%) 25 % $ 143, $ 35,881 Superstructure Asphalt Wearing Surface 55 Cu Yd $ $ 12,375 Corrugated Steel Flooring 3600 Sq Ft $ $ 47,340 Steel Truss, FBs, Stringers, etc. 1 Each $ 155, $ 155,000 Superstructure (12.5%) 12.5 % $ 214, $ 26,839 Subtotal $ 62,721 Design Contingency Add 25% $ 15,680 Total (2002) $ 78,401 Total (2010) $ 106,000

105 Alternative 4A - 3-span Non-Composite Box Beam Residual Value Cost Description Quantity Unit Unit Extended Substructure 12" CIP RC Piling, Driven 2700 Ft $ 7.50 $ 20,250 12" CIP RC Piling, Furnished 3000 Ft $ 8.50 $ 25,500 16" CIP RC Piling, Driven 1890 Ft $ $ 42,525 16" CIP RC Piling, Furnished 2100 Ft $ $ 42,000 Reinforcing Steel Pound $ 0.55 $ 6,050 Abutment Concrete 62 Cu Yd $ $ 24,800 Pier Cap Concrete 22 Cu Yd $ $ 17,600 Substructure (25%) 25 % $ 178, $ 44,681 Superstructure 1.75" Intermediate Course 25 Cu Yd $ $ 3, " Surface Course 14 Cu Yd $ $ 2,450 Reinforcing Steel 1000 Pound $ 0.55 $ 550 Superstructure Concrete 4 Cu Yd $ $ 2,000 Precast Box Beam, B17 24 Each $ 4, $ 108,000 Superstructure (12.5%) 12.5 % $ 116, $ 14,594 Subtotal $ 59,275 Design Contingency Add 25% $ 14,819 Total (2002) $ 74,094 Total (2010) $ 100,000

106

107 Appendix E Net Present Value Calculations

108 Alternative 1-3-span Concrete Slab Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2010 $ - $ - 1-A $ 876,000 $ - $ 876, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 1-B $ 8,100 $ - $ 11, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 1-C $ 82,800 $ - $ 85, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 1-D $ 26,500 $ - $ 29, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3,000

109 Alternative 1-3-span Concrete Slab Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2050 $ 500 $ 2,500 1-E $ 186,300 $ - $ 189, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 1-D $ 26,500 $ - $ 29, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 1-F $ 100,100 $ - $ 103, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 1-D $ 26,500 $ - $ 29, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ (75,000) $ (72,000) TOTAL $ 37,500 $ 187,500 $ 1,332,800 $ (75,000) $ 1,482,800 NPV $ 16,008 $ 80,038 $ 1,038,238 $ (10,169) $ 1,124,115

110 Alternative 2-1-span Precast I-beam Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2010 $ - $ - 2-A $ 1,142,800 $ - $ 1,142, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - 2-B $ 9,200 $ - $ 9, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - 2-C $ 90,900 $ - $ 91, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - 2-D $ 28,800 $ - $ 29, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ 500

111 Alternative 2-1-span Precast I-beam Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2050 $ 500 $ - 2-E $ 109,300 $ - $ 109, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - 2-F $ 674,300 $ - $ 674, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - 2-B $ 9,200 $ - $ 9, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - 2-C $ 90,900 $ - $ 91, $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ - $ $ 500 $ - $ - $ (232,000) $ (231,500) TOTAL $ 37,500 $ - $ 2,155,400 $ (232,000) $ 1,960,900 NPV $ 16,008 $ - $ 1,447,709 $ (31,456) $ 1,432,261

112 Alternative 3-1-span Half-through Truss Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2010 $ - $ - 3-A $ 949,400 $ - $ 949, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3-B $ 7,900 $ - $ 8, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3-C $ 82,100 $ - $ 82, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3-D $ 25,900 $ - $ 26, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ 700

113 Alternative 3-1-span Half-through Truss Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2050 $ 700 $ - 3-E $ 97,900 $ - $ 98, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3-F $ 633,400 $ - $ 634, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3-B $ 7,900 $ - $ 8, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3-C $ 82,100 $ - $ 82, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ (300,000) $ (299,300) TOTAL $ 52,500 $ - $ 1,886,600 $ (300,000) $ 1,639,100 NPV $ 22,411 $ - $ 1,230,496 $ (40,676) $ 1,212,231

114 Alternative 4-3-span Composite Box Beam Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2010 $ - $ - 4-A $ 848,400 $ - $ 848, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4-B $ 8,100 $ - $ 11, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4-C $ 82,800 $ - $ 85, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4-D $ 26,500 $ - $ 29, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3,000

115 Alternative 4-3-span Composite Box Beam Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2050 $ 500 $ 2,500 4-E $ 98,900 $ - $ 101, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4-F $ 607,600 $ - $ 610, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4-B $ 8,100 $ - $ 11, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4-C $ 82,800 $ - $ 85, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ (230,000) $ (227,000) TOTAL $ 37,500 $ 187,500 $ 1,763,200 $ (230,000) $ 1,758,200 NPV $ 16,008 $ 80,038 $ 1,124,014 $ (31,185) $ 1,188,875

116 Alternative 3A - 1-span Half-through Truss (LPA) Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2010 $ - $ - 3A-A $ 784,000 $ - $ 784, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3A-B $ 15,000 $ - $ 15, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3A-C $ 236,900 $ - $ 237, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3A-B $ 15,000 $ - $ 15, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ 700

117 Alternative 3A - 1-span Half-through Truss (LPA) Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2050 $ 700 $ - 3A-D $ 496,800 $ - $ 497, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3A-B $ 15,000 $ - $ 15, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3A-C $ 236,900 $ - $ 237, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - 3A-B $ 15,000 $ - $ 15, $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ - $ $ 700 $ - $ - $ (106,000) $ (105,300) TOTAL $ 52,500 $ - $ 1,814,600 $ (106,000) $ 1,761,100 NPV $ 22,411 $ - $ 1,166,610 $ (14,372) $ 1,174,648

118 Alternative 4A - 3-span Non-Composite Box Beam Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2010 $ - $ - 4A-A $ 670,100 $ - $ 670, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4A-B $ 15,000 $ - $ 18, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4A-C $ 51,800 $ - $ 54, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4A-B $ 15,000 $ - $ 18, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3,000

119 Alternative 4A - 3-span Non-Composite Box Beam Net Present Value of Construction and Annual Costs Discount Rate = 2.70% Construction Residual Total Year Insp. Maint. Project Cost Value Cost 2050 $ 500 $ 2,500 4A-D $ 416,700 $ - $ 419, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4A-B $ 15,000 $ - $ 18, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4A-C $ 51,800 $ - $ 54, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 4A-B $ 15,000 $ - $ 18, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ - $ 3, $ 500 $ 2,500 $ - $ (100,000) $ (97,000) TOTAL $ 37,500 $ 187,500 $ 1,250,400 $ (100,000) $ 1,375,400 NPV $ 16,008 $ 80,038 $ 879,047 $ (13,559) $ 961,534

120

121 Appendix F Life Cycle Costs Summaries

122 LIFE CYCLE COSTS SUMMARY (All costs in 2010 dollars) Alternative 1 Three-span continuous concrete slab End of Life $75,000 Project 1-A Project 1-C Project 1-E Project 1-F $876,000 $82,800 $186,300 $100,100 New Bridge Minor Rehab Major Rehab Minor Rehab Patch Deck Patch Deck Patch Deck Overlay Deck Edge Repair Overlay Minor Repairs Overlay Minor Repairs Minor Repairs Project 1-B Project 1-D Project 1-D Project 1-D $8,100 $26,500 $26,500 $26,500 Minor Repairs Minor Repairs Minor Repairs Minor Repairs Seal Deck Patch Deck Patch Deck Patch Deck Seal Deck Seal Deck Seal Deck Residual Value Annual Costs Insp. Maint. $500 $2,500 Inspection $16,008 Net Present Value of Life Cycle Costs Maintenance Projects Residual $80,038 $1,038,238 ($10,169) Total $1,124,115

123 LIFE CYCLE COSTS SUMMARY (All costs in 2010 dollars) Alternative 2 One-span precast concrete I-beam End of Study $232,000 Project 2-A Project 2-C Project 2-E Project 2-B $1,142,800 $90,900 $109,300 $9,200 New Bridge Minor Rehab Minor Rehab Minor Repairs Patch Deck Patch Deck Seal Deck Overlay Overlay Minor Repairs Minor Repairs Residual Value Project 2-B Project 2-D Project 2-F Project 2-C $9,200 $28,800 $674,300 $90,900 Minor Repairs Minor Repairs Major Rehab Minor Rehab Seal Deck Patch Deck New Superstructure Patch Deck Seal Deck Overlay Minor Repairs Annual Costs Insp. Maint. $500 $0 Inspection $16,008 Net Present Value of Life Cycle Costs Maintenance Projects Residual $0 $1,447,709 ($31,456) Total $1,432,261

124 LIFE CYCLE COSTS SUMMARY (All costs in 2010 dollars) Alternative 3 One-span steel half-through truss End of Study $300,000 Project 3-A Project 3-C Project 3-E Project 3-B $949,400 $82,100 $97,900 $7,900 New Bridge Minor Rehab Minor Rehab Minor Repairs Patch Deck Patch Deck Seal Deck Overlay Overlay Minor Repairs Minor Repairs Residual Value Project 3-B Project 3-D Project 3-F Project 3-C $7,900 $25,900 $633,400 $82,100 Minor Repairs Minor Repairs Major Rehab Minor Rehab Seal Deck Patch Deck New Deck Patch Deck Seal Deck New Floor System Overlay Galvanize Truss Minor Repairs Annual Costs Insp. Maint. $700 $0 Inspection $22,411 Net Present Value of Life Cycle Costs Maintenance Projects Residual $0 $1,230,496 ($40,676) Total $1,212,231

125 LIFE CYCLE COSTS SUMMARY (All costs in 2010 dollars) Alternative 4 Three-span continuous composite box beam End of Study $230,000 Project 4-A Project 4-C Project 4-E Project 4-B $848,400 $82,800 $98,900 $8,100 New Bridge Minor Rehab Minor Rehab Minor Repairs Patch Deck Patch Deck Seal Deck Overlay Overlay Minor Repairs Minor Repairs Residual Value Project 4-B Project 4-D Project 4-F Project 4-C $8,100 $26,500 $607,600 $82,800 Minor Repairs Minor Repairs Major Rehab Minor Rehab Seal Deck Patch Deck New Superstructure Patch Deck Seal Deck Overlay Minor Repairs Annual Costs Insp. Maint. $500 $2,500 Inspection $16,008 Net Present Value of Life Cycle Costs Maintenance Projects Residual $80,038 $1,124,014 ($31,185) Total $1,188,875

126 LIFE CYCLE COSTS SUMMARY (All costs in 2010 dollars) Alternative 3A One-span steel half-through truss End of Study $106,000 Project 3A-A Project 3A-C Project 3A-D Project 3A-C $784,000 $236,900 $496,800 $236,900 New Bridge Major Rehab Major Rehab Major Rehab New Deck New Deck New Deck New Stringers New Floor System New Stringers Minor Repairs Galvanize Truss Minor Repairs Residual Value Project 3A-B Project 3A-B Project 3A-B Project 3A-B $15,000 $15,000 $15,000 $15,000 Minor Repairs Minor Repairs Minor Repairs Minor Repairs Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill Annual Costs Insp. Maint. $700 $0 Inspection $22,411 Net Present Value of Life Cycle Costs Maintenance Projects Residual $0 $1,166,610 ($14,372) Total $1,174,648

127 LIFE CYCLE COSTS SUMMARY (All costs in 2010 dollars) Alternative 4A Three-span non-composite box beam End of Study $100,000 Project 4A-A Project 4A-C Project 4A-D Project 4A-C $670,100 $51,800 $416,700 $51,800 New Bridge Minor Rehab Major Rehab Minor Rehab New Waterproofing New Superstructure New Waterproofing New Wearing Surface New Wearing Surface Minor Repairs Minor Repairs Residual Value Project 4A-B Project 4A-B Project 4A-B Project 4A-B $15,000 $15,000 $15,000 $15,000 Minor Repairs Minor Repairs Minor Repairs Minor Repairs Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill Asphalt Mill & Fill Annual Costs Insp. Maint. $2,500 Inspection $16,008 Net Present Value of Life Cycle Costs Projects $879,047 Maintenance $80,038 Residual ($13,559) Total $961,534

BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012

BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012 Page 1 BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO. 87786 BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012 ROADWAY 1 201 CLEARING AND GRUBBING 1 LUMP $4,500.00 $4,500.00 $10,016.00

More information

2016 TRB Webinar. Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions

2016 TRB Webinar. Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions 2016 TRB Webinar Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions Adam Matteo Jeff Milton Todd Springer Virginia Department of Transportation Structure and Bridge Division

More information

AVERAGE OF BID ITEMS ENGINEERS ESTIMATE

AVERAGE OF BID ITEMS ENGINEERS ESTIMATE ROADWAY 1 Mobilization 1 LS $ 990,048.50 $ 80,000.00 $ 880,000.00 $ 880,000.00 $ 950,000.00 $ 950,000.00 $ 967,510.00 $ 967,510.00 $ 1,162,684.00 $ 1,162,684.00 2 Maintenance of Traffic ( incl. Pedestrian

More information

LETTING : CALL : 056 COUNTIES : MILLE LACS

LETTING : CALL : 056 COUNTIES : MILLE LACS S T A T E O F M I N N E S O T A PAGE : -1 NUMBER OF DAYS: 0 BRIDGE COUNT : 3 CONTRACT DESCRIPTION : GRADING, BIT PAVING & SURFACING, ROUNDABOUT, AND BRIDGES. CONTRACT LOCATION: LOCATED ON T.H. 95 AT THE

More information

City of Glendale, Arizona Pavement Management Program

City of Glendale, Arizona Pavement Management Program City of Glendale, Arizona Pavement Management Program Current Year Plan (FY 2014) and Five-Year Plan (FY 2015-2019) EXECUTIVE SUMMARY REPORT December 2013 TABLE OF CONTENTS TABLE OF CONTENTS I BACKGROUND

More information

LCC Methodology. Håkan Sundquist Structural Design and Bridges KTH. ETSI Methodology 1

LCC Methodology. Håkan Sundquist Structural Design and Bridges KTH. ETSI Methodology 1 LCC Methodology Håkan Sundquist Structural Design and Bridges KTH 1 There are many requirements on a bridge 2 The classic task 3 The classic bridge design task 4 LCC optimization 5 LCC/Construction cost

More information

ENGINEER'S ESTIMATE OF PROBABLE COST CCTA I 680 NORTH EXPRESS LANE PROJECT (SOUTHBOUND ONLY) EA 04 4H % PS&E Submittal

ENGINEER'S ESTIMATE OF PROBABLE COST CCTA I 680 NORTH EXPRESS LANE PROJECT (SOUTHBOUND ONLY) EA 04 4H % PS&E Submittal Page: 1 of 8 (F) Description 1 050000A CONTRACTOR STAKING LS 1 $ $ 2 070030 LEAD COMPLIANCE PLAN LS 1 $ $ 3 080000A POTHOLING LS 1 $ 50,000.00 $ 50,000.00 4 080050 PROGRESS SCHEDULE (CRITICAL PATH METHOD)

More information

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 6: Preliminary Cost Estimates.

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 6: Preliminary Cost Estimates. , Segments 2-4 Chapter 6: Preliminary Cost Estimates Table of Contents 6.1 Details of Facilities... 17 6.2 Pre-Development and Facility Feasibility... 1 6.2.1 Planning... 1 6.2.2 Environmental Mitigation...

More information

Trinity River Restoration Program

Trinity River Restoration Program Trinity River Restoration Program Trinity River Bridges: Hydraulic, Scour, and Riprap Sizing Analysis US DEPARTMENT OF THE INTERIOR BUREAU OF RECLAMATION TECHNICAL SERVICE CENTER Prepared by Kent L. Collins

More information

ADDENDUM No. 1 January 29, Paving Program Village of Milford

ADDENDUM No. 1 January 29, Paving Program Village of Milford ADDENDUM No. 1 2018 Paving Program Village of Milford The following changes, additions, and/or clarifications to the Contract Documents shall be incorporated in said documents and shall be allowed for

More information

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade. Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding

More information

Engineer's Preliminary Estimate - 100% Submittal

Engineer's Preliminary Estimate - 100% Submittal EA 284700 1 070010 PROGRESS SCHEDULE (CRITICAL PATH) LS 1 $ 15,000 $ 15,000 2 071325 TEMPORARY FENCE (TYPE ESA) M 1250 $ 10 $ 12,500 3 074019 PREPARE STORM WATER POLLUTION PREVENTION PLAN LS 1 $ 7,000

More information

CONTRACT TIME DETERMINATION

CONTRACT TIME DETERMINATION CONTRACT TIME DETERMINATION MISSOURI DEPARTMENT OF TRANSPORTATION March 15, 2004 DEFINITIONS Calendar Day: Any day shown on the calendar beginning and ending at midnight. Working Day: A calendar day during

More information

Requirements for Mapping Levees Complying with Section of the NFIP Regulations

Requirements for Mapping Levees Complying with Section of the NFIP Regulations FACT SHEET Requirements for Mapping Levees Complying with Section 65.10 of the NFIP Regulations As part of a mapping project, it is the levee owner s or community s responsibility to provide data and documentation

More information

OKLAHOMA TURNPIKE AUTHORITY

OKLAHOMA TURNPIKE AUTHORITY PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 250,000.00 $250,000.00 $ 240,978.56 $ 240,978.56 260,000.00 $ 260,000.00 201(A) CLEARING & GRUBBING LSUM 1.00 $ 30,000.00 $30,000.00 $ 17,188.20

More information

JANUARY 18, Reference Specifications, Attachment to Form 96 (BID FORM), Bid Proposal: Respectfully submitted,

JANUARY 18, Reference Specifications, Attachment to Form 96 (BID FORM), Bid Proposal: Respectfully submitted, ADDENDUM NO. 3 TO THE PLANS AND SPECIFICATIONS for STREET AND STORM SEWER IMPROVEMENTS ON HANCOCK AND WASHINGTON STREETS for the FRENCH LICK REDEVELOPMENT COMMISSION ORANGE COUNTY, INDIANA MEI PROJECT

More information

TOTAL QUANTITY UNIT COST UNIT

TOTAL QUANTITY UNIT COST UNIT BASE BID DIVISION 1 - GENERAL 1 1070-206-A-0 TRAFFIC CONTROL LS 1 $ 10,000 $ 10,000 $3,000.00 $3,000.00 $5,600.00 $5,600.00 2 2010-108-B-0 CLEARING AND GRUBBING AC 5 $ 9,000 $ 45,000 $7,192.50 $35,962.50

More information

A Financial Impact Assessment of LD 1725: Stream Crossings

A Financial Impact Assessment of LD 1725: Stream Crossings A Financial Impact Assessment of LD 1725: Stream Crossings Prepared by: The New England Environmental Finance Center For the Maine Department of Transportation Office of Environmental Planning Edmund S.

More information

EVALUATION OF EXPENDITURES ON RURAL INTERSTATE PAVEMENTS IN KANSAS

EVALUATION OF EXPENDITURES ON RURAL INTERSTATE PAVEMENTS IN KANSAS EXECUTIVE SUMMARY EVALUATION OF EXPENDITURES ON RURAL INTERSTATE PAVEMENTS IN KANSAS by Stephen A. Cross, P.E. Associate Professor University of Kansas Lawrence, Kansas and Robert L. Parsons, P.E. Assistant

More information

JANUARY 13, ILL. ADM. CODE CH. I, SEC TITLE 17: CONSERVATION CHAPTER I: DEPARTMENT OF NATURAL RESOURCES SUBCHAPTER h: WATER RESOURCES

JANUARY 13, ILL. ADM. CODE CH. I, SEC TITLE 17: CONSERVATION CHAPTER I: DEPARTMENT OF NATURAL RESOURCES SUBCHAPTER h: WATER RESOURCES TITLE 17: CONSERVATION CHAPTER I: DEPARTMENT OF NATURAL RESOURCES SUBCHAPTER h: WATER RESOURCES PART 3702 CONSTRUCTION AND MAINTENANCE OF DAMS Section Page No. 3702.10 Purpose 2 3702.20 Definitions 3 3702.30

More information

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E.

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. Life Cycle Cost Analysis in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. What is it? Economic procedure That uses

More information

LCCA Design and Maintenance

LCCA Design and Maintenance LCCA Design and Maintenance John Cunningham Iowa Concrete Paving Association ASCE Conference November 6, 2013 www.iowaconcretepaving.org Life Cycle Cost Analysis Life cycle cost analysis (LCCA) is an economic

More information

C ITY OF S OUTH E UCLID

C ITY OF S OUTH E UCLID C ITY OF S OUTH E UCLID T A B L E O F C O N T E N T S 1. Executive Summary... 2 2. Background... 3 3. PART I: 2016 Pavement Condition... 8 4. PART II: 2018 Current Backlog... 12 5. PART III: Maintenance

More information

ANNUAL LETTER. Visit our Highway Department Website!

ANNUAL LETTER. Visit our Highway Department Website! ANNUAL LETTER From: James Griesbach, Highway Commissioner Date: March 15, 2018 Visit our Highway Department Website! Marathon County Highway Department s Web Site includes information on the following

More information

AVGPR14.Y01 2/11/2014 DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 12/01/13 AND 12/31/13 BY ITEM GROUP

AVGPR14.Y01 2/11/2014 DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 12/01/13 AND 12/31/13 BY ITEM GROUP AVERAGE BID PRICES FOR AWARDED PROJECTS 14:48 Tuesday, February 11, 2014 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 1 $19 $18,500.00 1 2013 2013.602/00022 ROAD/WEATHER SENSOR AND CABLE EACH 3 $32

More information

2018 Road Improvements Engineer's Project Number: LK 01 Bid Deadline: May 1, 2018 at 2:00 p.m. local time

2018 Road Improvements Engineer's Project Number: LK 01 Bid Deadline: May 1, 2018 at 2:00 p.m. local time TABULATION PAGE 1 OF 6 PRE- ESTIMATE Pitlik and Wick, Inc. CONTRACT A - BASE Highway X (Friedle Road to Dam Road) A1.1 Single Layer Chip Seal 75,100 sq. yds. $ 2.50 $ 187,750.00 $ 1.60 $ 120,160.00 $ 1.19

More information

MEMORANDUM TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER

MEMORANDUM TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER MEMORANDUM TO: FROM: BY: CITY COUNCIL TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR JILL MCPEEK, CAPITAL IMPROVEMENT PROJECT MANAGER SUBJECT: CONSIDERATION OF A FOURTH AMENDMENT TO AGREEMENT FOR CONSULTANT

More information

Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE

Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE Cedar Hammock Community Development District Inframark, Infrastructure Management Services 210 N. University

More information

CECIL COUNTY, MARYLAND. ADDENDUM #3 Bid 18-14: Bohemia Church Road Culvert Replacements XCE1073, XCE1074 & XCE1075

CECIL COUNTY, MARYLAND. ADDENDUM #3 Bid 18-14: Bohemia Church Road Culvert Replacements XCE1073, XCE1074 & XCE1075 Office of the County Executive Alan J. McCarthy County Executive Department of Finance Purchasing Division Ken Jackson Purchasing/Fleet/Leasing Mgr. Alfred C. Wein, Jr. Purchasing Office Director of Administration

More information

SUTTER BUTTER FLOOD CONTROL AGENCY FEATHER RIVER WEST LEVEE PROJECT PROJECT C, CONTRACT NO C BID TABULATION

SUTTER BUTTER FLOOD CONTROL AGENCY FEATHER RIVER WEST LEVEE PROJECT PROJECT C, CONTRACT NO C BID TABULATION Bid Schedule A - Feather River West Levee Project C Improvements No. Item Description Quantity Unit Nordic/Magnus Pacific JV Engineer's Estimate Unit Price Total Price Unit Price Total Price A1 Injury

More information

TEC Proposal: Date Issued: April 18, 2017

TEC Proposal: Date Issued: April 18, 2017 1343 Rochester Road PO Box 249 Troy, Michigan 48099-0249 (248) 588-6200 or (313) T-E-S-T-I-N-G Fax (248) 588-6232 www.testingengineers.com Date Issued:, Director 167 Fourth Street Belleville, Michigan

More information

Public Works Maintenance STORMWATER AND

Public Works Maintenance STORMWATER AND Public Works Maintenance STORMWATER AND TRANSPORTATION Mission Statement T H E P U B L I C W O R K S M A I N T E N A N C E D I V I S I O N I S T H E M A I N C U S T O D I A N A N D P R I N C I P A L C

More information

FLINT HILL MANOR FLINT HILL MANOR. Replacement Reserve Study. Oakton, Virginia. Property Management: Flint Hill Manor Townhouse Association

FLINT HILL MANOR FLINT HILL MANOR. Replacement Reserve Study. Oakton, Virginia. Property Management: Flint Hill Manor Townhouse Association Replacement Reserve Study REPLACEMENT RESERVE STUDY Oakton, Virginia Property Management: Flint Hill Manor Townhouse Association Jamie Critchfield Vice President Email: tommie0200@aol.com Consultant: RICHARD

More information

2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction)

2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) 2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) Project Information The Glen at Widefield Filing No. 9 PDD File: SF-185 9/25/2018 Project Name Section 1 - Grading and Erosion

More information

REPLACEMENT OF MERCER COUNTY BRIDGE

REPLACEMENT OF MERCER COUNTY BRIDGE ADDENDUM NO. ONE Notice is hereby given that on April 26, 2019 at 11:00 AM (Prevailing time), sealed proposals will be opened and read in public by the Purchasing Department in the Mercer County McDade

More information

COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013

COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013 COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013 Pictures Key Front Cover Top Row 1) Administration Building Second Row, left to right 2) Brigden EMS Station 3) Judith & Norman Alix Art Gallery Third row,

More information

Bid No.: PO Box Cone Rd Asphalt Ave th Ave. E. Dunedin, FL Tampa, FL Tampa, FL Palmetto, FL 34221

Bid No.: PO Box Cone Rd Asphalt Ave th Ave. E. Dunedin, FL Tampa, FL Tampa, FL Palmetto, FL 34221 Bid : 7379 GENERAL 1 2 3 4 @ unit $ total $ @ unit $ total $ @ unit $ total $ @ unit $ total $ G-1.1 Mobilization 1 LS $ 450,000.00 $ 450,000.00 $ 720,000.00 $ 720,000.00 $ 750,000.00 $ 750,000.00 $ 530,000.00

More information

SHIPLEY S CHOICE DAM REHABILITATION COMMUNITY MEETING MINUTES

SHIPLEY S CHOICE DAM REHABILITATION COMMUNITY MEETING MINUTES SHIPLEY S CHOICE DAM REHABILITATION COMMUNITY MEETING MINUTES A community meeting was held on September 13, 2018 at the Shipley s Choice Elementary School. County staff from the Watershed Protection and

More information

UPDATE ON DALLAS FLOODWAY

UPDATE ON DALLAS FLOODWAY UPDATE ON DALLAS FLOODWAY ENVIRONMENTAL IMPACT STATEMENT [ EIS ] Transportation and Trinity River Project Committee Rob Newman Director, Trinity River Corridor Project, Fort Worth District 28 April 2014

More information

City of Sonoma 2015 Pavement Management Program Update (P-TAP 16) Final Report February 25, 2016 TABLE OF CONTENTS

City of Sonoma 2015 Pavement Management Program Update (P-TAP 16) Final Report February 25, 2016 TABLE OF CONTENTS City of Sonoma I. Introduction TABLE OF CONTENTS II. Methodology III. Pavement Condition Index (PCI) / Remaining Service Life (RSL) Report IV. Budget Analysis Reports A. Budget Needs Report Five Year B.

More information

PART A ROADWAY - BASE BID

PART A ROADWAY - BASE BID May 10, 2016 HEB-MC-61 PART A ROADWAY - BASE BID 202(A) - UNCLASSIFIED EXCAVATION - CY 34,946.00 $ 6.00 209,676.00 $ 7.98 $ 278,869.08 205(A) - TYPE A-SALVAGED TOPSOIL - LSUM 1.00 $ 22,500.00 $ 22,500.00

More information

PCI Definition. Module 1 Part 4: Methodology for Determining Pavement Condition Index (PCI) PCI Scale. Excellent Very Good Good.

PCI Definition. Module 1 Part 4: Methodology for Determining Pavement Condition Index (PCI) PCI Scale. Excellent Very Good Good. Module 1 Part 4: Methodology for Determining Pavement Condition Index (PCI) Basic Components PMS Evaluation of Flexible Pavements Fundamental Theory of Typical Pavement Defects and Failures Physical Description

More information

Tabulation of Bids. Counties: ROUTE 94 BLACK CREEK TRIBUTARY CULVERT REPLACEMENT

Tabulation of Bids. Counties: ROUTE 94 BLACK CREEK TRIBUTARY CULVERT REPLACEMENT Page 1 of 20 16 SSSEX ROTE 94 BLACK CREEK TRIBTARY CLVERT REPLACEMENT CONSTRCTION CORP INC. (2) KONKS CORPORATION (3) NORTHEAST REMSCO CONSTRCTION INC Quantity and nits nit Price nit Price nit Price 0001

More information

NON-MOTORIZED FACILITIES

NON-MOTORIZED FACILITIES NON-MOTORIZED FACILITIES POLICY The Board of Road Commissioners of the County of Kalamazoo non-motorized policy provides a guideline for the development of non-motorized facilities in the public right-of-way.

More information

Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements

Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements Resurfacing projects are among the most common and routine types of projects regularly conducted by highway agencies. When resurfacing projects

More information

Bridge Asset Management or IT S THE MONEY DUMMY

Bridge Asset Management or IT S THE MONEY DUMMY Bridge Asset Management or IT S THE MONEY DUMMY Chris Keegan, P. E. Bridge Maintenance Engineer Region Operations Engineer. Secretary of Transportation Roger Millar WBPP, Denver CO May, 2017 Asset Management

More information

FINAL TECHNICAL MEMORANDUM AWD FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012

FINAL TECHNICAL MEMORANDUM AWD FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012 FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012 Table of Contents TABLE OF CONTENTS Table of Contents... 1 Executive Summary... 2 1 Objective... 4 2 Study Approach...

More information

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM TOTAL PROJECT ESTIMATE ($) STATE ALLOCATION CODE (SAC) FUND TYPE ENCUMBERED FROM BEFORE FY 2011 PE/RW PRIOR TO FY 2016 LOCAL MATCH LOCAL LABOR STATE LABOR FED LABOR & TSKF LINE ITEM # ST. LINE ITEM

More information

NE WEST KINGSTON ROAD CULVERT REPLACEMENT

NE WEST KINGSTON ROAD CULVERT REPLACEMENT NE WEST KINGSTON ROAD CULVERT REPLACEMENT KITSAP COUNTY MILE POST 1.28 TO 1.44 PUBLIC WORKS BID TABULATION SECTION PREPARED: BLB LENGTH: 0.16 Mile REVISED: DATE: March 7, 2017 SCHEDULE A - ROADWAY IMPROVEMENTS

More information

Request for Continued Participation in the Midwest States Pooled Fund to Advance Roadside Safety Research

Request for Continued Participation in the Midwest States Pooled Fund to Advance Roadside Safety Research Request for Continued Participation in the Midwest States Pooled Fund to Advance Roadside Safety Research Project Champion & WYDOT Project Manager: Bill Wilson, P.E. Standards Engineer Wyoming Dept. of

More information

Paradise Island Condominium Association Final Report of the Reserve Study Review Committee

Paradise Island Condominium Association Final Report of the Reserve Study Review Committee Paradise Island Condominium Association Final Report of the Reserve Study Review Committee March 11, 2014 Chairperson Mary Linak Members Jeff Duppler Chuck Lanius Bill Murphy Paul Pudlas Advisor Mike Ashworth,

More information

OPTION A: 2 BITUMINOUS PAVING WITH SHOULDERS OPTION B: SCRATCH COURSE BITUMINOUS PAVING WITHOUT SHOULDERS

OPTION A: 2 BITUMINOUS PAVING WITH SHOULDERS OPTION B: SCRATCH COURSE BITUMINOUS PAVING WITHOUT SHOULDERS SHIAWASSEE COUNTY ROAD COMMISSION PROPOSAL FOR 2018 BITUMINOUS PAVING PROGRAM JUDDVILLE ROAD FROM CLINTON COUNTY LINE (MERIDIAN ROAD) TO GENESSEE COUNTY LINE (M-13) IN SHIAWASSEE COUNTY + / - 22.34 MILES

More information

TM TECHNICAL MANUAL PAVEMENT MAINTENANCE MANAGEMENT

TM TECHNICAL MANUAL PAVEMENT MAINTENANCE MANAGEMENT TECHNICAL MANUAL PAVEMENT MAINTENANCE MANAGEMENT HEADQUARTERS, DEPARTMENT 0F THE ARMY NOVEMBER 1982 TECHNICAL MANUAL HEADQUARTERS DEPARTMENT OF THE ARMY No. 5-623 WASHINGTON, DC, November 1982 } PAVEMENT

More information

INVITATION TO BID. CONTRACT PERIOD: The contract shall cover the County s needs for the period of July 21, 2015 through July 20, 2015.

INVITATION TO BID. CONTRACT PERIOD: The contract shall cover the County s needs for the period of July 21, 2015 through July 20, 2015. INVITATION TO BID The Etowah County Commission will, on June 22, 2015 in the Commission Chambers, 1st floor, 800 Forrest Avenue, Gadsden, AL, receive competitive bids on SUPERPAVE BITUMINOUS CONCRETE ASPHALT

More information

Gladwin County Road Commission 2016 Hot Mix Asphalt (HMA) Paving. Page 1 of 5

Gladwin County Road Commission 2016 Hot Mix Asphalt (HMA) Paving. Page 1 of 5 Page 1 of 5 SEALED PROPOSALS (BIDS) WILL BE RECEIVED UNTIL 9:30 A.M., EST, WEDNESDAY, March 9, 2016 Board of County Road Commissioners of the County of Gladwin, 301 South State Street, Gladwin, Michigan

More information

OHIO TURNPIKE CROSSING PERMIT REQUEST INFORMATION UNDERGROUND CROSSING

OHIO TURNPIKE CROSSING PERMIT REQUEST INFORMATION UNDERGROUND CROSSING OHIO TURNPIKE CROSSING PERMIT REQUEST INFORMATION UNDERGROUND CROSSING The Ohio Turnpike Commission requests that four (4) copies of the following information be submitted; TO: Chief Engineer Ohio Turnpike

More information

Village of Fife Lake 616 Bates/Box 298 Fife Lake, MI Phone: (231) Fax: (231)

Village of Fife Lake 616 Bates/Box 298 Fife Lake, MI Phone: (231) Fax: (231) Village of Fife Lake 616 Bates/Box 298 Fife Lake, MI 49633 Phone: (231)879-4291 Fax: (231)879-5153 RIGHT OF WAY PERMIT APPLICATION APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE AND/OR MAINTAIN WITHIN

More information

NCHRP Consequences of Delayed Maintenance

NCHRP Consequences of Delayed Maintenance NCHRP 14-20 Consequences of Delayed Maintenance Recommended Process for Bridges and Pavements prepared for NCHRP prepared by Cambridge Systematics, Inc. with Applied Research Associates, Inc. Spy Pond

More information

Highway Engineering-II

Highway Engineering-II Highway Engineering-II Chapter 7 Pavement Management System (PMS) Contents What is Pavement Management System (PMS)? Use of PMS Components of a PMS Economic Analysis of Pavement Project Alternative 2 Learning

More information

Munilla Construction HOOD RD., E. OF FLORIDA'S TURNPIKE TO W. OF CENTRAL BLVD. AND HOOD RD. & CENTRAL

Munilla Construction HOOD RD., E. OF FLORIDA'S TURNPIKE TO W. OF CENTRAL BLVD. AND HOOD RD. & CENTRAL JW Cheatham, ROADWAY 1 MOBILIZATION 1.0 LS $ 1,350,116.25 $ 906,000.00 $ 1,233,000.00 $ 1,233,000.00 $ 1,159,208.36 $ 1,159,208.36 $ 1,451,835.00 $ 1,451,835.00 $ 1,556,421.65 $ 1,556,421.65 2 MAINTENANCE

More information

RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO Item Description Est. Qty. Units Unit Price

RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO Item Description Est. Qty. Units Unit Price 2. BID SCHEDULE RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO. 7046 To the Honorable Mayor and City Council of the City of Hesperia: Schedule of prices to construct the Ranchero Road and BNSF

More information

PROJECT NO PID BEL TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02

PROJECT NO PID BEL TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02 AWARDED PROJECT PROJECT NO. 016002 PID. 19109 BEL-7-3.68 TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02 OHIO DEPARTMENT OF TRANSPORTATION GORDON PROCTOR, DIRECTOR CONTRACT

More information

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 1 T100 PROJECT LOCATION MAP Scale: NTS N Revisions: No. Date: Description: Scale As Indicated

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1113 VALUE ENGINEERING IN CONSTRUCTION. October 19, 2012

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1113 VALUE ENGINEERING IN CONSTRUCTION. October 19, 2012 STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1113 VALUE ENGINEERING IN CONSTRUCTION October 19, 2012 1113.01 Description 1113.02 References 1113.03 Definitions 1113.04 Value Engineering Change

More information

Including Maintenance & Rehabilitation Schedules

Including Maintenance & Rehabilitation Schedules Final Report Methodology for the Development of Equivalent Structural Design Matrix for Municipal Roadways- Montréal and Québec City Including Maintenance & Rehabilitation Schedules and Life Cycle Analysis

More information

a) Ensure public safety through reducing the threats to life and personal injury.

a) Ensure public safety through reducing the threats to life and personal injury. SECTION VII: FLOODPLAIN DISTRICT 7-1 Statement Of Purpose The purposes of the Floodplain District are to: a) Ensure public safety through reducing the threats to life and personal injury. b) Eliminate

More information

Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION

Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION Funding Allocations Routine State $ 166 Million Resurfacing Federal $ 260 Million

More information

NOTICE OF AWARD OF CONTRACT S.R. 408/S.R.417 INTERCHANGE IMPROVEMENTS PHASE 1. Project No. 253F Contract No

NOTICE OF AWARD OF CONTRACT S.R. 408/S.R.417 INTERCHANGE IMPROVEMENTS PHASE 1. Project No. 253F Contract No NOTICE OF AWARD OF CONTRACT S.R. 408/S.R.417 INTERCHANGE IMPROVEMENTS PHASE 1 Project No. 253F Contract No. 001118 October 8, 2015 Bids for this project were received and opened on September 16, 2015,

More information

Engineer s Report: School Section Lake Outlet 2017

Engineer s Report: School Section Lake Outlet 2017 WENCK File #0002-0230 June 2017 Revised August 2017 Engineer s Report: School Section Lake Outlet 2017 Prepared for: Clearwater River Watershed District 75 Elm St E PO Box 481 Annandale, MN 55389 Prepared

More information

FOR OFFICE USE ONLY CONTRACTOR/DEVELOPER APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE AND/OR MAINTAIN WITHIN THE RIGHT-OF-WAY/EASEMENT

FOR OFFICE USE ONLY CONTRACTOR/DEVELOPER APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE AND/OR MAINTAIN WITHIN THE RIGHT-OF-WAY/EASEMENT 40555 Utica Road P.O. Box 8009 Sterling Heights, MI 48311-8009 TEL 586-446-2720 FAX 586-276-4061 CONTRACTOR/DEVELOPER APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE AND/OR MAINTAIN WITHIN THE RIGHT-OF-WAY/EASEMENT

More information

GRAND TRAVERSE COUNTY ROAD COMMISSION

GRAND TRAVERSE COUNTY ROAD COMMISSION ADVERTISEMENT FOR BIDS EAST DUCK LAKE ROAD OVER MASON CREEK SINGLE SPAN TIMBER BRIDGE DESIGN, FABRICATION AND DELIVERY OF MATERIALS GRAND TRAVERSE COUNTY ROAD COMMISSION Sealed bids for materials for the

More information

Instructions for Completing the Annual Road and Street Finance Report

Instructions for Completing the Annual Road and Street Finance Report Instructions for Completing the Annual Road and Street Finance Report Additional information you wish to submit may be attached to the report on 8.5" by 11" paper. Please round all amounts up or down to

More information

SUBDIVISION IMPROVEMENTS AGREEMENT

SUBDIVISION IMPROVEMENTS AGREEMENT SUBDIVISION IMPROVEMENTS AGREEMENT THIS AGREEMENT, made between GLEN DEVELOPMENT COMPANY, hereinafter called the "Subdivider," and El Paso County by and through the Board of County Commissioners of El

More information

BID TABULATION BID REQUEST NO

BID TABULATION BID REQUEST NO BID TABULATION BID REQUEST NO. 13-1046 1 LOWEST RESPONSIVE BIDDER Dakota Contracting Bidder: Corporation D & G Concrete Bidder: Construction, Inc. Carl V. Carlson Bidder: Company Address: 431 NORTH PHILLIPS

More information

Including Maintenance & Rehabilitation Schedules

Including Maintenance & Rehabilitation Schedules Final Report Methodology for the Development of Equivalent Structural Design Matrix for Municipal Roadways- Including Maintenance & Rehabilitation Schedules and Life Cycle Analysis Prepared for: Cement

More information

HigHway Carrying Bridges in new Jersey

HigHway Carrying Bridges in new Jersey Highway Carrying Bridges in New Jersey Final Report October 2007 Table of Contents Executive Summary 2 I. Introduction 3 II. Findings Current Bridge Condition 4 Total Bridge Inventory 4 Age of Bridges

More information

NC STATE SURPLUS PROPERTY AGENCY BID CONTRACT. RE-Bid # D05083 Bid Opening: May 8, 10:00AM

NC STATE SURPLUS PROPERTY AGENCY BID CONTRACT. RE-Bid # D05083 Bid Opening: May 8, 10:00AM Bids will be publicly opened at the NC State Surplus Property Agency (SSPA) at the time and date specified. By signature, I certify that all bidder information is accurate and I agree to the Instructions,

More information

TIMBERLAKE COMMUNITY ASSOCIATION

TIMBERLAKE COMMUNITY ASSOCIATION TIMBERLAKE COMMUNITY ASSOCIATION REPLACEMENT RESERVE REPORT FY 2014 TIMBERLAKE COMMUNITY ASSOCIATION REPLACEMENT RESERVE REPORT FY 2014 Community Management by: Mr. Phil Massa, AMS, PCAM 933 Windsor Oaks

More information

Analysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs

Analysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs Analysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs Xiaoduan Sun, Ph.D., P.E. Civil Engineering Department University of Louisiana at Lafayette P.O. Box 4229, Lafayette,

More information

Allen County Highway Engineering Department Problems and Progress

Allen County Highway Engineering Department Problems and Progress Allen County Highway Engineering Department Problems and Progress K a r l J o h n s o n Allen County Highway Engineer Fort Wayne, Indiana IN T R O D U C T IO N The present and future traffic demands and

More information

Asset Management Plan

Asset Management Plan 2016 Asset Management Plan United Counties of Prescott and Russell 6/1/2016 Preface This Asset Management Plan is intended to describe the infrastructure owned, operated, and maintained by the United Counties

More information

1.0 CITY OF HOLLYWOOD, FL

1.0 CITY OF HOLLYWOOD, FL 1.0 CITY OF HOLLYWOOD, FL PAVEMENT MANAGEMENT SYSTEM REPORT 1.1 PROJECT INTRODUCTION The nation's highways represent an investment of billions of dollars by local, state and federal governments. For the

More information

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES GUIDANCE NOTES Rev 3 August 2017 INDEX Section Page 1 Introduction to Commuted Sums 3 2 When are Commuted

More information

OKLAHOMA TURNPIKE AUTHORITY

OKLAHOMA TURNPIKE AUTHORITY PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 70,000.00 $70,000.00 $ 15,735.00 $ 15,735.00 $ 60,000.00 $ 60,000.00 $ 25,000.00 $ 25,000.00 $ 20,000.00 $ 20,000.00 201(A) CLEARING & GRUBBING

More information

Reviax Constracting Corp. DeSantis Construction

Reviax Constracting Corp. DeSantis Construction Denise Piszkowski, Q.P.A., Purchasing Agent Bid Results for: 2016-B08 Reconstrucion of Preston Drive Submitted By: JTG Construction Black Rock Enterprises Top Line Construction Reviax Constracting Corp.

More information

REQUEST FOR PROPOSALS FOR WATER DISTRICT BRIDGE IMPROVEMENTS

REQUEST FOR PROPOSALS FOR WATER DISTRICT BRIDGE IMPROVEMENTS REQUEST FOR PROPOSALS FOR WATER DISTRICT BRIDGE IMPROVEMENTS January 4, 2019 The Town of Vail is seeking a qualified consultant team to provide design solutions required to repair or replace a damaged

More information

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES GUIDANCE NOTES Rev 1 January 2016 INDEX Section Page 1 Introduction to Commuted Sums 3 2 When are

More information

Appendix E: Revenues and Cost Estimates

Appendix E: Revenues and Cost Estimates Appendix E: Revenues and Cost Estimates Photo Source: Mission Media Regional Financial Plan 2020-2040 Each metropolitan transportation plan must include a financial plan. In this financial plan, the region

More information

Chapter 6: Financial Resources

Chapter 6: Financial Resources Chapter 6: Financial Resources Introduction This chapter presents the project cost estimates, revenue assumptions and projected revenues for the Lake~Sumter MPO. The analysis reflects a multi-modal transportation

More information

33 Ditch Bottom Inlet (DBI) -Type E $ 2, EA - 0 $ - 35 Ditch Bottom Inlet (DBI) -Type H (Modified) $ 5, EA $ 5,600.

33 Ditch Bottom Inlet (DBI) -Type E $ 2, EA - 0 $ - 35 Ditch Bottom Inlet (DBI) -Type H (Modified) $ 5, EA $ 5,600. CITY OF PLANT CITY WHEELER STREET RE-ALIGNMENT Opinion of Probable Construction Costs (Final Plans) Rev 7/22/2010 Rev 8/2/2010 Rev 8/27/20012 Bid Cost per Estimated Extended Item Item Unit Units Wheeler

More information

Opinion of Probable Cost

Opinion of Probable Cost Appendix E Opinion of Probable Cost 01054/8410233/14/Rohner_Alt_Analysis_Report Rohner Creek Flood Control, Habitat and Seismic Improvement Project Alternatives Analysis Cost Alternative 1: Improved Channel

More information

PennDOT Rapid Bridge Replacement Project

PennDOT Rapid Bridge Replacement Project PennDOT Rapid Bridge Replacement Project Ohio Transportation Engineering Conference October 27 28,2015 Agenda Project Overview Project Development and Scoping Procurement Process Technical Requirements

More information

CRISP COUNTY, GEORGIA AND INCORPORATED AREAS

CRISP COUNTY, GEORGIA AND INCORPORATED AREAS CRISP COUNTY, GEORGIA AND INCORPORATED AREAS Community Name Community Number ARABI, CITY OF 130514 CORDELE, CITY OF 130214 CRISP COUNTY (UNINCORPORATED AREAS) 130504 Crisp County EFFECTIVE: SEPTEMBER 25,

More information

PROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM

PROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM NAME OF CONTRACTOR PROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM PROJECT NO. 4907 1.08 miles of roadway reconstruction including clearing, grade establishment, sand subbase,

More information

STANDARD PROCEDURE FOR VALUE ENGINEERING IN CONSTRUCTION

STANDARD PROCEDURE FOR VALUE ENGINEERING IN CONSTRUCTION Standard Procedure No.: 510-008(SP) Effective Date: September 14, 2011 Responsible Division: Construction Management Approved: Megan Blackford, P.E. Deputy Director, Division of Construction Management

More information

Monroe County Road Commission. 840 S. Telegraph Road Monroe, MI Phone Fax Driveway Procedures. Driveway Procedures

Monroe County Road Commission. 840 S. Telegraph Road Monroe, MI Phone Fax Driveway Procedures. Driveway Procedures Monroe County Road Commission 840 S. Telegraph Road Monroe, MI 48161 Phone 734 240 5100 Fax 734 240 5101 Driveway Procedures Monroe County Road Commission Driveway Procedures WHEREAS, per section 247.325

More information

PN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS

PN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS PN 126 (LPA) - 12/31/2012- REVISIONS TO THE 2013 C&MS FOR DESIGN BUILD PROJECTS 101.01 On page 1, Add the following: NOTE: The fact that the bid items for this Design-Build project are general rather than

More information

Report on Concrete Dam Construction

Report on Concrete Dam Construction Workers Compensation Insurance Rating Bureau of California Workers Compensation Insurance Rating Bureau of California Report on Concrete Dam Construction Excerpt from the WCIRB Classification and Rating

More information

PROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM

PROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM NAME OF CONTRACTOR PROPOSAL AND SPECIFICATIONS FOR HIGHWAY CONSTRUCTION COUNTY LOCAL ROAD SYSTEM PROJECT NO. 4735 1.00 miles of roadway reconstruction including grade establishment, sand subbase, aggregate

More information

2016 PAVEMENT CONDITION ANNUAL REPORT

2016 PAVEMENT CONDITION ANNUAL REPORT 2016 PAVEMENT CONDITION ANNUAL REPORT January 2017 Office of Materials and Road Research Pavement Management Unit Table of Contents INTRODUCTION... 1 BACKGROUND... 1 DATA COLLECTION... 1 INDICES AND MEASURES...

More information