Paradise Island Condominium Association Final Report of the Reserve Study Review Committee

Size: px
Start display at page:

Download "Paradise Island Condominium Association Final Report of the Reserve Study Review Committee"

Transcription

1 Paradise Island Condominium Association Final Report of the Reserve Study Review Committee March 11, 2014 Chairperson Mary Linak Members Jeff Duppler Chuck Lanius Bill Murphy Paul Pudlas Advisor Mike Ashworth, Resident Manager

2 March 11, 2014 Final Report

3 Reserve Study Review Committee Report Summary The PICA Board of Directors chartered a Reserve Study Review Committee to update the previous study dated July 27th, Both the charter and committee members are in appendices at the end of this report. The team met nine times between September 17, 2013 and January 13, Ongoing verbal updates were given to the Board during this period. Key Points from the Review 1. All decks and balconies, including wood, metal & composite were physically measured and inspected for current condition as well as wear or defects. The worksheets are available from the Resident Manager. 2. Concrete patios, sidewalks and stoops were physically measured and inspected for current condition as well as wear or defects. The worksheets are available from the Resident Manager. 3. During the course of this review, the team members discussed the need for a strong maintenance program that is difficult to fund solely through the annual Operating Budget. To address this need, an auxiliary Reserve Refurbishment Budget was created and funded within the reserve budget. 4. With the addition of this Refurbishment Budget, several elements were not assigned a cost within the Reserve/Replacement Budget due to their extended remaining useful lives, but periodic maintenance expenses were covered. 5. Future replacement cost of the floating docks was split between the Association and slip owners. 6. Based on the Committee s findings during physical inspection, research, and estimates from various contractors, spending over the 30-year span of the study was realigned between replacement and refurbishment costs. Total expenditures are projected to be $ 2,566,934 over this time frame, representing the team s best efforts to balance costs and look for alternatives, while maintaining the integrity of PICA s assets. 1

4 Discussion The Reserve Committee members reviewed the 2010 study and decided to break out decks, balconies and concrete structures by unit, in order to create a current inventory and rating on the condition of each. The team was then able to predict the remaining useful life of these elements. By creating this level of detail, it was possible to account for several replacements completed in the last three years. This plan is similar to the way roofs were handled in the 2010 review. The Resident Manager was once again an advisor to the Committee, providing valuable technical support and access to past repair and replacement records. He was also in contact with various contractors, engineers and vendors throughout the study to ensure the accuracy of cost estimates. His assistance with the spreadsheets used and published in this study was crucial to the Committee meeting its goal within the expected timeframe. 2

5 Physical Exterior Building Elements Balconies, Metal Deck and Wood Frame: The details of size and condition are recorded in the report spreadsheet. In short, the committee found these decks to be in good condition and likely to have a useful life of 45 years. Replacement costs are estimated to be $35 per sq. ft. in today s dollars. Therefore, replacement is broken into five phases based on year built. However, these decks are likely to need maintenance before reaching the need for replacement. For that reason, there is a five-phased painting plan in the Refurbishment Budget beginning in 2026 and ending in During inspection, several support posts were found with cracks and the Committee would recommend that these be replaced as needed from the Operating Budget to prevent a larger expense. In addition, this team agrees with the findings of the 2010 (and earlier) report regarding insufficient overhang and misdirected storm water from the upper balconies on Holtz buildings and recommends drip edge flashing or gutters be installed. Decks and Balconies, Wood: The details of size and condition are recorded in the report spreadsheet. Based on recent replacements, the team discussed whether composite material or treated lumber should be used in the future. Based on a cost analysis that compared the life span of the various materials and the expense of periodic wood staining, the Committee recommends future replacements be done with composite material. This includes all rail systems. Estimates place the cost of this recommendation at $47 per sq. ft. in today s dollars. The timing for replacement is based on deck conditions found in the physical inventory and falls into five phases. Funds for staining were placed in the Refurbishment Budget until all wood decks have been replaced with composite material. Roofs, Asphalt Shingles: The Committee reviewed engineering reports on the Holtz roofs from 2008, and the 2013 inspection report from a local roofing contractor which included satellite measurements and a $330 per square all inclusive replacement cost. Based on this information, it is recommended that the roofs on buildings 14 and 15 be budgeted for replacement in 2015 and Thereafter, roof replacement has been spread between 2018 and 2024, with both the contractor s rating and budget concerns determining the order in which the work is completed. For those buildings that have already been reroofed and those planned in the future, the expected useful life is 25 years. This next round of roofing would begin in 2033 as shown in the Reserve Expenditures spreadsheet. The Committee retained the line item for attic inspections but extended the timing to every 10 years with the next inspections slated for This change is based on recent experience. 3

6 Walls, Aluminum Siding: The Committee found that aluminum siding within the Association remains in excellent condition and research found that, with periodic painting, the useful life of this material can be 50 years or more. Therefore, rather than budgeting for replacement costs, the team placed funds in the Refurbishment Budget for painting the aluminum siding in five phases beginning in The estimate is based on the original study square footage of 8075 sq. ft. and costs found on-line. Walls, Vinyl Siding: Through research, the Committee found vinyl siding is expected to have a useful life of 50 years. The vinyl siding within PICA is in excellent condition and no funds were budgeted within the span of this study for replacement. Chimney Caps: This item was removed from Reserve Funding and should be handled in the Operating Budget on an as needed basis. Gutters and Downspouts: The Committee recommends this element be replaced, if needed, in conjunction with the siding on a unit. Since both aluminum and vinyl siding have life spans of 50 years, there is no cost budgeted within the Reserve Fund for total replacement. However, there is a recommendation to install gutters and downspouts or drip edge flashing to the second story decks on Holtz buildings. Light Fixtures: This item was removed from Reserve Funding and should be handled in the Operating Budget on an as needed basis considering the recent wholesale replacement. Building Services Elements Elevator, Hydraulic Pump and Controls: The expected useful life of the elevator is 50 years which extends funding for replacement beyond the scope of this study. Periodic repairs and inspections will be funded through the Operating Budget. Property Site Elements Concrete Patios: The Committee inspected each concrete patio within PICA to record measurements and condition on a 1 5 scale with a rating of 5 meaning a useful life of 70 years. Of the nearly 80 patios, one was found to need maintenance within 3 years, one had a 5-year timeline and 6 will need work within 10 years. None of them were in need of complete replacement, but will need some repair. It was the inspection of all concrete surfaces within PICA that led to including $5000 in each of five different years over the span of this study in the Refurbishment Budget for concrete maintenance. 4

7 Repair of all the various concrete surfaces in this section of the study would be funded from this budget. Concrete Sidewalks: Of the 50 sidewalk sections inspected, two were found to be in poor condition and have been repaired. Four sections will need maintenance within five years and another twenty rated a 10-year timeline for repair. All others are considered to have a 50-year useful life. Concrete Stoops, Steps and Aprons: Eleven stoops/steps/aprons are in need of repair in Eight stoops would be in the next group to be repaired in The others were rated as fours and fives on the inspection scale and their repair would be funded by later budget allowances for concrete refurbishment. Asphalt Pavement, Phased Overlay: The Committee Advisor spoke to a local asphalt contractor to obtain quotes and potential timing for this three inch deep overlay estimate. The estimate is for $9.45 per sq. yd. over two phases in 2027 and Measurements from the previous study were used. This recommendation also includes continued funding for asphalt sealing every three years, but in the Refurbishment Budget. Asphalt Pavement, Partial Replacement: There are approximately 1100 square yards of pavement that require replacement this year. Their location is the driveway up to building 19 and the driveway between buildings 12 and 13. The contractor estimate for total asphalt replacement is $16 per sq. yd. and the funds are budgeted for Asphalt Pavement, Total Replacement: With the periodic resealing and phased overlay described above, the Committee recommends complete asphalt replacement beginning in Light Poles: This item was removed from Reserve funding and should be handled in the operating budget on an as needed basis. Retaining Walls, Stone: The Committee agreed with the recommendations of the previous study and kept the three-phase inspection and partial replacement funds in the reserve budget. Wells, Pumps: The Committee agreed with the recommendations of the previous study and funded the scheduled replacement of one pump per year beginning in 2018 and ending in Docks, Fixed: The deck surfaces of the fixed docks were replaced with composite material in 2013, giving them an expected useful life of 50 years from that date. Therefore, no funds were included in this study for future replacement. The metal frames 5

8 and supports may need repair or partial replacement when inspected each season. These costs would be part of the Operating Budget/Marina Budget. Docks, Floating: The Committee recommends splitting the cost of floating dock replacement between the Association and slip owners. The Association would be responsible for total linear feet on each central dock and the slip owners would cover the cost for total linear feet along the slips. This split is shown on the Reserve Expenditures spreadsheet. The cost for floating docks has been reduced based upon recent estimates from the manufacturer, ShoreStation. An exact replacement system is no longer available, but the new docks would be similar except for the decking material, which is now treated lumber as opposed to the existing plastic. Estimated assembly costs are also included in the spreadsheet. Since replacement is far in the future, decisions regarding the materials to be used will be made at that time. Pond and Lake Shoreline, Erosion Control: This element remains funded at the same level as recommended by the previous study. 6

9 Financial Inflation Rate Assumptions: Committee members researched various on-line references in regard to inflation rate predictions. These included the Federal Reserve Bank of Cleveland, Statista.com, the Congressional Budget Office and Federal Reserve.gov. Projections over the next ten years ranged from 1.5% to 2.0%. The Committee agreed to use a forecast of 1.85% inflation on average for spending projections. This estimate will need to be reviewed and updated by future Reserve Study teams. Interest Rate Assumptions: Interest rates are at all-time lows and it is difficult to predict when they will increase. The Committee is recommending that the PICA Board use a laddering method to reinvest the Certificate of Deposit (CD) that will mature this year in order to earn more interest on funds that will not be needed in the near future. Research does show that on-line banking institutions are offering higher interest rates on various types of deposits and could be an option for PICA. This CD along with the bond fund and deposit accounts will earn less than the 2010 estimate. The team agreed to set the interest projection at 1.85% with the goal of offsetting estimated inflation. Operating Budget Threshold: The Committee had many discussions on the dollar limit of expenditures to be financed within the Reserve Budget and noted the conflict between replacement and repair for high cost elements with long useful lives. In the end, a decision was reached to create an auxiliary to the Reserve Budget titled Reserve Refurbishment Budget that includes wood deck staining, asphalt sealing, concrete repair, aluminum siding painting and metal deck painting. The dollar threshold for costs to include in this budget was $5000, with one exception. Due to the wood deck replacement schedule, eventually there will not be enough wood decks that need staining to reach this dollar level. By providing for these scheduled refurbishments, the Committee enables the Board to avoid large swings in the Operating Budget. Maintain Adequate Reserves: The overriding goal of the Committee was to account for all necessary expenses to maintain the common elements within PICA while growing a Reserve Fund adequate to cover these expenses now and into the future. The path to accomplishing this goal is illustrated in the Reserve Funding Plan Cash Flow spreadsheet. Reserve funding consists of the current balance, interest earned, annual contributions from unit owners, reimbursement from slip owners for improvements and PIHOA payments for the new fixed docks. Based on this funding model, the Reserve balance would cover all costs itemized in the Reserve Expenditures spreadsheet through 7

10 2043. The Committee strove to keep contribution increases as low as possible while assuring funds would be available for replacements and repairs as specified. 8

11 Recommendations to the Board 1. The Reserve Committee recommends contributions to the Reserve Fund increase by 30% ($12,000) in 2014, with an additional 5% increase (not compounded) each subsequent year through 2029, thus ensuring adequate funds are available to cover expected costs and future inflation. See Reserve Funding spreadsheet. 2. Move several large refurbishment costs from the Operating Budget to a new section of the Reserve Budget as demonstrated in the Reserve Expenditures spreadsheet. This action will smooth out planning for operating expenses while assuring funds are available for deck staining, asphalt sealing, concrete repair, aluminum siding painting and metal deck painting when needed. 3. The Reserve Committee recommends a robust maintenance program within the annual Operating Budget to prolong the useful life of physical elements inventoried in this study. Replacement of various assets could be moved further into the future by planning for things like deck post replacements, building cleaning, and roof maintenance. 4. Light poles and fixtures along with chimney cap replacement should be moved to the Operating Budget due to their relatively low cost and sporadic need. 5. As a part of the plan to achieve investment earnings of 1.85% on average, per year, the Committee recommends laddering the Certificate of Deposit maturing in It is recommended the Board charter a new review every 3 to 5 years to update these working documents and accommodate new information or changes in the condition of PICA common elements. 9

12

13 Appendices: A. Charter B. Members C. Reserve Expenditure Spreadsheet D. Reserve Funding Sheet E. Reserve Funding Graph

14 Appendix A Charter for the Reserve Study Review Committee Purpose: The Reserve Study Review Committee is commissioned by the Board of Directors to review the July 27, 2010 Final Report of the Reserve Study Review Committee of the Paradise Island Condo Association and make recommendations back to the Board concerning actions that may be appropriate for the Board to take regarding PICA Reserves. Responsibilities: The committee will review the original study. They will review the physical analysis and comment on the completeness of the component inventory, the estimated years of replacement, useful life remaining, unit cost of the components, and the validity of the assumptions used in the physical study, making use of the repair, replacement and maintenance data over the past 3 years. They will also review the financial analysis and comment on the assumptions made concerning inflation rate and interest rate, the operating budget threshold, and potential need to augment the Reserves so as to maintain adequate Reserves. The committee will make periodic reports of progress to the Board and provide a written report to the Board by March Term: The committee shall exist for a period of 6 months, with potential extension by application to the Board. Committee Organization: The committee chair shall be Mary Linak. Additional and/or replacement members will be selected by the chairman with Board approval. Mike Ashworth, Resident Manager, will provide access to maintenance records, repair contracts, and any necessary files. Additionally, Mike Ashworth shall serve as an advisor to the committee as will Tim Hood, the previous Reserve Study Review Committee chairperson. Approved by the Board: 08/27/2013 Original Signed Mike Plumer, Board Secretary

15 Appendix B Reserve Study Committee Members Mary Linak Chairperson Jeff Duppler Chuck Lanius Bill Murphy Paul Pudlas Mike Ashworth Advisor

16 Appendix C Reserve Expenditures Paradise Island Condominium Association Inflation Rate = 1.85% TOTAL Expenditure over 30 year period = 2,566,934 Life Analysis 30 Yr Units No. Estimated Next Useful Life Remaining Use- Unit Cost Replacement 2014 Cost of Line Unit Per Phas Units Reserve Component Inventory Yr of Last Item Total Phase es Year Built Replacement Curr future Repl ful Life per Phase 1a sq ft ,820 1b sq ft ,110 Balconies, Metal Deck & Wood Frame, phased 1c sq ft ,478 replacement 1d sq ft ,984 1e sq ft ,270 2a sq ft varies 2017 varies varies NA ,740 2b sq ft varies 2021 varies varies NA ,766 Balconies, Wood Deck & Frame, phased replacement 2c sq ft varies 2022 varies varies NA ,800 (with composite) 2d sq ft varies 2024 varies varies NA ,860 2e sq ft varies 2029 varies varies NA ,852 3a each Roof Replacement - Building ,350 51,350 3b each Roof Replacement - Building ,350 51,350 3c each Roof Replacement - Building ,350 51,350 3c each Roof Replacement - Building ,350 51,350 3d each Roof Replacement - Building ,350 51,350 3e each Roof Replacement - Building ,350 51,350 3f each Roof Replacement - Building ,800 20,800 3g each Roof Replacement - Building ,800 20,800 3h each Roof Replacement - Building ,725 23,725 3i each Roof Replacement - Building ,725 23,725 3j each Roof Replacement - Building ,725 23,725 3l each Roof Replacement - Building ,950 33,950 3m each Roof Replacement - Building ,500 68,500 3n each Roof Replacement - Building ,200 59,200 3o each Roof Replacement - Building ,350 51,350 3p each Roof Replacement - Building ,500 41,500 3q each Roof Replacement - Building ,850 18,850 3r each Roof Replacement - Building ,850 18,850 3s each Roof Replacement - Building ,150 20,150 3t each Roof Replacement - Building ,850 18,850 3u each Roof Replacement - Building ,000 18,000 3v each Inspect all attics on 10 year basis NA NA 5 10,000 10, sq ft Walls, Vinyl Siding, partial replacement varies NA , sq ft Walls, Aluminum Siding varies NA NA see rfrb 5 43, each Elevator, Hydraulic Pump and Controls NA 30 36,000 36,000 7a sq yds Asphalt Pavement, Repaving, Phased Overlay varies to to 20 NA ,338 7b sq yds Asphalt Pvmt, Repaving, total repl, (12,13,19) varies to to 20 NA ,325 7c sq yds Asphalt Pvmt, Repaving, total repl ( in phases) varies to to , sq yds Concrete Replacement varies NA NA see rfrb unknown unknown lin ft Docks, floating (Associations portion) NA NA , sq ft Docks Fixed(*see narrative) NA NA unknown unknown lin ft Pond and Lake Shoreline, Erosion Control, partial NA , sq ft Ret.Walls, Stone, insp.& part. replacement varies NA , each Wells, Pumps varies ,000 4,000 Capital Expend Reserve Refurbishment Categories 14a Unit No.> 2771, 2777, 2779, 2783, 2785, ,294 7,294 14b Unit No.> 2780 & ,588 3,096 14c 2776, 2794, 2792, 2790, 2788, 2786, 2784, 2782, Unit No.> 2804, 2802, 2800, , ,602 9, Asphalt Sealing Every 3 Years beginning in , Concrete Repair As Needed 5, Aluminum Siding As Needed 7, Metal Deck Painting As Needed 5,000 Maintenance Expend Total - All Expendit Accumulated Expe Slip Owner's Reserve Components Lin. Ft Docks, floating (Slip Owners portion) NA NA ,915

17 s, Years > Total Future Cost of Repl (30 Yr proj ,856 20,856 76,383 76,383 23,000 23,000 21,850 21, ,627 71,651 56,279 56,279 59,461 59,461 43,785 43,785 18, ,961 55,257 61,681 61,681 29,466 23,648 23,648 27,981 27,981 28,498 28,498 28,498 28,498 40,040 40,040 76,464 76,464 83, ,384 52, ,744 43,050 27,701 20,659 20,659 22,084 22,084 27,198 20,843 20,843 39,938 10,960 13, , ,194 68,959 70,235 17,325 17,325 65,662 unknown 49,289 unknown 36,837 36, ,318 46,739 56,142 74,878 4,304 4,384 4,465 4,548 4,632 4,717 4,805 4,894 4,984 5,076 5,170 5,266 ditures By Year 17,325 52,300 89,788 20,856 59, , ,766 71,981 84, , ,482 49,744 61,126 74,036 75,405 90,082 7,567 8,143 3,271 3,520 9,960 10,718 11,533 15,560 16,440 17,369 18,351 19,389 5,000 5,480 6,117 6,582 8,256 17,128 9,215 6,230 6,345 6,463 6,582 ditures by Year 5, ,087 3, ,920 18,860 3,520 17,369 8,256 11,533 41,596 6,230 6,345 25,851 22,380 tures - by Year 22,325 52, ,876 24,127 59, , ,626 75, , , ,015 91,340 67,356 80, , ,462 enditures 22,325 74, , , , , , , , ,282 1,024,298 1,115,637 1,182,994 1,263,375 1,364,632 1,477,094 70,413

18 ,976 18,186 82,704 29,466 83,865 27,701 82,704 87,380 68,076 70,618 27,198 15,813 74,368 65,662 49,289 67,437 5,363 5,463 6,807 78,340 5, ,517 27,198 76,990 67, , ,408 68, ,835 20,485 21,643 22,866 24,159 25,525 7,907 9,560 9,916 6,704 6,704 30, ,916 21, , ,907 24, ,525 85,044 35, ,434 48,840 76,990 67,437 22, , ,567 68, ,359 1,562,138 1,597,644 1,597,644 1,739,078 1,787,919 1,864,908 1,932,345 1,955,211 1,955,211 1,978,932 2,168,499 2,236,575 2,236,575 2,566,934 70,413

19 Appendix D Reserve Funding Plan Cash Flow Analysis 2014 Budget Reserves at Beginning of , Reserve Contribution 40,000 Paradise Island Condominium Association Interest Rate 1.85% 2014 Reserve Contribution 59,233 Inflation rate DOES NOT apply to contributions Projected Reserves at EOY ,378 Multiple (of 2013) Year Reserve Category Reserves at Beginning of Year 335, , , , , , , , , ,767 Total Recommended Reserve Contribution 59,233 59,988 58,448 60,448 62,448 64,448 66,448 68,448 70,448 72,448 Estimated Interest Earned, During Year 6,880 7,150 6,090 6,875 7,055 5,857 4,667 4,623 4,119 2,624 Anticipated Expenditures, By Year -22,325-52, ,876-24,127-59, , ,626-75, , ,376 Anticipated Reserves at Year End 378, , , , , , , , , ,463 Absolute value of expenditure by year for graph 22,325 52, ,876 24,127 59, , ,626 75, , ,376 Increase All Owners Average Low High Marina Contributions PIHOA Slip Owners Electrical Reimbursement for Fixed Piers Marina Income Combined Multiple (of 2013) Year Reserve Category Reserves at Beginning of Year 144,463 85,447 71,861 84,487 86,118 68,555 41,291 41,448 89, ,742 Total Recommended Reserve Contribution 74,448 76,448 78,448 80,448 82,448 84,448 84,448 82,000 82,000 82,000 Estimated Interest Earned, During Year 1,552 1,305 1,535 1,564 1, ,627 3,174 2,133 Anticipated Expenditures, By Year -135,015-91,340-67,356-80, , ,462-85,044-35, ,434 Anticipated Reserves at Year End 85,447 71,861 84,487 86,118 68,555 41,291 41,448 89, , ,441 Absolute value of expenditure by year for graph 135,015 91,340 67,356 80, , ,462 85,044 35, ,434 Increase All Owners Average Low High Marina Contributions PIHOA Slip Owners Electrical Reimbursement for Fixed Piers Marina Income Combined

20 Multiple (of 2013) Year Reserve Category Reserves at Beginning of Year 117, , , , , , , , , ,878 Total Recommended Reserve Contribution 82,000 82,000 82,000 82,000 82,000 82,000 82,000 82,000 82,000 82,000 Estimated Interest Earned, During Year 2,786 2,930 3,254 4,408 6,007 7,196 5,339 5,696 7,318 2,859 Anticipated Expenditures, By Year -48,840-76,990-67,437-22, , ,567-68, ,359 Anticipated Reserves at Year End 153, , , , , , , , , ,378 Absolute value of expenditure by year for graph 48,840 76,990 67,437 22, , ,567 68, ,359 Increase All Owners Average Low High

21 Appendix E Paradise Island Condominium Association 2014 Reserve Study Expenditures and Funding Analysis 450, Total Recommended Reserve Contribution Anticipated Reserves at Year End Absolute value of expenditure by year for graph 400, ,000 Reserve Ac ccumulations 300, , , , , , Years

Update With Site Visit

Update With Site Visit Update With Site Visit Le Chateau Bellevue, WA 10/28/2011 Report #1002 Phone: 253-241-8151 Fax: 360-872-8073 E-mail: jeremy@reservesolutions.net www.reservesolutions.net Le Chateau Client Info: REPORT

More information

RESERVE FUND STUDY VILLAS OF HUDSON HOMEOWNERS ASSOCIATION HUDSON, OHIO

RESERVE FUND STUDY VILLAS OF HUDSON HOMEOWNERS ASSOCIATION HUDSON, OHIO RESERVE FUND STUDY VILLAS OF HUDSON HOMEOWNERS ASSOCIATION HUDSON, OHIO Criterium Liszkay Engineers 110 N. High St. Gahanna, OH 43230 614-418-7200 www.clengineers.com AUGUST, 2009 1.0 INTRODUCTION... 1

More information

Level 3 Reserve Study without a Site a Site Visit Visit

Level 3 Reserve Study without a Site a Site Visit Visit Level 3 Reserve Study without a Site a Site Visit Visit We offer two types of reports for a Level 3 Reserve Study with a Site Visit, RS-3 - Standard Reserve Study without a site visit SMRS-3 - Statutory

More information

SOMERSET CREEK STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT. With funding recommendations for the 2019 fiscal year

SOMERSET CREEK STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT. With funding recommendations for the 2019 fiscal year SOMERSET CREEK Bellevue, Washington STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT With funding recommendations for the 2019 fiscal year Issued April, 2018 Next Update: Level 2 by April, 2019

More information

REPLACEMENT RESERVE REPORT FY 2016

REPLACEMENT RESERVE REPORT FY 2016 REPLACEMENT RESERVE REPORT FY 2016 VILLAS AT PARKWOOD ESTATES VILLAS AT PARKWOOD ESTATES REPLACEMENT RESERVE REPORT FY 2016 Community Management by: Community Management Professionals, LLC Beth Maurer

More information

VILLAGE AT LAKE CHELAN

VILLAGE AT LAKE CHELAN VILLAGE AT LAKE CHELAN Manson, Washington STANDARD LEVEL 3 RESERVE STUDY UPDATE WITHOUT A SITE VISIT With funding recommendations for the 2019 fiscal year Issued October, 2018 Next Update: Level 3 by October,

More information

REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION. N & H Enterprises MILLER ~ DODSON ASSOCIATES. Community Management by:

REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION. N & H Enterprises MILLER ~ DODSON ASSOCIATES. Community Management by: REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION WOODWIND ASSOCIATION REPLACEMENT RESERVE REPORT FY 2010 Community Management by: N & H Enterprises PO Box 5539 Greenville, SC 29607 864-467-1600

More information

OAK CREEK CONDOMINIUMS

OAK CREEK CONDOMINIUMS 1515 Heritage Dr., Suite 204 McKinney, Texas75069 (972) 562-1011 TEL (972) 540-1031 FAX Firm Reg. No F-4577 www.criteriumdotson.com RESERVE FUND STUDY OAK CREEK CONDOMINIUMS 1700 BAIRD FARM CIRCLE ARLINGTON,

More information

Reserve Analysis Report

Reserve Analysis Report Reserve Analysis Report Soda Creek Condominiums Dillon, Colorado Version 2 Monday, August 19, 2013 6860 S. Yosemite Court, Suite 2000 Centennial, CO 80112 Phone (303) 953-2078 Facsimile (303) 953-2157

More information

FULL RESERVE STUDY Woodridge Park Homeowners' Association, Ltd. Orchard Park, New York November 10, 2017

FULL RESERVE STUDY Woodridge Park Homeowners' Association, Ltd. Orchard Park, New York November 10, 2017 FULL RESERVE STUDY Woodridge Park Homeowners' Association, Ltd. Orchard Park, New York November 10, 2017 This Report contains intellectual property developed by Reserve Advisors, Inc. and cannot be reproduced

More information

Parkwood HOA. Level 1 Reserve Study. Report Period 1/1/ /31/2012. Date of Property Inspection. Report prepared on Saturday, August 11, 2012

Parkwood HOA. Level 1 Reserve Study. Report Period 1/1/ /31/2012. Date of Property Inspection. Report prepared on Saturday, August 11, 2012 Parkwood HOA Level 1 Reserve Study Report Period 1/1/2012 12/31/2012 Client Reference Number Property Type Number of Units Fiscal Year End 12784 Townhouse 8 12/31 Date of Property Inspection Prepared By

More information

Ashleigh Commons Condominiums Association, Inc.

Ashleigh Commons Condominiums Association, Inc. RESERVE STUDY Full Study Ashleigh Commons Condominiums Association, Inc. Published - January 14, 2016 Browning Reserve Group / Emmett, ID 83617 Office (208) 365-0977 Tony@BrowningRG.com / www.browningrg.com

More information

2014 Reserve Study. The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee Report No: 2921 Version 2

2014 Reserve Study. The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee Report No: 2921 Version 2 2014 Reserve Study The Bear Creek Crossing Owner's Association, Inc. Bear Haven Way Sevierville, Tennessee 37862 Report No: 2921 Version 2 For the Period From: January 1, 2014 To: December 31, 2014 TABLE

More information

HARBOR POINTE CONDOMINIUM ASSOCIATION INC CONDOMINIUM APPROVED BUDGET YEAR ENDING DECEMBER 31, 2017

HARBOR POINTE CONDOMINIUM ASSOCIATION INC CONDOMINIUM APPROVED BUDGET YEAR ENDING DECEMBER 31, 2017 210 Monthly Condominium Assessment $ 477.00 Condominium Income Assessment Income Condominium 1,202,040.00 Assessment Income: $ 1,202,040.00 Condominium Expenses General / Administrative Management Fee

More information

REPLACEMENT RESERVE REPORT FY 2019 SANCTUARY AT FALSE CAPE. Prepared for: Ms. Rebecca Beamon

REPLACEMENT RESERVE REPORT FY 2019 SANCTUARY AT FALSE CAPE. Prepared for: Ms. Rebecca Beamon SANCTUARY AT FALSE CAPE REPLACEMENT RESERVE REPORT FY 2019 SANCTUARY AT FALSE CAPE REPLACEMENT RESERVE REPORT FY 2019 Prepared for: SANCTUARY AT FALSE CAPE Ms. Rebecca Beamon 3700 Sandpiper Road Virginia

More information

PROFESSIONAL RESERVE STUDY

PROFESSIONAL RESERVE STUDY PROFESSIONAL RESERVE STUDY LEVEL 3 UPDATE Tamarack Village 10701 to 10798-221 st Lane NE, Redmond, WA 98053 For: Tamrack Village Homeowners Association c/o Tim Ambre, Property Manager econdoservices 1500-112

More information

FLINT HILL MANOR FLINT HILL MANOR. Replacement Reserve Study. Oakton, Virginia. Property Management: Flint Hill Manor Townhouse Association

FLINT HILL MANOR FLINT HILL MANOR. Replacement Reserve Study. Oakton, Virginia. Property Management: Flint Hill Manor Townhouse Association Replacement Reserve Study REPLACEMENT RESERVE STUDY Oakton, Virginia Property Management: Flint Hill Manor Townhouse Association Jamie Critchfield Vice President Email: tommie0200@aol.com Consultant: RICHARD

More information

HUDSON PARK ESTATES HOMEOWNERS ASSOCIATION HUDSON, OHIO

HUDSON PARK ESTATES HOMEOWNERS ASSOCIATION HUDSON, OHIO RESERVE FUND STUDY HUDSON PARK ESTATES HOMEOWNERS ASSOCIATION HUDSON, OHIO Criterium Liszkay Engineers 110 N. High St. Gahanna, OH 43230 614-418-7200 www.clengineers.com AUGUST 2016 CONTENTS 1.0 INTRODUCTION...

More information

FULL RESERVE STUDY Ameri-Cana Resorts Co-op, Inc. Rockledge, Florida April 13, 2017

FULL RESERVE STUDY Ameri-Cana Resorts Co-op, Inc. Rockledge, Florida April 13, 2017 FULL RESERVE STUDY Ameri-Cana Resorts Co-op, Inc. Rockledge, Florida April 13, 2017 This Report contains intellectual property developed by Reserve Advisors, Inc. and cannot be reproduced or distributed

More information

Clearbrook HOA. Level 1 Reserve Study. Report Period 1/1/ /31/2010. Client Reference Number /23/2010 Prepared By

Clearbrook HOA. Level 1 Reserve Study. Report Period 1/1/ /31/2010. Client Reference Number /23/2010 Prepared By Clearbrook HOA Level 1 Reserve Study Report Period 1/1/2010 12/31/2010 Client Reference Number 11775 Property Type Apartment Style Number of Units 21 Fiscal Year End 12/31 Date of Property Inspection 3/23/2010

More information

WHAT IS A RESERVE STUDY AND WHY ARE THEY IMPORTANT?

WHAT IS A RESERVE STUDY AND WHY ARE THEY IMPORTANT? WHAT IS A RESERVE STUDY AND WHY ARE THEY IMPORTANT? Tom Larson, PE, RS, PRA Facility Engineering Associates, PC What is a Reserve Study? A budget planning tool which identifies the current status of the

More information

NEWTON PARISH REPLACEMENT RESERVE REPORT 2008 REPLACEMENT RESERVE REPORT FY CAS, Inc MILLER ~ DODSON ASSOCIATES. Community Management by:

NEWTON PARISH REPLACEMENT RESERVE REPORT 2008 REPLACEMENT RESERVE REPORT FY CAS, Inc MILLER ~ DODSON ASSOCIATES. Community Management by: REPLACEMENT RESERVE REPORT 2008 NEWTON PARISH NEWTON PARISH REPLACEMENT RESERVE REPORT FY 2008 Community Management by: CAS, Inc Mr. Dan Quartermane 1930 N. Salem Street, Suite 101 Apex, NC 27523 919-367-7711

More information

Shadow Ridge. Level 2 Reserve Study. Report Period 01/01/ /31/2015. Date of Property Inspection 8/21/2014

Shadow Ridge. Level 2 Reserve Study. Report Period 01/01/ /31/2015. Date of Property Inspection 8/21/2014 Shadow Ridge Level 2 Reserve Study Report Period 01/01/2015 12/31/2015 Client Reference Number 10160 Property Type Condominium Number of Units 168 Fiscal Year End 12/31 Date of Property Inspection 8/21/2014

More information

FULL RESERVE STUDY FUNDING ANALYSIS PLAN Level I

FULL RESERVE STUDY FUNDING ANALYSIS PLAN Level I FULL RESERVE STUDY FUNDING ANALYSIS PLAN Level I QUALCHAN HILLS HOMEOWNER S ASSOCIATION Prepared by: CRITERIUM PFAFF ENGINEERS 12128 N. DIVISION ST. #200 (509)467-8554 6 AUGUST 2012 CONTENTS 1.0 INTRODUCTION...

More information

Reserve Analysis Report

Reserve Analysis Report Reserve Analysis Report Sample HOA 2663 S Oakland St Los Angeles, CA Level I Study with Site Inspection Fiscal Year End: 11/30/2016 Phone: 858-764-1895 Fax: 800-436-3816 brian@mccafferyreserveconsulting.com

More information

TIMBERLAKE COMMUNITY ASSOCIATION

TIMBERLAKE COMMUNITY ASSOCIATION TIMBERLAKE COMMUNITY ASSOCIATION REPLACEMENT RESERVE REPORT FY 2014 TIMBERLAKE COMMUNITY ASSOCIATION REPLACEMENT RESERVE REPORT FY 2014 Community Management by: Mr. Phil Massa, AMS, PCAM 933 Windsor Oaks

More information

FIR RIDGE II CONDOMINIUM

FIR RIDGE II CONDOMINIUM FIR RIDGE II CONDOMINIUM BELLINGHAM, WASHINGTON UPDATE WITHOUT SITE VISIT FEBRUARY 2014 FOR USE WITH THE FEBRUARY 2012 RESERVE STUDY PREPARED BY: DENISE DANA, RESERVE SPECIALIST M. ARCH, REGISTERED ARCHITECT

More information

Bridgewood Manor HOA

Bridgewood Manor HOA Bridgewood Manor HOA Level 1 Reserve Study Report Period 01/01/2015 12/31/2015 Client Reference Number 18076 Property Type Condominium Number of Units 40 Fiscal Year End 12/31 Date of Property Inspection

More information

REPLACEMENT RESERVE REPORT FY 2015 WOODBRIDGE CONDOMINIUM CHESAPEAKE BAY MANAGEMENT. Community Management by: Ms. Kimberly Marston

REPLACEMENT RESERVE REPORT FY 2015 WOODBRIDGE CONDOMINIUM CHESAPEAKE BAY MANAGEMENT. Community Management by: Ms. Kimberly Marston REPLACEMENT RESERVE REPORT FY 2015 WOODBRIDGE CONDOMINIUM WOODBRIDGE CONDOMINIUM REPLACEMENT RESERVE REPORT FY 2015 Community Management by: CHESAPEAKE BAY MANAGEMENT Ms. Kimberly Marston 100 Volvo Parkway,

More information

Full Reserve Study. Twenty Four Neighborhood TOA. Carbondale, CO

Full Reserve Study. Twenty Four Neighborhood TOA. Carbondale, CO Full Reserve Study Twenty Four Neighborhood TOA Carbondale, CO Report #: 21306-0 For Period Beginning: January 1, 2011 Ending: December 31, 2011 Revision Date (2): February, 9, 2011 Date Prepared: September

More information

REPLACEMENT RESERVE REPORT FY 2018 SANCTUARY AT FALSE CAPE. Prepared for: Ms. Rebecca Beamon

REPLACEMENT RESERVE REPORT FY 2018 SANCTUARY AT FALSE CAPE. Prepared for: Ms. Rebecca Beamon SANCTUARY AT FALSE CAPE REPLACEMENT RESERVE REPORT FY 2018 SANCTUARY AT FALSE CAPE REPLACEMENT RESERVE REPORT FY 2018 Prepared for: SANCTUARY AT FALSE CAPE Ms. Rebecca Beamon 3700 Sandpiper Road Virginia

More information

What are Capital Reserves?

What are Capital Reserves? Capital Reserves What are Capital Reserves? A separate account set up by the Association to fund large, non-annual repairs Stormwater pond repair, dredging and drainage improvements Fence repair, retaining

More information

CAPITAL RESERVE STUDY

CAPITAL RESERVE STUDY CAPITAL RESERVE STUDY FOR THE HIALEAH CONDOMINIUM WILDWOOD CREST, NEW JERSEY Project Number: 12-1066 W:\2012\12-1066\CORR\12-1066v1.doc Date: March 29, 2013 Table of Contents Section Page Executive Summary...

More information

NEW ALBANY COUNTRY CLUB MASTER ASSOCIATION, INC NEW ALBANY, OHIO

NEW ALBANY COUNTRY CLUB MASTER ASSOCIATION, INC NEW ALBANY, OHIO RESERVE FUND STUDY NEW ALBANY COUNTRY CLUB MASTER ASSOCIATION, INC NEW ALBANY, OHIO Criterium Liszkay Engineers 110 N. High St. Gahanna, OH 43230 614-418-7200 www.clengineers.com NOVEMBER 2013 1.0 INTRODUCTION...1

More information

Brookwood Homeowners Association, Inc.

Brookwood Homeowners Association, Inc. RESERVE STUDY Full Study Brookwood Homeowners Association, Inc. Published - February 05, 2013 Browning Reserve Group / Emmett, ID 83617 Office (208) 365-0977 Tony@BrowningRG.com / www.browningrg.com Browning

More information

Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION CROZET, VA. Prepared by:

Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION CROZET, VA. Prepared by: RESERVE FUND STUDY THE VILLAGE AT HIGHLANDS CROZET, VA 22932 Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION CROZET, VA C/O ASSOCIA COMMUNITY GROUP 1828 PAVILION CIRCLE CHARLOTTESVILLE, VA 22911

More information

DRAFT WILLOUGHBY PARK GREENVILLE, NC. Prepared for: WILLOUGHBY PARK CONDOMINIUM ASSOCIATION & HOA MANAGEMENT COMPANY, LLC.

DRAFT WILLOUGHBY PARK GREENVILLE, NC. Prepared for: WILLOUGHBY PARK CONDOMINIUM ASSOCIATION & HOA MANAGEMENT COMPANY, LLC. DRAFT FULL RESERVE STUDY WILLOUGHBY PARK GREENVILLE, NC Prepared for: WILLOUGHBY PARK CONDOMINIUM ASSOCIATION GREENVILLE, NC & HOA MANAGEMENT COMPANY, LLC Prepared by: CRITERIUM GILES ENGINEERS, INC. 1150

More information

PROFESSIONAL RESERVE STUDY

PROFESSIONAL RESERVE STUDY PROFESSIONAL RESERVE STUDY Cascara at Redmond Ridge NE 112 th Place & Eastridge Drive NE, Redmond, WA 98052 For: Cascara at Redmond Ridge Homeowners Association c/o Luiza Limona Morris Management 325-118

More information

Parkwood Village Homeowner s Association (PVHA) Approved 2019 Budget

Parkwood Village Homeowner s Association (PVHA) Approved 2019 Budget Parkwood Village Homeowner s Association (PVHA) Approved 2019 Budget Introduction The 2019 Budget was prepared by Coal Morton and reviewed by the Board of Directors. The Budget covers maintenance, services

More information

OCEAN NEIGHBORS HOMEOWNERS ASSOCIATION REPLACEMENT RESERVE REPORT FY 2017 POSTON & COMPANY. Community Management by: Melissa Blocker, Property Manager

OCEAN NEIGHBORS HOMEOWNERS ASSOCIATION REPLACEMENT RESERVE REPORT FY 2017 POSTON & COMPANY. Community Management by: Melissa Blocker, Property Manager REPLACEMENT RESERVE REPORT FY 2017 OCEAN NEIGHBORS HOMEOWNERS ASSOCIATION OCEAN NEIGHBORS HOMEOWNERS ASSOCIATION REPLACEMENT RESERVE REPORT FY 2017 Community Management by: POSTON & COMPANY Melissa Blocker,

More information

Estates at River Ranch HOA

Estates at River Ranch HOA Full Reserve Study Estates at River Ranch HOA Tucson, Arizona Report #: 29634-0 For Period Beginning: January 1, 2017 Expires: December 31, 2017 Date Prepared: June 15, 2016 Hello, and welcome to your

More information

Full Reserve Study. Sample Condominium. Anywhere, USA. Report #: For Period Beginning: January 1, 2016 Expires: December 31, 2016

Full Reserve Study. Sample Condominium. Anywhere, USA. Report #: For Period Beginning: January 1, 2016 Expires: December 31, 2016 Full Reserve Study Sample Condominium Anywhere, USA Report #: 25161-0 For Period Beginning: January 1, 2016 Expires: December 31, 2016 Date Prepared: June 19, 2015 Hello, and welcome to your Reserve Study!

More information

RESERVE STUDY. Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION. Prepared by: 22 MONUMENT SQUARE PORTLAND, MAINE (800) , EXT 111

RESERVE STUDY. Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION. Prepared by: 22 MONUMENT SQUARE PORTLAND, MAINE (800) , EXT 111 RESERVE STUDY THE VILLAGE AT HIGHLANDS CHARLOTTESVILLE, VA Prepared for: VILLAGE AT HIGHLANDS OWNERS ASSOCIATION C/O ASSOCIA COMMUNITY GROUP 1413 SACHEM PLACE, SUITE 2 CHARLOTTESVILLE, VA 22901 Prepared

More information

RESERVE STUDY Component Analysis and Reserve Fund Plan Annual Review Study 2016/17 For Middlefield Meadows HOA Mountain View, CA Prepared By RESERVE ANALYSIS CONSULTING, LLC 1750 Bridgeway, Suite B106

More information

Reserve Analysis Report

Reserve Analysis Report Reserve Analysis Report Park Avenue 244 Quari St Denver, CO Level II Study with Site Inspection Fiscal Year End Date: 12/31/2016 Phone: 858-764-1895 Fax: 800-436-3816 brian@mccafferyreserveconsulting.com

More information

Central Pointe HOA. Level I Reserve Study. Report Period 1/01/08 12/31/08

Central Pointe HOA. Level I Reserve Study. Report Period 1/01/08 12/31/08 Central Pointe HOA Level I Reserve Study Report Period 1/01/08 12/31/08 Client Reference Number.... 10870 Property Type...... Mid-Rise Number of Units............ 83 Fiscal Year End....... December 31

More information

The Ranches HOA. Level II Reserve Study. Report Period 1/01/08 12/31/08

The Ranches HOA. Level II Reserve Study. Report Period 1/01/08 12/31/08 The Ranches HOA Level II Reserve Study Report Period 1/01/08 12/31/08 Client Reference Number.... 10329 Property Type..... Single Family Homes Number of Units.......... 1,750 Fiscal Year End......... December

More information

Reserve Study Transmittal Letter

Reserve Study Transmittal Letter Reserve Study Transmittal Letter Date: October 09, 2016 To: Joleen Cline, Cline & Associates From: Browning Reserve Group (BRG) Re: Whitehawk Townhomes Association; Update w/ Site Visit Review Attached,

More information

N SITE RESERVE STUDY Presented by:

N SITE RESERVE STUDY Presented by: N SITE RESERVE STUDY Presented by: PO Box 1714 Stow 44224 Akron 330.650.4318 Cleveland 330.656.3441 Fax 330.655.8957 www.karecondo.com STUDY FULL RESERVE IN THIS SECTION: NARRATIVE REPORT CONCLUSION DEFINITIONS

More information

TELFORD HILLS CONDOMINIUM ASSOCIATION, INC. FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION

TELFORD HILLS CONDOMINIUM ASSOCIATION, INC. FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION TABLE OF CONTENTS PAGE INDEPENDENT AUDITOR S REPORT... 1-2 FINANCIAL STATEMENTS Balance Sheet... 3 Statement of Revenues, Expenses and Changes in Fund

More information

CAPITAL RESERVE STUDY. Meadow Wood Commons. City, State

CAPITAL RESERVE STUDY. Meadow Wood Commons. City, State CAPITAL RESERVE STUDY FOR THE Meadow Wood Commons City, State Management Company: Any Management Company Contact Name: Mr. Bob Smith Date: July 28, 2014 Table of Contents Section Name Section # Executive

More information

RESERVE STUDY LEVEL I - Full Reserve Study. ABC Condominium Association, Inc.

RESERVE STUDY LEVEL I - Full Reserve Study. ABC Condominium Association, Inc. Insurance Appraisals Reserve Studies Wind Mitigation RESERVE STUDY LEVEL I - Full Reserve Study Prepared for: ABC Condominium Association, Inc. For the period of January 1, 214 - December 31, 214 71 Enterprise

More information

FULL RESERVE STUDY Stillwood Cluster Lot Owners' Association, Inc. Stow, Ohio August 15, 2017

FULL RESERVE STUDY Stillwood Cluster Lot Owners' Association, Inc. Stow, Ohio August 15, 2017 FULL RESERVE STUDY Stillwood Cluster Lot Owners' Association, Inc. Stow, Ohio August 15, 2017 This Report contains intellectual property developed by Reserve Advisors, Inc. and cannot be reproduced or

More information

CONTENTS 1.0 INTRODUCTION EXECUTIVE SUMMARY... 2

CONTENTS 1.0 INTRODUCTION EXECUTIVE SUMMARY... 2 CONTENTS 1.0 INTRODUCTION... 1 2.0 EXECUTIVE SUMMARY... 2 3.0 PURPOSE & SCOPE... 3 3.1 PURPOSE... 3 3.2 SCOPE... 3 3.3 SOURCES OF INFORMATION... 4 4.0 DESCRIPTION... 6 5.0 OBSERVATIONS... 6 6.0 RESERVE

More information

Pemberley at Robinsons Grove

Pemberley at Robinsons Grove Pemberley at Robinsons Grove Level I Reserve Study Report Period 1/01/06 12/31/06 Client Reference Number.... 10429 Property Type...... Apartment Style Number of Units............. 160 Fiscal Year End.......

More information

THE VINEYARDS AT DUBLIN GREENE OWNERS ASSOCIATION

THE VINEYARDS AT DUBLIN GREENE OWNERS ASSOCIATION THE VINEYARDS AT DUBLIN GREENE OWNERS ASSOCIATION Full Reserve Study With On-site Visual Inspection October 3, 2018 Reserve Study for Fiscal Year: 01/01/2019 through 12/31/2019 2059 Camden Ave. Suite 151

More information

Fieldstone RESERVE STUDY UPDATE. John D. Beatty & Company OWNERS ASSOCIATION. for. Date Prepared: 12/4/2018 for fiscal year 2019.

Fieldstone RESERVE STUDY UPDATE. John D. Beatty & Company OWNERS ASSOCIATION. for. Date Prepared: 12/4/2018 for fiscal year 2019. RESERVE STUDY UPDATE for Fieldstone OWNERS ASSOCIATION Date Prepared: 12/4/2018 for fiscal year 2019 Prepared By: John D. Beatty & Company 8425 Brentwood Blvd., Suite A7 Brentwood, CA 94513 (925) 831-1803

More information

Indian Peaks Townhomes 95 th Street Lafayette, CO 80026

Indian Peaks Townhomes 95 th Street Lafayette, CO 80026 Indian Peaks Townhomes 95 th Street Lafayette, CO 80026 Level 2, Premium Reserve Analysis Report Period 01/01/16 12/31/16 Client Reference Number - 4080 Property Type Townhome Development Number of Units

More information

Comprehensive Reserve Fund Study and Building Condition Assessment for Wellington Standard Condominium Corporation No. 149

Comprehensive Reserve Fund Study and Building Condition Assessment for Wellington Standard Condominium Corporation No. 149 Comprehensive Reserve Fund Study and Building Condition Assessment for Wellington Standard Condominium Corporation No. 149 820 Gartshore Street Fergus, Ontario Report Prepared for the Board of Directors

More information

Scope Criterium Engineers was hired to update a reserve study for the Reston Association. The specific tasks included: Review the previous study perfo

Scope Criterium Engineers was hired to update a reserve study for the Reston Association. The specific tasks included: Review the previous study perfo Scope Criterium Engineers was hired to update a reserve study for the Reston Association. The specific tasks included: Review the previous study performed by others Consult with Reston Association management

More information

Update With Site-Visit Reserve Study

Update With Site-Visit Reserve Study Washington Office Corporate Office 505 South 336 th St., Ste 620 Calabasas, CA Federal Way, WA 98003 Regional Offices TEL 253/661-5437 Phoenix, AZ FAX 253/661-5430 San Francisco, CA arwa@reservestudy.com

More information

Sea le, WA Account SAMPLE CONDO Version SAMPLE January 01, Bellevue Way NE, #483 Bellevue, WA

Sea le, WA Account SAMPLE CONDO Version SAMPLE January 01, Bellevue Way NE, #483 Bellevue, WA Sea le, WA Account SAMPLE CONDO Version SAMPLE January 01, 2017 227 Bellevue Way NE, #483 Bellevue, WA 98004 866 574 5115 www.rdanorthwest.com Prepared By Quality Check By Page 1 Disclosures Reserve Study

More information

CONTENTS. Greens at Lochmere Cary, NC

CONTENTS. Greens at Lochmere Cary, NC CONTENTS 1.0 INTRODUCTION... 1 2.0 EXECUTIVE SUMMARY... 2 3.0 PURPOSE & SCOPE... 3 3.1 PURPOSE... 3 3.2 SCOPE... 3 3.3 SOURCES OF INFORMATION... 4 4.0 DESCRIPTION... 6 5.0 OBSERVATIONS... 6 6.0 RESERVE

More information

CONTENTS 1.0 INTRODUCTION... 1

CONTENTS 1.0 INTRODUCTION... 1 CONTENTS 1.0 INTRODUCTION... 1 2.0 EXECUTIVE SUMMARY... 2 3.0 PURPOSE & SCOPE... 3 3.1 PURPOSE... 3 3.2 SCOPE... 3 3.3 SOURCES OF INFORMATION... 4 4.0 DESCRIPTION... 5 5.0 OBSERVATIONS... 6 6.0 RESERVE

More information

Reserve Study: Alpenrose Condominium Association

Reserve Study: Alpenrose Condominium Association Reserve Study: Alpenrose Condominium Association The Alpenrose Condominiums 74 Erste Strausse Snoqualmie Pass, Washington 98068 Originally Prepared October 5 th 2009 Updated with inspection November 15

More information

REPLACEMENT RESERVE REPORT FY 2011 VILLAGE GREEN HOA. Ravenel Associates, Inc. Community Management by: Chad Hammond, Property Manager

REPLACEMENT RESERVE REPORT FY 2011 VILLAGE GREEN HOA. Ravenel Associates, Inc. Community Management by: Chad Hammond, Property Manager REPLACEMENT RESERVE REPORT FY 2011 VILLAGE GREEN HOA VILLAGE GREEN HOA REPLACEMENT RESERVE REPORT FY 2011 Community Management by: Ravenel Associates, Inc. Chad Hammond, Property Manager 3690 Bohicket

More information

CONTENTS. Twisted Creek Townhomes Holly Springs, NC

CONTENTS. Twisted Creek Townhomes Holly Springs, NC CONTENTS 1.0 INTRODUCTION... 1 2.0 EXECUTIVE SUMMARY... 2 3.0 PURPOSE & SCOPE... 3 3.1 PURPOSE... 3 3.2 SCOPE... 3 3.3 SOURCES OF INFORMATION... 4 4.0 DESCRIPTION... 5 5.0 OBSERVATIONS... 6 6.0 RESERVE

More information

Reserve Analysis Report

Reserve Analysis Report Reserve Analysis Report Sample Condominium Association Laguna Hills, California Version 1 March 31, 2004 23201 Mill Creek Drive, Suite 100 Laguna Hills, California 92653 Phone (949) 474-9800 Facsimile

More information

RESERVE STUDY SPECIALISTS

RESERVE STUDY SPECIALISTS RESERVE STUDY SPECIALISTS P.O. BOX 9178, CALABASAS, CA 91372 TEL: 818-992-1312 FAX: 818-992-1338 VILLAGE GREEN EAST HOMEOWNERS ASSOCIATION FULL RESERVE STUDY September 06, 2017 for Fiscal Year 2018 RESERVE

More information

PROFESSIONAL RESERVE STUDY

PROFESSIONAL RESERVE STUDY PROFESSIONAL RESERVE STUDY Cambridge Court 9512-1 st Avenue Northeast, Seattle, WA 98115 For: Cambridge Court Homeowners Association c/o Tim Kammer, Property Manager Condo Managements, Inc. 1661 Harbor

More information

Reserve Study Transmittal Letter

Reserve Study Transmittal Letter Reserve Study Transmittal Letter Date: August 15, 215 To: Lorrie Olson, Caughlin Creek HOA From: Browning Reserve Group (BRG) Re: Caughlin Creek HOA; Full Study Attached, please find the reserve study

More information

Regarding: Level I Capital Replacement Reserve Study. We are pleased to submit this Level I Reserve Study for Summit Park Condominiums.

Regarding: Level I Capital Replacement Reserve Study. We are pleased to submit this Level I Reserve Study for Summit Park Condominiums. 1825 W. Ray Road, #1135, Chandler, AZ 85244 support@azreservestudy.com Tel: (480) 620-4757 Fax: (888) 842-9319 April 4, 2013 Summit Park Condominiums HOA Regarding: 2012 - Level I Capital Replacement Reserve

More information

Urban Heights Condominium

Urban Heights Condominium Condominium Capital 2011 2010, AssociationAnalysis, LLC Condominium Prepared For: Table of Contents Condominium Association, Inc. 1642 Maxwell Road Atlanta, GA 30012 October 19, 2010 INTRODUCTION INTRODUCTION

More information

Do-It-Yourself Reserve Study

Do-It-Yourself Reserve Study Washington Office Corporate Office 505 South 336 th St., Ste 620 Calabasas, CA Federal Way, WA 98003 Regional Offices TEL 253/661-5437 Phoenix, AZ FAX 253/661-5430 San Francisco, CA arwa@reservestudy.com

More information

Commercial Assessments

Commercial Assessments Commercial Assessments (888) 225-3755 www.commercialassessments.com Funding Reserve Analysis for Timberlake Crossing Condominium Unit Owners Association Hardy, VA January 15, 2013 Page 1 of 24 Pages Funding

More information

SAMPLE Reserve Study FULL. Serving the Nation.

SAMPLE Reserve Study FULL. Serving the Nation. SAMPLE Reserve Study FULL Serving the Nation www.reservestudy.com Welcome to your Reserve Study! A Reserve Study is a valuable tool to help you budget responsibly for your property. This report contains

More information

MILL CREEK CONDOMINIUMS RESERVE STUDY

MILL CREEK CONDOMINIUMS RESERVE STUDY MILL CREEK CONDOMINIUMS RESERVE STUDY Fiscal Year 2016 Prepared by: Eric Harker, Assoc. AIA Alliance Project Engineers and Construction Consultants November 6, 2015 Project Number: OR14-017 MILL CREEK

More information

2016 Reserve Study. Riverwood Plantation Homeowners Association, Inc Riverwood Drive Port Orange, Florida

2016 Reserve Study. Riverwood Plantation Homeowners Association, Inc Riverwood Drive Port Orange, Florida 2016 Reserve Study Riverwood Plantation Homeowners Association, Inc. 6200 Riverwood Drive Port Orange, Florida 32127 Report No: 4142 January 1, 2016 - December 31, 2016 Table of Contents Introduction 1-1

More information

Cottonwoods at Vine. Reserve Study. October 2012

Cottonwoods at Vine. Reserve Study. October 2012 Reserve Study October 2012 Tab Table of Contents Reserve Study Analysis Executive Summary... Remaining Useful Life Analysis... Reserve Study Schedule... Annual Expenditures... Funding Plan Summary... Percentage

More information

21289 E. Lords Way Queen Creek, AZ Tel: (480) Fax: (888) October 27, Sample Association

21289 E. Lords Way Queen Creek, AZ Tel: (480) Fax: (888) October 27, Sample Association 21289 E. Lords Way Queen Creek, AZ 85142 support@azreservestudy.com Tel: (480) 840-7130 Fax: (888) 842-9319 October 27, 2012 Sample Association Regarding: 2013 - Level I Capital Replacement Reserve Study

More information

F U L L R E S E RV E S T U DY R E P O RT

F U L L R E S E RV E S T U DY R E P O RT Office: (888) 927-7865 Fax: (813) 200-8448 Contact@customreserves.com 5470 E Busch Blvd., Unit 171 Tampa, FL 33617 Hawks Point Community Development District F U L L R E S E RV E S T U DY R E P O RT For

More information

505 South 336 th St., Ste 620 Calabasas, CA Federal Way, WA Regional Offices. Full Reserve Study. Steven's Cove HOA.

505 South 336 th St., Ste 620 Calabasas, CA Federal Way, WA Regional Offices. Full Reserve Study. Steven's Cove HOA. Washington Office Corporate Office 505 South 336 th St., Ste 620 Calabasas, CA Federal Way, WA 98003 Regional Offices TEL 253/661-5437 Phoenix, AZ FAX 253/661-5430 San Francisco, CA arwa@reservestudy.com

More information

Update With Site-Visit Reserve Study

Update With Site-Visit Reserve Study Washington Office Corporate Office 505 South 336 th St., Ste 620 Calabasas, CA Federal Way, WA 98003 Regional Offices TEL 253/661-5437 Phoenix, AZ FAX 253/661-5430 San Francisco, CA arwa@reservestudy.com

More information

RESERVE STUDY UPDATE SUMMARY

RESERVE STUDY UPDATE SUMMARY RESERVE STUDY UPDATE SUMMARY for Fieldstone OWNERS ASSOCIATION Date Prepared: 12/4/2018 for fiscal year 2019 Prepared By: John D. Beatty & Company 8425 Brentwood Blvd., Suite A7 Brentwood, CA 94513 (925)

More information

REPLACEMENT RESERVE REPORT FY 2016

REPLACEMENT RESERVE REPORT FY 2016 REPLACEMENT RESERVE REPORT FY 2016 EVANS MILL POND REPLACEMENT RESERVE REPORT FY 2016 EVANS MILL POND Community Management by: EVANS MILL POND, HOA Evans Mill Road McLean, Virginia 22101 Consultant: 929

More information

Reserve Analysis Report

Reserve Analysis Report Reserve Analysis Report Mountain Oaks Townhomes Flagstaff, Arizona Version 002 February 4, 2019 Advanced Reserve Solutions, Inc. 2761 E. Bridgeport Parkway - Gilbert, Arizona 85295 kthompson@arsinc.com

More information

MAINTENANCE GUIDE STRATHMORE COURT HOMEOWNERS ASSOCIATION, INC MAINTENANCE GUIDELINES

MAINTENANCE GUIDE STRATHMORE COURT HOMEOWNERS ASSOCIATION, INC MAINTENANCE GUIDELINES MAINTENANCE GUIDE STRATHMORE COURT HOMEOWNERS ASSOCIATION, INC MAINTENANCE GUIDELINES The following is a summary of the Association s responsibilities with regard to maintenance of the common area. 1.

More information

THE GALLERY at RIVERS EDGE OWNERS ASSOCIATION, INC Operating Budget 62 Unit Basis

THE GALLERY at RIVERS EDGE OWNERS ASSOCIATION, INC Operating Budget 62 Unit Basis THE GALLERY at RIVERS EDGE OWNERS ASSOCIATION, INC. 2018 Operating Budget 62 Unit Basis REVENUES Documentary Notes & Financial Management Plan 1. Regular Assessments (Acct # 36-05-4000) $111,476. The Regular

More information

- RS. D e sig n atio n

- RS. D e sig n atio n ALEXANDER LIU CAI - RS Reserve D e sig n atio n Specialist Sample Table Of HOA Contents Project Table of Contents Page Preface i Executive Summary 1 Membership Disclosure Summary 2 Disclosure Statement

More information

Full Reserve Study. Nelson Farms HOA. Fort Collins, CO. Report #: For Period Beginning: May 1, 2016 Expires: April 30, 2017

Full Reserve Study. Nelson Farms HOA. Fort Collins, CO. Report #: For Period Beginning: May 1, 2016 Expires: April 30, 2017 Full Reserve Study Nelson Farms HOA Fort Collins, CO Report #: 19185-0 For Period Beginning: May 1, 2016 Expires: April 30, 2017 Date Revised: January 13, 2016 Hello, and welcome to your Reserve Study!

More information

Calusa Point Association, Inc. Miami, Florida File #

Calusa Point Association, Inc. Miami, Florida File # A FULL RESERVE STUDY FOR Miami, Florida File # 22920-06289 FOR PERIOD: January 1, 2014 December 31, 2014 PREPARED BY GAB ROBINS, A DIVISION OF CUNNINGHAM LINDSEY 3300 W. LAKE MARY BLVD. SUITE 350 LAKE

More information

VÜxx~Ëá Xwzx tà fàéçç cé Çà géãç{éåxá

VÜxx~Ëá Xwzx tà fàéçç cé Çà géãç{éåxá VÜxx~Ëá Xwzx tà fàéçç cé Çà géãç{éåxá CAPITAL REPLACEMENT RESERVE STUDY December 5, 2011 Copyright 2011 Design Management Associates, Inc. Study Date: December 5, 2011 Prepared for: Creek s Edge at Stony

More information

RESERVE FUND STUDY. Hill & Associates Ltd. Member APEGNB July 2014

RESERVE FUND STUDY. Hill & Associates Ltd. Member APEGNB July 2014 2014 RESERVE FUND STUDY Hill & Associates Ltd. Member APEGNB July 2014 Reserve Fund Study Prepared for Bobak Place Townhome Condominiums Prepared by Hill & Associates Ltd. Consulting Professional Engineers

More information

Hyde Park Place Owners' Association, Inc.

Hyde Park Place Owners' Association, Inc. RESERVE STUDY Full Study Hyde Park Place Owners' Association, Inc. Published - February 10, 2016 Browning Reserve Group / Emmett, ID 83617 Office (208) 365-0977 Tony@BrowningRG.com / www.browningrg.com

More information

REPLACEMENT RESERVE REPORT FY 2017 CAMDEN TOWNES ROCKTOWN REALTY. Community Management by: Bernard Hamann

REPLACEMENT RESERVE REPORT FY 2017 CAMDEN TOWNES ROCKTOWN REALTY. Community Management by: Bernard Hamann REPLACEMENT RESERVE REPORT FY 2017 CAMDEN TOWNES REPLACEMENT RESERVE REPORT FY 2017 CAMDEN TOWNES Community Management by: ROCKTOWN REALTY Bernard Hamann 218 Market Street Harrisonburg, VA 22801 40-70-7080

More information

RESERVESTUDYUPDATE. The Villas at Blackberry Run Dallas, GA. Prepared for:

RESERVESTUDYUPDATE. The Villas at Blackberry Run Dallas, GA. Prepared for: RESERVESTUDYUPDATE Dallas, GA Prepared for: THE VILLAS AT BLACKBERRY RUN HOME OWNERS ASSOCIATION, INC. Carl Swanson-President Prepared by: CRITERIUM-CARUSO ENGINEERS 1065 POWERS PLACE, SUITE B ALPHARETTA,

More information

Update "With-Site-Visit" Reserve Study

Update With-Site-Visit Reserve Study Update "With-Site-Visit" Reserve Study Sample Townhouse HOA Ventura, CA Report #: For Period Beginning: Expires: Date Prepared: 99999999-0 January 1, 2019 December 31, 2019 June 27, 2018 T W Hello, and

More information

BUDGET APPROVED. GENERAL EXPENSES (158 Units)

BUDGET APPROVED. GENERAL EXPENSES (158 Units) TANGLEWOOD HILLS CONDOMINIUM Association name: Tanglewood Hills Condom Association number: 1457 General - Total # of Units 158 Fiscal year end: 12/31 Budget year: 2017 Budget type: M BUDGET APPROVED ACCT.

More information

TANGLEWOOD HILLS CONDOMINIUM

TANGLEWOOD HILLS CONDOMINIUM TANGLEWOOD HILLS CONDOMINIUM Association name: Tanglewood Hills Condom Association number: 1547 General - Total # of Units 158 Fiscal year end: 12/31 Budget year: 2018 Budget type: M BUDGET APPROVED ACCT.

More information

R E S E R V E S T U D Y

R E S E R V E S T U D Y SAGUARO CANYON SUBDIVISION HOMEOWNERS ASSOCIATION R E S E R V E S T U D Y Full Study Published - May 27, 2010 B R O W N I N G R E S E R V E G R O U P ~ Emmett, ID 83617 ~ Office (208) 365-0977 Fax (208)

More information