LCC Methodology. Håkan Sundquist Structural Design and Bridges KTH. ETSI Methodology 1

Size: px
Start display at page:

Download "LCC Methodology. Håkan Sundquist Structural Design and Bridges KTH. ETSI Methodology 1"

Transcription

1 LCC Methodology Håkan Sundquist Structural Design and Bridges KTH 1

2 There are many requirements on a bridge 2

3 The classic task 3

4 The classic bridge design task 4

5 LCC optimization 5 LCC/Construction cost 100 %

6 Include maintenance and operation costs 6

7 Agency or owner costs 7

8 The bridge must also contribute economically to the society 8

9 Include society costs during maintenance and repair Include eventual accident costs 9

10 User benefit and cost 10

11 Costs for the society due to accidents and total failure Accidents are usually covered by the society and not by agencies like SRA or FinnRA 11

12 LCC Life Cycle Costing LCC is a technique which enables comparative cost assessments to be made over a specified period of time, taking into account all relevant economic factors initial capital costs future operational and maintenance costs owner costs user costs society costs future disposal cost Used methodology is usually the present value of the total cost of this asset over its lifetime 12

13 LCC scheme 13

14 Definitions LCC owner or agency LCC = LCCA + LSC + LCCC LCCA = is the cost for acquisition of the project (design, construction ) by the net present value calculated to a specified time usually the opening of the bridge LSC = (Life Support Cost) is the cost for future operation, maintenance and repair of the bridge, by the net present value calculated to a specified time usually the opening of the bridge. LCCC = (Life Cycle Cost Consequence), is the future costs for eventual negative consequences, by the net present value calculated to a specified time, usually the opening of the bridge. 14

15 LSC, the Life Support Cost LSC = CI + CN CI = is the investment in the necessary equipment and other resources for the future operation and maintenance CN is the future cost for operation, maintenance and repair, by the net present value calculated to a specified time, usually the opening of the bridge The investment part of the maintenance, CI, could be divided in parts 15

16 CI = Investment for operation and maintenance CI = CI r + CI v + CI d + CI t CI r = spare parts and material CI v = instrument, tools, vehicles that is needed for inspection and maintenance CI d = documentation i.e. drawings and instruction manuals needed for inspection and maintenance CI t = education of personnel for operation and maintenance 16

17 The costs are recalculated to one point in time usually the day of opening the bridge LCC owner = T t= 0 1 C + t r ( ) t C t the sum of all costs incurred at time t, p the real interest rate or a rate taking into account changes in the benefit of the structure and t is the time period studied, typically for a structure for the infrastructure the expected life span. 17

18 Interest rate p = pl p 1 + p i i p L interest rate for loans with long duration p i inflation Interest rate p p = p L pi 1 + p i p c p c increase of usefulness of the bridge i.e. increase of traffic 18

19 Net present cost for a cost of value=1,0 year 0 100,00 Cost 10,00 1,00 2,5% 4,0% 6,0% 8,0% 0,10 0, Interval between MR&R actions 19

20 User cost delay T L L LCC = ADT N r w + r w ( (1 ) ) user,delay t t L L L D t t= 0 vr vn (1 + r) 1 L v r v n ADT t N t r L w L w L T length of affected roadway the traffic speed during bridge work activity the normal traffic speed the average daily traffic, i.e. cars per day at time t the number of days of road work at time t the amount of commercial traffic is the hourly time value for commercial traffic the hourly time value for drivers studied time interval T 20

21 User costs, operation T L L LCC = ADT N r o + o + r o ( ( ) (1 ) ) user,operating t t L L G L D t t= 0 vr vn (1 + r) New notations: o L operating cost for the commercial traffic vehicles o G operating cost for transported goods o D operating cost for cars T time interval 1 21

22 Societal costs, accidents and T failure ( ) LCC = A A ADT N C society, accident r n t t acc t t= 0 (1 + r) New notations: A n the normal accident rate per vehicle-kilometres A r the accident rate during roadwork the cost for each accident for the society C acc n society, failure = j= 1 H, j j j LCC K R ( 1+ r) R j probability for a specified failure coupled to K H,j. K H,j cost for failure (One value for ultimate limit state and one for serviceability limit state) For normal bridges the probability of failure is so small that it could be omitted in the analysis!

23 Valuation Degradation models Knowledge on interest rents (100 year!!) Knowledge about the future of the traffic system! (will the traffic increase or decrease??) Knowledge on costs for operation, maintenance, inspection and repair 23

24 Soft values must also be included 24

25 Environmental issues must also be included! 25

26 Parameters needed for the LCC analysis Methodologies for dividing the bridge into different parts and giving measures of the components Costs for construction and repair different parts of the bridge Yearly operating costs Actions in time for MR&R actions Cost for disposal of the bridge User and societal costs 26

27 Foundation Foundation slab, plinth, pile cap Excavation, soil Excavation, rock Pile Erosion protection Slope and embankment Embankment, embankment end, backfill Soil reinforcement and slope protection Abutments and piers All concrete structures belonging to the substructure excl. foundation Main load-bearing structure Slab / deck Beam Truss Arch, Vault Cable system Pipe, Culvert Secondary load-bearing system Secondary load-bearing beam, cross beam Secondary load-bearing truss, Wind bracing Equipment Bearing and Hinge Edge beam Insulation, Water proofing Surfacing Parapet, Railing Expansion joint Drainage system Suggestion for bridge parts 27

28 Bridge parts and measures 28

29 Cross-section definitions Total bridge width Clear bridge width V K V S GC 29

30 Foundation 30

31 Materials for LCC Material Measure Quality Description Concrete m 3 C25 1 Cylinder strength in MPa Reinforcement steel ton Yield strength in MPa Steel for pre-stressing, tendons, ton 1700 Yield strength in MPa cables Steel ton Yield strength in MPa Sawn Timber m 3 Glue laminated timber m 3 Impregnated timber m 3 Backfill soil m 3 Pile m Type 4 Directly coupled to the structural element OBS, LCA requires added material definitions! 31

32 Costs Cost parameters should be given by the agencies hopefully in data bases updated every year!? Costs for construction Cost for MR&R actions Parameters for calculating the user costs Societal costs 32

33 Definition of actions Management Operation Inspections Repair Upgrading Final demolition and disposal 33

34 Operation Management is the owners own work for keeping the bridge inventory, the planning and other actions to manage the bridge stock. Usually this work can be assigned as percentage of the actual value to re-build the bridge stock. Operation is the yearly work to superficially and regularly inspect, clean, repair small damages of the bridges. The Swedish term is Drift 34

35 Examples of operation (yearly) actions Examples of operation maintenance actions. In the Swedish system this is called Egenskaper or properties Action Frequency Aim Remark Regular inspection Often Detect acute damages Cleaning of the bridge Rodding of dewatering system Cleaning of expansion joints Removal of plants and bushes, Once a year Once a year Once a year Once a year Removal of de-icing salt 35

36 Time between different MR&R actions Needed parameters: Life span Yearly operation actions Time interval between inspections Time between maintenance and repair 36

37 Methods for judging time between MR&R actions 1. Mechanistic or chemical models 2. Evaluation results from large field observations, 3. The up to day most applied method is to use experience from specialists, usually people deeply involved with inspection of bridges 37

38 LCC With everything in hand it is just to calculate the LCC for a bridge or maybe all bridges in a county or for a road network!! 38

39 GOOD LUCK! Trying and commenting our programs! 39

BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012

BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012 Page 1 BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO. 87786 BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012 ROADWAY 1 201 CLEARING AND GRUBBING 1 LUMP $4,500.00 $4,500.00 $10,016.00

More information

ENGINEER'S ESTIMATE OF PROBABLE COST CCTA I 680 NORTH EXPRESS LANE PROJECT (SOUTHBOUND ONLY) EA 04 4H % PS&E Submittal

ENGINEER'S ESTIMATE OF PROBABLE COST CCTA I 680 NORTH EXPRESS LANE PROJECT (SOUTHBOUND ONLY) EA 04 4H % PS&E Submittal Page: 1 of 8 (F) Description 1 050000A CONTRACTOR STAKING LS 1 $ $ 2 070030 LEAD COMPLIANCE PLAN LS 1 $ $ 3 080000A POTHOLING LS 1 $ 50,000.00 $ 50,000.00 4 080050 PROGRESS SCHEDULE (CRITICAL PATH METHOD)

More information

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES GUIDANCE NOTES Rev 3 August 2017 INDEX Section Page 1 Introduction to Commuted Sums 3 2 When are Commuted

More information

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES GUIDANCE NOTES Rev 1 January 2016 INDEX Section Page 1 Introduction to Commuted Sums 3 2 When are

More information

BRIDGE ALTERNATE STUDY No. 1

BRIDGE ALTERNATE STUDY No. 1 BRIDGE ALTERNATE STUDY No. 1 RURAL STREAM CROSSING Prepared for U. S. Bridge Cambridge, Ohio Prepared by RICHLAND ENGINEERING LIMITED 29 North Park Street, Mansfield, Ohio 44902-1769 419/524-0074 FAX 419/524-1812

More information

Improving Transportation Investment Decision Through Life-Cycle Cost Analysis Case Study on some Bridges in the North of Sweden

Improving Transportation Investment Decision Through Life-Cycle Cost Analysis Case Study on some Bridges in the North of Sweden Improving Transportation Investment Decision Through Life-Cycle Cost Analysis Case Study on some Bridges in the North of Sweden M. Ditrani Luleå University of Technology, Luleå, Sweden L.Elfgren, J. Eriksen,

More information

2016 TRB Webinar. Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions

2016 TRB Webinar. Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions 2016 TRB Webinar Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions Adam Matteo Jeff Milton Todd Springer Virginia Department of Transportation Structure and Bridge Division

More information

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade. Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding

More information

ANNUAL LETTER. Visit our Highway Department Website!

ANNUAL LETTER. Visit our Highway Department Website! ANNUAL LETTER From: James Griesbach, Highway Commissioner Date: March 15, 2018 Visit our Highway Department Website! Marathon County Highway Department s Web Site includes information on the following

More information

Improving Bridge Risk and Deterioration Modeling

Improving Bridge Risk and Deterioration Modeling 11 th National Conference on Transportation Asset Management Improving Bridge Risk and Deterioration Modeling Mohammad Dehghani, Caitlin McKinley, Zach Rubin, and Wayne Francisco, GHD Minneapolis, MN July

More information

AVERAGE OF BID ITEMS ENGINEERS ESTIMATE

AVERAGE OF BID ITEMS ENGINEERS ESTIMATE ROADWAY 1 Mobilization 1 LS $ 990,048.50 $ 80,000.00 $ 880,000.00 $ 880,000.00 $ 950,000.00 $ 950,000.00 $ 967,510.00 $ 967,510.00 $ 1,162,684.00 $ 1,162,684.00 2 Maintenance of Traffic ( incl. Pedestrian

More information

CONTRACT TIME DETERMINATION

CONTRACT TIME DETERMINATION CONTRACT TIME DETERMINATION MISSOURI DEPARTMENT OF TRANSPORTATION March 15, 2004 DEFINITIONS Calendar Day: Any day shown on the calendar beginning and ending at midnight. Working Day: A calendar day during

More information

Assets Infrastructure

Assets Infrastructure Assets Infrastructure Tabled Documents 13 September 2018 Item 8 Item 11 Chairs Report Options and costs of retaining the existing Mangaweka Bridge Report Subject: To: From: Mangaweka Bridge Replacement

More information

PART A ROADWAY - BASE BID

PART A ROADWAY - BASE BID May 10, 2016 HEB-MC-61 PART A ROADWAY - BASE BID 202(A) - UNCLASSIFIED EXCAVATION - CY 34,946.00 $ 6.00 209,676.00 $ 7.98 $ 278,869.08 205(A) - TYPE A-SALVAGED TOPSOIL - LSUM 1.00 $ 22,500.00 $ 22,500.00

More information

Bridge Asset Management or IT S THE MONEY DUMMY

Bridge Asset Management or IT S THE MONEY DUMMY Bridge Asset Management or IT S THE MONEY DUMMY Chris Keegan, P. E. Bridge Maintenance Engineer Region Operations Engineer. Secretary of Transportation Roger Millar WBPP, Denver CO May, 2017 Asset Management

More information

Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE

Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE Cedar Hammock Community Development District Inframark, Infrastructure Management Services 210 N. University

More information

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 6: Preliminary Cost Estimates.

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 6: Preliminary Cost Estimates. , Segments 2-4 Chapter 6: Preliminary Cost Estimates Table of Contents 6.1 Details of Facilities... 17 6.2 Pre-Development and Facility Feasibility... 1 6.2.1 Planning... 1 6.2.2 Environmental Mitigation...

More information

Asset Sustainability Index

Asset Sustainability Index Asset Sustainability Index A Beta Version Using Existing State Data Conference Feb. 18, 2012 Gordon Proctor Conference Feb. 18, 2013 1 Project Scope Describe Australian sustainability indices Can we replicate

More information

Munilla Construction HOOD RD., E. OF FLORIDA'S TURNPIKE TO W. OF CENTRAL BLVD. AND HOOD RD. & CENTRAL

Munilla Construction HOOD RD., E. OF FLORIDA'S TURNPIKE TO W. OF CENTRAL BLVD. AND HOOD RD. & CENTRAL JW Cheatham, ROADWAY 1 MOBILIZATION 1.0 LS $ 1,350,116.25 $ 906,000.00 $ 1,233,000.00 $ 1,233,000.00 $ 1,159,208.36 $ 1,159,208.36 $ 1,451,835.00 $ 1,451,835.00 $ 1,556,421.65 $ 1,556,421.65 2 MAINTENANCE

More information

CAPITAL REPLACEMENT RESERVE FUND STUDY. April Prepared for. Condominium Corporation Operating as: Birchwood County Condo

CAPITAL REPLACEMENT RESERVE FUND STUDY. April Prepared for. Condominium Corporation Operating as: Birchwood County Condo CAPITAL REPLACEMENT RESERVE FUND STUDY Prepared for Operating as: Birchwood County Condo Contact: Jan Wells, Vice President (780) 542-3153 P.O. Box 134 Lindale, Alberta T0C 1W0 Email: mail@birchwoodcountrycondo.com

More information

REPLACEMENT OF MERCER COUNTY BRIDGE

REPLACEMENT OF MERCER COUNTY BRIDGE ADDENDUM NO. ONE Notice is hereby given that on April 26, 2019 at 11:00 AM (Prevailing time), sealed proposals will be opened and read in public by the Purchasing Department in the Mercer County McDade

More information

OKLAHOMA TURNPIKE AUTHORITY

OKLAHOMA TURNPIKE AUTHORITY PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 250,000.00 $250,000.00 $ 240,978.56 $ 240,978.56 260,000.00 $ 260,000.00 201(A) CLEARING & GRUBBING LSUM 1.00 $ 30,000.00 $30,000.00 $ 17,188.20

More information

Requirements for Mapping Levees Complying with Section of the NFIP Regulations

Requirements for Mapping Levees Complying with Section of the NFIP Regulations FACT SHEET Requirements for Mapping Levees Complying with Section 65.10 of the NFIP Regulations As part of a mapping project, it is the levee owner s or community s responsibility to provide data and documentation

More information

SINGLE PROJECT FACT FIND. This application is intended for contracts with a value in excess of 500,000

SINGLE PROJECT FACT FIND. This application is intended for contracts with a value in excess of 500,000 SINGLE PROJECT FACT FIND This application is intended for contracts with a value in excess of 500,000 SINGLE PROJECT FACT FIND underwriting Definitions to assist you in completing this application Contract

More information

Cost Control. Progress Measurement

Cost Control. Progress Measurement Cost Control Progress Measurement Introduction Once the execution of the project starts, the project team must periodically report their progress on each task. Since the nature of each task varies, no

More information

OKLAHOMA TURNPIKE AUTHORITY

OKLAHOMA TURNPIKE AUTHORITY PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 70,000.00 $70,000.00 $ 15,735.00 $ 15,735.00 $ 60,000.00 $ 60,000.00 $ 25,000.00 $ 25,000.00 $ 20,000.00 $ 20,000.00 201(A) CLEARING & GRUBBING

More information

Spartanburg County Roads & Bridges 9039 Fairforest Road Spartanburg, South Carolina Telephone Fax

Spartanburg County Roads & Bridges 9039 Fairforest Road Spartanburg, South Carolina Telephone Fax Spartanburg County Roads & Bridges 9039 Fairforest Road Spartanburg, South Carolina 29301 Telephone 864-595-5320 Fax 864-595-5364 ENCROACHMENT PERMIT APPLICATION Applicant s Name Address City, State, Zip

More information

QUONSET DEVELOPMENT CORPORATION (QDC) INVITATION TO BID

QUONSET DEVELOPMENT CORPORATION (QDC) INVITATION TO BID QUONSET DEVELOPMENT CORPORATION (QDC) A BID is solicited for the following work: INVITATION TO BID Name of Project: Background & Description of Work: Pavement Repairs: Utility Connections: On-Call Pavement

More information

EXHIBIT B WHATCOM COUNTY FOURTEEN-YEAR FERRY CAPITAL PROGRAM

EXHIBIT B WHATCOM COUNTY FOURTEEN-YEAR FERRY CAPITAL PROGRAM EXHIBIT B WHATCOM COUNTY 2016-2029 FOURTEEN-YEAR FERRY CAPITAL PROGRAM Overview This program provides a blueprint for the effective, efficient, and continuing operation of the Whatcom County Ferry System

More information

RIGHT-OF-WAY PERMIT APPLICATION

RIGHT-OF-WAY PERMIT APPLICATION PERMIT EXPIRES 180 DAYS AFTER DATE OF ISSUANCE. RIGHT-OF-WAY PERMIT APPLICATION DESCRIPTION OF WORK: (Mark all applicable) Pavement Cut: Directional Bore: Sewer / Water Connection: Driveway Apron: Sidewalk

More information

Both bids are substantially higher than the engineer s estimate of $362, The attached Bid Abstract shows the bid details.

Both bids are substantially higher than the engineer s estimate of $362, The attached Bid Abstract shows the bid details. STAFF REPORT MEETING DATE: September 12, 2017 TO: FROM: City Council David Dammuller, Senior Engineer Chris Blunk, Deputy Public Works Director 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/

More information

Chapter 8: Lifecycle Planning

Chapter 8: Lifecycle Planning Chapter 8: Lifecycle Planning Objectives of lifecycle planning Identify long-term investment for highway infrastructure assets and develop an appropriate maintenance strategy Predict future performance

More information

Allen County Highway Engineering Department Problems and Progress

Allen County Highway Engineering Department Problems and Progress Allen County Highway Engineering Department Problems and Progress K a r l J o h n s o n Allen County Highway Engineer Fort Wayne, Indiana IN T R O D U C T IO N The present and future traffic demands and

More information

Life Cycle Cost analysis in Drainage Projects TECHNICAL BULLETIN. Concrete Pipe Association of Australasia ACN

Life Cycle Cost analysis in Drainage Projects TECHNICAL BULLETIN. Concrete Pipe Association of Australasia ACN Life Cycle Cost analysis in Drainage Projects Concrete Pipe Association of Australasia ACN 007 067 656 TECHNICAL BULLETIN CONTENTS 1 INTRODUCTION 2 THE U.S. EXPERIENCE 3 FACTORS TO BE CONSIDERED IN LCA

More information

APPLICATION FOR RIGHT-OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI

APPLICATION FOR RIGHT-OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI APPLICATION FOR RIGHT-OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: _100.00 Date: / / Receipt No: APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE,

More information

TOTAL QUANTITY UNIT COST UNIT

TOTAL QUANTITY UNIT COST UNIT BASE BID DIVISION 1 - GENERAL 1 1070-206-A-0 TRAFFIC CONTROL LS 1 $ 10,000 $ 10,000 $3,000.00 $3,000.00 $5,600.00 $5,600.00 2 2010-108-B-0 CLEARING AND GRUBBING AC 5 $ 9,000 $ 45,000 $7,192.50 $35,962.50

More information

Asset Management Plan

Asset Management Plan 2016 Asset Management Plan United Counties of Prescott and Russell 6/1/2016 Preface This Asset Management Plan is intended to describe the infrastructure owned, operated, and maintained by the United Counties

More information

N E W J E R S E Y T U R N P I K E A U T H O R I T Y PROCEDURE FOR PREQUALIFICATION AND AWARD OF CONSTRUCTION CONTRACTS

N E W J E R S E Y T U R N P I K E A U T H O R I T Y PROCEDURE FOR PREQUALIFICATION AND AWARD OF CONSTRUCTION CONTRACTS N E W J E R S E Y T U R N P I K E A U T H O R I T Y PROCEDURE FOR PREQUALIFICATION AND AWARD OF CONSTRUCTION CONTRACTS (a) All prospective bidders for construction in excess of $50,000.00 shall be prequalified

More information

Engineer's Preliminary Estimate - 100% Submittal

Engineer's Preliminary Estimate - 100% Submittal EA 284700 1 070010 PROGRESS SCHEDULE (CRITICAL PATH) LS 1 $ 15,000 $ 15,000 2 071325 TEMPORARY FENCE (TYPE ESA) M 1250 $ 10 $ 12,500 3 074019 PREPARE STORM WATER POLLUTION PREVENTION PLAN LS 1 $ 7,000

More information

Prioritising bridge replacements

Prioritising bridge replacements Prioritising bridge replacements Andrew Sonnenberg, National Bridge Engineering Manager, Pitt&Sherry ABSTRACT Road and Rail managers own a variety of assets which are aging and will need replacement. There

More information

GRAND TRAVERSE COUNTY ROAD COMMISSION

GRAND TRAVERSE COUNTY ROAD COMMISSION ADVERTISEMENT FOR BIDS EAST DUCK LAKE ROAD OVER MASON CREEK SINGLE SPAN TIMBER BRIDGE DESIGN, FABRICATION AND DELIVERY OF MATERIALS GRAND TRAVERSE COUNTY ROAD COMMISSION Sealed bids for materials for the

More information

Hazard Mitigation Planning

Hazard Mitigation Planning Hazard Mitigation Planning Mitigation In order to develop an effective mitigation plan for your facility, residents and staff, one must understand several factors. The first factor is geography. Is your

More information

Time and Cost Optimization Techniques in Construction Project Management

Time and Cost Optimization Techniques in Construction Project Management Time and Cost Optimization Techniques in Construction Project Management Mr.Bhushan V 1. Tatar and Prof.Rahul S.Patil 2 1. INTRODUCTION In the field of Construction the term project refers as a temporary

More information

Project Summary Project Name: Route 37 Corridor Safety Sweep Project Number:

Project Summary Project Name: Route 37 Corridor Safety Sweep Project Number: Project Summary This project summary page details the benefit cost analysis (BCA) for the Route 37 Corridor Safety Sweep Project. A BCA provides estimates of the anticipated benefits that are expected

More information

Risk based inspections

Risk based inspections Risk based inspections Some railway industry initiatives Brian Bell, Network Rail Bridge Owners Forum, May 2010 1 Industry workstreams There have been 4 separate workstreams recently looking at RBI, 3

More information

Trinity River Restoration Program

Trinity River Restoration Program Trinity River Restoration Program Trinity River Bridges: Hydraulic, Scour, and Riprap Sizing Analysis US DEPARTMENT OF THE INTERIOR BUREAU OF RECLAMATION TECHNICAL SERVICE CENTER Prepared by Kent L. Collins

More information

IC Chapter 8. Distressed Roads

IC Chapter 8. Distressed Roads IC 8-14-8 Chapter 8. Distressed Roads IC 8-14-8-1 Purpose Sec. 1. The intent of this chapter is to create a method of providing financial assistance to counties, cities, and towns (referred to as "units"

More information

Port Tariffs Port of Bodø - Port Tariffs

Port Tariffs Port of Bodø - Port Tariffs Port Tariffs 2018 Port of Bodø - Port Tariffs 2018 1 2 Port of Bodø - Port Tariffs 2018 Contents 1. USE OF PORT INFRASTRUCTURE 1.1 Quay dues 1.2 Goods charges 1.3 Charge for storage of goods 1.4 Passenger

More information

SUTTER BUTTER FLOOD CONTROL AGENCY FEATHER RIVER WEST LEVEE PROJECT PROJECT C, CONTRACT NO C BID TABULATION

SUTTER BUTTER FLOOD CONTROL AGENCY FEATHER RIVER WEST LEVEE PROJECT PROJECT C, CONTRACT NO C BID TABULATION Bid Schedule A - Feather River West Levee Project C Improvements No. Item Description Quantity Unit Nordic/Magnus Pacific JV Engineer's Estimate Unit Price Total Price Unit Price Total Price A1 Injury

More information

Opportunities for Low-Volume Roads

Opportunities for Low-Volume Roads A5002: Committee on Low-Volume Roads Chairman: Gerald T. Coghlan for Low-Volume Roads GERALD T. COGHLAN, U.S. Department of Agriculture Forest Service The coming of the new millennium provides an excellent

More information

COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013

COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013 COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013 Pictures Key Front Cover Top Row 1) Administration Building Second Row, left to right 2) Brigden EMS Station 3) Judith & Norman Alix Art Gallery Third row,

More information

LOCAL MAJOR BRIDGE PROGRAM

LOCAL MAJOR BRIDGE PROGRAM LOCAL MAJOR BRIDGE PROGRAM The Local Major Bridge Program provides federal funds to counties and municipal corporations for bridge replacement or bridge major rehabilitation projects. A Local Major Bridge

More information

FOR OFFICE USE ONLY CONTRACTOR/DEVELOPER APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE AND/OR MAINTAIN WITHIN THE RIGHT-OF-WAY/EASEMENT

FOR OFFICE USE ONLY CONTRACTOR/DEVELOPER APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE AND/OR MAINTAIN WITHIN THE RIGHT-OF-WAY/EASEMENT 40555 Utica Road P.O. Box 8009 Sterling Heights, MI 48311-8009 TEL 586-446-2720 FAX 586-276-4061 CONTRACTOR/DEVELOPER APPLICATION AND PERMIT TO CONSTRUCT, OPERATE, USE AND/OR MAINTAIN WITHIN THE RIGHT-OF-WAY/EASEMENT

More information

BIDS WILL BE OPENED AT 1:00 p.m., local prevailing time, WEDNESDAY, MARCH 13, 2019.

BIDS WILL BE OPENED AT 1:00 p.m., local prevailing time, WEDNESDAY, MARCH 13, 2019. INSTRUCTIONS TO BIDDERS: This Proposal shall be legibly prepared with ink. UNIT PRICES, and LUMP SUM BIDS when called for on the itemized bid sheet, shall be entered with ink, in the Unit Price column.

More information

Village Glen HOA P.O. Box 1537, Arroyo Grande, CA. Reserve Study

Village Glen HOA P.O. Box 1537, Arroyo Grande, CA. Reserve Study Village Glen HOA P.O. Box 1537, Arroyo Grande, CA Reserve Study As required by the state of California, it is the responsibility of the Board of Directors to create and maintain adequate reserves to provide

More information

A DESIGN-BUILD PROJECT

A DESIGN-BUILD PROJECT Price Proposal A DESIGN-BUILD PROJECT Fall Hill Avenue Widening and Mary Washington Boulevard Extension From: 0.12 Miles West of Gordon W. Shelton Boulevard To: Route 1 at Mary Washington Boulevard Fredericksburg,

More information

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562 1 T100 PROJECT LOCATION MAP Scale: NTS N Revisions: No. Date: Description: Scale As Indicated

More information

Case Study: Key Performance Indicators implementation in gas transmission pipeline. María José Gutiérrez Argentina

Case Study: Key Performance Indicators implementation in gas transmission pipeline. María José Gutiérrez Argentina Paper Number: 2015-07 Case Study: Key Performance Indicators implementation in gas transmission pipeline María José Gutiérrez Argentina Abstract Corrosion is a major threat that affects many assets of

More information

MTA Bridges and Tunnels

MTA Bridges and Tunnels MTA Bridges and Tunnels New York Building Congress May 24th, 2016 Overview Capital/Sandy/Operating Program Projects New Initiatives & Directions Upcoming Opportunities Bridges and Tunnels 1 Program Growth

More information

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E.

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. Life Cycle Cost Analysis in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. What is it? Economic procedure That uses

More information

Fees: An application fee of one hundred dollars ($100) shall be included with the application submission.

Fees: An application fee of one hundred dollars ($100) shall be included with the application submission. Town of Conway, NH Construction/Driveway Permit Adopted by the Board of Selectmen, November 26, 1996 Applicability: In accordance with NH RSA Chapter 236 and the legislative authority cited in 131-1, 131-67.C.8.(j),

More information

Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements

Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements Resurfacing projects are among the most common and routine types of projects regularly conducted by highway agencies. When resurfacing projects

More information

Evaluating Different Bridge Management Strategies Using The Bridge Management Research System (bmrs)

Evaluating Different Bridge Management Strategies Using The Bridge Management Research System (bmrs) Purdue University Purdue e-pubs Open Access Theses Theses and Dissertations 2013 Evaluating Different Bridge Management Strategies Using The Bridge Management Research System (bmrs) Timothy Paul Stroshine

More information

NE WEST KINGSTON ROAD CULVERT REPLACEMENT

NE WEST KINGSTON ROAD CULVERT REPLACEMENT NE WEST KINGSTON ROAD CULVERT REPLACEMENT KITSAP COUNTY MILE POST 1.28 TO 1.44 PUBLIC WORKS BID TABULATION SECTION PREPARED: BLB LENGTH: 0.16 Mile REVISED: DATE: March 7, 2017 SCHEDULE A - ROADWAY IMPROVEMENTS

More information

Opinion of Probable Cost

Opinion of Probable Cost Appendix E Opinion of Probable Cost 01054/8410233/14/Rohner_Alt_Analysis_Report Rohner Creek Flood Control, Habitat and Seismic Improvement Project Alternatives Analysis Cost Alternative 1: Improved Channel

More information

SOLUTIONS FOR SAVING LIVES ON TEXAS ROADS

SOLUTIONS FOR SAVING LIVES ON TEXAS ROADS SOLUTIONS FOR SAVING LIVES ON TEXAS ROADS Darren McDaniel Texas Department of Transportation December 2016 Texas Traffic Safety Task Force Texas Traffic Safety Task Force was created in August 2015 with

More information

Powys County Council. Highway Asset Management Plan. Working Document Page 1

Powys County Council. Highway Asset Management Plan. Working Document Page 1 Powys County Council Highway Asset Management Plan 2017 Working Document Page 1 Foreword This plan sets out the council s strategy for the management of the council s highway asset for the future. It has

More information

APPANOOSE COUNTY USE OF RIGHT OF WAY PERMIT Date

APPANOOSE COUNTY USE OF RIGHT OF WAY PERMIT Date Permit Number APPANOOSE COUNTY USE OF RIGHT OF WAY PERMIT Date To the Board of Supervisors, Appanoose County, Iowa: I,, on behalf of,, Installer/Contractor Owner Address do hereby make application requesting

More information

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM TOTAL PROJECT ESTIMATE ($) STATE ALLOCATION CODE (SAC) FUND TYPE ENCUMBERED FROM BEFORE FY 2011 PE/RW PRIOR TO FY 2016 LOCAL MATCH LOCAL LABOR STATE LABOR FED LABOR & TSKF LINE ITEM # ST. LINE ITEM

More information

A Financial Impact Assessment of LD 1725: Stream Crossings

A Financial Impact Assessment of LD 1725: Stream Crossings A Financial Impact Assessment of LD 1725: Stream Crossings Prepared by: The New England Environmental Finance Center For the Maine Department of Transportation Office of Environmental Planning Edmund S.

More information

Manor Township, Lancaster County, PA Zoning Permit Application ( section 702) App. number App. date

Manor Township, Lancaster County, PA Zoning Permit Application ( section 702) App. number App. date Manor Township, Lancaster County, PA Zoning Permit Application ( section 702) App. number App. date 1. General Information Name of Applicant Address Telephone No. Cell No. Fax No. Name of Landowner of

More information

Single Project - Contract Works & General Liability proposal form

Single Project - Contract Works & General Liability proposal form Single Project - Contract Works & General Liability proposal form Broker or dealer details Company Name Phone Email Page 1 of 6 Insured details Name of Insured Registered Business address Suburb State

More information

APPENDICES APPENDICES

APPENDICES APPENDICES APPENDICES APPENDICES A PPENDIX A. ABBREVIATIONS A A BBREVIATIONS Common abbreviations used at NDOT are listed below: AEB Agreement Estimate Breakout AP Agreed Price B/L Bill of Ladings BMP Best Management

More information

INTERNATIONAL MARINE UNDERWRITERS COMMERCIAL MARINE PACKAGE POLICY APPLICATION

INTERNATIONAL MARINE UNDERWRITERS COMMERCIAL MARINE PACKAGE POLICY APPLICATION INTERNATIONAL MARINE UNDERWRITERS COMMERCIAL MARINE PACKAGE POLICY APPLICATION Name of Applicant: Mailing Address: Web: City: State: Zip: Applicant is a : Partnership Corporation Other Policy Period: From:

More information

Request for Continued Participation in the Midwest States Pooled Fund to Advance Roadside Safety Research

Request for Continued Participation in the Midwest States Pooled Fund to Advance Roadside Safety Research Request for Continued Participation in the Midwest States Pooled Fund to Advance Roadside Safety Research Project Champion & WYDOT Project Manager: Bill Wilson, P.E. Standards Engineer Wyoming Dept. of

More information

Modeling of Life Cycle Alternatives in the National Bridge Investment Analysis System (NBIAS) Prepared by: Bill Robert, SPP Steve Sissel, FHWA

Modeling of Life Cycle Alternatives in the National Bridge Investment Analysis System (NBIAS) Prepared by: Bill Robert, SPP Steve Sissel, FHWA Modeling of Life Cycle Alternatives in the National Bridge Investment Analysis System (NBIAS) Prepared by: Bill Robert, SPP Steve Sissel, FHWA TRB International Bridge & Structure Management Conference

More information

STUDY SCHEDULE STUDY PURPOSE

STUDY SCHEDULE STUDY PURPOSE STUDY SCHEDULE This Open House is the last of three public meetings for the Route Centennial Bridge Study. The material presented previously at the second Open House in July 2015 focused upon Corridor

More information

Executive Change Control Board. August 3, 2016

Executive Change Control Board. August 3, 2016 Executive Change Control Board August 3, 2016 1 Today s Topics Approval of Meeting Minutes 90% Cost Estimate Project Schedule Project Scope and Budget Action Next Steps 2 90% Cost Estimate 3 Project Cost

More information

Revenue Sharing Program Guidelines

Revenue Sharing Program Guidelines Revenue Sharing Program Guidelines For further information, contact Local VDOT Manager or Local Assistance Division Virginia Department of Transportation 1401 East Broad Street Richmond, Virginia 23219

More information

PROJECT NO PID BEL TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02

PROJECT NO PID BEL TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02 AWARDED PROJECT PROJECT NO. 016002 PID. 19109 BEL-7-3.68 TE21-G990(217) TYPE: SLIDE REPAIR LETTING: 06/07/01 COMPLETION DATE: 09/30/02 OHIO DEPARTMENT OF TRANSPORTATION GORDON PROCTOR, DIRECTOR CONTRACT

More information

Including Maintenance & Rehabilitation Schedules

Including Maintenance & Rehabilitation Schedules Final Report Methodology for the Development of Equivalent Structural Design Matrix for Municipal Roadways- Ontario Including Maintenance & Rehabilitation Schedules and Life Cycle Analysis Prepared for:

More information

$+ 121 $+ 120 $+ 122 $+ 155 $+ 155 $+ 109 $+ 139 $+ 136 $+ 111 $+ 124 $ MINNEHAHA COUNTY TIP Projects !.!. !.!. Dell Rapids.

$+ 121 $+ 120 $+ 122 $+ 155 $+ 155 $+ 109 $+ 139 $+ 136 $+ 111 $+ 124 $ MINNEHAHA COUNTY TIP Projects !.!. !.!. Dell Rapids. ST AVE TH AVE TH AVE BIG SIOUX RD TH AVE TH AVE TH AVE TH AVE TH AVE 9 9 0 Miles TH AVE $+ 0 $+ 0 TH AVE TH AVE 9 Humboldt TH ST TH AVE $+ 0 0 0-0-00 0 Construction 09 Construction 00 Construction 0 Construction

More information

CODE OF PRACTICE FOR WORKS AFFECTING THE CANAL & RIVER TRUST

CODE OF PRACTICE FOR WORKS AFFECTING THE CANAL & RIVER TRUST CODE OF PRACTICE FOR WORKS AFFECTING THE CANAL & RIVER TRUST PART 3 FORMS April 2018 Third Party Works Code of Practice: Part 3: Forms April 2018 1 CONTENTS FORM 1:NOTIFICATION FORM FORM 2: COST UNDERTAKING

More information

Revenue Sharing Program Guidelines

Revenue Sharing Program Guidelines Revenue Sharing Program Guidelines For further information, contact Local VDOT Manager or Local Assistance Division Virginia Department of Transportation 1401 East Broad Street Richmond, Virginia 23219

More information

Corridor Management Committee. May 6, 2015

Corridor Management Committee. May 6, 2015 Corridor Management Committee May 6, 2015 1 Today s Topics Project Budget and Schedule Update Project Options Work Plan Upcoming Meeting Schedule 2 Project Budget and Schedule Update 3 Project Updates:

More information

WASHTENAW COUNTY ROAD COMMISSION Permit Engineering Section 555 N. Zeeb Road Ann Arbor, MI 48103

WASHTENAW COUNTY ROAD COMMISSION Permit Engineering Section 555 N. Zeeb Road Ann Arbor, MI 48103 WASHTENAW COUNTY ROAD COMMISSION Permit Engineering Section The following is (1) a list of the activities which utility companies will be allowed to undertake in Washtenaw County road Right-of-Way under

More information

WASHTENAW COUNTY ROAD COMMISSION Permit Engineering Section 555 N. Zeeb Road Ann Arbor, MI 48103

WASHTENAW COUNTY ROAD COMMISSION Permit Engineering Section 555 N. Zeeb Road Ann Arbor, MI 48103 WASHTENAW COUNTY ROAD COMMISSION The following is (1) a list of the activities which utility companies will be allowed to undertake in Washtenaw County road Right-of-Way under a Blanket Permit ; and, (2)

More information

Risk Based Inspection A Key Component to Generating Value from a Mechanical Integrity Program API Singapore 2012

Risk Based Inspection A Key Component to Generating Value from a Mechanical Integrity Program API Singapore 2012 the global leader in asset performance management solutions Risk Based Inspection A Key Component to Generating Value from a Mechanical Integrity Program API Singapore 2012 Agenda Introduction Achieving

More information

EMERGENCY CONTRACT MANUAL

EMERGENCY CONTRACT MANUAL EMERGENCY CONTRACT MANUAL 2012, Commonwealth of Virginia Virginia Department of Transportation February, 2012 TABLE OF CONTENTS Introduction... 3 Requirements... 5 Emergency Authorization Chart... 6 District

More information

NOTICE OF AWARD OF CONTRACT S.R. 408/S.R.417 INTERCHANGE IMPROVEMENTS PHASE 1. Project No. 253F Contract No

NOTICE OF AWARD OF CONTRACT S.R. 408/S.R.417 INTERCHANGE IMPROVEMENTS PHASE 1. Project No. 253F Contract No NOTICE OF AWARD OF CONTRACT S.R. 408/S.R.417 INTERCHANGE IMPROVEMENTS PHASE 1 Project No. 253F Contract No. 001118 October 8, 2015 Bids for this project were received and opened on September 16, 2015,

More information

TOWN OF TIBURON ENCROACHMENT PERMIT APPLICATION EP Number:

TOWN OF TIBURON ENCROACHMENT PERMIT APPLICATION EP Number: TOWN OF TIBURON ENCROACHMENT PERMIT APPLICATION EP Number: APPLICATION DATE: ADDRESS OF WORK OR ENCROACHMENT: CROSS STREET: STARTING DATE: APN: - - No. Street City/Township ESTIMATED COST: $ COMPLETION

More information

STATE AID FINANCE ACCOUNTING MANUAL. For Counties

STATE AID FINANCE ACCOUNTING MANUAL. For Counties STATE AID FINANCE ACCOUNTING MANUAL For Counties Revised November 2017 (Left blank intentionally) STATE AID FINANCE ACCOUNTING MANUAL INTRODUCTION... I PURPOSE... I UPDATES... I QUESTIONS... I STATE AID

More information

Report on Concrete Dam Construction

Report on Concrete Dam Construction Workers Compensation Insurance Rating Bureau of California Workers Compensation Insurance Rating Bureau of California Report on Concrete Dam Construction Excerpt from the WCIRB Classification and Rating

More information

JCT Non Negligent Liability - Specific Contract Insurance Proposal Form

JCT Non Negligent Liability - Specific Contract Insurance Proposal Form JCT n Negligent Liability - Specific Contract Insurance Proposal Form Please Complete In Capital Letters Using Black Ink And Tick Boxes As Appropriate. Where requested, please enter further details in

More information

AVGPR14.Y01 2/11/2014 DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 12/01/13 AND 12/31/13 BY ITEM GROUP

AVGPR14.Y01 2/11/2014 DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 12/01/13 AND 12/31/13 BY ITEM GROUP AVERAGE BID PRICES FOR AWARDED PROJECTS 14:48 Tuesday, February 11, 2014 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 1 $19 $18,500.00 1 2013 2013.602/00022 ROAD/WEATHER SENSOR AND CABLE EACH 3 $32

More information

LETTING : CALL : 056 COUNTIES : MILLE LACS

LETTING : CALL : 056 COUNTIES : MILLE LACS S T A T E O F M I N N E S O T A PAGE : -1 NUMBER OF DAYS: 0 BRIDGE COUNT : 3 CONTRACT DESCRIPTION : GRADING, BIT PAVING & SURFACING, ROUNDABOUT, AND BRIDGES. CONTRACT LOCATION: LOCATED ON T.H. 95 AT THE

More information

OKLAHOMA DEPARTMENT OF TRANSPORTATION PRELIMINARY HIGHWAY DETAIL CONSTRUCTION ESTIMATE. PAGE NO. 1 DATE PRINTED : May 22, 2018

OKLAHOMA DEPARTMENT OF TRANSPORTATION PRELIMINARY HIGHWAY DETAIL CONSTRUCTION ESTIMATE. PAGE NO. 1 DATE PRINTED : May 22, 2018 LETTING DATE : 2018-06-14 CALL NUMBER : 772 OKLAHOMA DEPARTMENT OF TRANSPORTATION PRELIMINARY HIGHWAY DETAIL CONSTRUCTION ESTIMATE PAGE NO. 1 DATE PRINTED : JOB NUMBER : 170236 ESTIMATE NUMBER : PROJECT

More information

EVALUATION OF VARIANTS (CONTINUATION)

EVALUATION OF VARIANTS (CONTINUATION) EVALUATION OF VARIANTS (CONTINUATION) INVESTMENT COSTS (IN) (CONTINUATION) 2. The costs of land P: Include costs of lands for the road construction and the settlements of dispute Only necessary land is

More information

Yearly Totals $4,575,931 $29,650,463 $33,918,732 $8,480,000 $49,160,000 $24,630,000 $9,000,000 $145,839,195 $159,415,126. Revised March 26, 2018

Yearly Totals $4,575,931 $29,650,463 $33,918,732 $8,480,000 $49,160,000 $24,630,000 $9,000,000 $145,839,195 $159,415,126. Revised March 26, 2018 BHM Airport Capital Improvement Plan (ACIP) ACIP Annual Expense Summary 5 YEAR ACIP 2019 2023 Prior Year(s) Budgeted Budgeted Budgeted Budgeted Budgeted Estimated Five (5) Year Total Project NPS Priority

More information

32 nd Street Corridor Improvements

32 nd Street Corridor Improvements Benefit-Cost Analysis Supplementary Documentation TIGER Discretionary Grant Program 32 nd Corridor Improvements USDOT TIGER BCA Results City of Joplin, MO April 29, 2016 32nd Corridor Improvements Contents...

More information