2016 TRB Webinar. Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions

Size: px
Start display at page:

Download "2016 TRB Webinar. Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions"

Transcription

1 2016 TRB Webinar Using Asset Valuation as a Basis for Bridge Maintenance and Replacement Decisions Adam Matteo Jeff Milton Todd Springer Virginia Department of Transportation Structure and Bridge Division April 11, 2016

2 Presentation Outline 1. Calculate the current value and condition of bridges in an inventory Modified Health Index (MHI) Element Condition Data 2. Using current valuation (equity) as the basis for engineering decisions on maintenance/replacement Action-effectiveness models and associated cost estimates to develop comparative cost/benefit ratios Long-term predictions of asset values for various alternatives to perform life cycle analysis using estimates 3. Using Modified Health Index and other indices to select bridge projects with a Multi-Objective Prioritization Formula 2

3 Modified Health Index (MHI) Using detailed information about bridge conditions from element level data, cost data to develop Publicly-owned assets have value but no revenue in most cases How do we measure current value (depreciation) Thinking like a business WWUPSD? (What Would UPS Do?) 3

4 Current Valuation (Equity) Multiple Uses Equity can be a powerful tool in guiding bridge management Can determine the most cost-effective actions on a given structure Helpful in selecting which structures should be worked on Can be used to measure effectiveness of various work programs Helpful as a measurement of progress 4

5 Measuring Equity Common Practice (IRS): Time Based Depreciation $1,200,000 $1,000,000 Typical Straight-Line Depreciation Curve Initial Value ($1M) Residual (Salvage) Value Equity $800,000 $600,000 $400,000 $200,000 $ Age of Asset (Years) 5

6 Modified Health Index: Basic Equation If a structure has the following characteristics: 0 to 100 scale 0 means end of service life 100 for a new (ideal) structure Example: If a structure has deteriorated 32%, the MHI = 68 (100-32) MHI = Σ (MHI Element *Replacement Value Element ) Σ Replacement Value Elements If Σ Superstructure Value = 0, then deck = 0 If Σ Substructure Value = 0, then deck and superstructure = 0 6

7 Element Data Collected During Inspections AASHTO National Bridge Elements (NBE) 7

8 Additional VDOT Elements Component Number Title Deck 801 Sidewalk 802 Deck Drains Superstructure 811 Beam/Girder End 812 Reinforced Concrete Frame Substructure 821 Steel Abutment 822 Steel Wingwall 823 Reinf.\ Concrete Abutment 824 Reinf.\ Concrete Wingwall 825 Timber Abutment 826 Timber Wingwall 827 Masonry Abutment 828 Masonry Wingwall 829 MSE Abutments 830 MSE Wingwall Culverts 831 Concrete Culvert Endwall/Headwall 832 Concrete Cuvlert Wingwall 833 Roadway Over Culvert Joints 841 Asphalt Plug Joint 842 Elastomeric Concrete Plug Joint 843 Link Slab 844 Slab Extension 845 Joint Effectiveness Slopes & Channels 851 Unprotected Slope 852 Protected Slope - Paved 853 Protected Slope - Riprap 854 Channel Protective 881 Wearing Surface - Unprotected Asphalt Wearing Surface 882 Wearing Surface - Protected Asphalt Wearing Surface 883 Wearing Surface - Thin Overlay 884 Wearing surface - Rigid Overlay 885 Wearing Surface - Other 8

9 Using Deterioration Models to Determine Current Value: Step 1: Define End of Life of Elements in Terms of Condition States 100% Predicted % of Element in Each Condition State 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Steel Girders Element End of Element Life (Zero Value): 20% in Worst Condition State (CS4) Average life of Element is ~44 Years Years

10 Using Deterioration Models to Determine Current Value: Step 2: Determine Current Value in Terms of Current Condition Predicted % of Element in Each Condition State 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Steel Girders Element Element Currently has 6% in Worst Condition State (CS4) Element has deteriorated ~ 27 Years Average life of Element is ~44 Years Years

11 Using Deterioration Models to Determine Current Value: Step 3: Determine MHI for Each Element 100% Predicted % of Element in Each Condition State 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Steel Girders Element Element has deteriorated ~ 27 Years MHI Element = 100*(44-27)/44 = 39 Average life of Element is ~44 Years Years

12 Determination of Current Valuation (Equity): Example Equation Equity = MHI * Structure Replacement Cost Example Structure: MHI = 39 Replacement Value = $2,000,000 Equity =.39 * 2,000,000 = $780,000 12

13 Modified Health Index and Current Valuation: Example Calculation #1 Element Name MHI Element Element Replacement Value MHI * Replacement Value Columns 63 x $25,000 = $15,750 Pier Caps 54 x $30,000 = $16,200 Abutments 75 x $60,000 = $45,000 Girders 83 x $160,000 = $132,800 Diahragms 86 x $30,000 = $25,800 Deck 92 x $180,000 = $165,600 Joints 65 x $30,000 = $19,500 Parapet 92 x $40,000 = $36,800 Sum 82 $555,000 $457,450 MHI = ($457,450 $555,000)100 = 82 13

14 Modified Health Index and Current Valuation: Example Calculation #2 Element Name MHI Element Element Replacement Value MHI * Replacement Value Columns 63 x $25,000 = $15,750 Pier Caps 54 x $30,000 = $16,200 Abutments 75 x $60,000 = $45,000 Girders 83 x $160,000 = $132,800 Diahragms 86 x $30,000 = $25,800 Deck 0 x $180,000 = $0 Joints 0 x $30,000 = $0 Parapet 0 x $40,000 = $0 Sum 42 $555,000 $235,550 Note: Replacement Cost of Bridge < ΣElement Replacement Values MHI = ($235,550 $555,000)100 = 42 14

15 Using Current Valuation to Evaluate Performance of an Entire Inventory of Structures District Available Funds (Millions) Aggregate Valuation of Structures (Billions) Average MHI Maintenance Construction Total Start of year End of year Difference (Millions) Start of year End of year Difference A $19.1 $12.5 $31.6 $5.23 $5.21 -$ B $23.1 $15.5 $38.6 $7.22 $7.21 -$ C $20.4 $14.0 $34.4 $6.05 $5.76 -$ Total $62.6 $42.0 $104.6 $18.5 $ $ MHI is used as both a condition index and a measurement of current value 15

16 Using current valuation (equity) as the basis for engineering decisions on maintenance/replacement 16

17 Measuring Equity Benefits for Various Alternatives Immediate Benefit = Increase in Valuation due to Interventions Example: For a structure with MHI = 32 and a replacement cost of $2,600, Repair Option 1 will increase MHI to 92 for a cost of $600,000 Benefit = (92 32)*$2,600,000 = $1,560,000 Benefit/Cost = $1,560,000/ $600,000 = Repair Option 2 will increase MHI to 74 for a cost of $350,000 Benefit = (74 32)*$2,600,000 = $1,092,000 Benefit/Cost = $1,092,000/ $350,000 = Replace Option will increase MHI to 1.00 for a cost of $2,600,000 Benefit = (100 32)*$2,600,000 = $1,768,000 Benefit/Cost = $1,768,000/$2,600,000 =.68 17

18 The Benefits of Using Equity as the Basis for Engineering Decisions $1,200,000 Steel Culvert Depreciation $1,000,000 Current Value of Asset (Equity) $800,000 $600,000 $400,000 $200,000 $- Initial Value ($1M) Decision Residual (Salvage) Value Option 1 Replace with Steel Culvert $1M $(200,000) Age - Years

19 The Benefits of Using Equity as the Basis for Engineering Decisions $1,200,000 Current Value of Asset (Equity) $1,000,000 $800,000 $600,000 $400,000 $200,000 $- $(200,000) Decision Age - Years Slower Rate of Deterioration Option 2 Replace with New Concrete Culvert $1.15M

20 The Benefits of Using Equity as the Basis for Engineering Decisions $1,200,000 $1,000,000 Option 3 Line Culvert $250k Current Value of Asset (Equity) $800,000 $600,000 $400,000 $200,000 $- Decision $(200,000) Age - Years

21 With Equity Curves Simple Life Cycle Analysis is Practical Name Initial Construction Traffic Control Initial Costs Engineering, Inspection, R/W Total Initial Cost Estimated Maintenance Costs Per 10 Year Interval Replace ment Year Present Value (calculated) Option 1 Coated Steel $748,400 $64,500 $187,100 $1,000,000 $4, $1,131,192 Precast Option 2 Concrete $850,240 $87,200 $212,560 $1,150,000 $6, $893,554 Option 3 Steel Liner $190,000 $12,500 $47,500 $250,000 $4, $1,380,666 Discount Rate 1.50% Suggested PE, CEI, R/W Factor 0.25 Steel Liner Option Assumes New Steel Culvert Required in 25 Years 21

22 Similar Effort was Recently Performed on Hampton Roads Bridge Tunnel Approaches using Life Cycle Principles Structure (Fed ID#) Current Status Rehabilitate (Work in 2018) Replace (Work in 2038) Age MHI Current Equity (A) Cost 2018 Post- Repair Value (B) 2048 MHI 2048 Value (C) 2038 Cost = Post-Construct. Value (B) 2048 MHI 2048 Value (C) $48.1 $7.47 $ $41.6 $ $ $83.2 $17.95 $ $76.6 $ $ $77.3 $6.24 $ $84.6 $ $ $51.4 $4.32 $ $44.6 $ $ $71.1 $6.44 $ $64.4 $ $ $67.8 $6.44 $ $64.4 $ $97.9 Σ or Avg $398.9 $48.9 $ $376.1 $ $

23 Present Value Calculation with 20 Year Horizon Option Present Value Comparison - Replace vs. Repair 6 HRBT Approach Bridges - All Values in Millions of 2015 (uninflated) dollars Initial Costs Project Cost Estimated Annual Maintenance Costs Current Value (2016) MHI =.63 Post Repair (pre- Const- ruction) Equity Predicted Values 2048 Lost or Gained Equity per interval Present Repair $49 -$0.4 -$0.6 -$0.8 $399 $606 $561 $516 $376 -$45 -$45 -$140 (293) $ Replace '36-'38 -$645 -$1.1 -$1.9 -$2.4 $399 $395 $360 $322 $568 -$39 -$38 $174 $ (596) Replace or repair all structures. Maintenance costs are applied at year 5 in each interval. All values are expenditures. There are no revenues associated with either option. Lost equity is applied at the end of each 10 year interval Comparison is based solely on value of structures and maintenance needs associated with each option. User costs & other factors not included Value calculated Discount Rate 7.00% 22

24 Using MHI and Other Indices to Select Bridge Projects with a Multi-Objective Prioritization Formula 24

25 Multi-Objective Prioritization Formula Selection of Structures for Intervention Priority = a(if) + b(cf) + c(rf) + d(scf) + e(cef) All five unitless variables have a 0 to 1.0 scale IF = Importance Factor measures the relative importance of each bridge to the overall highway network CF = Condition Factor measures the overall physical condition of each bridge based on the condition of each individual element RF = Risk Factor measures four important risk factors: Redundancy, Scour Susceptibility, Fatigue, and Earthquake vulnerability SCF = Structure Capacity Factor measures the capacity of the structure to convey traffic, including the effects of weight restrictions, waterway adequacy, vertical clearance and deck width CEF = Cost-Effectiveness Factor measures the cost-effectiveness of the required work a, b, c, d, e are coefficients that may be selected to suit the particular evaluation being performed a + b + c + d + e =

26 Multi-Objective Prioritization Formula Selection of Structures for Intervention By separating the five variables users can readily understand why one project has a higher priority than another Coefficients can be selected to align with the programmatic goals of the agency Coefficients currently envisioned for VDOT s Bridge Construction Program: a = 0.30 (Importance) b = 0.25 (Condition) c = 0.15 (Risk) d = 0.10 (Structure Capacity) e = 0.20 (Cost-Effectiveness) 26

27 Importance Factor IF = Importance Factor. Measures relative importance of the structure to the roadway network Uses these variables: Traffic (ADT/Lane) Truck traffic (ADTT/Lane) Predicted future ADT growth Proximity to schools, hospitals and emergency facilities Detour vs. traffic Functional class of roadway 27

28 Condition Factor (CF) Condition is measured using the Modified Health Index (MHI) CF = 1.0 (Modified Health Index/100) MHI is a 0 to 100 measurement of condition MHI value of 100 represents a bridge without defects MHI value of zero represents a bridge that has reached the end of its service life MHI provides an overall condition measurement by weighting each element s condition as a proportion of its relative value to the whole bridge MHI is calculated using element-level data provided during bridge safety inspections, along with element replacement costs 28

29 Risk Factor RF = Risk Factor measures the risk to structures, with an emphasis on redundancy RF = Part A + Part B 1.0 Part A: = 0.75 if one of Scour Critical or Fracture Critical exists = 0.90 if both of Scour Critical and Fracture Critical exists Part B: = 0.10 if one of Seismic Critical or Fatigue Prone Details exists = 0.20 if both of Seismic Critical and Fatigue Prone Details exists 29

30 SCF = Structure Capacity Factor Structure Capacity Factor measures the load and geometric capacity of the structure to convey traffic, including the effects of weight restrictions, waterway adequacy, vertical clearance and deck width SCF =.40(Weight Reduction Factor) +.30(Waterway/Vertical Clearance Factor) +.30(Deck Width Factor) Weight Reduction Factor (WRF) = 0 to 1.0 score measuring ability of structure to carry Fire Trucks, Ambulances, School Buses and Design Vehicles Waterway/Vertical Clearance Factor = 0 to 1.0 score measuring the adequacy of vertical clearance for waterways, railways and trucks Deck Width Factor = 0 to 1.0 score measuring adequacy of deck width vs. need The Weight Reduction Factor is the subject of a forthcoming paper that will be published through the Virginia Transportation Research Council. 30

31 CEF = Cost-Effectiveness Factor Cost-Effectiveness Factor measures the cost-effectiveness of the required work CEF = -2(RC/SRC) +1.3 Max 1.00, Min 0.00 RC = Repair Cost: Initial Prioritization uses Bridge Management System Recommendations. Final Scoring uses refined scope and estimate after prescoping phase SRC = Structure Replacement Cost: Based on statewide replacement cost averages with escalation factors for preliminary engineering, right of way, growth, and construction inspection. Final Scoring may be adjusted using more in-depth cost estimates during pre-scoping phase Note: CEF = 1.00 for ratios of RC/SRC 0.15 CEF = 0.00 for ratios of RC/SRC 0.65 CEF varies linearly from 1.00 to 0.00 as ratio of RC/SRC varies from 0.15 to

32 Examples of CEF Calculations Repair Cost (RC) Structure Replacement Cost (SRC) Ratio (RC/SRC) CEF Score $ 50,000 $ 1,000, $ 150,000 $ 1,000, $ 250,000 $ 1,000, $ 350,000 $ 1,000, $ 367,523 $ 1,000, $ 450,000 $ 1,000, $ 550,000 $ 1,000, $ 650,000 $ 1,000, $ 750,000 $ 1,000, $ 850,000 $ 1,000, $ 950,000 $ 1,000,

33 1.20 CEF Score vs RC/SRC Ratio 1.00 CEF Score CEF Score RC/SRC Ratio

34 Formula- Produced Prioritized List Variables Final Values Bridge # Importance Factor Condition Factor Risk Factor Structure Capacity Factor Cost- Effectiveness Factor Score Rank Scope Estimate for Recommended Scope Estimated Total Replacement Cost Major Restoration $1,652,651 $15,034,241 Replace Superstructure $6,675,231 $13,014, Major Restoration $280,579 $3,435, Major Restoration $67,619 $837, Rehabilitate Culvert $378,938 $769, Replace Bridge $4,957,098 $4,957, Replace Bridge $2,179,301 $2,179, Replace Superstructure $308,190 $1,040, Replace Bridge $335,158 $335, Major Repair $363,855 $3,678, Replace Superstructure $257,366 $924, Replace Deck $1,949,697 $8,663,145 34

35 Thank you for your time and attention Questions??

BRIDGE ALTERNATE STUDY No. 1

BRIDGE ALTERNATE STUDY No. 1 BRIDGE ALTERNATE STUDY No. 1 RURAL STREAM CROSSING Prepared for U. S. Bridge Cambridge, Ohio Prepared by RICHLAND ENGINEERING LIMITED 29 North Park Street, Mansfield, Ohio 44902-1769 419/524-0074 FAX 419/524-1812

More information

LOCAL MAJOR BRIDGE PROGRAM

LOCAL MAJOR BRIDGE PROGRAM LOCAL MAJOR BRIDGE PROGRAM The Local Major Bridge Program provides federal funds to counties and municipal corporations for bridge replacement or bridge major rehabilitation projects. A Local Major Bridge

More information

Improving Bridge Risk and Deterioration Modeling

Improving Bridge Risk and Deterioration Modeling 11 th National Conference on Transportation Asset Management Improving Bridge Risk and Deterioration Modeling Mohammad Dehghani, Caitlin McKinley, Zach Rubin, and Wayne Francisco, GHD Minneapolis, MN July

More information

Revenue Sharing Program Guidelines

Revenue Sharing Program Guidelines Revenue Sharing Program Guidelines For further information, contact Local VDOT Manager or Local Assistance Division Virginia Department of Transportation 1401 East Broad Street Richmond, Virginia 23219

More information

Revenue Sharing Program Guidelines

Revenue Sharing Program Guidelines Revenue Sharing Program Guidelines For further information, contact Local VDOT Manager or Local Assistance Division Virginia Department of Transportation 1401 East Broad Street Richmond, Virginia 23219

More information

Analysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs

Analysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs Analysis of Past NBI Ratings for Predicting Future Bridge System Preservation Needs Xiaoduan Sun, Ph.D., P.E. Civil Engineering Department University of Louisiana at Lafayette P.O. Box 4229, Lafayette,

More information

Deck Preservation Strategies with a Bridge Management System. Paul Jensen Montana Department of Transportation

Deck Preservation Strategies with a Bridge Management System. Paul Jensen Montana Department of Transportation Deck Preservation Strategies with a Bridge Management System Paul Jensen Montana Department of Transportation Email : pjensen@mt.gov Development Of A Roadmap Definitions Outcomes Culture Models Performance

More information

LCC Methodology. Håkan Sundquist Structural Design and Bridges KTH. ETSI Methodology 1

LCC Methodology. Håkan Sundquist Structural Design and Bridges KTH. ETSI Methodology 1 LCC Methodology Håkan Sundquist Structural Design and Bridges KTH 1 There are many requirements on a bridge 2 The classic task 3 The classic bridge design task 4 LCC optimization 5 LCC/Construction cost

More information

Evaluating Different Bridge Management Strategies Using The Bridge Management Research System (bmrs)

Evaluating Different Bridge Management Strategies Using The Bridge Management Research System (bmrs) Purdue University Purdue e-pubs Open Access Theses Theses and Dissertations 2013 Evaluating Different Bridge Management Strategies Using The Bridge Management Research System (bmrs) Timothy Paul Stroshine

More information

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM

BHJTS TRANSPORTATION IMPROVEMENT PROGRAM FEDERAL, STATE & LOCAL PROJECTS 2016 THROUGH 2019 FOUR-YEAR SHORT RANGE PROGRAM TOTAL PROJECT ESTIMATE ($) STATE ALLOCATION CODE (SAC) FUND TYPE ENCUMBERED FROM BEFORE FY 2011 PE/RW PRIOR TO FY 2016 LOCAL MATCH LOCAL LABOR STATE LABOR FED LABOR & TSKF LINE ITEM # ST. LINE ITEM

More information

NCHRP Consequences of Delayed Maintenance

NCHRP Consequences of Delayed Maintenance NCHRP 14-20 Consequences of Delayed Maintenance Recommended Process for Bridges and Pavements prepared for NCHRP prepared by Cambridge Systematics, Inc. with Applied Research Associates, Inc. Spy Pond

More information

UNIFIED TRANSPORTATION PROGRAM

UNIFIED TRANSPORTATION PROGRAM 2002 UNIFIED TRANSPORTATION PROGRAM Blank Page SUMMARY OF CATEGORIES CATEGORIES NUMBER, NAME AND YEAR ESTABLISHED PROGRAMMING AUTHORITY FUNDING BANK BALANCE (Yes/) RESPONSIBLE ENTITY RANKING INDEX OR ALLOCATION

More information

Prioritising bridge replacements

Prioritising bridge replacements Prioritising bridge replacements Andrew Sonnenberg, National Bridge Engineering Manager, Pitt&Sherry ABSTRACT Road and Rail managers own a variety of assets which are aging and will need replacement. There

More information

Genesee-Finger Lakes Regional Bridge Network Needs Assessment and Investment Strategy

Genesee-Finger Lakes Regional Bridge Network Needs Assessment and Investment Strategy Genesee-Finger Lakes Regional Bridge Network Needs Assessment and Investment Strategy prepared for Genesee Transportation Council prepared by Cambridge Systematics, Inc. February 2015 GTC s Commitment

More information

Life-Cycle Cost Analysis: A Practitioner s Approach

Life-Cycle Cost Analysis: A Practitioner s Approach Life-Cycle Cost Analysis: A Practitioner s Approach FHWA Office of Performance Management 1 Topics Fundamentals of Economic Analysis Tools and resources What to do now 2 Learning Objectives By the end

More information

AVERAGE OF BID ITEMS ENGINEERS ESTIMATE

AVERAGE OF BID ITEMS ENGINEERS ESTIMATE ROADWAY 1 Mobilization 1 LS $ 990,048.50 $ 80,000.00 $ 880,000.00 $ 880,000.00 $ 950,000.00 $ 950,000.00 $ 967,510.00 $ 967,510.00 $ 1,162,684.00 $ 1,162,684.00 2 Maintenance of Traffic ( incl. Pedestrian

More information

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade. Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding

More information

Asset Management Plan

Asset Management Plan 2016 Asset Management Plan United Counties of Prescott and Russell 6/1/2016 Preface This Asset Management Plan is intended to describe the infrastructure owned, operated, and maintained by the United Counties

More information

HigHway Carrying Bridges in new Jersey

HigHway Carrying Bridges in new Jersey Highway Carrying Bridges in New Jersey Final Report October 2007 Table of Contents Executive Summary 2 I. Introduction 3 II. Findings Current Bridge Condition 4 Total Bridge Inventory 4 Age of Bridges

More information

FRAMEWORK FOR OBJECTIVE RISK ASSESSMENT IN BRIDGE MANAGEMENT. Word count: 5,646 words text + 5 tables/figures x 250 words (each) = 6,896 words

FRAMEWORK FOR OBJECTIVE RISK ASSESSMENT IN BRIDGE MANAGEMENT. Word count: 5,646 words text + 5 tables/figures x 250 words (each) = 6,896 words FRAMEWORK FOR OBJECTIVE RISK ASSESSMENT IN BRIDGE MANAGEMENT Paul D. Thompson (corresponding author) Consultant 17035 NE 28 th Place, Bellevue, WA 98008 USA Tel: 425-224-5443; Fax: 888-261-3658; Email:

More information

Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION

Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION Funding Allocations Routine State $ 166 Million Resurfacing Federal $ 260 Million

More information

PART II GUIDANCE MANUAL

PART II GUIDANCE MANUAL PART II GUIDANCE MANUAL Part II of NCHRP Report 483 (the Guidance Manual) is essentially the original text as submitted by the research agency and has not been edited by TRB. Page numbering for Part II

More information

Asset Management Ruminations. T. H. Maze Professor of Civil Engineering Iowa State University

Asset Management Ruminations. T. H. Maze Professor of Civil Engineering Iowa State University Asset Management Ruminations T. H. Maze Professor of Civil Engineering Iowa State University Why Transportation Asset Management Has Nothing to Do With Systems to Manage Individual Transportation Assets

More information

Forecasting Optimum Bridge Management Decisions and Funding Needs on the Basis of Economic Analysis

Forecasting Optimum Bridge Management Decisions and Funding Needs on the Basis of Economic Analysis 4 TRANSPORTATION RESEARCH RECORD 126 Forecasting Optimum Bridge Management Decisions and Funding Needs on the Basis of Economic Analysis CHWEN-JINQ CHEN AND DAVID w. JOHNSTON An analytic method is presented

More information

1.0 CITY OF HOLLYWOOD, FL

1.0 CITY OF HOLLYWOOD, FL 1.0 CITY OF HOLLYWOOD, FL PAVEMENT MANAGEMENT SYSTEM REPORT 1.1 PROJECT INTRODUCTION The nation's highways represent an investment of billions of dollars by local, state and federal governments. For the

More information

City of Glendale, Arizona Pavement Management Program

City of Glendale, Arizona Pavement Management Program City of Glendale, Arizona Pavement Management Program Current Year Plan (FY 2014) and Five-Year Plan (FY 2015-2019) EXECUTIVE SUMMARY REPORT December 2013 TABLE OF CONTENTS TABLE OF CONTENTS I BACKGROUND

More information

LETTING : CALL : 056 COUNTIES : MILLE LACS

LETTING : CALL : 056 COUNTIES : MILLE LACS S T A T E O F M I N N E S O T A PAGE : -1 NUMBER OF DAYS: 0 BRIDGE COUNT : 3 CONTRACT DESCRIPTION : GRADING, BIT PAVING & SURFACING, ROUNDABOUT, AND BRIDGES. CONTRACT LOCATION: LOCATED ON T.H. 95 AT THE

More information

Examples of Decision Support Using Pavement Management Data

Examples of Decision Support Using Pavement Management Data Examples of Decision Support Using Pavement Management Data John Coplantz, PE Pavement Management Engineer Oregon Department of Transportation October 27, 2016 Strategic Network (Tactical) Project (Operational)

More information

RISK ASSESSMENT FOR BRIDGE MANAGEMENT SYSTEMS

RISK ASSESSMENT FOR BRIDGE MANAGEMENT SYSTEMS RISK ASSESSMENT FOR BRIDGE MANAGEMENT SYSTEMS Paul D. Thompson Consultant 17035 NE 28 th Place, Bellevue, WA 98008 USA Tel: 425-224-5443; Fax: 888-261-3658; Email: pdt@pdth.com Patricia Bye, 215-262-3458,

More information

Bridge Asset Management or IT S THE MONEY DUMMY

Bridge Asset Management or IT S THE MONEY DUMMY Bridge Asset Management or IT S THE MONEY DUMMY Chris Keegan, P. E. Bridge Maintenance Engineer Region Operations Engineer. Secretary of Transportation Roger Millar WBPP, Denver CO May, 2017 Asset Management

More information

Highway Engineering-II

Highway Engineering-II Highway Engineering-II Chapter 7 Pavement Management System (PMS) Contents What is Pavement Management System (PMS)? Use of PMS Components of a PMS Economic Analysis of Pavement Project Alternative 2 Learning

More information

OKLAHOMA TURNPIKE AUTHORITY

OKLAHOMA TURNPIKE AUTHORITY PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 250,000.00 $250,000.00 $ 240,978.56 $ 240,978.56 260,000.00 $ 260,000.00 201(A) CLEARING & GRUBBING LSUM 1.00 $ 30,000.00 $30,000.00 $ 17,188.20

More information

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES GUIDANCE NOTES Rev 3 August 2017 INDEX Section Page 1 Introduction to Commuted Sums 3 2 When are Commuted

More information

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES

ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES ADEPT NATIONAL BRIDGES GROUP COMMUTED SUMS FOR THE RELIEF OF MAINTENANCE AND RECONSTRUCTION OF BRIDGES GUIDANCE NOTES Rev 1 January 2016 INDEX Section Page 1 Introduction to Commuted Sums 3 2 When are

More information

Bridges and Structures. FHWA Updates. AASHTO (T-18) Technical Committee for Bridge Management, Evaluation, and Rehabilitation.

Bridges and Structures. FHWA Updates. AASHTO (T-18) Technical Committee for Bridge Management, Evaluation, and Rehabilitation. FHWA Updates AASHTO (T-18) Technical Committee for Bridge Management, Evaluation, and Rehabilitation June 13, 2017 Talking Points 1. Regulation Update 2. Coding Guide Update (SNBI) 3. NBIS & NTIS Compliance

More information

10-Year Capital Highway Investment Plan DRAFT

10-Year Capital Highway Investment Plan DRAFT 10-Year Capital Highway Investment Plan DRAFT 2018-2027 DRAFT AUGUST 2017 1 Table of Contents PURPOSE OF 10-YEAR CAPITAL HIGHWAY INVESTMENT PLAN... 1 This page intentionally left blank. SUMMARY OF INVESTMENT

More information

NJDOT Standards for CoMBIS

NJDOT Standards for CoMBIS NJDOT Standards for CoMBIS 1. General NJDOT Policies: The County must plan on how to implement the CoMBIS Workflow as defined by the System into their current in-house process for report review and Priority

More information

Maximizing Return on Investment Utilizing a Bridge Depreciation Model

Maximizing Return on Investment Utilizing a Bridge Depreciation Model Maximizing Return on Investment Utilizing a Bridge Depreciation Model H.S. Kleywegt, P.Eng. Keystone Bridge Management Corp., Kingston, ON, Canada ABSTRACT: The challenge facing bridge managers is how

More information

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E.

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. Life Cycle Cost Analysis in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. What is it? Economic procedure That uses

More information

Opportunities for Low-Volume Roads

Opportunities for Low-Volume Roads A5002: Committee on Low-Volume Roads Chairman: Gerald T. Coghlan for Low-Volume Roads GERALD T. COGHLAN, U.S. Department of Agriculture Forest Service The coming of the new millennium provides an excellent

More information

CONTRACT TIME DETERMINATION

CONTRACT TIME DETERMINATION CONTRACT TIME DETERMINATION MISSOURI DEPARTMENT OF TRANSPORTATION March 15, 2004 DEFINITIONS Calendar Day: Any day shown on the calendar beginning and ending at midnight. Working Day: A calendar day during

More information

Hosten, Chowdhury, Shekharan, Ayotte, Coggins 1

Hosten, Chowdhury, Shekharan, Ayotte, Coggins 1 Hosten, Chowdhury, Shekharan, Ayotte, Coggins 1 USE OF VDOT S PAVEMENT MANAGEMENT SYSTEM TO PROACTIVELY PLAN AND MONITOR PAVEMENT MAINTENANCE AND REHABILITATION ACTIVITIES TO MEET THE AGENCY S PERFORMANCE

More information

Developing a Transportation Asset Management Plan

Developing a Transportation Asset Management Plan Developing a Transportation Asset Management Plan A Workshop for the NCDOT July 2, 2015 Conducted By: Katie Zimmerman, P.E., Applied Pavement Technology, Inc. (APTech) And Lacy Love, Volkert, Inc. Workshop

More information

Programed Totals $39,761 $35,676 $75,437 $73,111 $2,326 $0 $17,109 $17,109 $17,109 $0 $0 $14,580 $14,580 $14,580 $0

Programed Totals $39,761 $35,676 $75,437 $73,111 $2,326 $0 $17,109 $17,109 $17,109 $0 $0 $14,580 $14,580 $14,580 $0 WCOG Managed WHATCOM COUNCIL OF GOVERNMENTS 2014 Transportation Improvement Program Amendment #1 (1401) MPO Financial Feasibility Summary Anticipated Federal Funding* & Programmed Expenditures (in Thousands)

More information

final plan CDOT's Risk-Based Asset Management Plan Colorado Department of Transportation Cambridge Systematics, Inc. Larry Redd, P.E.

final plan CDOT's Risk-Based Asset Management Plan Colorado Department of Transportation Cambridge Systematics, Inc. Larry Redd, P.E. final plan prepared for Colorado Department of Transportation prepared by Cambridge Systematics, Inc. with Larry Redd, P.E. December 9, 2013 final plan CDOT's Risk-Based Asset Management Plan prepared

More information

EXCELLENCE INNOVATION SERVICE VALUE

EXCELLENCE INNOVATION SERVICE VALUE Incorporation of Geotechnical Elements as an Asset Class within Transportation Asset Management and Development of Risk Based and Life Cycle Cost Performance Strategies by Mark Vessely, P.E. Shannon &

More information

Norfolk County Asset Management Plan Roads

Norfolk County Asset Management Plan Roads Norfolk County Asset Management Plan Roads An overview of the County s Asset Management Practices based on the Ontario Ministry of Infrastructure s Building Together Initiative Prepared for: Norfolk County

More information

ABSTRACT STRATEGIES. Adel Abdel-Rahman Al-Wazeer, Doctor of Philosophy, 2007

ABSTRACT STRATEGIES. Adel Abdel-Rahman Al-Wazeer, Doctor of Philosophy, 2007 ABSTRACT Title of Dissertation: RISK-BASED BRIDGE MAINTENANCE STRATEGIES Adel Abdel-Rahman Al-Wazeer, Doctor of Philosophy, 2007 Directed By: Professor Bilal M. Ayyub, Department of Civil and Environmental

More information

8 FINANCIAL PLAN AND INVESTMENT STRATEGIES: SUPPLEMENTAL INFORMATION

8 FINANCIAL PLAN AND INVESTMENT STRATEGIES: SUPPLEMENTAL INFORMATION Chapter 8 FINANCIAL PLAN AND INVESTMENT STRATEGIES: SUPPLEMENTAL INFORMATION CHAPTER 8 FINANCIAL PLAN AND INVESTMENT STRATEGIES: SUPPLEMENTAL INFORMATION PAGE 86 FINANCIAL PLAN AND INVESTMENT STRATEGIES:

More information

Projected Funding & Highway Conditions

Projected Funding & Highway Conditions Projected Funding & Highway Conditions Area Commission on Transportation Gary Farnsworth ODOT Interim Region 4 Manager March, 2011 Overview ODOT is facing funding reductions that will require new strategies

More information

Emergency Relief Program. Ammon Heier, FHWA ER Coordinator

Emergency Relief Program. Ammon Heier, FHWA ER Coordinator Emergency Relief Program Ammon Heier, FHWA ER Coordinator What to Remember Time is of the Essence - Urgency Good documentation is crucial Early and Ongoing Communication If you don t know, ask. Emergency

More information

A Stochastic Approach for Pavement Condition Projections and Budget Needs for the MTC Pavement Management System

A Stochastic Approach for Pavement Condition Projections and Budget Needs for the MTC Pavement Management System A Stochastic Approach for Pavement Condition Projections and Budget Needs for the MTC Pavement Management System Rafael Arturo Ramirez-Flores Ph. D. Candidate Carlos Chang-Albitres Ph.D., P.E. April 16,

More information

PART A ROADWAY - BASE BID

PART A ROADWAY - BASE BID May 10, 2016 HEB-MC-61 PART A ROADWAY - BASE BID 202(A) - UNCLASSIFIED EXCAVATION - CY 34,946.00 $ 6.00 209,676.00 $ 7.98 $ 278,869.08 205(A) - TYPE A-SALVAGED TOPSOIL - LSUM 1.00 $ 22,500.00 $ 22,500.00

More information

Project Summary Project Name: Route 37 Corridor Safety Sweep Project Number:

Project Summary Project Name: Route 37 Corridor Safety Sweep Project Number: Project Summary This project summary page details the benefit cost analysis (BCA) for the Route 37 Corridor Safety Sweep Project. A BCA provides estimates of the anticipated benefits that are expected

More information

Asset Sustainability Index

Asset Sustainability Index Asset Sustainability Index A Beta Version Using Existing State Data Conference Feb. 18, 2012 Gordon Proctor Conference Feb. 18, 2013 1 Project Scope Describe Australian sustainability indices Can we replicate

More information

A Financial Impact Assessment of LD 1725: Stream Crossings

A Financial Impact Assessment of LD 1725: Stream Crossings A Financial Impact Assessment of LD 1725: Stream Crossings Prepared by: The New England Environmental Finance Center For the Maine Department of Transportation Office of Environmental Planning Edmund S.

More information

Pavement Preservation

Pavement Preservation Road Foreman Meeting West Windsor, Vermont March 24, 2015 Dan Patenaude, P.E. Hometown: Chester, VT Pavement Preservation Your Key to Pavement Management Success Since 1957 Corporate Headquarters Braintree,

More information

COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013

COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013 COUNTY OF LAMBTON ASSET MANAGEMENT PLAN 2013 Pictures Key Front Cover Top Row 1) Administration Building Second Row, left to right 2) Brigden EMS Station 3) Judith & Norman Alix Art Gallery Third row,

More information

UCI Legislative Update. May 26, 2016 Julie Brown Local Assistance Division

UCI Legislative Update. May 26, 2016 Julie Brown Local Assistance Division UCI Legislative Update May 26, 2016 Julie Brown Local Assistance Division Legislative Updates HB 1402 (2015) Payments to City of Richmond for movinglanes converted to bicycle lanes; also required study.

More information

MICHIGAN STATEWIDE GPA GUIDANCE 2017

MICHIGAN STATEWIDE GPA GUIDANCE 2017 Introduction Federal regulation 23 CFR 450.324 (f) states projects that are not considered to be of appropriate scale for individual identification in a given program year may be grouped by function, work

More information

Scope Criterium Engineers was hired to update a reserve study for the Reston Association. The specific tasks included: Review the previous study perfo

Scope Criterium Engineers was hired to update a reserve study for the Reston Association. The specific tasks included: Review the previous study perfo Scope Criterium Engineers was hired to update a reserve study for the Reston Association. The specific tasks included: Review the previous study performed by others Consult with Reston Association management

More information

I-64 Capacity Improvements Segment III Initial Financial Plan

I-64 Capacity Improvements Segment III Initial Financial Plan I-64 Capacity Improvements Segment III Initial Financial Plan State Project # 0064-965-229/0064-099-229 P101, R201, C501, B638, B639, B640, B641, B642, B643, D609, D610, D611 Federal # NHPP-064-3(498)/

More information

Chapter 6: Financial Resources

Chapter 6: Financial Resources Chapter 6: Financial Resources Introduction This chapter presents the project cost estimates, revenue assumptions and projected revenues for the Lake~Sumter MPO. The analysis reflects a multi-modal transportation

More information

Assets Infrastructure

Assets Infrastructure Assets Infrastructure Tabled Documents 13 September 2018 Item 8 Item 11 Chairs Report Options and costs of retaining the existing Mangaweka Bridge Report Subject: To: From: Mangaweka Bridge Replacement

More information

Valuing Transportation Assets at the CO DOT

Valuing Transportation Assets at the CO DOT William Johnson Ermias Weldemicael, PhD Webinar Presentation Value of Transportation October 28, 2016 Valuing Transportation Assets at the CO DOT Asset Valuation Introduction Agenda Introduction Overview

More information

Military Highway Continuous Flow Intersection (CFI) Initial Financial Plan

Military Highway Continuous Flow Intersection (CFI) Initial Financial Plan Military Highway Continuous Flow Intersection (CFI) Initial Financial Plan State Project Number(s): 0013-122-V03, 0165-122-V04, 0165-122-181 UPC(s): 9783, 1765, 84243 1 Table of Contents 1. Project Description...

More information

2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction)

2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) 2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction) Project Information The Glen at Widefield Filing No. 9 PDD File: SF-185 9/25/2018 Project Name Section 1 - Grading and Erosion

More information

AVGPR14.Y01 2/11/2014 DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 12/01/13 AND 12/31/13 BY ITEM GROUP

AVGPR14.Y01 2/11/2014 DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 12/01/13 AND 12/31/13 BY ITEM GROUP AVERAGE BID PRICES FOR AWARDED PROJECTS 14:48 Tuesday, February 11, 2014 1 2011 2011.601/00003 CONSTRUCTION SURVEYING LS 1 $19 $18,500.00 1 2013 2013.602/00022 ROAD/WEATHER SENSOR AND CABLE EACH 3 $32

More information

Modeling of Life Cycle Alternatives in the National Bridge Investment Analysis System (NBIAS) Prepared by: Bill Robert, SPP Steve Sissel, FHWA

Modeling of Life Cycle Alternatives in the National Bridge Investment Analysis System (NBIAS) Prepared by: Bill Robert, SPP Steve Sissel, FHWA Modeling of Life Cycle Alternatives in the National Bridge Investment Analysis System (NBIAS) Prepared by: Bill Robert, SPP Steve Sissel, FHWA TRB International Bridge & Structure Management Conference

More information

Development of a Priority Ranking System for Bridge Rehabilitation and Replacement

Development of a Priority Ranking System for Bridge Rehabilitation and Replacement Transportation Kentucky Transportation Center Research Report University of Kentucky Year 1989 Development of a Priority Ranking System for Bridge Rehabilitation and Replacement Theodore Hopwood II Vishwas

More information

Residential Street Improvement Plan

Residential Street Improvement Plan Residential Street Improvement Plan Introduction Aging infrastructure, including streets, is a nationwide problem and it is one of the biggest challenges facing many cities and counties throughout the

More information

Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE

Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE Agenda Page # 1 CEDAR HAMMOCK COMMUNITY DEVELOPMENT DISTRICT FEBRUARY 12, 2018 AGENDA PACKAGE Cedar Hammock Community Development District Inframark, Infrastructure Management Services 210 N. University

More information

Instructions for Completing the Annual Road and Street Finance Report

Instructions for Completing the Annual Road and Street Finance Report Instructions for Completing the Annual Road and Street Finance Report Additional information you wish to submit may be attached to the report on 8.5" by 11" paper. Please round all amounts up or down to

More information

Effective Use of Pavement Management Programs. Roger E. Smith, P.E., Ph.D. Zachry Department of Civil Engineering Texas A&M University

Effective Use of Pavement Management Programs. Roger E. Smith, P.E., Ph.D. Zachry Department of Civil Engineering Texas A&M University Effective Use of Pavement Management Programs Roger E. Smith, P.E., Ph.D. Zachry Department of Civil Engineering Texas A&M University 1 Pavement Management Is A Decision Making Process Effective Pavement

More information

Maintenance Management of Infrastructure Networks: Issues and Modeling Approach

Maintenance Management of Infrastructure Networks: Issues and Modeling Approach Maintenance Management of Infrastructure Networks: Issues and Modeling Approach Network Optimization for Pavements Pontis System for Bridge Networks Integrated Infrastructure System for Beijing Common

More information

Hydrology 4410 Class 29. In Class Notes & Exercises Mar 27, 2013

Hydrology 4410 Class 29. In Class Notes & Exercises Mar 27, 2013 Hydrology 4410 Class 29 In Class Notes & Exercises Mar 27, 2013 Log Normal Distribution We will not work an example in class. The procedure is exactly the same as in the normal distribution, but first

More information

RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO Item Description Est. Qty. Units Unit Price

RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO Item Description Est. Qty. Units Unit Price 2. BID SCHEDULE RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO. 7046 To the Honorable Mayor and City Council of the City of Hesperia: Schedule of prices to construct the Ranchero Road and BNSF

More information

Financial Model Update Public Presentation July 9, 2015

Financial Model Update Public Presentation July 9, 2015 Financial Model Update Public Presentation July 9, 2015 BBP financial model developed/refined over 10+ years Public updates Executing on the model First model created as part of initial park planning:

More information

Incorporating Climate and Extreme Weather Risk in Transportation Asset Management. Michael Meyer and Michael Flood WSP Parsons Brinckerhoff

Incorporating Climate and Extreme Weather Risk in Transportation Asset Management. Michael Meyer and Michael Flood WSP Parsons Brinckerhoff Incorporating Climate and Extreme Weather Risk in Transportation Asset Management Michael Meyer and Michael Flood WSP Parsons Brinckerhoff 1. Define Scope 2. Assess & Address Climate Risk 3. Integrate

More information

REPLACEMENT OF MERCER COUNTY BRIDGE

REPLACEMENT OF MERCER COUNTY BRIDGE ADDENDUM NO. ONE Notice is hereby given that on April 26, 2019 at 11:00 AM (Prevailing time), sealed proposals will be opened and read in public by the Purchasing Department in the Mercer County McDade

More information

Financial Model Update Public Presentation July 9, 2015

Financial Model Update Public Presentation July 9, 2015 Financial Model Update Public Presentation July 9, 2015 BBP financial model developed/refined over 10+ years Public updates Executing on the model First model created as part of initial park planning:

More information

RESERVE STUDY LEVEL II UPDATE WITH VISUAL SITE INSPECTION

RESERVE STUDY LEVEL II UPDATE WITH VISUAL SITE INSPECTION RESERVE STUDY LEVEL II UPDATE WITH VISUAL SITE INSPECTION Prepared for: WANDERMERE ESTATES HOMEOWNER S ASSOCIATION Prepared by: CRITERIUM-PFAFF ENGINEERS 12128 N. DIVISION ST. #200 SPOKANE, WA 99218 (509)

More information

Manor Township, Lancaster County, PA Zoning Permit Application ( section 702) App. number App. date

Manor Township, Lancaster County, PA Zoning Permit Application ( section 702) App. number App. date Manor Township, Lancaster County, PA Zoning Permit Application ( section 702) App. number App. date 1. General Information Name of Applicant Address Telephone No. Cell No. Fax No. Name of Landowner of

More information

Year Tax Supported Capital Budget Forecast Investing In Welland

Year Tax Supported Capital Budget Forecast Investing In Welland 2018-2027 10 Year Tax Supported Capital Budget Forecast Investing In Welland Budget Review Committee Meeting October 16, 2017 1 Plan for 2018 Projected for 9 years (2019-2027) Budget respects Council s

More information

Engineer's Preliminary Estimate - 100% Submittal

Engineer's Preliminary Estimate - 100% Submittal EA 284700 1 070010 PROGRESS SCHEDULE (CRITICAL PATH) LS 1 $ 15,000 $ 15,000 2 071325 TEMPORARY FENCE (TYPE ESA) M 1250 $ 10 $ 12,500 3 074019 PREPARE STORM WATER POLLUTION PREVENTION PLAN LS 1 $ 7,000

More information

SUBDIVISION IMPROVEMENTS AGREEMENT

SUBDIVISION IMPROVEMENTS AGREEMENT SUBDIVISION IMPROVEMENTS AGREEMENT THIS AGREEMENT, made between GLEN DEVELOPMENT COMPANY, hereinafter called the "Subdivider," and El Paso County by and through the Board of County Commissioners of El

More information

Glossary Candidate Roadway Project Evaluation Form Project Scoring Sheet... 17

Glossary Candidate Roadway Project Evaluation Form Project Scoring Sheet... 17 Kitsap County Public Works Transportation Project Evaluation System 2017 Table of Contents Introduction... 1 Four-Tier system... 4 Tier 1 - Transportation Improvement Program (TIP)... 4 Tier 2 Prioritized

More information

PROJECT EVALUATION FORM

PROJECT EVALUATION FORM PROJECT EVALUATION FORM Program Year 33 (2018-2019) (Revised 2/6/18) This form is to be used for both SCIP and LTIP projects. Remember that only transportation projects (roads, bridges, and culverts) are

More information

The City of Owen Sound Asset Management Plan

The City of Owen Sound Asset Management Plan The City of Owen Sound Asset Management Plan December 013 Adopted by Council March 4, 014 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY... 1 INTRODUCTION....1 Vision.... What is Asset Management?....3 Link to

More information

AECOM Redoubt Road - Mill Road Corridor Project Appendix B Cost Estimate Revision B 20-Jul-2014 Prepared for Auckland Transport Co No.: N/A Item Description Unit QTY Rates $ Alternative Alignment - Option

More information

Emergency Relief Program

Emergency Relief Program Chapter 33 Emergency Relief Program This chapter provides information and instructions on procedures applicable to emergency projects funded by FHWA under the Emergency Relief (ER) Program. Agencies should

More information

GASB Statement No. 34. GASB Statement No. 34. GASB Statement No. 34. GASB Statement No. 34. GASB Statement No. 34 the basics

GASB Statement No. 34. GASB Statement No. 34. GASB Statement No. 34. GASB Statement No. 34. GASB Statement No. 34 the basics GASB Statement No. 34 Indiana LTAP Annual Road School Conference Purdue University West Lafayette, Indiana March 11, 2004 GASB Statement No. 34 Summary of Capital Asset and General Infrastructure Accounting

More information

OKLAHOMA TURNPIKE AUTHORITY

OKLAHOMA TURNPIKE AUTHORITY PART A - BASE BID 106 QUALITY CONTROL & ACCEPTANCE LSUM 1.00 $ 70,000.00 $70,000.00 $ 15,735.00 $ 15,735.00 $ 60,000.00 $ 60,000.00 $ 25,000.00 $ 25,000.00 $ 20,000.00 $ 20,000.00 201(A) CLEARING & GRUBBING

More information

HIGHWAY SAFETY IMPROVEMENT PROGRAM (HSIP)

HIGHWAY SAFETY IMPROVEMENT PROGRAM (HSIP) HSIP GUIDEBOOK & APPLICATION FORM HIGHWAY SAFETY IMPROVEMENT PROGRAM (HSIP) Greater Minnesota Solicitation for District Projects State Fiscal Years 2019, 2020, 2021 and 2022 September 2017 2017 HSIP Solicitation

More information

Au stra li an Br idge Inspe cti on Pro ce sses

Au stra li an Br idge Inspe cti on Pro ce sses Number of structures Au stra li an Br idge Inspe cti on Pro ce sses by Andrew Sonnenberg, Bridge Engineering Manager, pitt&sherry Paper presented at the 2014 Small Bridges Conference pitt&sherry has undertaken

More information

Hazim M Abdulwahid, MSC, MBA Hazim Consulting

Hazim M Abdulwahid, MSC, MBA Hazim Consulting Road Map for Establishing Pavement Maintenance Management System on the Strategic Level 13 th International O&M Conference in the Arab Countries,17-19 Nov 2015 Hazim M Abdulwahid, MSC, MBA Hazim Consulting

More information

Agriculture, Road Conditions, and Road Funding. Farm Policy Study Group December 6, 2016

Agriculture, Road Conditions, and Road Funding. Farm Policy Study Group December 6, 2016 Agriculture, Road Conditions, and Road Funding Farm Policy Study Group December 6, 2016 Charge Estimate the spending gap for local road and bridge rehab for 20 years Needs Spending Gap Identify potential

More information

Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee

Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee Managing Change, Challenges & Other Things Malcolm T. Kerley, P.E. Chief Engineer, Virginia Department of Transportation Chair, AASHTO Subcommittee on Bridges & Structures April 19, 2010 1 Topics VDOT

More information

Asset Management. Linking Levels of Service and Lifecycle Management Strategies Andrew Grunda Peter Simcisko

Asset Management. Linking Levels of Service and Lifecycle Management Strategies Andrew Grunda Peter Simcisko Asset Management Linking Levels of Service and Lifecycle Management Strategies Andrew Grunda Peter Simcisko 1 Introduction Topics that we will address today Review of Ontario Regulation 588/17 Defining

More information

City of La Habra Heights. Benefit Assessment Districts. June 6, Presented by Pablo Perez, Director

City of La Habra Heights. Benefit Assessment Districts. June 6, Presented by Pablo Perez, Director City of La Habra Heights Benefit Assessment Districts June 6, 2016 Presented by Pablo Perez, Director 1 BENEFIT ASSESSMENT DISTRICTS Proposition 218 Defines Special Benefit as Particular and distinct benefit

More information