Actualtests.CCE-CCC.100 questions

Size: px
Start display at page:

Download "Actualtests.CCE-CCC.100 questions"

Transcription

1 Actualtests.CCE-CCC.100 questions Number: CCE-CCC Passing Score: 800 Time Limit: 120 min File Version: CCE-CCC Certified Cost Consultant (CCC)/Certified Cost Engineer (CCE) It was one and only which took me towards the biggest success without finding too much issues or worries in any way. It guided me step by step through the course. After studying for a month using it I achieved the highest in the whole city It offers easy understanding exam guide so that anyone can pass IT exam without any hesitation. This was good opportunity for me to grab exam certification with ease and for guide I did not have to go any further away it was just like that it was at my door step. Its magic did work on me as I passed exam with superb score. It has very mesmerizing patterned guidance. It gives you an easy but detailed review of the entire syllabus and the best thing is that their materials are designed as such so as to make you retain the maximum amount of course.

2 Exam A QUESTION 1 What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal. A. Engineer B. Alternate C. Project Manager D. Agent /Reference: : QUESTION 2 Budgeted cost of work scheduled is all of the following except: A. Total costs incurred in accomplishing work in a given-time period B. Baseline for performance measurement C. Sum of the budgets for work scheduled D. Includes portion of the budget for level-of-effort work /Reference: : QUESTION 3 Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities) A. ACWP/BCWS B. BCWS/BCWP C. ACWP/BCWP D. BCWP/ACWP /Reference: : QUESTION 4 is the application of total resources ($-workers-supports) and activity durations of the logic diagram. A. Planning B. Forecasting C. Scheduling D. Modeling Correct Answer: C

3 /Reference: : QUESTION 5 is defined as covering work whose component activities are less defined and whose interrelationships are conditional. A. Soft logic B. Hard logic C. Deductive logic D. Inductive logic /Reference: right answer. QUESTION 6 A work breakdown structure (WBS) is developed because: A. It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework. B. It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans C. It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup D. It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence Correct Answer: B /Reference: : QUESTION 7 Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is: A. Activity ID B. WBS Code C. Resource D. Account number

4 /Reference: : QUESTION 8 The purpose of a communication must be understood by if the message is to be clear to the A. Workers; management B. The speaker; the receiver C. Management; workers D. The receiver; the speaker Correct Answer: C /Reference: : QUESTION 9 Meetings require: A. Goals, an agenda, preparation, relevant discussions, support for your actions and to consider the total physical and human setting of the meeting B. Goals, an agenda, preparation, conclusions, control and conversations that are relevant C. Goals, an agenda, preparation, control, good listening skills and relevant discussions D. Goals, an agenda, flipchart, computer projector, laser pointer and consulting with others where appropriate Correct Answer: B /Reference: : QUESTION 10 Some of the principles of good communication are: A. Seek to clarify your ideas before communicating; examine the true purpose of each communication; consider the total physical and human setting whenever you communicate; be mindful, while you communicate, of the overtones as well as the basic content of the message B. Tell the other person what to do; give insincere praise; psychoanalyze the other person; make light of a serious problem; do not gain the trust of anyone; always have a hidden agenda C. Use short words; avoid jargon; avoid acronyms and abbreviations; use complete sentences; have a beginning, middle and end; be accurate; be interested in what topic is being communicated D. The social process by which people in a specific situation construct meaning using symbolic behavior Correct Answer: C /Reference: : QUESTION 11 The written word is often more useful than the spoken. Guidelines for writing include:

5 A. Use short sentences; use short words; avoid jargon and abbreviations; use complete sentences; stick to one idea per paragraph; have a beginning, middle and end; be accurate B. Organize the background information; state the problem list the options or alternatives; state the recommendation (s); conclude and summarize with why the recommendation is the best way to proceed C. Follow an outline; allow some time for "cooling" after compiling the draft before revising; when revising, allow plenty of time for several sessions D. Explain, report, describe, clarify, define and demonstrate Correct Answer: B /Reference: best suitable answer. QUESTION 12 The four steps to writing are: A. Introduction, paragraph, conclusion, works cited B. Start, write, complete, revise C. Abstract, body conclusion, bibliography D. Plan, write, cool, revise /Reference: : QUESTION 13 Listening to what is being said by all members of a group or audience and then summarizing or interpreting is called. A. Directive listening B. Non-listening C. Visual listening D. Facilitative listening /Reference: : QUESTION 14 In a fixed price contract the: A. Contractor has no risk in the project B. Contactor assumes all the performance risk C. Contractor is paid for actual costs D. Owner has all the risk Correct Answer: B

6 /Reference: well define answer. QUESTION 15 The following question requires your selection of CCC/CCE Scenario 2 ( ) from the right side of 6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned? A. 6,600 B. 6,960 C. 7,200 D. 6,573 /Reference: : QUESTION 16 The following question requires your selection of CCC/CCE Scenario 2 ( ) from the right side of 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current cost performance index (CPI)?

7 A B C D Correct Answer: C /Reference: : QUESTION 17 The following question requires your selection of CCC/CCE Scenario 2 ( ) from the right side of 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current schedule performance index (SPI)? A B C D /Reference: reliable answer. QUESTION 18

8 The following question requires your selection of CCC/CCE Scenario 2 ( ) from the right side of 10,278 hours have been expended to date. The CPI at this point in time is SPI is How many hours have been earned? A. 9,979 B. 10,586 C. 11,052 D. 9,559 /Reference: : QUESTION 19 The following question requires your selection of CCC/CCE Scenario 4 ( ) from the right side of

9 What is the cost of manufacturing labor for the piece of equipment today? A. $140,000 B. $875,000 C. $210,000 D. $105,000 /Reference: : QUESTION 20 The following question requires your selection of CCC/CCE Scenario 4 ( ) from the right side of What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions) A B C D /Reference: actual answer. QUESTION 21

10 The following question requires your selection of CCC/CCE Scenario 4 ( ) from the right side of At the end of 30 months, copper prices will have increased by what percentage over today's price? A. 4.6% B. 3.5% C. 6.6% D. 2.5% /Reference: : QUESTION 22

11 The following question requires your selection of CCC/CCE Scenario 4 ( ) from the right side of If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4? A. $1890/ton B. $1863/ton C. $1948/ton D. $1836/ton /Reference: : QUESTION 23

12 The following question requires your selection of CCC/CCE Scenario 4 ( ) from the right side of At the end of Year 4, the commodity which experienced the greatest projected percentage price index increase over today is: A. None of the above B. Manufacturing labor C. Steel D. Copper Correct Answer: B /Reference: : QUESTION 24

13 The following question requires your selection of CCC/CCE Scenario 6 ( ) from the right side of Calculate the mean unit cost. A. $48.09 B. $48.22 C. $48.35 D. $46.59 /Reference: real answer. QUESTION 25

14 The following question requires your selection of CCC/CCE Scenario 6 ( ) from the right side of What is the range of estimated quantities? A. $26.78 to $75.00 B. $485 C. $45 to $530 D. $48.22 Correct Answer: C /Reference: : QUESTION 26 The following question requires your selection of CCC/CCE Scenario 6 ( ) from the right side of What is the relative frequency of unit costs amounting to $55.00/unit?

15 A % B. $55.00 C. 2 D /Reference: : QUESTION 27 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The following question requires your selection of CCC/CCE Scenario 26 ( ) from the right side of What information is needed to develop a Class 2 definitive estimate? A. Soil data, detailed construction drawings, quantity takeoffs, minimum contingency detailed indirect costs, detailed engineering estimates B. Preliminary quantities with labor, material, and factors applied, square footage of facilities, minimum contingency detailed indirect costs C. Square footage of facilities, factored indirects and home office costs D. Vendor quotes, home office detailed estimate, preliminary quantities with labor, material, and factors applied /Reference: good sort of answer. QUESTION 28 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The following question requires your selection of CCC/CCE Scenario 26 ( ) from the right side of Select the statement that best describes the method to estimate the cost of the new rides: A. Break down the technology into components

16 B. Call vendors for quotes C. Use historical data from past projects D. Adjust known data from existing rides /Reference: : QUESTION 29 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The following question requires your selection of CCC/CCE Scenario 26( ) from the right side of Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected: A. To be exactly the percentages stated B. To fall within the percentage range stated C. To be higher or lower that the percentages stated D. To be outside the percentages stated Correct Answer: B /Reference: : QUESTION 30 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. According to Maslow's hierarchy of needs, giving the employees an award that acknowledges their achievements is most likely to satisfy which level of need? A. Belonging needs B. Safety needs C. Power needs D. Self-actualization /Reference: : QUESTION 31 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years

17 after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the stage of Maslow's hierarchy of needs. A. Need satisfaction B. Belonging needs C. Self-actualizations D. Esteem Correct Answer: C /Reference: : QUESTION 32 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. In an exit interview, an employee comments that the reason he is leaving the organization is lack of teamwork and cohesion among his co-workers. Which need of Maslow's hierarchy of needs is unmet? A. Belongingness needs B. Primary needs C. Self-actualization needs D. Esteem needs /Reference: : QUESTION 33 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. According to Maslow's hierarchy of needs, which level should be satisfied first? A. Physiological B. Self-actualization C. Safety needs D. Ego-status /Reference: :

18 QUESTION 34 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. In Rensis1 4 model system, the exploitative-authoritative management style is one in which: A. Management makes most decisions and passes them down B. Informal organizations generally support the goals of the formal organization C. Management issues orders, but employees have some freedom to comment D. Management has a lot of confidence in the employees /Reference: : QUESTION 35 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following percent complete measurement techniques is best suited for long-term nonproduction accounts (such as overhead accounts)? A. Ratio/level of effort B. Start/finish C. Units completed D. Incremental milestone /Reference: : QUESTION 36 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as: A. Activity total slack B. Remaining duration C. Just-in-time" scheduling D. Free float

19 /Reference: : QUESTION 37 The following question requires your selection of CCC/CCE Scenario 28 ( ) from the right side of If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best: A. Engineer -- cost plus, contractor fixed price B. Engineer -- cost plus, contractor cost plus C. Engineer fixed price, contactor cost plus D. Engineer -- fixed price, contractor fixed price /Reference: definite answer. QUESTION 38

20 The following question requires your selection of CCC/CCE Scenario 28 ( ) from the right side of Given a unit price contract between the owner and contractor, each assumes the following: A. Bid unit rate, owner quantities can exceed estimate range Contractor can perform above B. Bid unit rate, owner quantities are within estimate range C. Contractor can perform at or below bid unit rate, owner quantities can exceed estimate range D. Contractor can perform at or below bid unit rate, owner quantities are within estimate range /Reference: : QUESTION 39 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%. The following question requires your selection of CCC/CCE Scenario 7 ( ) from the right side of

21 If $10,000 is scheduled to be paid out 5 years from now, what is the minimum amount we can invest today? A. $3,855 B. $8,129 C. $6,209 D. $3,791 Correct Answer: C /Reference: : QUESTION 40 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%. The following question requires your selection of CCC/CCE Scenario 7 ( ) from the right side of If $20,000 is invested at the end of each fiscal year for the next 10 years, how much would our total investment be worth assuming the interest is at 10%? A. $289,370 B. $318,740 C. $265,798 D. $420,236 Correct Answer: B /Reference: : QUESTION 41 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%. The following question requires your selection of CCC/CCE Scenario 7 ( ) from the right side of Five years from now it is required the company have $100,000. How much money should be invested at the end of each year to reach this? A. $15,937 B. $15,397

22 C. $16,380 D. $13,168 Correct Answer: C /Reference: absoulte answer. QUESTION 42 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%. The following question requires your selection of CCC/CCE Scenario 7 ( ) from the right side of If the company needs to repay a loan of $100,000 in 10 uniform annual payments, how much will each payment be? A. $16,380 B. $16,578 C. $15,937 D. $16,273 /Reference: : QUESTION 43 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%. The following question requires your selection of CCC/CCE Scenario 7 ( ) from the right side of A contractor must purchase a piece of equipment for $150,000. It has an estimated life of 10 years with no salvage value at the end. Ten years from now it will be necessary to purchase another piece of equipment, but this time it will cost $250,000. How much will the contractor need to invest at the end of each year in order to have the right amount? A. $15,687 B. $12,550 C. $16,273 D. $9,412

23 Correct Answer: C /Reference: : QUESTION 44 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. The following question requires your selection of CCC/CCE Scenario 17 ( ) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. Present worth calculations is represented by which of the following equations? A. Option A B. Option B C. Option C D. Option D /Reference: : QUESTION 45 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. The following question requires your selection of CCC/CCE Scenario 17 ( ) from the right side of What is the "book value (BV) of the asset at the end of 5 years? A. $64,000 B. $16,000 C. $3,200 D. $60,000

24 /Reference: : QUESTION 46 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. The following question requires your selection of CCC/CCE Scenario 17 ( ) from the right side of Annual estimated tax would be: A. $3,869 B. $5,565 C. $10,500 D. $11,925 Correct Answer: B /Reference: : QUESTION 47 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. The following question requires your selection of CCC/CCE Scenario 17 ( ) from the right side of Assuming a 53% tax rate, how much cumulative depreciation will have been claimed at the end of the grain elevator's life span? A. None B. $42,400 C. $37,600 D. $80,000 /Reference: : QUESTION 48 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. The main financial objective of many enterprises is:

25 A. To maximize the total long-term economic return B. Subject to a well-conceived quality control plan C. To balance opportunities and risks D. Dependent on the backlog projects and the availability of resources /Reference: : QUESTION 49 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. Which of the following should be included in the life-cycle cost analysis of a power plant? A. Construction cost, operating cost, maintenance cost B. Factory expenses, distribution expenses, mark-up C. Capacity factor, end product units, physical dimensions D. Resources, work activities, final cost objects /Reference: nicely answered. QUESTION 50 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. If $100,000 is needed to purchase a piece of equipment 3 years from now, how much money needs to be invested today assuming a 10% rate of return (rounded to the nearest thousand)? A. $78,000 B. $70,000 C. $75,000 D. $82,000 Correct Answer: C /Reference: : QUESTION 51 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate.

26 How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually? A. $31,875 B. $12,550 C. $29,600 D. $13,515 Correct Answer: B /Reference: : QUESTION 52 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal? A. $6.80 B. $3.10 C. $5.35 D. $2.22 /Reference: : QUESTION 53 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. If you buy a lot for $3,000 and sell it for $6,000 at the end of 8 years, what is your annual rate of return? A. 10.4% B. 9.1% C. 8.3% D. 9.9% Correct Answer: B /Reference: reliable answer. QUESTION 54 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last

27 twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. Which of the following interest rates disregards the effects of compounding periods that occur more frequent than annually? A. Continuous compounding rate B. Simple interest rate C. Minimum attractive rate of return D. Nominal interest rate /Reference: : QUESTION 55 Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also, planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%. The following question requires your selection of CCC/CCE Scenario 7 ( ) from the right side of If $10,000 is invested now at 10% compounded annually, what will the investments be worth 10 years from now? A. $25,940 B. $29,450 C. $21,345 D. $16,180 /Reference: choice of answer is correct. QUESTION 56 Which of the following is NOT an aspect of quality management? A. Quality assurance B. Quality planning C. Quality checking D. Quality control Correct Answer: C /Reference:

28 correct answer. QUESTION 57 is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts. A. Percent complete B. Cost to complete C. Earned value D. Forecast /Reference: : QUESTION 58 If a project is said to be on a "fast track program/' the fast track method is: A. Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/ sequence and duration for all of the work B. First completing engineering and procurement, then executing construction C. Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance D. Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime /Reference: : QUESTION 59 The process of stating goals and determining the most effective way of reaching them is the definition for: A. Implementing B. Mission Statement C. Managing D. Planning /Reference: :

29 QUESTION 60 What is a basic element of work or a task that must be performed over a given period of time in order to complete a project called? A. WBS element B. Activity C. Resource D. Commodity Correct Answer: B /Reference: : QUESTION 61 A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a. A. Cost breakdown structure B. Code of accounts C. Cost estimate classification D. Schedule identification number Correct Answer: B /Reference: : QUESTION 62 An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as: A. Costing B. Cost-price analysis C. Bid shopping D. Negotiating a best and final offer Correct Answer: C /Reference: : QUESTION 63 A contract clause that provides the owner with the right to terminate the contract irrespective of the general

30 contractor's liability is: A. Termination of contract - convenience B. Termination of contract - default C. Substantial completion D. Breach of contract /Reference: accurate answer. QUESTION 64 The goal of listening is to: A. Analyze what the speaker is saying B. Find out what is going on C. Have time to formulate your thoughts on the subject D. Improve communication /Reference: : QUESTION 65 NO: 37 The following question requires your selection of CCC/CCE Scenario 2 ( ) from the right side of The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project? A. 45% B. 50% C. 95% D. 30%

31 /Reference: : QUESTION 66 The following question requires your selection of CCC/CCE Scenario 2 ( ) from the right side of 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion? A. 16,215 B. 14,201 C. 12,000 D. 10,526 /Reference: : QUESTION 67 The following question requires your selection of CCC/CCE Scenario 2 ( ) from the right side of 10,278 hours have been expended to date. The CPI at this point in time is SPI is How many hours were planned? A. 10,586 B. 9,280

32 C. 9,559 D. 10,278 /Reference: : QUESTION 68 The following question requires your selection of CCC/CCE Scenario 4 ( ) from the right side of At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal) A. 8.7% B. 8.2% C. 4.6% D. 8.0% /Reference: : QUESTION 69

33 The following question requires your selection of CCC/CCE Scenario 4 ( ) from the right side of At the end of 30 months, the final price for the piece of equipment will be: A. $328,810 B. $370,710 C. $375,658 D. $378,750 Correct Answer: C /Reference: : QUESTION 70

34 The following question requires your selection of CCC/CCE Scenario 6 ( ) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses. What is the range of unit costs? A. $21.57 B. $26.65 C. $48.22 D. $ /Reference: : QUESTION 71 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The following question requires your selection of CCC/CCE Scenario 26 ( ) from the right side of What class of estimate is used for the preliminary design phase of a project? A. Class 5 - order of magnitude estimate with +50% / -30% accuracy B. Class 1 - order of magnitude with +30% / -30% accuracy C. Class 4 - budget estimate with +30% / -15% accuracy D. Class 2 - definitive estimate with +15%/-5% accuracy

35 /Reference: : QUESTION 72 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The following question requires your selection of CCC/CCE Scenario 26 ( ) from the right side of Why is a +/- notation necessary when developing an estimate? A. Contingency cushion B. It makes up for the lack of time to develop a real estimate C. It is a government requirement D. There are unknowns that affect the final cost of a project /Reference: : QUESTION 73 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow's hierarchy of needs? A. Belonging needs B. Self-actualization C. Knowledge D. Pay and compensation /Reference: : QUESTION 74 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. A cyclical process model was chosen as the basis for total cost management (TCM) because: A. It is one of the basic tenets of quality improvement

36 B. Refinement is needed to prepare the estimate at completion (EAC) C. Strategic assets and projects have inherent life cycles D. It facilitates development of budgets and schedules Correct Answer: C /Reference: : QUESTION 75 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Resource planning must take all of the following into account except: A. Types of materials, equipment and labor skills required to complete the project B. Cash flow (expenditures) limitations for completing work on the project C. Time available to complete the project D. Earned value techniques established for the project /Reference: approved answer. QUESTION 76 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Profits that could not be formally recognized during a specific financial accounting period because the goods and services did not satisfy all the customer's requirements are: A. Marginal profits B. Lost profits C. Incurred profits D. Postponed profits /Reference: : QUESTION 77 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

37 Which of the following is least likely to improve a large earthmoving contractor's productivity? A. Using apprentice operators to save labor costs B. Starting summer work in the early morning hours to minimize work during peak heat periods of the day C. Remove underground hazards prior to excavation work D. Replacing old excavators with new, larger excavators Correct Answer: B /Reference: : QUESTION 78 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. The following question requires your selection of CCC/CCE Scenario 17 ( ) from the right side of What is the 25 year after tax present worth of this project? A. $13,738 B. $137,466 C. $(22,533) D. $22,533 /Reference: : QUESTION 79 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. The following question requires your selection of CCC/CCE Scenario 17 ( ) from the right side of Depreciation (in the United States) is calculated in accordance with which of the following? A. Modified Accelerated Cost Recovery System (MACRS) B. The Federal IRS Reform Act (FIRSRA) C. Generally Accepted Accounting Practices (GAAP) D. Accelerated Cost Recovery System (ACRS) /Reference: satisfied answer.

38 QUESTION 80 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. Which of the following is considered a measure of profitability? A. Rate of return B. Annual Dividends C. Total assets D. Annual sales /Reference: : QUESTION 81 If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual Percentage Rate) compounded monthly, how much will you have at the end of the period? A. $2,424 B. $2,976 C. $2,688 D. $2,697 /Reference: : QUESTION 82 In order to withdraw $400 at the end of each year for seven years, what amount should be deposited at 6.0% interest to leave nothing in the fund at the end of seven years? A. $2,233 B. $3,357 C. $2,483 D. $2,968

39 /Reference: : QUESTION 83 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000. Answer the question using a straight line depreciation and a 10% interest rate. You have been asked to provide ETC information to management. Based on the following information, what is the ETC? Original Budget = $9,000,000 Actuals to date = $3,513,000 Current estimate at completion = $10,613,000 Actuals for current month = $1,200,000 A. $10,613,000 B. $9,000,000 C. $5,487,000 D. $7,100,000 /Reference: : QUESTION 84 A schedule's late dates are calculated during the: A. Loop calculations B. Backward pass C. Forward pass D. Float Correct Answer: B /Reference: appropriate answer. QUESTION 85 Which of the following is NOT a type of float? A. Total B. Negative C. Open end D. Free Correct Answer: C /Reference: : QUESTION 86

40 The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as: A. Total float B. Remaining duration C. Free float D. Just-in-time scheduling /Reference: : QUESTION 87 A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required? A. 3.0 cubic yards B. 2.0 cubic yards C. 3.5 cubic yards D. 2.5 cubic yards /Reference: : QUESTION 88 Which of the following best describes the concept of total cost management: A. A method of quantifying construction damages where the total job costs are subtracted from the original bid or estimate to determine the total cost amount for a claim B. The practices and processes utilized to manage the total life cycle cost investment in a portfolio of strategic assets C. A job cost system for ensuring all aspects of a particular manufacturing process are accumulated completely D. An integrating process that maps the fields of practice of cost engineering without linking it to project management, resource management, or accounting /Reference: definite answer. QUESTION 89 AACE International defines as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms. A. Risk analysis B. Benefit/Cost ratio (B/C) method C. Net present worth method D. Life cycle costs method (LCC)

41 /Reference: : QUESTION 90 A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as: A. Surety bond B. Performance bond C. Bid bond D. Liability bond Correct Answer: C /Reference: : QUESTION 91 What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract? A. Liability insurance B. Performance bond C. Bid bond D. Surety bond Correct Answer: B /Reference: : QUESTION 92 Productivity increases with time. This improvement is commonly associated with improvements in efficiency brought about by increased experience and skill levels. What does this scenario describe? A. Productivity efficiency factor B. Value engineering C. Cash flow D. The learning curve /Reference: : QUESTION 93 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

42 Which of the following methods a used for creating critical path schedules: A. Precedence diagram method B. Precedence and arrow diagram methods only C. Gantt chart (bar chart) method D. Arrow diagram method Correct Answer: B /Reference: : QUESTION 94 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The following is NOT an advantage of the critical path method: A. The ability to determine cost overruns of critical path activities B. The ability to identify activities that cannot have their schedules slip if the desired project end date is to be achieved C. Reveals activities that additional resources need to be dedicated toward D. The ability to show slippage in the progress of key activities /Reference: : QUESTION 95 A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of What would you advise the management about the scheduled completion date? A. Project will be completed in 20 more weeks B. Project will be completed this week - on schedule C. Project will be completed in 4 more weeks D. Project will be completed in 12.8 more weeks Correct Answer: C /Reference: : QUESTION 96

AACE CCP Exam. Volume: 115 Questions

AACE CCP Exam. Volume: 115 Questions Volume: 115 Questions Question No : 1 The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of 10,278 hours have been expended to date. The CPI at this point

More information

ActualCollection. Actual dumps collection, higher pass rate

ActualCollection.   Actual dumps collection, higher pass rate ActualCollection http://www.actualcollection.com Actual dumps collection, higher pass rate Exam : CCP Title : Certified Cost Professional (CCP) Exam Vendor : AACE International Version : DEMO Get Latest

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

PROJECT MANAGEMENT DIPLOMA COURSE

PROJECT MANAGEMENT DIPLOMA COURSE PROJECT MANAGEMENT DIPLOMA COURSE UNIT THREE PROJECT PLANNING TUTOR TALK: The Learning Outcomes for this assignment are: Describe the following: o Planning parameters o Planning quality o Developing a

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23

Contents Cloud or On-Premises Content Introduction Data Dictionary... 23 P6 Data Dictionary Version 17 July 2017 Contents Cloud or On-Premises Content... 19 Introduction... 21 Data Dictionary... 23 % Allocation... 23 Access Level... 23 Access Time... 23 Accounting Variance...

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

Unit 8 - Math Review. Section 8: Real Estate Math Review. Reading Assignments (please note which version of the text you are using)

Unit 8 - Math Review. Section 8: Real Estate Math Review. Reading Assignments (please note which version of the text you are using) Unit 8 - Math Review Unit Outline Using a Simple Calculator Math Refresher Fractions, Decimals, and Percentages Percentage Problems Commission Problems Loan Problems Straight-Line Appreciation/Depreciation

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

PMI - Dallas Chapter. Sample Questions. March 22, 2002

PMI - Dallas Chapter. Sample Questions. March 22, 2002 PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

IP-CIS : CIS Project Management

IP-CIS : CIS Project Management Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany 1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Earned Value Management System

Earned Value Management System DEPARTMENT OF VETERANS AFFAIRS Office of Information and Technology Earned Value Management System Description Document VA-DI-MGMT-81466A RECORD OF CHANGES Change Number Date Reference (Page, Section,

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

PMI PMI-SP. PMI Scheduling Professional. Download Full Version :

PMI PMI-SP. PMI Scheduling Professional. Download Full Version : PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he

More information

SECTION PROGRESS SCHEDULE

SECTION PROGRESS SCHEDULE NOTE: Review this section carefully. If Project Scope is complex this Specification is to be used. If project is relatively simple and straightforward use Section 01310. SECTION 01311 PART 1 GENERAL 1.1

More information

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD)

SECTION PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) SECTION 01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS DESIGN/BID/BUILD) PART 1- GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment

More information

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs)

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs) Integrated Baseline Reviews (IBRs) Holding an IBR is a best practice for all programs, and it supports the implementation of an earned value management system (EVMS). EVM can be a valuable tool for controlling

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

Techniques to Assist Delivery of Projects

Techniques to Assist Delivery of Projects Techniques to Assist Delivery of Projects 1 Introduction Who am I? Ian Bell Where am I from? Adept Knowledge Management Ltd Based at 5 Carden Place Aberdeen AB10 1UT +44 (0) 1224 251015 2 Introduction

More information

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales The PRINCE2 Practitioner Examination Sample Paper TR Answers and rationales For exam paper: EN_P2_PRAC_2017_SampleTR_QuestionBk_v1.0 Qu Correct Syll Rationale answer topic 1 A 1.1a a) Correct. PRINCE2

More information

Estimate Considerations. Estimate Considerations

Estimate Considerations. Estimate Considerations Estimate Considerations Estimate Considerations Every estimate, whether it is generated in the conceptual phase of a project or at bidding time, must consider a number of issues Project Size Project Quality

More information

Earned Value Management Handbook. arne. alu

Earned Value Management Handbook. arne. alu Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change

More information

CHAPTER 6 PROJECT CASH FLOW

CHAPTER 6 PROJECT CASH FLOW CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter deals with project cash

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

Unit 5 Slide Lectures of 04/05/06 April 2017

Unit 5 Slide Lectures of 04/05/06 April 2017 PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT SCHEDULING, PROJECT DURATION AND PROJECT COMMUNICATION PLAN (CH. 8-9) Unit 5 Slide 5.2.1 Lectures of 04/05/06 April 2017 Overview of

More information

Project Management Initial Steps

Project Management Initial Steps Table of Contents Table of Contents...1 Introduction...1 Basic Project Management Outline...1 Managing Resources - People, Equipment, and Material...2 Managing Time and Schedule...3 Managing Costs, Money,

More information

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Table of Contents. Key Activity - Risk Analysis... 11.1. Purpose... 11.2. Risk Reporting Matrix...

More information

COPYRIGHTED MATERIAL. Index

COPYRIGHTED MATERIAL. Index Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

Appendix A Decision Support Analysis

Appendix A Decision Support Analysis Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated

More information

70-632_formatted. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0

70-632_formatted.   Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0 70-632_formatted Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ Microsoft EXAM 70-632 TS:Microsoft Office Project 2007. Managing Projects Total Questions:

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No. E 32R04 SA M PL DETERMI NI NGACTI VI TY DURATI ONS AACE International Recommended Practice No. 32R-04 DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development Rev. Note: As AACE

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Learning Legacy Document

Learning Legacy Document PROGRAMME CONTROLS - COST Performance Measurement Procedure Current Document History: Revision: Effective Date: Document Number: CRL1-XRL-Z9-GPD-CR001_Z-50001 Author(s) Reviewed by: Approved by: Reason

More information

Introduction to Construction Financial Management

Introduction to Construction Financial Management PART I Introduction to Construction Financial Management In this section we introduce you to construction financial management, how it is different from financial management in other industries, and why

More information

UNIT-II Project Organization and Scheduling Project Element

UNIT-II Project Organization and Scheduling Project Element UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite

More information

Professional Development Seminar Series

Professional Development Seminar Series Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context

More information

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience

More information

Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE

Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE Project Management for EPC Contracts Presented by: Dr. Jamal F. AlBahar, PMP, VMA Registered Arbitrator; Member: PMI, CMAA, AACE, AAA, PMA, CSI, SAVE INTRODUCTION: Project Management for Engineering and

More information

Introduction to Project Management. Modeling after NYS ITS

Introduction to Project Management. Modeling after NYS ITS Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project

More information

54R07 RECOVERYSCHEDULI PROCUREMENT,AND CONSTRUCTI

54R07 RECOVERYSCHEDULI PROCUREMENT,AND CONSTRUCTI E 54R07 SA M PL RECOVERYSCHEDULI NGASAPPLI EDI NENGI NEERI NG, PROCUREMENT,AND CONSTRUCTI ON AACE International Recommended Practice No. 54R-07 RECOVERY SCHEDULING AS APPLIED IN ENGINEERING, PROCUREMENT,

More information

Contract Performance Report

Contract Performance Report Contract Performance Report Description This report consists of five formats containing cost and related data for measuring contractors' cost and schedule performance on Department of Defense (DOD) acquisition

More information

CE303 Introduction to Construction Engineering. Importance of Cost Control System. Project Cost Control System

CE303 Introduction to Construction Engineering. Importance of Cost Control System. Project Cost Control System CE303 Introduction to Construction g PROJECT COST MANAGEMENT & BUSINESS METHODS LEARNING OBJECTIVES The student should be able to: Define and understand the need for a cost control system. Describe the

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP

More information

12 GeV CEBAF Upgrade. Risk Management Plan

12 GeV CEBAF Upgrade. Risk Management Plan 12 GeV CEBAF Upgrade Risk Management Plan May 29, 2007 12 GeV CEBAF Upgrade Risk Management Plan 1 Apr 05 ISSUE DATE PAGES AFFECTED DESCRIPTION Original CD-2 4/01/05 5/29/07 All All General update to maintain

More information

MS Project 2007 Page 1 of 18

MS Project 2007 Page 1 of 18 MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems

More information

Allocate and Level Project Resources

Allocate and Level Project Resources Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both

More information

Textbook: pp Chapter 11: Project Management

Textbook: pp Chapter 11: Project Management 1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use

More information

Chapter16Project Management and. Scheduling Project management

Chapter16Project Management and. Scheduling Project management Chapter6Project Management and Scheduling Figure 6. On completion of this chapter, you should be able to identify key components of projects and the issues associated with them, and you should be able

More information

Applying IFRS. Joint Transition Resource Group discusses additional revenue implementation issues. July 2015

Applying IFRS. Joint Transition Resource Group discusses additional revenue implementation issues. July 2015 Applying IFRS Joint Transition Resource Group discusses additional revenue implementation issues July 2015 Contents Overview 2 1. Issues that may require further discussion 2 1.1 Application of the constraint

More information

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. Accounts Payable Obligations to pay for goods and services that have

More information

Topic 2: Define Key Inputs and Input-to-Output Logic

Topic 2: Define Key Inputs and Input-to-Output Logic Mining Company Case Study: Introduction (continued) These outputs were selected for the model because NPV greater than zero is a key project acceptance hurdle and IRR is the discount rate at which an investment

More information

Delay Expert practical tips for making delay claims

Delay Expert practical tips for making delay claims Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of

More information

Project Management. A Practitioner s Guide. Steven M. Bragg

Project Management. A Practitioner s Guide. Steven M. Bragg Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project

More information

Fundamentals of Capital Cost Estimating A TCM approach. Lou Vidotto Managing Director of Vidotto Group

Fundamentals of Capital Cost Estimating A TCM approach. Lou Vidotto Managing Director of Vidotto Group Fundamentals of Capital Cost Estimating A TCM approach Lou Vidotto Managing Director of Vidotto Group Contents 1. Background; 2. Introduction; 3. Total Cost management; 4. Types of Estimates; 5. WBS and

More information

Basic Project Management

Basic Project Management PDHonline Course P103H (8 PDH) Basic Project Management Instructor: William J. Scott, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

EFCOG Best Practice #174

EFCOG Best Practice #174 EFCOG Best Practice #174 Best Practice Title: CPR/DID Monthly Validation Facility: Washington River Protection Solutions, Hanford Site, Richland Washington Point of Contact: Craig Hewitt, WRPS Hanford,

More information

Start Trade Payment Methods with the overview of the part. Show the Slide 2-66 and clarify each topic given in the overview.

Start Trade Payment Methods with the overview of the part. Show the Slide 2-66 and clarify each topic given in the overview. Overview 5 minutes Overview Start Trade Payment Methods with the overview of the part. Show the 2-66 and clarify each topic given in the overview. 2-66 Objectives 5 minutes What are you expecting to learn

More information

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project

More information

Braindumps.PMI-SP.323 questions

Braindumps.PMI-SP.323 questions Braindumps.PMI-SP.323 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PMI-SP PMI Scheduling Professional It gets you study tools online for

More information

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan PROJECT MANAGEMENT Trying to manage a project without project management is like trying to play a football game without a game plan K. Tate (Past Board Member, PMI). Brad Fink 28 February 2013 Executive

More information

PMI - Dallas Chapter. PMP Exam Sample Questions

PMI - Dallas Chapter. PMP Exam Sample Questions PMI - Dallas Chapter PMP Exam Sample Questions June 4, 1999 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

Energy Savings Performance Contracting Program Process Description

Energy Savings Performance Contracting Program Process Description Energy Savings Performance Contracting Program Process Description I. Program History The Energy Savings Performance Contracting (ESPC) program was developed to provide a means to install energy conservation

More information

Earned Value Management Tutorial Module 4: Budgeting. Prepared by:

Earned Value Management Tutorial Module 4: Budgeting. Prepared by: Earned Value Management Tutorial Module 4: Budgeting Prepared by: Module 4: Budgeting Welcome to Module 4. The objective of this module is to introduce you to Budgeting Concepts and Definitions. The Topics

More information

A Study on Risk Analysis in Construction Project

A Study on Risk Analysis in Construction Project A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------

More information

EST.04. Owner Validation of Contractor-Prepared Estimates

EST.04. Owner Validation of Contractor-Prepared Estimates EST.04 Owner Validation of Contractor-Prepared Estimates W. Doug Creech, CCC W ithout question, contractors have come to dominate the world of engineering and construction more than ever before. Gone are

More information

PROJECT MANAGEMENT BODY OF KNOWLEDGE

PROJECT MANAGEMENT BODY OF KNOWLEDGE A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education

More information

Construction Management

Construction Management Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect

More information

REPLACEMENT RESERVE REPORT FY 2015 WOODBRIDGE CONDOMINIUM CHESAPEAKE BAY MANAGEMENT. Community Management by: Ms. Kimberly Marston

REPLACEMENT RESERVE REPORT FY 2015 WOODBRIDGE CONDOMINIUM CHESAPEAKE BAY MANAGEMENT. Community Management by: Ms. Kimberly Marston REPLACEMENT RESERVE REPORT FY 2015 WOODBRIDGE CONDOMINIUM WOODBRIDGE CONDOMINIUM REPLACEMENT RESERVE REPORT FY 2015 Community Management by: CHESAPEAKE BAY MANAGEMENT Ms. Kimberly Marston 100 Volvo Parkway,

More information

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects

More information

Appendix E: Revenues and Cost Estimates

Appendix E: Revenues and Cost Estimates Appendix E: Revenues and Cost Estimates Photo Source: Mission Media Regional Financial Plan 2020-2040 Each metropolitan transportation plan must include a financial plan. In this financial plan, the region

More information

Project Management Chapter 13

Project Management Chapter 13 Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling

More information

King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting

King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting Determination of Construction Contract Duration for Public Projects in Saudi Arabia By:

More information

8.6 FORMULATION OF PROJECT REPORT. 160 // Management and Entrepreneurship

8.6 FORMULATION OF PROJECT REPORT. 160 // Management and Entrepreneurship 160 // Management and Entrepreneurship (9) Raw material: List of raw material required by quality and quantity, sources of procurement, cost of raw material, tie-up arrangements, if any for procurement

More information

Allegan County Courthouse Square

Allegan County Courthouse Square Allegan County Courthouse Square Master Plan Charrette Report Draft Executive Summary Date: August 4, 2014 Prepared By: Index to Report Executive Summary A. Introduction 1. Charrette Goals and Objectives.

More information

Full Reserve Study For Homeowners Association (HOA) At the Starlight Cove Community Located at Fairway Drive Boynton Beach, Florida 33437

Full Reserve Study For Homeowners Association (HOA) At the Starlight Cove Community Located at Fairway Drive Boynton Beach, Florida 33437 Full Reserve Study For Homeowners Association (HOA) At the Starlight Cove Community Located at 12241 Fairway Drive Boynton Beach, Florida 33437 Prepared by Sadat Engineering, Inc. Boynton Beach, Florida

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

Prince2 Foundation.exam.160q

Prince2 Foundation.exam.160q Prince2 Foundation.exam.160q Number: Prince2 Foundation Passing Score: 800 Time Limit: 120 min PRINCE2 Foundation PRINCE2 Foundation written Exam Sections 1. Volume A 2. Volume B Exam A QUESTION 1 Which

More information

2. Which of the following is a common characteristic of most project life cycle descriptions?

2. Which of the following is a common characteristic of most project life cycle descriptions? INTEGRATION MANAGEMENT 1. The review of key deliverables and project performance at the conclusion of a project phase is called: A. phase exit B. kill point C. stage gate D. a and c E. All above 2. Which

More information

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

Objectives of Project Cost Control System

Objectives of Project Cost Control System Project Cost Control Objectives of Project Cost Control System 1. To identify those work types having excessive costs and to give an indication of how serious those overruns are. 2. To forecast the final

More information

The Four Pillars of project management

The Four Pillars of project management The Four Pillars of project management Background This article is intended to give a round up of key practical project management practices to the novice as well as to the experienced. About 90% of this

More information

KERN COMMUNITY COLLEGE DISTRICT BAKERSFIELD COLLEGE INDA B132 COURSE OUTLINE OF RECORD

KERN COMMUNITY COLLEGE DISTRICT BAKERSFIELD COLLEGE INDA B132 COURSE OUTLINE OF RECORD Status: Final Last Revised: February 11, 2016 Proposal Type: New Course Start Term: Fall 2017 TOPS Code: 0935.00 CIP Code: 15.0406 (updated 6/1/16) KERN COMMUNITY COLLEGE DISTRICT BAKERSFIELD COLLEGE INDA

More information

DATA ITEM DESCRIPTION. Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date:

DATA ITEM DESCRIPTION. Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date: DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date: 20150916 AMSC Number: D9583 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing

More information

Department of Industrial Engineering

Department of Industrial Engineering Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define

More information

Project Tracking, Monitoring & Controlling

Project Tracking, Monitoring & Controlling Project Tracking, Monitoring & Controlling Project Tracking.... PROJECT TRACKING, MONITORING, CONTROLLING BASELINE STATUS REPORTING PROJECT REVIEWS CONTROL SYSTEMS Reason for a Baseline Plan It is necessary

More information