Delay Expert practical tips for making delay claims

Size: px
Start display at page:

Download "Delay Expert practical tips for making delay claims"

Transcription

1 Octavian Dan

2 Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of changes to specific clauses which are useful for consideration when making delay claims Recommendations regarding the use of the project programme for making delay claims: Typical delay scenarios principles Principles for setting up the delay analysis programme Delay analysis choices and methodology

3 FIDIC 2017 edition a short summary of changes to specific clauses which are useful for consideration when making delay claims

4 FIDIC Modifications to clauses related to delay claims Advance Warning (Cl.8.4) - Required to be issued by each Party to advise of known or probably future events affecting performance, price or delay. (but no apparent consequences for failure to comply). Notices (Cl.1.3) - All Notices must be in writing and specifically identified as a Notice (without the need to refer to the specific clause under which it is issued). - Nothing stated in the Progress Reports (Cl.4.20) or in the Programmes (Cl.8.3) can constitute a Notice unless the matter is specifically issued under Cl.1.3 Claims for Payment and/or EOT (Cl.20.2) - The provision requiring notification of the claim within 28 days is maintained; however, the Engineer/other party must give Notice within 14 days if it considers that the submission is out of time (otherwise the claim is deemed valid). - Later notifications are possible, if a party considers that there are justifying circumstances for the out of time submission (Cl ). Justification and supporting evidence is to be provided with the Fully detailed Claim (Cl ) within 84 days (or other period agreed) of being aware (or should have been aware) of the event or circumstance.

5 FIDIC Modifications to clauses related to delay claims Programme (Cl.8.3) - Details of programme clause expanded to include requirement for additional details in each programme: logic links, earliest and latest start and finish dates, float, critical path(s) - Deeming provisions regarding acceptance in relation to the initial programme, the revised programmes (and also the detailed test programme now required under Cl.9.1), failure of Engineer to give Notice of non-compliance with the Contract, inconsistency with actual progress or the Contractor s obligations (within 21 days, respectively 14 days) is deemed to be Notice of No-Objection and the detailed programme prepared by the Contractor will become the Programme. - Programming software can be stated in the Specifications or specified by the Engineer. - Programme submission at least one paper copy and one electronic copy for each programme submitted

6 FIDIC Modifications to clauses related to delay claims Entitlement to EOT - extended to additional items: - Access Route (Cl.4.15) relief grated for non-suitability/ non-availability of access route as a result of changes by third party which occurred after the Base Date. - Delays by private utility entities (Cl.8.5) added to delays caused by public authorities. - Delays generated by Employer- Supplied Materials (Cl.8.5) added to entitlement due to Unforeseeable shortages in the availability of personnel or Goods. - Delays generated by Permits (Cl.13.6) extended to changes in law to permits to be obtained by Employer or changes in requirements for the permits to be obtained by the Contractor.

7 FIDIC Modifications to clauses related to delay claims Clarifications to matters related to delay: - Adverse Climatic Conditions (Cl.8.5) relief grated/ limited to adverse climatic conditions affecting only the Site and which are Unforeseeable having regard to data provided by Employer or published in the Country for the specific location of the Site. - Concurrent Delay (Cl.8.5) new requirement from the Parties to adopt and apply rules and procedures which are to be stated in the Special Provisions. If the rules and procedures dealing with concurrency are not stated, the EOT entitlement is assessed as appropriate taking due regard to all relevant circumstances. [North Midland Building Ltd v Cyden Homes Lts [2017] EWHC 2414(TCC) confirmed that parties can deal with the risk of concurrent delay through contractual wording. Judgement: the contractual wording added was a clear agreement dealing with the proper approach to consideration of the appropriate extension of time in situations of concurrent delay, when one cause would otherwise entitle the contractor to such an extension (absent the concurrent event) but the other cause would not. The contractor is not entitled to an extension of time in that situation.

8 Concurrent Delays

9 Concurrency - principles Three commonly recognised approaches for dealing with the time aspects of concurrency: The first-in-line The dominant cause approach The apportionment approach The choice of approach will depend on the circumstances: The contract conditions The prevailing case law The context, the pragmatism and common sense

10 Concurrency - principles Scenario

11 Concurrency - principles First-In-Line (Scenario 1)

12 Concurrency - principles Dominant Cause (Scenario 2)

13 Concurrency - principles Apportionment (Scenario 3)

14 Typical delay scenarios principles

15 Typical delay scenarios principles EVENT 1 NO DELAY TO COMPLETION

16 Typical delay scenarios principles EVENT 1 CRITICAL PATH UNCHANGED

17 Typical delay scenarios principles EVENT 2 - NO DELAY TO COMPLETION, CRITICAL PATH UNCHANGED

18 Typical delay scenarios principles EVENT 3 DELAY TO START OF TASK 3

19 Typical delay scenarios principles EVENT 3 - NO DELAY TO COMPLETION, CRITICAL PATH UNCHANGED

20 Typical delay scenarios principles EVENT 4 CASCADING EFFECT TO TASK 3 AND TASK 4

21 Typical delay scenarios principles EVENT 4 - CRITICAL DELAY TO COMPLETION WITH CHANGE OF CRITICAL PATH

22 Setting up the delay analysis programme principles

23 Setting up the delay analysis programme 10 principles Scope: cover the entire Project scope (all phases and all disciplines). Milestones: Contractual Milestones (commercial and technical) and Key Project Milestones (main interfaces) placed at the top of the programme. Baseline: The Project Baseline reflects the sequence contractually agreed with the Employer, including any approved Variations. WBS structure: The Project programme structure should mirror the WBS.

24 Setting up the delay analysis programme 10 principles Logic Links: All activities should be linked to reflect the execution logic. Critical Path: The main Critical path and sub-critical paths clearly identified. Regular updates: The Project programme should be updated on a regular basis (reflecting standard business practices and/or the specific Contract requirements)

25 Setting up the delay analysis programme 10 principles Assumptions: An assumption note summarizing the key hypothesis for the elaboration of the baseline(s) should support the initial baseline and any subsequent updated baseline(s). Work and Cost structure: The project programme structure should be mapped to the Project cost structure. Claiming rules: The method of capturing physical progress should be defined at the beginning of the Project.

26 Delay analysis choices and methodology

27 AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS Table 1 Nomenclature correspondence (commonly names for classification)

28 SCL Delay and disruption Protocol 2 nd Edition February 2017 Six commonly use methods of delay analysis

29 Delay analysis IMPACTED AS-PLANNED

30 IMPACTED AS PLANNED ANALYSIS As Planned programme (logic linked) Impact Event 1 on the As Planned programme

31 IMPACTED AS PLANNED ANALYSIS Reschedule after Event 1 identification of delay 1 Impact Event 2 on the previous programme

32 IMPACTED AS PLANNED ANALYSIS ADVANTAGES 1) Simple, based on the As Planned programme with critical path 2) Easy to understand and communicate 3) No need of As Built programme (only relevant data for the events impacted) 4) Quick to implement 5) Method widely used by Contractors DISADVANTAGES 1) The Baseline is usually irrelevant after the first update 2) Difficult to demonstrate acceleration, mitigation and/or concurrency 3) Needs to impact separately the Contractor events and the Employer events 4) Almost no judicial support, weak results (theoretical conclusions) 5) Ignores actual progress Reschedule after Event 2 identification of delay 2

33 Delay analysis TIME IMPACT

34 TIME IMPACT ANALYSIS As Planned programme (logic linked) Update progress before Event 1 & reschedule

35 TIME IMPACT ANALYSIS Impact Event 1 into the activity network Reschedule after Event 1 = Delay 1

36 TIME IMPACT ANALYSIS Update progress & reschedule before Event 2 = no delay Impact Event 2 into the activity network

37 TIME IMPACT ANALYSIS ADVANTAGES 1) Simple, based on the As Planned programme with critical path 2) Easy to understand and communicate 3) Can demonstrate acceleration, mitigation and/or concurrency 4) Relies on the actual progress of the works 5) Method widely used by Contractors, sometimes recognised by the Courts DISADVANTAGES 1) Requires a robust/ correct Baseline programme 2) Time consuming, especially on complex projects 3) When used prospectively, can predict only the likely effect of events 4) Can generate theoretical conclusions if as built data is insufficient 5) Expensive to produce, relies on programming skills and experience Reschedule after Event 2 = Delay 2

38 Delay analysis TIME SLICE WINDOWS

39 TIME SLICE WINDOW ANALYSIS As Planned programme (logic linked) Update progress at Window 1 date

40 TIME SLICE WINDOW ANALYSIS Reschedule at Window 1 date identify delay at W1 Update progress at Window 2 date

41 TIME SLICE WINDOW ANALYSIS Reschedule at Window 2 date identify delay at W2 Update progress at Window 3 date

42 TIME SLICE WINDOW ANALYSIS Reschedule at Window 3 date identify any delay Update progress at Window 4 date

43 TIME SLICE WINDOW ANALYSIS ADVANTAGES 1) Simple, based on the As Planned programme with critical path 2) Easy to understand and communicate 3) Can demonstrate acceleration, mitigation and/or concurrency 4) Takes into consideration the actual progress of the works 5) Method widely used by Contractors. DISADVANTAGES 1) Requires a robust/ correct Baseline programme 2) Requires accurate As Built information 3) Difficulties when applied to sequences of work which are different from the planned intentions 4) Can generate theoretical conclusions if as built data is insufficient 5) Not suitable for complex projects with multiple planned critical paths Reschedule at Window 4 date identify delay at W4

44 Delay analysis COLLAPSED AS-BUILT

45 COLLAPSED AS BUILT ANALYSIS As Built programme (without logic links) Reconstructed (Analogous) As Built logic

46 COLLAPSED AS BUILT ANALYSIS Identification of Events 1 and 2 (as built data) Collapse Event 2 (zero duration)

47 COLLAPSED AS BUILT ANALYSIS Reschedule to identify the effect of collapsing Event 2 Collapse Event 1 (zero duration)

48 COLLAPSED AS BUILT ANALYSIS ADVANTAGES 1) The concept is simple, easy to understand 2) Does not need an As Planned programme 3) Relies upon the actual progress of the works 4) Based on records of actual events 5) No requirement to demonstrate the reasonableness of the baseline programme DISADVANTAGES 1) Subjective reconstruction of the Analogous (As Built) critical path 2) Very difficult to assess acceleration and/or mitigation measures implemented during the works 3) The programme/ progress updates during the works are ignored 4) Requires accurate As Built information 5) Requires hand-on experience in preparing the analysis Reschedule to identify the effect of collapsing Event 1

49 CONCLUSIONS RECCOMENDATIONS FOR MAKING AND PRESENTING DELAY CLAIMS Consideration of specific Contract requirements Consideration of the balance between the costs to produce a delay claim and the magnitude of the dispute Agreement on the Baseline programme and subsequent updates of the same Agreement on the method of delay analysis to be applied Treatment of each event separately, with focus on demonstrating: - Entitlement under the Contract - Timely Notice given - Cause of the delay - Effect of the event on the programme Use simple language, free from jargon Demonstrate that the results are grounded in common sense

50 THANK YOU

Mitigating Delay Claims and Scheduling Best Practices

Mitigating Delay Claims and Scheduling Best Practices Mitigating Delay Claims and Scheduling Best Practices Prepared and Presented by: Raquel Speers Shohet, EI, PSP Hill International, Inc. Claims and Consulting Group 10801 W. Charleston Blvd. Suite 650 Las

More information

PROSPECTIVE Vs. RETROSPECTIVE DELAY ANALYSIS. MASIN PROJECTS PRIVATE LIMITED (

PROSPECTIVE Vs. RETROSPECTIVE DELAY ANALYSIS. MASIN PROJECTS PRIVATE LIMITED ( PROSPECTIVE Vs. RETROSPECTIVE DELAY ANALYSIS BY:- ROHIT SINGHAL, SHISHIR KANT, ADARSH KUMAR MASIN PROJECTS PRIVATE LIMITED (www.masinproject.com) Page 1 of 10 ABSTRACT Infrastructure, construction and

More information

Project Delays and Extensions of Time. Dr Tony Farrow

Project Delays and Extensions of Time. Dr Tony Farrow Project Delays and Extensions of Time Dr Tony Farrow Topics 1. Why Extensions of Time? 2. Methods of Analysis and examples 3. Schedule Float 4. Concurrent Delay 5. Exercise 6. Questions Construction Contracts

More information

Evaluating Schedule Impacts. By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06

Evaluating Schedule Impacts. By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06 Evaluating Schedule Impacts By: Wendy Kaszycki, PE Randa Jarjour, CCE 12/06/06 Overview Definitions Methods of Evaluating Delays Best Practices 2 Classification of Project Delays (Risk Point of View) Non-excusable

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract

More information

TIME IS MONEY OR IS IT? (PART 2)

TIME IS MONEY OR IS IT? (PART 2) TIME IS MONEY OR IS IT? (PART 2) In Part 1 of this article we reviewed the legal and contractual principles which apply to the time for completion of construction works and the remedies available to both

More information

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation

More information

SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL

SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL 2nd edition February 2017 www.scl.org.uk Published by the Society of Construction Law (UK), 234 Ashby Road, Hinckley, Leicestershire, LE10 1SW.

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE

DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE Andrew Burr MA(Cantab), ACIArb, FFAVE(Master) ArbDB Chambers Silver Shemmings LLP London 1. Delay and disruption:

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Richard J. Long, P.E. and Rod C. Carter, CCP, PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

International Construction Projects Committee

International Construction Projects Committee International Construction Projects Committee Time Related Obligations in Key Jurisdictions: An Update 21 September 2016 Richard Bailey Goodman Derrick LLP London, England Polina Chtchelok ESPCs Multidisciplinary

More information

The Project Times and Costs

The Project Times and Costs The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step

More information

SPECIAL TENDER CONDITIONS FOR THE

SPECIAL TENDER CONDITIONS FOR THE Page 1 SPECIAL TENDER CONDITIONS FOR THE Integrated Applications Promotion (IAP) Programme (CALL FOR PROPOSALS) FEASIBILITY STUDIES Page 2 A. INTRODUCTION The following documents are available on http://emits.esa.int/

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management Running head: UNIT 3 RESEARCH PROJECT 1 Unit 3 Research Project Eddie S. Jackson Kaplan University IT511: Information Systems Project Management 04/06/2014 UNIT 3 RESEARCH PROJECT 2 Unit 3 Research Project

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION SCHEDULE F BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION cl. 7.3.1, 9.1.1 F1 Qualitative information required in a base capex proposal For the purpose of clause 7.3.1 (1) a base capex proposal must, in

More information

A VIEW FROM ACROSS THE POND: AN AMERICAN PERSPECTIVE ON THE SCL DELAY AND DISRUPTION PROTOCOL

A VIEW FROM ACROSS THE POND: AN AMERICAN PERSPECTIVE ON THE SCL DELAY AND DISRUPTION PROTOCOL A VIEW FROM ACROSS THE POND: AN AMERICAN PERSPECTIVE ON THE SCL DELAY AND DISRUPTION PROTOCOL A paper given to a meeting of the Society of Construction Law in London on 8th May 2006 Richard H Lowe, Evans

More information

General Principles of Contract Management

General Principles of Contract Management General Principles of Contract Management Training to DEME (2016) Mark Castell Regional Managing Director mark.castell@drivertrett.com www.drivertrett.com What we do Our dispute and advisory team, delivering

More information

Project Management -- Developing the Project Plan

Project Management -- Developing the Project Plan Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing

More information

Against All Odds. TE&A's Special Edition Issue. by Clive Horridge

Against All Odds. TE&A's Special Edition Issue. by Clive Horridge Against All Odds TE&A's Special Edition Issue by Clive Horridge Against All Odds by Clive Horridge Page 2 of 12 Not just a Phil Collins song-title depicting a common scenario of dispair, it is the case

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Somewhere in Time - Securing and Protecting your Contractual Rights

Somewhere in Time - Securing and Protecting your Contractual Rights Howard KLEIN, United Kingdom Keywords: Ascertaining Delays, Delay Costs, Notice, Provisions, Extension of Time, Records, Construction Economics. SUMMARY Time is money and this is no less the case on construction

More information

Contractor s Legal Guidance Note

Contractor s Legal Guidance Note Contractor s Legal Guidance Note Spring Edition 2010 Express Acceleration This Spring edition of the Contractor s Legal Guidance Bulletin picks up where the Autumn 2009 edition left off, by moving on from

More information

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA This section is used for projects over $1,000,000 use other section if less than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract

More information

Proving and Tracking Damages of your Claim

Proving and Tracking Damages of your Claim Proving and Tracking Damages of your Claim Jeffrey E. Fuchs, PE, CPA 1 1. Compensability 2. Excusability of a Delay 3. How is Compensable Delay Priced? 4. Costs and Rates 5. What Should a Schedule Expert

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS

VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS S108C00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY III PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted

More information

54R07 RECOVERYSCHEDULI PROCUREMENT,AND CONSTRUCTI

54R07 RECOVERYSCHEDULI PROCUREMENT,AND CONSTRUCTI E 54R07 SA M PL RECOVERYSCHEDULI NGASAPPLI EDI NENGI NEERI NG, PROCUREMENT,AND CONSTRUCTI ON AACE International Recommended Practice No. 54R-07 RECOVERY SCHEDULING AS APPLIED IN ENGINEERING, PROCUREMENT,

More information

SECTION PROGRESS SCHEDULE

SECTION PROGRESS SCHEDULE NOTE: Review this section carefully. If Project Scope is complex this Specification is to be used. If project is relatively simple and straightforward use Section 01310. SECTION 01311 PART 1 GENERAL 1.1

More information

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof, L 244/12 COMMISSION IMPLEMTING REGULATION (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU)

More information

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager lobowfok@icloud.com Mobile: 9819 4463 17 January 2017 Note: This set of notes has

More information

FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment

FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment Acknowledgments: (June 23, 2009 Revision) Kenji P. Hoshino, PSP CFCC (Author)

More information

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

The Mystery of Earned Value - An Oil & Gas Owner s Perspective The Mystery of Earned Value - An Oil & Gas Owner s Perspective 15 June 2011 William Harroun Head of Programme Controls, BG Group What we are going to cover Cost and progress reporting before --- Earned

More information

Session 3 by Zoltán Záhonyi, FIDIC AIT,

Session 3 by Zoltán Záhonyi, FIDIC AIT, Session 3 by Zoltán Záhonyi, FIDIC AIT, zoltan.zahonyi@zandpartners.com Contents of Session 3 Session 3: FIDIC 1999 Red Book Part 2 The Quality Issues (Plant, Materials and Workmanship) The Time is of

More information

How to Satisfy GAO Schedule Best Practices

How to Satisfy GAO Schedule Best Practices By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document

More information

Risk Management Plan for the Ocean Observatories Initiative

Risk Management Plan for the Ocean Observatories Initiative Risk Management Plan for the Ocean Observatories Initiative Version 1.0 Issued by the ORION Program Office July 2006 Joint Oceanographic Institutions, Inc. 1201 New York Ave NW, Suite 400, Washington,

More information

CUK Insider s Guide to IR35

CUK Insider s Guide to IR35 The UK's most visited IT Contractor Site - Online since 1998 CUK Insider s Guide to IR35 Compiled with from advice from Ray McMahon, ex Tax Inspector Contents: What is IR35? 2 How will I know if I m caught

More information

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M. Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project

More information

Decommissioning Basis of Estimate Template

Decommissioning Basis of Estimate Template Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare

More information

Earned Value Management Training Program

Earned Value Management Training Program Earned Value Management Training Program Course Brochure and Competency Matrix INDEX: 1. Company Introduction 2. Training Programme Description 3. Training Delivery Options 4. Course Syllabus 5. Programme

More information

Appendix K Model Letters for Use by the Engineer

Appendix K Model Letters for Use by the Engineer 175 Model Letters for Use by the Engineer Introduction This Appendix provides model letters for use by the Engineer primarily for formal correspondence with the Contractor. These model letters do not distinguish

More information

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs)

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs) Integrated Baseline Reviews (IBRs) Holding an IBR is a best practice for all programs, and it supports the implementation of an earned value management system (EVMS). EVM can be a valuable tool for controlling

More information

PROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr.

PROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr. PROPOSED SHARED SAVINGS (VALUE ENGINEERING) CLAUSE FOR GPO CONTRACTS OVER $100,000 OR NEW TECHNOLOGY. Prepared by Fred Antoun, Jr. (a) General. The Contractor is encouraged to develop, prepare, and submit

More information

A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT

A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT A COMPREHENSIVE PRACTICE OF PRE-ALLOCATION OF TOTAL FLOAT IN THE APPLICATION OF A CPM-BASED CONSTRUCTION CONTRACT JESÚS DE LA GARZA 1 AND APIRATH PRATEAPUSANOND 2 1-2 Charles E. Via, Jr. Department of

More information

DATA ITEM DESCRIPTION. Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date:

DATA ITEM DESCRIPTION. Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date: DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date: 20150916 AMSC Number: D9583 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing

More information

Proving and Tracking Damages of your Claim

Proving and Tracking Damages of your Claim Proving and Tracking Damages of your Claim J. Mark Dungan October 6, 2017 1 Schedules: Back to Basics I. CPM Scheduling Basics II. The Baseline Schedule III. The Schedule Update IV. Delay Analysis V. Proving

More information

Project planning and creating a WBS

Project planning and creating a WBS 37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and

More information

Revenue from Contracts with Customers

Revenue from Contracts with Customers International Financial Reporting Standard 15 Revenue from Contracts with Customers In April 2001 the International Accounting Standards Board (IASB) adopted IAS 11 Construction Contracts and IAS 18 Revenue,

More information

SIGMA Public Procurement Training Manual. Update 2015

SIGMA Public Procurement Training Manual. Update 2015 SIGMA Public Procurement Training Manual Update 2015 Module G 2 Rue André Pascal 75775 Paris Cedex 16 France mailto:sigmaweb@oecd.org Tel: +33 (0) 1 45 24 82 00 Fax: +33 (0) 1 45 24 13 05 www.sigmaweb.org

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

AiM User Guide Capital Planning and Project Management (CPPM) System

AiM User Guide Capital Planning and Project Management (CPPM) System AiM User Guide Capital Planning and Project Management (CPPM) System 2011 AssetWorks Inc. 1777 NE Loop 410, Suite 1250 San Antonio, Texas 78217 (800) 268-0325 TABLE OF CONTENTS INTRODUCTION... 5 CHAPTER

More information

Programmatic Risk Management in Space Projects

Programmatic Risk Management in Space Projects r bulletin 103 august 2000 Programmatic Risk Management in Space Projects M. Belingheri, D. von Eckardstein & R. Tosellini ESA Directorate of Manned Space and Microgravity, ESTEC, Noordwijk, The Netherlands

More information

PM TUTORIAL. Notes On Project Requirements

PM TUTORIAL. Notes On Project Requirements PM TUTORIAL Notes On Project Requirements Requirements are the first and most important thing to define on any project, spend real time making sure your requirements are adequate before any significant

More information

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES

SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES March 1, 2007 SUPPLEMENTAL SPECIFICATION CRITICAL PATH METHOD CONSTRUCTION SCHEDULES General This supplemental specification addresses the Critical Path Method (CPM) construction schedule requirements

More information

THREE PEER REVIEWED GUIDES ON FORENSIC SCHEDULE DELAY ANALYSIS - A COMPARISON

THREE PEER REVIEWED GUIDES ON FORENSIC SCHEDULE DELAY ANALYSIS - A COMPARISON GLOBAL CONSTRUCTION THREE PEER REVIEWED GUIDES ON FORENSIC SCHEDULE DELAY ANALYSIS - A COMPARISON John Livengood, Managing Director, Navigant San Francisco, CA There are three peer-reviewed institutional

More information

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time

More information

MnDOT use of Calendars in Primavera P6

MnDOT use of Calendars in Primavera P6 MnDOT Project Management Office Presents: MnDOT use of Calendars in Primavera P6 Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be

More information

Association for Project Management 2008

Association for Project Management 2008 Contents List of tables vi List of figures vii Foreword ix Acknowledgements x 1. Introduction 1 2. Understanding and describing risks 4 3. Purposes of risk prioritisation 12 3.1 Prioritisation of risks

More information

Contents Introduction Chapter 1 - Security Policy... 6

Contents Introduction Chapter 1 - Security Policy... 6 Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...

More information

Joint Office of Gas Transporters 0231: Changes to the Reasonable Endeavours Scheme to better incentivise the detection of Theft

Joint Office of Gas Transporters 0231: Changes to the Reasonable Endeavours Scheme to better incentivise the detection of Theft Workstream Report Changes to the Reasonable Endeavours Scheme Modification Reference Number 0231 Version 3.0 This Workstream Report is presented for the UNC Modification Panel's consideration. The Distribution

More information

Claim Avoidance on Highway Projects

Claim Avoidance on Highway Projects Claim Avoidance on Highway Projects Joseph R. Hellenbrand, P. E., PSP Capital Project Management, Inc. ASHE National Conference Bismarck, North Dakota June 13, 014 1 Joe Hellenbrand P.E.; PSP 0 years of

More information

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Implementing the Construction Supply Chain Payment Charter. January Guidance Note Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and

More information

PACING DELAY. Project Controls Expo 18 th Nov Emirates Stadium, London. The Practical Effect on Construction Projects & Delay Claims

PACING DELAY. Project Controls Expo 18 th Nov Emirates Stadium, London. The Practical Effect on Construction Projects & Delay Claims Project Controls Expo 18 th Nov 2014 Emirates Stadium, London PACING DELAY The Practical Effect on Construction Projects & Delay Claims About the Speaker Philip M. Spinelli Director, Navigant Consulting,

More information

Practice Notes. to the Multilateral Master Confirmation Agreement for Non-Deliverable FX Transactions

Practice Notes. to the Multilateral Master Confirmation Agreement for Non-Deliverable FX Transactions Practice Notes to the Multilateral Master Confirmation Agreement for Non-Deliverable FX Transactions Introduction The Foreign Exchange Committee (FXC), EMTA, Inc. (EMTA), and the FX Joint Standing Committee

More information

STRATEGIC ACTION PLAN GUIDELINES & MODEL

STRATEGIC ACTION PLAN GUIDELINES & MODEL Innovation and Networks Executive Agency STRATEGIC ACTION PLAN GUIDELINES & MODEL Background Article II.2.4 of the standard text of the Commission Decisions granting Community financial aid for projects

More information

IFRS News. Special Edition on IFRS 9 (2014) IFRS 9 Financial Instruments is now complete

IFRS News. Special Edition on IFRS 9 (2014) IFRS 9 Financial Instruments is now complete Special Edition on IFRS 9 (2014) IFRS News IFRS 9 Financial Instruments is now complete Following several years of development, the IASB has finished its project to replace IAS 39 Financial Instruments:

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE [---Section 01315A should be used for contracts for which a fully-developed computergenerated critical path method is appropriate for managing

More information

IFRS 15 for automotive suppliers

IFRS 15 for automotive suppliers IFRS 15 for automotive suppliers Are you good to go? Application guidance December 2017 Contents Contents Purpose of this document 1 What may change? 2 1 Tender offer phase Nomination fees 4 2 Framework

More information

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

SCHEDULE CREATION AND ANALYSIS. 1   Powered by POeT Solvers Limited SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project

More information

LONG INTERNATIONAL. James M. Bolin

LONG INTERNATIONAL. James M. Bolin James M. Bolin LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com James M. Bolin Table of

More information

SECTION PROJECT SCHEDULE 08/08

SECTION PROJECT SCHEDULE 08/08 SECTION 01 32 01.00 10 PROJECT SCHEDULE 08/08 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR SECTION 109 MEASUREMENT AND PAYMENT SECTION 102.01 PREQUALIFICATION OF BIDDERS of the Specifications is amended as follows: The eighth paragraph is replaced by the following: When the Contractor's actual progress is more than 10 percent

More information

Sheila Belayutham CHAPTER 6 CONTROL

Sheila Belayutham CHAPTER 6 CONTROL CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s

More information

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract

More information

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

Integrated Baseline Review

Integrated Baseline Review Integrated Baseline Review How To Achieve Project Success by Establishing a Realistic Baseline and Involving your Customer Eleanor Haupt Earned Value Associates LLC ehaupt@earnedvalue.biz 937-572-2586

More information

The Water Industry Commission for Scotland Scottish Water Scottish Water

The Water Industry Commission for Scotland Scottish Water Scottish Water The Water Industry Commission for Scotland Scottish Water Scottish Water Reporter s Report SR10 2 nd Draft Business Plan Appendix C Investment and Outputs Plan April 2009 SCOTTISH WATER REPORTER S REPORT

More information

PART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder

PART 3. Lump Sum Design-Build Agreement Between Department and Design-Builder PART 3 Lump Sum Design-Build Agreement Between Department and Design-Builder This AGREEMENT is made as of the day of in the year of, by and between the following parties, for services in connection with

More information

LPM ADVANCED: USING LEGAL PROJECT MANAGEMENT IN LITIGATION

LPM ADVANCED: USING LEGAL PROJECT MANAGEMENT IN LITIGATION LPM ADVANCED: USING LEGAL PROJECT MANAGEMENT IN LITIGATION Presented by the American Bar Association Law Practice Division, Center for Professional Responsibility, Section of Litigation and Center for

More information

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996 LIFE YLE Good Practice Guide ASSET MANAGEMENT Project Management Overview March 1996 Department of Energy Office of Field Management Office of Project and Fixed Asset Management ontents 1. INTRODUTION...1

More information

Construction Project Management from the Owner s Perspective

Construction Project Management from the Owner s Perspective Construction Project Management from the Owner s Perspective Presented at: IMUA 2013 Annual Meeting May 21, 2013 Page 1 Agenda Introduction to Risk Management Risk through the Project Life Cycle Project

More information

Mahmoud Abu Hussein 1

Mahmoud Abu Hussein 1 Mahmoud Abu Hussein 1 The White Book Review A Client s Perspective Contents The White Book Highlights The White Book Review (areas of concern/suggested amendments) Conclusion/Recommendations 2 The White

More information

Can a Contractor Be Entitled to a Time Extension If The Delay Is Not Critical?

Can a Contractor Be Entitled to a Time Extension If The Delay Is Not Critical? Can a Contractor Be Entitled to a Time Extension If The Delay Is Not Critical? Presented by Mark Nagata, PSP, Director/Shareholder, Trauner Consulting Services, Inc. 8/14/17 Meet Your Presenter, Mark Nagata,

More information

FUTURE CONCRETE 2014 QATAR

FUTURE CONCRETE 2014 QATAR FUTURE CONCRETE 2014 QATAR Delay and Disruption in the Construction of Mega Projects Dr. Khaled Ahmed Al-Naas 2 nd December 2014 Background Generally projects face delay and disruption especially the mega/complex

More information

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.) Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

Response to Ofcom s consultation on price rises in fixed term contracts

Response to Ofcom s consultation on price rises in fixed term contracts Response to Ofcom s consultation on price rises in fixed term contracts 14 March 2013 Price rises in fixed term contracts Ombudsman Services consultation response 1 Summary 1.1 About Ombudsman Services

More information

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet. . Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your

More information

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES PROLONGATION COST CLAIMS THE BASIC PRINCIPLES HKA Quantum Expert Craig Enderbury sets out the basic principles of prolongation cost claims using a simple and hypothetical example. He highlights the common

More information

Qualification Programme Examination Panelists Report. Final Examination (June 2016 Session) Paper I

Qualification Programme Examination Panelists Report. Final Examination (June 2016 Session) Paper I Qualification Programme Examination Panelists Report Final Examination (June 2016 Session) (The main purpose of the following report is to summarise candidates common weaknesses and make recommendations

More information

CONSTRUCTION DOCUMENTATION PREPARATION PROTECTING THE EMPLOYER WITHOUT BEING UNFAIR TO THE CONTRACTOR

CONSTRUCTION DOCUMENTATION PREPARATION PROTECTING THE EMPLOYER WITHOUT BEING UNFAIR TO THE CONTRACTOR CONSTRUCTION DOCUMENTATION PREPARATION PROTECTING THE EMPLOYER WITHOUT BEING UNFAIR TO THE CONTRACTOR ACKNOWLEDGEMENT I acknowledge with sincere appreciation the assistance of Professor Doug Jones AM and

More information

Litigation & Claims Facts & Figures

Litigation & Claims Facts & Figures Litigation & Claims Facts & Figures Paul Lomas-Clarke FRICS FCIArb FCIOB CEDR Accredited Mediator Executive Director 2011 The Global Leader in Managing Construction Risk The reasons claims arise Inadequate

More information

BEPS ACTION 8 - IMPLEMENTATION GUIDANCE ON HARD-TO- VALUE INTANGIBLES

BEPS ACTION 8 - IMPLEMENTATION GUIDANCE ON HARD-TO- VALUE INTANGIBLES BEPS ACTION 8 - IMPLEMENTATION GUIDANCE ON HARD-TO- VALUE INTANGIBLES PUBLIC DISCUSSION DRAFT 30 June 2017 Copenhagen Economics welcomes the opportunity to comment on the OECD s Discussion Draft on Implementation

More information

FIDIC 2017 First Impressions of the 3-Kilo Suite Kilo

FIDIC 2017 First Impressions of the 3-Kilo Suite Kilo FIDIC 2017 First Impressions of the 3-Kilo Suite Kilo Written by Edward Corbett 08/12/2017 In London this week, FIDIC launched its Second Editions of the Red, Yellow and Silver Books. They are big, weighing

More information