Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Size: px
Start display at page:

Download "Standard forms of partnering contracts The ultimate contractual commitment? Part 4"

Transcription

1 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard forms of partnering contract currently available. The first article in the series provided an introduction to partnering by identifying its ethos, history, aims and so on, and by setting its fundamental difference to conventional (confrontational) contracting forms. The second article set out how the relevant different standard forms of partnering contract address the corporate and personnel commitment to partnering. The third article considered how the forms address issues related to time. This fourth article considers how the forms address issues related to the cost of the project to the client and associated safeguards, together with the value to the contractor and associated incentives. Following the pattern in the previous articles, the forms are considered in the same order and in isolation from each other. It may be necessary for the reader to consult the previous articles in the series to understand some of the terminology used in relation to the general structure of the arrangements. PPC2000 As previously noted, the Association of Consultant Architects Standard Form of Contract for Project Partnering (PPC2000) envisages two distinct phases of a project; pre-construction under the project partnering agreement and construction under the commencement agreement. The project price is an agreed maximum price, which may be defined as the price for the project payable by the client to the constructor, and is to be developed and agreed during the pre-construction phase after the signing of the project partnering agreement and prior to signing of the commencement agreement. So, unlike most traditional forms of contract in which the contract price is effectively only the starting point from which the contractor s various entitlements for additional reimbursement commence, with this style of contract, it is clearly set out, right from the outset, that all the collaborating parties have the joint ultimate objective of coming in under the agreed maximum price. It is supported by detail in the price framework and comprises the following: Constructor profit, central office overheads and site overheads. Amounts built up through approved business cases for constructor proposals in respect of direct labour packages (work done by the constructor itself) and approved business cases in respect of preferred specialists (work done by specialist subcontractors, suppliers and subconsultants approved pursuant to single source proposals, without specialist tenders). Amounts built up through approved results of specialist tenders. Provisional sums (for all work remaining to be priced during the construction phase of the project). Risk contingencies approved after joint risk management processes (for risks priced by the constructor).

2 The agreed maximum price is subject to increase or decrease in accordance with the agreed change procedure (clause 17) and in the event of claims for listed unforeseeable instances of delay or disruption (clause 18) and any specific mechanisms stated in the price framework. However, the word 'maximum' is a reminder that the partnering team should continue to seek to make savings in the agreed maximum price wherever possible. Incentives may be set out within the partnering document or subsequently recommended to the client by the core group. Whilst there are no prescribed incentives, the form clearly envisages that the incentive schemes will provide for any cost savings, demonstrable added value and cost overruns to be shared between the relevant partners, and these are addressed in a little more detail in the next article in this series. A change (clause 17) may be in all or any part of the project by way of addition, omission or variation of any kind, or by way of expenditure of a provisional sum. Any partnering team member may propose a change to the client at any time, provided it is demonstrably in the best interests of the project; and the client may propose a change to the constructor and the other partnering team members at any time. If the client approves a change proposed by a partnering team member, it is referred to the constructor as if it were the client s proposal, thereby triggering the valuation process. The constructor submits a change submission in response to the client s proposal, comprising the constructor s proposals as to any effect on the agreed maximum price and any effect on the progress of the project and date of completion. The client shall seek to agree the submission with the constructor and responds within five days by either instructing or withdrawing the proposed change. If the change is instructed, but the client and constructor have not agreed the time and/or cost implications within 20 days of the instruction, the client s representative shall ascertain the cost and/or time effects of the change. The effects are to be ascertained on a fair and reasonable basis, utilising wherever possible relevant periods of time in the partnering or project timetable and prices for similar work in the price framework, and the constructor is notified accordingly. In the event that the constructor disagrees with the notified cost and/or time effects, it gives a notice of dispute within a further 20 days, failing which the agreed maximum price and date for completion are adjusted in line with the client s representative s assessment. If this all sounds rather prescriptive, then that is because it is! But it is, like the NEC requirements, a considerable practical aid to driving the parties to collective commitment to help each other and meet the necessary timescales to avoid insidious disagreement from establishing and then festering. If any of the relevant unforeseeable events of delay or disruption (clause 18) occurs and gives rise to an extension of the date of completion, the constructor is reimbursed on the basis of the site overheads that have been agreed, within the price framework, to be time-based. Where any of the relevant unforeseeable events occurs and properly requires unavoidable additional work or expenditure, the cost effect is to be calculated on an open-book (a defined term in the contract, see below) basis and does not include any profit, central office overheads or loss of profit on other projects. PPC2000 adopts an open-book approach to the actual cost, which is defined as:

3 ...involving the declaration of all price components including profit, central office overheads, site overheads and the costs of materials, goods, equipment work and services, with all relevant books of account, correspondence, agreements, orders, invoices, receipts and other relevant documents available for inspection. Open-book approaches are adopted in the construction phase for the calculation of unavoidable additional work or expenditure under clause 18 as noted above, and also for adjustment of any provisional sums that have been included within the agreed maximum price. Details, such as trade discounts and other financial benefits derived from the constructor's arrangements with its own supply chain, should also be disclosed when calculating the agreed maximum price. Whilst this may sound rather intrusive when judged against traditional arrangements, the approach to open-book under PPC2000 is explicitly more open than open-book arrangements under other partnering forms. Within the context of the agreement of the agreed maximum price itself, the open-book principles are also adopted for the presentation of the business cases and so on, noted above. There is also the option, by agreement within the price framework, for a fully open-book approach to be adopted throughout the project and that all or part of the agreed maximum price will be paid to reimburse actual expenditure by the constructor whether or not limited or linked to any shared excess or shortfall against a target cost. In this case, the open-book approach will be used to calculate all payments due. SPC2000 The terms in the Standard Form of Specialist Contract for Project Partnering (SPC2000) are generally back to back with those contained in PPC2000 in the way that would be expected from a subcontract written to be used by the constructor (contractor) as the method for employing its specialists (subcontractors). TPC2005 The terms in the Standard Form of Contract for Term Partnering (TPC2005) are generally consistent with the terms of PPC2000. NEC3 The issue of the outturn cost of a project to the employer is a declared fundamental aspect of the overall management of a project under any of the various optional forms of the Institution of Civil Engineers Engineering and Construction Contract third edition (NEC3). The forms are drafted such as to encourage collaboration between the employer s agents (the project manager) and the contractor. However, in adopting a partnering approach to a project, or a programme of projects, involving a wider participation than just employer and contractor, the NEC X12 partnering option provides the standardised mechanism for achieving that collaboration. The form of the contract cost and its subsequent adjustment is dependant on the primary option used for the own contract under the partnering umbrella. Option A: Priced contract with activity schedule

4 Essentially a lump sum contract; the final sum is the total of the prices for all activities. Option B: Priced contract with bill of quantities A remeasurement contract; the final sum is based on the actual quantities of completed work valued at bill rates. Option C: Target contract with activity schedule A target contract with a lump sum base; the final sum is the defined cost plus or minus a share of any saving or excess compared to the target. Option D: Target contract with bill of quantities A target contract with a bill of quantities base; the final sum is the defined cost plus or minus a share of any saving or excess compared to the target (which is remeasured based on the actual quantities of completed work valued at bill rates). Option E: Cost reimbursable contract The final sum is the defined cost plus the fee. Option F: Management contract The final sum is the defined cost plus the fee. The above schedule of options demonstrates a reducing degree of price certainty from A to F and, in consequence, an increasing level of risk for the employer following the same scale. The adjustment to the contract sum (total of the prices) to reflect change is by way of compensation events in all of the options. Compensation events are those events for which the contractor becomes entitled to an assessment of both the financial and time implications of a change, the assessment of which reflects one of the more radical departures that the NEC has taken from traditional principles. The assessment of the financial effect is based not on the contents of the activity schedule or bill of quantities, as the case may be, but is based on the actual or forecast defined cost using the schedule or shorter schedule of cost components. The premise behind this is that the contractor should be neither better off, nor worse off, for the change occurring; it is questionable about whether this premise has been achieved. Furthermore, it is intended that the financial and time effects of compensation events are pre-assessed contemporaneously and implemented within strict time limits, rather than being agreed and recognised retrospectively (and argumentatively!) as is usually the traditional method. Compensation events may be notified by either the contractor or the project manager, generally depending on who is better placed to be aware of the change. For example, the project manager should give notice of a compensation event arising from an instruction. If the project manager considers that the change may have an impact on time or cost it may instruct the contractor to provide a quotation for dealing with the compensation event. The contractor then has three weeks to submit the quotation and the project manager a further two weeks to respond by accepting the quotation or requesting a further

5 quotation which must be submitted within a further three weeks. In the event that the project manager fails to reply in time to a quotation, the contractor gives notice and if the default continues, the quotation is treated as having been accepted. The contract also provides for the project manager to assess the compensation event without the contractor s input if it considers that the contractor has not assessed it properly, or failed to submit a quotation within the required time or at all. The contract contains two negative incentives to the contractor: Firstly, if the contractor fails to give an early warning of any matter that might develop into a compensation event, then the assessment will be based on the costs that would have been incurred had the early warning been given. Secondly, if the contractor fails to notify a compensation event within eight weeks of becoming aware of it, the contractor is not entitled to cost or time, unless the project manager should have given the notification (again there are points of view which question whether this factor is legally robust). However, in practice these are not as clear-cut as they might appear and may require a detailed objective review of all of the surrounding facts before the proper implication of any apparent failure to give notice can be determined. As we have always said, collaborative partnering contracts do not automatically spread Disney-dust over the project; differing points of view still have to be thrashed out. The partnering forms simply provide a much more conciliatory and collaborative framework within which the traditional arm-wrestling still has to take place. The implementation of the compensation event results in the activity schedule or bill of quantities being adjusted accordingly and will impact on the cost to the employer and the value realised by the contractor. For main options C and D, the target is the total, as revised by the compensation mechanism of either the activity schedule (option C) or the bill of quantities (option D). The target cost options adopt an open-book approach for the assessment of the defined cost, which is not actual cost but is the cost of payment due to subcontractors plus the cost of components in the schedule of cost components, less disallowed cost. The fee is added to the defined cost to arrive at the price of work done to date (PWDD). The contractor is incentivised to keep its outgoings to a minimum by the use of a pain/gain share mechanism whereby the PWDD is compared to the adjusted target as the basis for the calculation of the share of any difference and the following generally applies: If the PWDD is less than the target, then the saving is shared between the employer and contractor in the specified proportions. If the PWDD is more than the target, then the extra cost is shared between the employer and contractor in the specified proportions. The contractor is obliged to keep the records of accounts and proof of payments of defined cost, communications relating to subcontractor s compensation events and any others stated in the works information. The contractor must allow the employer s project manager to inspect all such records and accounts.

6 An unusual feature of NEC (which was covered in more depth in our third article relating to time) relates to acceleration. Most forms of contract use the term acceleration to refer to the mitigation of delay in an attempt to complete the project on time. NEC, however, uses it to mean a formal shortening of the time allowed for completion, i.e. potentially the extended time to which, other things being equal, the contractor would have been entitled to if the requested shortening did not exist. This is arguably a much more contractually precise approach. The employer s project manager only has the power to request that the contractor submits a quotation to accelerate; it cannot instruct acceleration against the contractor s wishes. Partnering option X12 The X12 option itself does not contain any specific provisions relating to project cost; these are dealt with under the own contracts that are brought together by the use of X12. X12 does however have a collective incentive to performance that is unique within the range of forms under consideration. Where one partner lets the employer down for a particular target by poor performance, then all of the partners lose their bonus for that target. If the employer tries to prevent a target being met, it is in breach of clause 10.1 to act in a spirit of mutual trust and co-operation. Such collective responsibility is laudable but it is less popular with the insurers of individual parties' insurance cover. This is because insurers will cover their insured's liability but such liability may be triggered by default of another, not the insured. This issue can be addressed by putting in place a project insurance policy to cover all of the project participants. JCT Constructing Excellence and Project Team Agreement The Joint Contracts Tribunal Constructing Excellence and Project Team Agreement (CE) provides two payment options; target cost and contract sum. The target cost is agreed between the employer and the contractor (except that this form of contract describes them as the purchaser and the supplier) and will include allowance for risk. There is also the facility to introduce a guaranteed maximum cost which is the agreed upper limit that is recoverable by the supplier. The target cost option takes an open-book approach, i.e. records of actual costs are maintained by the supplier in a fully auditable manner and are made available to the purchaser whenever reasonably required for purposes of verification in connection with the project. The purchaser has to act reasonably, but may object to costs incurred by the supplier if they either constitute excluded costs, as defined, or are in excess of the amount that the supplier is entitled to receive since the cumulative actual cost exceeds either the target cost or guaranteed maximum cost. The contract provides (within section 7) that: If the actual cost is less than the target cost, then the saving is shared between the client and supplier in the specified proportions.

7 If the actual cost is more than the target cost, then the extra cost is shared between the client and supplier in the specified proportions. Any actual cost in excess of the guaranteed maximum cost is wholly borne by the supplier. Where the contract sum option is chosen, the parties will need to agree a payment schedule showing the payments due by reference to completed activities and/or milestones, or to progress against the project programme or any other method of assessment as may be agreed. Taking a leaf out of the NEC approach, there is also the further option to provide for the contract sum to be subject to remeasurement, in which case the amount of the contract sum will be an estimated sum based on rates and/or prices set out in the payment schedule. The payment schedule should show the dates on which the remeasurement will take place, the basis of the remeasurement and the rates or prices to be used. This remeasurement option has been included to allow flexibility in relation to the engagement of suppliers or subcontractors where it is either considered more cost effective or convenient to arrange payment in this way. The target cost and guaranteed maximum cost (if any) or the contract sum, as the case may be, are subject to increase or decrease in accordance with the conditions of contract. In essence, risks that are not reasonably foreseeable, beyond the control of the supplier and not referred to in the risk allocation schedule are relief events, the financial consequences of which are added to the cost or sum. If a relief event occurs, or is likely to occur, the partner who becomes aware of it shall immediately notify the other, and they shall co-operate in agreeing the best means of dealing with, and in mitigating, its effect. Not later than 10 business days after the notification, the supplier shall provide a statement setting out the effect that the relief event shall have on the cost of performing the services and/or the date or dates for completion. The purchaser and the supplier shall use reasonable endeavours to agree the effect of any relief event and shall co-operate to agree any action that mitigates any adverse effect. Once the effects are agreed or decided, the parties shall confirm, in writing, any change to the target cost and guaranteed maximum cost (if any), or to the contract sum and/or the date or dates for completion. As an incentive to the supplier, the purchaser shall, when considering the effect of any relief event which it was not aware of, take into account any delay on the part of the supplier in notifying the occurrence of a relief event after the date it became, or should reasonably have become, aware of it. The third article in the series that addressed the time provisions has already reviewed, in detail, the provision for the contract to provide damages for late completion and bonuses for early completion; the former reducing the payment to the supplier, the latter increasing the payment. Partnering charter non-binding The JCT partnering charter, as the above full title suggests, makes reference only to a non-binding list of objectives to be achieved by the partnering team, which are to be measured against performance indicators that are to be established as part of the partnering process, such as:

8 Commercial - Add value and enhance reputations. - Create incentives for maximising the rewards of all parties. - Provide transparency and certainty of information. - Provide feedback. Conclusions The impact of change can upset any carefully established balance of cost to the project client and value to the project contractor once the project moves from the state of euphoria that represents the conclusion of any pre-commencement courting of the parties to the reality of delivering a project within the modern construction environment. The way in which changes are dealt with is, therefore, a measure of the partnering spirit of the form. The various forms approach the contract sum in different ways; both PPC2000 and JCT CE provide for the relevant parties to the contract to set the amount through joint endeavours, whereas NEC assumes the amount is set by other, competitive, means. All the forms address the question of transparency of cost incurred by way of an open-book approach to the verification process, although the approach in PPC 2000 is more open than under the other partnering forms. The forms adopt a collaborative approach to assessing the financial effect of any changes; bringing an element of fairness to the process by basing the assessment on the additional cost incurred so that both parties, theoretically, are neither better off, nor worse off, for the change occurring. Incentives are used, in the main, to ensure compliance with contract procedures, although they may also produce a positive effect by driving down cost to the benefit of the project client and consequently increasing the profit margin of the project contractor. As we have commented previously, the partnering forms of contract differ from other traditional forms of construction contract in that they are designed to cater for change in a way that avoids conflict and promotes collaboration. As we hope will have become clear from a review as to how the forms address cost, the partnering provisions of these forms set a framework that survives the commercial rigours of the real contracting environment by seeking to be transparent about how the cost of the project is arrived at, in providing a series of safeguards for the client and incentives for the team who work with the client to deliver the project within budget. The Partnering Team cdrp@committees.cices.org The Partnering Team comprises members of the institution s Contracts and Dispute Resolution Panel. Led by John Bacon, ICES past president, the members are Mike Rowlinson, a director at Alway Associates, Jonathan Hosie, partner in the construction and engineering practice of Mayer Brown, and Steven Williams, an associate director at Turner and Townsend.

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Implementing the Construction Supply Chain Payment Charter. January Guidance Note Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and

More information

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

NEC4 ENGINEERING & CONSTRUCTION CONTRACT 1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box

More information

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Technical Forum on NEC3 Collaborative Contracts 7 March 2012 Ir Ken W. N. Ko 1 Agenda Subletting

More information

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC) NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

NEC3 ECC target contract option principles and innovative applications

NEC3 ECC target contract option principles and innovative applications INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract

More information

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice

More information

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry NEC4: Evolution not Revolution Delivering distinctive, high quality projects across the construction and property industry What is NEC? NEC is a family of contracts that facilitates the implementation

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

Unpacking framework agreements for the delivery and maintenance of infrastructure

Unpacking framework agreements for the delivery and maintenance of infrastructure Unpacking framework agreements for the delivery and maintenance of infrastructure INTRODUCTION Dr Ron Watermeyer ISO 10845-1 defines a framework agreement as an agreement between an employer and one or

More information

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR SCHEDULES 8 + 9 2015 EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR

More information

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT) Tenth Edition - October 2013 NEC: DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT reads: The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the

More information

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager lobowfok@icloud.com Mobile: 9819 4463 17 January 2017 Note: This set of notes has

More information

ICES. Narrative. Applicant s name

ICES. Narrative. Applicant s name ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed

More information

Internal Audit Report

Internal Audit Report Internal Audit Report MENORAH HIGH SCHOOL FOR GIRLS 13 July 2017 To: Copied to: Chair of Governors Headteacher Education and Skills Director Commissioning Director (Children and Young People) School Finance

More information

Professional Services Contract

Professional Services Contract Professional Services Contract Revising the programme 32 32.1 The Consultant shows on each revised programme. the actual progress achieved on each operation and its effect upon the timing of the reing

More information

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and

More information

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb.

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb. NEC3 A Practical Guide to Compensation Events Chris Holden LLB FRICS FBEng MCIArb www.kerrigans.net Introduction The intention of this presentation is to provide a practical approach to dealing with compensation

More information

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints

Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints Pricing Cost Assurance and Analysis Service (CAAS) Estimates Constraints None. Authoritative Guidance Summary 1. Cost Assurance and Analysis Service (CAAS) provide a range of services for the Defence Equipment

More information

Framework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch /

Framework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch / Framework agreements The Standard for Infrastructure Procurement and Delivery Management includes provisions for framework agreements. Framework agreements have similarities with term service and transversal

More information

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION. CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC

More information

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below: DOMESTIC SUB-CONTRACT CONDITIONS These are the Domestic Sub-Contract Conditions referred to by the Articles of Agreement to which they are attached. In the event that these Domestic Sub-Contract Conditions

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

Routes to Market: Smart Motorways Alliance Commercial Model Summary

Routes to Market: Smart Motorways Alliance Commercial Model Summary Routes to Market: Smart Motorways Alliance Commercial Model Summary August 2018 Overview: The proposals outlined within are draft proposals and subject to sign-off from our governance process. Non-participation

More information

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

2 nd Edition September 2005 (Second Edition of CIDB document 1020) Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF

More information

Construction Law Update The NEC4 suite of contracts are here!

Construction Law Update The NEC4 suite of contracts are here! Construction Law Update The NEC4 suite of contracts are here! Will Buckby and James Vernon 13 February 2018 Introductions Will Buckby, MCIHT Partner, Projects and Contracts Advisory +44 (0) 20 7469 0411

More information

Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element

Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element Purpose 1. The guidance in this chapter relates to a Qualifying Defence Contract (QDC)

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date NZS 3915:2005 COMMITTEE REPRESENTATION This Standard was prepared by Technical Committee P 3915 for the Standards Council established under the Standards Act 1988. Peter Fehl New Zealand Contractors Federation

More information

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner

More information

The NEC 3 Engineering and Construction Contract

The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract A Commentary Second Edition Brian Eggleston CEng, FICE, FIStructE, FCIArb Blackwell Science 2006 Brian Eggleston

More information

JCT 2016 Edition of Contracts

JCT 2016 Edition of Contracts JCT 2016 Edition of Contracts Welcome to the JCT 2016 Edition of Contracts What are the main new features of the 2016 Edition?... We ve incorporated the provisions of the JCT Public Sector Supplement 2011

More information

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising)

Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Making and defending claims Speaker: Edward Quigg BEng LLB LLM PGDipArb MCIPS FCIArb FInstCES Barrister (Non-Practising) Public Works Contracts Dealing with Change Introduction Minimising Change Schedule

More information

to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the

to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the RESIDENTIAL BUILDING CONSUMER GUIDE AND DETERMINATION UNDER SECTION 14 OF THE RESIDENTIAL BUILDING WORK CONTRACTS AND DISPUTE RESOLUTION

More information

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M. Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project

More information

G&T Weekends. Booking Terms & Conditions

G&T Weekends. Booking Terms & Conditions G&T Weekends Booking Terms & Conditions These Booking Terms and Conditions, together with our privacy policy and, where your holiday weekend is booked via our website, our website terms and conditions

More information

NEC4 Key Commercial Changes

NEC4 Key Commercial Changes NEC4 Key Commercial Changes NEC4 User's Group Seminar 2017; 22nd June 2017; County Hall, London On Thursday (22nd June 17), I was fortunate enough to attend the NEC User s Group Annual Seminar at County

More information

Beaufort Asset Clearing Services Limited ( BACSL ) in special administration (the Special Administration )

Beaufort Asset Clearing Services Limited ( BACSL ) in special administration (the Special Administration ) To BACSL s clients 9 May 2018 Dear Sir/Madam, Beaufort Asset Clearing Services Limited ( BACSL ) in special administration (the Special Administration ) Client Assets and Client Money Bar Dates Notifications:

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

Commentary: FIDIC Conditions

Commentary: FIDIC Conditions Commentary: FIDIC Conditions Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer Interpretation and application under the laws of the United Arab Emirates

More information

Form of Agreement Between the Client And the Quantity Surveyor

Form of Agreement Between the Client And the Quantity Surveyor Form of Agreement Between the Client And the Quantity Surveyor Second ACQS Edition (May 2009) Contents Agreement 1 Terms of Appointment 1. Quantity Surveyor's obligations 2 2. Client's obligations 2 3.

More information

Nutreco General Purchase Terms and Conditions

Nutreco General Purchase Terms and Conditions Nutreco General Purchase Terms and Conditions Article 1 - Definitions Agreement Conditions Contract Nutreco Order Products Seller : The purchase agreement between Nutreco and the Seller : The General Purchase

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract

More information

NEC 3: How to claim as the main

NEC 3: How to claim as the main SECOND EDITION FEBRUARY 2016 NEC 3: How to claim as the main contractor for compensation events arising from subcontracted work under main options A (Priced Contract with Activity Schedule) and B (Priced

More information

ICT SERVICES AGREEMENT SCHEDULES SCHEDULE 9.1 STAFF TRANSFER

ICT SERVICES AGREEMENT SCHEDULES SCHEDULE 9.1 STAFF TRANSFER ICT SERVICES AGREEMENT SCHEDULES SCHEDULE 9.1 STAFF TRANSFER CONTENTS Section A: Section B: Section C: Product Description Guidance Pro-forma/Example Schedule ICT_schedule9.1_v2.1 1 Section A Product Description

More information

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 Richard Patterson, Mott MacDonald Housekeeping Safety Facilities 2

More information

Commercial (QS) Core Competencies (Feb 17)

Commercial (QS) Core Competencies (Feb 17) 01 Financial and commercial processes in civil engineering Optimum Activity Detail of A K E Management of budgets for civil engineering works. Cost forecasting, management and control processes including

More information

Claims Analysis and Dispute Resolution Causes, Analysis, and Prevention

Claims Analysis and Dispute Resolution Causes, Analysis, and Prevention Claims Analysis and Dispute Resolution Causes, Analysis, and Prevention Karim El Dash 12/17/2010 1. CONSTRUCTION RISKS... 6 1.1 Design risks... 6 1.2 Professional indemnity insurance... 8 1.3 Risk analysis

More information

Subcontracting. Module 7

Subcontracting. Module 7 Subcontracting A guide to the legal implications of the Industry Standard Partnering Agreement for voluntary, community and social enterprise organisations Module 7 Dispute resolution, implications of

More information

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract London Bristol Dublin Dubai Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract Tom Pemberton, Partner James Vernon, Associate 12 April 2016 Introductions Tom Pemberton

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Valuation for Interim Payment Certificates Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 17 70.4 2 otherwise inserted after stated

More information

NEC4 Engineering and Construction Contract review of changes from NEC3

NEC4 Engineering and Construction Contract review of changes from NEC3 Here is a review from GMH Planning Ltd of the significant changes within the NEC4 ECC contract compared to that of the NEC3 version. We have not identified every single change, but picked out the main

More information

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001 NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 The National Audit Office scrutinises public spending on behalf of Parliament. The Comptroller

More information

OFFICIAL. Date and Time 15 th May 2018 SPA Boardroom, Pacific Quay Forensic Services Budget Management and Month End Guidelines Item Number 10.

OFFICIAL. Date and Time 15 th May 2018 SPA Boardroom, Pacific Quay Forensic Services Budget Management and Month End Guidelines Item Number 10. Meeting Finance Committee Date and Time 15 th May 2018 Location SPA Boardroom, Pacific Quay Title of Paper Forensic Services Budget Management and Month End Guidelines Item Number 10.2 Presented By Amy

More information

COSCCO016 - SQA Unit Code F Prepare and monitor costs and accounts in construction

COSCCO016 - SQA Unit Code F Prepare and monitor costs and accounts in construction Prepare and monitor costs and accounts in construction Overview This unit is about implementing cost systems, collecting information, analysing information and using information to prepare accounts. You

More information

Somewhere in Time - Securing and Protecting your Contractual Rights

Somewhere in Time - Securing and Protecting your Contractual Rights Howard KLEIN, United Kingdom Keywords: Ascertaining Delays, Delay Costs, Notice, Provisions, Extension of Time, Records, Construction Economics. SUMMARY Time is money and this is no less the case on construction

More information

PART 22 OF THE SCHEDULE: VARIATION PROCEDURE. Section 1A: Interpretation

PART 22 OF THE SCHEDULE: VARIATION PROCEDURE. Section 1A: Interpretation PART 22 OF THE SCHEDULE: VARIATION PROCEDURE Section 1A: Interpretation For the purposes of this Agreement, and in particular this Part 22 of the Schedule (Variation Procedure), unless the context requires

More information

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Financial Proposal. Part 6

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Financial Proposal. Part 6 ARTES Competitiveness & Growth Full Proposal Requirements for the Content of the Financial Proposal Part 6 Statement of Applicability and Proposal Submission Requirements Applicable Domain(s) Space Ground

More information

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals GENERAL CONDITIONS 1 GENERAL PROVISIONS.................................... 1 1.1 Definitions The Contract Persons Dates, Times and Periods Money and Payments Other Definitions 1.2 Interpretation 1.3 Priority

More information

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Valuation for Interim Payment Certificates Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant

More information

TYPES OF CONTRACTS. Presenter: Lucas Ouma

TYPES OF CONTRACTS. Presenter: Lucas Ouma TYPES OF CONTRACTS Presenter: Lucas Ouma SPECIFIC OBJECTIVEs To enable the learner understand types of contracts in common use. To differentiate their desired application with the nature of contract. To

More information

General Conditions of Contract for the Hire of Plant With or Without an Operator

General Conditions of Contract for the Hire of Plant With or Without an Operator General Conditions of Contract for the Hire of Plant With or Without an Operator CC7 April 1991 (Revised September 2010) Table of Clauses 1. Definition of Terms 2. Contractor s Proper Performance of the

More information

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management

A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management A18 Tendering Policy Authorised Reviewer: Head of Finance & Service Management 1. Purpose of policy This policy deals with the tendering for all types of expenditure undertaken by Andium Homes, including:

More information

GENERAL PURCHASING TERMS AND CONDITIONS Valid as of September 1 st, 2015 for any order or contract 4. DELIVERY

GENERAL PURCHASING TERMS AND CONDITIONS Valid as of September 1 st, 2015 for any order or contract 4. DELIVERY GENERAL PURCHASING TERMS AND CONDITIONS Valid as of September 1 st, 2015 for any order or contract 1. GENERAL INFORMATION The supplier s acceptance of an order implies ipso facto the acceptance of these

More information

MacRoberts. A law firm as individual as you.

MacRoberts. A law firm as individual as you. MacRoberts. A law firm as individual as you. The New NEC4: Exploring the Key Changes Mike Barlow, Partner MacRoberts LLP www.macroberts.com Glasgow Edinburgh Dundee 1 THE NEC4 ENGINEERING AND CONSTRUCTION

More information

Against All Odds. TE&A's Special Edition Issue. by Clive Horridge

Against All Odds. TE&A's Special Edition Issue. by Clive Horridge Against All Odds TE&A's Special Edition Issue by Clive Horridge Against All Odds by Clive Horridge Page 2 of 12 Not just a Phil Collins song-title depicting a common scenario of dispair, it is the case

More information

General Terms of Business for commissioned Translation Work

General Terms of Business for commissioned Translation Work Dorota Pawlak - Translation Services General Terms of Business for commissioned Translation Work In this document: No part of any numbered clause shall be read separately from any other part. Section headings

More information

AMENDMENTS APRIL 2013

AMENDMENTS APRIL 2013 AMENDMENTS APRIL 2013 The following amendments have been made to the December 2009 edition. Full details of all amendments are available on www.neccontract.com. Page Clause Line 11 40.1 1 replace: The

More information

GENERAL TERMS AND CONDITIONS OF PURCHASE OF CADCON HOLDING GMBH

GENERAL TERMS AND CONDITIONS OF PURCHASE OF CADCON HOLDING GMBH 1. General 1.1. The general terms and conditions of purchase below of CADCON Holding GmbH (hereinafter referred to as "CADCON") apply to the ordering from the Contractor and the delivery of goods by the

More information

Building & Construction Law all notes

Building & Construction Law all notes Building & Construction Law all notes Week 2 THE NATURE OF THE BUILDING AND CONSTRUCTION INDUSTRY Project participants Project stages Procurement methods Typical players and processes Typical project participants

More information

Commercial Policy Group Guideline No 7 - Target Cost Incentive Fee Arrangements - Issue No 1 dated 27 January 2004

Commercial Policy Group Guideline No 7 - Target Cost Incentive Fee Arrangements - Issue No 1 dated 27 January 2004 Commercial Policy Group Guideline No 7 - Target Cost Incentive Fee Arrangements - Issue No 1 dated 27 January 2004 Background 1. Target Cost Incentive Fee Arrangements are one of a range of contracting

More information

Part 2 Employer s preliminary notice of Fair Payment requirements 3. Part 4 Suggested modifications to SBCC Main Contracts 5

Part 2 Employer s preliminary notice of Fair Payment requirements 3. Part 4 Suggested modifications to SBCC Main Contracts 5 Contents Part 1 Introduction Page 1 Part 2 Employer s preliminary notice of Fair Payment requirements 3 Part 3 Incorporation of modifications 4 Part 4 Suggested modifications to SBCC Main Contracts 5 Standard

More information

General Conditions of Purchase Current: July 2009

General Conditions of Purchase Current: July 2009 General Conditions of Purchase Current: July 2009 1. GENERAL... 2 2. CONTRACT CONCLUSION / ORDERS... 2 3. BSCI - CODE OF CONDUCT (BUSINESS SOCIAL COMPLIANCE INITIATIVE)... 2 4. DELIVERY / DISPATCH / PACKING...

More information

AGC s Preliminary Commentary to the 2007 Edition of the AIA A201 General Terms and Conditions Document

AGC s Preliminary Commentary to the 2007 Edition of the AIA A201 General Terms and Conditions Document AGC s Preliminary Commentary to the 2007 Edition of the AIA A201 General Terms and Conditions Document The new edition of the AIA A201 2007 edition was published on November 5 th. The 600-member AGC Board

More information

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS AS 4903 2000 (Incorporating Amendment No. 1) AS 4903 2000 Australian Standard Subcontract conditions for design and construct This Australian Standard was prepared by Committee OB-003, General Conditions

More information

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND PROFESSIONAL ARCHITECT (PrArch) PROFESSIONAL SENIOR ARCHITECTURAL TECHNOLOGIST (PrSArchT) mark applicable registration

More information

GUIDANCE FOR PROFESSIONAL CONSULTANTS

GUIDANCE FOR PROFESSIONAL CONSULTANTS Diocese of Westminster Education Service Page 1 MANDATORY DOCUMENTATION GUIDANCE FOR PROFESSIONAL CONSULTANTS RICS Standard Form of Consultant s Appointment RICS Standard Form of Consultant s Appointment

More information

INTRODUCTORY NOTE ORGALIME GENERAL CONDITIONS FOR THE REPAIR OF MACHINERY AND EQUIPMENT - R02

INTRODUCTORY NOTE ORGALIME GENERAL CONDITIONS FOR THE REPAIR OF MACHINERY AND EQUIPMENT - R02 INTRODUCTORY NOTE ORGALIME GENERAL CONDITIONS FOR THE REPAIR OF MACHINERY AND EQUIPMENT - R02 Scope of use The General Conditions for the repair of machinery and equipment (including parts of these) are

More information

Subcontracting. Fees and Charges Policy

Subcontracting. Fees and Charges Policy Subcontracting Fees and Charges Policy College Vision Our vision is to be a strong independent College characterised by a clarity of purpose, to be outstanding in every thing we do and become renowned

More information

Amendments to IFRS 17 Insurance Contracts Recognition of the contractual service margin in profit or loss in the general model

Amendments to IFRS 17 Insurance Contracts Recognition of the contractual service margin in profit or loss in the general model STAFF PAPER IASB meeting January 2019 Project Paper topic Amendments to IFRS 17 Insurance Contracts Recognition of the contractual service margin in profit or loss in the general model CONTACT(S) Anne

More information

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering construction Superseding (in part) NZS 3910:2003 NZS 3910:2013 COMMITTEE REPRESENTATION This Standard was prepared under the

More information

Webinar - The Project Manager in the NEC4 ECC: What s new and different?

Webinar - The Project Manager in the NEC4 ECC: What s new and different? Webinar - The Project Manager in the NEC4 ECC: What s new and different? 17 th May 2017 Q&A session This document provides answers to the questions submitted during the webinar. The webinar can be viewed

More information

STANDARD FORMS: STANDARDISATION, BASTARDISATION AND THE VIRTUAL CONTRACT. Nicholas Gould. 8 November 2006 GARDINER & THEOBALD LECTURE

STANDARD FORMS: STANDARDISATION, BASTARDISATION AND THE VIRTUAL CONTRACT. Nicholas Gould. 8 November 2006 GARDINER & THEOBALD LECTURE STANDARD FORMS: STANDARDISATION, BASTARDISATION AND THE VIRTUAL CONTRACT Nicholas Gould 8 November 2006 GARDINER & THEOBALD LECTURE INTRODUCTION This paper reviews some of the standard forms and considers

More information

Terms & Conditions Supply of Goods or Services

Terms & Conditions Supply of Goods or Services Terms & Conditions Supply of Goods or Services 1. DEFINITIONS In these terms and conditions: Agreement means an agreement between the Purchaser and Supplier for the supply of Goods or Services constituted

More information

Current as of 1 May

Current as of 1 May General terms and conditions of purchase for transport, assembly, disassembly, waste disposal and other equipment-related services, including plant operation, VW AG / general purchasing division (current

More information

Scottish Conditions of Appointment of an Architect SCA/2014 (Apr 2015)

Scottish Conditions of Appointment of an Architect SCA/2014 (Apr 2015) SCA/201 (Apr 2015) Definitions Where the defined terms are used in the SCA/201 (Apr 2015) they are distinguished by an initial capital letter. Appointment The agreement between the Client and the Architect

More information

ROUGH DIAMOND SUPPLY AGREEMENT 1

ROUGH DIAMOND SUPPLY AGREEMENT 1 2015-2018 ROUGH DIAMOND SUPPLY AGREEMENT 1 GLOBAL SIGHTHOLDER SALES (INTERNATIONAL), GLOBAL SIGHTHOLDER SALES (BOTSWANA), SIGHTHOLDER SALES SOUTH AFRICA AND THE SUPPLY OF CANADIAN UN-AGGREGATED GOODS FOR

More information

Session 3 by Zoltán Záhonyi, FIDIC AIT,

Session 3 by Zoltán Záhonyi, FIDIC AIT, Session 3 by Zoltán Záhonyi, FIDIC AIT, zoltan.zahonyi@zandpartners.com Contents of Session 3 Session 3: FIDIC 1999 Red Book Part 2 The Quality Issues (Plant, Materials and Workmanship) The Time is of

More information

WESTMINSTER ADULT EDUCATION SERVICE. Subcontractor Management Fee Policy

WESTMINSTER ADULT EDUCATION SERVICE. Subcontractor Management Fee Policy WESTMINSTER ADULT EDUCATION SERVICE Subcontractor Management Fee Policy Lead Responsibility Director of Income Generation and External Business Approved by Executive Board Version 2 Date of approval 7

More information

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE 1. SCOPE ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE 1.1 These general conditions of purchase published at www.zanon.com -shall be deemed as an integral part of any order issued by Ettore Zanon

More information

Consultancy Services Contract

Consultancy Services Contract SERVICES AND RESOURCES INFRASTRUCTURE Consultancy Services Contract Based on AS 4122 2010 General Conditions of Contract for Consultants The University of Adelaide and The Consultant For Insert Project

More information

DOUKPSC04 Rev Feb 2013

DOUKPSC04 Rev Feb 2013 DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby

More information