Building & Construction Law all notes

Size: px
Start display at page:

Download "Building & Construction Law all notes"

Transcription

1 Building & Construction Law all notes

2 Week 2 THE NATURE OF THE BUILDING AND CONSTRUCTION INDUSTRY Project participants Project stages Procurement methods Typical players and processes Typical project participants The proprietor/principal for whose benefit is the project being done? Owner of the project. Eg UTS for UTS building works. Proprietor can be a company, government agency, partnership. The financiers who is putting up the money? Professional Team all of the professional consultants you need to design and build the project eg architects, engineers, quantity surveyors (cost controllers) Construction participants eg directly employed labour, subcontractors The five typical project stages 1. Inception 2. Detailed design 3. Documentation & tender 4. Construction a. Approvals b. Retention fund v unconditional c. Program of works i. Against which extension of time claims are measured ii. Critical path activities those which delay the project completion date d. Proof of insurance e. Role of superintendent f. Practical completion 5. Post construction period, after practical completion defects liability Typical procurement methods & contracts - Lump sum / hard dollar o Defined scope of work, fixed price o As described in drawings and specifications o If there is no issue with time, this is the best type of contract for the proprietor Design is finalised and documented o Bill of quantities o Contractor assumes most risk - Guaranteed maximum price o Advanced but incomplete design o Conditional fixed price o Contractor allowances

3 o Specification finalised post contract o Enables fast tracking o Owner bears risk of end price - Design and construct o Design is evolved only to basic design o Contract to both complete design and construct o Contractor engages consultants depending on how early contractor gets in on the act o Novation or own consultants o Loss of access to the design team - Cost plus o Design incomplete o Cost is not ascertainable o Time a significant factor o Design finalised after commencement o Payment on invoice plus agreed mark up o Proprietor assumes financial risk - Schedule of rates o Design incomplete o Cost not ascertainable o Time a significant factor o Suited to urgent works o Tendered schedule of rates o Capped maximum and minimums o Measurement basis of payment - Construction management o Contractor acts as agent o Infrastructure provided by contractor o Permits early works o Identifiable and agreed packages o Tender of packages by contractor o All sub-contracts direct with Proprietor o Payment as work progresses plus agreed mark up o Proprietor takes financial risk Important concepts Contract documents Superintendent Scope of work PC items (Prime Cost items) Provisional sums

4 Variation Delay Retention Liquidated damages Presentation on liquidated damages: - Possible losses that Investa might suffer if LL does not reach PC? o Tenants unable to move into building loss of rent o Additional equipment hire o Additional overheads - How could LL be protected in the contract? o Capped at a percentage of contract sum o Capped at days loss You don t have to prove your loss! Superintendent can certify X days late, and deduct liquidated damages from next progress claim. No requirement to show loss, only have to show did not achieve practical completion by X date. If I were advising, would always advise to put something in the contract for liquidated damages, because it caps the loss! You can price the risk in your price! Negotiate the liquidated damages. If nothing is in there, damages are at large! Can sue for ANYTHING that is in reasonable contemplation of the parties as long as not a penalty, they are not bad because they make things predictable. Contracts liquidated damages refers to schedule at the back amt per day/week, is BLANK! Supposed to fill in the schedule! If it is BLANK then not the sole remedy for late completion, and you are back to actual damages Risk management - Who bears the risk? - Party best placed to control should bear - Price is risk dependant - Management requires identification - Risk allocation by the contract - Risk occurrence and predictability - Failure to identify and allocate results in avoidable claims/disputes Summary - Construction is complex and involves risk - Potential for disputes is high

5 - Projects are established in defined stages - Procurement methods differ and each has a unique contract form - Each form allocates risk differently - All foreseeable risks should be identified and allocated - Foreseeable risks can be efficiently managed via the contract

6 Assignment - Implied terms in construction contracts o Implied term of good faith Termination for convenience clauses allow a contracting party to terminate at will and without cause. They are quite common in constructioncontracts. Clauses that empower the principal (or its representative) to remove part of the work from the contractor's scope of works are also quite common. Is the principal at large in exercising such rights, alternatively is the exercise of such rights tempered by either an impliedobligation to act in good faith, the equitable doctrine of penalties; or the equitable doctrine of relief against forfeiture? Can contract drafting assist and, if so, how? As some segments of the building and mining industries in Australia face straightened economic times, it is likely that the courts will be called on to resolve such issues. UK: In February the High Court said (in Yam Seng vs International Trade Corporation) this hostility was misplaced and suggested that duties of good faith should be implied more often. One of the bases for this was that a general norm which underlies almost all contractual relationships is an expectation of honesty. Some may query how normal that is in the construction industry. - Can hand it in either in class on Monday 14 September or by Friday 18 th September at Rob s chambers 9 th floor 67 Castlereagh St & King St - The marks are in the critical analysis. Eg this is the way the law works now, and this is why I think it could be improved by doing X Y and Z - Liquidated damages or penalties? Government use of LDs in contracts

Form of Agreement Between the Client And the Quantity Surveyor

Form of Agreement Between the Client And the Quantity Surveyor Form of Agreement Between the Client And the Quantity Surveyor Second ACQS Edition (May 2009) Contents Agreement 1 Terms of Appointment 1. Quantity Surveyor's obligations 2 2. Client's obligations 2 3.

More information

Conditions for the Carriage of Goods by Road

Conditions for the Carriage of Goods by Road Conditions for the Carriage of Goods by Road The Conditions set down the basis on which the Carrier will carry goods for the Customer (definitions of Carrier and Customer are given in Condition 1). The

More information

Ethical Contract Negotiation

Ethical Contract Negotiation Ethical Contract Negotiation Texas Society of Professional Engineers May 16, 2006 Brian W. Erikson Quilling, Selander, Cummiskey & Lownds, P.C. 2001 Bryan Street, Suite 1800 Dallas, Texas 75201 (214) 880-1844

More information

1 Exam Prep Business and Finance Practice Test 4

1 Exam Prep Business and Finance Practice Test 4 1 Exam Prep Business and Finance Practice Test 4 1. All the following are normally required for a loan application except. A. an income statement B. a balance sheet C. a tax return D. retained earnings

More information

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS AS 4903 2000 (Incorporating Amendment No. 1) AS 4903 2000 Australian Standard Subcontract conditions for design and construct This Australian Standard was prepared by Committee OB-003, General Conditions

More information

QBCC PERIOD MINOR WORKS SUBCONTRACT

QBCC PERIOD MINOR WORKS SUBCONTRACT Build better. QBCC PERIOD MINOR WORKS SUBCONTRACT The General Conditions of the QBCC Period Minor Works Subcontract may not be suitable for all work and the QBCC does not make any representation as to

More information

Western Water Development Consultant Accreditation Deed

Western Water Development Consultant Accreditation Deed Western Water Development Consultant Accreditation Deed Western Water ABN 67 433 835 375 and Company name: ABN : February 2018 TABLE OF CONTENTS 1. DEFINITIONS AND INTERPRETATION... 1 1.1 Definitions...

More information

Subcontract conditions

Subcontract conditions AS 2545 1993 (Incorporating Amendment No. 1) Australian Standard Subcontract conditions This Australian Standard was prepared by Committee OB/3, General Conditions of Contract. It was approved on behalf

More information

Payment Act Comparison NJ/DE/PA/MD/NY

Payment Act Comparison NJ/DE/PA/MD/NY Payment Act Comparison NJ/DE/PA/MD/NY Many Remedies Exist for Non- Payment or Untimely Payment: Mechanics Liens Payment Bond Claims Trust Fund Claims Prompt Payment Act Claims Litigation/Arbitration/Mediation

More information

Terms and Conditions of Supply for Staff Augmentation Services. 1. Supply. 2. Acknowledgement. 3. Term. 4. Purchase Orders. 5.

Terms and Conditions of Supply for Staff Augmentation Services. 1. Supply. 2. Acknowledgement. 3. Term. 4. Purchase Orders. 5. 1. Supply 1.1 Dimension Data Australia Pty Ltd (ABN 65 003 371 239) ("Dimension Data") agrees to supply the client named in the offer ("the Client") the employees and contractors ("the Dimension Data Personnel")

More information

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS TABLE OF CONTENTS Background 1 1. Introduction 1 2. Contract Works 1 3. Project

More information

L 320/46 EN Official Journal of the European Union

L 320/46 EN Official Journal of the European Union L 320/46 EN Official Journal of the European Union 29.11.2008 INTERNATIONAL ACCOUNTING STANDARD 11 Construction contracts OBJECTIVE The objective of this standard is to prescribe the accounting treatment

More information

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) Construction Industry Development Board Tel: 012 343 7136 or 012 481 9030 Fax: 012

More information

Standard Terms & Conditions for Purchase Order

Standard Terms & Conditions for Purchase Order 1. EVANS BUILT DEFINITION Each Party to this Agreement acknowledges and agrees that: a) each reference in this Agreement to Evans Built or to a Purchaser is a reference to Evans Built Pty Ltd (ABN 61 120

More information

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR SCHEDULES 8 + 9 2015 EDITION CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT 09 CONTRACT ADMINISTRATOR

More information

Construction Contracts Issues and Practical Solutions. Shahram Safai Partner Afridi & Angell

Construction Contracts Issues and Practical Solutions. Shahram Safai Partner Afridi & Angell Construction Contracts Issues and Practical Solutions Shahram Safai Partner Afridi & Angell About Afridi & Angell is one of the most established law firms in the UAE. The firm conducts a general corporate,

More information

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS PRACTITIONER, AND ARCHITECTURAL SERVICE TO THE CLIENT

PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS PRACTITIONER, AND ARCHITECTURAL SERVICE TO THE CLIENT PROFESSIONAL PRACTICE EXAM SEPTEMBER 2009 PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS PRACTITIONER, AND ARCHITECTURAL SERVICE TO THE CLIENT Question 1: In terms of the SACAP Code of Conduct what is meant

More information

Sri Lanka Accounting Standard-LKAS 11. Construction Contracts

Sri Lanka Accounting Standard-LKAS 11. Construction Contracts Sri Lanka Accounting Standard-LKAS 11 Construction Contracts CONTENTS paragraphs SRI LANKA ACCOUNTING STANDARD-LKAS 11 CONSTRUCTION CONTRACTS OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING

More information

CONTRACT COSTING. INTRODUCTION Contract or terminal costing is A form of specific order costing; attribution of costs to individual contracts.

CONTRACT COSTING. INTRODUCTION Contract or terminal costing is A form of specific order costing; attribution of costs to individual contracts. CONTRACT COSTING INTRODUCTION Contract or terminal costing is A form of specific order costing; attribution of costs to individual contracts. This method is used in case of big jobs described as contracts.

More information

Any additional services not detailed in the Quotation, and the price is subject to variation to take account of changes in any exclusions.

Any additional services not detailed in the Quotation, and the price is subject to variation to take account of changes in any exclusions. STANDARD TERMS & CONDITIONS for QUOTATIONS. Bitu-mill (Road Maintenance) Pty Ltd, Bitu-mill (Civil) Pty Ltd, Bitu-mill Services Pty Ltd and Bitu-mill Equipment Pty Ltd ( Bitu-mill ) These terms and conditions

More information

University of Maryland College Park Change Order Guidelines. I. Introduction

University of Maryland College Park Change Order Guidelines. I. Introduction University of Maryland College Park Change Order Guidelines I. Introduction This document is intended as a guideline for those currently doing business and those interested in pursuing business with the

More information

GUIDANCE ON USING THE BUILDING HUB CONTRACTS

GUIDANCE ON USING THE BUILDING HUB CONTRACTS GUIDANCE ON USING THE BUILDING HUB CONTRACTS Introduction As of 1 January 2015 it is now mandatory to have written building contracts for projects worth $30,000 or more. The Building Act 2004 ( the Act

More information

Consultancy Services Contract

Consultancy Services Contract SERVICES AND RESOURCES INFRASTRUCTURE Consultancy Services Contract Based on AS 4122 2010 General Conditions of Contract for Consultants The University of Adelaide and The Consultant For Insert Project

More information

Construction Contract Between Owner and Construction Manager at Risk

Construction Contract Between Owner and Construction Manager at Risk FINAL 10/10/03 Date: Project Name: ASU Project Number: Construction Manager at Risk: Owner: Arizona Board of Regents for and on behalf of Arizona State University CMAR and Owner hereby agree as follows:

More information

30 Questions You Should Ask Your Custom Home Builder

30 Questions You Should Ask Your Custom Home Builder 30 Questions You Should Ask Your Custom Home Builder 1) How long have you been building luxury custom homes? Your builder should at least 20 years experience in all facets of the new home construction

More information

Introduction. Construction Contracts. Unit 4: Principle of Contract Administration under JCT 5 SBC/Q 1/15/2016

Introduction. Construction Contracts. Unit 4: Principle of Contract Administration under JCT 5 SBC/Q 1/15/2016 Introduction R. Sarvananthan ( Sarva) B.Eng, MSc CPM, MIES, MASCE 1 Construction Contracts Unit 1: Introduction to Construction Contracts Unit 2: Standard form of Construction Contracts Unit 3: Managing

More information

CONDITIONS OF CONTRACT. The Builder must execute and complete the Works in a workmanlike manner and ensure the Works are adequately supervised.

CONDITIONS OF CONTRACT. The Builder must execute and complete the Works in a workmanlike manner and ensure the Works are adequately supervised. CONDITIONS OF CONTRACT 1. RESPONSIBILITY OF BUILDER The Builder must execute and complete the Works in a workmanlike manner and ensure the Works are adequately supervised. 2. WORK PERFORMED OR MATERIALS

More information

OWNER ARIZONA BOARD OF REGENTS. for and on behalf of ARIZONA STATE UNIVERSITY CMAR DESIGN PROFESSIONAL

OWNER ARIZONA BOARD OF REGENTS. for and on behalf of ARIZONA STATE UNIVERSITY CMAR DESIGN PROFESSIONAL Date (type in) Issued: CONSTRUCTION CONTRACT FOR CONSTRUCTION MANAGER AT RISK PROJECTS (SINGLE PROJECT FORM) Request for Qualifications Number OWNER ARIZONA BOARD OF REGENTS for and on behalf of ARIZONA

More information

Unfair Contract Terms

Unfair Contract Terms Unfair Contract Terms Protections for small businesses Isla McRobbie and Matthew Lang #6374386 Disclaimer Disclaimer: This presentation is intended to provide general information only and should not be

More information

GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT

GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT 1. Definition and Duration These conditions form part of a quotation submitted by the Contractor to the Client named in the quotation. The Contractor

More information

Subcontracting in UAE

Subcontracting in UAE Subcontracting in UAE PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Contents The need for Subcontracting Legal framework

More information

CS ENERGY LIMITED SERVICE CONDITIONS

CS ENERGY LIMITED SERVICE CONDITIONS CS ENERGY LIMITED SERVICE CONDITIONS 1. DEFINITIONS In these Conditions: Agreement means the agreement between CS Energy and the Contractor for the provision of Services and comprises the relevant Service

More information

to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the

to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the to the DIRECTOR OF BUILDING CONTROL DEPARTMENT OF JUSTICE TASMANIA on the RESIDENTIAL BUILDING CONSUMER GUIDE AND DETERMINATION UNDER SECTION 14 OF THE RESIDENTIAL BUILDING WORK CONTRACTS AND DISPUTE RESOLUTION

More information

4. The Division shall receive tenders at a location specified by the Secretary-Treasurer up to the time and date specified on the tender documents.

4. The Division shall receive tenders at a location specified by the Secretary-Treasurer up to the time and date specified on the tender documents. Administrative Procedure 515 FACILITIES AND MAINTENANCE TENDERING Background Golden Hills School Division believes in purchasing goods and services at competitive prices, treating suppliers fairly and

More information

SSAP 23 STATEMENT OF STANDARD ACCOUNTING PRACTICE 23 CONSTRUCTION CONTRACTS

SSAP 23 STATEMENT OF STANDARD ACCOUNTING PRACTICE 23 CONSTRUCTION CONTRACTS SSAP 23 STATEMENT OF STANDARD ACCOUNTING PRACTICE 23 CONSTRUCTION CONTRACTS (Issued May 1998; Revised January 2001) The standards, which have been set in bold italic type, should be read in the context

More information

This Webcast Will Begin Shortly

This Webcast Will Begin Shortly This Webcast Will Begin Shortly If you have any technical problems with the Webcast or the streaming audio, please contact us via email at: splemoderator@smartpros.com Thank You! 1 KEY ISSUES IN NEGOTIATING

More information

ACA UNIFORM TERMS AND CONDITIONS

ACA UNIFORM TERMS AND CONDITIONS ACA UNIFORM TERMS AND CONDITIONS ARIZONA COMMERCE AUTHORITY (ACA) UNIFORM TERMS AND CONDITIONS 1. Definition of Terms As used in this Solicitation and any resulting Contract, the terms listed below are

More information

ARIZONA STATE UNIVERSITY - STANDARD FORM AGREEMENT BETWEEN OWNER AND ON THE BASIS OF A GUARANTEED MAXIMUM PRICE March 1, 2015 Edition

ARIZONA STATE UNIVERSITY - STANDARD FORM AGREEMENT BETWEEN OWNER AND ON THE BASIS OF A GUARANTEED MAXIMUM PRICE March 1, 2015 Edition ARIZONA STATE UNIVERSITY - STANDARD FORM AGREEMENT BETWEEN OWNER AND CM@RISK ON THE BASIS OF A GUARANTEED MAXIMUM PRICE March 1, 2015 Edition Standard Form Agreement Between Owner and CM@Risk (March 1,

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date:... /... /.../ This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative)

More information

Practical guide to effective contract management

Practical guide to effective contract management Practical guide to effective contract management Session 2 Key Issues in Australian standard conditions of contract By Nathan Abbott This paper was regularly presented at IES Conferences "Practical guide

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

Construction Contracts

Construction Contracts International Accounting Standard 11 Construction Contracts This version includes amendments resulting from IFRSs issued up to 31 December 2009. IAS 11 Construction Contracts was issued by the International

More information

Page 1 CONTRACT DATA. used in conjunction with the. JBCC Minor Works Agreement. Edition published March 2014

Page 1 CONTRACT DATA. used in conjunction with the. JBCC Minor Works Agreement. Edition published March 2014 Page 1 Preface JBCC Constituents Association of South African Quantity Surveyors South African Black Technical and Allied Careers Organisation Application of JBCC Contract Documents Warning CONTRACT DATA

More information

HKIS QSD PQSL Series Payment Valuation and Post-Contract Cost Monitoring

HKIS QSD PQSL Series Payment Valuation and Post-Contract Cost Monitoring HKIS QSD PQSL Series 2013 Payment Valuation and Post-Contract Cost Monitoring by Kenneth Poon FHKIS; FRICS; RPS Global Construction Consultants Payment Valuation 1. Introduction Payment to contractors

More information

DOUKPSC04 Rev Feb 2013

DOUKPSC04 Rev Feb 2013 DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby

More information

A. Contracts considered in the context of construction projects. 3. Particular forms of agreement unit price, T&M, Design/Build.

A. Contracts considered in the context of construction projects. 3. Particular forms of agreement unit price, T&M, Design/Build. Issues in Interpretation and Drafting of Construction Contracts Overview of Course Materials and Subject Matters By Greg Harris Partner, Construction and Litigation Group January 2004 1. Overview of Course

More information

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below: DOMESTIC SUB-CONTRACT CONDITIONS These are the Domestic Sub-Contract Conditions referred to by the Articles of Agreement to which they are attached. In the event that these Domestic Sub-Contract Conditions

More information

[Based on or amended from] Australian Standard. Subcontract conditions for design and construct (QLD) Design and Construction of: PROJECT

[Based on or amended from] Australian Standard. Subcontract conditions for design and construct (QLD) Design and Construction of: PROJECT AS 4903 2000 [Based on or amended from] 4903 2000 (Incorporating Amendment No. 1) Design and Construction of: PROJECT At: Main Contractor: Subcontractor: ADDRESS EVANS BUILT PTY LTD SUBCONTRACTOR Australian

More information

INTERIOR ARCHITECTURE & DESIGN TERMS & CONDITIONS DESIGN SERVICES ZUNICA P/L LEVEL 1, 216 CHAPEL STREET PRAHRAN VICTORIA 3181

INTERIOR ARCHITECTURE & DESIGN TERMS & CONDITIONS DESIGN SERVICES ZUNICA P/L LEVEL 1, 216 CHAPEL STREET PRAHRAN VICTORIA 3181 1. 1.1 1.2 DEFINITIONS Brief: Statements and materials assembled by the Client with the Zunica s assistance to summarise the Client s initial requirements, to address the Client s preferences and priorities,

More information

EMP Commercial Terms and Conditions AS AT DECEMBER 2015 ENERGY DONE BRIGHT

EMP Commercial Terms and Conditions AS AT DECEMBER 2015 ENERGY DONE BRIGHT EMP Commercial Terms and Conditions AS AT DECEMBER 2015 ENERGY DONE BRIGHT 1. Definitions of terms 1. Goods and services means all goods and services we supply to you. It includes advice and recommendations.

More information

The 7 things you MUST ask BEFORE signing your Building Contract

The 7 things you MUST ask BEFORE signing your Building Contract The 7 things you MUST ask BEFORE signing your Building Contract 2 Buying a new home will likely be the largest purchase you ever make. You may be embarking on a new life purchasing your first home or upgrading

More information

CONSTRUCTION NEGOTIATIONS

CONSTRUCTION NEGOTIATIONS CONSTRUCTION NEGOTIATIONS I. Contracts November 6, 2017 Presented by: Bryan Thomas Bradley Arant Boult Cummings LLP Attorney-Client Privilege. Agenda Construction Negotiations I. Contracts Know the Deal

More information

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS 1. DEFINITIONS AND INTERPRETATION 1.1 Definitions In this Contract (as hereinafter defined)

More information

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies

Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Avoiding Common Payment Pitfalls for Subcontractors: A Primer on Federal Contracting Payment Remedies Shoshana E. Rothman BrigliaMcLaughlin, PLLC April 2017 Seminar Goals: 1. Understand key contract clauses

More information

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017 BIDP Standard FORMS & JBCC Minor WORKS Commentary ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW 01160007 04 th NOVEMBER 2017 Types of Contract Fixed Price Contracts For Specified work for a sum not adjustable

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3

More information

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/ MOMBASA Beach Hotel NGULIA Safari Lodge VOI Safari Lodge KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/2017-2018 KENYA

More information

Successfully Crafting and Prosecuting Contract Disputes Act Claims Against the Government

Successfully Crafting and Prosecuting Contract Disputes Act Claims Against the Government Successfully Crafting and Prosecuting Contract Disputes Act Claims Against the Government Webinar July 28, 2015 Sandy Hoe shoe@cov.com 202-662-5394 Justin Ganderson jganderson@cov.com 202-662-5422 Agenda

More information

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date NZS 3915:2005 COMMITTEE REPRESENTATION This Standard was prepared by Technical Committee P 3915 for the Standards Council established under the Standards Act 1988. Peter Fehl New Zealand Contractors Federation

More information

Reviewing Construction Claims INDOT Contracts

Reviewing Construction Claims INDOT Contracts Reviewing Construction Claims INDOT Contracts Why do we have claims? Changed Conditions Causes the work to substantially differ in kind or nature from the work as required in the original contract. (104.02)

More information

ACCOUNTING STANDARDS BOARD STANDARD OF GENERALLY RECOGNISED ACCOUNTING PRACTICE CONSTRUCTION CONTRACTS (GRAP 11)

ACCOUNTING STANDARDS BOARD STANDARD OF GENERALLY RECOGNISED ACCOUNTING PRACTICE CONSTRUCTION CONTRACTS (GRAP 11) ACCOUNTING STANDARDS BOARD STANDARD OF GENERALLY RECOGNISED ACCOUNTING PRACTICE CONSTRUCTION CONTRACTS (GRAP 11) Issued by the Accounting Standards Board December 2006 Acknowledgment This Standard of Generally

More information

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS.

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. TENDER NO. TCG/F&P/5/2017-2018 SEPTEMBER 2017 TABLE OF CONTENTS

More information

Liquidated Damages and Scope Changes in Korean Government Contracts

Liquidated Damages and Scope Changes in Korean Government Contracts Liquidated Damages and Scope Changes in Korean Government Contracts 2014.07.01 INTRODUCTION Liquidated Damages Treatment of LDs under Korean Act on Contracts to which the Government is a Party ( ACGP )

More information

Scottish Conditions of Appointment of an Architect SCA/2014 (Apr 2015)

Scottish Conditions of Appointment of an Architect SCA/2014 (Apr 2015) SCA/201 (Apr 2015) Definitions Where the defined terms are used in the SCA/201 (Apr 2015) they are distinguished by an initial capital letter. Appointment The agreement between the Client and the Architect

More information

Kirtanlal International / Al Zahra Scaffold TRD. LLC. Scaffolding and Formwork Division January Standard Terms and Conditions of trade.

Kirtanlal International / Al Zahra Scaffold TRD. LLC. Scaffolding and Formwork Division January Standard Terms and Conditions of trade. Kirtanlal International / Al Zahra Scaffold TRD. LLC Scaffolding and Formwork Division January 2016. Standard Terms and Conditions of trade. Definitions. Conditions means the Conditions of Trade. Contract

More information

IPSAS 11 CONSTRUCTION CONTRACTS

IPSAS 11 CONSTRUCTION CONTRACTS IPSAS 11 CONSTRUCTION CONTRACTS Acknowledgment This International Public Sector Accounting Standard (IPSAS) is drawn primarily from International Accounting Standard (IAS) 11 (revised 1993), Construction

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Australian Standard. Water Corporation Version July 2012 AS (Incorporating Amendment No. 1)

Australian Standard. Water Corporation Version July 2012 AS (Incorporating Amendment No. 1) Water Corporation Version July 2012 AS 4910 2002 (Incorporating Amendment No. 1) AS 4910 2002 Australian Standard Water Corporation General conditions of contract amended from General conditions of contract

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

Construction Claims and Pitfalls. Including General Claims/ Requests for Equitable Adjustment (REAs)

Construction Claims and Pitfalls. Including General Claims/ Requests for Equitable Adjustment (REAs) Construction Claims and Pitfalls Including General Claims/ Requests for Equitable Adjustment (REAs) OVERVIEW What Went Wrong? REAs vs. Claims Measuring Delay Damages Differing Site Conditions Who Has Authority

More information

SUMMARY OF ENGINEERING SERVICES MASTER SERVICES AGREEMENT

SUMMARY OF ENGINEERING SERVICES MASTER SERVICES AGREEMENT Filed: 0-0- EB-0-0 Schedule Attachment Page of 0 0 SUMMARY OF ENGINEERING SERVICES MASTER SERVICES AGREEMENT Contract Name: Extended Services Master Service Agreement Dates: Date of Summary: May, 0 E.S.

More information

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month and

More information

10 Tips For Pursuing Claims After Construction Accidents

10 Tips For Pursuing Claims After Construction Accidents Portfolio Media. Inc. 860 Broadway, 6th Floor New York, NY 10003 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com 10 Tips For Pursuing Claims After Construction Accidents

More information

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated: Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,

More information

THE LAKES DISTILLERY COMPANY QUATREFOIL COLLECTION TERMS & CONDITIONS

THE LAKES DISTILLERY COMPANY QUATREFOIL COLLECTION TERMS & CONDITIONS THE LAKES DISTILLERY COMPANY QUATREFOIL COLLECTION TERMS & CONDITIONS 1. THESE TERMS 1.1 These are the terms and conditions on which we supply the Quatrefoil Collection to you. Please read these terms

More information

AGREEMENT FOR PRELIMINARY CONSTRUCTION SERVICES FOR THE DEVELOPMENT OF (INSERT PROJECT NAME HERE)

AGREEMENT FOR PRELIMINARY CONSTRUCTION SERVICES FOR THE DEVELOPMENT OF (INSERT PROJECT NAME HERE) AGREEMENT FOR PRELIMINARY CONSTRUCTION SERVICES FOR THE DEVELOPMENT OF (INSERT PROJECT NAME HERE) This Agreement is made and entered into this (INSERT DATE HERE), 2015 between the Santa Maria Joint Union

More information

CONTRACT COSTING. Contracts given on lump sum fixed price is fixed price contract.

CONTRACT COSTING. Contracts given on lump sum fixed price is fixed price contract. CONTRACT COSTING Definition: Contract costing is that method of costing in cost accounting which is used to collect and identify all the expenses relating to a specific contract. It is a way of providing

More information

ELECTRONIC RECORDING VENDOR MEMORANDUM OF UNDERSTANDING

ELECTRONIC RECORDING VENDOR MEMORANDUM OF UNDERSTANDING ELECTRONIC RECORDING VENDOR MEMORANDUM OF UNDERSTANDING THIS VENDOR MEMORANDUM OF UNDERSTANDING (hereinafter referred to as MOU) dated, is between the office of the Register of Deeds of Wake County, North

More information

EXHIBIT "B" CRITERIA AND BILLING FOR EXTRA SERVICES

EXHIBIT B CRITERIA AND BILLING FOR EXTRA SERVICES EXHIBIT "B" CRITERIA AND BILLING FOR EXTRA SERVICES The following Extra Services to the Agreement shall be performed by Architect if needed and if authorized or requested by the District: A. Making revisions

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date: This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative) [If

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

2 nd Edition September 2005 (Second Edition of CIDB document 1020) Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF

More information

SAMPLE COPY ONLY NOT FOR USE. Client / Architect Agreement (Short Form 2011 Edition) Client Details. Contact Name:

SAMPLE COPY ONLY NOT FOR USE. Client / Architect Agreement (Short Form 2011 Edition) Client Details. Contact Name: Client / Architect Agreement (Short Form 2011 Edition) Client Details Name: Address: ACN/ABN: Telephone: Contact Name: Facsimile: Email: Use this clause if Client is an individual Client signature: Witness

More information

Preparing Interim Payment Valuations for Construction Works - Worked Examples and Solutions

Preparing Interim Payment Valuations for Construction Works - Worked Examples and Solutions Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2018-03-10 Preparing Interim Payment Valuations for Construction Works - Worked Examples and Solutions

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

DESERT COMMUNITY COLLEGE DISTRICT General Terms and Conditions

DESERT COMMUNITY COLLEGE DISTRICT   General Terms and Conditions DESERT COMMUNITY COLLEGE DISTRICT www.collegeofthedesert.edu General Terms and Conditions 1. PURCHASE ORDER DEFINED: The term purchase order as used in these terms conditions means the document entitled

More information

MANDATORY GENERAL TERMS AND CONDITIONS:

MANDATORY GENERAL TERMS AND CONDITIONS: MANDATORY GENERAL TERMS AND CONDITIONS: A. PURCHASING MANUAL: This solicitation is subject to the provisions of the College s Purchasing Manual for Institutions of Higher Education and their Vendors and

More information

Company Name: Address: Date: OFFICAL SIGNATURE PRINT

Company Name: Address: Date: OFFICAL SIGNATURE PRINT Section 3 Clause A. The work to be performed under this contract is subject to the requirements of section 3 of the Housing and Urban Development Act of 1968, as amended, 12 U.S.C. 1701u (section 3). The

More information

referred to: 6 Statutory obligations 4 Statutory Obligations, Notices, Fees and Charges Statutory Requirements

referred to: 6 Statutory obligations 4 Statutory Obligations, Notices, Fees and Charges Statutory Requirements HKIS QSD PQSL Series 2014 by Sr. TANG Ki-cheung FHKIS RPS(QS) FSZCEA MHKIVM Director of K C Tang Consultants Ltd. Quantity Surveyors. Construction Cost and Contract Consultants Ltd. on 14 August 2014 (Thursday)

More information

Chapter 26. The Contract

Chapter 26. The Contract Chapter 26. The Contract Summary This chapter identifies, in general terms, the required elements of a contract entered into for the procurement of goods or services. The specific elements of a contract

More information

U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS

U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS U.S. DEPARTMENT OF HOMELAND SECURITY'S URBAN AREAS SECURITY INITIATIVE GRANT PROGRAM REQUIREMENTS FOR PROCUREMENT CONTRACTS I. DEFINITIONS A. Agreement means the agreement between City and Contractor to

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT made by and between, hereinafter called the Owner, and SITESCOMMERCIAL, LLC 185 WIND CHIME COURT, SUITE

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of Short Course on Construction Law with particular reference to the JBCC 2000 Series of Contracts in particular the application of JBCC Principal Building Agreements Edition 5 (2007) and Edition 4.1 (2005),

More information

Dealing with Troublesome Contracts By Chris Early Early Electronics Presented to the IEEE LICN on June 3, 2015

Dealing with Troublesome Contracts By Chris Early Early Electronics Presented to the IEEE LICN on June 3, 2015 Onerous Contracts Dealing with Troublesome Contracts By Chris Early Early Electronics unixdev@ix.netcom.com Presented to the IEEE LICN on June 3, 2015 (c) Copyright 2015 Early Electronics Disclaimer: I

More information

Water Corporation July 2012 Version AS (Incorporating Amendment No. 1)

Water Corporation July 2012 Version AS (Incorporating Amendment No. 1) Water Corporation July 2012 Version AS 4906 2002 (Incorporating Amendment No. 1) AS 4906 2002 Water Corporation General conditions of contract amended from Australian Standard Minor Works Contract Conditions

More information

PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU

PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU COUNTY GOVERNMENT OF KIAMBU DIRECTORATE OF PUBLIC WORKS PROPOSED REHABILITATION AND CONSTRUCTION OF RUIRU STADIUM - KIAMBU AT TENDER NO. KCG/YASC/STADIUM/001/2015/2016 TENDER DOCUMENTS ISSUED BY: PREPARED/CHECKED

More information

Changes, Terminations, and Claims

Changes, Terminations, and Claims Changes, Terminations, and Claims J. Clark Pendergrass Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 jcp@lanierford.com www.lanierford.com Copyright

More information

PROCUREMENT CODE. Part A Authority to Bind County to a Contract

PROCUREMENT CODE. Part A Authority to Bind County to a Contract PROCUREMENT CODE ARTICLE 4 CONTRACT FORMATION Part A Authority to Bind County to a Contract 4-101 Authorization By Dollar Amount. Regardless of the acquisition or disposal method to be used, the level

More information