1 Exam Prep Business and Finance Practice Test 4

Size: px
Start display at page:

Download "1 Exam Prep Business and Finance Practice Test 4"

Transcription

1 1 Exam Prep Business and Finance Practice Test 4 1. All the following are normally required for a loan application except. A. an income statement B. a balance sheet C. a tax return D. retained earnings 2. According to Contractors Manual, what is the accounting term that describes the maintenance of a record of each invoice and each partial payment made, including late fees, interest, and discounts? A. transaction statement method B. subsidiary ledger method C. open invoice method D. note payable ledger method 3. According to the Builder's Guide to Accounting, the only reasonable way to assign overhead is in proportion to what? A. income B. total expenses C. cost of materials D. direct labor hours 4. A previously unrecognized error or omission in the contract documents resulted in damages on a project. According to AIA-A201, the contractor is: A. liable to the owner, only B. liable to the architect, only C. not liable to the architect or the owner D. liable to both the architect and the owner 5. According to AIA-A201, if the contractor does not agree with the method for adjustment in the contract sum for a change order, who will determine the method and the adjustment? A. the owner B. the contractor C. the architect D. the engineer 1 Exam Prep Business and Finance Practice Test 4 1

2 6. CPM and PERT are methods of construction. A. estimating B. scheduling C. accounting D. purchasing 7. All the following are characteristics of a cost-plus contract except that. A. the contractor's fee can be designated as a fixed percentage of the cost B. it usually only requires the contractor's best efforts be used to accomplish the work C. it provides for reimbursement of defined costs incurred, plus a fee for the D. contractor's services it provides for a stated price for the total amount of work to be performed on a project 8. A contractor observes a concealed condition that differs materially from that indicated in the contract documents. According to AIA-A201, in order to make a claim related to these concealed conditions, the contractor must notify the architect within how many days of the date of observance of the concealed condition? A. 7 B. 21 C. 30 D A subcontractor neglects to carry out the work in accordance with the contract agreement. According to AIA-A401, when must the contractor make good on such deficiencies? A. immediately B. after waiting a total of three days for the subcontractor C. if the subcontractor fails within three business days after receipt of written notice from the contractor to commence and continue correction of such default or neglect D. if the subcontractor fails within five business days after receipt of written notice from the contractor to commence and continue correction of such default or neglect 10. According to the Contractors Manual, the square footage method of estimating is not recommended for. A. guaranteed maximum price contracts B. cost t-plus fee contracts D. cost-plus contracts D. lump-sum contracts 1 Exam Prep Business and Finance Practice Test 4 2

3 11. What is meant by "discount" on a loan? A. the credit given to a contractor for experience B. the credit given the owner (borrower) for credit worthiness C. a one-time charge made as a percentage of a loan normally deducted from the amount of the loan D. the amount of the current prime lending rate charged for processing the loan 12. All the following can be accomplished as the result of a good cash budget except: A. plans for the use of excess funds when they are available B. reconciliation of the bank statement C. preparation for tax liabilities D. cash availability for day to day operations 13. To become valid, a change order must be signed by the: A. architect, owner and building inspector B. owner, contractor and lender C.architect, owner and contractor D. owner, architect and job superintendent 14. According to AIA - A701, the owner shall, at the request of the bidder to whom the award of a contract is under consideration, furnish reasonable evidence that financial arrangements have been made to fulfill the contract within how many days prior to expiration of the time for withdrawal of bids? A. 3 days B. 4 days C. 7 days D. 10 days 15. A change order is issued which changes the quantities of a material covered by a unit price in the original contract. According to AIA-A201, what price adjustment, if any, can be made? A. the unit price can be adjusted equitably in either the contractor's or owner's favor B. the unit price can only be adjusted jn the owner's favor C. the unit price can only be adjusted in the contractor's favor D. the unit price cannot be adjusted or changed 16. According to the Builder's Guide to Accounting, when estimating job costs, all the following should be included except for. A. labor B. material losses C. fixed overhead D. construction materials 1 Exam Prep Business and Finance Practice Test 4 3

4 17. What portion of the contract documents consist of the written requirements for materials, equipment, construction systems, standards and workmanship for the work, and performance of related services? A. drawings B. specifications C. as-builts D. submittals 18. What can a contractor determine at the break even-point? A. various yields for different types of jobs B. the kind of work that is needed to reach a volume goal C. growth potential D. the least amount of sales needed to break even, assuming costs and expenses remain reasonably constant 19. What is a joint venture? A. a creation by statures for people seeking a profit in a corporation B. any association of two or more entities or persons seeking a profit under a partnership agreement C. two or more entities or persons seeking a profit in a specific ongoing project D. two or more entities or persons seeking a profit with immunity from liability 20. A contractor computes the percentage of gross profit to sales volume over a number of months. The contractor finds that gross profit is decreasing in relationship to sales. Of the factors listed below, which is the most likely explanation? A. not enough volume of work B. sales prices are to high C. lack of control over costs D. material thefts are decreasing 21. According to AIA A401, the contractor must pay the subcontractor each progress payment within how many working days after the contractor receives payment from the owner? A. Day B. 3 days C. 7 days D. 14 days 22. A contractor will complete a project in 2 years. At the end of the first year, annual gross receipts were $8,500,000. What is the amount that the gross receipts for the second year cannot equal or exceed in order to use the completed contract method of accounting? A. $5,000,000 B $6,500,000 C. $10,000,000 D. $11,500,000 1 Exam Prep Business and Finance Practice Test 4 4

5 23. According to AIA-A201, all the following could be cause for an architect to withhold certification of payment except. A. material man filing claims for non-payment B. failure to carry out the work in accordance with the contract documents C. damage done by the owner to the contractor D. defective work not remedied 24. According to Builders Guide to Accounting, which accounting method is the most acceptable for recording income and expenses for large jobs which last longer than one tax year? A. percentage of completion B. completed contract C. combined accounting D. cash accounting 25. According to Contractors Manual, project supplementary general conditions include all the following except. A. site work B. masonry work C. temporary workers D. job surface explorations 26. A bid bond guarantees that when the contract is awarded, the bidder will. A. submit a breakdown of the bid together with a list of subcontractors B. enter into the contract at the bid price C. submit copies of all bid documents for the owner's review D. submit a statement of the contractor's qualifications and past performance 27. A subcontractor has a "Standard Form of Agreement Between Contractor and Subcontractor " with the prime contractor on a project. The subcontractor can terminate the contract in each situation, except A. for non-payment of amounts due for 60 days or longer B. when the contractor and subcontractor cannot settle a controversy or claim C. when the work is stopped for 30 days or longer due to an act of government that is making materials unavailable D. when the work is stopped for 30 days or longer due to the architect not issuing a Certificate for Payment 28. When a change order (which is not a construction change directive or a minor change) is issued, who must sign it? A. the architect only B. the owner and architect only C. the contractor and architect only D. the contractor, owner, and architect 1 Exam Prep Business and Finance Practice Test 4 5

6 29. Billings that have been mailed out by a firm, but for which payment has not been made, are called A. unearned income B. receivable C. deferred income D. accounts payable 30. When determining a bid for a job, which is considered a fixed overhead expense? A. Cod office staff B. materials needed for the job C. purchases of small tools D. rental of equipment to be used only for that job 31. A contractor performed work for the owner of a building knowing the work was contrary to laws, codes, and rules. The contractor did not notify the architect. The engineer worked closely with the architect in producing the plans and specifications. All work was done as per plans and specifications. Who shall assume full responsibility for the work? A. owner B. architect C. engineer D. contractor 32. According to AIA-A201, what is prepared by an architect ordering additional work to a contract that does not require the contractor's signature? A. change order B. construction change directive C. Notice of Commencement D. punch list 33. According to Builder's Guide to Accounting, a valuable method of preparing a cash budget for builders who have wide variations in business volume from month-to-month month is the: A. cash movement method B. percentage of completion method C. capitalized cost method D. source and application of funds method 34. A contract states the contractor will be held liable for all damages suffered due to poor workmanship by the contractor. There is no state law dealing with this situation. Generally, would the contractor's contractual liability insurance pay for the liability the contractor assumed in the contract? A. no, because liability insurance covers only those situations that arise from a duty imposed by law B. only if the contractor has a Completed Operations policy C. yes, because contractual liability insurance provides for all damages D. yes, because the liability arose out of a specific contract signed by the contractor 1 Exam Prep Business and Finance Practice Test 4 6

7 35. When a contract states a completion date, a penalty clause often calls for. A. extra work without compensation B. liquidated damages C. forfeiture of all retainage due D. withholding of funds for work in place 36. According to Contractors Manual, what is the term used when submitting a contract cost breakdown where a higher percentage of estimated cost is added to the early phases of construction and lower percentage is added to the phases near the end, resulting in increased cash flow that aids the contractor in financing of the project? A. one sided contract B. back-end loading C. heavy early-light late D. front-end loading 37. According to AIA-A201, all the following would be considered by the architect when calculating the cost of a change directive, except. A. bond premiums B. hand tool rental costs C. unloading materials cost D. labor fringe benefits 38. What prepared document would contain current information about revenue that is due to a company? A. cash flow statement B. bank balance statement C. aging of accounts receivable D. income statement 39. A lienor, who is a privity lienor, is one. A. whose lien has been filed B. whose lien has been satisfied C. with a direct contract with the owner D. with a contract with other than the owner 40. A lawsuit to claim breach of a written contract must be brought within. A. one year B. three years C. five years D. seven years 1 Exam Prep Business and Finance Practice Test 4 7

8 41. According to Contractors Manual, Type A soils require a maximum allowable slope for excavations less than 20' deep of. A. 3/4:1 B. 1:1 C. 1-1/4:1 D. 1-1/2:1 42. A person may engage in business under a fictitious name by filling out an "Application for Registration of Fictitious Name" and registering the name with the. A. Department of Business and Professional Regulation B. Division of Corporations C. Department of Commerce D. Internal Revenue Service 43. All of the following are considered construction activities as described in the Worker's Compensation statute except. A. architectural work that is included in a construction contract B the manufacturing of materials used in construction work C. landscaping for new construction D. carpet laying in new construction 44. Employers are required by regulation to keep so called "hard records" such as payroll, employment contracts, sales and purchase records for their employees a minimum of. A. 2 years B. 3 years C. 4 years D. 5 years 45. The division of Worker's Compensation does not consider to be a construction business. A. remodeling existing structures B. clearing land construction purposes C. rebuilding existing structures D. well drilling on land with existing buildings 46 A contractor's employee hurt a hand and leg on the job on March 15, causing a loss of 15 work days. What is the latest date that the employee may report the accident to the employer in order to be covered under Workers' Compensation? A. March 22nd B. March 30th C. April 14th D. April 29 th 1 Exam Prep Business and Finance Practice Test 4 8

9 47. Withholding and Social Security are deposited by mail and received by the proper financial institution after the due date. The Internal Revenue Service will consider the deposit to be timely if the employer can prove that the deposit was mailed. A. the date before the due date B. on the due date C. at least 2 days before the due date D. a minimum of 5 days before the due date 48. If the current ratio is too low, it may be raised by. A. converting cash to fixed assets B. retaining profits within the business to buy fixed assets C. replacing short-term borrowing with long-term borrowing D. increasing its operating costs 49. Which type of employer is required to maintain OSHA records? A. a partnership with no employees B. self-employed persons with one or more employees C. employers of household workers D. individuals not classified as "employees" 50. The Americans with Disabilities Act of 1990 (ADA). A. protects employees of an organization from people with disabilities B. protects employers from people with disabilities C. protects employees with disabilities from differential treatment D. protects the public from employers using employees with disabilities 1 Exam Prep Business and Finance Practice Test 4 9

10 1 Exam Prep Business and Finance Practice Test 4 10

11 ANSWER KEY 1. D Page 317 Builder's Guide to Accounting 2. C Ch. 3 Florida Contractors Manual 3. D Page 228 Builder's Guide to Accounting 4. C Section AIA Document A C Section AIA Document A B Ch. 10 Florida Contractors Manual 7. D Ch. 3 Florida Contractors Manual 8. B Section AIA Document A D Section 3.4 AIA Document A D Page Florida Contractors Manual 11. C Ch. 3 Florida Contractors Manual 12. B Page 173, 174 Builder's Guide to Accounting 13. C Section AIA Document A C Section 6.2 AIA Document A A Section AIA Document A B Page 227 Builder's Guide to Accounting 17. B Section AIA Document A D Page 178, 179 Builder's Guide to Accounting 19. C Ch. 1 Florida Contractors Manual 20. C Page 272 Builder's Guide to Accounting 21. B Section 11.3 AIA Document A C Page 25 Builder's Guide to Accounting 1 Exam Prep Business and Finance Practice Test 4 11

12 23. C Section AIA Document A A Page 25, 26 & 32 Builder's Guide to Accounting Page 25, completed contract method is used for small jobs. Answer B is eliminated. Page 26, combined accounting method is not recommended for long duration contracts and can complicate record keeping. Answer C is eliminated. Page 32, cash accounting method deals with cash entries only (cash changing hands) and is does not reflect a company's true financial condition. Answer D is eliminated. 25. B Ch. 10, masonry work is not one listed Florida Contractors Manual 26. B Ch. 8 and Ch. 3 Florida Contractors Manual 27. B Section 2.1 AIA Document A401 The subcontractor is bound by the same obligations and responsibilities to the prime contractor as the prime contractor is bound to the owner. Answer A: Answer B: Answer C: Answer D: the subcontractor can terminate the contract according to AIA Document A401, Section Answer A is eliminated. the subcontractor cannot terminate the contract according to AIA Document A401, Section 6.1 & 6.2 because all claims or disputes shall be settled by mediation or arbitration. Answer B is correct. the subcontractor can terminate the contract according to AIA Document A201, Section Answer C is eliminated. the subcontractor can terminate the contract according to MA Document A201, Section & Answer D is eliminated. 28. D Section AIA Document A B Page Ch. 3 Florida Contractors Manual Pages Builder's Guide to Accounting 30. A Page 142 and 143 Builder's Guide to Accounting 31. D Section AIA Document A B Section AIA Document A A Page 176 Builder's Guide to Accounting 34. D Ch. 4 Florida Contractors Manual 1 Exam Prep Business and Finance Practice Test 4 12

13 35. B Page Ch. 3 and Ch. 10 Florida Contractors Manual 36. D Ch. 10 and Ch. 3 Florida Contractors Manual 37. B Section AIA Document A C Page 46 Builder's Guide to Accounting 39. C Ch. 9, Florida Contractors Manual 40. C Ch. 8 Florida Contractors Manual 41. A Ch. 7 Florida Contractors Manual 42. B Ch. 1 Florida Contractors Manual 43. B Ch. 6 Florida Contractors Manual 44. B Ch. 5 Florida Contractors Manual 45. D Ch. 6 Florida Contractors Manual 46. C Ch. 6 Florida Contractors Manual The employee has 30 days to report the injury. March = 31 days - 15 days = 16 days + 14 days (30 days) into April = April 14th 47. C Ch. 3 Circular E, Employer's Tax Guide In Florida Contractors Manual 48. C Page 174, 175 Builder's Guide to Accounting 49. B Ch. 7 Florida Contractors Manual 50. C Ch. 5 Florida Contractors Manual 1 Exam Prep Business and Finance Practice Test 4 13

1 Exam Prep Business and Finance Practice Test 10

1 Exam Prep Business and Finance Practice Test 10 1 Exam Prep Business and Finance Practice Test 10 1. What is an advantage of a bad debt reserve? A. it reduces tax liability for earned profit B. it increases assets C. it increases profits D. it simplifies

More information

1 Exam Prep Business and Finance Practice Test 7

1 Exam Prep Business and Finance Practice Test 7 1 Exam Prep Business and Finance Practice Test 7 1. According to AIA-A201, which does NOT require written notice in order to file a claim for additional cost? A. minor change in the work B. work performed

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): Project University of Maine at Farmington THE OWNER: (Name and address):

More information

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition Document A232 2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address) THE CONSTRUCTION MANAGER: (Name,

More information

1 Exam Prep Florida Contractor s Reference Manual Practice Test 3

1 Exam Prep Florida Contractor s Reference Manual Practice Test 3 1 Exam Prep Florida Contractor s Reference Manual Practice Test 3 1. Before improving any real property, the owner should file a with the county clerk's office. A. Notice of commencement. B. Waiver of

More information

1 Exam Prep Business and Finance Practice Test 5

1 Exam Prep Business and Finance Practice Test 5 1 Exam Prep Business and Finance Practice Test 5 1. According to Builder's Guide to Accounting, the most precise ratio used to judge whether the level of the inventory is correct for the volume of work

More information

IFB F B-WING RENOVATIONS IFB F C OFFICES BUILD OUT. Addendum 3

IFB F B-WING RENOVATIONS IFB F C OFFICES BUILD OUT. Addendum 3 JUNE 23, 2016 ATTENTION ALL PROPONENTS: IFB F2015017 B-WING RENOVATIONS IFB F2015007 9C OFFICES BUILD OUT Addendum 3 The purpose of this Amendment is to advise all offertories of the following: 1. In Project

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor City, Zip Work Phone Number: Cell Phone Number: Fax Number: Email

More information

Document A Exhibit A Insurance and Bonds

Document A Exhibit A Insurance and Bonds Document A101 2017 Exhibit A Insurance and Bonds This Insurance and Bonds Exhibit is part of the Agreement, between the Owner and the Contractor, dated the day of in the year (In words, indicate day, month

More information

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE Page 1 of 37 for the following PROJECT: (Name and location or address) EXAMPLE THE OWNER: (Name and address) Example, THE ARCHITECT: (Name and address) TABLE OF ARTICLES 1 GENERAL PROVISIONS 2 OWNER 3

More information

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated: Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,

More information

SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS

SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS SUPPLEMENTARY AND SPECIAL TERMS AND CONDITIONS FOR MINOR PROJECTS HCPS STANDARDS DOC. No.: 01015 APPLICATION: ELEMENTARY, MIDDLE AND HIGH SCHOOL DATE OF ISSUE: 04-04-14 - Revised paragraph 13.10.1 to increase

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): A201 conversion Michigan State University East Lansing, MI THE OWNER:

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) Pre-Construction and Construction Management at Risk Services Lafayette

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition Document A232 2009 SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address)

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name and address) THE ARCHITECT: (Name and address) TABLE

More information

1 Exam Prep Business Procedures Florida Lien Law Practice Test

1 Exam Prep Business Procedures Florida Lien Law Practice Test 1 Exam Prep Business Procedures Florida Lien Law Practice Test Part 1 1. Furnished material as covered by the Construction Lien Law includes. A. Supplied materials included in the improvement, excluding

More information

ARTICLE 8 - OWNER S RESPONSIBILITIES

ARTICLE 8 - OWNER S RESPONSIBILITIES properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written

More information

1 Exam Prep Broward County Business Procedures Final Practice Exam

1 Exam Prep Broward County Business Procedures Final Practice Exam 1 Exam Prep Broward County Business Procedures Final Practice Exam Broward County Business Procedures Final Exam Please write what Book, Page number & Section for each answer 1 If an employee earns $28,000

More information

University of Maryland College Park Change Order Guidelines. I. Introduction

University of Maryland College Park Change Order Guidelines. I. Introduction University of Maryland College Park Change Order Guidelines I. Introduction This document is intended as a guideline for those currently doing business and those interested in pursuing business with the

More information

ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA

ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA A COMPARATIVE ANALYSIS OF THE 1997 CHANGES TO THE AIA GENERAL CONDITIONS TO THE CONTRACT FOR CONSTRUCTION (A201) STUART

More information

CHARLOTTE PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSALS ("RFP")

CHARLOTTE PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSALS (RFP) CHARLOTTE PUBLIC SCHOOLS CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSALS ("RFP") May 12, 2017 CHARLOTTE PUBLIC SCHOOLS A. Instructions REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES PART

More information

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) this Agreement; (2) the prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER-AT-RISK, TWO-STEP PROCESS

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER-AT-RISK, TWO-STEP PROCESS REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER-AT-RISK, TWO-STEP PROCESS GUADALUPE COUNTY EXISTING ROAD & BRIDGE SHOP RENOVATION 2605 N. Guadalupe St., Seguin, TX 78155 COUNTY WORK PROJECT RFQ NO. 2017-5302

More information

Subcontract Agreement

Subcontract Agreement S THIS AGREEMENT made as of the day of, 2012 BETWEEN the Contractor: TCL Partners 5212 123 rd Place SE Everett, WA 98208 and the For the Following Project: The Architect for the Project: The Contractor

More information

GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO (2004 Archdiocese Edition)

GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO (2004 Archdiocese Edition) GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO (2004 Archdiocese Edition) TABLE OF CONTENTS ARTICLE 1...1 General Provision...1 1.1 Definitions...1 1.2 Execution, Correlation

More information

Document A201 TM. General Conditions of the Contract for Construction

Document A201 TM. General Conditions of the Contract for Construction Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: Proposed Renovations to a Portion of the Township Municipal Building 175 West Valley Forge Road King

More information

GENERAL SPECIFICIATIONS TABLE OF CONTENTS

GENERAL SPECIFICIATIONS TABLE OF CONTENTS GENERAL SPECIFICIATIONS TABLE OF CONTENTS GS.1 CONTROL OF WORK 2 GS.2 CONTRACT DRAWINGS AND SPECIFICATIONS 2 GS.3 BID SCHEDULE FORM 2 GS.4 AWARD OF CONTRACT 2 GS.5 PERMITS AND RIGHTS-OF-WAY 3 GS.6 PROSECUTION

More information

3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents.

3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents. the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. 2.2.2

More information

Document A201 TM 2007 SP

Document A201 TM 2007 SP AIA Document A201 TM 2007 SP General Conditions of the Contract for Construction, for use on a Sustainable Project for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status

More information

AIA Document A103 TM 2007

AIA Document A103 TM 2007 AIA Document A103 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work plus a fee without a Guaranteed Maximum Price AGREEMENT made as of the

More information

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR CONTRACTOR S COPY SUBCONTRACT NO. Alberta Standard Construction Subcontract THIS AGREEMENT made this day of, A.D. 20 BETWEEN name (hereinafter called the

More information

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition)

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition) Document #: 861154 GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO for SOLE SOURCE CONTRACTS (2004 Archdiocese Edition) 86 Document #: 861161 TABLE OF CONTENTS ARTICLE

More information

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project Document A105 2007 Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

ConsensusDocs 750 vs. AIA A : Which is Best For You?

ConsensusDocs 750 vs. AIA A : Which is Best For You? ConsensusDocs 750 vs. AIA A401 2007: Which is Best For You? Presented for the AGC NE Building Chapter by Kory George and Brian Koerwitz Woods & Aitken LLP Omaha, Lincoln, Denver, Washington D.C. kgeorge@woodsaitken.com

More information

SUBCONTRACT (SHORT FORM)

SUBCONTRACT (SHORT FORM) SUBCONTRACTOR: PHONE SUBCONTRACT (SHORT FORM) PROJECT: LOCATION: This agreement is made and effective, by and between SUN CONSTRUCTION & FACILITY SERVICES, INC. (Contractor) and (Subcontractor) which are

More information

1 Exam Prep Business Procedures Practice Test 5

1 Exam Prep Business Procedures Practice Test 5 1 Exam Prep Business Procedures Practice Test 5 1. If a vehicle bears the name of a contractor or business organization what must be legibly and conspicuously displayed? A. Name and address of business

More information

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY

The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. Accounts Payable Obligations to pay for goods and services that have

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor Address Address City, Zip Work Phone Number: Cell Phone Number:

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT made by and between, hereinafter called the Owner, and SITESCOMMERCIAL, LLC 185 WIND CHIME COURT, SUITE

More information

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address)

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address) Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status and address) Case Western Reserve University

More information

This Webcast Will Begin Shortly

This Webcast Will Begin Shortly This Webcast Will Begin Shortly If you have any technical problems with the Webcast or the streaming audio, please contact us via email at: splemoderator@smartpros.com Thank You! 1 KEY ISSUES IN NEGOTIATING

More information

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor Document A104 2017 Standard Abbreviated Form of Agreement Between Owner and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal

More information

Document A201 TM. General Conditions of the Contract for Construction

Document A201 TM. General Conditions of the Contract for Construction Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name and address) Austin Community College District 9101

More information

Document A Exhibit A

Document A Exhibit A Design-Build Amendment Document A141 2014 Exhibit A This Amendment is incorporated into the accompanying AIA Document A141 2014, Standard Form of Agreement Between Owner and Design-Builder dated the day

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

Killer Contract Clauses. Presented by Ben Westcott Shareholder Andrews Myers, PC

Killer Contract Clauses. Presented by Ben Westcott Shareholder Andrews Myers, PC Killer Contract Clauses Presented by Ben Westcott Shareholder Andrews Myers, PC bwestcott@andrewsmyers.com Liability Considerations Design Defects Concealed Conditions Schedule Insurance Payment Terms

More information

AIA CONTRACT DOCUMENTS

AIA CONTRACT DOCUMENTS AIA CONTRACT DOCUMENTS A101, A102 and A201 Sanjay Kurian Becker & Poliakoff, P.A. Forms of Documents AIA A101-2007 (Lump sum) AIA A102-2007 (Guaranteed Maximum Price) AIA A201-2007 (General Conditions)

More information

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope TM Document A107 2007 Instructions Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope GENERAL INFORMATION Purpose. AIA Document A107 2007 establishes the agreement between

More information

1 Exam Prep Builder s Guide to Accounting (2)

1 Exam Prep Builder s Guide to Accounting (2) 1 Exam Prep Builder s Guide to Accounting (2) 1. All the following are normally required for a loan application except. A. an income statement B. a balance sheet C. a tax return D. retained earnings 2.

More information

Provide all materials to complete the {Contracts.Description} Scope of Work in strict accordance with this purchase order.

Provide all materials to complete the {Contracts.Description} Scope of Work in strict accordance with this purchase order. All invoices for goods and/or work covered by this Purchase Order shall be sent to ap@cmbteam.com, unless otherwise stated. PURCHASE ORDER NO.:{Contracts.ContractNum PROJECT NO.: {Projects.Number} CSI

More information

CITY OF AZLE REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER AT RISK NEW JOINT CITY HALL & POLICE ADMINISTRATION & JAIL FACILITY

CITY OF AZLE REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER AT RISK NEW JOINT CITY HALL & POLICE ADMINISTRATION & JAIL FACILITY CITY OF AZLE REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER AT RISK NEW JOINT CITY HALL & POLICE ADMINISTRATION & JAIL FACILITY The City of Azle will accept Request for Qualifications for Construction

More information

EXHIBIT B TO OWNER-CONTRACTOR CONTRACT BY AND BETWEEN UNIVERSITY OF SOUTHERN INDIANA AND SUPPLEMENTARY CONDITIONS

EXHIBIT B TO OWNER-CONTRACTOR CONTRACT BY AND BETWEEN UNIVERSITY OF SOUTHERN INDIANA AND SUPPLEMENTARY CONDITIONS EXHIBIT B TO OWNER-CONTRACTOR CONTRACT BY AND BETWEEN UNIVERSITY OF SOUTHERN INDIANA AND SUPPLEMENTARY CONDITIONS The following supplements modify, change, delete from, or add to the General Conditions

More information

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between SHORT FORM STANDARD SUBCONTRACT This Agreement is made this day of, 20, between (Contractor) and (Subcontractor). The work described in Section I below shall be performed in accordance with the prime contract

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Document A401 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN the Contractor: (Name, legal

More information

MASTER SUBCONTRACT AGREEMENT

MASTER SUBCONTRACT AGREEMENT MASTER SUBCONTRACT AGREEMENT This Master Subcontract Agreement ( Subcontract ), made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter

More information

Chapter Survey. Required Contract Elements. Offer and Acceptance

Chapter Survey. Required Contract Elements. Offer and Acceptance Contract Management Chapter Survey Required Contract Elements Contract Provisions Breach of Contract Boilerplate Provisions Provisions to Limit Risk What Are Recitals? Types of Construction Contracts Contracting

More information

SUBCONTRACT CONSTRUCTION AGREEMENT

SUBCONTRACT CONSTRUCTION AGREEMENT SUBCONTRACT CONSTRUCTION AGREEMENT THIS SUBCONTRACT CONSTRUCTION AGREEMENT, made and executed this day of, 20, by and between SHERWOOD CONSTRUCTION, INC (hereinafter referred to as "Contractor"), and (hereinafter

More information

2. TIME OF PERFORMANCE

2. TIME OF PERFORMANCE 1. SCOPE OF WORK 1.1 Subcontractor shall do the Work in accordance with the Contract Documents. Subcontractor shall furnish all necessary supervision, management, labor, tools, material, equipment, supplies,

More information

AIA Document B141 TM 1997 Part

AIA Document B141 TM 1997 Part 1 AIA Document B141 TM 1997 Part Standard Form of Agreement Between Owner and Architect with Standard Form of Architect's Services TABLE OF ARTICLES 1.1 INITIAL INFORMATION 1.2 RESPONSIBILITIES OF THE

More information

GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION ARTICLE 1 CONTRACT DOCUMENTS

GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION ARTICLE 1 CONTRACT DOCUMENTS GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION 1.1 DEFINITIONS ARTICLE 1 CONTRACT DOCUMENTS 1.1.1 The Contract Documents consist of the Owner-Construction Manager Agreement, the Conditions of the

More information

AGREEMENT FOR CONSTRUCTION PROJECT MANAGEMENT SERVICES

AGREEMENT FOR CONSTRUCTION PROJECT MANAGEMENT SERVICES AGREEMENT FOR CONSTRUCTION PROJECT MANAGEMENT SERVICES THIS AGREEMENT is made by and between the School District, a political subdivision of the State of California ("DISTRICT"), and, a California corporation,

More information

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope TM Document A107 2007 Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN

More information

PROJECT SUBCONTRACT 2012 Edition

PROJECT SUBCONTRACT 2012 Edition PROJECT SUBCONTRACT 2012 Edition This Subcontract has important consequences. Prior to its completion or modification, consultation with an attorney is encouraged. This Subcontract, unmodified, may not

More information

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor Assumes Risk of Owner Payment) The original text

More information

! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information)

!  # $  % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information) ! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information) Wynne Public Schools P.O. Box 69 Wynne, AR 72396 Telephone

More information

PBSC PALM BEACH STATE COLLEGE GENERAL CONDITIONS FOR CONSTRUCTION CONTRACTS ARTICLE 1 CONTRACT DOCUMENTS

PBSC PALM BEACH STATE COLLEGE GENERAL CONDITIONS FOR CONSTRUCTION CONTRACTS ARTICLE 1 CONTRACT DOCUMENTS PBSC PALM BEACH STATE COLLEGE GENERAL CONDITIONS FOR CONSTRUCTION CONTRACTS 1.1 DEFINITIONS ARTICLE 1 CONTRACT DOCUMENTS 1.1.1 The Contract Documents consist of the Owner-General Contractor Agreement,

More information

Document A104 TM. Standard Abbreviated Form of Agreement Between Owner and Contractor

Document A104 TM. Standard Abbreviated Form of Agreement Between Owner and Contractor Document A104 TM 2017 Standard Abbreviated Form of Agreement Between Owner and Contractor AGREEMENT made as of the Twenty Eighth day of June in the year Two Thousand Eighteen (In words, indicate day, month

More information

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents:

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: A101-2017: Standard Form of Agreement Between Owner and Contractor where

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL For Construction Manager as Constructor for Tri-North Middle School Response Due: April 2, 2018, 1:00 pm MCCSC Service Building 560 E. Miller Drive Bloomington, IN 47401. REQUEST FOR

More information

Bidding and Estimating

Bidding and Estimating Project Management Project management is a soft skill which will appear in parts of your NICET certification exam. There will be project management questions on your NICET Level 3 and 4 tests. We recommend

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

ADVERTISEMENT FOR BIDS CSD NO. 158 BID # B CONSOLIDATED SCHOOL DISTRICT # ELEMENTARY SCHOOLS CARPET INSTALLATION

ADVERTISEMENT FOR BIDS CSD NO. 158 BID # B CONSOLIDATED SCHOOL DISTRICT # ELEMENTARY SCHOOLS CARPET INSTALLATION ADVERTISEMENT FOR BIDS CSD NO. 158 BID #2011-29B CONSOLIDATED SCHOOL DISTRICT #158 2011 ELEMENTARY SCHOOLS CARPET INSTALLATION Consolidated School District #158 will receive single prime sealed bids for

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK MD ANDERSON AGREEMENT No. This Agreement is made as of, 2015 (the Effective Date ), by and between The Owner: The University of Texas M. D. Anderson

More information

SAFETY FIRST GRANT CONTRACT

SAFETY FIRST GRANT CONTRACT SAFETY FIRST GRANT CONTRACT This agreement (the Contract ) is made this day of, by and between (the Contractor ) and (the Owner ), for the (Name of Parish Corporation, ABN or high school corporation) purpose

More information

Document A201/CMa. General Conditions of the Contract for Construction where the Construction Manager is NOT a Constructor

Document A201/CMa. General Conditions of the Contract for Construction where the Construction Manager is NOT a Constructor TM Document A201CMa General Conditions of the Contract for Construction where the Construction Manager is NOT a Constructor 1992 for the following PROJECT: (Name and location or address): Interior Finish

More information

Construction Contracts and Risk Management

Construction Contracts and Risk Management Construction Contracts and Risk Management Presented By: Perry Safran - Attorney psafran@safranlaw.com 919-828-1396 www.safranlaw.com 2013 This presentation can be downloaded at: www.safranlaw.com/sloresources

More information

APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F

APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F Subcontract No.: Enter Number Cost Code: Enter Code TOCCI BUILDING CORPORATION Vendor No.: Enter Number APPLICATION FOR PAYMENT PROCEDURE SUBCONTRACT EXHIBIT F To standardize the Application for Payment

More information

QBCC PERIOD MINOR WORKS SUBCONTRACT

QBCC PERIOD MINOR WORKS SUBCONTRACT Build better. QBCC PERIOD MINOR WORKS SUBCONTRACT The General Conditions of the QBCC Period Minor Works Subcontract may not be suitable for all work and the QBCC does not make any representation as to

More information

ANNEX A Standard Special Conditions For The Salvation Army

ANNEX A Standard Special Conditions For The Salvation Army ANNEX A Standard Special Conditions For The Salvation Army TO BE ATTACHED TO AIA B101-2007 EDITION ABBREVIATED STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT 1. Contract Documents. This Annex supplements,

More information

ATTACHMENT A AIA DOCUMENT B EDITION STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT

ATTACHMENT A AIA DOCUMENT B EDITION STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT ATTACHMENT A AIA DOCUMENT B141 1987 EDITION STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT Winston-Salem/Forsyth County Board of Education June 15-2015 Revised Edition for Project: Architect: Amendments,

More information

WINDSOR NORTH WEST PARK NATURE CENTER ADDITION AND STRUCTURE PROJECT 145 LANG ROAD. WINDSOR, CT

WINDSOR NORTH WEST PARK NATURE CENTER ADDITION AND STRUCTURE PROJECT 145 LANG ROAD. WINDSOR, CT INVITATION TO BID Contractor Services Associated with: WINDSOR NORTH WEST PARK NATURE CENTER ADDITION AND STRUCTURE PROJECT 145 LANG ROAD. WINDSOR, CT 06095 THIS IS AN INVITATION FOR BIDS AND THE TOWN

More information

Document A South Carolina Division of Procurement Services, Office of the State Engineer Version of

Document A South Carolina Division of Procurement Services, Office of the State Engineer Version of South Carolina Division of Procurement Services, Office of the State Engineer Version of Document A201 2007 General Conditions of the Contract for Construction This version of AIA Document A201 2007 is

More information

CONSTRUCTION CONTRACT EXAMPLE

CONSTRUCTION CONTRACT EXAMPLE P a g e 1 CONSTRUCTION CONTRACT EXAMPLE THIS AGREEMENT, made and entered into this date, by and between, hereinafter called CONTRACTOR, and NPC QUALITY BURGER, INC., hereinafter called OWNER. IT IS HEREBY

More information

Project # and Name Subcontract Firm Name Subcontract #: Appendix F - Subcontract Terms and Conditions

Project # and Name Subcontract Firm Name Subcontract #: Appendix F - Subcontract Terms and Conditions ARTICLE 1 - SUBCONTRACTOR'S WORK AND SCHEDULE 1.1 WORK: Subcontractor agrees to furnish all supervision, labor, materials, tools, equipment, services, storage, and whatever else is required to perform

More information

Document A201 TM. General Conditions of the Contract for Construction

Document A201 TM. General Conditions of the Contract for Construction Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: for: (Name and location or address) Work for The University of Tennessee Section 00 72 13 2017 THE OWNER:

More information

C R D A Capital Region Development Authority

C R D A Capital Region Development Authority C R D A Capital Region Development Authority 100 Columbus Boulevard Suite 500 Hartford, CT 06103-2819 Tel (860) 527-0100 Fax (860) 527-0133 www.crdact.net September 26, 2018 Addendum #3 Regional Market

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

SUBCONTRACTOR AGREEMENT

SUBCONTRACTOR AGREEMENT SUBCONTRACTOR AGREEMENT THIS AGREEMENT MADE THIS DAY OF IN THE YEAR OF 2016 (In words, indicate day, month and year) BETWEEN DeWitt & Associates, Inc. 1256 South Barnes Springfield, Missouri 65804 AND:

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,

More information

EXHIBIT "B" CRITERIA AND BILLING FOR EXTRA SERVICES

EXHIBIT B CRITERIA AND BILLING FOR EXTRA SERVICES EXHIBIT "B" CRITERIA AND BILLING FOR EXTRA SERVICES The following Extra Services to the Agreement shall be performed by Architect if needed and if authorized or requested by the District: A. Making revisions

More information

SAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS

SAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS SAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS The following changes are made to the Section II. Instruction

More information

Document A Instructions

Document A Instructions TM Document A103 2007 Instructions Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee without a Guaranteed Maximum Price GENERAL INFORMATION

More information

OSE FORM 812 STANDARD SUPPLEMENTARY CONDITIONS

OSE FORM 812 STANDARD SUPPLEMENTARY CONDITIONS OSE FORM 812 STANDARD SUPPLEMENTARY CONDITIONS OWNER: PROJECT NUMBER: PROJECT NAME: 1 GENERAL CONDITIONS The General Conditions of the Contract for Construction, AIA Document A201, 2007 Edition, Articles

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month

More information

SUPPLEMENTARY CONDITIONS

SUPPLEMENTARY CONDITIONS SUPPLEMENTARY CONDITIONS Instructions for Use The A.I.A. A201-1997, General Conditions of the Contract for Construction, with Additions and Deletions by Michigan State University, along with the Supplementary

More information

Document A201 TM. General Conditions of the Contract for Construction

Document A201 TM. General Conditions of the Contract for Construction Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status and address) THE ARCHITECT: (Name, legal

More information

PART VII CONTRACT DELIVERABLES

PART VII CONTRACT DELIVERABLES PART VII CONTRACT DELIVERABLES SECTION TITLE Q R S T U Certificate of Insurance Surety Bonds Invoices Project Reports/Documents Closeout Submittals 58 SECTION Q CERTIFICATE OF INSURANCE Q.1 GENERAL REQUIREMENTS

More information

GENERAL CONDITIONS UNIT PRICE CONTRACT

GENERAL CONDITIONS UNIT PRICE CONTRACT GENERAL CONDITIONS OF UNIT PRICE CONTRACT INDEX GENERAL CONDITIONS OF CONTRACT SECTION PAGE 1 1 Definitions 2 2 Documents 3 3 Additional Instructions and Schedule of Work 4 3 Documents Provided 5 3 Documents

More information