Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

Size: px
Start display at page:

Download "Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES"

Transcription

1 Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of this presentation without written permission of the speaker and is prohibited AIA is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-aia members available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. 2 1

2 Audio Sessions Session 10 EXECUTING THE WORK Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of this presentation without written permission of the speaker and is prohibited Learning Objectives To understand the purpose and importance of schedules and complying with schedules To explore project time provisions typically established with the contract documents, and the ramifications of not performing responsibilities in a timely manner, including the effect on the project schedule To define typical contract provisions for handling delays, and which types of delays are and are not excusable To understand liquidated damages and bonus/penalty clauses 4 2

3 Session Outline STUDY GUIDE: Subject Matter Area No. 10 6% EXECUTING THE WORK A. Sequencing the Work B. Scheduling the Work C. Project Time Provisions 1. Time limits 2. Weather delays 3. Other delays 4. Liquidated damages and bonus/ penalty clauses 5 EXECUTING THE WORK STUDY GUIDE AREA NO

4 SEQUENCING THE WORK STUDY GUIDE: Submit Matter Area No A. 7 Sequencing the Work Effective sequencing requires understanding of construction processes Tasks are dependent on each other, for example Concrete forms are built first Reinforcing steel is placed Concrete is placed Forms striped Walls are framed Electrical is roughed in Plumbing is roughed in Mechanical is roughed in Wall framing is covered with wallboard

5 Sequencing the Work Common sense and experience dictate much of sequencing Contract documents may specify certain sequences Project phasing may be contractual sequencing of work that is typically established by Owner Usually set forth in Division 01 Requirements shown in construction progress schedule Common for completion of a phase is a milestone event SCHEDULING THE WORK STUDY GUIDE: Submit Matter Area No B. 10 5

6 Scheduling the Work Contractor responsible for Scheduling and timing the work Expected to keep project team informed of - Progress - Expected delivery dates - Start dates for tasks - Other issues Obtaining accurate schedules and delivery dates from subcontractors and suppliers Scheduling the Work Unanticipated events can affect schedule Labor strikes Inclement weather Plant shutdowns Availability of materials Discontinued product lines When product is late to be incorporated into project Has ripple affect on subsequently installed products Contractor should have a contingency plan for delays

7 PROJECT TIME PROVISIONS STUDY GUIDE: Submit Matter Area No C. 1. Time limits 2. Weather delays 3. Other delays 4. Liquidated damages and bonus/ penalty clauses 13 Project Time Provisions Construction progress schedule Important in context of sequencing and coordination Accurate, thorough and realistic is important Should show critical dates Should also include impact to completion when a date is not met Planning tool If project falters Recovery schedules should be required implemented by - Increased manpower - Lengthening of workday - Other methods Allows project to get back on track

8 Project Time Provisions Construction progress schedule should include anticipated weather delays Weather delays are sometimes defined in contracts as only those days in excess of those included that can be granted as extensions of time Weather delays can be included as an activity or time allowance within the critical path schedule Project Time Provisions Liquidated damages Included in many contracts that include time is of the essence provision Defined as amount that Owner has determined it will cost to not have use of facility Usually assessed for each day the project is not completed by indicated date or within indicated time Not assessed for Owner caused delays and

9 Penalty clauses Project Time Provisions Can be assessed against Contractor if: - Designated time is exceeded - Some portion of work does not comply with minimum requirements Bonus clauses Can be rewarded to Contractor if - Project is finished before designated date - Some portion of work exceeds minimum requirements and Review Outline STUDY GUIDE: Subject Matter Area No. 10 EXECUTING THE WORK A. Sequencing the Work B. Scheduling the Work C. Project Time Provisions 1. Time limits 2. Weather delays 3. Other delays 4. Liquidated damages and bonus/ penalty clauses 18 9

10 Audio Sessions Session 11 CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of this presentation without written permission of the speaker and is prohibited Learning Objectives To understand the differences between a claim and a dispute To identify the sources of claims To explore the methods for initiating and handling claims, including the determination and verification of valid claims To list the A/E s responsibilities in the claims process To understand the methods of preventing disputes and dispute resolution procedures 20 10

11 Session Outline STUDY GUIDE: Subject Matter Area No. 11 8% A. Claims and Disputes B. Claims CLAIMS AND DISPUTES 1. Sources of claims a. Contractor claims b. Owner claims c. Third-party claims 2. Contractual provisions governing claims a. Subcontractors, suppliers, and other third party must make claims through the prime contractor (an exception is the mechanic s lien) b. General conditions of the construction contract promote expeditious settling of claims by stipulating strict time constraints for filing, handling, and deciding c. A/E may request documentation form the claimant 3. Submitting claims a. A/E s responsibility as the impartial interpreter of the Contract Documents b. Claims must be filed initially with the A/E (or initial decision maker) c. Claims are initially decided by the A/E (or initial decision maker) as a condition precedent to dispute resolution Continued on following slide 21 Session Outline STUDY GUIDE: Subject Matter Area No Processing and settling claims C. Entitlement CLAIMS AND DISPUTES 1. Contractor entitlement a. Work not reasonably inferred in the contract documents b. Timely initiation of the claim 2. Owner entitlement a. Work not reasonably inferred in the Contract Documents b. Timely notification D. Resolving Claims Continued from previous slide 1. Claims involving adjustment in contract sum or time require supporting documentation a. Claims for additional cost are reviewed against A/E s independent estimate of cost, based on Contractor s schedule of values and published estimating guides b. Claims for extra time rely on documentation in the form of planned schedules, asbuilt schedules, and contemporaneous job site records Continued on following slide 22 11

12 Session Outline STUDY GUIDE: Subject Matter Area No A/E may order additional testing and sampling to prove or disprove defective or nonconforming work a. Testing should be in accordance with recognized standards b. Interested parties should have the opportunity to witness testing 3. Dispute avoidance a. Each party understanding the interests and limitations of the other b. A/E s role CLAIMS AND DISPUTES Continued from previous slide E. Disputes c. Keys are communication, documentation, and claim resolution action plans 1. When a claim cannot be resolved through negotiation 2. Contractual provisions governing disputes 3. Notification of demand for dispute resolution 4. Alternative dispute resolution 5. Methods of ADR a. Binding binding arbitration, judicial reference b. Nonbinding mediation, nonbinding arbitration, minitrial, disputes review board 23 CLAIMS AND DISPUTES STUDY GUIDE AREA NO

13 Claims and Disputes STUDY GUIDE: Submit Matter Area No A. 25 Successful project Claims and Disputes Completed on time Within budget With all claims resolved Claim is request for compensation for dealing with a situation that differs materially from what was anticipated by the parties at time of entering into the contract Change order is an undisputed claim Effective management of claims is important to success Dispute is a claim that cannot be resolved by parties of contract without intervention of independent third party

14 Claims STUDY GUIDE: Submit Matter Area No B. 1. Sources of claims 2. Contractual provisions governing claims 3. Submitting claims 4. Processing and settling claims 27 Sources of Claims Standard general conditions typically stipulate procedures and requirements about claims Filing Settling Disputing

15 Contractor prepares pricing based on Procurement documents Other factors that are reasonably foreseen at the time If during course of project, a condition is encountered contrary to those stipulated or inferred in contract documents, a claim may be initiated Sources of Claims Sources of Claims Contractor can encounter changed conditions that include Active interference by Owner or A/E Conditions beyond control of Contractor or Owner Unknown or concealed conditions affecting extent of work Modifications made to contract documents Errors and omissions in contract documents Contractor required to document changed condition was not foreseeable at time of pricing and resulted in demonstrable damages Types of breach of contract claims by Contractor For untimely payment or nonpayment Improper or ineffective construction contract administration

16 Sources of Claims Owner has firm price to perform work of the project Owner may initiate a claim if Owner believes Value of work received not commensurate with contract price Owners costs have increased because of inactions by Contractor Owner initiated claims may include Correction of nonconforming or defective work Repair of damages to existing property Liquidated or compensatory damages for late performance Ineffective management or control of the work by Contractor resulting in added costs Claims are also grounds for withholding payment Contractual Provisions Governing Claims Standard general conditions typically stipulate mechanisms for seeking relief when claims arise Promotes timely resolution Early notification by party making claim Discouraged from accumulating claims or delaying response Forfeiture of rights is consequence if time limits are exceeded Privity of contract only allows Owner and Contractor to make claims against the other Subcontractors, suppliers, and other participants rely on Contractor to pursue claims on their behalf A/E may request additional information to support claims and

17 Submitting Claims Standard general conditions typically stipulate A/E is responsible to interpret contract documents impartially A/E makes - initial - decision about claim If either party takes exception to A/E s decision, claim may be Negotiated Mediated Arbitrated Litigated Processing and Settling Claims Contractually based and focused on timely and equitable resolution Claims initially addressed by reviewing contract documents to determine entitlement Once entitlement established, cost and time adjustments should be determined If process produces desirable results, disputes can be avoided

18 Claims Management Process Figure Entitlement STUDY GUIDE: Submit Matter Area No C. 1. Contractor entitlement a. Work not reasonably inferred in the Contract Documents b. Timely initiation of the claim 2. Owner entitlement a. Work not reasonably inferred in the Contract Documents b. Timely notification 36 18

19 Entitlements Entitlement is defined as the right to benefits specified by law or contract Contractor Entitlement Involves two determinations Evaluation of contract documents to identify claim as being within Contractor s contract obligations - If found to not be reasonably inferable, Contractor entitled to modification - If found to be reasonable inferable, entitlement of claim denied Timing of claim - Standard general conditions typically stipulate Contractor required to notify Owner or A/E before performing extra work - Owner has right to proper notification - Allows Owner to evaluate situation and attempt to identify most cost effective action - Intended to avoid situations where passage of time prejudiced Owner s ability to challenge claim - Failure to properly notify can result in forfeiture of entitlements

20 Owner Entitlement Involves determination if work is reasonably inferred from contract documents If found to be reasonably inferable, Owner s claim may be upheld without modification If found not to be reasonable inferable - Owner s claim denied - Work either dismissed or provided by modification Resolving Claims STUDY GUIDE: Submit Matter Area No D. 1. Claims involving adjustment in contract sum or time require supporting documentation a. Claims for additional cost are reviewed against A/E s independent estimate of cost, based on Contractor s schedule of values and published estimating guides b. Claims for extra time rely on documentation in the form of planned schedules, as-built schedules, and contemporaneous job site records 2. A/E may order additional testing and sampling to prove or disprove defective or nonconforming work a. Testing should be in accordance with recognized standards b. Interested parties should have the opportunity to witness testing 3. Dispute avoidance a. Each party understanding the interests and limitations of the other b. A/E s role c. Keys are communication, documentation, and claim resolution action plans 40 20

21 Claims Involving Adjustments Require Supporting Documentation Upon receipt of claim, A/E may request supporting documentation Once claim clearly documented and understood, it is appropriate to issue preliminary response timeliness - Summarizing essence of claim Identify concerns toward reconciliation Summarize potential solution to resolve claim Justification of many claims apparent from outset; can be handled Properly addressing issues Negotiate a settlement Claims for Additional Costs Reviewed For stipulated sum contracts, claims reviewed against A/E s independent estimate of cost Contractor s schedule of values Published estimating guides For unit price contracts Claims reviewed against published estimating guides if unit price items do not apply to extra work A/E should verify if costs claimed are representative of total impact of conditions giving rise to claim

22 Claims for Extra Time Reviewed Contractor provides supporting documentation Planned schedules Historical or baseline schedules Site records supporting extent and duration of activities must be tied to critical path Additional Testing of Defective Work A/E / Owner may require additional testing or sampling if claim arises from defective or nonconforming work Procedures should conform to recognized industry standards Testing should certified by independent testing laboratory Samples should be accompanied by report indicating method of sampling A/E should - Establish procedures - Meet with Contractor and testing laboratory - Schedule testing or sampling so interested parties have opportunity to witness event Generally, costs responsibility of party against whom claim is decided

23 Dispute Avoidance Dispute avoidance is defined as management of claims and disputes Understanding interests and limitations of other party is first step Contractor accountable for cost elements reasonably inferable at time of pricing Owner s need for thorough documentation justifying claim Owner has right to claim for compensation for - Nonperformance - Poor performance - Negligence resulting in damage to Owner A/E s role is to Dispute Avoidance Interpret Contract Documents impartially Recommend settlement to parties A/E s role may be burdensome responsibility If decision favors Contractor rather than Owner Contractor s claim stem from errors and omissions in design A/E s integrity and sense of accountability can make difference between Claim being settled Claim becoming dispute

24 Dispute Avoidance Disputes occur when participants refuse to accept its contractual responsibilities Settling claims relies on Individual integrity Cooperation among participants Dispute avoidance Requires proactive approach that recognizes that claims are an expected part of construction Administration should be planned Dispute Avoidance First key is communication Establish methods and protocols that offer best opportunity for early identification and discussion of issues, events, or circumstances producing a claim Respecting required lines of communications Second key is documentation Precise Pertinent Accurate Timely

25 Dispute Avoidance Third key is claim resolution action plan Prioritizes claims and promptly submits detailed documentation for evaluation Identifies parties with responsibility and authority for settling claims Advances claim to higher authority when initial parties are in dispute Disputes STUDY GUIDE: Submit Matter Area No E. 1. When a claim cannot be resolved through negotiation 2. Contractual provisions governing disputes 3. Notification of demand for dispute resolution 4. Alternative dispute resolution 5. Methods of ADR a. Binding binding arbitration, judicial reference b. Nonbinding mediation, nonbinding arbitration, minitrial, disputes review board 50 25

26 Disputes occur Disputes One or both parties do not agree with A/E s decision Claim cannot be resolved through negotiations Failure to negotiate effectively is due to one of more of participants failing to understand and accept rights, responsibilities and requirements established by Contract Documents Disputes Standard general conditions typically stipulates that specified method of dispute resolution should be used when claim cannot be negotiated successfully Either party can demand the other party to file for mediation If other party does not file, then both parties waive mediation If mediation unsuccessful, parties may choose to - Invoke any dispute resolution process specified - Submit to another dispute resolution process acceptable to both parties - Submit to a court of competent jurisdiction Standard general conditions typically stipulates that A/E make a final determination on claim prior to dispute Then notify Owner and Contractor

27 Disputes Litigation is the least desirable method of dispute resolution Parties lose control of outcome Cost and time detract from success of project Alternative dispute resolution (ADR) Prevents a single party from initiating litigation Provides suitable method for economically and expeditiously addressing disputes Types of ADR - Binding - Nonbinding Disputes Binding dispute resolution is defined where both parties agree to resolve disputes by specified method and to honor findings and award, usually without appeal or litigation Binding Arbitration - Parties select neutral arbitrator, or panel of arbitrators, that have construction experience - Similar to litigation but with more expeditious resolution Judicial reference - State statutes establish authority to retain independent private party to decide claim - Appeal is same as for litigation

28 Disputes Nonbinding dispute resolution is defined where both parties agree to resolve disputes by specified method and to honor findings and award, however appeal or litigation is still an option Mediation is an extension of negotiation whereby neutral party acts as facilitator to assist in finding mutually acceptable settlement Nonbinding arbitration is a form of arbitration that can be appealed Mini-trial is not an actual trial, but structured process that allows parties to present claim to neutral party in a compressed time Disputes review board is a three member board of construction experts who periodically convene to review status of project - To detect areas of potential conflict - Make recommendations for resolution of issues before they become claims A. Claims and Disputes B. Claims C. Entitlement D. Resolving Claims E. Disputes Review Outline STUDY GUIDE: Subject Matter Area No. 11 CLAIMS AND DISPUTES Continued on following slide 56 28

Audio Sessions. Session 3 PRECONSTRUCTION. Construction Contract Administration Education Program

Audio Sessions. Session 3 PRECONSTRUCTION. Construction Contract Administration Education Program Audio Sessions Session 3 PRECONSTRUCTION Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation is protected by US and International

More information

Contracting for Small Projects. DPLE 246 July 5, 2017

Contracting for Small Projects. DPLE 246 July 5, 2017 Contracting for Small Projects DPLE 246 July 5, 2017 RLI Design Professionals is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion

More information

Learning When to Waive Good-Bye. DPLE 195 September 19, 2018

Learning When to Waive Good-Bye. DPLE 195 September 19, 2018 Learning When to Waive Good-Bye DPLE 195 September 19, 2018 1 RLI Design Professionals is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on

More information

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition Document A232 2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address) THE CONSTRUCTION MANAGER: (Name,

More information

Document A201 TM 2007 SP

Document A201 TM 2007 SP AIA Document A201 TM 2007 SP General Conditions of the Contract for Construction, for use on a Sustainable Project for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status

More information

SUBCONTRACTOR TERMS AND CONDITIONS

SUBCONTRACTOR TERMS AND CONDITIONS SUBCONTRACTOR TERMS AND CONDITIONS ARTICLE 1.0 GENERAL OBLIGATIONS The Prime Contract, including all general conditions; appendices; special and supplemental conditions or provisions; drawings or plans;

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): Project University of Maine at Farmington THE OWNER: (Name and address):

More information

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor Document A104 2017 Standard Abbreviated Form of Agreement Between Owner and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal

More information

Chapter Survey. Required Contract Elements. Offer and Acceptance

Chapter Survey. Required Contract Elements. Offer and Acceptance Contract Management Chapter Survey Required Contract Elements Contract Provisions Breach of Contract Boilerplate Provisions Provisions to Limit Risk What Are Recitals? Types of Construction Contracts Contracting

More information

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE Page 1 of 37 for the following PROJECT: (Name and location or address) EXAMPLE THE OWNER: (Name and address) Example, THE ARCHITECT: (Name and address) TABLE OF ARTICLES 1 GENERAL PROVISIONS 2 OWNER 3

More information

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project Document A105 2007 Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the day of in the year (In words, indicate day, month and

More information

AIA Document A201 TM 1997

AIA Document A201 TM 1997 AIA Document A201 TM 1997 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address): A201 conversion Michigan State University East Lansing, MI THE OWNER:

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

AIA Document A103 TM 2007

AIA Document A103 TM 2007 AIA Document A103 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work plus a fee without a Guaranteed Maximum Price AGREEMENT made as of the

More information

Document A Standard Form of Agreement Between Contractor and Subcontractor

Document A Standard Form of Agreement Between Contractor and Subcontractor Document A401 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name, legal

More information

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor Assumes Risk of Owner Payment) The original text

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2017 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

MASTER SUBCONTRACTOR AGREEMENT

MASTER SUBCONTRACTOR AGREEMENT MASTER SUBCONTRACTOR AGREEMENT THIS MASTER SUBCONTRACTOR AGREEMENT ("Agreement") is made this day of, 20, between, a ("Contractor"), and, a ("Subcontractor"). 1. Recitals: Contractor has entered into a

More information

Standard Form of Agreement Between Owner and Architect without a Predefined

Standard Form of Agreement Between Owner and Architect without a Predefined Document B102 2007 Standard Form of Agreement Between Owner and Architect without a Predefined Scope of Architect s Services AGREEMENT made as of the in the year (In words, indicate day, month and year.)

More information

Document A Exhibit A Determination of the Cost of the Work

Document A Exhibit A Determination of the Cost of the Work Document A121 2014 Exhibit A Determination of the Cost of the Work THE OWNER: (Name, legal status, address and other information) THE CONTRACTOR: (Name, legal status, address and other information) This

More information

Stopping and Restarting Projects Not Business as Usual. RLI Design Professionals Design Professionals Learning Event DPLE 224 April 20, 2016

Stopping and Restarting Projects Not Business as Usual. RLI Design Professionals Design Professionals Learning Event DPLE 224 April 20, 2016 Stopping and Restarting Projects Not Business as Usual RLI Design Professionals Design Professionals Learning Event DPLE 224 April 20, 2016 With Special Thanks To David J. Hatem of Donovan Hatem LLP Presented

More information

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor) OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor

More information

AIA Document A101 TM 2007

AIA Document A101 TM 2007 AIA Document A101 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AS MODIFIED BY OWNER AGREEMENT made as of the day of in the year (In words,

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,

More information

Five Frustrating but Controllable Aspects of Contracts. DPLE 180 April 19, 2017

Five Frustrating but Controllable Aspects of Contracts. DPLE 180 April 19, 2017 Five Frustrating but Controllable Aspects of Contracts DPLE 180 April 19, 2017 1 RLI Design Professionals is a Registered Provider with The American Institute of Architects Continuing Education Systems.

More information

Risk Allocation, Contractual Defenses and General Risk Management Practices to Mitigate Claims. DPLE 283 November 2, 2016

Risk Allocation, Contractual Defenses and General Risk Management Practices to Mitigate Claims. DPLE 283 November 2, 2016 Risk Allocation, Contractual Defenses and General Risk Management Practices to Mitigate Claims DPLE 283 November 2, 2016 RLI Design Professionals is a Registered Provider with The American Institute of

More information

Time is of the Essence and Force Majeure Provisions. DPLE 136 January 16, 2019

Time is of the Essence and Force Majeure Provisions. DPLE 136 January 16, 2019 Time is of the Essence and Force Majeure Provisions DPLE 136 January 16, 2019 1 RLI Design Professionals is a Registered Provider with The American Institute of Architects Continuing Education Systems.

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Document A401 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN the Contractor: (Name, legal

More information

ADDENDUM TO AGCC3. Unless otherwise stated, the contract price includes all taxes.

ADDENDUM TO AGCC3. Unless otherwise stated, the contract price includes all taxes. ADDENDUM TO AGCC3 This is an Addendum to the AGCC3 Long Form Standard Subcontract and shall amend and modify the Subcontract and any Contract Documents. 1. Section 3: Add the following language: Unless

More information

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition Document A232 2009 SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition for the following PROJECT: (Name, and location or address)

More information

IFB F B-WING RENOVATIONS IFB F C OFFICES BUILD OUT. Addendum 3

IFB F B-WING RENOVATIONS IFB F C OFFICES BUILD OUT. Addendum 3 JUNE 23, 2016 ATTENTION ALL PROPONENTS: IFB F2015017 B-WING RENOVATIONS IFB F2015007 9C OFFICES BUILD OUT Addendum 3 The purpose of this Amendment is to advise all offertories of the following: 1. In Project

More information

MASTER SUBCONTRACT AGREEMENT

MASTER SUBCONTRACT AGREEMENT MASTER SUBCONTRACT AGREEMENT This Master Subcontract Agreement ( Subcontract ), made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter

More information

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties.

Contractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties. SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office

More information

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT

SAMPLE DOCUMENT SUBCONTRACT AGREEMENT SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office and

More information

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated: Document A142 2014 Standard Form of Agreement Between Design-Builder and Contractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Design-Builder: (Name,

More information

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract

More information

Slide 1. Slide 2. Slide 3 LEARNING OBJECTIVES WHAT S THE DIFFERENCE? PERSONAL AND PROFESSIONAL EXCELLENCE

Slide 1. Slide 2. Slide 3 LEARNING OBJECTIVES WHAT S THE DIFFERENCE? PERSONAL AND PROFESSIONAL EXCELLENCE Slide 1 PERSONAL AND PROFESSIONAL EXCELLENCE Contract Administration Beginning With the End in Mind David E. Nash, CPPO, CPPB 50 TH ANNUAL CONFERENCE MAY 24-27, 2017 ORLANDO, FLORIDA Slide 2 LEARNING OBJECTIVES

More information

CLAUSE AND EFFECT BASIC CONTRACT LAW PRINCIPLES AND KILLER CONTRACT CLAUSES

CLAUSE AND EFFECT BASIC CONTRACT LAW PRINCIPLES AND KILLER CONTRACT CLAUSES CLAUSE AND EFFECT BASIC CONTRACT LAW PRINCIPLES AND KILLER CONTRACT CLAUSES Presented to: Insulation Contractors Association of America 2016 Annual Convention and Trade Show Denver, Colorado September

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name and address) THE ARCHITECT: (Name and address) TABLE

More information

AIA Document B141 TM 1997 Part

AIA Document B141 TM 1997 Part 1 AIA Document B141 TM 1997 Part Standard Form of Agreement Between Owner and Architect with Standard Form of Architect's Services TABLE OF ARTICLES 1.1 INITIAL INFORMATION 1.2 RESPONSIBILITIES OF THE

More information

Construction Phase Services: Pitfalls, Perils and Payment. RLI Design Professionals Design Professionals Learning Event DPLE 147 May 18, 2016

Construction Phase Services: Pitfalls, Perils and Payment. RLI Design Professionals Design Professionals Learning Event DPLE 147 May 18, 2016 Construction Phase Services: Pitfalls, Perils and Payment RLI Design Professionals Design Professionals Learning Event DPLE 147 May 18, 2016 RLI Design Professionals is a Registered Provider with The American

More information

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor

Document A401 TM. Standard Form of Agreement Between Contractor and Subcontractor Document A401 TM 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Contractor: (Name,

More information

AIA Document A102 TM 2007

AIA Document A102 TM 2007 AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the

More information

Building Liability Procurement and Project Delays: Covering All the Bases

Building Liability Procurement and Project Delays: Covering All the Bases Building Liability Procurement and Project Delays: Covering All the Bases The Canadian Institute s 22 nd Annual Conference on Provincial/ Municipal Government Liability. January 28, 2016 Damon Stoddard,

More information

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS

DOCUMENT SCHEDULING OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS DOCUMENT 01 32 13 PART 1 GENERAL 1.1 RELATED DOCUMENTS AND PROVISIONS All Contract Documents should be reviewed for applicable provisions related to the provisions in this document, including without limitation:

More information

ATTACHMENT A AIA DOCUMENT B EDITION STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT

ATTACHMENT A AIA DOCUMENT B EDITION STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT ATTACHMENT A AIA DOCUMENT B141 1987 EDITION STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT Winston-Salem/Forsyth County Board of Education June 15-2015 Revised Edition for Project: Architect: Amendments,

More information

Key Contracting Issues

Key Contracting Issues Key Contracting Issues Owner & Design Professional Agreements ConsensusDocs v. AIA 1 Speakers: Timothy M. Gibbons, Esq. Chambliss, Bahner & Stophel, P.C. Chattanooga, TN Frank E. Riggs, Esq. Troutman &

More information

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address)

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address) Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status and address) Case Western Reserve University

More information

ARTICLE 8 - OWNER S RESPONSIBILITIES

ARTICLE 8 - OWNER S RESPONSIBILITIES properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written

More information

Appendix C. Standard Form of Agreement Between [Consultant] and the Iowa Department of Transportation with Standard Form of Consultant's Services

Appendix C. Standard Form of Agreement Between [Consultant] and the Iowa Department of Transportation with Standard Form of Consultant's Services Appendix C Sample Contract for Professional Services Contract # xxxx Standard Form of Agreement Between [Consultant] and the Iowa Department of Transportation with Standard Form of Consultant's Services

More information

AGC s Preliminary Commentary to the 2007 Edition of the AIA A201 General Terms and Conditions Document

AGC s Preliminary Commentary to the 2007 Edition of the AIA A201 General Terms and Conditions Document AGC s Preliminary Commentary to the 2007 Edition of the AIA A201 General Terms and Conditions Document The new edition of the AIA A201 2007 edition was published on November 5 th. The 600-member AGC Board

More information

Contract Administration Final Exam

Contract Administration Final Exam Contract Administration Final Exam 1. You want to solicit bids for a one year contract for concrete to support your roadway construction work. At this time, prices are fluctuating due to high demand and

More information

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope TM Document A107 2007 Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN

More information

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor Address Address City, Zip Work Phone Number: Cell Phone Number:

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) Pre-Construction and Construction Management at Risk Services Lafayette

More information

SARPY COUNTY AND SARPY CITIES WASTEWATER AGENCY

SARPY COUNTY AND SARPY CITIES WASTEWATER AGENCY SARPY COUNTY AND SARPY CITIES WASTEWATER AGENCY RESOLUTION APPROVING AGREEMENT WITH HDR FOR ENGINEERING SERVICES RELATED TO THE SOUTHERN SARPY COUNTY WASTEWATER TREATMENT STUDY PHASE 2B WHEREAS, Sarpy

More information

Washington University in St. Louis

Washington University in St. Louis Washington University in St. Louis Construction Terms and Conditions A. AGREEMENT. The Purchase Order, these Terms and Conditions, any special conditions, Owner s Policies, Design Standards and Insurance

More information

Force Vector, Inc. Master Contract for Sales of Goods and Services

Force Vector, Inc. Master Contract for Sales of Goods and Services Force Vector, Inc. Master Contract for Sales of Goods and Services 1. Force Vector s Business. Force Vector, Inc., an Illinois corporation ( Force Vector ) sells various industrial goods as a reseller

More information

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner: Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE

AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE THIS AGREEMENT, entered into this day of, by and between the Arkansas State Highway

More information

SUBCONTRACT CONSTRUCTION AGREEMENT

SUBCONTRACT CONSTRUCTION AGREEMENT SUBCONTRACT CONSTRUCTION AGREEMENT THIS SUBCONTRACT CONSTRUCTION AGREEMENT, made and executed this day of, 20, by and between SHERWOOD CONSTRUCTION, INC (hereinafter referred to as "Contractor"), and (hereinafter

More information

Document A South Carolina Division of Procurement Services, Office of the State Engineer Version of

Document A South Carolina Division of Procurement Services, Office of the State Engineer Version of South Carolina Division of Procurement Services, Office of the State Engineer Version of Document A201 2007 General Conditions of the Contract for Construction This version of AIA Document A201 2007 is

More information

FIXED CONTRACT AMOUNT THIS AGREEMENT, Made as of (Current Date), In the Year of (Current Year),

FIXED CONTRACT AMOUNT THIS AGREEMENT, Made as of (Current Date), In the Year of (Current Year), FIXED CONTRACT AMOUNT THIS AGREEMENT, Made as of (Current Date), In the Year of (Current Year), Between the Owner: Owner s Name Phone Number And the Contractor: For the Project: Contractor s Name License

More information

AIA Document A102 TM 2007

AIA Document A102 TM 2007 AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the

More information

Document A104 TM. Standard Abbreviated Form of Agreement Between Owner and Contractor

Document A104 TM. Standard Abbreviated Form of Agreement Between Owner and Contractor Document A104 TM 2017 Standard Abbreviated Form of Agreement Between Owner and Contractor AGREEMENT made as of the Twenty Eighth day of June in the year Two Thousand Eighteen (In words, indicate day, month

More information

SUBCONTRACT FOR BUILDING CONSTRUCTION

SUBCONTRACT FOR BUILDING CONSTRUCTION SUBCONTRACT FOR BUILDING CONSTRUCTION TABLE OF ARTICLES 1. AGREEMENT 2. SCOPE OF WORK 3. SCHEDULE OF WORK 4. CONTRACT PRICE 5. PAYMENT 6. CHANGES, CLAIMS AND DELAYS 7. CONTRACTOR'S OBLIGATIONS 8. SUBCONTRACTOR'S

More information

ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA

ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA ICSC CENTERBUILD CONFERENCE DECEMBER 2-5, 1998 ARIZONA BILTMORE PHOENIX, ARIZONA A COMPARATIVE ANALYSIS OF THE 1997 CHANGES TO THE AIA GENERAL CONDITIONS TO THE CONTRACT FOR CONSTRUCTION (A201) STUART

More information

ANNEX A Standard Special Conditions For The Salvation Army

ANNEX A Standard Special Conditions For The Salvation Army ANNEX A Standard Special Conditions For The Salvation Army TO BE ATTACHED TO AIA B101-2007 EDITION ABBREVIATED STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT 1. Contract Documents. This Annex supplements,

More information

The Battle Royal: AGC Consensus Contracts vs. AIA Documents

The Battle Royal: AGC Consensus Contracts vs. AIA Documents The Battle Royal: AGC Consensus Contracts vs. AIA Documents David A. Ericksen, Esq. Severson & Werson, A Professional Corporation One Embarcadero Center, 26th Floor, San Francisco, CA 94111 Direct Line:

More information

20% of the Fee and 80% of the Liability: Navigating the Minefield of Construction Contract Administration

20% of the Fee and 80% of the Liability: Navigating the Minefield of Construction Contract Administration 20% of the Fee and 80% of the Liability: Navigating the Minefield of Construction Contract Administration RLI Design Professionals Design Professionals Learning Event DPLE 272 August 5, 2015 RLI Design

More information

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.) Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT

More information

AIA Document A201 TM 2007

AIA Document A201 TM 2007 AIA Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: (Name and location or address) THE OWNER: (Name and address) THE ARCHITECT: (Name and address) TABLE

More information

Document A Exhibit A Insurance and Bonds

Document A Exhibit A Insurance and Bonds Document A101 2017 Exhibit A Insurance and Bonds This Insurance and Bonds Exhibit is part of the Agreement, between the Owner and the Contractor, dated the day of in the year (In words, indicate day, month

More information

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope

Document A107. Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope TM Document A107 2007 Instructions Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope GENERAL INFORMATION Purpose. AIA Document A107 2007 establishes the agreement between

More information

Ethical Contract Negotiation

Ethical Contract Negotiation Ethical Contract Negotiation Texas Society of Professional Engineers May 16, 2006 Brian W. Erikson Quilling, Selander, Cummiskey & Lownds, P.C. 2001 Bryan Street, Suite 1800 Dallas, Texas 75201 (214) 880-1844

More information

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project Document B108 2009 Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project AGREEMENT made as of the in the year (In words, indicate day, month and year.)

More information

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) this Agreement; (2) the prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract

More information

The "Standard" Form Contract: Exploring the Decennial 2017 Changes to the AIA Contract Forms

The Standard Form Contract: Exploring the Decennial 2017 Changes to the AIA Contract Forms The "Standard" Form Contract: Exploring the Decennial 2017 Changes to the AIA Contract Forms Daniel Lund III Carys A. Arvidson February 1, 2018 CPM Conference New Orleans What happens when the construction

More information

AIA Document A102 TM 2007

AIA Document A102 TM 2007 AIA Document A102 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT made as of the

More information

Functional program Technical and other owner project requirements Project team members Construction delivery method Budget Schedule

Functional program Technical and other owner project requirements Project team members Construction delivery method Budget Schedule Contract Review Checklist TOP standard professional services agreement or an Risk management begins with your contract. In a perfect world, you would always use your firm s industry standard professional

More information

Welcome to the Model Residential Owner/Design Consultant Professional Service Agreement

Welcome to the Model Residential Owner/Design Consultant Professional Service Agreement Welcome to the Model Residential Owner/Design Consultant Professional Service Agreement The Council for the Construction Law Section of the Washington State Bar Association prepared this Model Residential

More information

Document A141 TM. Standard Form of Agreement Between Owner and Design-Builder

Document A141 TM. Standard Form of Agreement Between Owner and Design-Builder Document A141 TM 2014 Standard Form of Agreement Between Owner and Design-Builder Contract made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal status,

More information

Document A Exhibit A

Document A Exhibit A Design-Build Amendment Document A141 2014 Exhibit A This Amendment is incorporated into the accompanying AIA Document A141 2014, Standard Form of Agreement Between Owner and Design-Builder dated the day

More information

Document A Instructions

Document A Instructions TM Document A103 2007 Instructions Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee without a Guaranteed Maximum Price GENERAL INFORMATION

More information

4/15/2014. The Changing Landscape of Construction Projects traditional contracting collaborative approaches

4/15/2014. The Changing Landscape of Construction Projects traditional contracting collaborative approaches Hall & Company is a Registered Provider with the American Institute of Architects Continuing Education Systems. Credit earned based on the completion of this program will be reported to AIA/CES for AIA

More information

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents:

In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: In September 2018, NCARB updated the ARE 5.0 Handbook to include 2017 AIA Contract Documents updates for the following documents: A101-2017: Standard Form of Agreement Between Owner and Contractor where

More information

Contract Review Checklist

Contract Review Checklist Contract Review Checklist Risk management begins with your contract. In a perfect world, you would always use your firm s standard professional services agreement or an industry-standard professional association

More information

Document A201 TM. General Conditions of the Contract for Construction

Document A201 TM. General Conditions of the Contract for Construction Document A201 TM 2007 General Conditions of the Contract for Construction for the following PROJECT: Proposed Renovations to a Portion of the Township Municipal Building 175 West Valley Forge Road King

More information

Construction Law Update Comparing Contracts-A Review Of The AIA 201 and ConsensusDocs

Construction Law Update Comparing Contracts-A Review Of The AIA 201 and ConsensusDocs Construction Law Update Comparing Contracts-A Review Of The 201 and ConsensusDocs Michael P. Sams, Esq. Kenney & Sams, P.C. Old City Hall 45 School Street Boston, MA 02108 (617)-722-6045 mpsams@kandslegal.com

More information

CUSTOMER S ACCEPTANCE OF

CUSTOMER S ACCEPTANCE OF Force Vector Master Contract for Equipment Rental and Services 1) FVI s Business. (a) Force Vector, Inc., an Illinois corporation, ( FVI ) rents various types of industrial equipment ( Rented Equipment

More information

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between SHORT FORM STANDARD SUBCONTRACT This Agreement is made this day of, 20, between (Contractor) and (Subcontractor). The work described in Section I below shall be performed in accordance with the prime contract

More information

S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows:

S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows: S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows: S-1.1 The last sentence of 1804 is deleted and replaced with the following: If the Contractor

More information

SAFETY FIRST GRANT CONTRACT

SAFETY FIRST GRANT CONTRACT SAFETY FIRST GRANT CONTRACT This agreement (the Contract ) is made this day of, by and between (the Contractor ) and (the Owner ), for the (Name of Parish Corporation, ABN or high school corporation) purpose

More information

CONTRACT. Owner and Contractor agree as follows: 1. Scope of Work.

CONTRACT. Owner and Contractor agree as follows: 1. Scope of Work. CONTRACT This agreement (the "Contract") is made this day of, by and between (the "Contractor") and (name of parish corporation, ABN or high school corporation) (the "Owner"), for the purpose of stating

More information

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT This Equipment Purchase Agreement ( Agreement ) is entered into this day of, 20, by and between the Western Riverside Council of Governments,

More information

1 Exam Prep Business and Finance Practice Test 4

1 Exam Prep Business and Finance Practice Test 4 1 Exam Prep Business and Finance Practice Test 4 1. All the following are normally required for a loan application except. A. an income statement B. a balance sheet C. a tax return D. retained earnings

More information

General Terms and Conditions of Sale of DMS Enterprise GmbH

General Terms and Conditions of Sale of DMS Enterprise GmbH General Terms and Conditions of Sale of DMS Enterprise GmbH These General Terms and Conditions have been prepared in English only for information purposes. When in doubt about meaning and intention of

More information

PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS PRACTITIONER, AND ARCHITECTURAL SERVICE TO THE CLIENT

PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS PRACTITIONER, AND ARCHITECTURAL SERVICE TO THE CLIENT PROFESSIONAL PRACTICE EXAM SEPTEMBER 2009 PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS PRACTITIONER, AND ARCHITECTURAL SERVICE TO THE CLIENT Question 1: In terms of the SACAP Code of Conduct what is meant

More information

STATE OF VERMONT STANDARD FORM. GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017)

STATE OF VERMONT STANDARD FORM. GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017) STATE OF VERMONT STANDARD FORM GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017) The following general conditions are for use with DESIGN BUILD construction contracts with the State of Vermont,

More information