Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

Size: px
Start display at page:

Download "Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)"

Transcription

1 NEC3: Introduction to the Engineering and Construction Contract (ECC) Course agenda Welcome and Introductions Session 1 elearning review Session 2 the ECC system and contract strategy the Options Session 3 General provisions and Contractor s main responsibilities Session 4 Time, testing and Defects Course agenda Session 5 Payment Session 6 - Compensation events Session 7 Other aspects of the ECC Session 8 Summary & open forum NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 1

2 Course objectives Delegates should: Understand the philosophy of NEC Develop skills to advise on appropriate contract strategies Appreciate the use of Contract Data, Works Information and Site Information Course objectives Delegates should: Understand roles and responsibilities of key parties Understand important ECC clauses in particular early warning, programme, Risk Register, communications and compensation events Understand how to apply ECC in practice and achieve satisfactory solutions to problems Session 1 elearning review Recap of key points NEC characteristics stimulates good management flexible clear and simple NEC family for procurement of goods, works and services NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 2

3 NEC family Project Manager PSC or PSSC Employer Adjudicator AC Designer PSC or PSSC Supervisor PSC or PSSC Contractor ECC Typical Employer designed arrangement Subcontractor ECS or ECSS Supplier SC or SSC NEC family Project Manager PSC or PSSC Employer Adjudicator AC Supervisor PSC or PSSC Contractor ECC Typical design & build arrangement Subcontractor ECS or ECSS Designer PSC or PSSC Supplier SC or SSC Session 2 The ECC system and contract strategy the Options The Option structure is modular in form with 5 modules, normally chosen by the Employer ALWAYS have the core clauses and Schedules of Cost Components Choose ONE main Option clause (A to F) which decides the mechanism for payment Choose ONE dispute resolution Option clauses (W1 or W2) Choose as many secondary Option clauses as required (prefixed X or Y) Add any additional clauses (prefixed Z) NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 3

4 ECC structure Core clauses 1 General 2 The Contractor s main responsibilities 3 Time 4 Testing and Defects 5 Payment 6 Compensation events 7 Title 8 Risks and insurance 9 Termination ECC structure Main Option clauses are as follows: A - Priced contract with activity schedule B - Priced contract with bill of quantities C - Target contract with activity schedule D - Target contract with bill of quantities E - Cost reimbursable contract F - Management contract ECC structure Activity schedule (Option A) Lump sum contract Project well defined at tender Activities generally defined by Contractor Activities priced by Contractor Payment on completion of defined activities Milestone payments by grouping activities NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 4

5 ECC structure Bill of Quantities (Option B) Project well defined at tender but change likely Standard method of measurement used Contractor prices items in BOQ at tender stage Contractor paid for quantity of work completed Original work is re-measured (but not necessarily changes) ECC structure Target cost contracts (Options C & D) Work must be adequately defined to establish target Target cost set by activity schedule (C) or bill of quantities (D) Contractor tenders Fee (2 types) Target moves with compensation events (Options C & D) and remeasurement (Option D) Contractor gets paid forecast Defined Cost + Fee Contractor is paid or pays a share of the difference between total costs and final target ECC structure Cost reimbursable contract (Option E) Used on emergency works, where scope undefined, experimental, research work Contractor tenders Fee (2 types) Contractor gets paid forecast Defined Cost + Fee Contractor has no financial risk (except adequacy of Fee) NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 5

6 ECC structure Management contract (Option F) Contractor generally organises work only Most work carried out by Subcontractors Contractor tenders prices (lump sum) and Fee (2 types) Contractor gets paid forecast Defined Cost + Fee Contractor has limited financial risk, except for adequacy of Fee and prices for work he does himself ECC structure Employer E F C D B Financial risk of main Options A Contractor ECC structure Secondary Option clauses X1 - Price adjustment for inflation X2 - Changes in the law X3 - Multiple currencies X4 - Parent company guarantee X5 - Sectional Completion X6 - Bonus for early Completion X7 - Delay damages X12 Partnering X13 - Performance bond X14 - Advanced payment to the Contractor NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 6

7 ECC structure Secondary Option clauses X15 - Limitation of the Contractor s liability for his design to reasonable skill & care X16 - Retention X17 - Low performance damages X18 Limitation of liability X20 Key Performance Indicators Y(UK)1 Project Bank Account Y(UK)2 The Housing Grants, Construction and Regeneration Act 1996 Y(UK)3 The Contracts (Rights of Third Parties) Act 1999 Z - Additional conditions of contract Other ECC contract documents Contract Data (CD) parts 1 & 2 details specifics see generic CD included in packs Prices depends on main Option chosen include activity schedule or bill of quantities Works Information (WI) specifies and describes the works and states any constraints mainly specification and drawings Supplied by Employer or Contractor (for his design) Site Information describes the Site and its surroundings Others eg programme, performance bond Session 3 General provisions and Contractor s main responsibilities General provisions Actions Identified and defined terms Communications Project Manager and Supervisor Early warning Contractor s main responsibilities Providing the Works Contractor s design People Working with the Employer and Others Subcontracting NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 7

8 General provisions Actions (10.1) Act as stated in this contract obliges persons to do everything the contract states Act in a spirit of mutual trust and co-operation recommended in Latham Report underpins all NEC contracts legal interpretation? enforceability? Covers obligations and attitude General provisions Identified terms in Contract Data in italics Defined terms, capitalised and in 11.2 (2) Completion (certainty of requirements) (5) Defect (two types) (7) Equipment (8) Fee (covers all costs not in Defined Cost (52.1)) (12) Plant and Materials (14) Risk Register (17) Subcontractor General provisions Communications (13) Must be in a form that can be read, copied & recorded See example forms in packs Replies within period for reply or as in contract Notifications to be communicated separately NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 8

9 General provisions Project Manager and Supervisor (14) Project Manager (PM) manages ECC for Employer PM has a great deal of authority PM must be even handed in matters such as assessing payment PM is only person who can instruct changes to WI PM constrained by need to give reasons if rejects a Contractor s submission if not in contract then Contractor is compensated Supervisor is checking Contractor s compliance with the WI General provisions Acceptance of any communication (programme, design etc) by the PM or Supervisor does not change the Contractor s responsibility to Provide the Works or liability for his design (14.1) PM or Supervisor may delegate any actions (14.2) General provisions Early warning (16) - a vital part of ECC Contractor and PM have a duty to notify the other as soon as they are aware of a matter which could increase the total of the Prices delay Completion, delay meeting a Key Date or impair the performance of the works in use (16.1) Contractor may give an early warning by notifying PM of any other matter which could increase total cost PM enters early warning matters in Risk Register (16.1) NEC3: Introduction to the Engineering & Construction Contract nec 04/2013 9

10 General provisions Early warning (16) Either party may at any time instruct the other to attend risk reduction meeting (16.2); those attending co-operate in making and considering proposals to avoid or reduce risk, seeking solutions, deciding actions, updating Risk Register (16.3) PM revises Risk Register to record decisions and issues (16.4) Encourages collaboration, innovation and ability to adjust to circumstances during the contract Contractor s main responsibilities Providing the Works (20) Contractor Provides the Works in accordance with the WI Contractor s design (21) Contractor designs the parts of the works which the WI states he is to design Default is Employer design Design acceptance before proceeding Reasons for not accepting design Contractor s main responsibilities People (24) Contractor employs each key person stated in Contract Data or Employs replacement person accepted by PM Reasons for not accepting (24.1) PM may instruct removal of persons (24.2) NEC3: Introduction to the Engineering & Construction Contract nec 04/

11 Contractor s main responsibilities Working with Employer and Others (25) Multi-contract projects are coordinated through use of Key Dates, by which stated conditions have to be met If the PM decides (25.3) work does not meet Condition stated for a Key Date by the date stated and Employer incurs additional cost additional cost paid by the Contractor Optional no obligation to use Key Dates Contractor s main responsibilities Subcontracting (26) If subcontracts, Contractor still responsible for Providing the Works (26.1) Contractor submits name of each proposed Subcontractor to PM for acceptance (26.2) proposed subcontract conditions unless NEC contract is proposed or PM agrees no submission required (26.3) proposed contract data (26.4, Options C to F) Session 4 Time, testing and Defects Time Starting, Completion and Key Dates Programme Testing and Defects Searching for and notifying Defects Correcting Defects Accepting Defects Uncorrected Defects NEC3: Introduction to the Engineering & Construction Contract nec 04/

12 Time Starting, Completion and Key Dates (30) Contractor does not start work on Site until first access date (30.1) & does work so that Completion is on or before Completion Date PM decides date of Completion & certifies (30.2) Contractor does work so that Condition stated for each Key Date is met by Key Date (30.3) Completion Date can only be changed by PM as a result of compensation events, or acceleration (36) Time Take over (35) is not the same as Completion Contractor is responsible for works until take over Employer takes over within 2 weeks of Completion Employer may state in Contract Data he will not take over early, i.e. before Completion Date (35.1) Employer may take over part of works before Completion will be a compensation event if before Completion Date (60.1(15)) Time Programme (31) - very important in ECC Can be submitted with tender or post Contract Date (31.1) Accepted Programme is latest accepted by PM and includes (31.2) various key dates order and timing of operations order and timing of work of Employer and Others provisions for float, time risk allowances for each operation, a statement of how Contractor plans to do work identifying principal Equipment and resources Likely to be collection of documents which may include resource statements, information required schedules, network diagrams, bar charts Reasons for not accepting (31.3) NEC3: Introduction to the Engineering & Construction Contract nec 04/

13 neccontract.com Time Programme has to be updated regularly (32) Shows a number of things including the actual progress achieved on each operation & its effect on remaining work (32.1) How frequent? on instruction by PM when Contractor chooses interval stated in Contract Data (32.2) Testing and Defects Searching for and notifying Defects (42) Search provisions (42.1) Supervisor & Contractor notify each other of Defects they find (42.2) Correcting Defects (43) Contractor corrects notified Defects before end of defect correction period (43.2) Access required after take over to correct a Defect (43.4) NEC3: Introduction to the Engineering & Construction Contract nec 04/

14 Testing and Defects Completion defects date Defects notified: before Completion after Completion defect correction period defect correction period defect correction period before defects date Latest issue of Defects Certificate Testing and Defects Uncorrected Defects (45) Contractor pays where Contractor has not corrected Defect within defect correction period (45.1) Accepting Defects (44) Proposals that Defect not corrected (44.1) Quotation for reduced Prices and/or earlier Completion Date (44.2) Session 5 Payment Assessing the amount due Times for assessment and payment Schedule of Cost Components (SCC) Shorter Schedule of Cost Components (SSCC) NEC3: Introduction to the Engineering & Construction Contract nec 04/

15 Payment assessing the amount due PM assesses amount due at each assessment date (50.1) considers any application for payment Contractor has submitted (50.4) gives Contractor details of assessment (50.4) Assessments made at assessment interval Amount due is Price for Work Done to Date (PWDD) plus/less other amounts eg. retention, delay damages, KPIs (50.2) 1/4 PWDD retained if there is no first programme (50.3) Payment assessing the amount due - what is PWDD for each Option? Option A B C to F PWDD Total of Prices for completed activities 11.2(27) Quantities of completed work at BQ rates and proportions of lump sums 11.2(28) Defined Cost forecast to be paid before next assessment date + Fee 11.2(29) Payment assessing the amount due what is Defined Cost in Option C to F? Option C to E F Defined Cost Payments due to Subcontractors for work subcontracted and cost of components in SCC for other work, less Disallowed Cost (11.2(23)) Payments due to Subcontractors for work subcontracted and prices for work done by Contractor, less Disallowed Cost (11.2(24)) NEC3: Introduction to the Engineering & Construction Contract nec 04/

16 Payment assessing the amount due what is Disallowed Cost in Option C to F? Option Disallowed Cost C to E 11.2(25) Cost which PM decides eg - is not justified by the Contractor s accounts - should not have been paid to Subcontractor - was incurred only because Contractor did not give early warning - correcting Defects after Completion F As C to E plus 11.2(26) - payment to Subcontractor for work which CD states Contractor will do himself or Contractor s management Payment assessing the amount due what is Defined Cost in Option C to F? Defined Cost includes only amounts calculated using rates and percentages stated in the Contract Data other amounts at open market or competitively tendered prices with deductions for all discounts, rebates and taxes (52.1) Payment assessing the amount due what is the Fee in Option C to F? All Contractor s costs not included in Defined Cost are treated as included in Fee (52.1) The Fee (11.2(8)) is calculated by applying subcontracted fee percentage to Defined Cost of subcontracted work and direct fee percentage to Defined Cost of other work NEC3: Introduction to the Engineering & Construction Contract nec 04/

17 Payment times without Y(UK)2 assessment date 1 week PM certifies payment Certified payment is made 3 weeks or other period stated in CD Interest 51.2 Payment times with Y(UK)2 assessment date 7 days Y2.2 due date for payment 14 days or other period stated in CD Y2.2 final date for payment 7 days Y2.3 notice to pay less than PM s assessment Interest 51.2 Y2.4 suspension of performance of all or part of works Payment the SCC Used only in Options C to E Used for assessing both compensation events, and Price for Work Done to Date (PWDD) Contractor means the Contractor and not Subcontractors An amount is included only in one cost component and only if incurred to Provide the Works NEC3: Introduction to the Engineering & Construction Contract nec 04/

18 Payment the SSCC Used only for assessing compensation events in Options A and B in Options C to E if PM and Contractor both agree In Option A or B Defined Cost is cost of the components in the SSCC whether work is subcontracted or not 11.2(22). Therefore used to assess work carried out by Contractor and Subcontractor In Options C to E, SSCC is not used to assess work carried out by Subcontractors Amount is included only in one cost component and only if incurred to Provide the Works Payment the SCC & SSCC Components People Equipment Plant and Materials Charges Manufacture and fabrication Design Insurance Data completed in Contract Data Part 2 Session 6 - compensation events Definition Process Method of assessment Sanctions for non-compliance NEC3: Introduction to the Engineering & Construction Contract nec 04/

19 Compensation events - definition Compensation events are events which if they do not arise from Contractor s fault, entitle Contractor to be compensated for effect on the Prices, Key Dates and Completion Date Therefore it is important to remember that compensation events deal with both time and money Compensation events - definition Where are compensation events stated? 19 in subclause in main Options B & D Also in secondary Options X2, X12.3(6) & (7), X14.2, X15.2 and Y2.4 May be additional compensation events in secondary Option Z Compensation events - definition Compensation events, examples 60.1 (1) PM gives instruction changing the WI (2) Employer does not allow access to and use of part of the Site (3) Employer does not provide something (5) Default by Employer or Others (12) Contractor encounters certain physical conditions (13) A weather measurement is recorded, less frequently than once in ten year NEC3: Introduction to the Engineering & Construction Contract nec 04/

20 Compensation events - process There is a defined process to agree (or impose) the effects of a compensation event within defined time limits Notification (61) Quotation (62) Assessment (63/64) Implementation (65) Either Party can make sure that process and time scales are adhered to Compensation events - process Notification If the compensation event arises from PM or Supervisor instruction, certificate, changing decision, correcting assumption then PM notifies and instructs Contractor to provide quotation (61.1) Otherwise Contractor notifies (61.3) PM may also instruct quotation for proposed instruction (61.2) Compensation events - process Notification When Contractor notifies PM replies within one week with yes or no Answer is no if PM decides event is Contractor s fault, has not happened/will not happen, has no effect on Defined Cost or time, or is not a listed compensation event (61.4) Otherwise answer is yes and PM instructs Contractor to provide a quotation (61.4) NEC3: Introduction to the Engineering & Construction Contract nec 04/

21 Compensation events - process Quotation When instructing a quotation PM may instruct alternative quotations (after discussion with Contractor) (62.1), and/or state assumptions on which quotation is to be based (61.6), if effects are unclear Contractor provides quotation within 3 weeks (62.3), which can be extended by agreement (62.5) Compensation events - process Quotation PM replies within 2 weeks of receipt of quotation (62.3) The reply is one of following (62.3) Accept quotation Reject quotation, because it has not been prepared in accordance with contract, in which case PM must ask Contractor to provide revised quotation (with reasons), or tell Contractor he will make own assessment Note PM can t just reject Confirm that proposed instruction will not be given Compensation events - process Project Manager s assessment (64) PM makes his own assessment if Contractor has not responded within time PM decides Contractor has not assessed CE correctly No programme submitted by Contractor with quotation PM has not accepted Contractor s latest programme PM makes assessment within the time allowed for Contractor NEC3: Introduction to the Engineering & Construction Contract nec 04/

22 Compensation events - process Implementation Compensation event is implemented when PM accepts Contractor s quotation, PM notifies Contractor of own assessment, or Contractor s quotation is treated as having been accepted (65.1) Once implemented It is not reviewed if forecast is wrong (65.2) Only the Adjudicator can change it if one Party still disagrees (W1/W2) Compensation events method of assessment Change to the Prices Defined Cost of work already done forecast Defined Cost of work not yet done resulting Fee (63.1) Delay to the Completion Date length of time that, due to compensation event, planned Completion is later than planned Completion shown on Accepted Programme (63.3) Compensation events method of assessment If PM and Contractor both agree, rates and lump sums may be used as a basis for assessment (63.14 A,B,E&F, C&D) Otherwise Prices or rates in the BQ or Activity Schedule are NOT used NEC3: Introduction to the Engineering & Construction Contract nec 04/

23 Compensation events - sanctions If Contractor does not notify of CE he is supposed to (not one to be notified by PM) within 8 weeks of becoming aware of event, he loses rights to any additional time or money (61.3) If PM fails to reply to Contractor s notification of CE within 1 week, Contractor may give PM a reminder (61.4) If failure continues for a further 2 weeks after reminder, deemed that PM has accepted it is a CE & instructed a quotation to be provided (61.4) Compensation events - sanctions If PM fails within allowed time to reply to quotation (62.6), or assess quotation (64.4) Contractor may give reminder (62.6/64.4) If failure continues for a further 2 weeks after reminder, the Contractor s quotation is treated as having been accepted (62.6/64.4) Session 7 Other aspects of the ECC Title Risks & insurance Employer s risks Insurance Termination Dispute resolution NEC3: Introduction to the Engineering & Construction Contract nec 04/

24 Title Whatever title Contractor has to Plant and Materials passes to Employer when brought into Working Areas (70.2), or if they are outside the Working Areas, when they are marked by Supervisor (70.1) Objects and materials within Site (73) PM instructs how to deal with object of value or historic or other interest (73.1) Contractor has title to materials from excavation & demolition only as stated in the WI (73.2) Risks & insurance Risks & insurance 80 Employer s risks (damage and 3 rd party claims) 81 Contractor s risks (by difference) 83 Indemnity» Each party indemnifies the other» Net contribution Insurance cover 4 No Insurance policies 87 Insurance by Employer X18 Limitation of liability Termination Termination is of Contractor s obligation to Provide the Works (90.1) Contractor may terminate only for reasons in Termination Table (90.2) Employer may terminate for any reason (90.2) Stated reasons for termination (91) Procedures on termination (92) Payment on termination (93) NEC3: Introduction to the Engineering & Construction Contract nec 04/

25 Dispute resolution 2 options, W1 and W2 Choice is entered in Contract Data Part 1 W1 used unless HGCRA applies W2 used if HGCRA applies will concentrate on that Both options use adjudication as the primary means of dispute resolution Dispute resolution key points of W2 Adjudication can be at any time (W2.1(1)) Adjudicator is an independent 3 rd party who can be named in the contract, or agreed or appointed when the dispute arises (W2.2) Adjudicator has 28 days to make his decision, which can be extended by agreement (W2.3(8)) Adjudicator s decision is binding but not necessarily final (W2.3(11)) Subcontract joinder possible by agreement (W2.3(3)) Dispute resolution key points of W2 Final decision is made by tribunal named in Contract Data Part 1 Arbitration, or The courts (W2.4) Can t use tribunal until after Adjudicator makes decision (W2.4(1)) Parties have 4 weeks after decision to notify disagreement with it, otherwise becomes final as well as binding (W2.4(2)) NEC3: Introduction to the Engineering & Construction Contract nec 04/

26 Session 8 - Summary & open forum Questions and answers Were the course objectives met? Delegates should: Understand the philosophy of NEC Be able to advise on appropriate contract strategies Appreciate the use of Contract Data, Works Information and Site Information Understand the roles and responsibilities of key parties Understand important ECC clauses in particular early warning, programme, Risk Register, communications and compensation events Understand how to apply ECC in practice and achieve satisfactory solutions to problems Next steps? Further training? NEC Users Group membership? Internal NEC champion? Share best practice case studies/newsletter articles/document sharing? NEC3: Introduction to the Engineering & Construction Contract nec 04/

ENGINEERING AND CONSTRUCTION CONTRACT

ENGINEERING AND CONSTRUCTION CONTRACT THE NEC 3RD EDITION ENGINEERING AND CONSTRUCTION CONTRACT INTRODUCTION AND CRITICAL APPRAISAL For the HKIS March 23 rd 2010 Ian Heaphy Agenda Engineering and Construction Contract 3rd Edition: Aim of Presentation

More information

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Technical Forum on NEC3 Collaborative Contracts 7 March 2012 Ir Ken W. N. Ko 1 Agenda Subletting

More information

NEC4 Engineering and Construction Contract review of changes from NEC3

NEC4 Engineering and Construction Contract review of changes from NEC3 Here is a review from GMH Planning Ltd of the significant changes within the NEC4 ECC contract compared to that of the NEC3 version. We have not identified every single change, but picked out the main

More information

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION. CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION Peter Kerrigan LL.B (HONS), FRICS, FCIARB, BARRISTER www.kerrigans.net 1 Course Content Introduction and overview of ECC

More information

Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996

Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996 NEC4 ECC 5 Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996 This practice note has been prepared due to feedback from UK based users who

More information

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1 CONTRACT DATA Part one Data provided by the Employer Statements given in all contracts Completion of the data in full, according to the Options chosen, is essential to create a complete contract. 1 General

More information

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT) Tenth Edition - October 2013 NEC: DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT reads: The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the

More information

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry NEC4: Evolution not Revolution Delivering distinctive, high quality projects across the construction and property industry What is NEC? NEC is a family of contracts that facilitates the implementation

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

Construction Law Update The NEC4 suite of contracts are here!

Construction Law Update The NEC4 suite of contracts are here! Construction Law Update The NEC4 suite of contracts are here! Will Buckby and James Vernon 13 February 2018 Introductions Will Buckby, MCIHT Partner, Projects and Contracts Advisory +44 (0) 20 7469 0411

More information

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

NEC4 ENGINEERING & CONSTRUCTION CONTRACT 1. Introduction 1.1 This paper provides an overview of the NEC Engineering & Construction Contract summarising the key features and structure of the NEC family of contracts. The NEC4 (4 th Edition) box

More information

Professional Services Contract

Professional Services Contract Professional Services Contract Revising the programme 32 32.1 The Consultant shows on each revised programme. the actual progress achieved on each operation and its effect upon the timing of the reing

More information

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

2 nd Edition September 2005 (Second Edition of CIDB document 1020) Supply of Goods (Short Contract) 2 nd Edition September 2005 (Second Edition of CIDB document 1020) CIDB Supply of Goods (Short Contract) September 2005, Second Edition of CIDB document 1020 SUPPLY OF

More information

2 The Contractor s main responsibilities

2 The Contractor s main responsibilities Core Clauses 2 The Contractor s responsibilities Providing the Service 20 20.1 The Contractor Provides the Service in accordance with the Service Information. 20.2 In Providing the Service, the Contractor

More information

The Contractor s NEC3 ECC Handbook

The Contractor s NEC3 ECC Handbook The Contractor s NEC3 ECC Handbook The Contractor s NEC3 ECC Handbook Steven C. Evans This edition first published 2017 2017 John Wiley & Sons Ltd All rights reserved. No part of this publication may

More information

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong KH Fok NEC3 ECC Accredited Project Manager lobowfok@icloud.com Mobile: 9819 4463 17 January 2017 Note: This set of notes has

More information

Webinar - The Project Manager in the NEC4 ECC: What s new and different?

Webinar - The Project Manager in the NEC4 ECC: What s new and different? Webinar - The Project Manager in the NEC4 ECC: What s new and different? 17 th May 2017 Q&A session This document provides answers to the questions submitted during the webinar. The webinar can be viewed

More information

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract London Bristol Dublin Dubai Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract Tom Pemberton, Partner James Vernon, Associate 12 April 2016 Introductions Tom Pemberton

More information

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner

More information

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012 Richard Patterson, Mott MacDonald Housekeeping Safety Facilities 2

More information

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 59 Contract Data Part one, 1. 3 added, (with

More information

NEC3 ECC target contract option principles and innovative applications

NEC3 ECC target contract option principles and innovative applications INFRASTRUCTURE NEC3 ECC target contract option principles and innovative applications INTRODUCTION ISO 6707-2, Building and civil engineering Vocabulary Part 2: Contract terms, defines a target cost contract

More information

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council 07 March 2012 By Mike Allen General Background Background: 1st Edition of The New Engineering Contract

More information

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking New Terminology The main theme of NEC is that it represents an evolution rather than a revolution in thinking References to project participants as him and his actions are now stated in a neutral voice

More information

AMENDMENTS APRIL 2013

AMENDMENTS APRIL 2013 AMENDMENTS APRIL 2013 The following amendments have been made to the December 2009 edition. Full details of all amendments are available on www.neccontract.com. Page Clause Line 11 40.1 1 replace: The

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters AMENDMENTS JUNE 2006 The following amendments have been made to the June 2005 edition. Page Clause Line 10 32.1 4 deleted: and of notified early warning matters 17 70.4 2 otherwise inserted after stated

More information

The NEC 3 Engineering and Construction Contract

The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract The NEC 3 Engineering and Construction Contract A Commentary Second Edition Brian Eggleston CEng, FICE, FIStructE, FCIArb Blackwell Science 2006 Brian Eggleston

More information

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date Workshop Agenda Programme requirements within ECC contract Types of float + critical path Time risk allowance Issues associated

More information

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS C1.2 Contract Data Part one - Data provided by the Employer Clause Statement Data 1 General The conditions of contract are the core clauses and the clauses for main Option B: Priced Contract with Bill

More information

HKIS Resolving Disputes between Contractors

HKIS Resolving Disputes between Contractors HKIS Resolving Disputes between Contractors 12 December 2012 (Wednesday) 7:00pm 7:45pm Gilbert Kwok FHKIS, FRICS Partner, Hong Kong and China Construction Group Clyde & Co For further information: gilbert.kwok@clydeco.com

More information

MacRoberts. A law firm as individual as you.

MacRoberts. A law firm as individual as you. MacRoberts. A law firm as individual as you. The New NEC4: Exploring the Key Changes Mike Barlow, Partner MacRoberts LLP www.macroberts.com Glasgow Edinburgh Dundee 1 THE NEC4 ENGINEERING AND CONSTRUCTION

More information

Unpacking framework agreements for the delivery and maintenance of infrastructure

Unpacking framework agreements for the delivery and maintenance of infrastructure Unpacking framework agreements for the delivery and maintenance of infrastructure INTRODUCTION Dr Ron Watermeyer ISO 10845-1 defines a framework agreement as an agreement between an employer and one or

More information

ICES. Narrative. Applicant s name

ICES. Narrative. Applicant s name ICES Narrative Applicant s name CM Core 1 QS Financial and commercial processes in civil engineering Management of the budget is a key element of a successful project; increasingly the employer has a fixed

More information

The Key Role of the NEC Programme and who really owns the float?

The Key Role of the NEC Programme and who really owns the float? The Key Role of the NEC Programme and who really owns the float? Presentation: Objectives of the NEC form Programme requirements under NEC Ownership of float Acceptance of programmes Issues with other

More information

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals GENERAL CONDITIONS 1 GENERAL PROVISIONS.................................... 1 1.1 Definitions The Contract Persons Dates, Times and Periods Money and Payments Other Definitions 1.2 Interpretation 1.3 Priority

More information

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012 2 Februray 2012 EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC Option C) Contract No. DC/2008/02 Improvement of Fuk Man Road Nullah in Sai Kung Discussion on Contract Management

More information

All Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success

All Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success All in the Clause NEC to NEC4 Comparison of Core Clause 6 Compensation Events giving priority to your commercial success About us We provide: Quantity surveying and cost management Commercial management

More information

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M. Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project

More information

Framework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch /

Framework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch / Framework agreements The Standard for Infrastructure Procurement and Delivery Management includes provisions for framework agreements. Framework agreements have similarities with term service and transversal

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015)

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015) Ref: W/RFQ-GCC GENERAL CONDITIONS OF CONTRACT REQUEST FOR QUOTATION [Issued in terms of section

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3

More information

Conditions of Contract for PLANT and Design-Build

Conditions of Contract for PLANT and Design-Build Conditions of Contract for PLANT and Design-Build FOR ELECTRICAL AND MECHANICAL WORKS AND FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE CONTRACTOR General Conditions 1st Edition 1999 FEDERATION INTERNATIONALE

More information

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS AS 4903 2000 (Incorporating Amendment No. 1) AS 4903 2000 Australian Standard Subcontract conditions for design and construct This Australian Standard was prepared by Committee OB-003, General Conditions

More information

NEC CONTRACTS ASSESSMENT OF COMPENSATION EVENTS - NEC3 and NEC4

NEC CONTRACTS ASSESSMENT OF COMPENSATION EVENTS - NEC3 and NEC4 NEC CONTRACTS ASSESSMENT OF COMPENSATION EVENTS - NEC3 and NEC4 Northern Ireland Housing Executive v Healthy Buildings (Ireland) Limited [2017] NIQB 43 One of the common themes that we have covered in

More information

Appendix K Model Letters for Use by the Engineer

Appendix K Model Letters for Use by the Engineer 175 Model Letters for Use by the Engineer Introduction This Appendix provides model letters for use by the Engineer primarily for formal correspondence with the Contractor. These model letters do not distinguish

More information

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010 Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010 Please note that this comparison is for guidance only and does not purport to be complete and exhaustive. All corrections and improvements

More information

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister The NEC Contract Key Concepts and the Proper Approach to Assessment The proper basis of assessment of Compensation Events By Karen Gough, Barrister 1 Overriding principles in NEC3: ECC Flexibility Usable

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date:... /... /.../ This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative)

More information

Contractual Awareness Introduction

Contractual Awareness Introduction Contractual Awareness Introduction Geraldine Fleming Vice President and Executive Director February 2016 The Global Leader in Managing Construction Risk CORPORATE OVERVIEW Founded in 1973 in Manchester

More information

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1 COMPLIANCE TO CONDITIONS OF CONTRACT - SCC.1(Renovation) Please indicate clearly below your compliance to each clause of the Conditions of Contract. Where you are not in agreement, you should give your

More information

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016) Construction Industry Development Board Tel: 012 343 7136 or 012 481 9030 Fax: 012

More information

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract

More information

Session 3 by Zoltán Záhonyi, FIDIC AIT,

Session 3 by Zoltán Záhonyi, FIDIC AIT, Session 3 by Zoltán Záhonyi, FIDIC AIT, zoltan.zahonyi@zandpartners.com Contents of Session 3 Session 3: FIDIC 1999 Red Book Part 2 The Quality Issues (Plant, Materials and Workmanship) The Time is of

More information

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE

More information

Contract Review Handbook for Civil Contractors

Contract Review Handbook for Civil Contractors Contract Review Handbook for Civil Contractors Civil Contractors Federation - WA Branch P: (08) 9414 1486 www.ccfwa.com.au LAVAN LEGAL S EXpERTISE Practical advice on construction contracts, tendering

More information

NEC4 Key Commercial Changes

NEC4 Key Commercial Changes NEC4 Key Commercial Changes NEC4 User's Group Seminar 2017; 22nd June 2017; County Hall, London On Thursday (22nd June 17), I was fortunate enough to attend the NEC User s Group Annual Seminar at County

More information

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Fifth Edition - May 2017 NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT. Author: Vaughan Hattingh and

More information

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of Short Course on Construction Law with particular reference to the JBCC 2000 Series of Contracts in particular the application of JBCC Principal Building Agreements Edition 5 (2007) and Edition 4.1 (2005),

More information

Works Appointment: We, on behalf of the Employer, would like to inform you that your quotation, Reference Number

Works Appointment: We, on behalf of the Employer, would like to inform you that your quotation, Reference Number 6/F Dorset House, Taikoo Place, 979 King's Road, Quarry Bay, Hong Kong Project Works Order Works Order No.: Name of Contractor: Description of the works: Date: "Contractor") "Works") Address of premises:

More information

The 2014 JBCC suite of documents: a legal contract, risk and administration tool

The 2014 JBCC suite of documents: a legal contract, risk and administration tool Welcome! 1 The 2014 JBCC suite of documents: a legal contract, risk and administration tool Uwe Putlitz Pr Arch 2444-1976 and Pr CPM D434-2005, AA(SA) 173 Chief Executive Officer: The Joint Building Contracts

More information

Market Contract Terms

Market Contract Terms Market Contract Terms Electricity Market Retail Contract between Aurora Energy and you Aurora Energy Pty Ltd l ABN 85 082 464 622 21 Kirksway Place, Battery Point Tasmania 7004 Ph: 1300 132 003 Fax: (03)

More information

Off-Site Manufacturing

Off-Site Manufacturing Off-Site Manufacturing The Legal Implications YORhub Conference 15 th November 2018 Dr Julie Morrissy A word of warning MODERNISE OR DIE 1 Modernise or die 2016 - The Farmer Review of the UK Construction

More information

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND PROFESSIONAL ARCHITECT (PrArch) PROFESSIONAL SENIOR ARCHITECTURAL TECHNOLOGIST (PrSArchT) mark applicable registration

More information

Do your. homework. A contractor s guide to rights and obligations when contracting with homeowners

Do your. homework. A contractor s guide to rights and obligations when contracting with homeowners Do your homework A contractor s guide to rights and obligations when contracting with homeowners Disclaimer: This document is a guide only. It should not be used as a substitute for legislation or legal

More information

PROJECT NAME: SCC - Cherokee Campus Sidewalk Improvements. Table of Contents SE-310, Invitation for Construction Services...

PROJECT NAME: SCC - Cherokee Campus Sidewalk Improvements. Table of Contents SE-310, Invitation for Construction Services... TABLE OF CONTENTS 2016 Edition PROJECT NAME: SCC - Cherokee Campus - 2017 Sidewalk Improvements PROJECT NUMBER: H59-D891-01-A SECTION NUMBER OF PAGES Table of Contents... 1 SE-310, Invitation for Construction

More information

AM Request for Proposal (RFP)

AM Request for Proposal (RFP) AM - 2138 Request for Proposal (RFP) Supply of Services for Australia Awards PNG Management Information System Services Structure of Invitation Part A Invitation and Rules of Proposal Part B Scope of Services

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS

NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS IAN PARKINSON Senior Consultant, Manchester The NEC3 suite of contracts were first published in 2005, meaning that the industry has had 13 years getting to

More information

Insert heading depending. Insert heading depending on line on line length; please delete cover options once

Insert heading depending. Insert heading depending on line on line length; please delete cover options once Insert Insert heading depending Insert heading depending on line on line length; please delete on NHS on line length; line Standard length; please Contract please delete delete other other cover cover

More information

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date NZS 3915:2005 COMMITTEE REPRESENTATION This Standard was prepared by Technical Committee P 3915 for the Standards Council established under the Standards Act 1988. Peter Fehl New Zealand Contractors Federation

More information

General Terms and Conditions of Purchase (edition )

General Terms and Conditions of Purchase (edition ) General Terms and Conditions of Purchase (edition 03.05.2010) 1. Scope of validity 1.1. Orders placed by the Buyer (hereinafter referred to as Buyer ) shall be subject exclusively to these conditions,

More information

Subcontract conditions

Subcontract conditions AS 2545 1993 (Incorporating Amendment No. 1) Australian Standard Subcontract conditions This Australian Standard was prepared by Committee OB/3, General Conditions of Contract. It was approved on behalf

More information

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb.

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb. NEC3 A Practical Guide to Compensation Events Chris Holden LLB FRICS FBEng MCIArb www.kerrigans.net Introduction The intention of this presentation is to provide a practical approach to dealing with compensation

More information

Section 108. PROSECUTION AND PROGRESS

Section 108. PROSECUTION AND PROGRESS 108.01 Section 108. PROSECUTION AND PROGRESS 108.01. Subcontracting of Contract Work. No portion of the contract may be subcontracted, other than the providing of necessary materials, except as provided

More information

COAA EPC Contract Philosophy

COAA EPC Contract Philosophy 1. Introduction COAA COAA EPC Contract Committee, March 2005 The COAA EPC Contract Committee has developed a standard form EPC Contract for use in industrial projects. This EPC Contract is intended to

More information

Mono-Beneficiary Model Grant Agreement

Mono-Beneficiary Model Grant Agreement Justice Programme & Rights, Equality and Citizenship Programme Mono-Beneficiary Model Grant Agreement (JUST/REC MGA Mono) Version 2.0 10 January 2017 Disclaimer This document is aimed at assisting applicants

More information

SURCO TRAINING. presents a series of AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALSS

SURCO TRAINING. presents a series of AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALSS BK SURCO TRAINING presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS for CONSTRUCTION PROFESSIONALSS BK SURCO Limited Suite 1901-2, 19 th Floor, Hopewell Centre 183 Queen s Road

More information

NEC 3: How to claim as the main

NEC 3: How to claim as the main SECOND EDITION FEBRUARY 2016 NEC 3: How to claim as the main contractor for compensation events arising from subcontracted work under main options A (Priced Contract with Activity Schedule) and B (Priced

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

PROCUREMENT CODE. Part A Authority to Bind County to a Contract

PROCUREMENT CODE. Part A Authority to Bind County to a Contract PROCUREMENT CODE ARTICLE 4 CONTRACT FORMATION Part A Authority to Bind County to a Contract 4-101 Authorization By Dollar Amount. Regardless of the acquisition or disposal method to be used, the level

More information

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS 1. DEFINITIONS AND INTERPRETATION 1.1 Definitions In this Contract (as hereinafter defined)

More information

Helpful instructions for webinar attendees

Helpful instructions for webinar attendees Helpful instructions for webinar attendees 1. Ensure you have clicked Yes to the Integrated Voice pop up when you entered. If No, then log out and join again. This will ensure you have sound. It will not

More information

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS.

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS. TENDER NO. TCG/F&P/5/2017-2018 SEPTEMBER 2017 TABLE OF CONTENTS

More information

Plain English Commercial and Industrial Building Contract

Plain English Commercial and Industrial Building Contract Plain English Commercial and Industrial Building Contract Date: This contract is between 1 Limited (we, us, our)(the builder) of and 2 (you, your)(the client) of and (your authorised representative) [If

More information

Disputing an assessment

Disputing an assessment IR776 June 2018 Disputing an assessment What to do if you dispute an assessment 2 DISPUTING AN ASSESSMENT Introduction While we make every effort to apply the tax laws fairly and correctly, there may be

More information

Sub Contract Agreement

Sub Contract Agreement Sub Contract Agreement In a building project there is always a contractor. There need not be any sub-contractors However there will invariably be sub-contractors. There are two types of sub-contractors

More information

TRUSTED TRADER. Trusted Trader terms and conditions. Contents.

TRUSTED TRADER. Trusted Trader terms and conditions. Contents. Trusted Trader terms and conditions Contents 1. TRUSTED TRADER... 2 2. TRADING STANDARDS COMMITMENTS... 2 3. TRUSTED DIRECTORY SERVICES LTD COMMITMENTS... 2 4. BUSINESS CODE OF PRACTICE... 3 5. REQUIREMENT

More information

GUIDANCE FOR PROFESSIONAL CONSULTANTS

GUIDANCE FOR PROFESSIONAL CONSULTANTS Diocese of Westminster Education Service Page 1 MANDATORY DOCUMENTATION GUIDANCE FOR PROFESSIONAL CONSULTANTS RICS Standard Form of Consultant s Appointment RICS Standard Form of Consultant s Appointment

More information

DIRECTORATE OF ESTATES AND FACILITIES

DIRECTORATE OF ESTATES AND FACILITIES DIRECTORATE OF ESTATES AND FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006

More information

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between SHORT FORM STANDARD SUBCONTRACT This Agreement is made this day of, 20, between (Contractor) and (Subcontractor). The work described in Section I below shall be performed in accordance with the prime contract

More information

1 2 Tender Terms and Conditions: 1. This NOTICE INVITING LIMITED TENDER is open to all contractors, Class-Small registered with the Construction Development Board. 2. The bidder shall be conducted through

More information

JCT 2016 Edition of Contracts

JCT 2016 Edition of Contracts JCT 2016 Edition of Contracts Welcome to the JCT 2016 Edition of Contracts What are the main new features of the 2016 Edition?... We ve incorporated the provisions of the JCT Public Sector Supplement 2011

More information

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Implementing the Construction Supply Chain Payment Charter. January Guidance Note Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE

DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE DIVISION 1 - GENERAL REQUIREMENTS SECTION 01315A PROJECT SCHEDULE [---Section 01315A should be used for contracts for which a fully-developed computergenerated critical path method is appropriate for managing

More information

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below: DOMESTIC SUB-CONTRACT CONDITIONS These are the Domestic Sub-Contract Conditions referred to by the Articles of Agreement to which they are attached. In the event that these Domestic Sub-Contract Conditions

More information