Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs)
|
|
- Garey Robertson
- 6 years ago
- Views:
Transcription
1 Integrated Baseline Reviews (IBRs) Holding an IBR is a best practice for all programs, and it supports the implementation of an earned value management system (EVMS). EVM can be a valuable tool for controlling and tracking contractor performance. The foundation of successful earned value management is the integrated baseline review (IBR). Both the Government and contractor benefit from the IBR. It enables both parties to have a mutual understanding of the contractor's plan for executing the program. The cornerstone of the IBR is the performance measurement baseline (PMB). The PMB lays out the contractor's plan for executing the program, and establishes a baseline against which progress can be measured. In this lesson, you will learn about the purpose and objectives of conducting an IBR. You will find out when to schedule the IBR, and get some pointers on where and how to conduct it. You'll walk through the steps for creating the PMB, and examine the relationship between the PMB and the integrated master schedule (IMS). You'll also learn about re-baselining the PMB in response to changing circumstances. You may print the Integrated Baseline Review lesson or save it for future reference. Page 1 of 26
2 For programs requiring EVM, program managers can find best practices and guidance in the Integrated Baseline Review (IBR) Guide (2010).
3 Objectives: Upon completion of this lesson, you should be able to: Identify the purpose, objectives, and process of conducting an integrated baseline review (IBR) Identify the steps in the development of a performance measurement baseline (PMB) Recognize the relationship between the contractor's performance measurement baseline (PMB) and integrated master schedule (IMS) Identify the three reasons for making changes to the performance measurement baseline (PMB) Page 2 of 26
4 Purpose of the IBR The IBR is a formal review conducted jointly by the Government and the contractor to verify the: Technical content of the contract's baseline Accuracy of the related budgets and schedules An effective IBR provides a mutual understanding between the Government and the contractor of the inherent risks in the contractor's performance plans. The primary purpose of the IBR is to confirm that the contractor's Performance Measurement Baseline (PMB) covers the entire technical scope of work, that the work is realistically and accurately scheduled, and that the proper amount and mix of resources have been assigned to accomplish the work. Page 3 of 26
5 IBR Objectives The participants in an IBR typically include the Government PM and technical staff, along with the related contractor PM and staff. Their objectives for the IBR are to ensure: Technical scope of work is fully included and consistent with authorizing documents Key schedule milestones are identified Supporting schedules reflect a logical flow to accomplish the technical scope of work Resources (budgets, facilities, personnel) are adequate and available Tasks are planned and can be measured objectively, relative to technical progress Underlying PMB and IMS rationale is reasonable and achievable Managers have appropriately implemented required management processes Page 4 of 26
6 IBR Benefits Conducting an IBR provides many benefits for the program manager. An IBR: Promotes Government PM and contractor PM knowledge of the PMB Improves communications by enabling a comparison of each PM s understanding of technical/schedule/cost objectives, and identification of any differences so they can be addressed before problems arise Ensures that meaningful and reliable performance monitoring techniques are employed Lays a solid foundation for mutual understanding of risks and opportunities Assesses the PMB s capability to provide timely, reliable, and actionable schedule, cost, and scope information Uncovers new or hidden risks that need to be analyzed and entered into the program s risk register Page 5 of 26
7 Scheduling the IBR At DHS, all contracts that require an ANSI/EIA-verified earned value management system (EVMS), also require an IBR to validate it. Post-award IBRs shall be completed within ninety days of contract award. Pre-award IBRs are appropriate only when the IBR results are essential for the source selection process, and the program has adequate funding to conduct IBRs. A pre-award IBR ensures the validity of the contractor's EVMS against the contract, and assesses the contractor's ability to perform successfully. Page 6 of 26 The American National Standards Institute (ANSI) Electronics Industries Alliance (EIA) standard 748; Standard for Earned Value Management Systems (EVMS); Version C updated March 1, 2013.
8 Additional IBRs Even the best laid plans are likely to change during the course of executing a program. From time to time, it may become necessary to revisit the PMB and conduct a follow-on IBR. When a follow-on IBR is conducted, the goal and objectives are the same as those of the initial IBR: to gain a mutual understanding and confidence in the baseline plan (the PMB). In-process IBRs are typically held at key points during program development, such as: At the completion of requirements development At the end of the Design phase of the SELC Following development and testing prior to implementation Subsequent IBRs may be required whenever an established PMB is unachievable, and a new PMB and/or IMS is required to manage the contract. Like the original IBR, the subsequent IBR evaluates the risks and validity of the new PMB and IMS. Page 7 of 26
9 IBR Process The following IBR process is a best practice based upon the National Defense Industrial Association's document, Integrated Baseline Review (IBR) Guide (2010). This is the best source for DHS program managers seeking guidance on preparing for, and conducting an IBR. This IBR Guide refers to the IBR as both an event and an ongoing process. The guide suggests that once the initial IBR establishes a PMB that is mutually accepted, the Government PM should strive to maintain his or her understanding of, and confidence in, the baseline throughout the period of execution. To achieve this objective, the guide outlines a three-step, iterative, IBR process. D Page 8 of 26 Graphic depicting the IBR Process. The three steps, conducted in order and repeatedly, are: IBR needs assessment, PMB development/maintenance, and Integrated Baseline Review. In the center of the graphic are the words "Program Managers' Mutual Understanding."
10 IBR Process: IBR Need Assessment Recall that for programs required to use EVM, an initial IBR is also required. The focus of any IBR is to review and understand the program's PMB. The objective of the need assessment is simply to determine whether or not an additional IBR is necessary. Changes to the program are inevitable, and some may require a revised PMB, which may (or may not) lead to another IBR. Generally, significant changes to the PMB warrant conducting an additional IBR. The Government PM is responsible for making this decision. D Page 9 of 26 Graphic depicting the IBR Process with the first step highlighted: IBR need assessment. In the center of the graphic are the words "Program Managers' Mutual Understanding."
11 IBR Process: PMB Development/Maintenance The PMB is the time-phased budget plan against which contract performance is measured. It is formed by the budgets established at the control account level. It establishes the baseline plan which, if followed, should lead to the successful achievement of program objectives. D Page 10 of 26 Graphic depicting the IBR Process with the second step highlighted: PMB Development/Maintenance. In the center of the graphic are the words "Program Managers' Mutual Understanding."
12 Developing the PMB The contractor will develop the PMB using some version of the following three step process. This is a simplified view of a very complex and iterative process used for comprehensive project planning. Step 1: Define the Work Decompose the statement of objectives or performance work statement (SOO/PWS) into executable work elements using the work breakdown structure (WBS). The executable work elements should represent discrete and measurable work whenever possible. These discrete elements of work are called control accounts. D Page 11 of 26 Graphic labeled "Scope" with a chart depicting a work breakdown structure. The top element is labeled 1.0, and is broken down into three parts: 1.1, 1.2, and is further broken down into boxes labeled and is further broken down into boxes labeled and is further broken down into boxes labeled and
13 Developing the PMB (continued) Step 2: Schedule the Work Develop the integrated master schedule (IMS) Determine task durations for each work element Define a logical sequence of work flow Establish inter-relationships among work elements The IMS contains the networked, detailed tasks necessary to ensure successful program execution. It shows how individual tasks are related by defining their predecessor and successor relationships. The IMS also shows the planned duration for each task. These are all key planning inputs into the creation of the PMB, which takes the IMS and adds the resource allocations (budgets) to provide a more fully integrated view of the baseline plan of execution. D Page 12 of 26 Graphic labeled "Schedule" depicting a chart with four columns labeled 1st quarter, 2nd quarter, 3rd quarter, and 4th quarter. Colored rectangles lie across the schedule, stretching between various columns.
14 Developing the PMB (continued) Step 3: Allocate Resources Establish budgets ο Determine labor requirements (skill mix, experience levels) ο Identify materials and other non-labor resources ο Identify resource constraints D Page 13 of 26 Graphic labeled "Budget" with three items listed. Materials at 10 million dollars, Labor at 60 million dollars, and security at 25 million dollars.
15 Knowledge Review Match each PMB activity to the step where it belongs. Activity Place in the PMB Process Establish budgets Break down the work into individual control accounts Determine task durations for each work element Define a logical sequence of work flow Determine labor requirements (skill mix, experience levels) Establish inter-relationships among work elements That's correct. View the correct answers. Page 14 of 26 Activity Establish budgets Break down the work into individual control accounts Determine task durations for each work element Define a logical sequence of work flow Determine labor requirements (skill mix, experience levels) Establish inter-relationships among work elements Place in the PMB Process Step 3: Allocate resources Step 1: Define the work Step 2: Schedule the work Step 2: Schedule the work Step 3: Allocate resources Step 2: Schedule the work
16 PMB Example This table shows how work breakdown structure (WBS) work elements (tasks) are time-phased with their monthly resource requirements. The cumulative totals at the bottom of the table represent the planned value (PV) for that period. For example, the planned value for all tasks to be completed by June is $237K. This table is one view of a program's PMB. See a graphical view of a similar PMB on the next screen. Project X Task Jan Feb Mar Apr May Jun 1.0 $17 $25 $55 $58 $60 $ $10 $10 $5 1.2 $5 $8 $ $2 $5 $9 $10 $ $5 $10 $ $8 $8 $8 $8 1.6 $5 $5 $10 $10 $10 $5 1.7 $5 $5 $5 $4 1.8 $5 $5 $5 $5 Planned Value * Dollars in Thousands $17 $42 $97 $155 $155 $237 Page 15 of 26 Planned value (PV) refers to a time-phased budget plan for work that is currently scheduled. It includes the cost of previous work completed and can address a specific period of performance or a date in time.
17 PMB Graph This graphical representation of a PMB shows the contractor's plan for executing the program. Each point on the PMB curve represents a dollar value of work effort that is planned to be accomplished by a specific point in time. The contractor's progress will be compared against this baseline over time to determine whether the program will be completed on schedule and within budget. D Page 16 of 26 Graph representing a notional PMB. The vertical axis is dollars and the horizontal axis is time. A line curves upward gently from left to right, representing the PMB, over time. The far right horizontal line is labeled Completion Date. The PMB line meets, and stops at, the completion date line.
18 Attributes of a PMB The PMB represents all work to be performed under the contract; it includes every task and activity needed to achieve the scope of work. Likewise, it does not include any task or activity that is extraneous to the scope of work. A well-developed PMB: Is reasonably time-phased to achieve specific contract and program milestones. Is appropriately budgeted or resourced; the PMB represents the integration of the work scope with the schedule and the budget; for work to be accomplished as planned, the plan needs to consider the proper number of people and right mix of skills, talents, and experience needed to accomplish the work Represents the consolidated inputs from the entire team (building a PMB is a highly participative process) Reflects risk assessments; the schedule durations and the budgets should be adjusted for risk Most important of all, a good PMB is realistic and achievable, as well as comprehensive and measurable. Page 17 of 26 The relationship between the two components of risk probability and consequence/impact is inherent in a risk assessment. The risk owner or risk assignee determines the probability of the risk's occurrence and its impact on the program's objectives. As risk assessments are completed for individually identified risks, the risk owner or assignee updates the information captured during risk identification. The assessment phase concludes when the risk owner believes that the data described in this section is complete and accurate.
19 Knowledge Review At a conference you attended last week, the speaker mentioned that the performance measurement baseline (PMB) is the contractor's baseline plan of execution for the project. Later, you heard another presenter at the same conference say that the integrated master schedule (IMS) is the plan the PM uses to guide program execution. It sounds like the IMS and PMB are the same thing, but your supervisor assures you they are not. Which best describes the relationship between the PMB and the IMS? A. Your supervisor is mistaken, the PMB and the IMS are essentially the same thing; both represent the plan of execution B. The IMS focuses on the details of the schedule, whereas the PMB integrates the schedule and the resources into a time-phased budget plan. C. The IMS represents the planning process, while the PMB represents actual performance data. In other words, the IMS looks forward, and the PMB focuses on the past. Correct! The IMS and the PMB are related, but are not the same. They each provide a different view of the project plan. The IMS shows the planned duration for each task, as well as their interdependencies. This information provides input for creating the PMB, which allocates resources (budget) to the tasks in the IMS. Page 18 of 26
20 IBR Process: Integrated Baseline Review Joint preparation by the Government and the contractor is key to a successful IBR. Both the government and contractor PMs must work closely together to establish mutual expectations for conducting the IBR and expected outcomes. A primary goal of the IBR is the identification and quantification of risks that may impact project execution, and the supplier's plans for handling them. The Government PM is ultimately responsible for the timely and successful execution of the IBR. He or she will determine the composition and work assignments of the government IBR team. The Government PM will also plan for IBR training. Many PMs have found it beneficial to conduct joint training with the Government and contractor teams. This approach helps to establish common expectations and can be used as a working session to continue making risk assessments. D Page 19 of 26 Graphic depicting the IBR Process with the third step highlighted: Integrated Baseline Review. In the center of the graphic are the words "Program Managers' Mutual Understanding."
21 IBR Process: Integrated Baseline Review (continued) IBR Execution The execution of the IBR refers to the conduct of the actual IBR event: the review itself. The focus of the review is on gaining a mutual understanding of the detailed program plan and the risks associated with the plan. There are a few time-tested best practices for conducting an IBR: The IBR should include those closest to the work IBR sessions are generally small group discussions, not formal presentations The primary source documents for the review are schedules, work authorization documents, control account plans, resource plans, and budgets The IBR is intended to be cooperative and frank, not confrontational; participants will focus on understanding the scope of work, assumptions made to support the plan, and risks to successful completion The IBR review is conducted in a professional manner in a spirit of constructive assessment and discovery that increases the probability of success for the execution of the project Page 20 of 26
22 Management Processes Once the IBR is complete, the Government PM relies on contractor management processes to carry out the plan and provide data to demonstrate progress. The health of these management processes are critical to the ultimate success of the program. The Government PM will look at three areas of management processes for which the contractor PM is responsible: Baseline maintenance - maintaining the PMB as the plan for accomplishing the remaining work Risk management - documenting and classifying risks associated with the PMB Business - providing effective and integrated technical/schedule/cost planning, and establishing and maintaining valid, accurate, timely, actionable performance data Each of these processes supports the management of the program. Inappropriate or inadequate use of these processes may not only fail to identify risks that could lead to failure of the program, but may actually add risk to the program. Page 21 of 26
23 Knowledge Review The Transportation Security Agency (TSA) is getting ready for an integrated baseline review (IBR) for the contract to develop a faster and more accurate screening device for air cargo placed on passenger aircraft. Which of the following best describes the primary objective of the IBR? A. Break down the work into individual control accounts B. Identify resource constraints on the program C. Ensure the program schedule and budget are realistic and achievable D. Review the contract clauses relating to performance measurement Correct! One of the primary purposes of the IBR is to ensure that the schedule and budget are realistic and achievable by validating the performance measurement baseline (PMB). Page 22 of 26
24 Changes to the PMB: Rebaselining How do we know when to change, or update the PMB? There are no established criteria for this. However, the intent of the PMB is to represent a realistic, achievable, measurable, and mutually understood plan. If, at any time, the PMB is found not to meet these criteria, then a change to the PMB is in order. There are three reasons a PMB will need to be revised or re-baselined: Contract changes - When the Government initiates a change to the contract scope, budget or schedule, the PMB will have to change to reflect the current contract. Internal replanning - During the normal execution of the program, the contractor may find opportunities to accelerate work. They might also need to delay work for various reasons. This is a normal part of the contractor PM managing the approved work effort. If these changes do not impact the total cost at completion or final delivery date, then the contractor simply does internal replanning. These changes are within the budget and time available in the baseline. Formal reprogramming - When the work remaining cannot be reasonably accomplished within the schedule and/or budget remaining, formal reprogramming becomes necessary. The remaining work is rescheduled, and a revised budget at completion (BAC) is developed and approved by both the government and the contractor. A formal reprogramming action will normally trigger an IBR to ensure the new PMB is understood and accepted. Page 23 of 26 Budget at Completion (BAC) is the total budget from which individual period EV values are derived. It serves as a benchmark for computing overruns and under runs at the end of the contract.
25 PMB Rebaselining Here is a closer look at the reasons for rebaselining the PMB that are initiated by the contractor. Select each of the buttons below to read the reasons for rebaselining. Internal Replanning PMB needs adjustment in response to problems or opportunity Formal Reprogramming Remaining budget and/or schedule are unrealistic or no longer reflect the contract scope of work Page 24 of 26 Internal Replanning Remaining work re-planned within the remaining budget and schedule PMB curve changes shape, but the end point (the budget at completion) remains unchanged Formal Reprogramming Contractor requires more time and/or dollars to complete planned work PMB exceeds the contract target cost; budget is insufficient Original objectives cannot be met Contract modification changes to scope, budget and/or schedule
26 Knowledge Review The United States Visitor and Immigrant Status Indicator Technology (US VISIT) awarded a contract to develop a new biometric system to identify foreign visitors to the United States. The period of performance is 18 months. Four months into the contract, the contractor identified serious supplier difficulties that will delay delivery of key components by two months. Installation of these components is on the critical path to developing and testing the system. What type of change to the PMB is appropriate? A. Formal reprogramming B. Contract change C. Internal re-planning Correct! Formal reprogramming is required to adjust the PMB and its components since the contract delivery date cannot be met. Associated contracting discussions would also be required. Page 25 of 26
27 Summary A well-constructed performance measurement baseline (PMB) is an essential first step to effective earned value management (EVM). This time-phased budget plan is developed by the contractor to serve as the baseline against which performance will be measured. Constructed from individual control accounts, the PMB integrates technical performance with the integrated master schedule (IMS) and the allocated budget for the program. The integrated baseline review (IBR) is conducted jointly by the Government and the contractor to verify that the PMB covers the entire scope of work and is realistic, measurable, comprehensive, and achievable. It provides an opportunity for both parties to gain a mutual understanding of the contractor's plan of execution and the associated risks. The first IBR should be held within 90 days of contract award. Subsequent IBRs may be held when a major change in the program occurs. If the established PMB becomes unachievable, it may be necessary to re-baseline the PMB. For changes that do not impact the total cost at completion or final delivery date, the contractor will simply do some internal replanning. For changes that impact the program budget or delivery date, formal reprogramming is needed, and an IBR must be held to verify the revised PMB. You may print the Integrated Baseline Review lesson or save it for future reference. Page 26 of 26
28
PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationDEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers
1 Recognize key concepts about Earned Value as an integrated program management tool that integrates cost, schedule, and technical performance Recognize that Earned Value is a management tool that program
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More informationIntegrated Baseline Review
Integrated Baseline Review How To Achieve Project Success by Establishing a Realistic Baseline and Involving your Customer Eleanor Haupt Earned Value Associates LLC ehaupt@earnedvalue.biz 937-572-2586
More informationEarned Value Management Tutorial Module 4: Budgeting. Prepared by:
Earned Value Management Tutorial Module 4: Budgeting Prepared by: Module 4: Budgeting Welcome to Module 4. The objective of this module is to introduce you to Budgeting Concepts and Definitions. The Topics
More informationThe First Steps in Implementing a Simplified Earned Value Management System
2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface
More informationEarned Value Management. Danielle Kellogg. Hodges University
Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level
More informationManagement Reserve Defined
Management Reserve Defined Management Reserve (MR) is defined in EIA 748 Earned Value Management Systems, the commercial standard for EVMS, as An amount of the total budget withheld for management control
More informationRoberta Tomasini Defense Acquisition University DSN
$ ACWP C Program at a Glance BCWS C Total Allocated Budget Management Reserve Raleigh Distribution PMB BCWP C Over Budget P R O J E C T E D S L I P P A G E EAC Earned Value and the Acquisition Program
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs Budget Earned Value Management (EVM) EVM projections 2 IT projects have a poor track record for meeting budget goals
More informationLong Description. Figure 15-1: Contract Status. Page 1 of 7
Page 1 of 7 Figure 15-1: Contract Status A single performance report provides the status of the Program at a point in time. When combined with previous reports, a much more revealing picture of the Program
More informationEarned Value Management Training Program
Earned Value Management Training Program Course Brochure and Competency Matrix INDEX: 1. Company Introduction 2. Training Programme Description 3. Training Delivery Options 4. Course Syllabus 5. Programme
More informationDownloaded from
Over Target Baseline and Over Target Schedule Handbook May 7, 2003 1 Authors Ivan Bembers, NIMA Melissa Boord Traci Ann Byrnes, Department of Defense, Australia Tony Finefield, Finefield Consulting Will
More informationSMC/PMAG Control Account Manager (CAM) Notebook Evaluation
Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com 2010 ISPA/SCEA International Conference SMC/PMAG Control Account Manager (CAM) Notebook Evaluation Ms
More informationAppendix B: Glossary of Project Management Terms
Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances
More informationPerformance Based Management at Raytheon Aircraft Company. Joe Kusick Raytheon Aircraft Company EVMS Manager May 18, 1998
Performance Based Management at Raytheon Aircraft Company Joe Kusick Raytheon Aircraft Company EVMS Manager May 18, 1998 Raytheon Aircraft Policy for Performance Based Management EVMS is a Tool for Performance
More informationCase Study. IR-SIP Risk Management Plan Outline
Case Study IR-SIP Risk Management Plan Outline Baselined: Last Modified: Owner: Purpose: Section 1. Introduction 1.1 Purpose and Scope 1.2 Assumptions, Constraints, and Policies 1.3 Related Documents and
More informationEarned Value Management System
DEPARTMENT OF VETERANS AFFAIRS Office of Information and Technology Earned Value Management System Description Document VA-DI-MGMT-81466A RECORD OF CHANGES Change Number Date Reference (Page, Section,
More informationGuide to Earned Value Management (EVM) Scalability for Non-Major Acquisition Implementations
Guide to Earned Value Management (EVM) for Non-Major Acquisition Implementations Prepared by the Civilian Agencies and Industry Working Group (CAIWG) March 2015 CAIWG Guide to EVM Table of Contents Introduction...
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationChapter 7 Earned Value Management
Chapter 7 Earned Value Management Table of Contents 7.1 Introduction 7-4 7.2 Policy and Directives 7-4 7.3 Roles and Responsibilities 7-5 7.3.1 DoD Executive Agent 7-5 EVM Center 7-5 7.3.2 Component EVMS
More informationAgile Methods with. Performance-Based Earned Value
Agile Methods with Performance-Based Earned Value CMMI Technology Conference Abstract 7110 November 20, 2008 Paul Solomon, PMP Performance-Based Earned Value www.pb-ev.com 1 Agenda Customer expects valid
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationHow to Estimate and Use Management Reserve in an EVM System
How to Estimate and Use Management Reserve in an EVM System Earned Value Management Systems Best Practices Presented by Mark Infanti Vice President of Program Planning & Control Solutions This presentation
More informationHumphreys &Associates, Inc.
Humphreys &Associates, Inc. 3111 N. Tustin Street, Suite 250 Orange, CA 92865 (714) 685-1730 (Phone) (714) 685-1734 (Fax) Email: humphreys@humphreys-assoc.com http://www.humphreys-assoc.com No portion
More information4. Outline of EIA for Development Assistance
4. Outline of EIA for Development Assistance 4.1 EIA and Development EIA has an important role to play resolving these environmental problems through its ability to contribute to environmentally sound
More informationGOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION
GEIA STANDARD ANSI/EIA-748-B-2007 Approved: September 10, 2007 EIA-748-B Earned Value Management Systems EIA-748-B JUNE 2007 GOVERNMENT ELECTRONICS AND INFORMATION TECHNOLOGY ASSOCIATION A Sector of the
More informationDownloaded from UNITED STATES DEPARTMENT OF ENERGY EARNED VALUE MANAGEMENT APPLICATION GUIDE
UNITED STATES DEPARTMENT OF ENERGY EARNED VALUE MANAGEMENT APPLICATION GUIDE VERSION 1.6 JANUARY 1, 2005 FORWARD Standards seldom can stand alone and always require interpretation and discussion. ANSI/EIA
More informationFrom the Federal Register Online via the Government Printing Office [
Federal Register, Volume 70 Issue 67 (Friday, April 8, 2005) [Federal Register Volume 70, Number 67 (Friday, April 8, 2005)] [Proposed Rules] [Pages 17945-17949] From the Federal Register Online via the
More informationEarned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;
Dollars $M Earned Value Project Management Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/284-0634; allewis@sandia.gov 95 th ISM Annual International Supply Management Conference,
More informationContract Performance Report
Contract Performance Report Description This report consists of five formats containing cost and related data for measuring contractors' cost and schedule performance on Department of Defense (DOD) acquisition
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationEarning Value From Risk
Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned
More informationProject Management Fundamentals
Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)
More information... I Poge1of4 I... Back Next
EVMlOl Fundam entals of Earned Value Managem ent lesson 6.0 - Module I ntr oduction RESOURCES I PRINT I HELP Module 6 W elcome - Baseline Maintenance Program Manager... I Poge1of4 I... EVMlOl Fundamentals
More informationDATA ITEM DESCRIPTION. Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date:
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861A Approval Date: 20150916 AMSC Number: D9583 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
More informationProject Planning. Planning is an important step in project execution. Planning means:
Project Planning Planning is an important step in project execution. Planning means: Thinking through future project actions Seeking and mentally inspecting the long path from the start to the finish Achieving
More informationEVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes
EVMS Fundamentals v.7.0 (Part 2 of 2) Slides and Notes Course Outline Incorporating Actual Costs 07A. Types of Actual Cost 07B. Direct and Indirect Costs 07C. Applying Indirect Costs Earned Value Basics
More informationProject Performance Evaluation By Earned Value Method
Project Performance Evaluation By Earned Value Method Antony Prasanth M A #, K Thirumalai Raja * # Department of Civil Engineering, EBETi Kangayam, Thirupur Dist, Thamilnadu, Anna University Chennai *
More informationEFCOG Best Practice #174
EFCOG Best Practice #174 Best Practice Title: CPR/DID Monthly Validation Facility: Washington River Protection Solutions, Hanford Site, Richland Washington Point of Contact: Craig Hewitt, WRPS Hanford,
More informationResearch Methods Outline
: Project Management James Gain jgain@cs.uct.ac.za Outline Introduction [] Project Management [] Experimental Computer Science [] Role of Mathematics [1] Designing User Experiments [] Qualitative Research
More informationA Project Management Guide for Researchers
A Project Management Guide for Researchers Prepared by: Research Grant and Contract Services January 2018 Copyright 2018 Memorial University of Newfoundland Table of Contents 1.0 Introduction... 4 2.0
More informationHow to Satisfy GAO Schedule Best Practices
By Dr. Mohamed Hegab, PE, PMP Executive Vice President November 2010 EyeDeal Tech 3943 Irvine Blvd, #127 Irvine, Ca 92602 www.schedulecracker.com Copyright 2010EyeDeal Tech. All rights reserved. This document
More informationEARNED VALUE AS A RISK ASSESSMENT TOOL
EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at
More informationCONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationTHE VALUE OF EARNED VALUE MANAGEMENT
THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs
More informationA Study on Risk Analysis in Construction Project
A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------
More informationEarned Value Management Handbook. arne. alu
Earned Value Management Handbook arne alu March 2013 Table of contents Contents 1 Introduction 7 2 Overview 8 3 Definition 39 4 Planning 57 5 Data collection 77 6 Analysis, review and action 80 7 Change
More informationEARNED VALUE MANAGEMENT SYSTEM (EVMS)
NOT MEASUREMENT SENSITIVE DOE G 413.3-10A EARNED VALUE MANAGEMENT SYSTEM (EVMS) [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents and
More informationEarned Schedule Analysis
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Analysis A Better Set of Schedule Metrics Eleanor Haupt President PMI College of Performance Management Walt Lipke Member PMI
More informationRETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1
RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationAnalysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh
Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS
More informationEarned Value Management An Overview March 2014
Earned Value Management An Overview March 2014 SAVE International Cascadia Chapter Introduction What is Earned Value? Why is Earned Value important? What is required? Earned Value Definitions & Process
More informationRisk Management Plan for the Ocean Observatories Initiative
Risk Management Plan for the Ocean Observatories Initiative Version 1.0 Issued by the ORION Program Office July 2006 Joint Oceanographic Institutions, Inc. 1201 New York Ave NW, Suite 400, Washington,
More informationEarned Value Management
Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationEarned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327
Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING
More informationEarned Schedule in Action
Earned Schedule in Action Earned Value Analysis - 11 Conference London, United Kingdom 12-17 June 2006 Kym Henderson Education Director PMI Sydney Australia Chapter Kym.Henderson@froggy.com.au EVM Schedule
More informationDATA ITEM DESCRIPTION
DATA ITEM DESCRIPTION Form Approved OMB NO. 0704-0188 Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions,
More informationpm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationSheila Belayutham CHAPTER 6 CONTROL
CHAPTER 6 CONTROL LEARNING OUTCOME Students will be able to: Understand monitoring and control in construction. Understand the monitoring and control methods in construction. MONITORING & CONTROL It s
More informationRISK MANAGEMENT GUIDE FOR DOD ACQUISITION
RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Table of Contents. Key Activity - Risk Analysis... 11.1. Purpose... 11.2. Risk Reporting Matrix...
More informationSAMPLE. AACE International Recommended Practice No. 80R-13
E 80R13 SA M PL ESTI MATEATCOMPLETI ON( EAC) AACE International Recommended Practice No. 80R-13 ESTIMATE AT COMPLETION (EAC) TCM Framework: 7.6 Risk Management 9.1 Project Cost Accounting 9.2 Progress
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT Planning DETERMINE BUDGET PROCESSES BY PROCESS GROUP Monitoring and Controlling 7.1 Plan Costs Management 7.4 Control Costs 7.2 Estimate Costs 7.3 Determine Budget DETERMINE BUDGET
More informationProcurement Class Deviation
Page 1 of 7 National Aeronautics and Space Administration Washington, DC 20546 Procurement Class Deviation PCD 15-05 November 10, 2015 Class Deviation to NFS 1834.2, 1834.203-70, 1852.234-1 and 1852.234-2
More informationJefferson Science Associates, LLC Earned Value Management System 2013 Surveillance Plan
Jefferson Science Associates, LLC Earned Value Management System 2013 Surveillance Plan 4-5 December, 2013 V1 Earned Value Management System Surveillance Plan The Department of Energy (DOE) certified the
More informationEarned Value Management (EVM) and the Acquisition Program
American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.
More informationA Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs
Calhoun: The NPS Institutional Archive Theses and Dissertations Thesis Collection 2012-09 A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense
More informationPM TUTORIAL. Notes On Project Requirements
PM TUTORIAL Notes On Project Requirements Requirements are the first and most important thing to define on any project, spend real time making sure your requirements are adequate before any significant
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from https://mosaicprojects.com.au/pmki-sch.php
More informationPresenting Earned Value
Successfully Presenting Your guide to Management What is Management? Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question, What
More informationIntegrated Baseline Review (IBR) Handbook
NASA/SP-2010-3406 Integrated Baseline Review (IBR) Handbook National Aeronautics and Space Administration NASA Headquarters Washington, D.C. 20546 February 2013 NASA STI Program in Profile Since its founding,
More informationEVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS
EVMI - BUILDING & EDUCATING PROJECT STAFF MEMBERS WHO EXECUTE AND DELIVER PROJECTS & PROGRAMS SUCCESSFULLY ACROSS ALL INDUSTRIES EVMi 101: EARNED VALUE MANAGEMENT FUNDAMENTALS COURSE HIGHLIGHTS EVMI 101:
More informationProfessional Development Seminar Series
Professional Development Seminar Series Feb, 2019 2019. All rights reserved. online@3foldtraining.com. www.pmexamstudy.com. www.3foldtraining.com. PMP Exam Review Agenda Introduction to Definition Context
More informationThe Project Times and Costs
The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step
More information[Project Name] Project Schedule Management Plan. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP
[Company] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] May 16, 2015 [Ref. number] Marc Arnecke, PMP [Project Name] [Sub-Project, phase, etc.] The project schedule management
More informationBasel Committee on Banking Supervision. Consultative Document. Pillar 2 (Supervisory Review Process)
Basel Committee on Banking Supervision Consultative Document Pillar 2 (Supervisory Review Process) Supporting Document to the New Basel Capital Accord Issued for comment by 31 May 2001 January 2001 Table
More informationVendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo
Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated
More informationAdministration. Course Aim. Introductions
Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More information1 of 14 4/27/2009 7:45 AM
1 of 14 4/27/2009 7:45 AM Chapter 7 - Network Models in Project Management INTRODUCTION Most realistic projects that organizations like Microsoft, General Motors, or the U.S. Defense Department undertake
More informationProject Connect. June 22, 2011
Project Connect June 22, 2011 Introduction Meeting Minutes Approval Project Status Report IV&V Update By Ernst & Young Other Business Public Comments Review of Actions from Meeting Schedule Next Meeting
More informationFinancial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany
1 Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT Dr. Ahmed Elyamany 2 Course Content Project financial management: Cash flow prediction, Cash flow analysis, Cost of finance
More informationSECTION ARCHITECTURAL AND ENGINEERING CPM SCHEDULES
SECTION 01 32 16.01 ARCHITECTURAL AND ENGINEERING CPM SCHEDULES PART 1- GENERAL 1.1 DESCRIPTION: The Architect/Engineer of Record (A/E) shall develop a Critical Path Method (CPM Schedule) plan and schedule
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationOutline. Project Management. Introduction. What is a Project?
Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction
More informationGate Value Method Overview document
Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person
More informationProject Assessment Exercise
Project Assessment Exercise www.spmbook.com We have been assigned the task of assessing the project status of a project, whose Gantt chart is presented in Illustration 1, where: 1. we are currently at
More informationThe Living Estimate. Leveraging LCCEs Throughout the Program Lifecycle
The Living Estimate Leveraging LCCEs Throughout the Program Lifecycle Sriram Krishnan Lead Consultant skrishnan@cobec.com Kevin Schutt Director of Finance kschutt@cobec.com Click to edit Introduction Master
More informationMnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Project Reporting Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationUnderstanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc.
Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc. 1 Abstract The recent rise of integrated risk analyses methods has created
More informationThe [Whole] Truth about ANSI Compliant EVMS
The [Whole] Truth about ANSI Compliant EVMS ICEAA Workshop June 2013 1 Introduction 2 EVMS that complies with ANSI/EIA 748(B) Standard often characterized as good project management Basic concepts/principles
More informationUnit 5 Slide Lectures of 04/05/06 April 2017
PROJECT AND COMMUNICATION MANAGEMENT Academic Year 2016/2017 PROJECT SCHEDULING, PROJECT DURATION AND PROJECT COMMUNICATION PLAN (CH. 8-9) Unit 5 Slide 5.2.1 Lectures of 04/05/06 April 2017 Overview of
More informationCritical Path and Earned Value Management
Critical Path and Earned Value Management Two elegantly simple metrics, both rich with meaning, have been part of project management since the very beginning of the profession: 1. Critical Path Method
More informationComprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data
Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data William Laing Technomics, Inc. wlaing@technomics.net 2011 ISPA/SCEA Joint Annual Conference & Training Workshop
More informationGPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties
More informationPlanning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique
Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique Suvarna P 1 Research Scholar, School of Civil Engineering, REVA University, Bengaluru,
More informationVIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS
S108D00-0911 VIRGINIA DEPARTMENT OF TRANSPORATION SPECIAL PROVISION FOR CPM PROGRESS SCHEDULE FOR CATEGORY IV PROJECTS March 1, 2011 Section 103.06(e) Progress Schedule of the Specifications is deleted
More information