DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE

Size: px
Start display at page:

Download "DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE"

Transcription

1 DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE Andrew Burr MA(Cantab), ACIArb, FFAVE(Master) ArbDB Chambers Silver Shemmings LLP London

2 1. Delay and disruption: some attempted definitions Comparative terms Completion dates No intrinsic qualities Causes and effects of each other 2

3 2. Introduction Walter Lilly and Company Limited v Mackay, [2012] EWHC 1773 (TCC), per Akenhead J Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TRC), per Ramsey J 3

4 3. Apportionment concurrency and progress against the contract programme 3.1 The English and Welsh way: Walter Lilly and Company Limited v MacKay [2012] EWHC 1773 (TCC) JCT standard form of BC 1998 edition: almost 30 months delay; 234 EoTs requested with 196 EoTs going unanswered; evaluation in judgment depended upon Lilly s design responsibilities and of the defects Who has the responsibility to pay up? Defects claim almost totally unsuccessful Further payment of 2.3 million (plus costs) and EoTs awarded to the date of practical completion (PC) Unclear contractual allocation of design responsibility 4

5 Apportionment, concurrency and progress against the contract programme EoT: 1. Look at what the contract stipulates 2. Look at relevant evidence; actual facts and expert advice (minus any theoretical possibilities) 3. If delay results from two or more effective causes, one entitling the contractor to an EoT as a relevant event, EoT should be granted (an all or nothing approach) 4. The central question = CAUSATION 5

6 Apportionment, concurrency and progress against the contract programme Based upon: Principle that these are relevant events that would otherwise amount to an act of prevention; unfair not to award an EoT in such circumstances The straight contractual approach ; clause 25 of JCT stated nothing about apportionment if the contractor is partially responsible for delay 6

7 Apportionment, concurrency and progress against the contract programme How to assess causation in relation to delay? 1. Criticality 1. Generally, not the last item of work but what delays this 2. Snagging? Only if excessive 2. Prospective and retrospective analysis 1. Should come to the same conclusions 2. Prospective: requires a critical path programme (CPP) (absent in this case from 2007) 3. Cross-checking (in absence of a CPP): 1. Month-month review of probable delays 2. Cross check with facts (factual analysis) 7

8 Apportionment, concurrency and progress against the contract programme 3.2 The Scottish way: City Inn v Shepherd [2010] CSIH 68 Amended JCT 80 contract (construction of a hotel in Bristol) employer, (City Inn) dismissed design team and contractor, Shepherd claimed 11 week EoT to the completion date. Is there an entitlement to EoT, if the architect's instructions which caused delays were concurrent with delays arising from matters which were the contractor' s responsibility? 8

9 Apportionment, concurrency and progress against the contract programme Elements of relevance for the decision: Principles of calculation of EoTs Critical path analysis Causation in law when there are concurrent events 9

10 Apportionment, concurrency and progress against the contract programme Lord Drummond Young: Thorough examination of the construction process supported by expert witnesses Mere critical path analysis approach not possible in the case at hand (eg because of lack of full electronic records from the contractor) Where there is a true concurrency between a relevant event and a contractor default, in the sense that both existed simultaneously, regardless of which started first, it may be appropriate to apportion responsibility for the delay between the two causes. 10

11 Apportionment, concurrency and progress against the contract programme Inner House of the Court of Session, Scotland (majority) held Where two concurrent causes are operative, one being a relevant event and the other being an event for which the contractor is responsible, the certifier should approach the matter in a fair and reasonable manner and apportion the delay between the causes unless one is dominant. 11

12 Apportionment, concurrency and progress against the contract programme Five Hudson principles for the evaluation of a delay claim 1. Is there a relevant event which is likely to cause / has caused delay as a result of which completion of the work is likely to be / has been delayed? 2. Application of common sense 3. Discretion of the decision maker as to the choice and use of evidence 4. Is the cause dominant? 5. In case of concurrent events, neither of which is dominant Discretion of the decision maker to apportion the delay by applying the principles of fairness and reasonableness 12

13 4. Assessment of causation Mirant City Inn Allocation of responsibility by expert witnesses of opinion DDCCS 13

14 5. Time at large and the prevention principle Multiplex v Honeywell [2007] EWHC 447 (TCC) Honeywell = sub-contractor, responsible for the security and communication installations at Wembley Multiplex = main contractor Did Multiplex mismanage the project? Did this mismanagement release Honeywell from its obligations to complete the project within the period foreseen in the sub-contract? 14

15 Time at large and the prevention principle Honeywell s line of argument: Prevention principle Failure by Multiplex to provide adequate programming data deprived Honeywell of the possibility to give proper notices or particulars of delay ( condition of the right to an EoT) Gaymark Investments v Walter Construction (no liquidated damages for delay, even though no EoT could be given) 15

16 Time at large and the prevention principle Jackson J (as he then was): Prevention principle not applicable, since the contract allowed Multiplex to grant EoTs for acts of prevention Sub-contractor is only expected to give notices when practicable and if there is requisite knowledge Contractual terms requiring the contractor to give prompt notice of delay should be preserved, regardless of the other party complicating matters 16

17 6. Notice as a condition precedent Education 4 Ayrshire v South Ayrshire Council [2009] CSOH 146 Contractor had to work towards certain phases of the project to achieve target service availability dates (TSAD) Contractor had to give notice if it could not achieve a TSAD within 20 business days of the delay event Contractor served a TSAD notice of delay due to asbestos (containing a claim for EoT and damages) Contract provided for an obligation of the contractor to comply with a 20 day deadline for notice of works compensation event (WCE) such notice was not served 17

18 Notice as a condition precedent Cautionary tale for contractors entering into contracts requiring a strict formal process in order to obtain time and money Determination of the meaning and effect of a condition precedent clause by a Scottish Court (= clause regularly used in FIDIC and NEC contracts to prevent contractors claiming an EoT, or additional payment unless they provide written notice of the delay event, within a prescribed time limit): 18

19 Notice as a condition precedent Decision: Strict and clear contractual requirements for relief (including WCE notice) Non compliance with these requirements leads to loss of right to extra time and payment Decision is in line with previous cases (eg Steria Limited v Sigma Wireless Communications Limited): no interference by the courts in cases of clear and unambiguous contractual requirements 19

20 7. The valuation of damages for prolongation Costain v Haswell [2010] TCLR 1 Claim for damages for breach of contract /negligence Is a recovery of prolongation costs for the period during which it was alleged that the project encountered delays from the abandonment of the surcharged scheme and the later design and construction of piled foundations possible? What is the critical delay to the completion of a project in the case of a negligent foundation design? 20

21 The valuation of damages for prolongation Experts from both parties agreed on delays to foundations causing critical delays due to one of the affected structures being on the critical path at the time Unanimity between experts as to a common methodology to assess delay (using time impact analysis), the baseline programme as well as as-built data Differences between the experts on how the agreed methodology should apply 21

22 The valuation of damages for prolongation Deputy High Court Judge Richard Fernyhough QC in the TCC: Design had failed to produce the intended result Negligence Criticism of both experts: - Failure to undertake an analysis of a specific period - Failure to consider what effect the foundation delays actually had on follow-on activities and other structures - Failure to investigate whether Costain could have mitigated or negated the initial delays by later events. 22

23 The valuation of damages for prolongation Held: Recovery of prolongation costs for the whole project requires the demonstration that the delay relied upon in fact led to an overall delay to the completion of the project as a whole, not due to other reasons Since there were other delays caused by United Utilities as well as Costain, there was no justification for Costain recovering all its costs in maintaining the site The extent of critical delay can only be determined retrospectively once the works are completed 23

24 The valuation of damages for prolongation Clause 26 JCT: Walter Lilly and Co Limited v Mackay [2012] EWHC 1773 (TCC) Contractor informs architect of losses/expenses incurred or likely to be incurred which, under the contract terms, will not be reimbursed which, will materially affect the progress of Works Architect agrees that works will be materially affected Architect shall instruct a quantity surveyor to quantify the loss/expense AS LONG AS... 24

25 The valuation of damages for prolongation Conditions: Provisions of ff. of the JCT contract are followed Timely application Provision of factual supporting details and evidence -> But what does this entail? Common sense fact-fact approach Consider knowledge available to Architect and their involvement in the project Put architect in reasonable position This can be retrospective, or prospective 25

26 The valuation of damages for prolongation Global and/or total loss claims: These are not terms of art or statutorily defined terms...what is commonly referred to as a global claim is a contractor s claim which identifies numerous potential or actual causes of delay and/or disruption, a total cost on the job, a net payment from the employer and a claim for the balance between costs and payment which is attributed without more and by inference to the causes of delay and disruption relied upon Akenhead J 26

27 The valuation of damages for prolongation Principles: Contractor must prove delays occurred and caused it to incur loss on the balance of probabilities No need to show that it is impossible to prove cause and effect in the normal way Any condition precedent clauses re notification are complied with No established method of proof for such claims Evidentiary difficulties: Contractor must show that loss has been incurred would not have been incurred in any event They had a sufficiently well-priced tender which would have made a net return 27

28 The valuation of damages for prolongation Not all, or nothing: If the claim includes an event, not caused by the employer, this does not wipe out the claim It all depends upon the impact of such events A deduction can be made from the global claim total for such individual events (ie in a claim for 1M with an underpriced 50K item, that 50K item is deducted) However: No need for such a claim, if it is possible to find the actual cost attributable to individual events Possible, even if contractor is responsible for the inability to disentangle individual events 28

29 The valuation of damages for prolongation The facts: Contract was a complete mess on the administrative side Insufficient design from the outset and no sufficient allocation of this responsibility to WLC Multiple variations Hopelessly late provision of instructions and information Lack of unity and certainty between owner and designers Allowed for certain losses/expenses to be claimed as a global claim 29

30 The valuation of damages for prolongation Head office overheads and profit: 1. Contractor can recover the above as a result of ownercaused delay 2. Contractor must prove, on balance of probabilities, that if there had not been delay, it would have won tenders for other projects which would produce a profitable return or contributed to head office overheads 3. Emden/Hudson formula are useful methodologies for calculating number 2 above 4. There need be certainty that the loss or expense has been incurred because of a clause 26 delay. 30

31 8. Global and/or total costs claims Impossibility of proving cause and effect Lilly 31

32 9. Head office overheads and profit Proof that the contractor would otherwise have successfully won other contracts Clause 26 relevant event 32

33 10. Material breach: programming Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC) Material breach for the purpose of termination: failure to provide a rev 4 programme? Hudson on Building and Engineering Contracts (8-056 to 8-058): Facts of the case Consequences of termination Importance attached to the type of breach Actual circumstance of the breach Commercial consequences of the breach Here: time of completion = important aspect of the project 33

34 Material breach: programming Contractor s inability to provide a rev 4 programme Five principles derived from Hudson 34

35 11. Obligation to proceed regularly and diligently Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC) West Faulkner Associates v London Borough of Newham [1992] 71 BLR 1 Contractor obliged to do both Regularly: With sufficient way of men, materials and plant to have physical capacity to progress works substantially in accordance with contractual obligations Diligently: Physical capacity must be applied industriously an efficiently with successful progress towards contractual obligations 35

36 Obligation to proceed regularly and diligently West Faulkner Associates definitions Vivergo v Redhall 36

37 Obligation to proceed regularly and diligently Facts: Vivergo claims Redhall breached this obligation by: Inadequate resourcing of critical path works to DET Lack of productivity Lack of programming Poor labour management and supervision Poor material controls and site management Ruled: in breach of productivity and programming obligations because of a lack of a proper programme. This gave rise to a notice under 43.2(b) of the Contract. 37

38 12. Notices Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC) Unilateral notices: Construe against the relevant objective contextual scene Meaning as understood by the reasonable recipient Purpose of notice is relevant to its construction Sufficiently clear and unambiguous In addition, default and termination notices: Must be reasonably connected in content and time Notify the default Indicate seriousness, or link to clause

39 Notices Facts: No explicit clause 43.2 reference > valid in the background context, or improperly construed? Not specific and unambiguous enough in the three notices The reasonable recipient of the letter would...not know that it had to take steps to remedy a default within 14 days to avoid termination Fourth notice: contained a sufficient link to a clause 43.2 notice BUT only with regard to one aspect of the claim Not consider that it can be construed as giving clear and unambiguous notice that Redhall had to take other steps 39

40 13. Opinion evidence Walter Lilly v DMW [2012] EWHC 1773 (TCC) Expert witnesses Persons of this description though in English law confounded with witnesses and not without advantage treated as such, are in fact a sort of assistant to the Judge and treated as such by Roman law. The expert witness is in quite a special position. He is an assistant in the determination of truth. He is a purveyor of information on which decisions are arrived at, and to the truth and validity on that information his professional credit and reputation are pledged Attributed to Jeremy Bentham 40

41 Opinion evidence Vivergo Fuels Limited v Redhall Engineering Solutions Limited [2013] EWHC 4030 (TCC) How an expert s approach can help assess delay and disruption, which leads to breach? Use common programme and factual information Aware of each other s approach Problems: Lack of coherent reasoning and analysis 41

42 Thank you for your attention! 42

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb.

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb. NEC3 A Practical Guide to Compensation Events Chris Holden LLB FRICS FBEng MCIArb www.kerrigans.net Introduction The intention of this presentation is to provide a practical approach to dealing with compensation

More information

GLOBAL CLAIMS. BuildLaw - Issue No 16 December Jeremy Glover JEREMY GLOVER

GLOBAL CLAIMS. BuildLaw - Issue No 16 December Jeremy Glover JEREMY GLOVER BuildLaw - Issue No 16 December 2012 1 GLOBAL CLAIMS - Jeremy Glover Global claims were defined by Byrne J in the Australian case John Holland Construction v Kvaerner RJ Brown as being a claim where: the

More information

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract London Bristol Dublin Dubai Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract Tom Pemberton, Partner James Vernon, Associate 12 April 2016 Introductions Tom Pemberton

More information

Delay Expert practical tips for making delay claims

Delay Expert practical tips for making delay claims Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of

More information

Hong Kong Institute of Surveyors "EOT and Liquidated Damages"

Hong Kong Institute of Surveyors EOT and Liquidated Damages Hong Kong Institute of Surveyors "EOT and Liquidated Damages" 18 February 2014 Damon So, Partner Projects (Engineering & Construction) Practice Extension of Time Time Obligations 1. No express agreement

More information

Practical Issues arising from Valuation of Claims

Practical Issues arising from Valuation of Claims Practical Issues arising from Valuation of Claims Presented by KK Cheung and Joseph Chung, Partners of Deacons and Allen Lai, Senior Consultant of Charlton Martin Consultants Limited Presentation on 16

More information

Lilly and Doyle: A Common Sense Approach to Global Claims. Anneliese Day QC and Jonathan Cope

Lilly and Doyle: A Common Sense Approach to Global Claims. Anneliese Day QC and Jonathan Cope Lilly and Doyle: A Common Sense Approach to Global Claims Anneliese Day QC and Jonathan Cope Introduction 1. Like all good detective pairings, the judiciary in England and Scotland have not always adopted

More information

NEC4: BREACHES BY THE EMPLOYER AND A DEPARTURE FROM THIS PRINCIPLE OF FAIRNESS

NEC4: BREACHES BY THE EMPLOYER AND A DEPARTURE FROM THIS PRINCIPLE OF FAIRNESS NEC4: BREACHES BY THE EMPLOYER AND A DEPARTURE FROM THIS PRINCIPLE OF FAIRNESS Author: Trenelle Moodley The NEC4, like its predecessors, has been drafted with the objective of 1) facilitating better and

More information

Early Completion and its Effect on the Contractor

Early Completion and its Effect on the Contractor Early Completion and its Effect on the Contractor By Andrew Stephenson 1 Introduction This article addresses two questions related to early completion. 1 The first is whether the contractor is entitled

More information

International Construction Projects Committee

International Construction Projects Committee International Construction Projects Committee Time Related Obligations in Key Jurisdictions: An Update 21 September 2016 Richard Bailey Goodman Derrick LLP London, England Polina Chtchelok ESPCs Multidisciplinary

More information

Omar is recommended as a leading junior in the most recent editions of Chambers and Partners and Legal 500.

Omar is recommended as a leading junior in the most recent editions of Chambers and Partners and Legal 500. ENERGY AND NATURAL RESOURCES PROFESSIONAL NEGLIGENCE PFI DISPUTES CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE GENERAL COMMERCIAL Omar Eljadi Call Date: 2009 // oeljadi@atkinchambers.com PRACTICE Omar

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

Concurrently delayed?

Concurrently delayed? Concurrently delayed? Is an employer or contractor entitled to an extension of time and/or claim for damages in a situation where there are two or more events that have caused a delay, and where the delays

More information

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES

Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation

More information

Early completion and its effect on the contractor s right to an extension of time

Early completion and its effect on the contractor s right to an extension of time Bourke Place 600 Bourke Street Melbourne VIC 3000 GPO Box 9925 Melbourne VIC 3001 Tel +61 3 9672 3000 Fax +61 3 9672 3010 www.corrs.com.au Sydney Melbourne Brisbane Perth Early completion and its effect

More information

Extension of Time (EOT) principles

Extension of Time (EOT) principles Anand ANTHONY 安杰褔 [M: 9693 0407] CHARTERED BUILDING ENGINEER (UK), Adjudicator (Malaysia), Mediator (UK) EXPERT in FORENSIC PLANNING (Delay/Disruption/Production/Acceleration)

More information

Experiences of FPSO Construction/Conversion Disputes: Learning the Lessons to Protect Budgets

Experiences of FPSO Construction/Conversion Disputes: Learning the Lessons to Protect Budgets Experiences of FPSO Construction/Conversion Disputes: Learning the Lessons to Protect Budgets 19 February 2019 K&L Gates, Jeremy Farr, Partner Copyright 2018 by K&L Gates LLP. All rights reserved. Petrojarl

More information

TIME IS MONEY OR IS IT? (PART 2)

TIME IS MONEY OR IS IT? (PART 2) TIME IS MONEY OR IS IT? (PART 2) In Part 1 of this article we reviewed the legal and contractual principles which apply to the time for completion of construction works and the remedies available to both

More information

Reference to Clause 9 or to the Tests on Completion is found in the following clauses:-

Reference to Clause 9 or to the Tests on Completion is found in the following clauses:- Clause 9 Summary Clause 9 deals with the Tests on Completion. Sub-Clause 9.1 requires the Contractor to give notice when it is ready to carry out the Tests on Completion. Tests on Completion are a defined

More information

Delays & EOT. Most Common Dispute Most Complex Dispute Most Uncertain Dispute

Delays & EOT. Most Common Dispute Most Complex Dispute Most Uncertain Dispute Delays & EOT Most Common Dispute Most Complex Dispute Most Uncertain Dispute Construction & Time It has been said that the only major construction project to finish on time and to budget was a church where,

More information

SCSI Western Region CPD

SCSI Western Region CPD SCSI Western Region CPD Unlimited liability in GCCC Conditions of Engagement, 8 November 2016 - Finola McCarthy, Partner C O R K D U B L I N G A L W A Y L O N D O N W W W. R D J. I E 1 SCOPE OF LIABILITY

More information

University of Vienna. Variation and Design

University of Vienna. Variation and Design University of Vienna Variation and Design Thursday 28 June 2012 Nicholas Gould Partner, Fenwick Elliott LLP Senior Visiting Lecturer, King's College London 1 Payment under the Contract 1.1 The way in which

More information

Introduction. Construction Contracts. Unit 4: Principle of Contract Administration under JCT 5 SBC/Q 1/15/2016

Introduction. Construction Contracts. Unit 4: Principle of Contract Administration under JCT 5 SBC/Q 1/15/2016 Introduction R. Sarvananthan ( Sarva) B.Eng, MSc CPM, MIES, MASCE 1 Construction Contracts Unit 1: Introduction to Construction Contracts Unit 2: Standard form of Construction Contracts Unit 3: Managing

More information

Robert specialises in litigation and arbitration, domestic and international, in the construction, civil engineering, energy, oil and gas sectors.

Robert specialises in litigation and arbitration, domestic and international, in the construction, civil engineering, energy, oil and gas sectors. CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE ENERGY, NATURAL RESOURCES AND UTILITIES PROFESSIONAL NEGLIGENCE INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS GENERAL COMMERCIAL Robert Clay Call Date: 1989

More information

The NEC Definitely, Maybe?

The NEC Definitely, Maybe? The NEC Definitely, Maybe? Rob Horne - Simmons & Simmons David Thomas QC - Keating Chambers Keith Strutt - DriverTrett General Introduction 1 / B_LIVE_EMEA1:1842195v2 The NEC Why is it relevant The 2015

More information

He has broad experience of all methods of dispute resolution with expertise in domestic and international arbitration, mediation and adjudication.

He has broad experience of all methods of dispute resolution with expertise in domestic and international arbitration, mediation and adjudication. CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE PROFESSIONAL NEGLIGENCE ENERGY, NATURAL RESOURCES AND UTILITIES INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS GENERAL COMMERCIAL Nicholas Collings Call Date:

More information

Somewhere in Time - Securing and Protecting your Contractual Rights

Somewhere in Time - Securing and Protecting your Contractual Rights Howard KLEIN, United Kingdom Keywords: Ascertaining Delays, Delay Costs, Notice, Provisions, Extension of Time, Records, Construction Economics. SUMMARY Time is money and this is no less the case on construction

More information

Clause 17: Care of the Works and Indemnities

Clause 17: Care of the Works and Indemnities Clause 17: Care of the Works and Indemnities Written by George Rosenberg 1 This Clause has been substantially reworked. The content of the former Clause 17.6 [Limitation of Liability] has been removed

More information

CHAPTER 1 25 INTRODUCTION

CHAPTER 1 25 INTRODUCTION CHAPTER 1 25 INTRODUCTION 1.1 Introduction Construction project is unique production due to its natural condition, which is produced by the contractor for the owner/client/employer within specified time

More information

STAMPING OUT SMASH AND GRAB ADJUDICATIONS?

STAMPING OUT SMASH AND GRAB ADJUDICATIONS? BRIEFING STAMPING OUT SMASH AND GRAB ADJUDICATIONS? APRIL 2018 ENGLISH COURT SIGNALS AN END TO SMASH AND GRAB ADJUDICATIONS WHERE PAYMENT OR PAY LESS NOTICE IS INVALID, EMPLOYER REMAINS ENTITLED TO COMMENCE

More information

THE COMMON LAW LIBRARY NUMBER 12 JACKSON & POWELL ON PROFESSIONAL NEGLIGENCE FOURTH EDITION

THE COMMON LAW LIBRARY NUMBER 12 JACKSON & POWELL ON PROFESSIONAL NEGLIGENCE FOURTH EDITION THE COMMON LAW LIBRARY NUMBER 12 JACKSON & POWELL ON PROFESSIONAL NEGLIGENCE FOURTH EDITION LONDON SWEET & MAXWELL 1997 Preface Table of Principal Works Referred To Table of Cases Table of Statutes Table

More information

Saudi Arbitration Law

Saudi Arbitration Law Our newsletter provides informative and practical information regarding legal and commercial developments in construction and energy sectors around the world. Inside this issue: Contract Corner - Global

More information

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC CONTRACTS A COMPARATIVE Uttam Sengupta Sr. GM Contracts & Risk Management FIDIC AND INTRODUCTION TO FIDIC CONDITIONS OF CONTRACT 2 OUTLINE What is FIDIC? Characteristics of FIDIC Conditions of Contract

More information

Consultants Is your duty of care under attack? Webinar

Consultants Is your duty of care under attack? Webinar Consultants Is your duty of care under attack? Webinar Will Buckby and Nadir Hasan 4 July 2018 Introductions Will Buckby Partner, Projects and Contracts Advisory Nadir Hasan Solicitor, Projects and Contracts

More information

Building & Construction Law all notes

Building & Construction Law all notes Building & Construction Law all notes Week 2 THE NATURE OF THE BUILDING AND CONSTRUCTION INDUSTRY Project participants Project stages Procurement methods Typical players and processes Typical project participants

More information

The Hong Kong Institute of Surveyors. Presented by Paul Barrett 11 May 2010

The Hong Kong Institute of Surveyors. Presented by Paul Barrett 11 May 2010 The Hong Kong Institute of Surveyors Common problems encountered with variations, valuations and re-rating under HK forms of contract. Presented by Paul Barrett 11 May 2010 1 The Standard Form of Building

More information

Suspension and Termination

Suspension and Termination Suspension and Termination Nicholas Gould Partner, Fenwick Elliott LLP Visiting Professor, King s College London Termination Typical contract provisions (dual notices) Suspension The grounds for suspension

More information

Design-Build and P3s Contractual Risk Allocation Principles: New Terrain, Old Ground, or Both. Risk Management for Underground Construction

Design-Build and P3s Contractual Risk Allocation Principles: New Terrain, Old Ground, or Both. Risk Management for Underground Construction Design-Build and P3s Contractual Risk Allocation Principles: New Terrain, Old Ground, or Both Risk Management for Underground Construction David J. Hatem, PC Donovan Hatem LLP Boston, MA November 15, 2016

More information

JUDGMENT. Aberdeen City Council (Respondent) v Stewart Milne Group Limited (Appellant) (Scotland)

JUDGMENT. Aberdeen City Council (Respondent) v Stewart Milne Group Limited (Appellant) (Scotland) Michaelmas Term [2011] UKSC 56 On appeal from: [2010] CSIH 81; [2010] CSOH 80 JUDGMENT Aberdeen City Council (Respondent) v Stewart Milne Group Limited (Appellant) (Scotland) before Lord Hope, Deputy President

More information

`the contractor may at any time submit for the PM s agreement proposals for the amendment of the Programme.'

`the contractor may at any time submit for the PM s agreement proposals for the amendment of the Programme.' 6 PROGRAMME 6.1 Where a contractor submits a programme which is approved or accepted by the architect/engineer,is he obliged to follow it or can he amend it at his own discretion? 6.1.1 The programme is

More information

Mitigating Risk through Construction Contracts and Claims Avoidance

Mitigating Risk through Construction Contracts and Claims Avoidance Mitigating Risk through Construction Contracts and Claims Avoidance By Jeremy S. Sharon, Esq. Wright, Fulford, Moorhead & Brown, P.A. 505 Maitland Avenue, Suite 1000 Altamonte Springs, Florida 32701 (407)

More information

15/8/2014. Extension of time clause. Contents. HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION Pre-qualification Structured Learning

15/8/2014. Extension of time clause. Contents. HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION Pre-qualification Structured Learning 1 HONG KONG INSTITUTE OF SUREYORS QUANTITY SUREYING DIISION Pre-qualification Structured Learning 10 July 2014 Liquidated Damages and Extension of Time Presented by Sr. KC Chang BSc(Hons), MA, LLM, FHKIS,

More information

CONSTRUCTION DOCUMENTATION PREPARATION PROTECTING THE EMPLOYER WITHOUT BEING UNFAIR TO THE CONTRACTOR

CONSTRUCTION DOCUMENTATION PREPARATION PROTECTING THE EMPLOYER WITHOUT BEING UNFAIR TO THE CONTRACTOR CONSTRUCTION DOCUMENTATION PREPARATION PROTECTING THE EMPLOYER WITHOUT BEING UNFAIR TO THE CONTRACTOR ACKNOWLEDGEMENT I acknowledge with sincere appreciation the assistance of Professor Doug Jones AM and

More information

Introduction I The joint venture between Carillion (Qatar) LLC (a subsidiary of Carillion pie) and Qatar Building Company was selected and appointed to construct "Phase 1 B" of the Msheireb Downtown Doha

More information

Proving and Tracking Damages of your Claim

Proving and Tracking Damages of your Claim Proving and Tracking Damages of your Claim J. Mark Dungan October 6, 2017 1 Schedules: Back to Basics I. CPM Scheduling Basics II. The Baseline Schedule III. The Schedule Update IV. Delay Analysis V. Proving

More information

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017 BIDP Standard FORMS & JBCC Minor WORKS Commentary ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW 01160007 04 th NOVEMBER 2017 Types of Contract Fixed Price Contracts For Specified work for a sum not adjustable

More information

Time Provisions in Standard Forms of Local and International Construction Contract

Time Provisions in Standard Forms of Local and International Construction Contract Time Provisions in Standard Forms of Local and International Construction Contract Ling Zhe Huei 1, Ting Sim Nee 2 Abstract In any construction contract, the use terms and conditions in construction contract

More information

SLQS JOURNAL. Head Office Overheads Revisited. December Prof. Indrawansa Samaratunga

SLQS JOURNAL. Head Office Overheads Revisited. December Prof. Indrawansa Samaratunga Head Office Overheads Revisited Prof. Indrawansa Samaratunga Head Office Overheads is not an expression that is found in FIDIC Forms of contract, resulting in frequent debate as to why a prolongation cost

More information

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP

Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Richard J. Long, P.E. and Rod C. Carter, CCP, PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

IN THE COURT OF APPEAL KENNETH HARRIS. and SARAH GERALD

IN THE COURT OF APPEAL KENNETH HARRIS. and SARAH GERALD MONTSERRAT CIVIL APPEAL NO.3 OF 2003 BETWEEN: IN THE COURT OF APPEAL KENNETH HARRIS and SARAH GERALD Before: The Hon. Mr. Brian Alleyne, SC The Hon. Mr. Michael Gordon, QC The Hon Madam Suzie d Auvergne

More information

Financing Briefing. slaughter and may. IMO Car Wash: what it means for restructurings. August Case Summary

Financing Briefing. slaughter and may. IMO Car Wash: what it means for restructurings. August Case Summary slaughter and may Financing Briefing August 2009 IMO Car Wash: what it means for restructurings A scheme of arrangement is a statutory procedure under Part 26 of the Companies Act 2006 for effecting a

More information

THE EFFECT OF TIME AT LARGE AND WAIVER OF THE COMPLETION DATE ON CPM SCHEDULE DELAY ANALYSIS

THE EFFECT OF TIME AT LARGE AND WAIVER OF THE COMPLETION DATE ON CPM SCHEDULE DELAY ANALYSIS THE EFFECT OF TIME AT LARGE AND WAIVER OF THE COMPLETION DATE ON CPM SCHEDULE DELAY ANALYSIS Robert M. D Onofrio, P.E. 1 I. SCL Protocol Reversal of Position in Second Edition... 1 II. Example Scenario...

More information

Standard Form of Agreement Between Contractor and Subcontractor

Standard Form of Agreement Between Contractor and Subcontractor Standard Form of Agreement Between Contractor and Subcontractor GENERAL TERMS AND CONDITIONS ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) these General Terms and Conditions,

More information

FIDIC WORKSHOP 2016 GROUP 6

FIDIC WORKSHOP 2016 GROUP 6 FIDIC WORKSHOP 2016 GROUP 6 QUESTION 1 WHAT ARE THE ESSENTIAL REQUIREMENTS FOR FORMATION OF CONTRACT? DISCUSS WHETHER A BINDING AND ENFORCEABLE CONTRACT HAS BEEN CONCLUDED BETWEEN JOLLY AND CAN-DO. 1.

More information

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of Short Course on Construction Law with particular reference to the JBCC 2000 Series of Contracts in particular the application of JBCC Principal Building Agreements Edition 5 (2007) and Edition 4.1 (2005),

More information

INTERNATIONAL. Plant and Design - Build TRAINING PROGRAMME DECEMBER Conditions of Contract for EPC/Turnkey Projects

INTERNATIONAL. Plant and Design - Build TRAINING PROGRAMME DECEMBER Conditions of Contract for EPC/Turnkey Projects INTERNATIONAL TRAINING PROGRAMME 19-22 DECEMBER 2016 THE TRANS LUXURY HOTEL, BANDUNG-INDONESIA 4 DAYS T TWO DAYS TRAINING Conditions of Contract for Plant and Design - Build TWO DAYS TRAINING Conditions

More information

Session 3 by Zoltán Záhonyi, FIDIC AIT,

Session 3 by Zoltán Záhonyi, FIDIC AIT, Session 3 by Zoltán Záhonyi, FIDIC AIT, zoltan.zahonyi@zandpartners.com Contents of Session 3 Session 3: FIDIC 1999 Red Book Part 2 The Quality Issues (Plant, Materials and Workmanship) The Time is of

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

Ethical Contract Negotiation

Ethical Contract Negotiation Ethical Contract Negotiation Texas Society of Professional Engineers May 16, 2006 Brian W. Erikson Quilling, Selander, Cummiskey & Lownds, P.C. 2001 Bryan Street, Suite 1800 Dallas, Texas 75201 (214) 880-1844

More information

ALBON ENGINEERING AND MANUFACTURING LIMITED. - and - Sitting in public at the Royal Courts of Justice, Strand, London WC2A 2LL on 16 June 2017

ALBON ENGINEERING AND MANUFACTURING LIMITED. - and - Sitting in public at the Royal Courts of Justice, Strand, London WC2A 2LL on 16 June 2017 [17] UKFTT 60 (TC) TC06002 Appeal number:tc/14/01804 PROCEDURE costs complex case whether appellant opted out of liability for costs within 28 days of receiving notice of allocation as a complex case date

More information

JUDGMENT. Nelson and others (Appellants) v First Caribbean International Bank (Barbados) Limited (Respondent)

JUDGMENT. Nelson and others (Appellants) v First Caribbean International Bank (Barbados) Limited (Respondent) [2014] UKPC 30 Privy Council Appeal No 0043 of 2013 JUDGMENT Nelson and others (Appellants) v First Caribbean International Bank (Barbados) Limited (Respondent) From the Court of Appeal of St Lucia before

More information

Litigation & Claims Facts & Figures

Litigation & Claims Facts & Figures Litigation & Claims Facts & Figures Paul Lomas-Clarke FRICS FCIArb FCIOB CEDR Accredited Mediator Executive Director 2011 The Global Leader in Managing Construction Risk The reasons claims arise Inadequate

More information

There continues to be considerable debate concerning the ownership of float,

There continues to be considerable debate concerning the ownership of float, Page Number 1 of 19 Abstract There continues to be considerable debate concerning the ownership of float, the implications of concurrent delays and the assessment of delays relative to the award of extension

More information

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage NEC 3 NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED Gary Blackburn Michael Conway Damien Savage 26 June 2013 COMPANY PROFILE UK: Construction Claims & Dispute Avoidance/Resolution, Commercial Management, Project

More information

NIRS 2: Contract extension

NIRS 2: Contract extension NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 LONDON: The Stationery Office 0.00 Ordered by the House of Commons to be printed on 12

More information

NEC3 ECC Introductory Training

NEC3 ECC Introductory Training NEC3 ECC Introductory Training John Rayner House Keeping and Safety Fire Alarm Toilets Mobile phones Please remember to switch all mobile phones to silent 1 Introductions John Rayner Name: NEC3 Knowledge:

More information

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Implementing the Construction Supply Chain Payment Charter. January Guidance Note Implementing the Construction Supply Chain Payment Charter January 2017 Guidance Note Contents Introduction 3 Implementing the Payment Charter 3 Commitments 3 1. We will make correct full payment as and

More information

Blueprint. for Design Professionals September 2011 Volume 2 Issue 2. What do you do when served with a lawsuit?

Blueprint. for Design Professionals September 2011 Volume 2 Issue 2. What do you do when served with a lawsuit? Blueprint for Design Professionals September 2011 Volume 2 Issue 2 Welcome to our third edition of Blueprint For Deisgn Professionals. The articles for this issue provide a primer for the litigation process

More information

HKIS Resolving Disputes between Contractors

HKIS Resolving Disputes between Contractors HKIS Resolving Disputes between Contractors 12 December 2012 (Wednesday) 7:00pm 7:45pm Gilbert Kwok FHKIS, FRICS Partner, Hong Kong and China Construction Group Clyde & Co For further information: gilbert.kwok@clydeco.com

More information

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager London Bristol Dublin Dubai Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager Tom Pemberton, Partner James Vernon, Partner

More information

Construction & Time. Dr. Julian Critchlow

Construction & Time. Dr. Julian Critchlow 1 Construction & Time It has been said that the only major construction project to finish on time and to budget was a church where, presumably, divine intervention played a role Dr. Julian Critchlow 2

More information

DGA Group. International Construction Consultants

DGA Group. International Construction Consultants DGA Group International Construction Consultants Q4 2016 In this Issue: (Click on title to read article or scroll down) A message from the CEO Concurrent delay the Saga continues Grove Developments v Balfour

More information

Technical Conditions. A. Payment Services. Free NONSTOP infoline ,

Technical Conditions. A. Payment Services. Free NONSTOP infoline , Technical Conditions A. Payment Services 1.1 Introductory Provisions 1.1.1 Subject of Technical Conditions These Technical Conditions regulate the relationships between the Client and the Bank, particularly

More information

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016 SARAH KELLERMAN PARTNER m +44 (0) 7810 850 387 e sarah.kellerman@arcadis.com Arcadis Arcadis,

More information

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M. Construction Management Approach based on FIDIC Conditions of Contract for Construction, 1999 1st Edition Dr. Munther M. Saket March 2015 1 Traditional Construction Contracts Owner of a construction project

More information

These Terms & Conditions may only be used by members of Koninklijke Metaalunie.

These Terms & Conditions may only be used by members of Koninklijke Metaalunie. METAALUNIE CONDITIONS General delivery and payment conditions of Koninklijke Metaalunie (the Dutch organisation for small and mediumsized enterprises in the metal industry), referred to as the METAALUNIE

More information

Damages for delay to completion. 1st edition Guidance note

Damages for delay to completion. 1st edition Guidance note Damages for delay to completion 1st edition Guidance note Damages for delay to completion 1st edition Guidance note 2 Damages for delay to completion No responsibility for loss or damage caused to any

More information

The JCT Contract In a Cold Climate

The JCT Contract In a Cold Climate King s College Construction Law Association Sweet & Maxwell Annual Lecture 18 February 2009 The JCT Contract In a Cold Climate Adam Constable Keating Chambers THE ARTICLES AND PAPERS PUBLISHED BY KEATING

More information

Contractors Claims for Loss and Expense under the Principle Traditional Forms of Irish Building Contract

Contractors Claims for Loss and Expense under the Principle Traditional Forms of Irish Building Contract Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2014-03-31 Contractors Claims for Loss and Expense under the Principle Traditional Forms of Irish

More information

ProMinent Verder B.V.

ProMinent Verder B.V. Terms & Conditions ProMinent Verder B.V. (30100444) Filed at the Chamber of Commerce on 29-01-2015 1. General 1.1 These terms and conditions use the following terms and definitions: Product: items, as

More information

Conditions of Appointment for an Architect for a Domestic Project 2010 (2012 revision) Incorporating Amendment 1, September 2011

Conditions of Appointment for an Architect for a Domestic Project 2010 (2012 revision) Incorporating Amendment 1, September 2011 Conditions of Appointment for an Architect for a Domestic Project 2010 (2012 revision) Incorporating Amendment 1, September 2011 This and the following seven pages (numbered 2 8) are the Conditions of

More information

Mitigating Delay Claims and Scheduling Best Practices

Mitigating Delay Claims and Scheduling Best Practices Mitigating Delay Claims and Scheduling Best Practices Prepared and Presented by: Raquel Speers Shohet, EI, PSP Hill International, Inc. Claims and Consulting Group 10801 W. Charleston Blvd. Suite 650 Las

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL

SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL 2nd edition February 2017 www.scl.org.uk Published by the Society of Construction Law (UK), 234 Ashby Road, Hinckley, Leicestershire, LE10 1SW.

More information

Refusing a liquidator s wrongful trading application

Refusing a liquidator s wrongful trading application 1 Refusing a liquidator s wrongful trading application 12/09/2016 Restructuring & Insolvency analysis: David Bowden, solicitor-advocate of David Bowden Law, Andy Whelan, insolvency practitioner and partner

More information

DOUKPSC04 Rev Feb 2013

DOUKPSC04 Rev Feb 2013 DOUKPSC04 Purchasing Standard conditions for the Purchase of Consultancy Services 1 DEFINITIONS In the Contract (as hereinafter defined) the following words and expressions shall have the meanings hereby

More information

Pursuing claims under FIDIC. Jeremy Glover

Pursuing claims under FIDIC. Jeremy Glover Pursuing claims under FIDIC Jeremy Glover Force Majeure: a common law definition An act of God or force majeure clause, generally operates to discharge a contracting party when a supervening, sometimes

More information

Contracts Management. Variations CCF. Fenwick Elliott Grace. 17 March 2016

Contracts Management. Variations CCF. Fenwick Elliott Grace. 17 March 2016 Contracts Management Variations CCF 17 March 2016 From a construction lawyer s perspective Most disputes arise out of or involve claims for variations Often result in being a significant portion of the

More information

FEDERAL CONSTRUCTION PROJECT MANAGER S BULLETIN Devoted exclusively to problems encountered while performing Government construction contracts

FEDERAL CONSTRUCTION PROJECT MANAGER S BULLETIN Devoted exclusively to problems encountered while performing Government construction contracts FEDERAL CONSTRUCTION PROJECT MANAGER S BULLETIN Devoted exclusively to problems encountered while performing Government construction contracts Volume II Number 21 ENFORCEABILITY OF CONTRACTS Readers of

More information

Dominique Rawley QC PRACTICE POWER, ENERGY, OIL & GAS. Call Date: 1991, Silk: 2012//

Dominique Rawley QC PRACTICE POWER, ENERGY, OIL & GAS. Call Date: 1991, Silk: 2012// POWER, ENERGY, OIL & GAS RAIL PROCESS PLANTS DOMESTIC CONSTRUCTION AND ROADS PFI PROFESSIONAL NEGLIGENCE INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS BONDS AND CONFLICTS OF LAWS Dominique Rawley QC Call

More information

Robert Stokell Call

Robert Stokell Call Robert Stokell Call 1995 +44 (0)20 7797 8100 stokell@crownofficechambers.com Robert Stokell specialises in substantial construction and engineering disputes, insurance-related advice and litigation, product

More information

Default and termination

Default and termination Default and termination GLOBAL INFRASTRUCTURE HUB TURNER & TOWNSEND Contents 7 Default and termination 3 7.1 Background 4 7.2 Guidance 5 7.3 Summary data analysis 12 DEFAULT AND TERMINATION 7 Default and

More information

JANE LEMON QC. Declan Redmond T: +44 (0) E:

JANE LEMON QC. Declan Redmond T: +44 (0) E: Keating Chambers 15 Essex Street London WC2R 3AA T +44 (0)20 7544 2600 F +44 (0)20 7544 2700 keatingchambers.com DX: LDE 1045 Call: 1993 / Silk: 2015 jlemon@keatingchambers.com Areas of practice Clerks

More information

GENERAL PURCHASING TERMS AND CONDITIONS Valid as of September 1 st, 2015 for any order or contract 4. DELIVERY

GENERAL PURCHASING TERMS AND CONDITIONS Valid as of September 1 st, 2015 for any order or contract 4. DELIVERY GENERAL PURCHASING TERMS AND CONDITIONS Valid as of September 1 st, 2015 for any order or contract 1. GENERAL INFORMATION The supplier s acceptance of an order implies ipso facto the acceptance of these

More information

Why a Project Owner Isn t Made an Additional Insured Under a Design Professional s Errors and Omissions Policy

Why a Project Owner Isn t Made an Additional Insured Under a Design Professional s Errors and Omissions Policy constructionrisk.com http://www.constructionrisk.com/2011/07/why-project-owners-aren t-made-additional-insureds-under-a-design-professional s-errorsand-omissions-policy/ Why a Project Owner Isn t Made

More information

Client Update August 2009

Client Update August 2009 giv Highlights Introduction...1 Brief Facts...1 Holding On Appeal...3 Concluding Words...8 Termination Of Contract Under Common Law: Is It A Defence That The Party Seeking To Terminate Was Itself Guilty

More information

Introduction. Background to the Breyer Case

Introduction. Background to the Breyer Case Breyer Group Plc & Others ( Claimants ) v Department of Energy and Climate Change ( DECC ): A Cautionary Tale for Policy Makers and Regulators and Possible Implications for Irish I-SEM Design Introduction

More information

Presented by: Art Barry, QC

Presented by: Art Barry, QC Construction Contracts - Risk Management 101 Liquidated damages and notice provisions Presented by: Art Barry, QC April 17, 2013 2013 Stewart McKelvey. All rights reserved. Not to be copied or used in

More information

The Quantity Surveyor and the Law

The Quantity Surveyor and the Law The Quantity Surveyor and the Law Edward Jayathunga AAIQS Edward attached Bond Communications as Chief Quantity Surveyor since 2008, prior to that he served Gardiner and Theobold International as a Senior

More information

International Advanced Certificate in Purchasing and Supply PREPARING AND MANAGING CONTRACTS. A8/May11 LEVEL 4 MARKING SCHEME. May 2011.

International Advanced Certificate in Purchasing and Supply PREPARING AND MANAGING CONTRACTS. A8/May11 LEVEL 4 MARKING SCHEME. May 2011. International Advanced Certificate in Purchasing and Supply PREPARING AND MANAGING CONTRACTS A8/May11 LEVEL 4 MARKING SCHEME May 2011 Shenstone SECTION A Questions 1-10 are multiple choice questions. For

More information