Hong Kong Institute of Surveyors "EOT and Liquidated Damages"
|
|
- Allen Mason
- 5 years ago
- Views:
Transcription
1 Hong Kong Institute of Surveyors "EOT and Liquidated Damages" 18 February 2014 Damon So, Partner Projects (Engineering & Construction) Practice
2 Extension of Time
3 Time Obligations 1. No express agreement reasonable time 2. Date agreed a. Duty to complete by a certain date b. Breach: damages/liquidated damages
4 The Prevention Principle Set at large Reasonable Time Commencement Date Employer s delay Contractual Completion Date Liquidated Damages Damages
5 Extension of Time WHY? FOR CONTRACTOR? It: - avoids the prevention principle - ensures certainty of date - preserves LD's FOR EMPLOYER
6 HKIA Form (1986 Edition) Clause if in the opinion of the Architect the completion of the Works is likely to be or has been delayed beyond the Date for Completion or beyond any extended time previously fixed, a.by force majeure, or b.by reason of inclement weather, or c.by reason of civil commotion, local combination of workmen, strike or lockout, or d.by reason of Architect s instructions issued, or e.by reason of the Main Contractor not having received in due time necessary instructions, drawings, details or levels from the Architect, or
7 HKIA Form (1986 Edition) (Cont'd) f. by delay on the part of artists, tradesmen or others engaged by the Employer in executing work not forming part of this Contract, or... then the Architect shall so soon as he is able to estimate the length of the delay beyond the date or time aforesaid make in writing a fair and reasonable extension of time for completion of the Works.
8 Relevant Events a. Employer s delays e.g. variations, delay by their agents, delay in providing instructions, drawings, details or level b. Neutral events e.g. force majeure, inclement weather, strikes, c. What is not covered?
9 Question What if a delay by Employer is not covered by the provision?
10 Notice Provisions a. Two-stage notices - notice of delay - submission of particulars b. Failure to submit notices - damages - loss of right to claim EOT c. Condition Precedent
11 Position in Australia Gaymark Investments Pty Ltd v Walter Construction Group Ltd, (1999) NTSC 143 Arbitration: Claim by Walter: - variations - prolongation, disruption and accelerations costs Counterclaim by Gaymark: - late completion - liquidated damages
12 Time Provisions Original Clause Superintendent has general power to extend time despite Contractor s failure to comply with notice. Clause 35.4 replaced by SC initial notice of 14 days after every cause of delay - second notice with particulars within 21 days of first notice SC Contractor shall only be entitled to an extension of time if SC19.1 is strictly complied with.
13 Claim for liquidated damages The Arbitrator found - Gaymark caused 77 days delay to Walter - acts of prevention - Walter failed to comply with notice provisions - no general power to grant EOT - time set at large - complete within a reasonable time - no LD s
14 Arbitrator s Reasoning Three possible constructions:- 1. Implication of discretionary power similar to Clause care taken in amending the EOT provisions - Superintendent considered his power being exhausted once time bar was hit. 2. Too bad for the Contractor - prolongation costs + liquidated damages 3. Risk taken by Employer - EOT at Contractor's option
15 Arbitrator s Reasoning (Cont'd) EOT claims Superintendent s assessment EOT Granted Delay by Gaymark 1. Discretionary power 2. Non-compliance 3. Optional Reasonable time Extended Completion Date Commencement Date Original Completion Date
16 Criticisms of Gaymark IND Wallace QC (Hudson's): 1. Practical considerations ignored: a. criticality better known to Contractor b. Owner s opportunity to reduce or avoid delay. 2. Judicial dislike of LD clauses no longer exists 3. Rejection of EOT based on failure to comply with notice rather than own wrong 4. First principle: contractual intention from language used
17 Position in Hong Kong Hsin Chong Construction (Asia) Limited v Henble Limited [2006] HCCT -rejected Gaymark -cited submissions from Hudson's
18 Position in Hong Kong (Con't) W Hing Construction Co Ltd v Boost Investments Ltd [2009] 2 HKLRD 501 (CFI) -Did not follow Gaymark -Contractor required to comply with contractual notice provisions for EOT; failure to comply meant no EOT
19 Concurrent Delay - Issue arises where there is more than one effective cause for delay - E.g. where both employer and contractor, or contractor and sub-contractor cause or contribute to delaying events - Should contractor/sub-contractor be entitled to full EOT caused by both events, or only to a pro-rated EOT for events not caused by contractor/sub-contractor?
20 Position in Hong Kong W Hing Construction Co Ltd v Boost Investments Ltd [2009] 2 HKLRD 501(CFI) -Considered Scottish case of City Inn Ltd v Shepherd Ltd [2008] BLR 269: apportionment of responsibility for delays caused by different parties -No apportionment of EOT because contractor did not comply with contractual notice requirements for EOT -Whether apportionment approach to be adopted in HK is open question
21 Position in England De Beers Ltd v Atos Origin IT Services [2011] BLR 274 -Where employer and contractor both responsible for concurrent delay, contractor entitled to EOT but cannot recover in respect of loss caused by delay -Contractor would suffer the same loss due to causes within his control or for which he is contractually responsible
22 Position in England (Con't) Walter Lilly & Co v Mackay & DMW Developments [2012] EWHC Contractor is entitled to full EOT for delay caused by two or more events (if one of them is a relevant event in contract) -Applied Malmaison approach
23 Liquidated Damages
24 Meaning - agreed sums payable upon breach - genuine pre-estimate of loss - cf unliquidated damages or general damages - fixed remedy for contractor s delay e.g. $10,000 per day of delay after PC
25 Effect - exhaustive remedy on delay - payable even where no actual loss is suffered - liability capped at agreed damages - if nil inserted as the rate of LD s? no LD s recoverable for delay Temloc v Errill Properties Ltd. (CA)
26 Advantages a. Certainty b. Avoids expensive and difficult investigation e.g. public works project c. Causation/remoteness/foreseeability d. Pre-agreed level of damages
27 Defences 1. Time at large 2. Penalty Defences successful - revert to general damages - may be capped at LD
28 Penalty Two conflicting policies General rule: - contract to be enforced Exception: - damages compensatory - unjustifiable amount for breach - not enforced by the Court - onus on the party being sued upon it
29 What is Penalty? Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd [1915] 1. penalty or liquidated damages. 2. "in terrorem" of the offending party. 3. genuine pre-estimate of damage. 4. circumstances 5. Tests: breach of non-payment, greatest loss, single sum payable for different events, sectional completion
30 Difficulty in estimating? Philips Hong Kong Ltd v The AG of HK [1993] PC a. virtuably impossible to calculate precisely in advance. b. sensible approach by Government c. Not enough to identify hypothetical situations d. Is it a genuine pre-estimate? e. What actually happens subsequently provides valuable evidence
31 Genuine Pre-estimate Alfred McAlpine Capital Projects v Tilebox [2005] EWHC not "genuiness or honesty" of party estimating - objective test at the time of contracting - substantial discrepancy between LD's and likely loss - tendency to uphold commercial contractual terms - echoed in Steria v Sigma Wireless Communications [2008] BLR 79
32 Cascading Argument Liberty Mercian v Dean & Dyball Construction [2008] (TCC) - construction of 4 retail units, 5 sections - LD's for each section - possession of later section on completion of preceding section - 4 weeks delay for the first section - 20 weeks of LD's imposed Court: nothing unfair
33 City Inn Limited v Shepherd Construction Ltd. (2003) Inner House, Court of Session Notice Provisions:- a. Whenever Contractor received an instruction to carry out works which would require an adjustment to the contract sum or EOT, before executing the works, the Contractor should give notice with particulars to the Architect b. Condition precedent to Contractor s right to EOT Shepherd failed to comply with those provisions
34 Shepherd's Arguments No Gaymark argument Penalty argument :- - procedural default - no relation to LD s imposed - not a genuine pre-estimate of loss suffered as a result of breach
35 The Court a. LD s imposed a a result of delay in completion b. EOT provision only gave them a right to relief c. Right lost because of failure to comply with notice provisions d. LD s not penalty
36 Court's reasoning Delay EOT Claims The Court s finding Failed to comply with notice provisions EOT entitlement Shepherd s argument LD s No EOT
37 Defeating Penalty 1. Incentive vs Penalty 2. Optional Completion Obligations 3. Lane and site rental
38 The End
39 Damon So Partner Direct line: Hogan Lovells has offices in: Abu Dhabi Alicante Amsterdam Baltimore Beijing Berlin Brussels Budapest* Caracas Colorado Springs Denver Dubai Dusseldorf Frankfurt Hamburg Hanoi Ho Chi Minh City Hong Kong Houston Jeddah* London Los Angeles Madrid Miami Milan Moscow Munich New York Northern Virginia Paris Philadelphia Prague Riyadh* Rome San Francisco Shanghai Silicon Valley Singapore Tokyo Ulaanbaatar* Warsaw Washington DC Zagreb* "Hogan Lovells" or the "firm" refers to the international legal practice comprising Hogan Lovells International LLP, Hogan Lovells US LLP, Hogan Lovells Worldwide Group (a Swiss Verein), and their affiliated businesses, each of which is a separate legal entity. Hogan Lovells International LLP is a limited liability partnership registered in England and Wales with registered number OC Registered office and principal place of business: Atlantic House, Holborn Viaduct, London EC1A 2FG. Hogan Lovells US LLP is a limited liability partnership registered in the District of Columbia. The word "partner" is used to refer to a member of Hogan Lovells International LLP or a partner of Hogan Lovells US LLP, or an employee or consultant with equivalent standing and qualifications, and to a partner, member, employee or consultant in any of their affiliated businesses who has equivalent standing. Rankings and quotes from legal directories and other sources may refer to the former firms of Hogan & Hartson LLP and Lovells LLP. Where case studies are included, results achieved do not guarantee similar outcomes for other clients. New York State Notice: Attorney Advertising. Hogan Lovells All rights reserved. * Associated offices
Responding to Commercial Bribery Investigations What to Do When the Chinese Administration for Industry and Commerce (AIC) Arrives At Your Door
Responding to Commercial Bribery Investigations What to Do When the Chinese Administration for Industry and Commerce (AIC) Arrives At Your Door Eugene Chen Counsel, Hogan Lovells International LLP September
More informationShareholders' Rights in a Russian Joint-Stock Company
Shareholders' Rights in a Russian Joint-Stock Company Further information If you would like further information on any aspect of the issues described in this note please contact a person mentioned below
More informationDirectors and Officers Liabilities in Russia
Directors and Officers Liabilities in Russia Further information If you would like further information on any aspect of the issues described in this note please contact a person mentioned below or the
More informationThe Act Amending the Right of Inquiry
The Act Amending the Right of Inquiry Further information If you would like further information on any aspect of the Act amending the right of inquiry please contact a person mentioned below or the person
More informationThird Party Rights / Licence. Binding Framework. Negotiating Framework
Structures for Group Procurement Operations This pack provides an overview of various structures which can be considered when establishing a group procurement operation It assumes that the operation may
More informationNEW CHANNEL OPENED FOR FLOWING-BACK OF OVERSEAS RENMINBI ("RMB")
NEW CHANNEL OPENED FOR FLOWING-BACK OF OVERSEAS RENMINBI ("RMB") 1 NEW CHANNEL OPENED FOR FLOWING-BACK OF OVERSEAS RENMINBI ("RMB") The People's Bank of China ("PBOC") issued the Administrative Measures
More informationHogan Lovells (Luxembourg) LLP. What do you know about us?
Hogan Lovells (Luxembourg) LLP What do you know about us? Who is Hogan Lovells? Who is Hogan Lovells? Change is happening faster than ever. To stay ahead, you need to anticipate what s next. Whether that
More informationArbitrability of IP Disputes in Russia
Arbitrability of IP Disputes in Russia Date Natalia Gulyaeva Partner, Head of IP, Media and Technology Practice CIS IP Arbitration Pros? When does IP arbitration make sense? disputes related to IP license
More informationStrategic and Operational Challenges Resulting from the New PPACA
Strategic and Operational Challenges Resulting from the New PPACA Eric M. Baim, Esq., Hogan Lovells Jennifer Colapietro, Partner, PwC Thursday, October 21, 2010 The Big Questions Who s in charge here?
More informationMiFID II 18 January MiFID II
MiFID II 18 January 2017 1 MiFID II Suitability December 2016 MiFID II 18 January 2017 1 Key Points A specific requirement to take the client's ability to bear losses and risk tolerance into account when
More informationFirms will be required to appoint a single officer with specific responsibility for client assets
MiFID II Safeguarding of client assets Key Points Firms will be required to appoint a single officer with specific responsibility for client assets Title transfer collateral arrangements ("TTCAs") will
More informationMiFID II Best execution and client order handling
2015 MiFID II Best execution and client order handling Key Points The definition of trading venue will include the new MiFID II concept of an organised trading facility A firm's obligation to take steps
More informationMiFID II Information to clients on costs and charges
MiFID II Information to clients on costs and Key Points associated /ancillary services and financial instruments should be disclosed to clients. This encompasses a wider range of costs than were previously
More informationRoundtable on Anti-Bribery and Anti- Corruption Compliance in Latin America Latin American Anti-Corruption Laws
Roundtable on Anti-Bribery and Anti- Corruption Compliance in Latin America Latin American Anti-Corruption Laws Peter Spivack, Co-Chair, Investigations, White Collar and Fraud Practice Area Hogan Lovells
More informationGrey areas in the spotlight Update on Investment Regulations Non-public companies
Grey areas in the spotlight Update on Investment Regulations Non-public companies Phong Nguyen, Senior Associate 24 October 2013 Corporate / Vietnam Contents Private placement of shares / bonds Official
More informationHIPAA Privacy Rule and Research
HIPAA Privacy Rule and Research Melissa Bianchi Partner February 24, 2014 Healthcare/Privacy Research Pre-January 2013 Under HIPAA, may use PHI for research with: an individual s written authorization
More informationMiFID II 31 December MiFID II
MiFID II 31 December 2016 MiFID II Information to clients about investment advice and financial instruments December 2016 MiFID II 31 December 2016 1 Key Points Firms will be required to give additional
More informationContents. Introduction 4. Directors conflicts duties 4. What is a conflict? 5. Who can authorise? 6. Authorising conflicts 7
Directors conflicts of interests under the Companies Act 2006 Contents Introduction 4 Directors conflicts duties 4 What is a conflict? 5 Who can authorise? 6 Authorising conflicts 7 Practical steps for
More informationListing in London An introductory guide
Listing in London An introductory guide Further information If you would like further information on any aspect of Listing in London please contact a person mentioned below or the person with whom you
More informationMiFID II 31 December MiFID II
MiFID II 31 December 2016 MiFID II Appropriateness December 2016 MiFID II 31 December 2016 1 Key Points Appropriateness assessments will be applied to new types of complex investments. New record-keeping
More informationMiFID II 31 December MiFID II. Third country access
MiFID II 31 December 2016 1 MiFID II Third country access December 2016 MiFID II 31 December 2016 1 Key Points MiFID II will allow third country (i.e. non-eu) firms to provide cross-border services in
More informationDerivatives: trade execution
2016 MiFID II Derivatives: trade execution Key Points MiFID II requires certain standardised derivative contracts to be traded through a trading venue This obligation only applies to those classes of derivatives
More informationMiFID II. Inducements. Key Points
MiFID II Inducements Key Points There will be further guidance on the meaning of the phrase "designed to enhance the quality of the service" (which is a pre-requisite for an inducement to be permitted
More informationA New Frontier Amendments to the Listing Rules, Prospectus Rules and Disclosure and Transparency Rules
A New Frontier Amendments to the Listing Rules, Prospectus Rules and Disclosure and Transparency Rules Feedback on FSA Consultation Paper 12/2 as set out in FSA Consultation Paper 12/25 October 2012 1
More informationPhysician Payment Transparency Provisions of the Affordable Care Act Sunshine 101
Physician Payment Transparency Provisions of the Affordable Care Act Sunshine 101 Danielle Drissel, Associate February 19, 2013 Health/ Washington DC What is Sunshine? Deceptively simple: Applicable manufacturers
More informationMiFID II 31 December MiFID II
MiFID II 31 December 2016 2 MiFID II Safeguarding of client assets December 2016 MiFID II 31 December 2016 1 Key Points Firms will be required to appoint a single officer with specific responsibility for
More informationABA Mutual Institutions Council Capital Issues for Mutuals
ABA Mutual Institutions Council Capital Issues for Mutuals Richard A. Schaberg Richard L. Quad October 14, 2012 Contents I. Sources of Capital for Mutuals II. III. Regulatory Issues with Preferred Stock
More informationMiFID II 31 December MiFID II. Derivatives: trade execution
MiFID II 31 December 2016 1 MiFID II Derivatives: trade execution December 2016 MiFID II 31 December 2016 1 Key Points MiFID II requires certain standardised derivative contracts to be traded through a
More informationMiFID II 31 December MiFID II
MiFID II 31 December 2016 1 MiFID II Recordkeeping and telephone and email recording December 2016 MiFID II 31 December 2016 1 Key Points Like MiFID I, MiFID II requires firms to keep records of transactions.
More informationEvery cent counts: China slashes certain IP application fees. April 2017
Every cent counts: China slashes certain IP application fees April 2017 Every cent counts: China slashes certain IP application fees April 2017 1 Every cent counts: China slashes certain IP application
More informationMiFID II 31 December MiFID II
MiFID II 31 December 2016 MiFID II Underwriting and placing December 2016 MiFID II 31 December 2016 1 Key Points Firms must identify and prevent or manage conflicts of interest that may arise due to underwriting
More informationSummary of principles from recent NEC cases
Summary of principles from recent NEC cases September 2018 Summary of principles from recent NEC cases September 2018 1 Summary of principles from recent NEC cases As a market leading construction team
More informationMiFID II 31 December MiFID II. Information to clients on costs and charges
MiFID II 31 December 2016 1 MiFID II Information to clients on costs and December 2016 MiFID II 31 December 2016 1 Key Points All costs and associated investment/ancillary services and financial instruments
More informationThe Eurozone Crisis: Checklist of issues for finance documentation. May 2012
The Eurozone Crisis: Checklist of issues for finance documentation May 2012 This checklist is for guidance only and should not be relied on as legal advice in relation to a particular transaction or situation.
More informationThe Eurozone Crisis: Corporate briefing. May 2012
The Eurozone Crisis: Corporate briefing May 2012 This briefing is for guidance only and should not be relied on as legal advice in relation to a particular transaction or situation. 2 The Eurozone Crisis:
More informationDirectors duties under the Companies Act An introduction
Directors duties under the Companies Act 2006 An introduction Contents Introduction and background 4 The duties 5 Duty to promote the success of the company 6 Duty to exercise reasonable care, skill and
More informationThe PSC register. The requirement for a register of persons with significant control over UK entities
The PSC register The requirement for a register of persons with significant control over UK entities 2 Hogan Lovells Since 6 April 2016, UK companies have been required to maintain a register of persons
More informationPayment Services Academy
Payment Services Academy 2018 2 Hogan Lovells Payment Services Academy Our interactive digital training has been created by our industry-leading payments lawyers to help you and your teams comply with
More informationMiFID II March MiFID II
MiFID II March 2015 1 MiFID II FCA Discussion Paper and HM Treasury Consultation Paper March 2015 MiFID II March 2015 1 Key Points The FCA has released a Discussion Paper (DP15/3) on its approach to implementation
More informationSEC adopts requirement for disclosure of hedging policies for employees, officers, and directors
SEC Update January 24, 2019 This is a commercial communication from Hogan Lovells. See note below. SEC adopts requirement for disclosure of hedging policies for employees, officers, and directors On December
More informationNew listing regime proposals for emerging and innovative companies
New listing regime proposals for emerging and innovative companies March 2018 New listing regime proposals for emerging and innovative companies March 2018 1 New listing regime proposals for emerging and
More informationMiFID II 31 December MiFID II. Commodity derivatives
MiFID II 31 December 2016 1 MiFID II Commodity derivatives December 2016 MiFID II 31 December 2016 1 Key Points An expanded range of commodity derivatives will be brought within the scope of regulation.
More informationHKMA reboots virtual banking. February 2018
HKMA reboots virtual banking February 2018 HKMA reboots virtual banking February 2018 1 HKMA reboots virtual banking On 6 February, 2018, the Hong Kong Monetary Authority (the HKMA ) published draft revisions
More informationObservations on US LNG Export Prospects in Latin America Eduardo Carvajal, Hogan Lovells US-Americas LNG Forum I, Rio de Janeiro, Brazil May 23, 2018
Observations on US LNG Export Prospects in Latin America Eduardo Carvajal, Hogan Lovells US-Americas LNG Forum I, Rio de Janeiro, Brazil May 23, 2018 Discussion Map Hogan Lovells and LNG Capabilities Delfin
More informationMerger Control Rules in the EEA
Merger Control Rules in the EEA Further information If you would like further information on any aspect of this client note please contact a person mentioned below or the person with whom you usually deal.
More informationMEMORANDUM FOR THE NATONAL STRUCTURED SETTLEMENTS TRADE ASSOCIATION
MEMORANDUM FOR THE NATONAL STRUCTURED SETTLEMENTS TRADE ASSOCIATION December 6, 2015 Re: Possible Contingent Liability of Settling Defendants/Liability Insurers Who Have Made Qualified Assignments If a
More informationArbitration in Vietnam
Arbitration in Vietnam An introduction Contents Vietnam's arbitration law 1 Disputes that may be arbitrated 1 Arbitration agreements 1 Alternative Dispute Resolution 6 Conclusions 6 About Hogan Lovells
More information2017 Singapore Insolvency and Restructuring Reforms
2017 Singapore Insolvency and Restructuring Reforms June 2017 Contents Introduction 1 1. Better accessibility to Singapore's corporate rescue and restructuring framework for foreign companies 2 2.Chapter
More informationA survival guide for private equity
EU General Data Protection Regulation A survival guide for private equity EU General Data Protection Regulation 3 Introduction Time to prepare To say that the EU General Data Protection Regulation (GDPR
More informationTaking security in Vietnam
Taking security in Vietnam June 2015 1 Taking security in Vietnam Contents Introduction 1 Secured transactions in general 1 Typical security package 2 Security regime for public-privatepartnership projects
More informationMiFID II Market data reporting
2016 MiFID II Market data reporting Key Points MiFID I requires investment firms to report transactions to national competent authorities ( NCAs ) This transaction data allows NCAs to detect and investigate
More informationInternational Swaps and Derivatives Association, Inc.
Allen & Overy LLP MEMORANDUM To Peter Werner Graham Bryant International Swaps and Derivatives Association, Inc. From Our ref Richard Tredgett RPT/0030047-0001105 ICM:27517080.4 Date 19 September, 2017
More informationInsurance aggregation issues. Dave Newmann and Stuart Hill (Hogan Lovells International LLP) 18 th July Insurance aggregation issues
Insurance aggregation issues Dave Newmann and Stuart Hill (Hogan Lovells International LLP) 18 th July 2014 1 Insurance aggregation issues Stuart Hill 2 1 Aggregation Something old, something new Stuart
More informationInvestment Protection and Arbitration
Investment Protection and Arbitration Further information This brochure is a short introduction to investment protection and arbitration and to our practice. If you have any questions about investment
More informationDrafting international contracts for a global marketplace
Drafting international contracts for a global marketplace Nicole Mansell, General Counsel & Compliance, Arjowiggins Security Christine Gateau, Litigation Partner, Hogan Lovells Mikael Salmela, Corporate/Commercial
More informationCase BLS Doc 548 Filed 10/30/18 Page 1 of 9 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE
Case 18-11120-BLS Doc 548 Filed 10/30/18 Page 1 of 9 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE In re VG LIQUIDATION, INC., et al., Debtors. 1 Chapter 11 Case No. 18-11120 (BLS)
More informationThe April 2015 tax changes
OFFICIAL PARTNER The April 2015 tax changes A practical guide for trustees The April 2015 tax changes 3 Contents 1. April 2015 tax changes a reminder 4 2. How is my scheme affected? 5 3. Issues for DC
More informationFor the record: China's foreign investment regime enters a new phase
For the record: China's foreign investment regime enters a new phase September 2016 2 Hogan Lovells For the record: China's foreign investment regime enters a new phase Overview and background On 3 September
More informationDC flexibility: providing DC access through external providers.
DC flexibility: providing DC access through external providers www.allenovery.com DC flexibility: providing DC access through external providers March 2015 Background Many schemes and sponsors are being
More informationSaudi Arabia opens Stock Market to Foreign Investors. May 2015
Saudi Arabia opens Stock Market to Foreign Investors May 2015 2 Saudi Arabia opens Stock Market to Foreign Investors May 2015 Following the restriction on direct ownership of securities listed on the Saudi
More informationRemuneration voting 2015 AGM season. CA Brochure_Remuneration Voting (Dinesh Rajan).indd 1
Remuneration voting 2015 AGM season CA1510026 - Brochure_Remuneration Voting (Dinesh Rajan).indd 1 2 Remuneration voting 2015 AGM season Allen & Overy LLP 2015 CA1510026 - Brochure_Remuneration Voting
More informationWells Fargo Bank, N.A. as Trustee v. Chukchansi Economic Development Authority, et al., Index No /2013
Robert J. Malionek Direct Dial: 212-906-1816 robert.malionek@lw.com October 15, 2013 Honorable Melvin L. Schweitzer Supreme Court of the State of New York County of New York 26 Broadway New York, NY 10004
More informationSaudi Arabia opens Stock Market to Foreign Investors. May 2015
Saudi Arabia opens Stock Market to Foreign Investors May 2015 2 Saudi Arabia opens Stock Market to Foreign Investors May 2015 Following the restriction on direct ownership of securities listed on the Saudi
More informationDELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE
DELAY AND DESTRUCTION: CURRENT PRACTICE, PROCEDURE AND THE RELEVANCE OF EXPERT EVIDENCE Andrew Burr MA(Cantab), ACIArb, FFAVE(Master) ArbDB Chambers Silver Shemmings LLP London 1. Delay and disruption:
More informationFinancing Africa s future. Who is taking the lead in lending?
Financing Africa s future Who is taking the lead in lending? 2 Hogan Lovells Financing Africa s future Who is taking the lead in lending? On 5th July 2018, Hogan Lovells hosted its 5th annual Africa Forum
More informationSAFE issues new circular on the foreign exchange administration of fund management firms and securities firms making overseas investments: will it
SAFE issues new circular on the foreign exchange administration of fund management firms and securities firms making overseas investments: will it open the floodgates to new investment quotas? Further
More informationEmployers pension consultation obligations
Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Employers pension consultation obligations Briefing December 2017 Introduction
More informationNew Circular to Relax the Filing Process
New Circular to Relax the Filing Process for Foreign-Invested Real Estate Enterprises 31st July 2014 SPEED READ In June 2014, the Ministry of Commerce ( MOFCOM ) and the State Administration of Foreign
More information3. Full protection and security. Often interpreted as complementary to, and overlapping with, fair and equitable treatment, full
Investment Treaty Arbitration Mitigating Risk and Protecting Cross-Border Deals Investment treaties provide important protection for cross-border investments. These provide investors making investments
More informationMIFID2 ASIAN FINANCIAL INSTITUTIONS BEST EXECUTION SEPTEMBER 2017
MIFID2 ASIAN FINANCIAL INSTITUTIONS BEST EXECUTION SEPTEMBER 2017 IS MIFID2 RELEVANT TO ME? Trading on EU trading venues Using an EU affiliate to book trades Providing services to / trading with EU clients
More informationBack to the future but no idea when
Back to the future but no idea when What Brexit could mean for the Anglo-European restructuring industry What happens now? On 23 June 2016, the UK voted to leave the European Union. The nature of the UK
More informationMiFID II 31 December MiFID II. Market infrastructure, trading venues and central counterparties
MiFID II 31 December 2016 1 MiFID II Market infrastructure, trading venues and central counterparties December 2016 MiFID II 31 December 2016 1 Market infrastructure Key Points Creation of a new category
More informationM&A ACADEMY: TAX ISSUES IN M&A TRANSACTIONS
M&A ACADEMY: TAX ISSUES IN M&A TRANSACTIONS Daniel Nelson, Partner Casey August, Partner February 12, 2019 2019 Morgan, Lewis & Bockius LLP Introductory Notes Focus on domestic transactions Cross-border
More informationCase BLS Doc 690 Filed 01/23/19 Page 1 of 9 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE.
Case 18-11120-BLS Doc 690 Filed 01/23/19 Page 1 of 9 IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE In re VG LIQUIDATION, INC., et al, Debtors.' Chapter 11 Case No. 18-11120 (BLS) (Jointly
More informationWhich Market? Equity Capital Markets
Which Market? Equity Capital Markets Further information If you would like any further information on any aspect of listing in London, please contact the person at Hogan Lovells with whom you usually deal
More informationTAX ISSUES IN M&A TRANSACTIONS
MORGAN LEWIS 2018 M&A ACADEMY PRESENTS: TAX ISSUES IN M&A TRANSACTIONS Daniel Nelson, Partner Casey August, Partner March 6, 2018 2018 Morgan, Lewis & Bockius LLP Introductory Notes Focus on domestic transactions
More informationUAE securities regulator creates regime for promotion and introduction to UAE investors
UAE securities regulator creates regime for promotion and introduction to UAE investors 1 Briefing note February 2017 UAE securities regulator creates regime for promotion and introduction to UAE investors
More informationClient Alert. Hong Kong Jurisdiction Relating to Cross Border Insolvency Issues Becomes Increasingly Clear. Background
Number 1502 22 April 2013 Client Alert Latham & Watkins Litigation Department Jurisdiction Relating to Cross Border Insolvency Issues Becomes Increasingly Clear The fact that the controlling mind of a
More informationLaw of 10 August on commercial companies
Law of 10 August 1915 on commercial companies - 2 - This translation is a courtesy of Hogan Lovells (Luxembourg) LLP. Hogan Lovells (Luxembourg) LLP advises in all types of corporate transactions, from
More informationWill Rising Interest Rates Pummel Your Portfolio?
Will Rising Interest Rates Pummel Your Portfolio? ULI Fall Meeting Chicago - November 2013 Dr. Richard Barkham, MRICS Global Research Director, Grosvenor Group Eileen Marrinan, CRE Director of Research,
More informationGuide to becoming a self-employed lawyer
Guide to becoming a self-employed lawyer 2 Contents Legal consulting a new way of thinking 4 Peerpoint the right choice for you? 5 The basics of self-employment 6 Setting up and running a PSC 7 What next?
More informationThe Cost of Capital Navigator. The New Online Resource for Estimating Cost of Capital
The Cost of Capital Navigator The New Online Resource for Estimating Cost of Capital DUFF & PHELPS Duff & Phelps is the global advisor that protects, restores and maximizes value for clients in the areas
More informationGood Oil Conference 2015 Shareholder activism. Clare Pope and Simon Rear
Good Oil Conference 2015 Shareholder activism Clare Pope and Simon Rear Overview of presentation The development of shareholder activism in Australia The objectives of shareholder activists Assessing whether
More informationSuccessful Dealmaking in Today s Challenging Environment: What you need to know
Hogan & Hartson in partnership with the Association of Corporate Counsel Europe Successful Dealmaking in Today s Challenging Environment: What you need to know Tuesday, April 13, 2010 Hogan & Hartson L.L.P.
More informationChina's new foreign exchange controls create fresh concerns. September 2017
China's new foreign exchange controls create fresh concerns September 2017 Contents Background 1 Current account v capital account transactions 1 Why has China imposed the new controls? 1 What do the new
More informationItaly inbound: look no further. Foreign direct investments in Italy
Italy inbound: look no further Foreign direct investments in Italy Research highlights November 2017 2 Hogan Lovells Introduction As a global law firm with Italian roots, we have a keen interest in the
More informationWhy choose us? United States.
Why choose us? United States 2 Why choose us? Our New York and Washington, D.C. offices Covering North America from the financial and regulatory hubs of the United States They are very hardworking and
More informationOur International Disputes experience in Africa
Our International Disputes experience in Africa April 2016 Hogan Lovells 2 Further information If you would like further information relating to our international disputes capabilities in Africa please
More informationPensions Group. Employment & Benefits.
Pensions Group Employment & Benefits www.allenovery.com 2 Pensions Group Employment & Benefits Highly regarded team of pensions specialists with notable strength in handling the full range of pensions
More informationUnitranche On the up, down under 2017
Unitranche On the up, down under 2017 Unitranche on the up, down under 2017 3 Unitranche facilities have been a feature of the European and U.S. markets for a number of years, and have recently been making
More informationEfficient use of orbit/spectrum by satellite systems - the impact of fees
Efficient use of orbit/spectrum by satellite systems - the impact of fees BR Workshop on the efficient use of the spectrum/orbit resource Gerry Oberst 6 May 2009 Hogan & Hartson LLP. All rights reserved.
More informationClient Alert. Amendments to the Prospectus and Transparency Directives. Summary of Key Changes
Number 1121 18 January 2011 Client Alert Latham & Watkins Finance Department Amendments to the Prospectus and Transparency Directives Wholesale debt issuers should pay particular attention to the limited
More informationThe SCA approves Regulations concerning Securities Lending and Borrowing, Short Selling, Market Making and Liquidity Providers
Briefing note October 2012 The SCA approves Regulations concerning Securities Lending and Borrowing, Short Selling, Market Making and The UAE Securities and Commodities Authority (the "SCA") has issued
More informationCompetition law in Singapore JANUARY. Contents Introduction 1. The Competition Act 1. Section 34 anti-competitive agreements and practices 1
JANUARY 2015 Competition law in Singapore Contents Introduction 1 The Competition Act 1 Section 34 anti-competitive agreements and practices 1 Section 47 - monopolies and abuse of dominant market position
More informationTAXING CAPITAL GAINS MADE BY NON- RESIDENTS DISPOSING OF UK COMMERCIAL AND RESIDENTIAL PROPERTY FROM APRIL A BOMBSHELL
Changes at a glance The Government has announced that from April 2019 tax will be charged on gains made by non-residents on the disposal of all types of UK real estate, extending existing charges that
More informationRestructuring Across Borders
September 2017 Restructuring Across Borders Cayman Islands: corporate restructuring and insolvency procedures Contents Introduction 2 Enforcement of security 3 Receivership 3 Schemes of arrangement 3 Provisional
More informationEnterprise Management Incentives ("EMI")
Enterprise Management Incentives ("EMI") Introduction The EMI is a tax qualified discretionary share option arrangement aimed at small growing companies to help them recruit and retain employees in the
More informationMitigating the Growing Risk Posed by the FCPA and Global Anti-Bribery Regulations
Mitigating the Growing Risk Posed by the FCPA and Global Anti-Bribery Regulations Prepared for the 4 th Annual FDA Regulatory Symposium September 30, 2009 Presented by: Stuart M. Altman Partner, Hogan
More informationCypressEnergyPartners,L.P.
UNITEDSTATES SECURITIESANDEXCHANGECOMMISSION Washington,D.C.20549 FORM8-K CURRENTREPORT PURSUANTTOSECTION13OR15(D) OFTHESECURITIESEXCHANGEACTOF1934 DateofReport(Dateofearliesteventreported):March23,2017
More informationClient Alert. Recent Changes to CONSOB Rules on Cash Tender Offers and Exchange Offers for Debt Securities Extended into Italy
Number 1230 6 September 2011 Client Alert Latham & Watkins Corporate Department Recent Changes to CONSOB Rules on Cash Tender Offers and Exchange Offers for Debt Securities Extended into Italy Recent changes
More information