Chapter 1. The World of Project Management. MEM 612 Project Management
|
|
- Cody Nicholson
- 6 years ago
- Views:
Transcription
1 Chapter 1 The World of Project Management
2 WHAT IS A PROJECT?
3 Why the emphasis on project management? Many tasks do not fit neatly into businessas-usual. Need to assign responsibility and authority for achievement of organizational goals.
4 Characteristics of Projects Unique Specific Deliverable Specific Due Date
5 Other Common Characteristics of Projects Multidisciplinary Complex Conflict Part of Programs
6 PMI Definition A temporary endeavor undertaken to create a unique product or service Project Management Institute, 2000
7 PROJECT MANAGEMENT VS. GENERAL MANAGEMENT
8 Skill Requirements for Effective Project Management Conflict Resolution Creativity and Flexibility Ability to Adjust to Change Good Planning Negotiation win-win versus win-lose
9 WHAT IS MANAGED? THE THREE GOALS OF A PROJECT
10 Figure 1-1: Performance, Cost, and Time Project Targets
11 THE LIFE CYCLES OF PROJECTS
12 Figure 1-2 The Project Life Cycle
13 Figure 1-3 An Alternate Project Life Cycle
14 SELECTING PROJECTS
15 Nonnumeric Selection Methods The Sacred Cow The Operating/Competitive Necessity Comparative Benefits
16 Figure 1-4 The Q-Sort Method
17 Numeric Selection Methods Financial Assessment Methods payback period discounted cash flow Scoring Methods unweighted 0-1 factor method weighted factor scoring method
18 Payback Period Initial Fixed Investment Annual Net Cash Inflows
19 Discounted Cash Flow where NPV (project) = - I 0 + n t= 1 (1 + Ft k ) t I 0 = the initial investment F t = the net cash flow in period t k = the required rate of return or hurdle rate
20 The Weighted Scoring Model S i = n j= 1 s ij w j where S i = the total score of the i th project s ij = the score of the i th project on the j th criterion w j = the weight or importance of the j th criterion
21 Confronting Uncertainty The Management of Risk
22 What uncertainties are encountered in project management? Time required to complete a project Availability of key resources Cost of resources Timing of solutions to technological problems Actions taken by competitors
23 Can uncertainty surrounding projects ever be eliminated? No, but it can be managed
24 Risk Analysis Estimate probabilities or distributions associated with key parameters Develop analytic or simulation model Analyze distribution of outcomes generated by model
25 Risk Analysis with Crystal Ball Assumption Cells Distribution Gallery Forecast Cells
26 THE PROJECT PORTFOLIO PROCESS
27 The Project Portfolio Process Step 1: Establish a Project Council Step 2: Identify Project Categories and Criteria Step 3: Collect Project Data Step 4: Assess Resource Availability Step 5: Reduce the Project and Criteria Set Step 6: Prioritize the Projects within Categories Step 7: Select the Projects to be Funded and Held in Reserve Step 8: Implement the Process
28 The Aggregate Project Plan
29 Figure 1-12 An Example Aggregate Project Plan
30 Chapter 2 The Manager, the Organization, and the Team
31 THE PM S ROLES
32 Facilitator Manager-as-supervisor versus manageras-facilitator Systems approach versus analytical approach Suboptimization Must ensure project team members have appropriate knowledge and resources Micromanagement
33 Communicator Figure 2-1 Communication Paths Between a Project s Parties-At-Interest
34 Virtual Project Manager Geographically dispersed projects Communication via Web Telephone Video conferencing Never let the boss be surprised!
35 THE PM S RESPONSIBILITIES TO THE PROJECT
36 Three Overriding Responsibilities Acquiring resources Getting necessary quantity and quality can be key challenge Irrational optimism Fighting fires and obstacles Leadership and making trade-offs
37 Negotiation, Conflict Resolution, and Persuasion Necessary to meet three overriding responsibilities
38 SELECTION OF A PROJECT MANAGER
39 Key Criteria Credibility - The PM is believable technical credibility administrative credibility Sensitivity - Politically astute and aware of interpersonal conflict Leadership, Style, Ethics - Ability to direct project in ethical manner
40 PROJECT MANAGEMENT AS A PROFESSION
41 Project Management as a Profession Project Management Institute More than 64,000 members Project Management Body of Knowledge (PMBOK) Project-oriented organization
42 FITTING PROJECTS IN THE PARENT ORGANIZATION
43 More on Why Projects? Emphasis on time-to-market Need for specialized knowledge from a variety of areas Explosive rate of technological change Accountability and control
44 Figure 2-2 The Pure Project Organization
45 The Pure Project Organization Advantages Effective and efficient for large projects Resources available as needed Broad range of specialists short lines of communication Drawbacks Expensive for small projects Specialists may have limited technological depth May require high levels of duplication for certain specialties
46 Figure 2-3 Functional Project Organization
47 Functional Project Organization Advantages technological depth Drawbacks lines of communication outside functional department slow technological breadth project rarely given high priority
48 Figure 2-4 Matrix Project Organization
49 Matrix Project Organization Advantages flexibility in way it can interface with parent organization strong focus on the project itself contact with functional groups minimizes projectitis ability to manage fundamental trade-offs across several projects Drawbacks violation of the unity of command principle complexity of managing full set of projects conflict
50 Figure 2-5 Mixed Project Organization
51 THE PROJECT TEAM
52 Characteristics of Effective Project Team Members Technically competent Politically sensitive Problem orientation Goal orientation High self-esteem
53 Matrix Team Problems Weak (functional) matrix PM has no direct reports Ability to communicate directly with team members important Matrix projects Important to maintain good morale Project office
54 Intrateam Conflict Life cycle phase and source of conflict Name-only team Interpersonal conflict
55 Chapter 3 Planning the Project
56 Two Extremes Ready, Fire, Aim Paralysis by Analysis
57 CONTENTS OF A PROJECT PLAN
58 Elements of Project Master Plan Overview brief description of project deliverables milestones expected profitability and competitive impact intended for senior management Objectives detailed description of project s deliverables project mission statement
59 Elements of Project Master Plan continued General approach technical and managerial approaches relationship to other projects deviations from standard practices Contractual aspects agreements with clients and third parties reporting requirements technical specifications project review dates
60 Elements of Project Master Plan continued Schedules outline of all schedules and milestones Resource requirements estimated project expenses overhead and fixed charges Personnel special skill requirements necessary training legal requirements
61 Elements of Project Master Plan concluded Evaluation methods evaluation procedures and standards procedures for monitoring, collecting, and storing data on project performance Potential problems list of likely potential problems
62 THE PLANNING PROCESS
63 PM s First Job Understand the expectations that the organization has for the project. Identify who among senior managers has a major interest in the project. Determine if anything about the project is atypical.
64 Developing Invitation List At least one representative from senior management. Managers from functional areas that will contribute to the project. Perhaps highly specialized technical experts.
65 The Launch Meeting Senior management introduces PM PM chairs meeting develop general understanding of the functional inputs the project will need may brainstorm the problem may develop preliminary plan Important results scope understood and temporarily fixed functional managers understand their responsibilities and have committed to developing the initial plan
66 Sorting Out the Project Hierarchical planning process begin with project s objectives list major activities needed to achieve objectives (level 1 activities) delegate level 1 activities to individuals or functional areas to develop list of level 2 activities degree of detail should be same within a given level
67 Three Levels of Detail in Hierarchical Planning
68 The Project Action Plan Project activities identified and arranged in successively finer detail (by levels). Type and quantity of each required resource identified for each activity. Predecessors and durations estimated for each activity. Milestones identified. Individual or group assigned to perform the work identified for all activities.
69 Using the Project Action Plan Project master schedule created by combining milestones, durations, and predecessors used to compare actual and planned performance Use of templates
70 THE WORK BREAKDOWN STRUCTURE
71 Simple Approach for Creating the WBS Gather project team Provide team members with pad of stickynotes Team members write down all tasks they can think of. Sticky-notes placed and arranged on wall
72 A Partial WBS (Gozinto Chart) for an Annual Tribute Dinner Project
73 A Linear Responsibility Chart
74 MULTIDISCIPLINARY TEAMS - - BALANCING PLEASURE AND PAIN
75 Concurrent Engineering Carrying out steps concurrently rather than sequentially also referred to as simultaneous engineering Key advantages helps minimize conflict across functional groups reduces project duration
76 Interface Coordination -- Interface Management Key challenge facing PM is coordinating work of different functional groups. One approach is to identify and map the interdependencies between members of the project team.
77 An Interface Mapping of a Silicon Chip Design Project
78 A Coordination Structure Model for Project Management
79 Design Structure Matrix (DSM) Traditional project management tools tend to focus on which tasks have to be completed in order for other to start Another important question is what information is needed from other tasks to complete another task
80 Example DSM for Project with Six Activities a b c d e f a b X X c X X d X X X e X f X X X X -- information flow
81 Modified DSM to Show Activities to Be Completed Concurrently a b c d e f a b X O c X O d X X X e X f X X X tasks to be completed concurrently X -- information flow O -- potential rework situation
82 Comments on Empowerment and Work Teams Participatory management Success of empowered teams depends heavily on how team program implemented
83 Advantages of Empowerment High quality solutions Avoid micromanagement Team has accountability for part of project deliverable Synergistic solutions Tool for timely evaluation and feedback
84 Chapter 4 Budgeting the Project
85 Introduction Budgets are plans for allocating organizational resources to project activities. forecasting required resources, quantities needed, when needed, and costs Budgets help tie project to overall organizational objectives. Budgets can be used as tool by upper management to monitor and guide projects.
86 METHODS OF BUDGETING
87 Top-Down Budgeting Based on collective judgements and experiences of top and middle managers. Overall project cost estimated by estimating costs of major tasks Advantages accuracy of estimating overall budget errors in funding small tasks need not be individually identified
88 Bottom-Up Budgeting WBS or action plan identifies elemental tasks Those responsible for executing these tasks estimate resource requirements Advantage more accurate in the detailed tasks Disadvantage risk of overlooking tasks
89 COST ESTIMATING
90 Work Element Costing Determine resource requirements and then costs for each task costs (e.g., materials) labor time labor rate equipment time equipment rate overhead GS&A
91 The Impact of Budget Cuts Two project life cycles
92 Activity Versus Program Budgeting Activity oriented budgets are based on historical data accumulated through an activity-based accounting system. expenses assigned to basic budget lines With program budgets, each project has its own budget. expenses by task and time period are shown
93 IMPROVING COST ESTIMATES
94 Learning Curves where T = T n 1 T n = the time required to complete the n th unit T 1 = the time required to complete the first unit n r = log(learning rate)/log(2) r
95 Tracking Signals Used to determine if there is a systematic bias in cost or other estimates
96 Other Factors Changes in resource prices Increase all estimates by same percentage Estimate rate of price change individually for inputs that have significant impact on costs Waste and spoilage Team member turnover Mythical man-month Organization climate
97 BUDGET UNCERTAINTY AND RISK MANAGEMENT
98 Estimate of Project Cost: Estimate Made at Project Start
99 Three Basic Causes for Change in Projects Errors made by cost estimator about how to achieve tasks. New knowledge about the nature of the performance goal or setting. A mandate.
100 Risk Management Risk Management Planning Risk Identification Qualitative Risk Analysis Risk Response Planning Risk Monitoring and Control
101 Failure Mode and Effect Analysis (FMEA) List ways project might fail Evaluate severity (S) of each failure Estimate likelihood (L) of each failure occurring Estimate ability to detect each failure (D) Calculate Risk Priority Number (RPN) Sort potential failures by their RPNs
102 Other Approaches Game theory Expected value Simulation
103 Chapter 5 Scheduling the Project
104 PERT AND CPM NETWORKS
105 History Late 1950s Program Evaluation and Review Technique (PERT) U.S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft Probabilistic activity durations Critical Path Method (CPM) Dupont De Nemours Inc. Deterministic activity durations
106 The Language of PERT/CPM Activity task or set of tasks use resources Event state resulting from completion of one or more activities consume no resources or time predecessor activities must be completed
107 The Language of PERT/CPM continued Milestones events that mark significant progress Network diagram of nodes and arcs used to illustrate technological relationships Path series of connected activities between two events
108 The Language of PERT/CPM concluded Critical Path set of activities on a path that if delayed will delay completion of project Critical Time time required to complete all activities on the critical path
109 Building the Network AOA Network AON Network
110 Table 5-1 A Sample Set of Project Activities and Precedences Task Predecessor a -- b -- c d e f g a b b c, d e
111 Figure 5-1 Stage 1 of a Sample AON Network
112 Figure 5-2 Stage 2 of a Sample AON Network
113 Figure 5-3 A Completed Sample AON Network
114 Figure 5-4 Stage 1 of a Sample AOA Network
115 Figure 5-5 Stage 2 of a Sample AOA Network
116 Figure 5-6a A Completed Sample AOA Network
117 Figure 5-6b A Completed Sample AOA Network Showing the Use of a Dummy Task
118 Table 5-2 A Sample Problem for Finding the Critical Path and Critical Time Activity Predecessor Duration a -- 5 days b -- 4 c a 3 d a 4 e a 6 f b, c 4 g d 5 h d, e 6 i f 6 j g, h 4
119 Figure 5-7 Stage 1 of a Sample Network
120 Figure 5-8 A Complete Network
121 Figure 5-9 Information Contents in an AON Node
122 Figure 5-10 The Critical Path and Time for Sample Project
123 Calculating Activity Slack Slack or Float LST - EST = LFT - EFT = Slack
124 Figure 5-11 An MSP Version of PERT/CPM Network
125 Figure 5-12 A Modified Version of MSP Network
126 PROJECT UNCERTAINTY AND RISK MANAGEMENT
127 Calculating Probabilistic Activity Times Three Time Estimates pessimistic (a) most likely (m) optimistic (b)
128 Figure 5-13 The Statistical Distribution of all Possible Times for an Activity
129 Activity Expected Time and Variance T E = ( a + 4m 6 + b) σ = ( b 6 a) Var = σ 2 ( b = 6 a) 2
130 95 Percent Level Task will be a or lower 5 percent of the time Task will be b or greater 5 percent of the time σ = ( b a) 3.3
131 90 Percent Level Task will be a or lower 10 percent of the time Task will be b or greater 10 percent of the time σ = ( b a) 2.6
132 95 Percent Level (Alternative Interpretation) Task will be between a and b 95 percent of the time σ = ( b a) 3.92
133 90 Percent Level (Alternative Interpretation) Task will be between a and b 90 percent of the time σ = ( b a) 3.29
134 Figure 5-14 An AON Network
135 Figure 5-15 An MSP Version of a Sample Problem Network
136 Figure 5-16 A Pert/CPM Network for the Day Care Project
137 Figure 5-17 An MSP Calendar for the Day Care Project, 4/16/00 to 5/27/00
138 The Probability of Completing the Project on Time Z ( ) = D µ σ 2 µ =NORMDIST(D,µ,σ µ,true)
139 Figure 5-18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h
140 Selecting Risk and Finding D D = µ + Z 2 σ µ NORMINV(probability,µ,σ µ,true)
141 SIMULATION
142 Traditional Statistics Versus Simulation Similarities must enumerate alternate paths Differences simulation does not require assumption of path independence
143 THE GANNT CHART
144 Figure 5-23 A Gantt Chart of a Sample Project
145 Figure 5-24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT
146 Figure 5-25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements
147 Figure 5-26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline
148 EXTENSIONS TO PERT/CPM
149 Precedence Diagramming Finish-to-start linkage Start-to-start linkage Finish-to-finish linkage Start-to-finish linkage
150 Figure 5-27 Precedence Diagramming Conventions
151 Other Methods Graphical Evaluation and Review Technique (GERT) combines flowgraphs, probabilistic networks, and decision trees allows loops back to earlier events and probabilistic branching
152 Chapter 6 Allocating Resources to the Project
153 Introduction Projects Compete With One Another for Resources resources that are not consumed resources that are consumed Goal of Resource Allocation is to Optimize Use of Limited Supply Requires making trade-offs time constrained resource constrained
154 EXPEDITING A PROJECT
155 The Critical Path Method Normal Duration Estimates Normal Costs Crash Duration Estimates Crash Costs Crash Cost Per Day Normal Duration - Crash Duration Crash Cost - Normal Cost
156 Figure 6-1(a) Gantt Chart Crash Problem Day Project
157 Figure 6-1(b) AON Network for Sample Crash Problem Day Project
158 Figure 6-2 Gantt Chart for 20- Day Solution to Crash Problem
159 Figure 6-3 Gantt Chart for 19- Day Solution to Crash Problem
160 Figure 6-4 Gantt Chart for 18- Day Solution to Crash Problem
161 Figure 6-5 Gantt Chart for 16- Day Solution to Crash Problem
162 Figure 6-6 Project Cost Versus Project Duration for Sample Crash Problem
163 Probabilistic Activity Durations Three time estimates made for both normal resource loading and crash resource loading Variance of normal activity may be different than variance of crash time
164 Using Excel s Solver to Crash a Project Target Cell minimize crashing costs By Changing Cells amount to crash activities time events occur Constraints amount each activity can be crashed precedence relationships complete project by specified time nonnegativity
165 Figure 6-7 AOA Network of Sample Crash Problem
166 Figure 6-9 Cost/Duration Graph for Sample Crashing Project
167 Fast-Tracking a Project Used Primarily in Construction Industry Building phase started before design and planning phases completed Particularly appropriate when large proportion of work is routine
168 RESOURCE LOADING
169 Resource Loading Amount of specific resources that are scheduled for use on specific activities or projects at specific times. Usually a list or table.
170 Figure 6-10 Action Plan and Gantt Chart for Production of a Videotape
171 The Charismatic VP Subordinates have hard time saying no to well liked boss. Leads to overcommitted subordinates. Problem further compounded because more experienced workers tend to be most over worked. One solution is to set specific limits on amount of overscheduling permitted.
172 RESOURCE LEVELING
173 Figure 6-11 Gantt Chart for Videotape Project, Adjusted for Client Availability
174 Figure 6-12 Resource Overallocation Report for Scriptwriter Showing all Activities
175 Figure 6-13 Graphic Resource Overallocation Report for Scriptwriter
176 Figure 6-14 Resource Leveled Report for Scriptwriter Showing all Activities
177 Figure 6-15 Graphic Resource Leveled Report for Scriptwriter
178 Figure 6-16 Daily Resource Loading Chart for Videotape Project, Scriptwriter Leveled
179 Figure 6-17 Final Videotape Project Gantt Chart Schedule, With Two Scriptwriters and Producer Leveled
180 Resource Loading/Leveling and Uncertainty 28,282 Hours Needed Group Capacity 21 (people) 40 (hrs/wk) 34 wk = 28,560 labor hrs Correction for Holidays 21 3 (days) 8 (hours) = 504 labor hrs Vacations 11 2 (weeks) 40 = 880 labor hrs
181 Resource Loading/Leveling and Uncertainty continued Hours Available 28, = 27,176 about 1100 less than needed 28,282/27176 = 1.04 What about Workers getting sick? Task not ready when worker is ready? Change orders?
182 Figure 6-18 Thirty-Four-Week Resource Loading Chart for a Software Engineering Group
183 ALLOCATING SCARCE RESOURCES TO PROJECTS
184 Use of Software Begin with Pert/CPM Schedule Activities examined period by period and resource by resource In cases where demand for resource exceeds supply, tasks considered one by one and resources assigned to these tasks based on priority rules
185 Some Comments about Constrained Resources Scarcity of resources rarely applies to resources in general Walts
186 Some Priority Rules As soon as possible As late as possible Shortest task duration first Minimum slack first Most critical followers Most successor Most resources first
187 Choosing a Priority Rule Schedule Slippage amount project or set of projects delayed Resource Utilization extent that resources are over or underworked In-Process Inventory amount of unfinished work in the system
188 ALLOCATING SCARCE RESOURCES TO SEVERAL PROJECTS
189 Pseudoactivities Used to link several project together Have duration but do not require any resources This approach allows a set of projects to be dealt with as though it were a single project use of MSP s resource loading and leveling charts and tables
190 Figure 6-19 Multiple Projects Connected with Pseudoactivities Shown on a Time Line
191 Resource Allocation and the Project Life Cycle Figure 6-20 Project or task life cycles
192 GOLDRATT S CRITICAL CHAIN
193 Introduction Similar issues that trouble people about working on projects regardless of type of project unrealistic due dates too many changes resources and data not available unrealistic budget These issues/problems related to need to make trade-offs To what extent are these problems caused by human decisions and practices?
194 Figure 6-21 Three Project Scenarios
195 Table 6-6 Project Completion Time Statistics Based on Simulating Three Projects 200 Times Scenario 1 Scenario 2 Scenario 3 Average Std Dev Max Min Median
196 Observations Average Completion Times Implications of Assuming Known Activity Times Shape of the Distribution Worker Time Estimates Impact of Inflated Time Estimates Student Syndrome
197 Multitasking Figure 6-24 Two Small Projects
198 Figure 6-25 Alternative Gantt Charts for Projects A and B
199 Common Chain of Events Underestimate time needed to complete project assumption of known activity times and independent paths Project team members inflate time estimates Work fills available time student syndrome early completions not reported
200 Common Chain of Events continued Safety time misused Misused safety time results in missed deadlines Hidden safety time complicates task of prioritizing project activities Lack of clear priorities results in poor multitasking
201 Common Chain of Events concluded Poor multitasking increases task durations Uneven demand on resources also results due to poor multitasking More projects undertaken to ensure all resources fully utilized More projects further increases poor multitasking
202 Reversing the Cycle Reduce number of projects assigned to each individual Schedule start of new projects based on availability of bottleneck resources Reduce amount of safety time added to individual tasks and then add some fraction back as project buffer activity durations set so that there is a high probability the task will not be finished on time
203 The Critical Chain Longest chain of consecutively dependent events considers both precedence relationships and resource dependencies Project Buffer Feeding Buffer
204 Figure 6-26 Sample Network Diagram
205 Figure 6-27 Project and Feeder Buffers
206 Chapter 7 Monitoring and Controlling the Project
207 Introduction Monitoring and Control are opposite sides of selection and planning bases for selection dictate what to monitor plans identify elements to control Monitoring is collection, recording, and reporting of information Control uses monitored information to align actual performance with the plan
208 THE PLAN-MONITOR- CONTROL CYCLE
209 Plan-Monitor-Control Cycle Closed loop process Planning-monitoring-controlling effort often minimized to spend time on the real work
210 Figure 7-1 Project Authorization and Expenditure Control System Information Flow
211 Designing the Monitoring System Identify special characteristics of performance, cost, and time that need to be controlled performance characteristics should be set for each level of detail in the project Real-time data should be collected and compared against plans mechanisms to collect this data must be designed Avoid tendency to focus on easily collected data
212 DATA COLLECTION AND REPORTING
213 Formats of Data Frequency Counts Raw Numbers Subjective Numeric Ratings Indicators and Surrogates Verbal Characterizations
214 Data Analysis Aggregation Techniques Fitting Statistical Distributions Curve Fitting Quality Management Techniques
215 Figure 7-2 Number of Bugs per Unit of Test Time
216 Figure 7-3 Percent of Specified Performance Met During Successive Repeated Trials
217 Figure 7-4 Ratio of Actual Material Cost to Estimated Material Cost
218 Reporting Reports Project Status Reports Time/Cost Reports Variance Reports Not all stakeholders need to receive same information Avoid periodic reports Impact of Electronic Media Relationship between project s information system and overall organization s information system
219 Report Types Routine Exception Special Analysis
220 Meeting Guidelines Meetings should be help primarily for group decision making avoid weekly progress report meetings Distribute written agenda in advance of meeting
221 Meeting Guidelines continued Ensure everyone is properly prepared for meeting Chair of meeting should take minutes avoid attributing remarks to individuals in the minutes Avoid excessive formality If meeting is held to address specific crisis, restrict meeting to this issue alone
222 Virtual Reports, Meetings, and Project Management Use of the Internet Use of Software Programs Virtual Project Teams
223 EARNED VALUE
224 Earned Value task budgeted cost all tasks task % completition Percent of task s budget actually spent not good indicator of percent completion
225 Conventions Used to Estimate Progress on Tasks % complete when task started and other 50% added when task finished 100% 100% complete when finished and zero percent before that Ratio of Cost Expended to Cost Budgeted
226 Variances Cost/Spending Variance EV - AC Schedule Variance EV - PV CPI EV/AC SPI EV/PV
227 Additional Items of Interest Estimated (Remaining Cost) to Completion ETC = (BAC - EV)/CPI (Total Cost) Estimated at Completion EAC = ETC + AC
228 PROJECT CONTROL
229 Background Acts which seek to reduce differences between plan and actuality Difficult Task human behavior involved problems rarely clear cut
230 Purposes of Control Stewardship of Organizational Assets physical asset control human resources financial control Regulation of Results Through the Alteration of Activities
231 DESIGNING THE CONTROL SYSTEM
232 Background Purpose is to correct errors, not punish the guilty Investments in control subject to diminishing returns Must consider impact on creativity and innovation Be careful not emphasize short-run results at the expense of long-run objectives Dangers of across the board cuts
233 Primary Mechanisms by Which PM Exerts Control Process Reviews Personnel Assignments Resource Allocations
234 Components of a Control System Sensor Standard Comparator Decision Maker Effector
235 Types of Control Systems Go/No-Go Controls predetermined standard must be met for permission to be granted to continue Post-Control done after project completed purpose is to allow future projects to learn from past project experience
236 Figure 7-7 Sample Project Milestone Status Report
237 Tools for Control Variance Analysis Trend Projections Earned Value Analysis Critical Ratio actual progress scheduled progress budgeted cost actual cost
238 Figure 7-8 Trend Projection
239 Figure 7-9 Critical Ratios with Control Limits
240 Figure 7-10 Cost Control Chart
241 SCOPE CREEP AND CHANGE CONTROL
242 Scope Creep Coping with changes frequently cited by PMs as the single most important problem Common Reasons for Change Requests Client Availability of new technologies and materials
243 Purpose of Change Control System Review all requested changes Identify impact of change Evaluate advantages and disadvantages of requested change Install process so that individual with authority may accept or reject changes
244 Purpose of Change Control System continued Communicate change to concerned parties Ensure changes implemented properly Prepare reports that summarize changes made to date and their impact
245 Rules for Controlling Scope Creep Include in contract change control system Require all changes be introduced by a change order Require approval in writing by the client s agent and senior management Consult with PM prior to preparation of change order Amend master plan to reflect changes
246 Chapter 8 Evaluating and Terminating the Project
247 EVALUATION
248 Background A project evaluation appraises the progress and performance relative to the project s initial or revised plan. Also appraises project against goals and objectives set for it during selection process. Projects should be evaluated at a number of crucial points. Purpose is to improve process of carrying out project.
249 Evaluation Criteria Original criteria for selecting and funding project Success to date Business/Direct Success Future Potential Contribution to Organization s Goals Contribution to Team Member Objectives
250 Measurement Measuring performance against planned budgets and schedules straightforward Earned value analysis more complicated
251 PROJECT AUDITING
252 The Audit Process Timing depends on purpose Three Levels general audit detailed audit technical audit
253 Steps in Project Audit Familiarize audit team with requirements of project Audit project on-site Write up audit report Distribute report
254 Behavior Aspects Audit team must have free access to anyone with knowledge of the project Project team members rarely trust auditors Audit team must understand politics of project team Information must be confirmed Project team should be made award of inprocess audit No judgmental comments
255 The Audit Report Introduction description of project and its goals Current Status comparison of work completed and planned Future Project Status conclusions regarding project progress recommendations for changes
256 The Audit Report continued Critical Management Issues issues senior management should monitor Risk Analysis and Risk Management potential for project failure and monetary loss Final Comments caveats, assumptions, limitations
257 PROEJCT TERMINATION
258 When to Terminate a Project Sunk Cost Approach whether organization is willing to invest the time and cost required to complete the project Two Other Criteria the degree to which the project has met its goals the degree to which the project qualifies against a set of factors associated with success or failure
259 Types of Project Termination Project Extinction project activity suddenly stops either successfully completed or high expectation for failure Termination-By-Addition becomes a new formal part of organization Termination-By-Integration becomes standard part of operating systems
260 Types of Project Termination continued Termination-By-Starvation a project in name only
261 The Termination Process Decision made by broad based committee of senior managers Termination process should be specified in project plan Termination manager
262 Figure 8-3 A Termination Project
263 The Project Final Report Project Performance what was achieved and reasons for resulting performance Administrative Performance review of how well administrative practices worked Organizational Structure identify modifications to help future projects
264 The Project Final Report continued Project Management Techniques recommendations for improvements in future projects
PROJECT MANAGEMENT IN PRACTICE
PROJECT MANAGEMENT IN PRACTICE Fourth Edition Samuel J. Mantel, Jr. University of Cincinnati Jack R. Meredith Wake Forest University Scott M. Shafer Wake Forest University Margaret M. Sutton button Associates
More informationProject Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams
Project Planning Identifying the Work to Be Done Activity Sequencing Network Diagrams Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure Be able
More informationInternational Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ
International Project Management prof.dr MILOŠ D. MILOVANČEVIĆ Project time management Project cost management Time in project management process Time is a valuable resource. It is also the scarcest. Time
More informationProject Management Professional (PMP) Exam Prep Course 06 - Project Time Management
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com
More informationMS Project 2007 Page 1 of 18
MS Project 2007 Page 1 of 18 PROJECT MANAGEMENT (PM):- There are powerful environment forces contributed to the rapid expansion of the projects and project management approaches to the business problems
More informationProject planning and creating a WBS
37E01500 Project Management and Consulting Practice Project planning and creating a WBS Matti Rossi Lecture 3, Tue 28.2.2017 Learning objectives Describe the project time management planning tasks, and
More informationReal-World Project Management. Chapter 15
Real-World Project Chapter 15 Characteristics of Project Unique one-time focus Difficulties arise from originality Subject to uncertainties Unexplained or unplanned events often arise, affecting resources,
More informationUNIT-II Project Organization and Scheduling Project Element
UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite
More informationProject Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark
Project Planning jesla@man.dtu.dk Department of Management Engineering Technical University of Denmark 1 Project Management Project Management is a set of techniques that helps management manage large-scale
More informationOutline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling
Project Management Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling Outline - Continued Project Management Techniques:
More informationCOPYRIGHTED MATERIAL. Index
Index Note to the reader: Throughout this index boldfaced page numbers indicate primary discussions of a topic. Italicized page numbers indicate illustrations. A A+ certification, 28 acceptance criteria
More informationSCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016
All Rights Reserved No. of Pages - 10 No of Questions - 06 SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016 MGT 30725 Project
More informationTextbook: pp Chapter 11: Project Management
1 Textbook: pp. 405-444 Chapter 11: Project Management 2 Learning Objectives After completing this chapter, students will be able to: Understand how to plan, monitor, and control projects with the use
More informationIntroduction to Project Management. Modeling after NYS ITS
Introduction to Project Management Modeling after NYS ITS What is Project Management? Project management is the application of knowledge, skills, tools and techniques to project activities to meet project
More informationRisk Video #1. Video 1 Recap
Risk Video #1 Video 1 Recap 1 Risk Video #2 Video 2 Recap 2 Risk Video #3 Risk Risk Management Process Uncertain or chance events that planning can not overcome or control. Risk Management A proactive
More informationSCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited
SCHEDULE CREATION AND ANALYSIS 1 www.pmtutor.org Powered by POeT Solvers Limited While building the project schedule, we need to consider all risk factors, assumptions and constraints imposed on the project
More informationThe Project Times and Costs
The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step
More informationAgenda. Projektledning. Why the emphasis on project management? How are we doing so far? What is a project? Gunnar Wettergren
Agenda What is a project? Why is it important? Life cycle Roles/Management People Planning & Budgets Resources and Scheduling Risks Projektledning Gunnar Wettergren Why the emphasis on project management?
More informationAppendix B: Glossary of Project Management Terms
Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances
More informationManagement Management
Project Management Management Management in all business and organizational activities is the act of getting people together to accomplish desired goals and objectives using available resources efficiently
More informationPROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, PMP, PMI-RMP
More informationIntroduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES
Valua%on and pricing (November 5, 2013) LEARNING OBJECTIVES Lecture 12 Project Management Olivier J. de Jong, LL.M., MM., MBA, CFD, CFFA, AA www.olivierdejong.com 1. Understand how to plan, monitor, and
More informationCISC 322 Software Architecture
CISC 22 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan (Edited For Course Presentation, 206) Project A project is a temporary endeavour undertaken to create a "unique" product or service
More informationIP-CIS : CIS Project Management
Meltem Özturan www.mis.boun.edu.tr/ozturan/mis301 1 Project Management Tools and Techniques (PMTT) Feasibility Analysis Organizational Breakdown Structure Work Breakdown Structure Scheduling Earned Value
More informationProject Management Chapter 13
Lecture 12 Project Management Chapter 13 Introduction n Managing large-scale, complicated projects effectively is a difficult problem and the stakes are high. n The first step in planning and scheduling
More informationProject Theft Management,
Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationVendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo
Vendor: PMI Exam Code: CA0-001 Exam Name: Certified Associate in Project Management Version: Demo QUESTION: 1 On what is project baseline development established? A. Approved product requirements B. Estimated
More informationAfter complete studying this chapter, You should be able to
Chapter 10 Project Management Ch10: What Is Project Management? After complete studying this chapter, You should be able to Define key terms like Project, Project Management, Discuss the main characteristics
More informationJAYARAM COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF INFORMATION TECHNOLOGY
JAYARAM COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF INFORMATION TECHNOLOGY Two Mark Question for Student s Reference 1. Define software project management. Software Project Management has key ideas
More informationA convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.
Introduction Any project involves planning, scheduling and controlling a number of interrelated activities with use of limited resources, namely, men, machines, materials, money and time. The projects
More informationu w 1.5 < 0 These two results imply that the utility function is concave.
A person with initial wealth of Rs.1000 has a 20% possibility of getting in a mischance. On the off chance that he gets in a mishap, he will lose Rs.800, abandoning him with Rs.200; on the off chance that
More informationPMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005
PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes
More informationPMI - Dallas Chapter. Sample Questions. March 22, 2002
PMI - Dallas Chapter PMP Exam Sample Questions March 22, 2002 Disclaimer: These questions are intended for study purposes only. Success on these questions is not necessarily predictive of success on the
More informationAllocate and Level Project Resources
Allocate and Level Project Resources Resource Allocation: Defined Resource Allocation is the scheduling of activities and the resources required by those activities while taking into consideration both
More informationINSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.
. Surname, given names: Student Number: INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points This is a closed book exam. Answer all the questions in the booklet. Ensure that your
More informationOutline. Project Management. Introduction. What is a Project?
Outline Project Management Jeffrey Pinto, Ph.D. Penn State Erie What is Project Management? Scope Management Risk Management Planning and Scheduling Project Evaluation and Control Project Termination Introduction
More informationTeori Pengambilan Keputusan. Week 12 Project Management
Teori Pengambilan Keputusan Week 1 Project Management Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM) PERT and CPM Network techniques Developed in 195 s CPM
More informationPROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana
PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT G.N. Sandhy Widyasthana widyasthana@gmail.com 022 70702020 081 225 702020 1 2 3 Process of identifying the specific actions to be performed to produce
More informationPMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved
Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are
More informationINSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.
INSE 6230: Assignment - Winter 208 (0% of final grade). The table below provides information about a short IT project. Activity Predecessors Duration (Months) A - 2 B - 3 C A 4 D A, B 2 E D 2 F B, C, E
More informationPass PMP in 21 Days - ITTO Toolbox PROCESS MAP
PROCESS MAP 1 IntEgratIon Pass PMP in 21 Days - ITTO Toolbox InItIatIng PlannIng ExEcutIng MonItorIng & controlling closing Develop Project Charter Develop Project Management Plan Direct & Manage Project
More informationPMI PMI-SP. PMI Scheduling Professional. Download Full Version :
PMI PMI-SP PMI Scheduling Professional Download Full Version : http://killexams.com/pass4sure/exam-detail/pmi-sp QUESTION: 311 A company hires a scheduler for one of its projects. What skills should he
More informationCONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon
CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,
More informationSystems Engineering. Engineering 101 By Virgilio Gonzalez
Systems Engineering Engineering 101 By Virgilio Gonzalez Systems process What is a System? What is your definition? A system is a construct or collection of different elements that together produce results
More informationMohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators
Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators Profile of Mohammed Rafiuddin Mohammed is an active member of AACE International since 2006 with 30 years of experience
More informationDepartment of Industrial Engineering
Department of Industrial Engineering Engineering Project Management Presented By Dr. Abed Schokry Chapter 15: Cost Control Learning Outcomes After completing this chapter students should be able to: Define
More informationManaging Project Risk DHY
Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or
More informationVALLIAMMAI ENGINEERING COLLEGE
VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF CIVIL ENGINEERING QUESTION BANK VI SEMESTER CE6005 CONSTRUCTION PLANNING AND SCHEDULING Regulation 2013 Academic Year 2017
More informationAdministration. Course Aim. Introductions
Practical Application of Earned Value Performance Measurement presented by Paul E Harris of Eastwood Harris Pty Ltd Copyright Copyright 2010 by Eastwood Harris Pty Ltd. No part of this publication may
More informationProject Management. A Practitioner s Guide. Steven M. Bragg
Project Management A Practitioner s Guide Steven M. Bragg Chapter 1 Overview of Project Management... 1 Learning Objectives... 1 Introduction... 1 Project Management Activities... 1 The Need for Project
More informationAchieve PMP Exam Success Five-Day Course Syllabus
Course Delivery Format: Traditional class room 5-day format, 35 hrs. Achieve PMP Exam Success Five-Day Course Syllabus Course Description: Achieve PMP Exam Success is a 35-hour PMP exam preparation course
More informationProject Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.
Project Mangement ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala. Page 1 of 380 26/4/2008 Syllabus 1. Total Project Management Concept, relationship with other function and other organizations,
More informationTHE PMP EXAM PREP COURSE
THE PMP EXAM PREP COURSE Session 3 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falcontraining.co.nz Agenda 9:00 10:15 10:15 10:30 10:30 12:00 12:00 12:45 12:45
More informationHaeryip Sihombing 1. Risk. Risk Management
Project Management Managing Risk 7 Haeryip Sihombing Universiti Teknikal Malaysia Melaka (UTeM) BMFP 4542 1 2 Risk Management Process The Risk Event Graph Risk Uncertain or chance events that planning
More informationPoor Man s Approach to Monte Carlo
Poor Man s Approach to Monte Carlo Based on the PMI PMBOK Guide Fourth Edition 20 IPDI has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI).
More information2. Which of the following is a common characteristic of most project life cycle descriptions?
INTEGRATION MANAGEMENT 1. The review of key deliverables and project performance at the conclusion of a project phase is called: A. phase exit B. kill point C. stage gate D. a and c E. All above 2. Which
More informationChapter 11 Project Execution and Control
Chapter 11 Project Execution and Control Project Management for Business, Engineering, and Technology Prepared by John Nicholas, Ph.D. Loyola University Chicago Phase C: Project Execution Most projects
More informationFive-Day Schedule and Course Content
Five-Day Schedule and Course Content The following sequence is suggested to balance out the material over five sessions. Note that Chapter 10 is placed with Chapters 12 and 13 on Day 5. DAY 1 DAY 1 Course
More informationProject Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall
Project Management Chapter 2 02-0 1 What is a Project? Project An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of
More informationMaking sense of Schedule Risk Analysis
Making sense of Schedule Risk Analysis John Owen Barbecana Inc. Version 2 December 19, 2014 John Owen - jowen@barbecana.com 2 5 Years managing project controls software in the Oil and Gas industry 28 years
More informationCHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM
CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities
More informationGPE engineering project management. Project Management in an Engineering Context
GPE engineering project management Project Management in an Engineering Context Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities
More informationProject Management Techniques (PMT)
Project Management Techniques (PMT) Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) are 2 main basic techniques used in project management. Example: Construction of a house.
More informationADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS
ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS DAVID T. HULETT, PH.D. 1 HULETT & ASSOCIATES, LLC 1. INTRODUCTION Quantitative schedule risk analysis is becoming acknowledged by many project-oriented organizations
More informationSection II PROJECT MANAGEMENT METHODOLOGY GUIDELINES
Section II B PROJECT MANAGEMENT METHODOLOGY GUIDELINES Chapter 8 INTRODUCTION TO A METHODOLOGY Vision The vision of the Project Management Center of Excellence (PMCoE) organization is to achieve a world-class
More informationPMP Exam Preparation Workshop Chapter 7 Project Cost Management
PMP Exam Preparation Workshop Chapter 7 Project Cost Management 1 Learning Objectives By the end of this session, you should understand: Importance of cost management for the success of a project Cost
More informationProject Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7
Project Management THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Chapter 7 Managing Risk Copyright 2006 The McGraw-Hill Companies. All rights reserved. PowerPoint Presentation by
More informationProject Management -- Developing the Project Plan
Project Management -- Developing the Project Plan Dr. Tai-Yue Wang Department of Industrial and Information Management National Cheng Kung University Tainan, TAIWAN, ROC 1 Where We Are Now 6 2 Developing
More informationProject Risk Management
Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management
More informationConstruction Management
Construction Management 1. Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast 2. Pick up the incorrect
More informationProject Management Fundamentals
Project Management Fundamentals Course No: B04-003 Credit: 4 PDH Najib Gerges, Ph.D., P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)
More informationProject Controls Expo 16 th Nov 2016
Project Controls Expo 16 th Nov 2016 Emirates Stadium, London Introduction to Planning, Scheduling and Earned Value followed by Case Study on Data Analytics on improved Schedule Data Quality Tushar Tohan
More informationProject Integration Management
Project Integration Management The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all of the other knowledge areas throughout a project s life cycle.
More informationProject Integration Management
Project Integration Management Describe an overall framework for project integration management as it relates to the other PM knowledge areas and the project life cycle. Explain the strategic planning
More informationSSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION
1 ` SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL SSC-JE Civil Engineering 2 Estimating, Costing and Valuation : Estimate, Glossary of technical terms, Analysis of rates, Methods and
More informationCost Reduction: Planning & Control. Impacting the Bottom Line
Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/11) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,
More informationAppendix A Decision Support Analysis
Field Manual 100-11 Appendix A Decision Support Analysis Section I: Introduction structure development, and facilities. Modern quantitative methods can greatly facilitate this Complex decisions associated
More informationOptimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT
Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur Lecture - 18 PERT (Refer Slide Time: 00:56) In the last class we completed the C P M critical path analysis
More informationChapter-8 Risk Management
Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not
More informationApplication of Earned Value Management (EVM) for Effective Project Control
Application of Earned Value Management (EVM) for Effective Project Control Course No: B02-012 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education and Development, Inc. 9 Greyridge
More informationChapter 5: Estimating Project Times and Costs 4KF3
Lecture Notes Importance of Estimates Support good decisions Schedule work o Make sure your team members can take on added work of project Determine length of project and costs o Projects can be cancelled
More informationRisk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:
for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:
More informationCrowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001
Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001 CHAPTER 13 Evaluating Product Risks 13.1 Introduction This chapter addresses
More informationCHAPTER 5. Project Scheduling Models
CHAPTER 5 Project Scheduling Models 1 5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project
More informationProject Management Certificate Program
Project Management Certificate Program Risk Management Terry Skaggs ( Denver class) skaggst@centurytel.net 719-783-0880 Lee Varra-Nelson (Fort Collins class) lvarranelson@q.com 970-407-9744 or 970-215-4949
More informationPlan Implementation. Pushpa Lal Shakya
Plan Implementation Pushpa Lal Shakya Outline of Presentation 1. Plan Implementation: Meaning 2. Use of MTEF in Plan Implementation 3. Plan implementation Process and Implementation Modalities 4. Application
More informationLesson 7 The Project Budget
MBA, Msc, Bsc, PMP, CSM, PMI-ACP Indike Manthilake MBA, Msc, Bsc, CSM, PMI-ACP indikem@unitedmotors.lk.com Lesson 7 The Project Budget Agenda Estimate Costs and income Creating a Preliminary Budget Budget
More informationACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.
Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur
More informationPROJECT MANAGEMENT BODY OF KNOWLEDGE
A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK GUIDE ) Sixth edition Chapter 7 Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc Slide # 1 3FOLD Education
More informationThomas Carlos Consulting. Simple Earned Value Management
Thomas Carlos Consulting Simple Earned Value Management Financial analysis that goes one step beyond Budget versus Actual Presented by Tom Carlos, PMP September 11, 2008 Thomas Carlos Consulting, Roseville,
More informationIE 102 Spring Project Management
IE 102 Spring 2018 Project Management 1 Management of Projects Planning - goal setting, defining the project, team organization Scheduling - relates people, money, and supplies to specific activities and
More informationDISCLAIMER. The Institute of Chartered Accountants of India
DISCLAIMER The Suggested Answers hosted in the website do not constitute the basis for evaluation of the students answers in the examination. The answers are prepared by the Faculty of the Board of Studies
More informationConference Paper A New Cost Management Policy for Your Organization: An Integrated Approach Woomi Chase Ken Odom Tom Dauber
Conference Paper A New Cost Management Policy for Your Organization: An Integrated Approach Woomi Chase Ken Odom Tom Dauber Denver, CO June 2014 1 Table Of Contents Introduction Program/Project Structure
More informationProcess Optimization Level I (Introduction)
Process Optimization Level I (Introduction) 8 Hours A hands-on, interactive introduction to Business Process Optimization Focused on the most effective tools & concepts from the many process improvement
More informationTHE CORPORATION OF THE CITY OF WINDSOR POLICY
THE CORPORATION OF THE CITY OF WINDSOR POLICY Service Area: Office of the Chief Administrative Officer Policy No.: CR252/2014 Department: Approval Date: October 6, 2014 Division: Corporate Initiatives
More informationEarned Value Management - EVM
Earned Value Management (EVM) technique used to track the Progress and Status of a Project & Forecast the likely future performance of the Project. Earned Value Management (EVM) technique integrates the
More information6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM
/7/018 PERT / CPM BSAD 0 Dave Novak Summer 018 Overview Introduce PERT/CPM Discuss what a critical path is Discuss critical path algorithm Example Source: Anderson et al., 01 Quantitative Methods for Business
More informationUNIVERSITY OF TOLEDO INTERNAL AUDIT DEPARTMENT DEVELOP BUDGETS
The following control objectives provide a basis for strengthening your control environment for the process of developing budgets. When you select an objective, you will access a list of the associated
More informationImpacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)
Cost Reduction: Planning & Control Break Even Point & Decision Tree Analysis (l.u. 4/2/13) Impacting the Bottom Line Calls for an understanding of: Variation Waste & Value Investments (time, capital, resources,
More information