Facilities Update Construction Progress

Size: px
Start display at page:

Download "Facilities Update Construction Progress"

Transcription

1 Major Projects Update October 2018 Prepared by Business and Operations October 19, 2018 Facilities Update Construction Progress Bismarck High School Addition & Renovation Auditorium: Concrete foundation walls continue to be poured. The curved foundation wall for the front of the stage has been poured Precast walls will be arriving in the next week, creating the high walls of the auditorium. Underground plumbing 95% complete Front Entrance: Exterior is 95% complete. Roof caps and caulking along with the Aluminum entrances being worked on. Interior walls painted, ceiling started and flooring work installed this week. Punchlist for Front Entrance set for Week of Oct. 8th Gymnasium Addition: Work on Foundation walls continue. Existing North entrance & stair have been demoed. Temporary walls have been installed. Structural steel is arriving on site the first half of Oct. 1

2 Bismarck High School Back stage wall Front stage wall Exterior front entrance Interior front entrance 2

3 Century High School Addition and Renovation Phase II East Addition Framing of exterior in Area G is progressing. Interior framing on 2 nd floor of Area G has begun. Setting steel in Area E. One more pour of slab on grade is remaining in Areas F & G. FACS lab, Fashions lab and Child Related Careers rooms are finished. Century High School Progress Area F & G Exterior framing Setting steel in Area F FACS area complete 3

4 Simle Middle School Addition & Renovation Gym foundation is in and backfilled. Gym precast scheduled to arrive October 15 th and take a week to install. Gym roof joists schedule to arrive October 22 nd. Mechanical is working on some underground at gym and controls. Simle Middle School Gym slab area awaiting precast Gym foundation wall/demo at gym tie-in 4

5 Transportation Update We have 4,984 students registered for busing so far this year, 110 ahead of last month and 153 more than this time last year. We are seeing some capacity issues on a Miller route. Some students have been moved to another bus to help capacity. I have attached three graphs: o Registered to Riding. This graph compares the number of students riding to those registered. o Capacity to Registered. This graph compares number of registered students to the bus capacity. We use a 3 to a seat formula for elementary students and 2 to a seat formula for secondary students. o Riding to Capacity. This graph compares number of students riding to the bus capacity. 5

6

7 BISMARCK PUBLIC SCHOOLS Building Fund Revenues and Expenditures September 30, 2018 Beginning Fund Balance - July 1, 2018 $ 7,943,684 Revenue For FY-19: Property Tax Receipts $ 20,202 Misc. Property Tax Receipts Facility Rent Proceeds from Sale of Bonds Fundraising 6,533 Interest Income/Misc. - Total Revenue $ 26,735 26,735 Total Funds Available $ 7,970,419 Expenditures For FY-19: Bond Payment Bond Professional Services 12,568 Bank Fees Athletic Complex 21, Projects 3,542,990 LHS Resolution 2,813 HMS Water Damage (22,464) BHS Water Damage 223,599 Elementary Projects 85,685 Special Assessments - Total Expenditures 3,866,787 3,866,787 Fund Balance as of September 30, ,103,632 Special Assessments Beginning Balance - July 1, 2018 $ - Revenue For FY-19: Property Tax Receipts $ 2,527 Total Revenue 2,527 Total Funds Available $ 2,527 Expenditures For FY-19: Minimum Payment Payment towards Balance Total Expenditures - - Balance as of September 30, 2018 $ 2,527 Special Assessment Balance $ 3,199, Building Fund - Summary FY19 10/4/2018

8 Project Detail Expenditures September 30, 2018 Horizon Middle School - ($7,759,500) Change Orders To Date $ (13,516) Construction Expenses $ 817,705 $ 6,431,206 Fees $ 14,247 $ 432,404 FFE & Technology $ 10,571 $ 57,654 Misc (Testing, Surveying) $ 4,198 $ 33,529 Total $ 846,721 $ 6,954,793 Simle Middle School - ($12,512,290) Change Orders To Date $ (89,471) Construction Expenses $ (8,986) $ 9,222,879 Fees $ 8,082 $ 792,578 FFE & Technology $ 89,169 $ 173,192 Misc (Testing, Surveying) $ 4,749 $ 40,414 Total $ 93,014 $ 10,229,063 Wachter Middle School - ($10,256,680) Change Orders To Date $ 31,199 Construction Expenses $ 261,545 $ 8,666,800 Fees $ 13,601 $ 592,060 FFE & Technology $ 45,289 $ 117,173 Misc (Testing, Surveying) $ 5,334 $ 43,312 Total $ 325,769 $ 9,419,345 Bismarck High School - ($14,000,000 estimate) Change Orders To Date Construction Expenses $ 783,669 $ 1,750,157 Fees $ 24,845 $ 1,155,211 FFE & Technology $ - $ 9,985 Misc (Testing, Surveying) $ - $ 51,782 Total $ 808,513 $ 2,967,134 Century High School - ($13,000,000 estimate) Change Orders To Date $ 82,846 Construction Expenses $ 1,365,197 $ 5,137,383 Fees $ - $ 1,110,661 FFE & Technology $ 103,776 $ 186,081 Misc (Testing, Surveying) $ - $ 95,429 Total $ 1,468,972 $ 6,529,553 Total Bond Projects - ($57,500,000) 5% = 2,875,000 Change Orders To Date $ - $ 11,058 Total $ 3,542,990 $ 36,099,889 Building Fund - Back Up to FY19 10/4/2018

The Beverly Middle School Flexible Learning Academy

The Beverly Middle School Flexible Learning Academy Transformative Learning Through Architecture The Beverly Middle School Flexible Learning Academy Flexible Classroom Studios FLEXIBLE ACADEMY Flexible Configurations Flexible Support Exhibits Cross Discipline

More information

Burlington Area School District Community Survey Results. Winter 2016

Burlington Area School District Community Survey Results. Winter 2016 Burlington Area School District Community Survey Results Winter 2016 Survey Summary The community survey was conducted in December of 2016. Residents within the District were mailed a paper survey. Each

More information

PROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue

PROPOSITION FARMINGTON SCHOOLS. April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS April 8, 2014 Bond Issue PROPOSITION FARMINGTON SCHOOLS - BOND LANGUAGE Shall the Board of Education of the Farmington R-7 School District of St. Francois County, Missouri,

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 11 FACILITIES PLAN STATUS REPORT June 22, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

Status: Structural steel installation underway at primary building. Observatory construction underway.

Status: Structural steel installation underway at primary building. Observatory construction underway. Page 1 of 11 FACILITIES PLAN STATUS REPORT March 30, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid Allocation:

More information

CAPITAL FUNDING SUMMARY

CAPITAL FUNDING SUMMARY CAPITAL SUMMARY SCC (School Consolidation Capital ) CAPITAL : B19 -December 1, Specifically to address a school board s excess capacity : B11 -May 26, Opportunity to identify most urgent & pressing accommodations

More information

Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182

Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Operational Services/Central Services/Axtell Park School

More information

School District of Horicon Community Survey Results. Fall 2017

School District of Horicon Community Survey Results. Fall 2017 School District of Horicon Community Survey Results Fall 2017 Survey Summary The survey was conducted in November December of 2017. Residents within the District were mailed a paper survey. Each survey

More information

2019 Capital Projects Plan

2019 Capital Projects Plan Rev. 03/18 School Name Crawford County Community School Corporation County Name Crawford School No. 1300 2019 Capital Projects Plan The following plan format should be used for your 2019 Capital Projects

More information

Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160

Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 - Page Item 153 Overview 154 Revenues 156 Expenditures 157 Elementary School Allocation 158 Middle School Allocation 159 High School Allocation 160 Special Education Allocation 161 Operational Services

More information

Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent

Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Tumwater University School District Budget Myths Bond Project Update February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent Construction Update $136,000,000 in bonds approved

More information

Listing of Events Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School

Listing of Events Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School Fort McMurray Roman Catholic Seperate School District Fr. M. Beauregard School Building Events 2004 2005 2006 2007 2008 Total Code Repair Add ventilation to storage room $ 1,000.00 $ - $ - $ - $ - $ 1,000.00

More information

Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175

Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Page Item 165 Overview 167 Revenue 168 Expenditures 169 Elementary School Allocation 171 Middle School Allocation 173 High School Allocation 175 Special Education Allocation 176 Operational Services Allocation

More information

FACILITIES PLANNING COMMITTEE

FACILITIES PLANNING COMMITTEE Marble Falls ISD FACILITIES PLANNING COMMITTEE Meeting 2 April 26, 2018 Love and Inspire WELCOME! Agenda Welcome Co-Chairs School Finance 101 MFISD Financial Overview Aging Facilities Small Group and Large

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

Bond Oversight Committee Bond program. January 7, 2016

Bond Oversight Committee Bond program. January 7, 2016 Bond Oversight Committee 2014 Bond program January 7, 2016 Bond Oversight Committee 1 AGENDA Welcome, introductions, reminder of scope/role of BOC Stewart Jacobson, Chair Program Management: Max Cleaver

More information

Pleasantdale Elementary

Pleasantdale Elementary DeKalb County School District/Elementary Schools Pleasantdale Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 5 School

More information

2009/10 Capital Plan. Capital Plan Instructions

2009/10 Capital Plan. Capital Plan Instructions 2009/10 Capital Plan Capital Plan Instructions January 2009 2009/10 CAPITAL PLAN - CAPITAL PLAN INSTRUCTIONS TABLE OF CONTENTS Part I - OVERVIEW 1. Introduction 1 2. Capital Funding 2 3. Capital Cost Drivers

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

PROJECT BUDGET PRESENTATION

PROJECT BUDGET PRESENTATION PROJECT BUDGET PRESENTATION Monomoy Regional High School Building Committee Meeting June 19, 2012 Project Features Serves 700 Students Grades 8-12 8 th Grade Wing located near main entrance 168,000 GSF

More information

(TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I

(TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I SCHOOL PROJECTS (TOTAL MANASSAS CITY PUBLIC SCHOOLS PROJECTS DOLLARS IN THOUSANDS I 1 Sum of Prior Years and Estimate to Complete Project Estimates: PlanningIDesign Land Construction Total 1 Sum of FY

More information

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 Edwin Ataide Deputy Director Plant & Facilities SCH-1 School Projects All Schools Priority FY15 FY16 FY17 FY18 FY19 ADA Compliance (Handicap Accessibility)

More information

Freedom Area School District Community Survey Results. Fall 2018

Freedom Area School District Community Survey Results. Fall 2018 Freedom Area School District Community Survey Results Fall 2018 Survey Summary The survey was conducted in late October/early November of 2018. Residents within the District were mailed a paper survey.

More information

2016 Budget CENTER GROVE COMMUNITY SCHOOL CORPORATION. Budget Hearing September 24, 2015

2016 Budget CENTER GROVE COMMUNITY SCHOOL CORPORATION. Budget Hearing September 24, 2015 2016 Budget CENTER GROVE COMMUNITY SCHOOL CORPORATION Budget Hearing September 24, 2015 Budget Adoption Calendar September 4, 2015 Budget Advertised September 24, 2015 October 6, 2015 Budget Hearing Bus

More information

Public Presentation Capital Bond November 27, 2017

Public Presentation Capital Bond November 27, 2017 Public Presentation Capital Bond November 27, 2017 Capital Bond The Board of Education facilities committee working in concert with building administration, central administration, and the district architect

More information

Springfield High School

Springfield High School 5.1 Springfield High School Springfield School District Delaware County - Pennsylvania Master Plan Presentation Town Hall Meeting 5 Project Cost Estimates/ Project Financing Strategy / Tax Impact February

More information

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus)

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus) of Colorado Capital Project Status SUMMARY - May (accounting noted by campus) Legend On-Track Risks Approved - Adjustments Needed Awaiting $ Start-Up Phase In Bidding Phase In Closeout Project Completed

More information

Educational & Performing Arts Center: Downriver Campus

Educational & Performing Arts Center: Downriver Campus Educational & Performing Arts Center: Total Estimated Project Construction Cost: $ 18.04 million Groundbreaking: September 2006 Percentage Completed: 100 percent Anticipated Completion Date: Completed

More information

Sheboygan Falls School District Facilities Public Taskforce - Project Report March 29th' 2011

Sheboygan Falls School District Facilities Public Taskforce - Project Report March 29th' 2011 Sheboygan Falls School District Facilities Public Taskforce - Project Report March 29th' 2011 1 Sheboygan Falls School District Facilities Public Taskforce - Project Report March 29th' 2011 Project Overview

More information

CH-UH Board of Education Meeting. June 27, 2017

CH-UH Board of Education Meeting. June 27, 2017 CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle

More information

$1,028,255 $1,028,255 $1,028,255 $1,040, % 1 Aug Project completed. Awaiting budget reallocations before Variations can be settled.

$1,028,255 $1,028,255 $1,028,255 $1,040, % 1 Aug Project completed. Awaiting budget reallocations before Variations can be settled. I. Progress on Outcomes Quarterly Performance Monitoring Report First Quarter, FY 07 Infrastructure Development and Maintenance Program A. Status of Projects, Progress through end of the 1Q IDMP identified

More information

I. PROJECT DESCRIPTION

I. PROJECT DESCRIPTION REQUEST FOR QUALIFICATIONS The Board of Education of the Mariemont City School District (the Owner ) is seeking sealed, signed, written qualification statements from qualified Construction Management firms

More information

BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee

BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee BERKELEY UNIFIED SCHOOL DISTRICT Measure I Construction Oversight Committee AGENDA November 17, 2011 6:00 7:30 PM 1720 Oregon Street Berkeley, CA 94703 (510) 644-6066 1. Call to Order 2. Approval of Meeting

More information

THIS IS A PAYMENT CLAIM MADE UNDER THE CONSTRUCTION CONTRACTS ACT 2002 A PAYMENT CLAIM MADE IN RELATION TO THE FOLLOWING CONSTRUCTION CONTRACT:

THIS IS A PAYMENT CLAIM MADE UNDER THE CONSTRUCTION CONTRACTS ACT 2002 A PAYMENT CLAIM MADE IN RELATION TO THE FOLLOWING CONSTRUCTION CONTRACT: THIS IS A PAYMENT CLAIM MADE UNDER THE CONSTRUCTION CONTRACTS ACT 2002 FROM: Name (or/payee) Contact Person/Representative Address Ph Email TO: Name (Owner/Principal/PAYER) Contact Person/Representative

More information

SPACE UTILIZATION STUDY ANALYSIS November 5, 2013

SPACE UTILIZATION STUDY ANALYSIS November 5, 2013 SPACE UTILIZATION STUDY ANALYSIS November 5, 2013 Space Utilization Study Analysis Ongoing questions regarding enrollment and the use of our facilities 2010 an internal analysis was performed with no decisions

More information

Schenectady City School District

Schenectady City School District Schenectady City School District Mosaic Associates Architects Callie Gaspary, AIA Kersten Lorcher, AIA Hamlin Design Group Shawn Hamlin, AIA Turner Construction Larry Tune 19 November, 2014 CAPITAL PROJECT

More information

RESERVE FUND STUDY VILLAS OF HUDSON HOMEOWNERS ASSOCIATION HUDSON, OHIO

RESERVE FUND STUDY VILLAS OF HUDSON HOMEOWNERS ASSOCIATION HUDSON, OHIO RESERVE FUND STUDY VILLAS OF HUDSON HOMEOWNERS ASSOCIATION HUDSON, OHIO Criterium Liszkay Engineers 110 N. High St. Gahanna, OH 43230 614-418-7200 www.clengineers.com AUGUST, 2009 1.0 INTRODUCTION... 1

More information

Building and Site Sinking Fund Millage. Election Date: November 7th 2017

Building and Site Sinking Fund Millage. Election Date: November 7th 2017 Building and Site Sinking Fund Millage Election Date: November 7th 2017 How do Districts Fund Facilities and Technology Needs? General Fund - Use current operating dollars. These are limited to the amount

More information

State of North Carolina Prequalification Form for First Tier Subcontractors under CM at Risk

State of North Carolina Prequalification Form for First Tier Subcontractors under CM at Risk Pursuant to the statute, this form gathers information about the subcontractors seeking to qualify for the work and provides a general format for the prequalification criteria. Completing this questionnaire

More information

PINE TREE ISD BUDGET WORKSHOP 2 MAY 29, /29/2013 1

PINE TREE ISD BUDGET WORKSHOP 2 MAY 29, /29/2013 1 PINE TREE ISD BUDGET WORKSHOP 2 MAY 29, 2013 5/29/2013 1 GENERAL FUND SCENARIO 1 GENERAL FUND BASED ON FLAT PROPERTY TAX VALUES TOTAL REVENUES - $34,105,847 TOTAL EXPENDITURES - $34,584,579 EXPENDITURES

More information

Lebanon Public Schools Board of Education Budget Presentation

Lebanon Public Schools Board of Education Budget Presentation 2017-2018 Board of Education Budget Presentation Board of Finance March 7, 2017 Board of Education Albert Vertefeuille, C James Mello, VC Sandra Tremblay, S Berthier Bosse Nicole McGillicuddy Stephen Nelson

More information

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017 Facilities Planning & Construction Report 2017 18 2 nd Quarter Ending December 31, 2017 Overview District SRID Spending (MG100) Summary By College By Site District Measure J Spending (MJ100) Summary By

More information

Measure G Quarterly Progress Update

Measure G Quarterly Progress Update Measure G Quarterly Progress Update February 3, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure

More information

Performance Audit on 2008 and 2013 SPLOST Revenues For the Fiscal Year ended June 30, 2012

Performance Audit on 2008 and 2013 SPLOST Revenues For the Fiscal Year ended June 30, 2012 Thomas County School System Performance Audit on 2008 and 2013 SPLOST Revenues 300 Mulberry Street, Suite 300 P.O. Box 1877 Macon, Georgia 31202-1877 Phone: (800) 277-0050 Facsimile: (478) 464-8051 Web:

More information

Ronald E. McNair Discovery Learning Academy

Ronald E. McNair Discovery Learning Academy DeKalb County School District/Elementary Schools Ronald E. McNair Discovery Learning Academy Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive

More information

Robert Shaw Theme Elementary

Robert Shaw Theme Elementary DeKalb County School District/Elementary Schools Robert Shaw Theme Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School

More information

2016 Bond Steering Committee Meeting

2016 Bond Steering Committee Meeting 2016 Bond Steering Committee Meeting Meeting 1: June 23, 2016 Bond Blueprint Meeting Agenda 1. Background and Overview 2. Capital Needs 3. Debt Position 4. Voter Survey 5. Wrap up and Questions Background

More information

FIXING RHODE ISLAND SCHOOL BUILDINGS. Office of General Treasurer Seth Magaziner

FIXING RHODE ISLAND SCHOOL BUILDINGS. Office of General Treasurer Seth Magaziner FIXING RHODE ISLAND SCHOOL BUILDINGS Office of General Treasurer Seth Magaziner 1 SCHOOLS OUR STUDENTS DESERVE All students deserve to go to schools that are warm, safe, dry and equipped for 21 st century

More information

Page Item 172 Overview 173 Revenue 175 Expenditures 176 Elementary School Allocation 177 Middle School Allocation 178 High School Allocation 179

Page Item 172 Overview 173 Revenue 175 Expenditures 176 Elementary School Allocation 177 Middle School Allocation 178 High School Allocation 179 Page Item 172 Overview 173 Revenue 175 Expenditures 176 Elementary School Allocation 177 Middle School Allocation 178 High School Allocation 179 Special Education Allocation 180 Operational Services/Central

More information

Barnesville Public Schools Proposed Building Program

Barnesville Public Schools Proposed Building Program May 6, 2016 Proposal for Submitted to: Commissioner Dr. Brenda Cassellius Minnesota Department of Education Barnesville Public Schools Proposed Building Program Barnesville Public School District Independent

More information

Presented by Jeffrey R. Appelbaum

Presented by Jeffrey R. Appelbaum Presented by Jeffrey R. Appelbaum Project Scope Building Size -- 1,003,000 sf Site Area -- 14.6 Acres Development Budget--$465M Construction Schedule Construction Start Date January 3, 2011 Substantial

More information

University of Colorado Capital Construction Project Status SUMMARY - Second Quarter 2016

University of Colorado Capital Construction Project Status SUMMARY - Second Quarter 2016 of Colorado Capital Project Status SUMMARY - Second Quarter Legend On-Track Risks Approved - Adjustments Needed Awaiting $ Start-Up Design Phase In Bidding Phase In Closeout Project Completed or Withdrawn

More information

Sagamore Hills Elementary

Sagamore Hills Elementary DeKalb County School District/Elementary Schools Sagamore Hills Elementary Final School Assessment Report May 20, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School

More information

NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017

NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017 NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus Dashboard

More information

Release Date: January 3, 2019 Due Date: January 17, 2019

Release Date: January 3, 2019 Due Date: January 17, 2019 SAN JUAN SCHOOL DISTRICT REQUEST FOR BID CONSTRUCTION OF NEW BLUFF ELEMENTARY SCHOOL AND NEW MONTEZUMA CREEK ELEMENTARY GYM Release Date: January 3, 2019 Due Date: January 17, 2019 I. GENERAL A. Intent

More information

The Pillar Blueprint A FRAMEWORK FOR CONSTRUCTION FINANCING. Solution Based Lender

The Pillar Blueprint A FRAMEWORK FOR CONSTRUCTION FINANCING. Solution Based Lender A FRAMEWORK FOR CONSTRUCTION FINANCING Solution Based Lender What is the Pillar Blueprint? The primary goal of the Pillar Blueprint is to provide competitive, flexible mortgages for those planning on building

More information

Wissahickon School District Ambler, PA FINANCE COMMITTEE AGENDA. February 21, :30 pm Administration Building Board Room

Wissahickon School District Ambler, PA FINANCE COMMITTEE AGENDA. February 21, :30 pm Administration Building Board Room Wissahickon School District Ambler, PA 19002 FINANCE COMMITTEE AGENDA February 21, 2017 5:30 pm Administration Building Board Room 1. Discussion of Facilities Master Plan 2. Resolution Parameters for Bond

More information

Middletown Township Public Schools Budget Development. March 20, 2018 Board Workshop Meeting Presentation

Middletown Township Public Schools Budget Development. March 20, 2018 Board Workshop Meeting Presentation Middletown Township Public Schools 2018-2019 Budget Development March 20, 2018 Board Workshop Meeting Presentation Tonight s Focus Background to 2018-2019 budget development Current budget considerations

More information

SAMPLE CONDO RESERVE STUDY for fiscal year 2012

SAMPLE CONDO RESERVE STUDY for fiscal year 2012 SAMPLE CONDO RESERVE STUDY for fiscal year 2012 RDA REPORT - UPDATED RESERVE ANALYSIS FOR FISCAL YEAR 2012 RESERVE DATA ANALYSIS, INC MPLS (612) 616-4817 TOLL FREE (866) 780-7943 WWW.RDAMIDWEST.COM UPDATE

More information

Two Ballot Proposals. August 8, 2017

Two Ballot Proposals. August 8, 2017 Two Ballot Proposals August 8, 2017 Per-Pupil Foundation Allowance Ten-Year History for Schools* Per-Pupil Foundation Allowance Ten-Year History for Schools* FYs 2007-08 through 2016-17 FY2008 FY2009 FY2010

More information

RESERVE FUND STUDY. Reserve Fund Study

RESERVE FUND STUDY. Reserve Fund Study RESERVE FUND STUDY Reserve Fund Study The reserve fund study for the condominium corporation is prepared in a format to be presented to the Condominium Corporation s Board of Directors or for use in delayed

More information

Monthly Report. April 2017

Monthly Report. April 2017 Monthly Report April 2017 El Paso ISD Bond Program Program Manager: Jacobs Table of Contents Report Date: 04/30/2017 Understanding the Monthly Report... 3 Executive Summary. 7 Program Report by Phase...

More information

Residential Construction Guide.

Residential Construction Guide. Residential Construction Guide. for Builders and Mortgage Brokers MARCH 2018 British Columbia Brokerage #X022176 Alberta Brokerage #MW-1411086 ON Brokerage #12560 Admin #12500 page 3 construction guide

More information

Barneveld School District Community Survey Results. Spring 2017

Barneveld School District Community Survey Results. Spring 2017 Barneveld School District Community Survey Results Spring 2017 Survey Summary The survey was conducted in late May/early June of 2017. Residents within the District were mailed a paper survey. Each survey

More information

Barnesville Public Schools Proposed Building Program

Barnesville Public Schools Proposed Building Program August 1, 2018 Proposal for Submitted to: Commissioner Dr. Brenda Cassellius Minnesota Department of Education Barnesville Public Schools Proposed Building Program Barnesville Public School District Independent

More information

West Bend School District Community Survey Results. Spring 2018

West Bend School District Community Survey Results. Spring 2018 West Bend School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in June of 2018. Residents within the District were mailed a paper survey. Each survey included a

More information

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects

More information

Fiscal Year GUIDE TO UNDERSTANDING THE BUDGET CHERRY CREEK SCHOOL DISTRICT #5 ARAPAHOE COUNTY, COLORADO

Fiscal Year GUIDE TO UNDERSTANDING THE BUDGET CHERRY CREEK SCHOOL DISTRICT #5 ARAPAHOE COUNTY, COLORADO Fiscal Year 2015-16 GUIDE TO UNDERSTANDING THE BUDGET CHERRY CREEK SCHOOL DISTRICT #5 ARAPAHOE COUNTY, COLORADO ACKNOWLEDGMENTS Thank you to the members of the Budget Department for their dedicated efforts

More information

Letter of Instructions

Letter of Instructions Letter of Instructions Trade Contractor Prequalification Statement Please complete the following and return at your earliest convenience by email to prequal@chanen.com. 1. Trade Contractor Prequalification

More information

Community College District. Measure M

Community College District. Measure M Community College District Measure M Monthly Report October 2015 San Bernardino Community College District Program Management Measure M Monthly Report October 2015 1. Valley Campus Project Sheets 2. Crafton

More information

RIVERSIDE ACADEMY TUITION & FEE SCHEDULE Tuition Rates

RIVERSIDE ACADEMY TUITION & FEE SCHEDULE Tuition Rates RIVERSIDE ACADEMY 2017-2018 TUITION & FEE SCHEDULE Tuition Rates FAMILY TUITION DISCOUNTS (Deducted from total) Children Discount High School (9 th -12 th ) $6,248.00 2 13% Middle School (6 th -8 th )

More information

Central Davie Academy

Central Davie Academy NC School District/300 Davie County/High School Central Davie Academy Final Campus Assessment Report March 10, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 4 Campus

More information

Backlog Reduction Plan

Backlog Reduction Plan 2003-2013 Executive Summary proposes to achieve reductions in our facilities maintenance backlog by documenting and completing backlog projects on a priority basis and by minimizing or eliminating future

More information

Purpose of the Public Hearing

Purpose of the Public Hearing Public Hearing on 2013-2014 Proposed Budget June 18, 2013 Purpose of the Public Hearing Present the district budget to the community: Discuss prior year events that affected budget Discuss upcoming events

More information

Cecil County Public Schools Board of Education Proposed Budget

Cecil County Public Schools Board of Education Proposed Budget Cecil County Public Schools Board of Education Proposed Budget County Council Presentation April 12, 2016 Fiscal 2017 Operating Fund Capital Fund Debt Service Fund Budget Prioritization Survey Results

More information

Capital Projects Completed since 1988

Capital Projects Completed since 1988 Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990

More information

DeKalb Elementary School of the Arts at Terry Mills

DeKalb Elementary School of the Arts at Terry Mills DeKalb County School District/Elementary Schools DeKalb Elementary School of the Arts at Terry Mills Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School

More information

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete. Page 1 of 14 FACILITIES PLAN STATUS REPORT August 24, 2015 SADDLEBACK COLLEGE 1. SCIENCES BUILDING Project Budget: $52,234,000 $8,308,000 $67,358,000 State Match: $36,564,000 ($36,564,000) - Basic Aid

More information

Reserve Studies Turnover Reports Insurance Appraisals

Reserve Studies Turnover Reports Insurance Appraisals Reserve Studies Turnover Reports Insurance Appraisals Dear Board Members, Managers and Unit Owners, For twenty years we having been serving community associations throughout Florida and the Southeast United

More information

Click to edit Master title style

Click to edit Master title style Click to edit Master title style School Board FY 2018 Budget Retreat January 14, 2017 Click FY 2018 to edit Budget Master Retreat title Agenda style Overview of State requirements Overview of budget development

More information

CAPITAL PROJECT PROCESS

CAPITAL PROJECT PROCESS CAPITAL PROJECT PROCESS May 2009 GETTING STARTED What is a project? A project is defined as all work (maintenance & repair or renovation) that requires 5,000 or more in time and materials and/or is sufficiently

More information

Capital Improvement Budgeting

Capital Improvement Budgeting Capital Improvement Budgeting This presentation is to be informative and not to promote specific products, services companies, etc. Illinois ASBO Sponsored Programs are permitted to promote products and

More information

McPherson Contractors, Inc.

McPherson Contractors, Inc. McPherson Contractors, Inc. Construction Manager Manual Bishop Professional Development Center Bid Package #3 *****FROM***** McPherson Contractors, Inc. 3501 SW Fairlawn Rd., Suite 100 Topeka, Kansas 66614

More information

Measure G Quarterly Progress Update

Measure G Quarterly Progress Update Measure G Quarterly Progress Update May 4, 2016 Table of Contents Section I. Program and Projects Update...1 Section II. Financial Summary...4 I. Program & Projects Update PROGRAM UPDATE: Measure G is

More information

Bob Mathis Elementary

Bob Mathis Elementary DeKalb County School District/Elementary Schools Bob Mathis Elementary Final School Assessment Report May 19, 2016 PARSONS School Assessment Report Table of Contents School Executive Summary 4 School Condition

More information

This workbook is designed as a supplement to the 2018 Department memo labeled "Capital Projects Plan Template and Notices for Budget Year 2019.

This workbook is designed as a supplement to the 2018 Department memo labeled Capital Projects Plan Template and Notices for Budget Year 2019. Capital Projects Plan Template and Notices for Budget Year 2019 Amended August 21, 2018 Pursuant to IC 20-40-18-6 and IC 20-40-18-7 and in conjunction with the implementation of HEA 1009-2017 and HEA 1167-2018,

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

Franklin Township Public Schools FINAL BUDGET PRESENTATION BOARD OF EDUCATION MEETING - APRIL 27, 2017

Franklin Township Public Schools FINAL BUDGET PRESENTATION BOARD OF EDUCATION MEETING - APRIL 27, 2017 Franklin Township Public Schools 2017 2018 FINAL BUDGET PRESENTATION BOARD OF EDUCATION MEETING - APRIL 27, 2017 Franklin Township Board of Education Edward Potosnak, President Nancy LaCorte, Vice President

More information

Our Focus: Your Future

Our Focus: Your Future Town of Fort Erie Infrastructure Services Our Focus: Your Future Prepared for Council-in-Committee Report No. IS-53-07 Agenda Date November 19, 2007 File No. 220102 Subject 5 YEAR FACILITY CONDITION STATUS

More information

Lake Mills Area School District Community Survey Results. Spring 2018

Lake Mills Area School District Community Survey Results. Spring 2018 Lake Mills Area School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in late May through mid-june of 2018. Residents within the District were mailed a paper survey.

More information

Weston Public Schools PROPOSED BUDGET OF EXPENDITURES

Weston Public Schools PROPOSED BUDGET OF EXPENDITURES Weston Public Schools PROPOSED BUDGET OF EXPENDITURES 2012-2013 School Facilities 2012-2013 Budget Presentation Please refer to pages 111-117 in the Budget Binder Budget Preface The Past: Unreliable boilers

More information

$12,769,962 $15,919,892 $9,184,256 $9,491,206 $0 $47,365,316

$12,769,962 $15,919,892 $9,184,256 $9,491,206 $0 $47,365,316 INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

Ballot Measures-T Section

Ballot Measures-T Section T, Westminster School District Classroom Improvement Measure To upgrade aging schools and improve the quality of education with funding that cannot be taken by the State; provide heating, ventilation and

More information

Facility and Financial Overview. Brandywine Heights Area School District

Facility and Financial Overview. Brandywine Heights Area School District Facility and Financial Overview Brandywine Heights Area School District BHASD Mission: Our Mission is to enable students to strive for success in an ever-changing global society. Agenda 1. Overview of

More information

Annual Report on Parish Facilities. Patrick Jendraszak

Annual Report on Parish Facilities. Patrick Jendraszak Annual Report on Parish Facilities Patrick Jendraszak May 15, 2018 Buildings & Grounds Committee Andy Bauer (School Liaison) Sue MacGill (School Liaison) Progress on Last Year s Plans Renovate Grades 3/4

More information

Architect: WESKetch Architecture, Inc, Millington, NJ. William Kaufman/Tom Vierschilling

Architect: WESKetch Architecture, Inc, Millington, NJ. William Kaufman/Tom Vierschilling April 20, 2017 INVITATION FOR CONTRACTORS TO BID Project Address: 40 Maple Street Summit, NJ 07901 Project Summary Overview: Approximately 3,220 sf 3 rd story addition over existing 2 story building in

More information

School Referendum Results School Amount Type of Debt Description Arrowhead UHS Failed

School Referendum Results School Amount Type of Debt Description Arrowhead UHS Failed School Referendum Results School Amount Type of Debt Description Arrowhead UHS Arrowhead UHS Baraboo Beaver Dam Belleville Cambridge Campbellsport Chippewa Falls Chippewa Falls $64,700,000.00 Issue Debt

More information

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011

UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 UNIVERSITY OF NORTHERN COLORADO: FINANCIAL REPORT 03/31/2011 OVERVIEW Financial highlights of the 3 rd quarter financial report for fiscal year 2011-12 are summarized below: Cash The University s cash

More information

Ms. Walden made a motion to approve the minutes of January 12,2017. Mr. Dixon seconded the motion. The motion passed unanimously.

Ms. Walden made a motion to approve the minutes of January 12,2017. Mr. Dixon seconded the motion. The motion passed unanimously. MINUTES PALM BEACH COUNTY CONSTRUCTION BOARD OF ADJUSTMENTS AND APPEALS (CBAA) 1. CALL TO ORDER/ CONVENE AS CBAA Chairman Marc Wiener called the meeting to order at 1:57 p.m. The meeting was conducted

More information

City School District of Albany Five Year Facilities Plan 3/14/2019

City School District of Albany Five Year Facilities Plan 3/14/2019 Bold indicates change from 3/7/19 BOE meeting Available Local Share $ 3,300,000 1 SPA Air condition gymnasium $ 267,000 1 $ 41,385 $ 41,385 $ 267,000 2 DCS Air condition gymnasium $ 221,000 1 $ 34,255

More information