1 Indonesia Industry Focus Indonesia Construction Refer to important disclosures at the end of this report DBS Group Research. Equity 5 Jul 2017 Adjusting expectations Decelerating new contract growth and rising capital needs cap sector s upside potential; turning Neutral on the sector Contractors with ample balance sheet capacity stand a better chance of winning more projects Execution and earnings are key catalysts. Top picks: PTPP and WTON Turning Neutral on Indonesia s construction sector; the stockpicking game continues. We are turning Neutral on the sector (from Positive previously) as we expect new contract growth to decelerate while the higher capital needs pose a risk to profitability. We advise investors to stay selective. We like PTPP due to its attractive valuation at 0.34x EV/order book, lower than peers. PTPP also has a smaller capex commitment compared to its peers, and a less leveraged balance sheet to support its future earnings and new contract growth. As the government and project owners accelerate the execution of infrastructure projects, we believe precast producers, including WTON, are in a sweet spot. Contractors with ample balance sheet capacity stand a better chance of winning more projects. Job opportunities are aplenty for contractors given Indonesia s massive need for infrastructure. Nonetheless, funding remains a challenge with fiscal deficit being capped at 3% by law while the government has been taking a break from injecting capital into SOEs. A number of funding alternatives are taking place but mostly require the contractors to also invest in the infrastructure projects or work under a turnkey scheme. Capital requirements to win a project will continue to rise, hence we prefer contractors with ample balance sheet capacity, established JVs with foreign players and good cash flow management. Where we differ. Consensus' blanket overweight stance on the sector implies an expectation that earnings delivery will be smooth for all listed stateowned contractors, which may not be the case as some contractors are facing land acquisition issues and funding constraints. We also expect new contracts to peak out this year and decline by 6% in On contrary to consensus Buy call on all listed stateowned contractors, we believe selective investing in the sector is the best approach given the peaking new contract growth and differing risk profile among the contactors. Our top picks in the sector are PTPP and WTON. JCI : 5, Analyst Chong TjenSan tjensan@alliancedbs.com Tiesha PUTRI tiesha.narandha@id.dbsvickers.com STOCKS Source: AllianceDBS, DBSVI, Bloomberg Finance L.P. Closing price as of 5 Jul 2017 Waskita Karya : Waskita Karya is a stated owned construction company engaging in a wide variety of construction activities including highways, bridges, ports, airports, and LRT. Pembangunan Perumahan : PT PP (Persero) is Indonesia's leading construction company with business portfolio encompassing from building and civil infrastructure constructions. Wijaya Karya : Wijaya Karya is a construction company with interests in EPC, civil, building works, precast and realty. Wijaya Karya Beton : Wika beton (a subsidiary of Wikaya Karya) is a leader in precast in Indonesia with c.40% market share. Construction companies PE valuation range since 2012 (x) WSKT PTPP WIKA WTON Source: AllianceDBS, DBSVI Price Mkt Cap Target Price Performance (%) Rp US$m Rp 3 mth 12 mth Rating Waskita Karya 2,270 2,306 2,400 (2.1) (6.8) HOLD Pembangunan Perumahan 3,330 1,545 4, (7.2) BUY Wijaya Karya 2,220 1,491 2,050 (4.7) (15.6) HOLD Wijaya Karya Beton (21.5) (33.7) BUY edth / sa MA, PY

2 Industry Focus We identify three key issues that will shape the sector's performance for the rest of the year: 1) The speed of project execution. The three contractors under our coverage are now sitting on a recordhigh order book. After two years of stellar new contract growth, we expect the pace of project awards for the big three stateowned contractors (Wijaya Karya, PT PP and Waskita Karya) to decelerate in the coming months given the already high new contract base last year (Rp157tr vs Rp84tr in 2015). That said, the focus will shift to project delivery, and consequently earnings. 2) Land acquisition funding. A number of landintensive toll road projects have been awarded by the government and there are more new toll road concessions that are in talks. We identify over 2,500 km toll roads in the pipeline, exceeding the government s initial target of developing 1,000 km new toll roads by Land acquisition for infrastructure projects are typically funded by the government, but the disbursement of the funds has been delayed since last year due to bureaucratic hurdles. A new scheme that allows the project owner to prefinance the land acquisition cost while awaiting the government to disburse the funds has been adopted since then. However, this has also become an additional burden for the project owners balance sheets. We believe the fund disbursement would be a positive catalyst for the sector to speed up land acquisition activities and project delivery. 3) Asset recycling and securitisation, particularly for Waskita Karya (WSKT), which has the highest exposure to toll road projects. WSKT has been actively acquiring stakes in greenfield toll road projects with the aim of selling them after the construction works complete. This strategy has also been adopted by other listed contractors, albeit at a much less aggressive pace. A timely and valueaccretive divestment will be a positive catalyst for the contractors. In addition, we estimate that a potential new contract worth Rp80tr would come from JSMR. However, given JSMR s hefty funding needs, the execution of its securitisation and divestment plans are important to ensure that its new projects would take off. Page 2

3 Industry Focus New contract growth to peak out; execution to take the spotlight The three stateowned contractors under our coverage booked Rp47.5tr worth of new contracts in 5M17, a 71% increase yoy. This was driven largely by SOE and to some extent private contracts. We nonetheless anticipate the new contract growth to slow down in the coming months with the three contractors only guiding for a 4% increase in new contracts for FY17. 5M17 new contracts Rp tr % 31% *based on management s target 19% 33% WIKA PTPP WSKT WTON 5M16 new contracts 5M17 new contracts % of FY17 guidance (RHS) Among the three stateowned contractors under our coverage, PTPP is guiding for the highest new contract growth of 25%, coming from a relatively low base last year where it won Rp32.6tr new contracts over the year (vs. WSKT at Rp70tr and WIKA at Rp54.8tr). WSKT announced its ambitious new contract growth of 14% to Rp80tr after more than doubling its new contracts last year. This forecast is above our expectations. WSKT has been able to secure large order books in the past two years by shifting its business model from a pure civil contractor to toll road developer. The company currently owns 18 toll road concessions through its subsidiary Waskita Toll Road. We estimate that most of the construction contracts were awarded and included in WSKT s 2016 order book. Unlike last year where its new contract target was relatively secured, the company has to resume its toll road acquisition spree. This means that a strong and sustainable new contract growth will likely come at the expense of its balance sheet strength. In our view, this is a key negative given its already poor operating cashflow. Meanhile, WIKA expects its new contracts to decline by 21% due to the high base last year where the company was % 45% 40% 35% 30% 25% 20% 15% 10% 5% 0% awarded the Rp15.8tr JakartaBandung HSR civil works construction contract. As new contracts are peaking out this year, project execution and earnings delivery would take the spotlight. New contract trend Rp tr *based on management s target New contract growth trend 140% 120% 100% 80% 60% 40% 20% 0% 20% 40% *based on management s target WIKA PTPP WSKT Total 43% 117% FY14A FY15A FY16A FY17F* 34% 25% 21% 3% 70% 118% 42% 40% 19% 1% WIKA PTPP WSKT Total 21% 14% FY14A FY15A FY16A FY17F* % Due to the government s fiscal constraint, the rule of the game has changed. In the past, contractors were largely dependent on governmentfunded projects (with the exception of PTPP which in the past won a number of projects from private property developers), specifically infrastructure projects under Ministry of Public Works and Housing and Ministry of Transportation. Nowadays, balance sheet strength is becoming increasingly important as more bigticket projects are implemented using the PublicPrivate Partnership (PPP) scheme. That said, contractors typically had to acquire equity stakes in the project to be able to win the civil work contracts. 4% Page 3

4 Industry Focus Governmentfunded projects that are up for bidding remain aplenty, but are more prone to delay, especially if the state s revenue collection falls short of target. Meanwhile, the government s strategy to decentralise its infrastructure budget from ministries to regional government also means a smaller chance for largescale stateowned contractors, i.e. WIKA, PTPP and WSKT, to win the projects due to their relatively small ticket size, slower execution and tighter competition against regional players. New contracts from governmentfunded projects Rp tr Contribution of governmentfunded projects* to total new contract 45% 40% 35% 30% 25% 20% 15% 10% 5% 15% *Excluding projects funded by SOE Recordhigh order book to support revenue visibility On the positive side, the three contractors under our coverage are now sitting on a recordhigh order book. WSKT is leading with Rp92.9tr outstanding order book supported by the greenfield toll road acquisition spree by its 70%owned subsidiary Waskita Toll Road. In second position is WIKA with A 2015A 2016A 43% 20% WIKA WSKT PTPP 35% 31% 22% 20% 19% 19% 24% 30% WIKA WSKT PTPP Total % Rp76.2tr backlog contracts, of which 21% comes from the JakartaBandung highspeed railway project (where WIKA has an effective stake of 23%). Meanwhile, PTPP has Rp58.1tr backlog contracts. Among the three contractors, PTPP s order book is more diverse and least concentrated to a single or one type of project. Note that the majority of WKST s order book are highly leveraged to toll road projects in Java while 21% of WIKA s order book is from the JakartaBandung highspeed railway project. Contractors revenue visibility Rp tr *As et end of May 2017 Land acquisition risk same old story? The three contractors under our coverage recorded a strong new contract growth of 86% yoy in FY16. Nonetheless, execution was slower than expected, particularly in 4Q16 with combined revenue of WSKT, WIKA and PTPP (exproperty and toll road operations) in the quarter only growing by 21% yoy, decelerating from the 40% growth booked in 9M16. The deceleration was mostly due to WIKA and PTPP, whose revenue exproperty grew by only 6% and 2% yoy respectively. Based on our checks, land acquisition issue remained the key hurdle as most of the contracts awarded in the past 12 months are landintensive toll road projects. In our view, aside from technical issues, the project execution to some extent hinges on the disbursement of land acquisition funds. Our discussions with industry players suggest that land clearing process is typically faster when the funding is ready. 2.7 WIKA PTPP WSKT Outstanding order book* (LHS) Revenue FY17F (LHS) Outst. order book/revenue FY17F (RHS) 2.5 (x) Page 4

5 Industry Focus Under the 2016 revised state budget and 2017 state budget, the government allocated Rp16tr and Rp20tr respectively to fund land acquisitions for infrastructure projects. As at the time of writing, a large part of the budget has yet to be disbursed due to bureaucratic and regulatory hurdles. As a result, toll road concession owners are asked to cover for the land costs to speed up execution. Land acquisition bailout fund from project owners Rp tr % 7.0 Our discussions with project owners suggest that reimbursement will likely take time as the claim must be verified by two government agencies, Audit Board (BPK) and State s Asset Management Agency (BLU LMAN). It is also worth noting that the budget allocation can only cover 57% of land acquisition cost estimated by Ministry of Public Work and Housing. Hence, the concession owners will likely continue to prefinance the shortage to speed up the project execution. We have highlighted that more capital is required by contractors to grow their order books either to acquire some stakes in the infrastructure projects they bid for or to work under semiturnkey or turnkey projects. Given the high capital needs, the disbursement of the land acquisition budget will help to ease the cash flow burden of the project owners and allow them and the contractors to execute more projects. Projects up for bidding % 20.2 In our past report (Indonesia Construction: Bridging ASEAN connectivity gap through port buildout), we listed down a number of transportbased infrastructure projects in the government s pipeline. Job opportunities remain aplenty for contractors given Indonesia s massive need for infrastructure upgrade. We however note that funding remains a challenge % 7.1 Jasa Marga* Hutama Karya** Waskita Karya* 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% Total equity (LHS) Bailout fund (LHS) Bailout fund/total equity (RHS) especially with fiscal deficit being capped at 3% by law. In addition, the government is no longer actively injecting capital into SOEs. Alternative funding such as PrivatePublic Partnership (PPP) is required to enable the project to take off, but bureaucratic bottlenecks and complexity of land acquisition issues may push these projects backward. The government may also be more active in leveraging on foreign funding in line with One Belt One Road where the Jakarta Bandung High Speed Rail is being financed by the China Development Bank. We narrow down our list to a number of transportbased infrastructure projects that in our view are the most plausible to be executed in the next 12 months based on our checks with contractors and project owners. Toll road Rp80tr potential new contracts in The government continues its aggressive rollout of new toll road projects although toll roads entering land acquisition or construction phases already far exceed the initial goal of 1,000 km. At the end of last year, Indonesia s leading toll road operator Jasa Marga (JSMR) announced its plan to further expand its toll road network by another 800 km. This toll road expansion plan, if realised, will translate to c. Rp80tr worth of new jobs for contractors in In our previous sector reports, we had noted that among all infrastructure projects, toll roads have shown the best progress among all of the government s infrastructure initiatives, supported by land acquisition reform, capital injection to infrarelated SOEs and given the less complex designing and civil work process. Based on our discussion with JSMR, a number of new toll roads will be rolled out in the near future. However, due to JSMR s hefty funding needs, most of the projects will adopt contractor prefinancing (CPF) scheme (also known as turnkey ) where contractors will only receive the payment once the toll road construction is entirely completed. We see a risk that these projects would command a lower profit margin compared to noncpf toll road projects won in the past due to the higher working capital requirement. Port eyes on Patimban project Port projects, on the other hand, have moved slower than our expectation. Two key issues are funding and the higher complexity of the projects, particularly on the design. Two port projects are currently in the tender process with one of them being the mega Patimban port project in West Java Page 5

6 Industry Focus worth US$3bn (c. Rp40tr). Japan will likely finance most of the projects with the loan deal expected to be signed this year. Based on our channel check, local contractors can win at least 40% of the total contract value, or approximately Rp16tr, while the remaining will likely be awarded to foreign contractors, depending on the loan term. In a recent Belt and Road Forum in Beijing, there are also two port projects offered to China for financing, namely Kuala Tanjung port and Bitung port. The projects will comprise several phases. Both ports are estimated to cost Rp34tr each. Highspeed and urban railway some changes to the initial plans The likelihood of government expanding the planned Jakarta Bandung highspeed railway network to Surabaya appears to be lower now. Instead, it is mulling over revitalising the existing railway by building an elevated track. Nevertheless, the potential new order book from this railway revitalisation project would still be sizeable at Rp80tr. The plan to build an LRT in Bandung was also called off. Based on our checks, the project will likely be replaced by metro capsule which has a lower investment cost (c. Rp1tr). Meanwhile, there has been a discussion on LRT development in Surabaya. A feasibility study for the project is currently taking place, however the contract size is estimated to only reach Rp3.8tr. Another urban railway project scheduled to start this year is MRT phase 2. The MRT track will be entirely underground and span 14 km from Hotel Indonesia Roundabout to Ancol. The project is estimated to cost at least Rp22.5tr. Note that WIKA has constructed 15% of the underground portion for the current Jakarta MRT line and should be a front runner for this portion. On the subsequent page, we present our new contract estimates after taking into account the contribution from the central government s annual capex spending. New contracts what can surprise on the upside? For power plant projects, competition is tighter as stateowned contractors also compete with private players, both from local and foreign countries. As at end of December 2016, only power plants with total capacity of 14.6 GW were still in the initial phase (planning and procurement). Assuming US$1.5m investment per megawatt, this would translate to potential new contracts of Rp291.9tr. However, a big chunk of the investment is related to EPC while for the civil works, the size is typically less than 30% of the total investment. Given the high complexity of power plant projects and intense competition from more experienced foreign EPC players, we only take into account the civil works with 50% winning rate for the three contractors. An increase in winning rate is possible if the contractors actively participate as an equity investor in the power plant projects. Progress of 35 GW programme (as at end of 2016) Source: PLN Operational, 707 Start Construction, 10,291 Power Purchase Agreement, 10,063 Planning, 5,824 Procurement, 8,810 We expect 2018 new contracts to start declining. New contracts of the big three stateowned contractors have surged from a mere Rp60.5tr in FY14 to Rp157.3tr in FY16, supported by higher government infrastructure spending, both through ministerial spending and the multiplier of capital injection to SOEs. In 2017, the big three state contractors only guided for a 4% yoy growth after almost doubling their new contracts yoy in With the government being less active in injecting capital into SOEs and given that the contractors already have a sizable outstanding order book to be delivered over the next 12 years, we think a further surge in new contracts is less likely. Page 6

7 Industry Focus Potential new contracts from 35 GW programme Ca pa c ity (MW) Planning 5,824 Procurement 8,810 Total 14,634 Key assumptions: Investment (USD/mn) 1.50 Civil work portion 25% USDIDR 13,300 Potential new contract (Rp bn) 72,987 Big 3 stateowned contractors' winning rate 50% Potential new contract for big 3 stateowned contractors (Rp bn) 36,494 Contract awarded per annum assuming: 3 years contract award (Rp bn) 12,165 2 years contract award (Rp bn) 18,247 Source: PLN, AllianceDBS, DBSVI New contracts from governmentfunded projects We also note that there are a number of refinery projects with estimated total investment of Rp596tr listed as the government s priority projects. These projects are overseen by a special committee called KPPIP (Committee for Acceleration of Priority Infrastructure Delivery which reports directly to President. We have yet to include the potential contracts from these projects while awaiting more clarity on the project funding. Recently, Pertamina announced its plan to delay the project completion to after 2020 due to financing issues. Given the high complexity of the refinery projects, we think only a small part of the contract size can be awarded to the listed stateowned contractors. If this projects go through, we believe the contract can provide potential upside to WIKA, which has better experience in refinery projects compared to PTPP and WSKT. Governmentfunded new contracts (Rp bn) 2014A 2015A 2016A 2017F 2018F 2019F WIKA WSKT PTPP Total new contracts Growth yoy 75% 27% 3% 5% 6% Gov't capex budget Gov't capex spending Actual spending/budget 86% 83% 81% 83% 84% 85% Gov't capex growth yoy Budget 57% 18% 6% 4% 5% Actual 51% 20% 3% 5% 6% Actual t1 vs. budget 83% 1% 17% 25% 25% WIKA, WSKT and PTPP's market share* 11% 12% 20% 20% 20% 20% * New contracts of WIKA+WSKT+PTPP / gov't capex spending Page 7

8 Industry Focus Identifiable projects in 2017F 2018F Toll road Project Location Investment (Rp bn) Jasa Marga's toll road expansion plan Indonesia 80,000 Railway BandungSurabaya railway revitalisation West Java, East Java 80,000 Bandung Metro Capsule West Java 1,000 Surabaya LRT East Java 3,800 Jakarta MRT Phase 2* Jakarta 3,375 Port Patimban Port Stage 1 Phase 1* West Java 7,052 Kuala Tanjung Port Phase 2* North Sumatra 3,200 Power 2018F Indonesia 18,247 Governmentfunded projects 2018F state budget Indonesia 33,281 Total 229, F new contract assuming two years of contract award 149,955 New contracts FY15A 84,380 FY16A 157,337 FY17F 159,787 FY18F 149,955 New contract growth yoy FY16A 86% FY17F 2% FY18F 6% * Civil work portion only Source: Company, various media sources, AllianceDBS, DBSVI Page 8

9 Industry Focus On to the next catalysts Below we highlight five upcoming events and two mega projects that will likely become the key catalysts for the sector and the individual companies. 1) 2018 Fiscal Budget proposal (August 2017) The government is scheduled to submit the budget proposal to parliament in August The amount the government allocates for infrastructure development and stateowned enterprises (if any) will be important to gauge the direction of contractors order book growth in ) Waskita Toll Road divestment WSKT plans to further divest its stake, while Waskita Toll Road also plans to sell 34 toll roads this year. The contractor has shifted its business model to become a toll road developer, which is highly capital intensive. While the impact on WSKT will depend on the toll road s valuation, the divestment proceeds should help to ease WSKT s cash flow burden. 3) CDB loan disbursement for JakartaBandung highspeed railway (HSR) project The construction of JakartaBandung HSR has come to a halt after the groundbreaking ceremony in January 2016 due to prolonged delay on financial close. The loan agreement was finally signed in May Nonetheless, the disbursement will be pending the verification of land acquisition progress by an independent auditor. WIKA, which leads the local consortium for the project, expects the loan to be disbursed and the construction works to resume in July The resumption of the project will be positive for both WIKA and WTON. 4) PTPP s 2Q17 earnings release After recording a weakerthanexpected construction revenue in the past two consecutive quarters mainly due to land acquisition issue, 2Q17 will be an important quarter to regain investor s confidence on PTPP s ability to execute its large outstanding order book. In May 2017 analyst briefing, the management assured investors that the revenue should catch up in 2Q17 with a target revenue of Rp10tr in 1H17. This implies Rp7.1tr revenue target in 2Q17 vs. Rp2.9tr achieved in 1Q16. 5) Jasa Marga s securitisation and subsidiary IPO plan JSMR is planning to expand its toll road network up to 800 km by 2019, on top of the c. 600 km greenfield toll roads in its existing pipeline. Due to the hefty investment needed, any fundraising activities, particularly the securitisation of its mature toll roads and divestment of its subsidiaries, will help to ensure that its existing and upcoming pipelines can be executed timely. 6) Patimban port The location of Patimban port has been approved by the government. More clarity on the project should come after the signing of the loan commitment from Japan, which is expected to take place in July The tender of the project is ongoing. Based on our checks, two contractors under our coverage, PTPP and WIKA, are vying for the project. 7) JakartaSurabaya railway revitalisation Given the sizeable project size, that is Rp80tr or approximately 51% of the combined FY16 new contract achievement of WIKA, PTPP and WSKT, more clarity on the project would be positive catalyst for the sector. Page 9

10 Industry Focus What is consensus expecting? Consensus is expecting 47% yoy revenue growth in FY17 for the big three stateowned contractors with net profit growing slower at 33% yoy. As a comparison, the big three stateowned contractors booked 34% yoy revenue growth and 54% headline net profit growth in FY16. Current consensus earnings forecasts imply an expectation that consolidated EBIT and net margin would shrink in FY17. A similar trend was also implied on consensus 2018 earnings forecast. We believe this is because the consensus expects competition among contractors to tighten, coupled with higher financing needs. The magnitude of net margin decline in 2017 based on consensus expectation is the largest on WSKT, followed by WIKA. Valuation and recommendation Construction sector s 12month forward PE Jan12 Apr12 Jul12 Oct12 Jan13 Apr13 Jul13 Oct13 Jan14 Apr14 Jul14 Oct14 Jan15 Apr15 Jul15 Oct15 Jan16 Apr16 Jul16 Oct16 Jan17 Apr17 Source: Bloomberg Finance L.P, AllianceDBS, DBSVI +2sd +1sd Avg. 1sd 2sd Consensus 2017 net profit revision 35% 30% 28% 27% 25% 20% 16% 15% 15% 10% 6% 5% 0% 1% 3% 1% 1% 0% 5% WSKT WIKA 0.2% PTPP 3% WTON 10% 6% Past 12 months YTD Post FY16 audited results Post 1Q17 results Source: Bloomberg Finance L.P Consensus 2018 net profit revision 40% 30% 28% 20% 17% 14% 12% 10% 5% 1% 4% 3% 1% 0% WSKT WIKA 1% PTPP WTON 10% 20% 18% Past 12 months YTD Post FY16 audited results Post 1Q17 results Source: Bloomberg Finance L.P Construction sector s 12month forward PE relative to JCI Jan12 Apr12 Jul12 Oct12 Jan13 Apr13 Jul13 Oct13 Source: Bloomberg Finance L.P, AllianceDBS, DBSVI Jan14 Construction PE premium to JCI (RHS) JCI PE Apr14 Jul14 10% 20% 30% 40% 50% 60% We are turning Neutral on Indonesia s construction sector from Positive previously. The sector s PE multiple has derated significantly in the past few months. However, we do not see any significant catalyst that will support a broadbased upward rerating in the near future. We expect new contract growth to decelerate in the coming months and we think governmentfunded projects are unlikely to provide significant upside potential to our order book forecasts as the government continues to decentralise infrastructure development. As the government seeks funding alternatives and push the PPP scheme, capital requirement to win a project will continue to rise up to the point where contractors have to choose between growing their order books (at the expense of higher interest expense and margins) or coping with a declining order book. Oct14 Jan15 Apr15 Jul15 Oct15 Construction PE Jan16 Apr16 Jul16 40% 30% 20% 10% 0% Avg. construction PE premium to JCI (RHS) We like PTPP due to its attractive valuation and promising growth outlook. The company now trades at 0.34x EV/order Page 10

11 Industry Focus book, lower than WSKT at 0.61x. It is also worth noting that PTPP has a smaller capex commitment compared to WSKT, and a relatively less leveraged balance sheet to support its future earnings and new contract growth. We forecast PTPP s net profit to grow at a CAGR of 27% in 2016A2018F. While WIKA s EV/order book multiple is on par with PTPP, it is now trading at 17.5x 17F PE (vs. PTPP at 15.4x 17F PE). Given the higher PE multiple and downside risk on earnings, we prefer to wait for the JakartaBandung HSR progress to accelerate before turning more positive on the stock. As work on the projects commence, WTON is in a sweet spot as it starts to receive new orders from contractors/project owners. We view WTON as a good proxy to the infrastructure sector given its strong presence across Indonesia. EV/order book Rp tr *As at end of March 2017; ** As of 5 July 2017 Gross and net gearing* 0.34 *As at end of March WIKA PTPP WSKT Avg Outstanding order book* (LHS) EV** (LHS) EV/outst. order book* (RHS) WIKA PTPP WSKT WTON Gross gearing Net gearing (x) Where we differ We are less bullish on the sector compared to the street, particularly on WIKA and WSKT. The consensus Buy call on all listed stateowned contractors (refer to the table below) suggests that a broadbased execution improvement is expected to lift the share prices of all stateowned contractors. On the contrary, given the peaking new contract growth and differing risk profile among the contractors, we believe selective investing in the sector is the best approach. DBS vs. consensus recommendation No. of analyst Consensus' recommendation BUY HOLD SELL WIKA HOLD PTPP BUY WSKT HOLD WTON BUY Source: AllianceDBS, DBSVI, Bloomberg Finance L.P. Our FY17 net profit forecasts for WIKA and WSKT are one of the lowest on the street. We have a HOLD call among consensus Buy calls on both companies. WIKA. WIKA s FY17 net profit largely depends on the construction progress of JakartaBandung highspeed railway. Assuming 6.3% net margin and 37% progress for FY17, the project (exprecast) should contribute Rp183bn net profit to WIKA or 30% of management s net profit target for FY17. We see downside risk on WIKA s net profit given that the construction work is expected to resume only in July Our FY17 net profit forecast for WIKA is 9% lower than consensus as we expect higher capital requirement and debt to support its new contract and earnings growth. WSKT. Our net profit forecasts for WSKT are 9%/27% lower relative to consensus as we have factored in potential startup losses from its toll road business. Summary of net profit forecast changes DBS' re c omme nda tion FY17F net profit FY18F net profit Old New Change Old New Change WSKT 1,824 2,168 19% 1,745 2,209 27% WIKA 1,111 1,140 3% 1,530 1,595 4% PTPP 1,331 1,341 1% 1,645 1,644 0% WTON % % Aggregate 4,632 5,016 8% 5,338 5,865 10% Source: AllianceDBS, DBSVI Page 11

12 Industry Focus Summary of recommendation and TP changes Target Price Recommendation Old New Change WSKT 2,950 2,400 19% Maintain Hold WIKA 2,780 2,050 26% Maintain Hold PTPP 4,950 4,100 17% Maintain Buy WTON 1, % Maintain Buy Source: AllianceDBS, DBSVI DBS s net profit forecast relative to consensus FY17F FY18F 0.20 WSKT WIKA PTPP WTON Source: AllianceDBS, DBSVI, Bloomberg Finance L.P Key risks Delay in project execution due to technical, land acquisition and funding issues, and bureaucratic hurdle. Tax revenue shortfall. The government has set a target to increase tax revenue by 17% this year to Rp1,499tr. Failure to meet this target could lead to spending cuts and delays in project execution. Political headwinds. Conflicting interest between government and opposing parties may impede reform momentum. A case in point is the delay in SOE capital injection last year. Tightening competition among contractors, especially in 2018 where we project aggregate new contracts to decline. This may lead to a drop in margins. Further slowdown in property sector. PTPP, and to a lesser extent WIKA, have exposure to the property sector. Page 12

13 Industry Focus Valuation summary *Nonrated; based on Bloomberg consensus **Order book as at end of May 2017 M arket Cap Price Rec. TP Diluted PE (x) P/B(x) EV/ EBITDA (x) ROAE EPS CAGR EV/ Net order Gearing ( ID R bn) ( ID R ) F Y 17 F Y 18 F Y 17 F Y 18 F Y 17 F Y 18 F Y 17 F Y 18 F Y 16 A 18 F book** (x) Wijaya Karya 19,913 2,270 HOLD 2, % 12% 6% 0.26 Net Cash PT PP (Persero ) 20,646 3,330 BUY 4, % 14% 12% 0.34 Net Cash Waskita Karya 30,813 2,270 HOLD 2, % 16% 14% Adhi Karya* 7,763 2,180 N/R N/A Wijaya Karya Beton 5, BUY % 15% 24% Simple average % 14 % Weighted average % 13 % Source: AllianceDBS, DBSVI, Bloomberg Finance L.P Page 13

14 Industry Focus Company Guides Page 14

15 Indonesia Company Guide Waskita Karya Version 6 Bloomberg: WSKT IJ Reuters: WSKT.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 5 Jul 2017 HOLD Last Traded Price ( 5 Jul 2017): Rp2,270 (JCI : 5,865.40) Price Target 12mth: Rp2,400 (6% upside) (Prev Rp2,950) Analyst Chong TjenSan tjensan@alliancedbs.com Tiesha PUTRI tiesha.narandha@id.dbsvickers.com What s New Funding risk reduced post sale of stake in Waskita Toll Road but further fund raising required Maintain HOLD with a lower SOPbased TP of Rp2,400 Toll road divestment is key catalyst Price Relative Forecasts and Valuation FY Dec (Rp m) 2015A 2016A 2017F 2018F Revenue 14,153 23,788 37,666 49,997 EBITDA 2,041 3,527 5,332 6,674 Pretax Profit 1,398 2,481 3,688 4,113 Net Profit 1,048 1,713 2,168 2,209 Net Pft (Pre Ex.) 955 1,713 2,168 2,209 Net Pft Gth (Preex) (%) EPS (Rp) EPS Pre Ex. (Rp) EPS Gth Pre Ex (%) Diluted EPS (Rp) Net DPS (Rp) BV Per Share (Rp) ,081 PE (X) PE Pre Ex. (X) P/Cash Flow (X) 46.8 nm nm nm EV/EBITDA (X) Net Div Yield (%) P/Book Value (X) Net Debt/Equity (X) ROAE (%) Earnings Rev (%): Consensus EPS (Rp): N/A Other Broker Recs: B: 25 S: 0 H: 4 Source of all data on this page: Company, AllianceDBS, DBSVI, Bloomberg Finance L.P Further fund raising needed Funding risk reduced post sale of stake in Waskita Toll Road but further fund raising is needed. Waskita Karya (WSKT) has shifted to a more capitalintensive business model with 18 toll road concessions in its portfolio (of which 10 concessions are majority owned by WSKT through Waskita Toll Road or WTR). Hefty funding will be required to keep growing its order book and earnings at the current pace. WSKT recently raised Rp3.5tr cash through a 29% stake sale in WTR to SMI and a stateowned pension fund Taspen. We view this positively as it would help to reduce funding concerns and ease potential startup losses. Nonetheless, further fund raising or divestments would be needed. Post divestment to Taspen and SMI, we estimate that WSKT would still need more than Rp7.2tr cash to fund its equity portion for its toll road concessions over the next three years. Where we differ. We are one of the few houses in the market with a HOLD call compared to Buy calls on the stock. Our earnings forecast for FY17F/FY18F are 8%/27% below consensus as we have factored in potential startup losses from WSKT s toll road business. We are also concerned on its persistent negative operating cash flow arising from increasing contribution of turnkey projects. We believe consensus may be over estimating the ease of further equity raising to fund its toll road expansion. This is especially in light of diminishing prospects of more capital injections by the government. Potential catalysts. WSKT plans to further divest its stake in WTR, while its subsidiary Waskita Toll Road also plans to sell 34 toll roads this year. While the impact on WSKT will depend on the toll road s valuation, divestment proceeds should help to ease WSKT s cash flow burden. Valuation: We valued WSKT s construction business at 10x FY17F EPS ( 1.5SD below sector historical mean PE), precast business at 15x FY17F EPS and toll road concessions using the DCF method. Our sumoftheparts TP of Rp2,400 implies 15x FY17F PE. Key Risks to Our View: Failure to divest its toll roads could result in lower earnings and an overstretched balance sheet. At A Glance Issued Capital (m shrs) 13,574 Mkt. Cap (Rpbn/US$m) 30,813 / 2,306 Major Shareholders (%) Republic of Indonesia 68.0 Free Float (%) m Avg. Daily Val (US$m) 2.7 ICB Industry : Industrials / Construction & Materials ed: JS / sa:ma, PY

16 Waskita Karya WHAT S NEW Cutting TP to Rp2,400; further toll road divestment is key catalyst Order book at record high, boosting its revenue visibility to 2.5 years. We estimate WSKT s outstanding order book stood at Rp92.9tr as at end of May 2017 after winning Rp14.9tr worth of new contracts in 5M17. WSKT s sizeable backlog which mainly comprises of Trans Java toll roads and Palembang LRT offers revenue visibility for 2.5 years. Revised up new contract assumptions and earnings. Due to the strong new contract flows in 4Q17, we raised our FY17F new contract assumption to Rp78tr (from Rp40tr previously). With a higher order book, we revised up our FY17F/FY18F net profit by 19%/27%. Despite the upward revision, our earnings forecast for FY17F/FY18F are 8%/27% below consensus as we have factored in potential startup losses from WSKT s toll road business. Cutting TP to Rp2,400. We updated our sum of parts (SOP) valuation, resulting in a lower TP of Rp2,400, from Rp2,950 previously. We value WSKT s exprecast and toll road business at 10x PE 17F (1.5SD below sector s historical mean). Our PE multiple is at discount to sector s historical mean PE given the nature of WSKT s business where the big chunk of the construction earnings can only be converted to cash upon the divestment of its toll road concession. We pegged Waskita s precast business, WSBP, at 15x PE FY17F, a 20% discount to our target multiple for Wijaya Karya Beton (WTON). We think the discount is justified Operating cash flow and capex trend and forecasts Rp bn 20,000 15,000 10,000 5,000 0 (5,000) (10,000) 1,210 (89) 658 7,086 6, A 2015A 2016A 2017F 2018F (1,747) (3,201) (7,762) Operating cash flow Capex 13,983 10,661 because of its smaller geographical presence, less extensive product range and narrower clientele. Lastly, we value WSKT s toll road concessions using DCF. We apply 10% WACC and 0% longterm growth as we run our DCF until the end of the concession period. Note that we have yet to take into account WSKT s five newly acquired toll roads into our calculation i.e. Kuala Tanjung Tebing Tinggi Parapat (143 km), Cileunyi Sumedang Dawuan (60 km), Cibitung Cilincing (35 km), Krian Legundi Blunder Manyar (38 km) and Kaya Agung Palembang Betung (112 km), as we await more details on these concessions. Looking beyond this year s strong earnings outlook. We maintain our Hold call on WSKT. We think the stock is fairly valued at current price, trading at 14.2x 17F PE with net profit CAGR of 14% in F. Despite the strong earnings growth outlook this year (we forecast 27% net profit growth in FY17F), we reserve our concern over the company s cash flow generation and its high capex commitment to fund its toll road concessions. We believe hefty funding is needed to keep growing its order book and earnings at the current pace. Further divestment of its toll road concession at a favourable price is key catalyst for the stock. Gearing trend and forecasts (x) A 2015A 2016A 2017F 2018F Net gearing Gross gearing WSKT s sum of parts (SOP) valuation WSKT exprecast and toll road business Equity value (Rp bn) WSKT's effective ownership Equity value (adj. to ownership) Equity value per share 18, % 18,118 1,335 56% % of TP Remarks Based on target PE of 10x; 1.5SD below sector historical mean Precast (WSBP IJ) 14,389 60% 8, % Based on target PE of 15x Toll road (WTR) 5, % DCF; 10% WACC Target price (Rp/share) 2,400 Implied PE 17F (x) 15.0 Source: AllianceDBS, DBSVI Page 16

17 Waskita Karya Earnings revision 2017F 2018F Old New % change Old New % change Revenue 32,055 37,666 18% 37,900 49,997 32% Gross profit 4,687 6,111 30% 5,381 7,699 43% EBIT 3,767 4,932 31% 4,281 6,141 43% Net Profit 1,824 2,168 19% 1,745 2,209 27% GP margin (%) EBIT margin (%) Net margin (%) New contracts (Rp bn) 40,000 78,000 95% 25,000 67, % Cum. order book (Rp bn) 116, ,514 34% 114, ,788 62% Net interest exp ,245 94% 783 2, % Source: AllianceDBS, DBSVI Page 17

18 Waskita Karya CRITICAL DATA POINTS TO WATCH New Contract Wins (Rp bn) Critical Factors A shift in business model. Following the toll road acquisition spree over the past two years, WSKT has shifted its business model to become more of a toll road developer from a pure civil contractor previously. The company would continue to acquire greenfield toll road concessions in the foreseeable future, build them and divest the stakes after the construction is completed to free up capital. This way, it would be able to secure profit in a shorter time span compared to if it operates the toll roads over the concession period on its own, as the company would be able to reap gains from both the civil work (during construction phase) and the asset divestment. Its subsidiary Waskita Toll Road is the majority stakeholder for nine toll road concessions in Java and one in Sumatra with a total investment value of Rp65tr. It also owns minority stakes in eight other toll road concessions. All eyes on toll road divestment. The change in business model makes toll road divestments crucial for WSKT given the high capital requirements to build the toll roads. Assuming a capital structure of 70% debt and 30% equity for its toll roads, we estimate that WSKT would need to raise Rp7.2tr cash over the next three years to fund its equity stakes. With the current shareholding structure of Waskita Toll Roads, we estimate WSKT would have to raise debt by c.rp25tr. This would further exacerbate its weak operating cash flow position. Given the potential surge in interest expense, its earnings outlook could be at risk. We believe toll road divestments will remain a key focus from 2017 onwards. New wins from government or external parties. The award of new contracts had been a key positive driver of WSKT s share price. This was evident where the strong growth in new contracts in drove the shares outperformance in the same period. However, we think the concern over the sustainability of its new contract wins has outweighed the excitement over its recent new contract wins, especially since most of the growth in its order book has been driven by its internal toll road projects instead of the government or external projects. Note that internal toll road projects are riskier in nature as the profit would only fully translate into cash upon the divestment of the concessions a process that would likely take additional time. This has caused WSKT s share price to underperform the market despite the company s relatively strong new contract and earnings growth (refer to Appendix 1) in the past few months. Carry Over Contract (Rp bn) Construction Gross Margin (%) Page 18

19 Waskita Karya Appendix 1: A look at the company's listed history what drives its share price? WSKT share price vs. peers* 3,000 WSKT share price (LHS) WSKT share price vs. peers* (RHS) Dec 18, 2012 = 1.0 E 2.5 2,500 C 2.0 2,000 1,500 A B D 1.5 1, Dec12 Jun13 Dec13 Jun14 Dec14 Jun15 Dec15 Jun16 Dec16 *Based on the average return of the listed stateowned contractors A: Rupiah fluctuation WSKT s share price was hit by concerns over profitability after the sharp depreciation of Rupiah in mid2013. Investors saw infra project s cost overrun as a key risk, which could lead to a decline in contractors profitability. The risk was deemed higher on WSKT as it was more reliant on government contracts compared to peers. WSKT s share price vs. Rupiah WSKT share price (LHS) Source: Bloomberg Finance L.P. USDIDR (RHS) 16,000 15,000 14,000 13,000 12,000 11,000 10,000 9,000 8,000 B: Share price moved in line with new contract growth WSKT s new contracts grew strongly by 70% yoy in FY16, outperforming its peers, PT PP (PTPP) and Wijaya Karya (WIKA), whose new contracts were flat yoy. WSKT s share price vs. growth in new contracts 3,000 2,500 2,000 1,500 1, , Bloomberg Finance L.P. C: Earnings momentum The company delivered strong earnings in 1H16, fueled by enlarged capital post rights issue. In addition, strong earnings momentum (with consensus upgrading earnings forecasts by 43% in the same period) led to a rally in its share price. WSKT s share price vs. consensus earnings forecasts 3,000 2,800 2,600 2,400 2,200 2,000 1,800 1,600 1,400 1,200 1,000 Dec12 Mar13 Jun13 Sep13 Dec13 Mar14 Jun14 WSKT share price (LHS) Sep14 Dec14 Mar15 Jun15 Sep15 Dec15 Mar16 Jun16 Sep16 Dec16 Mar17 T12M new contract growth yoy (RHS) 200% 150% 100% 50% 0% 50% WSKT share price (LHS) Consensus EPS 16F (RHS) Consensus EPS 17F (RHS) Source: Bloomberg Finance L.P. Page 19

20 Waskita Karya D: Fiscal revenue and state budget. The government s plan to cut spending in 2016 following weak revenue collection caused stateowned contractors share price, including WSKT, to derate. WSKT and construction sector return vs. JCI Dec 18, 2012 = Dec12 Jun13 Dec13 Jun14 Dec14 Jun15 Dec15 Jun16 Dec16 Sector performance relative to JCI WSKT's share price return relative to JCI E: Concern over cash flow and balance sheet capacity appears to be the reasons that halted WSKT s share price rally in the past one year. WSKT s share price return relative to JCI vs. free cash flow Dec12 Dec13 Dec14 Dec15 Dec16 WSKT's share price return relative to JCI FCFE (RHS) Rp bn 10,000 5,000 0 (5,000) (10,000) (15,000) (20,000) Page 20

21 Waskita Karya Balance Sheet: Further fund raising needed. As at endmarch 2017, WSKT had a net debt of Rp6.7tr, translating to gross and net gearing of 1.28x and 0.83x respectively. We expect its debt to rise as the company extends its business model to include the capitalintensive toll road operating business and expansion of its precast business. Management has budgeted Rp32tr capex this year, most of which is for toll road expansion. Leverage & Asset Turnover (x) Share Price Drivers: Award of largesized infrastructure contracts. The award of largesized, multiyear projects will improve WSKT s revenue and earnings visibility, and ultimately lead to an upward rerating of its share price. Rpbn Capital Expenditure Toll road divestment. After divesting a 29% stake in Waskita Toll Road to SMI and Taspen, WSKT is planning to raise more funds by further divesting its stakes in WTR and conducting rights issue. Both corporate actions are targeted to take place this year and are crucial for WSKT given its high capex needs. Key Risks: Persistently weak operating cash flow. We have yet to see positive operating cash flows at WSKT despite strong contract wins last year. Its venture into the toll road operating business could also deteriorate WSKT s operating cash flow during the early years of operations. As such, its balance sheet could remain stretched, forcing it to make another rights or bond issue in the future. ROE (%) Delay in toll road divestment. A delay in toll road divestment would be negative for WSKT. As it continues to acquire new greenfield toll road concessions to grow its order book, a timely fund raising is needed to make sure that the projects do not stall due to cash flow constraints. Forward PE Band (x) Company Background PT Waskita Karya Tbk (WSKT) is a stateowned contractor engaged in a wide variety of construction activities including toll roads, bridges, ports and buildings. It is the most leveraged proxy to the Indonesian construction sector, deriving c. 95% of its revenues from construction. PB Band (x) Page 21

22 Waskita Karya Key Assumptions FY Dec 2014A 2015A 2016A 2017F 2018F New Contract (Rp bn) 22,625 32,084 69,974 78,000 67,940 Carry Over Contr. (Rp bn) 10,516 19,746 34,049 77, ,849 Construction GPM (%) Precast Gross Margin (%) Toll road startup losses (287) (1,282) Segmental Breakdown FY Dec 2014A 2015A 2016A 2017F 2018F Revenues (Rpbn) Construction 9,484 12,052 22,373 30,120 40,340 Building rentals/property Precast 803 2,069 1,149 7,219 8,862 Energy Others Total 10,287 14,153 23,788 37,666 49,997 Gross Profit (Rpbn) Construction 963 1,561 3,591 4,518 5,648 Building rentals/property Precast ,444 1,684 Energy Others Total 1,109 1,889 3,968 6,111 7,699 Gross Profit Margins (%) Construction Building rentals/property Precast Energy N/A N/A 94.9 N/A N/A Others N/A Total Revenue contribution from toll road operation business. Income Statement (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F Revenue 10,287 14,153 23,788 37,666 49,997 Cost of Goods Sold (9,178) (12,232) (19,821) (31,555) (42,298) Gross Profit 1,109 1,921 3,968 6,111 7,699 Other Opng (Exp)/Inc (431) (518) (788) (1,179) (1,558) Operating Profit 678 1,403 3,180 4,932 6,141 Other Non Opg (Exp)/Inc Associates & JV Inc (7.4) Net Interest (Exp)/Inc (140) (267) (795) (1,245) (2,029) Exceptional Gain/(Loss) Pretax Profit 756 1,398 2,481 3,688 4,113 Tax (254) (350) (667) (1,019) (888) Minority Interest (99.8) (500) (1,016) Preference Dividend Net Profit 502 1,048 1,713 2,168 2,209 Net Profit before Except ,713 2,168 2,209 EBITDA 934 2,041 3,527 5,332 6,674 Growth Revenue Gth (%) EBITDA Gth (%) Opg Profit Gth (%) Net Profit Gth (Preex) (%) Margins & Ratio Gross Margins (%) Opg Profit Margin (%) Net Profit Margin (%) ROAE (%) ROA (%) ROCE (%) Div Payout Ratio (%) Net Interest Cover (x) Page 22

23 Waskita Karya Quarterly / Interim Income Statement (Rpbn) FY Dec 1Q2016 2Q2016 3Q2016 4Q2016 1Q2017 Revenue 3,072 5,013 5,923 9,780 7,142 Cost of Goods Sold (2,552) (4,043) (4,986) (8,239) (6,107) Gross Profit ,541 1,034 Other Oper. (Exp)/Inc 58.2 (143) (114) (430) (45.4) Operating Profit , Other Non Opg (Exp)/Inc (151) (1.5) (90.9) Associates & JV Inc (35.2) 27.4 (14.3) Net Interest (Exp)/Inc (132) (190) (225) (249) (287) Exceptional Gain/(Loss) Pretax Profit Tax (136) (205) (105) (222) (168) Minority Interest (157) 53.4 (43.1) Net Profit Net profit bef Except EBITDA ,273 1,004 Growth Revenue Gth (%) (54.4) (27.0) EBITDA Gth (%) (65.0) (21.1) Opg Profit Gth (%) (26.1) 43.1 (0.4) 35.0 (11.0) Net Profit Gth (Preex) (%) (78.0) (24.1) (47.8) Margins Gross Margins (%) Opg Profit Margins (%) Net Profit Margins (%) Balance Sheet (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F Net Fixed Assets 622 1,923 3,275 16,859 26,988 Invts in Associates & JVs 735 1,572 2,071 2,071 2,071 Other LT Assets 1,080 11,009 19,197 19,197 19,197 Cash & ST Invts 1,700 5,522 10,664 3, Inventory ,819 1,800 2,412 Debtors 6,842 7,824 19,795 31,748 42,142 Other Current Assets 1,237 2,018 4,605 7,021 9,260 Total Assets 12,542 30,309 61,425 81, ,011 ST Debt 1,917 3,483 15,344 15,344 15,344 Creditor 5,272 8,773 14,653 22,735 30,478 Other Current Liab 539 1,409 1,464 1,464 1,464 LT Debt 1,246 4,547 9,890 19,875 30,536 Other LT Liabilities 803 2,394 3,300 3,300 3,300 Shareholder s Equity 2,759 9,547 11,070 12,895 14,670 Minority Interests ,704 6,204 7,219 Total Cap. & Liab. 12,542 30,309 61,425 81, ,011 NonCash Wkg. Capital 2, ,101 16,370 21,873 Net Cash/(Debt) (1,463) (2,508) (14,570) (32,097) (44,939) Debtors Turn (avg days) Creditors Turn (avg days) Inventory Turn (avg days) Asset Turnover (x) Current Ratio (x) Quick Ratio (x) Net Debt/Equity (X) Net Debt/Equity ex MI (X) Capex to Debt (%) Net gearing to increase from capex at its toll road subsidiary. Page 23

24 Waskita Karya Cash Flow Statement (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F PreTax Profit 756 1,398 2,480 3,687 4,112 Dep. & Amort Tax Paid (254) (350) (667) (1,019) (888) Assoc. & JV Inc/(loss) Chg in Wkg.Cap. (417) 2,417 (10,099) (6,269) (5,503) Other Operating CF (211) (3,275) Net Operating CF (88.7) 658 (7,762) (3,201) (1,747) Capital Exp.(net) (329) (938) (611) (13,983) (10,661) Other Invts.(net) Invts in Assoc. & JV (755) (498) (172) Div from Assoc & JV Other Investing CF 0.0 (5,491) (8,772) Net Investing CF (1,083) (6,927) (9,555) (13,983) (10,661) Div Paid (110) (100) (210) (343) (434) Chg in Gross Debt 1,782 (729) 17,227 9,985 10,661 Capital Issues , Other Financing CF (3.1) 5,580 5, Net Financing CF 1,728 10,099 22,459 9,642 10,228 Currency Adjustments (1.2) Chg in Cash 556 3,836 5,143 (7,542) (2,181) Opg CFPS (Rp) 34.0 (130) Free CFPS (Rp) (43.2) (20.7) (617) (1,266) (914) We expect operating cash flow to remain negative due to the high contribution of turnkey projects. Target Price & Ratings History Source: AllianceDBS, DBSVI Analyst: Chong TjenSan Tiesha PUTRI Page 24

25 Indonesia Company Guide Pembangunan Perumahan Version 6 Bloomberg: PTPP IJ Reuters: PTPP.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 5 Jul 2017 BUY Last Traded Price ( 5 Jul 2017): Rp3,330 (JCI : 5,825.10) Price Target 12mth: Rp4,100 (23% upside) (Prev Rp4,950) Analyst Chong TjenSan tjensan@alliancedbs.com Tiesha PUTRI tiesha.narandha@id.dbsvickers.com What s New New contract flow in line with 5M17 new contract wins representing 33% of our fullyear forecast Maintain BUY with lower TP of Rp4,100 Price Relative Forecasts and Valuation FY Dec (Rp m) 2015A 2016A 2017F 2018F Revenue 14,217 16,459 21,911 26,878 EBITDA 1,678 2,071 3,019 3,879 Pretax Profit 1,288 1,704 2,207 2,747 Net Profit 740 1,023 1,341 1,644 Net Pft (Pre Ex.) 740 1,023 1,341 1,644 Net Pft Gth (Preex) (%) EPS (Rp) EPS Pre Ex. (Rp) EPS Gth Pre Ex (%) Diluted EPS (Rp) Net DPS (Rp) BV Per Share (Rp) 911 1,580 1,757 1,970 PE (X) PE Pre Ex. (X) P/Cash Flow (X) EV/EBITDA (X) Net Div Yield (%) P/Book Value (X) Net Debt/Equity (X) 0.0 CASH ROAE (%) Earnings Rev (%): Consensus EPS (Rp): N/A Other Broker Recs: B: 29 S: 0 H: 0 Source of all data on this page: Company, AllianceDBS, DBSVI, Bloomberg Finance L.P CRITICAL DATA POINTS TO WATCH All eyes on project execution Maintain BUY. Pembangunan Perumahan (PTPP) s share price has underperformed the JCI by 23% YTD on the back of choppy execution in the past two quarters due to delays in land acquisitions and rollout of contracts. Revenue exproperty grew by only 15% yoy in 1Q17 despite value of new contracts growing by 68% yoy during the same period as land acquisition issues had hindered construction works. During the recent analyst meeting, management reaffirmed that revenue should catch up in 2Q17 as progress on land acquisitions has picked up pace. Orderbook provides revenue visibility for 2.7 years. We estimate that PTPP s order backlog stood at Rp58tr as at the end of May In May 2017, the company won new contracts worth Rp12.6tr, representing 33%/31% of our/management s new contract forecast. The management has guided for 25% growth in new contracts in FY17 (vs. our forecast of 19%), the highest growth among our coverage. We are confident that PTPP will be able to record an increase in new contracts awarded over the next two years supported by its enlarged equity base post IPO. Where we differ. Our Buy call is in line with consensus. Potential catalysts. A better progress of toll road land acquisitions should help to boost earnings and restore investor confidence after two quarters of posting weakerthanexpected earnings. In addition, having a long standing experience in port construction, we think PTPP stands a chance to win the mega project at Patimban Port. The tender of the project is underway. Positive newsflow on the financing and execution of the project should lead to a rerating of its share price. Potential M&A as a precursor to the listing of PTPP s subsidiaries represent another catalyst. Valuation: We cut our TP to Rp4,100 (from Rp4,950) as we lower our target PE multiple to 19x PE (20% premium to the sector s historical mean PE). PTPP is trading at 15.4x/12.6x 17F/18F PE, on par with peers despite its stronger balance sheet to fuel new contract growth in the coming years. Key Risks to Our View: Prolonged slowdown in property sector. PTPP has both direct and indirect exposure to the property sector. A prolonged slowdown in the economy and demand for property can negatively impact earnings and cash flows. At A Glance Issued Capital (m shrs) 6,200 Mkt. Cap (Rpbn/US$m) 20,646 / 1,545 Major Shareholders (%) Republic of Indonesia (%) 51.0 Free Float (%) m Avg. Daily Val (US$m) 6.3 ICB Industry : Industrials / Construction & Materials ed: JS / sa:ma, PY

26 Pembangunan Perumahan New Contract Win (Rp bn) Critical Factors Maintaining positive new contract growth momentum post rights issue. PTPP successfully raised Rp4.4tr cash through a rights issue in December It intends to use 76% of the proceeds to fund equity investments in infrastructure projects, among which are Kuala Tanjung MultiPurpose Terminal and Industrial Estate, five toll roads (such as BalikpapanSamarinda toll road, ManadoBitung toll road, PandaanMalang toll road), a 2x200MW power plant in Sumatra, and lowcost apartments, while the remaining 24% will be used for working capital. With ample cash post rights issue, the company should be able to take on more projects in FY17. This year, the company is eyeing new contracts worth Rp40.6tr, representing 25% increase yoy. Carry Over Contract (Rp bn) Beneficiary of Indonesia s port buildout. PTPP has over the years developed a niche in port construction in Indonesia. According to Bapennas, Indonesia would need as much as Rp59tr to develop and expand 24 ports from Among the larger projects is the multiyear expansion projects at Kuala Tanjung port (Rp18.4tr). The port was initially built by PTPP, hence this would raise the company's competitive edge to secure work contracts once the projects are out for tender. This year, Pelindo IIV, staterun port operators that will carry out a significant part of the government s port development plan, have allocated capex of more than Rp13tr for port expansion. Progress on the mega project at Patimban Port is also important to watch as the company eyes the construction contract. More clarity on the funding of the project is expected to come this year, while construction is scheduled to start in Redirecting focus to governmentrelated infrastructure projects. We estimate that 15%20% of PTPP s backlog is from private property developers. The pace of project execution may be slower amid the still subdued property market, and may potentially negatively affect the company s contract burn rate and earnings. Since 2016, management has redirected its focus to governmentrelated infrastructure projects, including the higher margin EPC projects. Currently, PTPP has three power plant projects in its order book with total capacity of 420 MW. The company plans to bid for more smallscale power plant projects in the future. With this strategy, the company expects to clinch 30% higher new EPC contracts in FY17 from FY16 s Rp6tr. Subsidiaries IPOs. Management is still pursuing inorganic growth ahead of the planned IPO of its subsidiaries. Recently, it acquired three companies through its precast and power business. The IPOs will likely be in 2H17 at the soonest, awaiting green light from the parliament and government. 14,000 12,000 10,000 Rp tr 8,000 6,000 4,000 2, ,300 4,300 11% 11% New Contract 7,000 17% Contractors revenue visibility 9,000 22% 12,600 31% 1M17 2M17 3M17 4M17 5M PTPP's new contracts (Rp bn) as % of FY17 target 92.9 WIKA PTPP WSKT Outstanding order book* (LHS) Revenue FY17F (LHS) Outst. order book/revenue FY17F (RHS) % 30% 25% 20% 15% 10% 5% (x) Page 27

27 Pembangunan Perumahan Appendix 1: A look at the company's listed history what drives its share price? PTPP s share price vs. peers* PTPP share price (LHS) PTPP share price vs. peers (RHS) 5,000 A 4,500 4,000 3,500 3,000 C 2,500 B 2,000 1,500 1, Dec12 Jun13 Dec13 Jun14 Dec14 Jun15 Dec15 Jun16 Dec16 *Based on the average return of the listed stateowned contractors Source: Company, AllianceDBS, DBS Vickers Dec 18, 2012 = 1.0 D A: Rupiah depreciation PTPP s share price along with the other stateowned contractors were under pressure due to concerns over cost overruns, particularly related to government s infrastructure projects. A portion of raw materials are imported, hence Rupiah depreciation may impact margins and earnings negatively. However, PTPP has been least affected compared to other stateowned contractors due to its lower exposure to government infrastructure projects in the past. PTPP s share price vs. USDIDR 5,000 4,000 3,000 2,000 1,000 Dec12 Mar13 Jun13 Sep13 Dec13 Mar14 Jun14 Source: Bloomberg Finance L.P. B: Fiscal revenue collection and state budget The government s plan to cut spending in 2016 following weak revenue collection caused stateowned contractors share prices, including PTPP, to derate. Sep14 Dec14 PTPP share price (LHS) Mar15 Jun15 Sep15 Dec15 Mar16 Jun16 USDIDR (RHS) 16,000 15,000 14,000 13,000 12,000 11,000 10,000 9,000 8,000 C: Higher exposure to power plant projects and awards of big ticket infrastructure projects Earnings recovery in 2Q16 was strong with core profit surging by 260% yoy, mainly driven by EPC business (power plant construction). Furthermore, the management shared its plan to expand its higher margin EPC business. PTPP s share price rerated upwards following the award of two mega toll road projects in June PTPP s share price vs. new contract 5,000 4,000 3,000 2,000 1,000 Dec12 Mar13 Jun13 Sep13 Dec13 Mar14 Jun14 Sep14 Dec14 Mar15 Jun15 Sep15 Dec15 Mar16 Jun16 Sep16 Dec16 Mar17 PTPP share price (LHS) Source: Company, AllianceDBS, DBS Vickers 40,000 35,000 30,000 25,000 20,000 15,000 10,000 5,000 0 T12M new contract, Rp bn (RHS) D: Slow project execution and concern over investment in property sector PTPP s order book replenishment has picked up pace since mid 2016 after winning a number of infrastructure projects. However, construction progress had been slow due to land acquisition issues, causing earnings to fell short of market expectations. In addition, PTPP s equity injection into its property arm PP Properti (PPRO) through a rights issue created some concerns among investors, given the still weak property market. Page 28

28 Pembangunan Perumahan Balance Sheet: Strong balance sheet enables PTPP to take on more projects. PTPP is in a net cash position after receiving rights issue proceeds of Rp4.4tr in December We forecast PTPP s debt to rise with gross gearing of 0.12x in FY17 as the company starts to fund its equity investments in a number of infrastructure projects. Subsidiaries IPOs. Management is still pursuing inorganic growth ahead of the planned IPO of its subsidiaries PP Perlatan (construction equipment rental), PP Urban (low cost housing and precast concrete) and PP Energi (power plant). Recently, it acquired three companies through its precast and power business. The IPOs will likely be in 2H17 at the soonest, awaiting green light from the parliament and government. Management seeks to raise Rp7tr from these IPOs. Share Price Drivers: Award of a largesized, multiyear infrastructure contracts. The award of largesized, multiyear contracts will further improve PTPP s revenue and earnings visibility, and ultimately lead to rerating of its share price. Leverage & Asset Turnover (x) Capital Expenditure ROE (%) Key Risks: Slowdown in property sector. PTPP s exposure to the property sector has increased notably with net profit contribution from the property arm at 23% in FY16. We estimate that 15%20% of PTPP s outstanding order book are contracts from private developers. A prolonged slowdown in the property market may pose risks to PTPP s earnings and cash flows. Slow execution of infrastructure project. Delay in project execution due to land acquisition and technical issues or funding constraints such as government s budget cut may cause revenue and earnings to fall short of our projections. Forward PE Band (x) Company Background PTPP is Indonesia's leading construction company with a portfolio ranging from building engineering to infrastructure construction projects. It has established a solid reputation in the construction of highrise buildings and ports. PB Band (x) Page 29

29 Pembangunan Perumahan Key Assumptions FY Dec 2014A 2015A 2016A 2017F 2018F New Contract Win (Rp bn) 20,240 27,074 32,600 38,760 44,244 Carry Over Contract (Rp 22,278 29,867 39,600 48,400 48,861 Segmental Breakdown FY Dec 2014A 2015A 2016A 2017F 2018F Revenues (Rpbn) Construction 10,662 11,611 11,815 11,174 11,275 Real Estate and Property 645 1,573 2,180 2,258 2,845 EPC 1, ,366 5,264 8,644 Others ,215 4,114 Total 12,427 14,217 16,459 21,911 26,878 Gross Profit (Rpbn) Construction 1,414 1,244 1,422 1,229 1,240 Real Estate and Property ,175 1,135 1,431 EPC ,124 Others (91.8) (124) (518) Total 1,732 2,007 2,456 3,404 4,275 Gross Profit Margins (%) Construction Real Estate and Property EPC Others (313.1) (117.1) (529.0) Total Income Statement (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F Revenue 12,427 14,217 16,459 21,911 26,878 Cost of Goods Sold (10,878) (12,210) (14,003) (18,507) (22,604) Gross Profit 1,550 2,007 2,456 3,404 4,275 Other Opng (Exp)/Inc (281) (410) (487) (714) (799) Operating Profit 1,268 1,597 1,968 2,690 3,476 Other Non Opg (Exp)/Inc (94.2) (50.5) (69.4) Associates & JV Inc Net Interest (Exp)/Inc (326) (326) (350) (483) (729) Exceptional Gain/(Loss) Pretax Profit 921 1,288 1,704 2,207 2,747 Tax (387) (442) (552) (760) (970) Minority Interest (0.1) (105) (128) (106) (133) Preference Dividend Net Profit ,023 1,341 1,644 Net Profit before Except ,023 1,341 1,644 EBITDA 1,326 1,678 2,071 3,019 3,879 Growth Revenue Gth (%) EBITDA Gth (%) Opg Profit Gth (%) Net Profit Gth (Preex) (%) Margins & Ratio Gross Margins (%) Opg Profit Margin (%) Net Profit Margin (%) ROAE (%) ROA (%) ROCE (%) Div Payout Ratio (%) Net Interest Cover (x) Page 30

30 Pembangunan Perumahan Quarterly / Interim Income Statement (Rpbn) FY Dec 1Q2016 2Q2016 3Q2016 4Q2016 1Q2017 Revenue 2,588 3,885 4,374 5,613 2,917 Cost of Goods Sold (2,228) (3,338) (3,765) (4,672) (2,526) Gross Profit Other Oper. (Exp)/Inc (105) (119) (124) (139) (155) Operating Profit Other Non Opg (Exp)/Inc (19.4) 30.6 (42.8) (37.8) (14.4) Associates & JV Inc Net Interest (Exp)/Inc (21.4) (66.5) (69.4) (193) 26.5 Exceptional Gain/(Loss) Pretax Profit Tax (90.4) (138) (145) (179) (102) Minority Interest (31.7) (23.3) (36.2) (36.8) (31.4) Net Profit Net profit bef Except EBITDA Growth Revenue Gth (%) (52.5) (48.0) EBITDA Gth (%) (67.9) 93.8 (4.0) 85.7 (65.3) Opg Profit Gth (%) (63.8) (70.6) Net Profit Gth (Preex) (%) (72.9) (17.8) (71.5) Margins Gross Margins (%) Opg Profit Margins (%) Net Profit Margins (%) Balance Sheet (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F Net Fixed Assets 710 2,989 4,178 10,849 13,946 Invts in Associates & JVs Other LT Assets ,225 2,225 2,225 Cash & ST Invts 2,611 3,302 9,424 2,671 1,272 Inventory 2,675 2,499 2,656 3,473 4,241 Debtors 7,244 8,829 10,920 14,537 18,737 Other Current Assets ,345 1,345 1,345 Total Assets 14,579 19,159 31,233 35,585 42,252 ST Debt 1,577 1,722 3,698 3,698 3,698 Creditor 7,022 7,372 10,237 13,387 17,097 Other Current Liab 1,263 1,677 1,943 1,943 1,943 LT Debt 1,455 1,827 3,048 3,048 4,548 Other LT Liabilities 928 1,414 1,510 1,510 1,510 Shareholder s Equity 2,334 4,410 9,796 10,893 12,216 Minority Interests ,000 1,106 1,240 Total Cap. & Liab. 14,579 19,159 31,233 35,585 42,252 NonCash Wkg. Capital 2,583 3,080 2,739 4,023 5,283 Net Cash/(Debt) (421) (247) 2,678 (4,074) (6,974) Debtors Turn (avg days) Creditors Turn (avg days) Inventory Turn (avg days) Asset Turnover (x) Current Ratio (x) Quick Ratio (x) Net Debt/Equity (X) CASH Net Debt/Equity ex MI (X) CASH Capex to Debt (%) ZScore (X) Page 31

31 Pembangunan Perumahan Cash Flow Statement (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F PreTax Profit 921 1,288 1,704 2,207 2,747 Dep. & Amort Tax Paid (387) (442) (552) (760) (970) Assoc. & JV Inc/(loss) Chg in Wkg.Cap. (719) (497) 341 (1,284) (1,259) Other Operating CF 410 (403) (608) Net Operating CF Capital Exp.(net) (160) (420) (1,305) (7,000) (3,500) Other Invts.(net) (192) (83.3) (124) Invts in Assoc. & JV (78.2) (125) (440) Div from Assoc & JV Other Investing CF (95.1) (33.7) Net Investing CF (525) (662) (1,826) (7,000) (3,500) Div Paid (126) (106) (177) (245) (321) Chg in Gross Debt , ,500 Capital Issues , Other Financing CF Net Financing CF 243 1,182 6,899 (245) 1,179 Currency Adjustments Chg in Cash ,100 (6,753) (1,400) Opg CFPS (Rp) Free CFPS (Rp) 25.3 (81.5) (65.8) (1,050) (416) Target Price & Ratings History Source: AllianceDBS, DBSVI Analyst: Chong TjenSan Tiesha PUTRI Page 32

32 Indonesia Company Guide Wijaya Karya Version 6 Bloomberg: WIKA IJ Reuters: WIKA.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 5 Jul 2017 HOLD Last Traded Price ( 5 Jul 2017): Rp2,220 (JCI : 5,825.10) Price Target 12mth: Rp2,050 (8% downside) (Prev Rp2,780) Analyst Chong TjenSan tjensan@alliancedbs.com Tiesha PUTRI tiesha.narandha@id.dbsvickers.com What s New Strong 5M17 new contracts signed, representing 53%/46% of our/management s FY17F target Revise down TP to Rp2,050; maintain HOLD Price Relative Forecasts and Valuation FY Dec (Rp m) 2015A 2016A 2017F 2018F Revenue 13,620 15,669 22,844 37,126 EBITDA 1,681 2,231 2,718 4,388 Pretax Profit 1,098 1,596 2,055 3,014 Net Profit 625 1,012 1,140 1,595 Net Pft (Pre Ex.) 625 1,012 1,140 1,595 Net Pft Gth (Preex) (%) EPS (Rp) EPS Pre Ex. (Rp) EPS Gth Pre Ex (%) 3 56 (20) 40 Diluted EPS (Rp) Net DPS (Rp) BV Per Share (Rp) 711 1,266 1,370 1,522 PE (X) PE Pre Ex. (X) P/Cash Flow (X) 57.3 nm nm nm EV/EBITDA (X) Net Div Yield (%) P/Book Value (X) Net Debt/Equity (X) 0.2 CASH ROAE (%) Earnings Rev (%): Consensus EPS (Rp): N/A Other Broker Recs: B: 26 S: 0 H: 6 Source of all data on this page: Company, AllianceDBS, DBSVI, Bloomberg Finance L.P. Positives priced in Maintain HOLD with a lower TP. We maintain our HOLD call on WIKA with a lower TP of Rp2,050. We are encouraged by the steady progress of WIKA s infrastructure projects, which we believe is one of the key reasons for its YTD share price outperformance relative to peers. However, we think WIKA s earnings outlook largely hinges on its signature JakartaBandung highspeed railway (HSR) project whose progress has remained slow. Despite financial close having been reached in May 2017, the disbursement of the loan from China Development Bank is still being delayed, pending the audit of land acquisition progress. We would like to see better progress on the HSR project along with the planned transitoriented development (TOD) before turning more positive on the stock. Sizeable backlog provides revenue visibility. WIKA clinched new contracts worth Rp20tr in 5M17 (+164% yoy). This represents 53%/46% of our/management s new contract forecasts for FY17F. We estimate that WIKA had Rp76.2tr backlog as at end of May 2017, providing revenue visibility of 3.3 years. Where we differ. Our FY17F net profit forecast is 9% lower than consensus as we expect higher capex and debt levels. Due to fiscal constraints faced by the government and selected infrastructure companies, we believe contractors have to raise their capex budgets and debt levels in order to grow their order books going forward. Potential catalyst. The disbursement of loan from China Development Bank would accelerate the progress of the Jakarta Bandung HSR project and improve WIKA s earnings outlook. In addition, more clarity on the TOD concept and funding, which is expected to compensate for the low IRR for the HSR project, would be a positive catalyst for WIKA. Valuation: We revise down our TP to Rp2,050, now pegged to 16x FY17F EPS (equal to the sector s mean PE). Key Risks to Our View: Delay in project rollout. Any delay in project rollout, especially the mega project JakartaBandung HSR, should lead to lowerthanexpected revenue and earnings. At A Glance Issued Capital (m shrs) 8,970 Mkt. Cap (Rpbn/US$m) 19,913 / 1,491 Major Shareholders (%) Republic of Indonesia (%) 65.2 Free Float (%) m Avg. Daily Val (US$m) 2.8 ICB Industry : Industrials / Construction & Materials ed: CK / sa:ma, PY

33 Wijaya Karya WHAT S NEW Revise up FY17F new contract and earnings Earnings revision. WIKA won new contract worth Rp20tr in 5M17 vs. our initial FY17 new contract forecasts of Rp37.6tr. Among the largest wins were SerangPanimbang toll road (Rp3.5tr) and CengkarengBatu CeperKunciran toll road (Rp2.2tr). Taking into account stronger than expected new contract achievement in 5M17, we revise up our FY17F new contract forecasts by 15% to Rp43tr. Our new contract forecast for FY17 implies a 21% yoy decline, in line with management s expectation. We raise our FY17F/FY18F net profit forecast by 3%/4%. Our revised new profit forecast implies 13%/40% net profit growth in FY17F/FY18F. Summary of earnings revision (in Rp bn) 2017F 2018F Old New Change Old New Change Revenue 22,703 22,844 1% 33,019 37,125 12% Gross profit 2,746 2,860 4% 3,951 4,461 13% EBIT 2,041 2,154 6% 3,043 3,538 16% Net Profit 1,111 1,140 3% 1,530 1,595 4% GP margin (%) EBIT margin (%) Net margin (%) New Contract Win 37,564 43,027 15% 37,652 37,771 0% Carry Over Contract 56,970 59,996 5% 62,372 74,484 19% Total Orderbook (cumulative) 92, ,356 11% 98, ,588 14% Capex 2,000 3,850 93% 3,000 3,850 28% Net interest income (exp.) (299) (390) 30% (607) (819) 35% Source: AllianceDBS, DBSVI Page 33

34 Wijaya Karya CRITICAL DATA POINTS TO WATCH New Contract Win (Rp bn) Critical Factors New contracts had peaked; eyes on project execution. After the award of the JakartaBandung highspeed railway contract in 2016, we expect WIKA s new contracts to decline by 21% yoy in FY17F. Nonetheless, we acknowledge that the company s revenue visibility has improved strongly with a contract backlog of Rp84.8tr, providing revenue visibility of 3.3 years. As new contract growth has peaked, we believe project execution and earnings delivery would be the key focus going forward. This hinges a great deal on the HSR contract which forms 21% of its total orderbook and has only achieved less than 5% progress thus far. Contract Backlog (Rp bn) Progress of JakartaBandung highspeed project. In 2016, WIKA was awarded the civil work contract of the JakartaBandung highspeed railway (HSR) worth Rp15.8tr. We estimate that this project contributed c.21% of WIKA s total backlog (as at end of May 2017). The mega project is now running behind schedule after breaking ground in Jan 2016 due to land acquisition issues. The project is scheduled to be delivered in mid2019. The resumption of JakartaBandung HSR construction, expected in July 2017, is important for WIKA in boosting its earnings growth. Blended Gross Margin (%) Transit oriented development to compensate for HSR s low IRR. The HSR consortium plans to develop a transitoriented development (TOD) in the vicinity of HSR s four stations i.e. Halim Perdanakusuma (East Jakarta), Karawang (West Java), Walini (West Java) and Tegalluar (Bandung, West Java). Walini would become the largest township project with a total area of 2,900ha, followed by Tegalluar (450ha). The consortium has appointed three worldclass property and urban development consultants (Aedas, Atkins and Surbana Jurong) back in Jan 2016, and more details on the TOD plan will be revealed this year. This should shed more light on how the consortium plans to compensate for HSR s low IRR (estimated FIRR is in the range of 6.5%10.8%). The HSR consortium plans to team up with private developers given the high capital requirement to develop new townships. Nonetheless, we believe WIKA Realty, WIKA s property arm, would play an important role in the development % New Contract 38% 27% 42% 46% 50% 45% 40% 35% 30% 25% 20% 15% 10% Government s tax collection. 20%40% of WIKA s annual new contracts for the period were infrastructure projects funded by the government. Slow tax collection may lead to fiscal budget shortfalls and some delay in government s projects. This may results in lowerthanexpected contract wins and earnings for WIKA. Rp tr M17 2M17 3M17 4M17 5M17 New contract, Rp tr (LHS) as % of FY17F (RHS) New Contract Based on Project Owner 5% ExGov't Gov't Page 34

35 Wijaya Karya Appendix 1: A look at Company's listed history what drives its share price? WIKA s share price vs. peers* WIKA share price (LHS) WIKA share price vs. peers* (RHS) Dec 18, 2012 = 1.0 4, ,500 3,000 2,500 B , ,500 1, A1 A Dec12 Jun13 Dec13 Jun14 Dec14 Jun15 Dec15 Jun16 Dec16 *Based on the average return of the listed stateowned contractors A: New contract achievement WIKA s share price underperformed its peers in as the company booked lowerthanexpected new contracts during the period. In 2013, WIKA s new contracts fell short of management s target by 11% or c.rp2tr. In 2014, WIKA only managed to secure Rp17.6tr worth of new contracts in FY14 ( 1% y oy) vs. management s guidance of Rp25.8tr. WIKA s share price vs. new contract 4,000 3,500 3,000 2,500 2,000 1,500 1, Dec12 Mar13 Jun13 Sep13 Dec13 Mar14 Jun14 Sep14 Dec14 Mar15 Jun15 Sep15 Dec15 Mar16 Jun16 Sep16 Dec16 Mar17 80,000 70,000 60,000 50,000 40,000 30,000 20,000 10,000 0 WIKA s share price Rp 4,000 3,500 3,000 2,500 2,000 1,500 1, WIKA was selected as one of the contractors to build phase 1 of MRT project in Jakarta 0 Dec12 Jun13 Dec13 Jun14 Dec14 Jun15 Dec15 Jun16 Gov't of Indonesia assigned WIKA to lead consortium of SOE in JakartaBandung HSR project JakartaBandung HSR project stalled after ground breaking ceremony in January PLN called off plan to develop mega power plant Java 5 WIKA share price (LHS) T12M new contract, Rp bn (RHS) B: Progress of mega projects WIKA s share price movement has been largely influenced by the state of mega project that it bid for or won, i.e. Jakarta MRT phase 1, JakartaBandung highspeed railway and Mega Power Plant Java 5. Page 35

36 Wijaya Karya Balance Sheet: Stronger capital post rights issue. WIKA had Rp6.9tr debt at the end of Mar However, the company is in a net cash position of Rp1.1tr. We expect WIKA s net gearing to rise to 0.3x by the end of 2017 from 0.1x as at the end of March Leverage & Asset Turnover (x) Listing of WIKA Gedung and WIKA Realty. The company is currently in the process of spinning off its building construction business and merging it into WIKA Gedung, one of WIKA s subsidiaries. Following the spinoff, WIKA plans to divest a 30% stake in WIKA Gedung through an IPO, which is expected to raise Rp1tr. WIKA also plans to list its property business, WIKA Realty, in Rpbn Capital Expenditure Share Price Drivers: Progress on HSR project. Improved clarity on the HSR project could act as a positive catalyst for WIKA. Among the key events to watch for are: i) land acquisition progress, and ii) disbursement of loan from China Development Bank. Faster land acquisition progress. Further reform on land acquisition which can accelerate the construction progress of infrastructure projects would be positive for WIKA s earnings and share price. ROE (%) Key Risks: Delay in infrastructure project execution. Any delay in project execution could lead to lower order book and earnings. Such newsflow could also create negative sentiment towards Indonesia's construction sector and lead to valuation derating. Lower free cashflow generation in the medium term. Aside from being the contractor, WIKA typically owns some stakes in the assets being built. This exposes WIKA to the risk of deteriorating cashflow generation, as such a business model requires high capital investments and normally generates negative cashflows in the early years of operations. Forward PE Band (x) Company Background Wijaya Karya is a construction company with interests in EPC, civil, building works, precast and realty. PB Band (x) Page 36

37 Wijaya Karya Key Assumptions FY Dec 2014A 2015A 2016A 2017F 2018F New Contract Win (Rp bn) 17,632 25,222 54,764 43,027 37,771 Contract Backlog (Rp bn) 23,784 23,302 28,526 59,329 73,817 Segmental Breakdown FY Dec 2014A 2015A 2016A 2017F 2018F Revenues (Rpbn) Construction 4,731 5,984 7,476 15,014 26,492 EPC 3,179 3,370 2,875 2,058 3,440 Industrial (Precast) 3,271 2,830 3,292 4,743 5,551 Property 1,283 1,436 2,026 1,029 1,643 Total 12,463 13,620 15,669 22,844 37,126 Gross Profit (Rpbn) Construction ,763 2,995 EPC Industrial (Precast) Property Total 1,425 1,655 2,227 2,860 4,461 Gross Profit Margins (%) Construction EPC Industrial (Precast) Property Total We assume HSR construction would contribute 32% and 33% to WIKA s FY17F and FY18F revenue respectively. Income Statement (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F Revenue 12,463 13,620 15,669 22,844 37,126 Cost of Goods Sold (11,039) (11,965) (13,442) (19,984) (32,665) Gross Profit 1,425 1,655 2,227 2,860 4,461 Other Opng (Exp)/Inc (393) (429) (527) (707) (923) Operating Profit 1,032 1,226 1,700 2,154 3,538 Other Non Opg (Exp)/Inc (131) (38.6) (61.0) (61.0) (61.0) Associates & JV Inc Net Interest (Exp)/Inc (124) (372) (384) (390) (819) Exceptional Gain/(Loss) Pretax Profit 1,139 1,098 1,596 2,055 3,014 Tax (395) (395) (448) (718) (1,199) Minority Interest (136) (78.0) (135) (198) (220) Preference Dividend Net Profit ,012 1,140 1,595 Net Profit before Except ,012 1,140 1,595 EBITDA 1,393 1,681 2,231 2,718 4,388 Growth Revenue Gth (%) EBITDA Gth (%) Opg Profit Gth (%) Net Profit Gth (Preex) (%) Margins & Ratio Gross Margins (%) Opg Profit Margin (%) Net Profit Margin (%) ROAE (%) ROA (%) ROCE (%) Div Payout Ratio (%) Net Interest Cover (x) Page 37

38 Wijaya Karya Quarterly / Interim Income Statement (Rpbn) FY Dec 1Q2016 2Q2016 3Q2016 4Q2016 1Q2017 Revenue 2,727 3,307 3,306 6,330 3,813 Cost of Goods Sold (2,435) (2,869) (2,919) (5,220) (3,401) Gross Profit , Other Oper. (Exp)/Inc (87.0) (141) (107) (193) (118) Operating Profit Other Non Opg (Exp)/Inc (0.7) (73.8) 12.7 Associates & JV Inc Net Interest (Exp)/Inc (60.4) (87.6) (86.6) (150) (57.1) Exceptional Gain/(Loss) Pretax Profit Tax (77.9) (88.7) (92.3) (190) (114) Minority Interest (22.5) (26.5) (20.3) (66.0) (20.1) Net Profit Net profit bef Except EBITDA , Growth Revenue Gth (%) (50.7) (39.8) EBITDA Gth (%) (46.7) 24.8 (10.0) (45.5) Opg Profit Gth (%) (61.7) 45.5 (6.0) (67.9) Net Profit Gth (Preex) (%) (69.4) (21.6) (59.8) Margins Gross Margins (%) Opg Profit Margins (%) Net Profit Margins (%) Balance Sheet (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F Net Fixed Assets 2,676 3,184 3,466 7,043 10,338 Invts in Associates & JVs 1,897 1,898 2,608 2,960 3,316 Other LT Assets 1,855 1,960 3,470 3,470 3,470 Cash & ST Invts 2,301 2,560 9,270 3,177 1,119 Inventory 817 1,031 1,248 1,890 3,079 Debtors 4,416 6,278 7,533 15,406 27,640 Other Current Assets 1,948 2,691 3,501 3,677 3,860 Total Assets 15,909 19,602 31,097 37,622 52,823 ST Debt 1,691 1,796 5,388 5,388 5,388 Creditor 3,903 4,323 4,680 9,856 17,744 Other Current Liab 2,882 4,479 4,538 4,755 4,983 LT Debt 1,275 1,646 1,289 1,289 6,789 Other LT Liabilities 1,281 1,921 2,703 2,703 2,703 Shareholder s Equity 3,888 4,375 11,352 12,287 13,651 Minority Interests 989 1,063 1,147 1,345 1,565 Total Cap. & Liab. 15,909 19,602 31,097 37,622 52,823 NonCash Wkg. Capital 395 1,198 3,065 6,362 11,852 Net Cash/(Debt) (665) (882) 2,593 (3,501) (11,058) Debtors Turn (avg days) Creditors Turn (avg days) Inventory Turn (avg days) Asset Turnover (x) Current Ratio (x) Quick Ratio (x) Net Debt/Equity (X) CASH Net Debt/Equity ex MI (X) CASH Capex to Debt (%) We expect the company to return to net debt position on the back of rising capex and working capital requirement. Page 38

39 Wijaya Karya Cash Flow Statement (Rpbn) FY Dec 2014A 2015A 2016A 2017F 2018F PreTax Profit 1,139 1,098 1,596 2,055 3,014 Dep. & Amort Tax Paid (370) (479) (448) (718) (1,199) Assoc. & JV Inc/(loss) (363) (283) (341) (352) (356) Chg in Wkg.Cap. (665) (811) (1,878) (3,297) (5,490) Other Operating CF (49.2) 503 (299) Net Operating CF (178) 238 (1,120) (2,039) (3,477) Capital Exp.(net) (1,036) (701) (285) (3,850) (3,850) Other Invts.(net) (316) (12.0) (67.9) Invts in Assoc. & JV (48.6) 282 (366) Div from Assoc & JV Other Investing CF (92.6) Net Investing CF (1,268) (325) (811) (3,850) (3,850) Div Paid (171) (129) (125) (205) (231) Chg in Gross Debt , ,500 Capital Issues , Other Financing CF 1,446 (4.0) Net Financing CF 2, ,638 (205) 5,269 Currency Adjustments Chg in Cash ,710 (6,094) (2,058) Opg CFPS (Rp) Free CFPS (Rp) (197) (75.2) (220) (657) (817) Our capex assumption is 50% lower than management s guidance but 56% higher than consensus forecasts. Target Price & Ratings History Source: AllianceDBS, DBSVI Analyst: Chong TjenSan Tiesha PUTRI Page 39

40 Indonesia Company Guide Wijaya Karya Beton Version 6 Bloomberg: WTON IJ Reuters: WTON.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 5 Jul 2017 BUY Last Traded Price ( 5 Jul 2017): Rp605 (JCI : 5,825.10) Price Target 12mth: Rp760 (26% upside) (Prev Rp1,050) Analyst Chong TjenSan tjensan@alliancedbs.com Tiesha PUTRI tiesha.narandha@id.dbsvickers.com What s New Maintain BUY with a new TP of Rp760 Improving revenue visibility with contract backlog already reaching 1.1x of our FY17 revenue forecast Building competitive edge by offering onestop service Price Relative Excellent proxy for construction growth Maintain BUY. As infrastructure projects move to execution phase, we believe Wijaya Karya Beton (WTON) is in a sweet spot as it starts to receive precast orders from contractors or project owners. Faster execution of infrastructure projects, and improving revenue visibility with contract backlog already reaching 1.1x of our FY17 revenue forecast should support an upward rerating of WTON s share price. The company currently trades at attractive PE valuations of 14x/13x on FY17F/18F earnings, at the lower end of its trading range. We maintain our BUY call with a lower TP of Rp760, providing 26% potential upside. Banking on WIKA s large order book. In 5M17, WTON clinched Rp2.3tr worth of new contracts (+48% yoy), representing 33% of management s target. We are confident that WTON will be able to achieve its target of Rp7tr in FY17 supported by contracts from its parent company Wijaya Karya (WIKA). With stronger balance sheet post rights issue in 4Q16, WIKA has more capacity to take on largerscale projects, which should further boost WTON s earnings outlook. Where we differ. Our Buy call and earnings is in line with consensus. Forecasts and Valuation FY Dec (Rp m) 2015A 2016A 2017F 2018F Revenue 2,653 3,482 4,743 5,551 EBITDA Pretax Profit Net Profit Net Pft (Pre Ex.) Net Pft Gth (Preex) (%) (47.1) EPS (Rp) EPS Pre Ex. (Rp) EPS Gth Pre Ex (%) (47) Diluted EPS (Rp) Net DPS (Rp) BV Per Share (Rp) PE (X) PE Pre Ex. (X) P/Cash Flow (X) 11.5 nm EV/EBITDA (X) Net Div Yield (%) P/Book Value (X) Net Debt/Equity (X) CASH ROAE (%) Earnings Rev (%): Consensus EPS (Rp): N/A Other Broker Recs: B: 14 S: 1 H: 1 Source of all data on this page: Company, AllianceDBS, DBSVI, Bloomberg Finance L.P Potential catalyst. The disbursement of loans from China Development Bank would accelerate the construction progress of JakartaBandung HSR project and boost WTON s earnings and order flows. On a macro level, a steady rollout of infrastructure projects will eventually filter down to precast players like WTON. We also expect 2Q17 revenue to be stronger as projects that were delayed in 1Q17 have picked up pace. Valuation: We revise down our TP to Rp760. We pegged our TP to 18x FY17F, a 10% premium to our revised target multiple for WIKA (on par with its historical mean). Key Risks to Our View: Delays in project rollout, particularly for the JakartaBandung HSR, would result in lowerthanexpected earnings for WTON. At A Glance Issued Capital (m shrs) 8,715 Mkt. Cap (Rpbn/US$m) 5,273 / 395 Major Shareholders (%) PT Wijaya Karya (Persero) Tbk 60.0 KKMS 8.8 Treasury Stock 4.3 Free Float (%) m Avg. Daily Val (US$m) 0.46 ICB Industry : Industrials / Construction & Materials ed: JS/ sa:ma, PY

41 Wijaya Karya Beton WHAT S NEW Building competitive edge Building competitive edge by offering onestop service. WTON targets to increase revenue contribution from precast concrete installation service from 4% in FY16 to 25% over the next five years. The company plans to offer a one stop service to customers, from precast production to installation, to strengthen its competitive position in the market. Our checks with management suggests that this onestop package typically commands higher margins compared to regular sales. However, this may delay the revenue recognition and hence stretch WTON s inventory days. We note that for regular sales, revenue is typically recorded once the precast concrete is shipped, whereas for onestop package, revenue is recorded only when the precast concrete is installed at the project owner s site. A case in point was the MedanKuala Namu railway project. The project faced some technical issues in 1Q17, leading to a delay in precast concrete installment and revenue recognition for WTON in the same period. South Lampung factory. WTON recently commissioned its new factory in South Lampung. The factory location enables the company to transport precast concrete via sea freight, which is generally cheaper compared to land transport. Based on our discussions with management, ASPs for precast sourced from the South Lampung factory to Balikpapan (East Kalimantan) is 36% lower compared to those sourced from the West Java factory. With this strategically located factory, we believe WTON will be able to benefit from the government s push to decentralise infrastructure development to areas outside Java. Page 41

42 Wijaya Karya Beton CRITICAL DATA POINTS TO WATCH Critical Factors Clear beneficiary of JakartaBandung HSR. The JakartaBandung highspeed railway (HSR) project is estimated to require 33.5m tons of precast concrete in with a contract value of Rp6tr Rp9tr. WTON expects to win at least Rp2tr Rp3tr of the total contract size. The company plans to set up several temporary production facilities near HSR s construction site to cater to this large order. In addition, the HSR consortium also plans to build a Transit Oriented Development (TOD) in the vicinity of HSR s four stations. We expect the HSR project to contribute 13%/22% to our FY17/FY18 revenue and EBIT forecasts. Firstmover advantage in ex Java market. WTON has continued to expand its coverage to markets outside Java where there are fewer competitors. In these areas, the company often serves as the only largescale precast producer, allowing it to maintain higher pricing and margins compared to those in Java. Based on our channel checks, WTON s staterun competitors will still be focusing on expanding in the Java market in the near future. Therefore, we are confident that WTON s position outside Java markets will remain firm. The rollout of toll roads and port projects outside Java should benefit WTON as it will be able to meet the precast requirements. In FY16, net margin of ex Java market was 500bps higher than Java s. Best proxy to domestic construction boom. We believe WTON is in a sweet spot to benefit from the government s ambitious infrastructure buildout plan given that it has the most extensive product offerings and geographical reach. It is worth noting that 24% of WTON s total installed capacity (610,000 ton p.a.) is located outside Java, the largest among peers. As the government plans to place more focus on infrastructure development outside Java, we believe WTON would be the biggest beneficiary of this shift. Based on our analysis, supply and demand dynamics for the domestic precast market would still be favourable in the next three years if the government manages to execute priority infra projects in a timely manner. We forecast a total precast supply of 4.75m tons p.a. from the four largest precastarms of listed stateowned contractors by the end of To estimate the demand, we selected power plants and transportationbased projects listed in the government s priority project list and JakartaBandung HSR. Based on our estimates, these infra projects would require 15.3m tons of precast within three years or 5.1m tons p.a. Hence, we believe that the demand and supply dynamics of the industry is still in favour of players like WTON. Gross margin (%) Production capacity ('000 tons) Sales volume ('000 tons) Utilisation rate (%) Page 42

43 Wijaya Karya Beton Appendix 1: A look at the company's listed history what drives its share price? WTON s share price vs. peers* 1,600 1,400 1,200 1, A B C 1 C 2 D WTON share price (LHS) WTON vs. construction (RHS) *Based on the average return of the listed stateowned contractors A: Strong pricing power WTON s share price rally post IPO in April 2014 was driven by its strong earnings growth. WTON had a strong competitive position with market share of 38.6% in 2013, while the second largest player only commanded 15.9% market share. This allows the company to enjoy strong pricing power and margin expansion. B: Intensifying competition Slower than expected rollout of government s infrastructure projects along with intensifying competition, especially among stateowned precast producers, caused WTON s share price to derate in In FY15, WTON saw its revenue declining by 19% on the combination of declining ASP and revenue contribution from stateowned contractors. Stateowned contractors such as Waskita Karya, Hutama Karya and PTPP started to expand precast production capacity and opted to source their precast requirements internally. This caused revenue contribution from stateowned contractors to decline by 43% yoy in FY15 with contribution to WTON s consolidated sales shrinking from 13% to 9%. Meanwhile, we reckon intense competition resulted in WTON lowering its selling price to maintain market share. The following chart shows the correlation between WTON s share price and revenue contribution from stateowned contractors. WTON share price vs. revenue from stateowned contractors 1,600 1,400 1,200 1, Apr14 Oct14 Apr15 Oct15 Apr16 Oct16 WTON share price (LHS) Revenue from SOE contractors, Rp bn (RHS) C: JakartaBandung highspeed railway (HSR) Despite the declining order book from stateowned contractors, the appointment of its parent company, WIKA, as one of the main contractors for the mega project JakartaBandung HSR is positive for WTON. Initially, the management indicated a potential contract worth Rp6tr Rp9tr from the mega project. This positive news caused WTON s share price to rally following the ground breaking of the project in early 2016 (C1). However, after a prolonged series of negotiations with China, the management guided that it would likely get a significantly lower contract target of Rp2tr Rp3tr as it was unable to meet some of the product specifications. This along with the delay in HSR construction caused the share price to derate (C2). D: Delay in project execution Delay in execution of infrastructure project caused WTON s revenue to fall short of market expectations. In 1Q17, WTON s revenue was flat yoy while net profit grew a marginal 2% despite its large contract backlog. Page 43

44 Wijaya Karya Beton Balance Sheet: Robust balance sheet to fund expansion plan. As at end of Mar 2017, WTON had Rp782bn of interestbearing debt, bringing its gross and net gearing to 0.3x. The company has allocated a capex budget of Rp680bn for FY17 which will be funded by the combination of internal cash and debt. The company also plans to sell treasury stocks to the public starting this year. Assuming the treasury stocks are sold at Rp665 /share, proceeds raised would be Rp236bn. Leverage & Asset Turnover (x) Share Price Drivers: Award of largesized, multiyear contracts. Among the potential contracts are the JakartaBandung HSR and Giant Sea Wall. There is also a clear pipeline of multiyear contracts from its parent WIKA which could amount to Rp1.5tr. Rpbn Capital Expenditure Better progress of JakartaBandung HSR construction. The construction progress of the JakartaBandung HSR project is running behind schedule after breaking ground in January Construction work has finally resumed after months of delay but the consortium has to wait for loan disbursement from China Development Bank before it is able to accelerate the construction progress. Better progress for the project would be a rerating catalyst for WTON s earnings and share price. ROE (%) Key Risks: Delay in government s infrastructure project rollout, particularly for the JakartaBandung HSR, would result in lowerthanexpected order book and profit for WTON. Delays in infrastructure project execution will cause WTON s revenue to fall short of expectations, and also lower WTON s profitability given its high operating leverage. Increasing competition in the Java market. Major SOE contractors are looking to increase their precast production capacities, particularly in the Java market. Intensifying competition may weaken WTON s pricing power in Java and erode its margins. In FY16, Java contributed 56% and 38% of WTON s consolidated revenue and earnings respectively. The bulk of WTON s cost of goods sold (COGS) is in USD. Steel and cement make up 30% and 20% of WTON s COGS respectively. Additionally, some overhead costs for its production facilities are also in USD, which exposes WTON s profitability to currency fluctuations. Nevertheless, the company has mitigated this risk by signing umbrella contracts for its key raw materials, enabling it to lock in prices for three months. Forward PE Band (x) PB Band (x) Company Background WTON is the dominant market leader in precast concrete with over 30% market share. Page 44

Adhi Karya Company Focus

Adhi Karya Company Focus Dec 9, 14 Adhi Karya Company Focus Maria Renata (maria.renata@trimegah.com) Cheapest infra proxy A story of the fallen angel Backed by disappointment from several default projects in the past, investors

More information

Flash Note. Indonesia. Indonesia Construction. Strong start to DBS Group Research. Equity 31 Jan 2017

Flash Note. Indonesia. Indonesia Construction. Strong start to DBS Group Research. Equity 31 Jan 2017 Indonesia Flash Note Refer to important disclosures at the end of this report DBS Group Research. Equity 31 Jan 2017 Indonesia Construction Analyst Chong Tjen San +60 3 26043972; tjensan@alliancedbs.com

More information

Wijaya Karya (WIKA IJ)

Wijaya Karya (WIKA IJ) Equity Indonesia Construction Wijaya Karya (WIKA IJ) BUY (Unchanged) Stock Data Target price (Rp) Prior TP (Rp) Shareprice (Rp) Rp2,900 Rp2,900 Rp1,745 Upside/downside (%) +66.2 Sharesoutstanding (m) 8,970

More information

BUY (Unchanged) Pembangunan Perumahan (PTPP IJ) Equity Indonesia Construction. Company Update. Solid fundamental with stellar performance

BUY (Unchanged) Pembangunan Perumahan (PTPP IJ) Equity Indonesia Construction. Company Update. Solid fundamental with stellar performance Pembangunan Perumahan (PTPP IJ) BUY (Unchanged) 17 January 2018 Company Update Equity Indonesia Construction Stock Data Target price (Rp) Prior TP (Rp) Shareprice (Rp) Rp4,700 Rp4,700 Rp3,030 Upside/downside

More information

BUY Target Price, IDR 2,100 Upside (downside) 17%

BUY Target Price, IDR 2,100 Upside (downside) 17% Friday, 5 March 2015 BUY Target Price, IDR 2,100 Upside (downside) 17% WSKT IJ/WSKT.JK Last Price, IDR 1,795 No. of shares (mn) 9,632 Market Cap, IDR bn 17,289 (US$ mn) 1,331 3M T/O, US$mn 4.3 Last Recommendation

More information

Waskita Karya (WSKT IJ)

Waskita Karya (WSKT IJ) Waskita Karya (WSKT IJ) BUY(Unchanged) 31 January 2018 Company Update Equity Indonesia Construction Stock Data Target price (Rp) Prior TP (Rp) Shareprice (Rp) Rp3,100 Rp3,100 Rp2,780 Upside/downside (%)

More information

Elnusa. Indonesia Company Guide. FULLY VALUED Last Traded Price: Rp500 (JCI : 4,814.09) Price Target : Rp400 (-20% downside) (Prev Rp205)

Elnusa. Indonesia Company Guide. FULLY VALUED Last Traded Price: Rp500 (JCI : 4,814.09) Price Target : Rp400 (-20% downside) (Prev Rp205) Indonesia Company Guide Version 1 Bloomberg: ELSA IJ Reuters: ELSA.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 28 Apr 2016 FULLY VALUED Last Traded Price: Rp500

More information

Wijaya Karya Beton (WTON IJ)

Wijaya Karya Beton (WTON IJ) Equity Research Result Notes Thursday,30 November 2017 BUY Maintain Last price (IDR) 600 Target Price (IDR) 800 Upside/Downside +33.3% Previous Target Price (IDR) 1,100 Stock Statistics Sector Bloomberg

More information

Waskita Beton Precast(WSBP IJ)

Waskita Beton Precast(WSBP IJ) Equity Research Company Update Monday,20 August 2018 BUY Maintain Waskita Beton Precast(WSBP IJ) Looking for more external works Last price (IDR) 382 Target Price (IDR) 500 Upside/Downside +30.9% Previous

More information

Thermal coal sector. Indonesia Industry Focus. The current rally has legs. DBS Group Research. Equity 19 Jan 2018 JCI : 6,472.70

Thermal coal sector. Indonesia Industry Focus. The current rally has legs. DBS Group Research. Equity 19 Jan 2018 JCI : 6,472.70 Indonesia Industry Focus Thermal coal sector Refer to important disclosures at the end of this report DBS Group Research. Equity 19 Jan 2018 The current rally has legs Coal stocks posted a good start and

More information

Bursa Malaysia. Company Guide

Bursa Malaysia. Company Guide Version 9 Bloomberg: BURSA MK Reuters: BMYS.KL Refer to important disclosures at the end of this report Malaysia Equity Research 26 Oct 2017 BUY Last Traded Price ( 25 Oct 2017): RM10.02 (KLCI : 1,739.05)

More information

BUY Target Price, Rp 4,350 Upside 11,9%

BUY Target Price, Rp 4,350 Upside 11,9% Friday, 9 May 214 BUY Target Price, Rp 4,350 Upside 11,9% SMSM IJ/SMSM.JK Last Price, Rp 3,885 No. of shares (bn) 1,439 Market Cap, Rp bn 5,591 (US$ mn) 484 3M T/O, US$mn 0.2 Last Recommendation 09Jan14

More information

Equity Research PT Waskita karya (Persero) Tbk

Equity Research PT Waskita karya (Persero) Tbk Equity Research karya (Persero) Tbk 3 August 2018 Construction, Equity Price IDR. 2070 Target Price IDR. 3140 JKSE Index 6011.72 3500 3000 2500 2000 1500 1000 500 0 Last Price (IDR) LS Stock Code Bloomberg

More information

Buy Dec 2018 TP (IDR) 4,770 Consensus Price (IDR) 4,002 TP to Consensus Price +19.2% vs. Last Price +61.1%

Buy Dec 2018 TP (IDR) 4,770 Consensus Price (IDR) 4,002 TP to Consensus Price +19.2% vs. Last Price +61.1% Pembangunan Perumahan Tbk (PTPP) Optimism Beyond Expectation Consistent and Stellar Growth in New Contracts Compared to other State-Owned Enterprises (SOEs) construction, PTPP s new contract growth figures

More information

PT Wijaya Karya Beton Tbk

PT Wijaya Karya Beton Tbk 2-Dec-16 2-Jan-17 2-Feb-17 2-Mar-17 2-Apr-17 2-May-17 2-Jun-17 2-Jul-17 2-Aug-17 2-Sep-17 2-Oct-17 2-Nov-17 7 December 2017 Precast, Equity Price IDR. 510 Target Price IDR. 775 JKSE Index 6,035.508 250

More information

Wika Beton (WTON IJ) BUY (Unchanged) Equity Indonesia Construction. In-line result with increased capacity. Results Note.

Wika Beton (WTON IJ) BUY (Unchanged) Equity Indonesia Construction. In-line result with increased capacity. Results Note. Wika Beton (WTON IJ) BUY (Unchanged) 03 May 2018 Results Note Equity Indonesia Construction Stock Data Target price (Rp) Rp750 Prior TP (Rp) Rp750 Shareprice (Rp) Rp464 Upside/downside (%) +61.6 Sharesoutstanding

More information

EQUITY RESEARCH. A secular growth story. Construction Sector. Initiating Coverage. 22 January 2014

EQUITY RESEARCH. A secular growth story. Construction Sector. Initiating Coverage. 22 January 2014 22 January 2014 EQUITY RESEARCH Construction Sector Initiating Coverage Stocks Adhi Karya Jaya Konstruksi Manggala Pratama Pembangunan Perumahan Wijaya Karya Waskita Karya Share Performance Ticker ADHI

More information

Telecom Sector. Regional Industry Focus. Stocks with 25-40% upside potential. DBS Group Research. Equity 11 Jul 2017 JCI : 5,814.

Telecom Sector. Regional Industry Focus. Stocks with 25-40% upside potential. DBS Group Research. Equity 11 Jul 2017 JCI : 5,814. Regional Industry Focus Telecom Sector Refer to important disclosures at the end of this report DBS Group Research. Equity 11 Jul 2017 Stocks with 25-40% upside potential Mobile revenue share is a critical

More information

Mitra Keluarga Company Focus

Mitra Keluarga Company Focus October 13, 2015 Mitra Keluarga Company Focus Patricia Gabriela (patricia.gabriela@trimegah.com) Titan in medical industry Initiate coverage on MIKA with BUY We initiate our coverage on MIKA with a Buy

More information

Flash Note. Bumi Armada (BAB MK) : BUY. 2Q16 in line: Recognized RM575m impairment. Malaysia Equity Research 29 Aug 2016

Flash Note. Bumi Armada (BAB MK) : BUY. 2Q16 in line: Recognized RM575m impairment. Malaysia Equity Research 29 Aug 2016 Refer to important disclosures at the end of this report Malaysia Equity Research 29 Aug 2016 Bumi Armada (BAB MK) : BUY Mkt. Cap: US$1,111m I 3m Avg. Daily Val: US$4.7m Last Traded Price : RM0.77 Price

More information

Mayora Indah. Indonesia Company Guide. HOLD Last Traded Price: Rp40,000 (JCI : 4,743.66) Price Target : Rp39,200 (-2% downside) (Prev Rp29,500)

Mayora Indah. Indonesia Company Guide. HOLD Last Traded Price: Rp40,000 (JCI : 4,743.66) Price Target : Rp39,200 (-2% downside) (Prev Rp29,500) Indonesia Company Guide Version 3 Bloomberg: MYOR IJ Reuters: MYOR.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 24 May 2016 HOLD Last Traded Price: Rp40,000 (JCI

More information

Waskita Karya. Lower TP on worries of funding. Exhibit 1 : Financial Highlights. Source : WSKT, Ciptadana Estimates

Waskita Karya. Lower TP on worries of funding. Exhibit 1 : Financial Highlights. Source : WSKT, Ciptadana Estimates BUY TP: Rp2,600 (+37.6%) Waskita Karya Lower TP on worries of funding Sector Bloomberg Ticker Share Price Performance Construction WSKT IJ Last price (Rp) 1,890 Avg. daily T/O (Rpbn/USDmn) 37.7/2.9 3m

More information

TP Sh.Pr. Ups/dw Earnings PE (x) EV/EBITDA (x) Div. yield (%) PEG (x) Rec. (Rp/sh) (Rp/sh) (%) CAGR('15-18)

TP Sh.Pr. Ups/dw Earnings PE (x) EV/EBITDA (x) Div. yield (%) PEG (x) Rec. (Rp/sh) (Rp/sh) (%) CAGR('15-18) February 6, 2015 Cement Sector Focus Maria Renata (maria.renata@trimegah.com) A new era in cement industry Government s intervention raises ASP uncertainty... We cut our ASP by ~6% or Rp3000/bag for our

More information

Construction Sector. Bigger, Stronger, and Wiser OVERWEIGHT. 25 June 2018

Construction Sector. Bigger, Stronger, and Wiser OVERWEIGHT. 25 June 2018 Construction Sector Bigger, Stronger, and Wiser OVERWEIGHT 25 June 2018 What does not kill you makes you stronger. Having withstood a tough year, SOE contractors survived the winter storm and are headed

More information

FOCUS RESEARCH. Site Visit to the Balikpapan Samarinda Toll Project BUY 22 NOVEMBER 2018

FOCUS RESEARCH. Site Visit to the Balikpapan Samarinda Toll Project BUY 22 NOVEMBER 2018 FOCUS RESEARCH 22 NOVEMBER 2018 COMPANY UPDATE BUY STOCK INFORMATION Bloomberg Code WTON IJ Sector Precast Concrete Current Price Rp 354 Target Price Rp 700 Upside/Downside 98% Share Out (bn shares) 8.7

More information

Wijaya Karya Beton(WTON IJ)

Wijaya Karya Beton(WTON IJ) Equity Research Results Note Wednesday,02 May 2018 BUY Maintain Last price (IDR) 476 Target Price (IDR) 730 Upside/Downside +53.4% Previous Target Price (IDR) 730 Stock Statistics Sector Bloomberg Ticker

More information

Nam Cheong Ltd (LHS) Singapore Company Focus BUY S$0.44 STI : 3, Expanding presence in Indonesia. DBS Group Research. Equity 30 Sep 2014

Nam Cheong Ltd (LHS) Singapore Company Focus BUY S$0.44 STI : 3, Expanding presence in Indonesia. DBS Group Research. Equity 30 Sep 2014 Singapore Company Focus Bloomberg: NCL SP Reuters: NMCG.SI Refer to important disclosures at the end of this report DBS Group Research. Equity 3 Sep 4 BUY S$.44 STI : 3,89.7 Price Target : -Month S$.5

More information

Indonesia Company Guide Unilever Indonesia

Indonesia Company Guide Unilever Indonesia Indonesia Company Guide Version 4 Bloomberg: UNVR IJ Reuters: UNVR.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 9 Feb 2017 FULLY VALUED Last Traded Price ( 8 Feb

More information

Tenaga Nasional. Company Guide

Tenaga Nasional. Company Guide Version 5 Bloomberg: TNB MK Reuters: TENA.KL Refer to important disclosures at the end of this report Malaysia Equity Research 27 Oct 2016 BUY Last Traded Price ( 27 Oct 2016): RM14.32 (KLCI : 1,669.03)

More information

Semen Baturaja (Persero) (SMBR IJ)

Semen Baturaja (Persero) (SMBR IJ) 1/14/16 2/11/16 3/10/16 4/7/16 5/5/16 6/2/16 6/30/16 7/28/16 8/25/16 9/22/16 10/20/16 11/17/16 12/15/16 1/12/17 Equity Research Company Update Monday, 16 January 2017 SELL Maintain Last price Rp 2,200

More information

Overseas Education (LHS)

Overseas Education (LHS) Singapore Company Guide Version 2 Bloomberg: OEL SP EQUITY Reuters: OVER.SI Refer to important disclosures at the end of this report DBS Group Research. Equity 17 Feb 2016 HOLD Last Traded Price: S$0.49

More information

Tower Bersama Infrastructure

Tower Bersama Infrastructure Indonesia Company Guide Version 3 Bloomberg: TBIG IJ Reuters: TBIG.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 13 Feb 2017 HOLD Last Traded Price ( 10 Feb 2017):

More information

PT PP (Persero) (LHS)

PT PP (Persero) (LHS) Indonesia Company Focus Bloomberg: PTPP IJ EQUITY Refer to important disclosures at the end of this report DBS Group Research. Equity 24 Jun 2014 BUY Rp1,775 JCI : 4,847.70 (Initiating Coverage) Price

More information

Animal Protein. Indonesia Industry Focus. Supply adjustment to nullify the impact of weak demand. DBS Group Research. Equity 26 Oct 2017

Animal Protein. Indonesia Industry Focus. Supply adjustment to nullify the impact of weak demand. DBS Group Research. Equity 26 Oct 2017 Indonesia Industry Focus Animal Protein Refer to important disclosures at the end of this report DBS Group Research. Equity 26 Oct 2017 Supply adjustment to nullify the impact of weak demand The culling

More information

Indonesia Cement Sector

Indonesia Cement Sector Indonesia Industry Focus Indonesia Cement Sector Refer to important disclosures at the end of this report DBS Group Research. Equity 29 Sep 2015 Incumbents under siege Supply-demand balance will remain

More information

Asian Pay Television Trust (LHS)

Asian Pay Television Trust (LHS) SingaporeCompany Guide Edition 1 Version 1 Bloomberg: APTT SP Reuters: ASIA.SI Refer to important disclosures at the end of this report DBS Group Research. Equity 2 Dec 2015 HOLD Last Traded Price: S$0.745

More information

Indonesia Company Guide PT Sarana Menara Nusantara

Indonesia Company Guide PT Sarana Menara Nusantara Indonesia Company Guide Version 4 Bloomberg: TOWR IJ Reuters: TOWR.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 1 Jun 2017 BUY Last Traded Price ( 31 May 2017):

More information

Pembangunan Perumahan (PTPP IJ)

Pembangunan Perumahan (PTPP IJ) Equity Research Company Update Tuesday, 31 October 2017 BUY Maintain Last price (IDR) 2,860 Target Price (IDR) 3,900 Upside/Downside +36.4% Previous Target Price (IDR) 3,900 Stock Statistics Sector Bloomberg

More information

Tenaga Nasional. Company Guide

Tenaga Nasional. Company Guide Version 9 Bloomberg: TNB MK Reuters: TENA.KL Refer to important disclosures at the end of this report Malaysia Equity Research 27 Oct 2017 BUY Last Traded Price ( 26 Oct 2017): RM14.34 (KLCI : 1,736.80)

More information

MNCS COMPANY UPDATE MNC Sekuritas Research Division September 18, 2017

MNCS COMPANY UPDATE MNC Sekuritas Research Division September 18, 2017 MNCS COMPANY UPDATE MNC Sekuritas Research Division September 18, 2017 PT Waskita Beton Precast Tbk (WSBP) Basic Industry and Chemicals Bargain Hunting Time! Target Price Stock Data Current Price 52wk

More information

Jasa Marga(JSMR IJ) Equity Research Results Note BUY. Monday,30 April 2018

Jasa Marga(JSMR IJ) Equity Research Results Note BUY. Monday,30 April 2018 Equity Research Results Note Monday,30 April 2018 BUY Maintain Last price (IDR) 4,210 Target Price (IDR) 5,300 Upside/Downside +25.9% Previous Target Price (IDR) 5,300 Stock Statistics Sector Bloomberg

More information

JCI : 5, STOCKS

JCI : 5, STOCKS Indonesia Industry Focus Thermal coal sector Refer to important disclosures at the end of this report DBS Group Research. Equity 15 Nov 217 218: Muted output growth to support coal prices Strong coal prices

More information

Market Access. Results Review 4Q15. M&A Securities. Digi.Com Berhad. Survives the Headwinds BUY (TP:RM5.90) Results Review

Market Access. Results Review 4Q15. M&A Securities. Digi.Com Berhad. Survives the Headwinds BUY (TP:RM5.90) Results Review M&A Securities Results Review 4Q15 PP14767/09/2012(030761) Digi.Com Berhad BUY (TP:RM5.90) Wednesday, February 10, 2016 Results Review Survives the Headwinds Current Price (RM) New Fair Value (RM) Previous

More information

Kimlun Corp. Company Guide

Kimlun Corp. Company Guide Version 10 Bloomberg: KICB MK Reuters: KICB.KL Refer to important disclosures at the end of this report Malaysia Equity Research 24 Jul 2017 BUY Last Traded Price ( 21 Jul 2017): RM2.29 (KLCI : 1,759.16)

More information

Market Access. M&A Securities. Results Review 1Q15. BIMB Holdings Bhd BUY (TP:RM4.84) Brilliant Beginning. Results Review

Market Access. M&A Securities. Results Review 1Q15. BIMB Holdings Bhd BUY (TP:RM4.84) Brilliant Beginning. Results Review M&A Securities Results Review 1Q15 PP14767/09/2012(030761) BIMB Holdings Bhd BUY (TP:RM4.84) Wednesday, May 27, 2015 Brilliant Beginning Results Review Actual vs. expectation. BIMB Holdings Berhad (BIMB)

More information

Telkom (TLKM IJ) HOLD (from Buy) Recovery mostly priced-in. Equity Indonesia Telecommunication. Company Update. 28 November 2018

Telkom (TLKM IJ) HOLD (from Buy) Recovery mostly priced-in. Equity Indonesia Telecommunication. Company Update. 28 November 2018 Equity Indonesia Telecommunication Telkom (TLKM IJ) HOLD (from Buy) Stock Data Target price (Rp) Prior TP (Rp) Shareprice (Rp) Rp4, Rp4,1 Rp3,72 Upside/downside (%) +7.5 Sharesoutstanding (m) 99,62 Marketcap.

More information

Macau Gaming Sector SECTOR REVIEW. What can excite you to pay more? Figure 1: Limited room for upside surprises. Source: DICJ, Credit Suisse estimates

Macau Gaming Sector SECTOR REVIEW. What can excite you to pay more? Figure 1: Limited room for upside surprises. Source: DICJ, Credit Suisse estimates Asia Pacific/Hong Kong Equity Research Casinos & Gaming Research Analysts Gabriel Chan, CFA 852 211 6523 gabriel.chan@credit-suisse.com Macau Gaming Sector SECTOR REVIEW What can excite you to pay more?

More information

Indonesia Cement Sector

Indonesia Cement Sector Indonesia Industry Focus Indonesia Cement Sector Refer to important disclosures at the end of this report DBS Group Research. Equity 30 Sep 2016 Nobody s position is sacrosanct Recent stock rallies unwarranted

More information

Wika Beton. Exhibit 1 : Financial Highlights. Source : WTON, Ciptadana Estimates

Wika Beton. Exhibit 1 : Financial Highlights. Source : WTON, Ciptadana Estimates BUY TP: Rp910 (+73.3%) Wika Beton Solid set of results, strong outlook remains Sector Bloomberg Ticker Share Price Performance Construction WTON IJ Last price (Rp) 525 Avg. daily T/O (Rpbn/USDmn) 5.4/0.4

More information

Lippo Karawaci (LHS) Indonesia Company Guide

Lippo Karawaci (LHS) Indonesia Company Guide Indonesia Company Guide Version 3 Bloomberg: LPKR IJ Reuters: LPKR.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 18 Jul 2016 FULLY VALUED Last Traded Price: Rp1,170

More information

Indonesia Banks. Indonesia Industry Focus. Improving growth traction. DBS Group Research. Equity 17 Mar 2015 JCI : 5,426.47

Indonesia Banks. Indonesia Industry Focus. Improving growth traction. DBS Group Research. Equity 17 Mar 2015 JCI : 5,426.47 Indonesia Industry Focus Indonesia Banks Refer to important disclosures at the end of this report DBS Group Research. Equity 17 Mar 2015 Improving growth traction FY14 results largely in line for big banks

More information

Buy. Morning Call. Bank Al-Falah Limited (BAFL) IFC Capital Injection; EPS Accretive; Revised Earnings, BUY. November 10, 2014

Buy. Morning Call. Bank Al-Falah Limited (BAFL) IFC Capital Injection; EPS Accretive; Revised Earnings, BUY. November 10, 2014 Morning Call November 10, 2014 Bank Al-Falah Limited (BAFL) Banks IFC Capital Injection; EPS Accretive; Revised Earnings, BUY Buy Target Price 38.3 Last Closing Upside 22.3% KSE Code Bloomberg Code Market

More information

Market Access. M&A Securities. Results Review 1Q15. Axiata Group Berhad. Slow in Recovery. Wednesday, May 20, 2015 HOLD (TP:RM7.

Market Access. M&A Securities. Results Review 1Q15. Axiata Group Berhad. Slow in Recovery. Wednesday, May 20, 2015 HOLD (TP:RM7. M&A Securities Results Review 1Q15 PP14767/09/2012(030761) Axiata Group Berhad Wednesday, May 20, 2015 HOLD (TP:RM7.40) Slow in Recovery Results Review Actual vs. expectations. Axiata Group Bhd (Axiata)

More information

Market Access. M&A Securities. Results Review 1Q15. Malayan Banking Bhd BUY (TP: RM10.70) Stabilizing Period. Results Review

Market Access. M&A Securities. Results Review 1Q15. Malayan Banking Bhd BUY (TP: RM10.70) Stabilizing Period. Results Review M&A Securities Results Review 1Q15 PP14767/09/2012(030761) Malayan Banking Bhd BUY (TP: RM10.70) Friday, May 29, 2015 Stabilizing Period Results Review Actual vs. expectation. Malayan Banking Berhad (Maybank)

More information

Tenaga Nasional Berhad TP: RM17.38 (+16.5%)

Tenaga Nasional Berhad TP: RM17.38 (+16.5%) COMPANY UPDATE Wednesday, December 20, 2017 FBMKLCI: 1,736.95 Sector: Power & Utilities THIS REPORT IS STRICTLY FOR INTERNAL CIRCULATION ONLY* Tenaga Nasional Berhad TP: RM17.38 (+16.5%) RP2 Uncertainty

More information

Mitra Adiperkasa. Indonesia Company Guide

Mitra Adiperkasa. Indonesia Company Guide Indonesia Company Guide Version 8 Bloomberg: MAPI IJ Reuters: MAPI.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 2 Nov 2017 BUY Last Traded Price ( 1 Nov 2017):

More information

Market Access. M&A Securities. Results Review (1Q16) Gamuda Berhad. Strong Job Flow in the Pipeline BUY (TP: RM5.80)

Market Access. M&A Securities. Results Review (1Q16) Gamuda Berhad. Strong Job Flow in the Pipeline BUY (TP: RM5.80) M&A Securities Results Review (1Q16) PP14767/09/2012(030761) Thursday, December 17, 2015 Gamuda Berhad BUY (TP: RM5.80) Strong Job Flow in the Pipeline Results Review Actual vs. expectations. Gamuda (Gamuda

More information

Results Review. 3QFY13: Downsizing its workforce. Technology Bloomberg Ticker: UNI MK Bursa Code: November 2013

Results Review. 3QFY13: Downsizing its workforce. Technology Bloomberg Ticker: UNI MK Bursa Code: November 2013 Results Review (Member of Alliance Bank group) PP7766/03/2013 (032116) 8 November 2013 Analyst Toh Woo Kim wookim@alliancefg.com +603 2604 3917 12-month upside potential Previous target price 0.89 Revised

More information

Bank Tabungan Negara. Indonesia Company Guide

Bank Tabungan Negara. Indonesia Company Guide Indonesia Company Guide Version 9 Bloomberg: BBTN IJ Reuters: BBTN.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 27 Mar 2017 HOLD Last Traded Price ( 24 Mar 2017):

More information

TCL Communication (LHS)

TCL Communication (LHS) China / Hong Kong Company Focus Bloomberg: 2618 HK EQUITY Reuters: 2618.HK DBS Group Research. Equity 13 August 2015 Refer to important disclosures at the end of this report HOLD Last Traded Price: HK$5.73

More information

AUSTRALIAN INFRASTRUCTURE METRIC

AUSTRALIAN INFRASTRUCTURE METRIC AUSTRALIAN INFRASTRUCTURE METRIC December Quarter 216 The IPA/BIS Oxford Economics Australian Infrastructure Metric (the Metric) is the leading indicator of real investment in Australia s civil infrastructure.

More information

Equity Research. PT Wijaya Karya Bangunan GedungTbk. 14 August 2018 Building Construction, Equity

Equity Research. PT Wijaya Karya Bangunan GedungTbk. 14 August 2018 Building Construction, Equity 1-Dec-17 1-Jan-18 1-Feb-18 1-Mar-18 1-Apr-18 1-May-18 1-Jun-18 1-Jul-18 1-Aug-18 Equity Research 14 August 2018 Building Construction, Equity Price IDR. 222 Target Price IDR. 488 JKSE Index 5861.25 180

More information

CSE Global. Singapore Company Focus

CSE Global. Singapore Company Focus Singapore Bloomberg: CSE SP Reuters: CSES.SI DBS Group Research. Equity 14 Nov 2012 HOLD S$0.855 STI : 3,007.57 (Downgrade from BUY) Price Target : 12-month S$ 0.85 (Prev S$ 0.90) Reason for Report : Change

More information

Trendlines Group (LHS)

Trendlines Group (LHS) Singapore Company Guide Version 1 Bloomberg: TTGL SP Reuters: THET.SI Refer to important disclosures at the end of this report DBS Group Research. Equity 26 Feb 2016 BUY Last Traded Price: S$1 (STI : 2,619.96)

More information

Indocement Tunggal Prakarsa (INTP IJ)

Indocement Tunggal Prakarsa (INTP IJ) 1/14/16 2/11/16 3/10/16 4/7/16 5/5/16 6/2/16 6/30/16 7/28/16 8/25/16 9/22/16 10/20/16 11/17/16 12/15/16 1/12/17 Equity Research Company Update Monday, 16 January 2017 SELL Maintained Last price Rp 14,950

More information

Indonesia Construction Sector Sector Focus

Indonesia Construction Sector Sector Focus August 25, 2015 Indonesia Construction Sector Sector Focus Tim Alamsyah, Sebastian Tobing CFA (Tim.Alamsyah@trimegah.com) (Sebastian.Tobing@trimegah.com) Growth still on the table Massive opportunity,

More information

Bumi Serpong Damai (BSDE.IJ)

Bumi Serpong Damai (BSDE.IJ) May-14 Jul-14 Sep-14 Nov-14 Jan-15 Mar-15 May-15 Equity Research Company Update Thursday,02 Feb 2017 BUY Maintain Last price Rp 2,200 Target Price Rp2,200 Upside/Downside 0. Previous Target Price Stock

More information

CEMEX Cement. Quarterly Report February 9, CEMEX remains on track to regain its investment grade.

CEMEX Cement. Quarterly Report February 9, CEMEX remains on track to regain its investment grade. Quarterly Report CEMEX Market Outperformer 2017 Price Target US$11.0 Price 8.9 12M Price Range 4.1/9.5 Shares Outstanding (Mill)* 1,545 Market Cap USD (Mill) 13,797 Float 78.6% Net Debt USD (Mill)** 12,516

More information

CEMEX Cement. Quarterly Report July 27, CX: Proving the success of its Value-before-Volume strategy.

CEMEX Cement. Quarterly Report July 27, CX: Proving the success of its Value-before-Volume strategy. Quarterly Report CEMEX Market Outperformer 12M FWD Price Target US$10.8 Price 7.1 12M Price Range 3.8/8.6 Shares Outstanding (Mill)* 1,542 Market Cap USD (Mill) 10,976 Float 78.6% Net Debt USD (Mill)**

More information

Ramayana Lestari (RALS IJ)

Ramayana Lestari (RALS IJ) Ramayana Lestari (RALS IJ) HOLD (Unchanged) 29 March 2018 Results Note Equity Indonesia Retail Stock Data Target price (Rp) Prior TP (Rp) Shareprice (Rp) Rp1,185 Rp1,030 Rp1,280 Upside/downside (%) (7.4)

More information

PT Acset Indonusa Tbk BUY: IDR 1,917 (+30.4%)

PT Acset Indonusa Tbk BUY: IDR 1,917 (+30.4%) Analysts Joshua Tan Analyst, Equity Research joshua.tan@u.nus.edu Jeremy Ee Analyst, Equity Research jeremy.ee@u.nus.edu Brandon Yeap Analyst, Equity Research brandonyeap.yt@u.nus.edu Pai Hong Wei Analyst,

More information

Market Access. Company Note. M&A Securities. Nestle Malaysia Berhad. Steering Away From Turbulence. Tuesday, June 21, 2016 HOLD (TP: RM79.

Market Access. Company Note. M&A Securities. Nestle Malaysia Berhad. Steering Away From Turbulence. Tuesday, June 21, 2016 HOLD (TP: RM79. M&A Securities Company Note PP14767/09/2012(030761) Nestle Malaysia Berhad Steering Away From Turbulence 1Q16 results review. To recap, Nestle Malaysia Berhad (Nestle) registered its 1Q16 revenue at RM1.3

More information

Timah (TINS IJ) Equity Research Company Update BUY. Better outlook on supply risks. Thursday,05 October 2017

Timah (TINS IJ) Equity Research Company Update BUY. Better outlook on supply risks. Thursday,05 October 2017 Equity Research Company Update Thursday,5 October 217 BUY Maintain Timah (TINS IJ) Better outlook on supply risks Last price (IDR) 845 Target Price (IDR) 1,1 Upside/Downside +3.2% Previous Target Price

More information

Market Access. Briefing Notes. M&A Securities. BIMB Holdings Bhd BUY (TP:RM4.60) Shifting into High Gears

Market Access. Briefing Notes. M&A Securities. BIMB Holdings Bhd BUY (TP:RM4.60) Shifting into High Gears M&A Securities Briefing Notes PP14767/09/2012(030761) BIMB Holdings Bhd BUY (TP:RM4.60) Monday, October 12, 2015 Shifting into High Gears We attended post-1h15 results briefing organized by BIMB Holdings

More information

Sheng Siong Group (LHS)

Sheng Siong Group (LHS) Singapore Company Guide Edition 1 Version 2 Bloomberg: SSG SP Reuters: SHEN.SI Refer to important disclosures at the end of this report DBS Group Research. Equity 15 Dec 2015 BUY Last Traded Price: S$0.84

More information

Market Access. M&A Securities. Results Review 1Q16. Malayan Banking Berhad. Hampered by Loan Loss. Monday, May 30, 2016 HOLD (TP: RM9.

Market Access. M&A Securities. Results Review 1Q16. Malayan Banking Berhad. Hampered by Loan Loss. Monday, May 30, 2016 HOLD (TP: RM9. M&A Securities Results Review 1Q16 PP14767/09/2012(030761) Malayan Banking Berhad Monday, May 30, 2016 HOLD (TP: RM9.10) Hampered by Loan Loss Results Review Actual vs. expectations. Malayan Banking Bhd

More information

TICKER Price (Rp.) Mkt. Cap (%) TARGET P/E (X) ROE (%) EPS g (%) 13-Sep-11 (Rpbn) to JCI Rec Price

TICKER Price (Rp.) Mkt. Cap (%) TARGET P/E (X) ROE (%) EPS g (%) 13-Sep-11 (Rpbn) to JCI Rec Price September 16, 2011 TRIM Sector Update Bank: Strong Result Amid Global Uncertainty Hanel Topada Era Tania Equity Analyst hanel.tania@trimegah.com (021) 2924-9098 Loans Growth Pull Back on Seasonality Banking

More information

Malaysian Bulk Carriers

Malaysian Bulk Carriers Bloomberg: MBC MK Equity Reuters: MBCB.KL Refer to important disclosures at the end of this report Malaysia Equity Research 25 Aug 214 HOLD RM1.77 1.77KLCI : 1,87.99 Downgrade from BUY Price Target :12-Month

More information

Supermax. Rubber Gloves. Company Update. Bouncing back in BUY (maintain) Price Target: RM2.60 ( ) 26 January 2012

Supermax. Rubber Gloves. Company Update. Bouncing back in BUY (maintain) Price Target: RM2.60 ( ) 26 January 2012 Rubber Gloves 26 January 2012 PP 10251/07/2012(030525) Company Update Supermax SUCB MK RM2.20 BUY (maintain) Bouncing back in 2012 Bright skies ahead We recently visited Supermax to get an update on the

More information

Indonesia Company Guide Perusahaan Gas Negara

Indonesia Company Guide Perusahaan Gas Negara Indonesia Company Guide Version 6 Bloomberg: PGAS IJ Reuters: PGAS.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 30 Apr 2018 BUY Last Traded Price ( 27 Apr 2018):

More information

Market Access. Results Review (4Q16) M&A Securities. Scientex Berhad. Unstoppable Growth Amid Challenging Times. Tuesday, September 27, 2016

Market Access. Results Review (4Q16) M&A Securities. Scientex Berhad. Unstoppable Growth Amid Challenging Times. Tuesday, September 27, 2016 Market Access M&A Securities Results Review (4Q16) PP14767/04/2012(029 Tuesday, September 27, 2016 Scientex Berhad Unstoppable Growth Amid Challenging Times BUY (TP: RM8.33) Current Price (RM) New Target

More information

Tenaga Nasional. Company Guide

Tenaga Nasional. Company Guide Version 8 Bloomberg: TNB MK Reuters: TENA.KL Refer to important disclosures at the end of this report Malaysia Equity Research 28 Jul 2017 BUY Last Traded Price ( 27 Jul 2017): RM14.24 (KLCI : 1,770.07)

More information

Hartalega Holdings. Company Guide

Hartalega Holdings. Company Guide Version 8 Bloomberg: HART MK Reuters: HTHB.KL Refer to important disclosures at the end of this report Malaysia Equity Research 13 Mar 2017 HOLD La st Traded Price ( 10 Mar 2017): RM4.80 (KLCI : 1,717.58)

More information

Bank Mandiri. Indonesia Company Guide

Bank Mandiri. Indonesia Company Guide Indonesia Company Guide Version 8 Bloomberg: BMRI IJ Reuters: BMRI.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 24 Mar 2017 HOLD Last Traded Price ( 23 Mar 2017):

More information

Padini Holdings. Company Guide. HOLD (Downgrade from Buy) : 5,122.10) Price Target 12-mth. Not everything fits well

Padini Holdings. Company Guide. HOLD (Downgrade from Buy) : 5,122.10) Price Target 12-mth. Not everything fits well Version 7 Bloomberg: PAD MK Reuters: PDNI.KL Refer to important disclosures at the end of this report Malaysia Equity Research 28 Nov 2016 HOLD (Downgrade from Buy) Last Traded Price ( 25 Nov 2016): RM2.82

More information

China Tian Lun Gas (1600 HK)

China Tian Lun Gas (1600 HK) China Tian Lun Gas (1600 HK) Scrambling for growth in vehicle market We initiate on China Tian Lun Gas with an Outperform rating. Our DCF-based target price of HK$6.80 suggests 16% potential upside. The

More information

Market Access. Results Review 1Q FY17. M&A Securities. Hartalega Holdings Berhad. Record Sales with Lower Margins BUY (TP:RM4.

Market Access. Results Review 1Q FY17. M&A Securities. Hartalega Holdings Berhad. Record Sales with Lower Margins BUY (TP:RM4. M&A Securities Results Review 1Q FY17 PP14767/09/2012(030761) Hartalega Holdings Berhad BUY (TP:RM4.78) Wednesday, August 03, 2016 Record Sales with Lower Margins Results Review Current Price (RM) New

More information

Panin Bank. Indonesia Company Guide. BUY (Upgrade from HOLD) Last Traded Price: Rp780 (JCI. Undervalued proposition

Panin Bank. Indonesia Company Guide. BUY (Upgrade from HOLD) Last Traded Price: Rp780 (JCI. Undervalued proposition Indonesia Company Guide Version 5 Bloomberg: PNBN IJ Reuters: PNBN.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 1 Aug 2016 BUY (Upgrade from HOLD) Last Traded

More information

Market Access. Company Update. M&A Securities. Public Bank Berhad. Wednesday, April 27, BUY (Target Price: RM21.38) Proves to be Bellwether

Market Access. Company Update. M&A Securities. Public Bank Berhad. Wednesday, April 27, BUY (Target Price: RM21.38) Proves to be Bellwether M&A Securities Company Update PP14767/09/2012(030761) Public Bank Berhad Wednesday, April 27, 2016 BUY (Target Price: RM21.38) Proves to be Bellwether We recommend investors to accumulate Public Bank Bhd

More information

Indofood Sukses Makmur(INDF IJ)

Indofood Sukses Makmur(INDF IJ) Equity Research Company Update Thursday,27 September 2018 BUY MAINTAIN Last price (IDR) 5,975 Target Price (IDR) 8,200 Upside/Downside +37.2% Previous Target Price (IDR) 8,000 Stock Statistics Sector Bloomberg

More information

Telekom Malaysia. Company Guide. BUY : 1,627.26) Price Target 12-mth. Stable growth in fixed-line business. Malaysia Equity Research 28 Nov 2016

Telekom Malaysia. Company Guide. BUY : 1,627.26) Price Target 12-mth. Stable growth in fixed-line business. Malaysia Equity Research 28 Nov 2016 Version 4 Bloomberg: T MK Reuters: TLMM.KL Refer to important disclosures at the end of this report Malaysia Equity Research 28 Nov 2016 BUY Last Traded Price ( 25 Nov 2016): RM6.22 (KLCI : 1,627.26) Price

More information

SMRT. Singapore Company Focus

SMRT. Singapore Company Focus Singapore Company Focus Bloomberg: MRT SP Reuters:.SI Refer to important disclosures at the end of this report DBS Group Research. Equity 18 Jul 2016 FULLY VALUED (Downgrade from HOLD) Last Traded Price:

More information

Semen Indonesia (Persero)(SMGR IJ)

Semen Indonesia (Persero)(SMGR IJ) Equity Research Company Update Friday, 20 October 2017 HOLD Maintain Last price (IDR) 10,500 Target Price (IDR) 9,600 Upside/Downside -8.6% Previous Target Price (IDR) 8,600 Stock Statistics Sector Bloomberg

More information

Nippon Indosari (ROTI IJ)

Nippon Indosari (ROTI IJ) Nippon Indosari (ROTI IJ) HOLD (Unchanged) 16 November 2017 Company Update Equity Indonesia Consumer Stock Data Target price (Rp) Prior TP (Rp) Shareprice (Rp) Rp1,200 Rp1,400 Rp1,295 Upside/downside (%)

More information

PT Link Net Tbk. Indonesia Company Guide

PT Link Net Tbk. Indonesia Company Guide Indonesia Company Guide Version 1 Bloomberg: LINK IJ Reuters: LINK.JK Refer to important disclosures at the end of this report DBS Group Research. Equity 26 Mar 2018 BUY Last Traded Price ( 23 Mar 2018):

More information

Yonyou Network Technology

Yonyou Network Technology China / Hong Kong Company Focus Bloomberg: 600588 CH Equity Reuters: 600588.SS DBS Group Research. Equity 31 August 2015 Refer to important disclosures at the end of this report FULLY VALUED Last Traded

More information

Market Access. M&A Securities. Results Review (2Q16) SapuraKencana Petroleum Berhad. Solid Orderbook as a Shield BUY (TP: RM2.

Market Access. M&A Securities. Results Review (2Q16) SapuraKencana Petroleum Berhad. Solid Orderbook as a Shield BUY (TP: RM2. M&A Securities Results Review (2Q16) PP14767/09/2012(030761) SapuraKencana Petroleum Berhad Thursday, September 17, 2015 BUY (TP: RM2.55) Solid Orderbook as a Shield Results Review Actual vs. expectations.

More information

TRIM Company Update HOLD. RALS: Good August, Change in Expansion Plan. Maintained. September 14, 2011

TRIM Company Update HOLD. RALS: Good August, Change in Expansion Plan. Maintained. September 14, 2011 September 14, 2011 TRIM Company Update RALS: Good August, Change in Expansion Plan Maintained HOLD Share Price : Rp770 Sector : Retail Price Target : Rp870(13.0%) (Previously Rp880) Stock Data Reuters

More information

Pembangunan Perumahan

Pembangunan Perumahan 4/16 /16 6/16 7/16 8/16 9/16 1/16 11/16 12/16 1/17 2/17 3/17 (PTPP IJ) 1Q17 review: Expecting better days ahead Construction Company Report May 2, 217 (Maintain) Buy Target Price (12M, IDR) 4,2 Share Price

More information

BHARAT HEAVY ELECTRICALS LIMITED RESEARCH

BHARAT HEAVY ELECTRICALS LIMITED RESEARCH RESULTS REVIEW Bharat Heavy Electricals Limited Hold Share Data Market Cap Rs. 779.4 bn Price Rs. 1,592.10 BSE Sensex 13,791.54 Reuters BHEL.BO Bloomberg BHEL IN Avg. Volume (52 Week) 0.26 mn 52-Week High/Low

More information