Chapter 12: Programming/Resource Allocation

Size: px
Start display at page:

Download "Chapter 12: Programming/Resource Allocation"

Transcription

1 Chapter 12: Programming/Resource Allocation What is works programming? Works programming refers to the preparation of annual and multi-annual works programs in which road assets requiring treatment are identified, selected, and prioritized and resources are allocated from available funds (Robinson et al. 1998). Programming implies the application of asset management principles to make decisions at the network or subnetwork level for budget allocation in the short to medium term. Assuming that appropriate levels of service have been set, this process includes identifying asset requirements, developing a total needs program, and prioritizing/optimizing programs for the existent budget constraints (Austroads 2009). The preparation of works programs has at its core a resource allocation process, which ideally distributes the available funding among projects that have been identified as the best alternatives for investing funds. Best practice includes the application of benefit-cost analysis for each candidate project within a lifecycle framework. Modern analysis tools are based on such a framework and provide mathematical optimization routines to determine the best investment choices subject to limited budgets (FHWA 2004). While the economic factor is important, it is not the only criterion used for selecting projects. Other aspects that may also be considered are network connectivity, neighborhood cohesion, preservation of corridor standards, and economic necessity (AASHTO 2002). At high levels of maturity in asset management, works programming also considers risk and thus applies a risk-based approach when carrying out tasks like identifying candidate projects or prioritizing works programs by road asset (UKRLG and HMEP 2013). In addition, mature works programming features resource allocation across asset classes, which is often implemented using risk criteria as well. In developing works programs, it is important to make sure that treatment options, intervention criteria, and system priorities comply with established strategic directions (Austroads 2009). Why should works programs be prepared? The main goals of the works programming process include the following (Austroads 2002 and UKRLG and HMEP 2013): Develop an effective and efficient works programs aligned with the adopted asset management approach and deliver the service Identify a list of candidate projects to close the existing performance gaps Define and broadly estimate the costs of candidate projects 88

2 Prioritize and optimize the projects comprising the works program to comply with existent resource constraints Monitor works to ensure their consistency with the chosen approach to asset management Program effectiveness is measured in terms of the program s contribution to achieving asset management policy and strategic goals, attaining performance targets defined by the transportation agency and meeting the expectations of stakeholders. The efficiency of programs is determined as a function of the benefits generated (user cost savings, improved road safety, congestion reduction, and so on) per investment unit. Works programs and the associated performance measures and targets, when made publicly available, also provide means for increasing the accountability and transparency of the transportation agency operations. Ultimately, the goal of works programming in asset management is to deploy, maintain, and operate assets in a manner that maximizes the accomplishment of the organization s mission (FHWA Transportation Asset Management Expert Task Group 2013). Maturity levels The level of maturity for works programming can be assessed based on a number of features, such as the length of the programming period, application of analysis tools, or resource distribution across asset classes. In this way, for each maturity level a particular feature may or may not be present, as shown in Table Maturity levels can then be characterized by the set of features they support. Table 12.1 Maturity levels for works programming Feature Basic Proficient Advanced Annual program Application of analysis tools Stakeholder needs taken into account Alignment with strategic objectives Multi-annual program Consideration of risk Program optimization across assets The following sections present a brief discussion of maturity levels with regard to the programming process. 89

3 Basic A basic approach to programming normally allows for the production of annual works programs only. At this maturity level, organizational barriers still exist that limit the use of strategic objectives and other elements of planning to support longer programming periods. Another restricting factor for the development of multi-annual programs is a high level of uncertainty with respect to future revenue. Though management systems and/or analysis tools are present at the basic maturity level, agencies at this stage tend to privilege the implementation of such systems over the improvement of the business process they should support, thus reducing the potential impact that the use of these tools may have on the overall performance of the organization. Nevertheless, at this level return on investment might be used as a basis for decision making when this capability is built into the analysis tools employed. Also, at the basic level performance models within management systems are frequently not developed or calibrated to an appropriate degree to ensure that local conditions are properly simulated. In this respect, it should be emphasized that all performance models used in asset management systems (road deterioration, traffic assignment, vehicle operating costs, etc.) should be carefully adjusted to local conditions. Using default models, as is done in a number of countries due to economic or technical issues, should be discouraged if not prohibited because all medium- and long-term results from studies such as benefit-cost analysis or risk analysis are strongly dependent on the relevance of the models. Most management systems in operation at the basic level support works programming only for pavements and, to a lesser extent, for bridges. Budget allocation for assets other than pavements or bridges are often carried out based on historical expenses. Finally, because management of stakeholders expectations is usually also at an early stage, pressure may arise to favor projects addressing the needs of specific groups or projects with special political significance at the expense of other projects with better potential to achieve the goals of the transportation agency. Proficient A distinctive feature of proficient organizations with respect to works programming is their ability to support development of multi-year work programs. These organizations have typically succeeded in reaching a proficient level in other aspects of asset management, including data management, lifecycle planning, and performance management. The above is evidenced by the existence of more reliable information and tools at the disposal of road managers. These allow managers to expand the programming time horizon, which is also leveraged by an increased commitment from senior executives to use business cases effectively in securing funds for road investment over longer periods. Pavement and bridge management systems are well established as corporate tools, and their application is aligned with the business processes the agency has implemented for allocating resources. Other systems for managing slopes and/or embankments, accidents, and signs may 90

4 have already been deployed. Evaluation and prioritization of treatment options are based on benefit-cost analysis, particularly in the case of pavements. At the proficient level, risk is used as an additional criterion to identify and prioritize candidate projects for assets such as bridges, earthworks, and drainage or for projects related to road safety. Risk may also be taken into account to manage sources of uncertainty affecting program delivery, including costs, funding levels, and adverse environmental events. Risk management is an additional factor enabling the agency to prepare multi-year works programs. This level also features mechanisms for managing stakeholder expectations so that the needs of particular groups are properly balanced with the strategic objectives of the transportation agency. At the same time, new means for capturing customer perception, such as road user surveys, are put into practice. Advanced Organizations at this stage of maturity have successfully incorporated asset management into their corporate culture and are immersed in a continuous improvement process. In this context, they investigate further actions to enhance the efficacy and efficiency of their business practices. One of these actions is the implementation of a cross-asset schema for budget allocation, which broadens the scope of project selection and prioritization to ensure that projects that best contribute to the organization s mission are adequately funded, regardless of the asset class or operational feature each project is related to. A prerequisite for an organization to implement cross-asset resource allocation procedures is the existence of a suitable organizational structure for allowing the steady flow of information that might be required. Cross-asset methods are still at an early stage of development worldwide. In this regard, riskbased approaches have also proven useful for organizations already engaged in adopting such methods. Advanced works programming is closely linked to asset management financial planning. On the one hand, financial planning takes as input information regarding historical funding levels and the amount of funds expected to be available in the foreseeable future (FHWA 2013). On the other hand, it defines how these funds will be allocated in the short to medium term. The works programming process The overall process of developing works programs and allocating resources to individual projects can be depicted as a sequence of stages, as shown in Figure

5 Identify candidate projects and prepare the initial subprogram for each asset class Prioritize works subprograms for each asset class Prepare and optimize the multi-year works program Prepare and optimize the annual program Based on UKRLG and HMEP 2013 Figure 12.1 Works programming process These stages are described in the following sections. Identification of candidate projects and preparation of the initial programs by asset class The identification of candidate projects implies the analysis of a given asset (e.g., a pavement section or a bridge) to determine what actions, if any, should be taken to maintain or improve its performance (Cambridge Systematics et al. 2002). This analysis relies on information sources like the following: condition surveys, safety inspections, knowledge of local staff, stakeholder needs, accident claims, and requirements to meet corporate objectives. Data from condition surveys and safety inspections should ideally be available from the asset management system, in some cases through advanced platforms such as GIS (UKRLG and HMEP 2013) A comprehensive approach to project identification may include the following steps (Austroads 2002): Define levels of service, i.e., describe the quality of services associated with the assets considered. Levels of service are usually defined in terms of performance measures and targets, as discussed in Chapter 5. Develop a level of service hierarchy specifying the associated asset class (e.g., dualcarriageway motorways for trunk roads, medium standard single carriageway for secondary roads, and so on). Target levels of service to transportation asset classes to express condition or performance requirements in terms of capital investment needs. Identify performance gaps by comparing the current asset configuration and condition with the required configuration and condition as defined by performance targets. Incorporate the informed view of the community involved through formal community consultation. In order to define the projects required to close the gaps identified from the above steps, several treatment alternatives may be evaluated for each asset. Transportation management systems such as pavement, bridge, accident, and other management systems have been developed over the years to streamline the analysis of alternative works. At this stage, evaluation may include assessing the economic benefits of each option, particularly in the case of pavement assets. The final lists of candidate projects obtained by identifying the optimal intervention option for the various assets may be referred to as the total needs program (Austroads 2009). Figure 12.2 contains a simplified representation of the programing stage concerning project identification and the preparation of initial programs. 92

6 Treatment options Asset condition Local knowledge Stakeholder needs Identify candidate projects and prepare the initial subprogram for each asset class Asset operation Customer complaints Corporate objectives Initial subprograms for pavements, bridges, slopes, etc. Figure 12.2 Selecting candidate projects for the initial subprograms Works prioritization by asset class Prioritization is basically a method of arranging proposals on new lists that indicate which projects are to be funded first (Austroads 2009). Each new list corresponds to a prioritized subprogram per asset class. The prioritization process is built upon a set of criteria involving aspects such as physical condition, safety, risk, and economic feasibility. The initial works program usually includes assets whose performance has fallen below specified standards in terms of condition or safety measures. It may also comprise assets subject to high levels of risk, such as those located in areas of extreme weather conditions as well as those attracting the interest of stakeholders for other reasons (e.g., political or socioeconomic). Because available budgets will in most cases be insufficient to address all needs, safety-critical assets or having the highest level of risk (Figure 12.3) will normally be put at the top of the list. Figure 12.3 Example of a high-risk asset, which should be given a higher priority 93

7 Candidate projects should also be prioritized depending on their lifecycle return on investment to ensure that value for money is achieved, particularly in the case of assets such as pavements, structures, or lighting (UKRLG and HMEP 2013). Again, road management systems usually help in performing this task. Modern prioritization procedures call for applying a multi-criteria approach in which factors such as sustainability, stakeholder requirements, and social benefits are combined with serviceability, safety, and value for money. This approach requires assigning appropriate weights to each factor depending on the institutional vision. It should be noted that agencies at the proficient maturity level might not be in a position to apply the multi-criteria approach described above, while agencies at the basic level usually only use serviceability and economic return as criteria for prioritizing. Inputs and outputs of the prioritization stage are illustrated in Figure Initial subprograms Prioritizing criteria: risk, value for money, serviceability, etc. Stakeholder interests Prioritize works subprograms for each asset class Strategic objectives Prioritized subprograms for pavements, bridges, etc. Figure 12.4 Preparing prioritized subprograms Preparation and optimization of the multi-year works program Multi-year programs comprise projects for the various asset classes to be executed within periods from three to five years (UKRLG and HMEP 2013). When information is available, indicative programs can be developed for longer periods, e.g., 10 or more years. The preparation of multiyear programs is an essential phase of the programming process where project-level needs are reconciled with network-level resource constraints and performance goals. The multi-year program supports financial planning by demonstrating what projects needs to be done and where and when they are to be undertaken. This planning must be reviewed annually and updated using the latest information available. A multi-year program should indicate the amounts of funding corresponding to routine, preventive, and periodic maintenance, as well as resources intended for rehabilitation and construction (Austroads 2009). It should also contain details of the specific works considered for budget allocation. These features may be challenged by senior decision makers, so multi-year programs need to be robust and based on reliable information. 94

8 The list of projects to be included in the multi-year program is compiled by selecting projects from the prioritized program and adding up the costs estimated for each project until the forecasted budget is exhausted. At the advanced maturity level, the asset management plan and the investment strategy serve as a basis for determining which projects should be selected. For projects around the budget ceiling or those requiring significant investment, additional data may be required to verify any assumptions made. The actual benefits from obtaining these data should be carefully assessed when the costs and risks involved are significant (UKRLG and HMEP 2013). Project selection from prioritized programs often involves an optimization process. In this context, optimization refers to selecting investment options from various alternatives with the aim of achieving the highest benefits from constrained resource levels (Austroads 2009). One of the ranking criteria used for optimizing the available budget is the incremental benefit-cost ratio, which seeks to maximize the economic benefits for each additional unit of expenditure (Morosiuk et al. 2006). Various management systems provide optimization modules for conducting impact analyses of different funding scenarios (Austroads 2009). Scenarios that might be considered include current constrained funds, incremented funds, reduced funds, and changes in the level of service offered. Results can then be presented to senior management to either support a particular funding scenario or examine various scenario options. In performing program optimization, considerations such as the following may also be addressed (UKRLG and HMEP 2013): Minimizing occupation of the network, which refers to reducing disruption to users by coordinating different works programs and integrating transport projects on related parts of the network Deliver efficiencies by combining activities, e.g., combining projects identified as being close to each other in the works program but scheduled for different years Optimization of works programs has been traditionally carried out separately for the various asset classes, with a different budget ceiling established for each class. Using this approach, the resulting multi-annual program is actually made up of as many subprograms as the number of asset classes included in the programming process. Organizations at the advanced maturity level of asset management consider the implementation of methods for optimizing resource allocation across asset classes, using optimization processes based on a multi-criteria approach similar to that described for the prioritization stage. Figure 12.5 shows the main information flows occurring at this stage of the programming process. 95

9 Prioritized subprograms Estimated budget for the programming period Prepare and optimize the multi-year works program Optimizing criteria for each asset Criteria for cross-asset optimization (advanced level only) Multi-year program Figure 12.5 Preparing multi-year works program As mentioned above, organizations at the basic level only support development of annual works programs. In this case, the preparation and optimization of the multi-annual program is omitted or, more precisely, the tasks described above are performed using an analysis period of one year, and cross-asset optimization is not addressed. Project selection for the annual program The multi-annual program should be reviewed annually to update the list of projects with the highest priority that can be delivered from the available budget and produce an annual works program or annual plan (UKRLG and HMEP 2013). In generating the annual program, consideration must be given to projects deferred in the last year, the backlog of needs, and the updated availability of resources (Austroads 2009). Projects in the annual works program should already have undergone a detailed design process and be ready for delivery. This enables contractors to plan the works properly and minimize any potential risks. In project design, the collection of additional detailed data on the involved assets should be considered to ensure that the proposed intervention produces the expected outcomes. Also, a more detailed cost estimate for each project should be made allowing a suitable contingency for risk (UKRLG and HMEP 2013). Case study: Works programming for the Mexican federal toll-free network One of the major components of Mexican roads is the federal toll-free network, which comprises 40,752 km of paved roads (Figure 12.6) and 7,483 bridges. 96

10 Figure 12.6 Mexican federal toll-free network This part of the network is managed by the General Directorate of Road Maintenance (DGCC) of the Mexican Secretariat of Communications and Transport (SCT). As part of the planning process implemented by the federal government for developing and preserving the federal roads, the DGCC prepares, on the one hand, a six-year plan for each period of the federal administration and, on the other hand, an annual road maintenance program. Both the six-year plan and the annual program are composed of a series of asset-specific subprograms, including pavement maintenance, bridge reconstruction, and black spot treatment. The programming process for pavement maintenance is supported by a pavement management system, which makes use of HDM-4 for analyzing investment options. Based on information about pavement condition, traffic forecasts, and other data items, this process determines the set of pavement works yielding the greatest return on investment for the available resources. Other funding scenarios simulating budget cuts or the allocation of additional resources are also analyzed. With regard to bridges, inspection data are used as input to the DGCC bridge management system in order to identify bridges requiring treatment, define the necessary bridge works, and prioritize the resulting works list using criteria such as current bridge condition, traffic volume, 97

11 and the impact of failure on network connectivity. Resources are allocated to projects based on the priorities defined. Finally, concerning black spots, a priority list is also prepared based on accident information provided by other areas of the SCT. The DGCC has not yet implemented procedures for allocating resources among asset classes. However, in the final stage of the annual program preparation, a thorough review is performed to identify bridges and other structures involving high levels of risk and, eventually, redistribute parts of the available budget. References American Association of State Highway and Transportation Officials (AASHTO) Transportation Asset Management Guide. American Association of State Highway and Transportation Officials. Washington, DC. Austroads Asset Management Publications & Resources. Last accessed July 29, Austroads Guide to Asset Management Part 4: Program Development and Implementation. Austroads Inc. Sydney, Australia "Integrated Asset Management Guidelines for Road Networks." Austroads Publications Online. Accessed April 9, Cambridge Systematics, Inc., Applied Research Associates, Inc., Arora and Associates, KLS Engineering, PB Consult, Inc., and Louis Lambert NCHRP Report 632: An Asset- Management Framework for the Interstate Highway System. Transportation Research Board of the National Academies. Washington, DC. Last accessed July 24, 2015 at Federal Highway Administration (FHWA) Asset Management. Last accessed July 29, Executive Brief: Advancing a Transportation Asset Management Approach. Federal Highway Administration Office of Asset Management. Washington, DC. Last accessed July 29, Cambridge Systematics, Inc., Parsons Brinckerhoff Quade and Douglas, Inc., Roy Jorgensen Associates, Inc., and Paul D. Thompson Phase I Report Task 2 of 3: Asset Management Framework. NCHRP Web Document 41. National Cooperative Highway Research Program, Washington, DC. Last accessed July 30, Federal Highway Administration (FHWA) Transportation Asset Management Expert Task Group AASHTO Asset Management Guide A Focus on Implementation. Executive Summary. American Association of State Highway and Transportation Officials. Washington, DC. Last accessed July 29, FHWA Asset Management Position Paper. Federal Highway Administration. Last accessed July 30,

12 Generic Work Plan for Developing a TAMP. Federal Highway Administration Office of Asset Management. Last accessed July 30, HMEP Asset Management. 1 May. Accessed June 3, Morosiuk, Greg, Mike Riley, and Tyrone Tool HDM-4: Highway Development and Management. Volume Two: Applications Guide. World Road Association (PIARC). Paris, France. NAMS NAMS. Accessed June 3, PIARC Road assets management Knowledge base PIARC. Accessed June 3, Robinson, Richard, Uno Danielson, and Martin Snaith Road Maintenance Management: Concepts and Systems. Macmillan. Basingstoke, Hampshire, UK. United Kingdom Roads Liaison Group (UKRLG) and Highways Maintenance Efficiency Programme (HMEP) Highway Infrastructure Asset Management Guidance Document. Department for Transport, London. Last accessed July 24,

Chapter 8: Lifecycle Planning

Chapter 8: Lifecycle Planning Chapter 8: Lifecycle Planning Objectives of lifecycle planning Identify long-term investment for highway infrastructure assets and develop an appropriate maintenance strategy Predict future performance

More information

NCHRP Consequences of Delayed Maintenance

NCHRP Consequences of Delayed Maintenance NCHRP 14-20 Consequences of Delayed Maintenance Recommended Process for Bridges and Pavements prepared for NCHRP prepared by Cambridge Systematics, Inc. with Applied Research Associates, Inc. Spy Pond

More information

House Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2.

House Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2. House Bill 20 Implementation Tuesday,, 1:00 P.M. Capitol Extension E2.020 INTRODUCTION In response to House Bill 20 (HB 20), 84 th Legislature, Regular Session, 2015, and as part of the implementation

More information

Chapter 7: Risk. Incorporating risk management. What is risk and risk management?

Chapter 7: Risk. Incorporating risk management. What is risk and risk management? Chapter 7: Risk Incorporating risk management A key element that agencies must consider and seamlessly integrate into the TAM framework is risk management. Risk is defined as the positive or negative effects

More information

Risk Approach to Prioritising Maintenance Risk Factors for Value Management

Risk Approach to Prioritising Maintenance Risk Factors for Value Management Transport Research Laboratory Risk Approach to Prioritising Maintenance Risk Factors for Value Management by R Abell CPR966 2/462_155 CLIENT PROJECT REPORT Transport Research Laboratory CLIENT PROJECT

More information

MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT

MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT Mason, Rangamuwa, Henning Page 1 of 15 MAXIMISE THE LEVEL OF SERVICE USING CROSS ASSET PORTFOLIO RENEWALS MANAGEMENT Michael Mason 1, Siri Rangamuwa 1, Theunis F. P Henning 2 Corresponding Author: Michael

More information

Treasury Board Secretariat. Follow-Up on VFM Section 3.07, 2015 Annual Report RECOMMENDATION STATUS OVERVIEW

Treasury Board Secretariat. Follow-Up on VFM Section 3.07, 2015 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 1 Section 1.07 Treasury Board Secretariat Infrastructure Planning Follow-Up on VFM Section 3.07, 2015 Annual Report Chapter 1 Follow-Up Section 1.07 RECOMMENDATION STATUS OVERVIEW # of Status of

More information

Maintenance Management of Infrastructure Networks: Issues and Modeling Approach

Maintenance Management of Infrastructure Networks: Issues and Modeling Approach Maintenance Management of Infrastructure Networks: Issues and Modeling Approach Network Optimization for Pavements Pontis System for Bridge Networks Integrated Infrastructure System for Beijing Common

More information

Updated Capital Infrastructure Investment Strategy for Council Approval:

Updated Capital Infrastructure Investment Strategy for Council Approval: Updated Capital Infrastructure Investment Strategy for Council Approval: Introduction The City of Calgary (The City) seeks to improve the quality of life, build public confidence and trust and demonstrate

More information

Stephen Gaj Leader, Asset Management Team Office of Asset Management, Pavements, and Construction FHWA

Stephen Gaj Leader, Asset Management Team Office of Asset Management, Pavements, and Construction FHWA Stephen Gaj Leader, Asset Management Team Office of Asset Management, Pavements, and Construction FHWA National Goals Focus the Federal-aid program on the following national goals: 1) SAFETY 2) INFRASTRUCTURE

More information

Mn/DOT Scoping Process Narrative

Mn/DOT Scoping Process Narrative Table of Contents 1 Project Planning Phase...3 1.1 Identify Needs...4 1.2 Compile List of Needs = Needs List...4 1.3 Define Project Concept...5 1.4 Apply Fiscal/Other Constraints...5 1.5 Compile List of

More information

White Paper: Performance-Based Needs Assessment

White Paper: Performance-Based Needs Assessment White Paper: Performance-Based Needs Assessment Prepared for: Meeting Federal Surface Transportation Requirements in Statewide and Metropolitan Transportation Planning: A Conference Requested by: American

More information

An Inclusive and Data-Rich Approach to Infrastructure Development

An Inclusive and Data-Rich Approach to Infrastructure Development Network-Level Analysis An Inclusive and Data-Rich Approach to Infrastructure Development By Israr Ahmad and John Murray The state of a community s capital infrastructure is inextricably linked with its

More information

Tony Mento, P.E. January 2017

Tony Mento, P.E. January 2017 Tony Mento, P.E. January 2017 Evolution of the Federal Program Manage ITS & Operations Manage Build preserve maintain Outcome Performance 2 National Highway Performance Program ($21.8B) Funds an enhanced

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT A. Sector Road Map Road Improvement and Institutional Development Project (RRP PHI 41076) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems and Opportunities 1. Roads provide

More information

Introduction. The Assessment consists of: A checklist of best, good and leading practices A rating system to rank your company s current practices.

Introduction. The Assessment consists of: A checklist of best, good and leading practices A rating system to rank your company s current practices. ESG / CSR / Sustainability Governance and Management Assessment By Coro Strandberg President, Strandberg Consulting www.corostrandberg.com September 2017 Introduction This ESG / CSR / Sustainability Governance

More information

FY Statewide Capital Investment Strategy... asset management, performance-based strategic direction

FY Statewide Capital Investment Strategy... asset management, performance-based strategic direction FY 2009-2018 Statewide Capital Investment Strategy.. asset management, performance-based strategic direction March 31, 2008 Governor Jon S. Corzine Commissioner Kris Kolluri Table of Contents I. EXECUTIVE

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP Advantages of PPP A key advantage of having the private sector provide public services is that it allows public administrators to concentrate on planning, policy and regulation. The private sector, in

More information

GASB Statement 34 the On-Ramp to Transportation Asset Management or a Detour Leading to Business as Usual?

GASB Statement 34 the On-Ramp to Transportation Asset Management or a Detour Leading to Business as Usual? GASB Statement 34 the On-Ramp to Transportation Asset Management or a Detour Leading to Business as Usual? Thomas H. Maze and Omar Smadi Department of Civil, Construction, and Environmental Engineering

More information

Network Modelling. David Yeoell Assistant City Commissioner of Transportation

Network Modelling. David Yeoell Assistant City Commissioner of Transportation Network Modelling David Yeoell Assistant City Commissioner of Transportation We have (a duty) to maintain our highway network in a safe and reliable condition that meets the need of customers / users Asset

More information

SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM. Frequently Asked Questions

SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM. Frequently Asked Questions SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM Frequently Asked Questions SMEC COMPANY DETAILS SMEC Australia Pty Ltd Sun Microsystems Building Suite 2, Level 1, 243 Northbourne Avenue, Lyneham ACT

More information

THE ROAD TO ECONOMIC GROWTH

THE ROAD TO ECONOMIC GROWTH THE ROAD TO ECONOMIC GROWTH Introduction 1. As in many countries, the road sector accounts for the major share of domestic freight and inter-urban passenger land travel in Indonesia, playing a crucial

More information

Mind the Maintenance Gap: Framework, Global Trends, and Maintenance in OIC Member States

Mind the Maintenance Gap: Framework, Global Trends, and Maintenance in OIC Member States Mind the Maintenance Gap: Framework, Global Trends, and Maintenance in OIC Member States Dr Adnan Rahman Director General, IRF www.irfnet.ch THE INTERNATIONAL ROAD FEDERATION Promoting the development

More information

In addition to embarking on a new dialogue on Ohio s transportation priorities,

In addition to embarking on a new dialogue on Ohio s transportation priorities, Strategic Initiatives for 2008-2009 ODOT Action to Answer the Challenges of Today In addition to embarking on a new dialogue on Ohio s transportation priorities, the Strategic Initiatives set forth by

More information

Economic Analysis Concepts

Economic Analysis Concepts Economic Analysis Concepts Questions & Decisions (1) Is the project justified?- Are benefits greater than costs? Which is the best investment if we have a set of mutually exclusive alternatives? If funds

More information

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects

Seminar on African Electrical Interconnection. Module 6 - Financing Interconnection Projects Seminar on African Electrical Interconnection Module 6 - Financing Interconnection Projects Module 6 - Financing Interconnection Projects Contents 1) Major Financing Features 2) Basic Financing Approaches

More information

Improving infrastructure outcomes through better capital allocation

Improving infrastructure outcomes through better capital allocation Improving infrastructure outcomes through better capital allocation Capital Projects & Infrastructure November 2017 Jose Luis Blanco André Dua Tyler Duvall Needham Hurst Jonathan Law Ben Safran Improving

More information

Developing a Transportation Asset Management Plan

Developing a Transportation Asset Management Plan Developing a Transportation Asset Management Plan A Workshop for the NCDOT July 2, 2015 Conducted By: Katie Zimmerman, P.E., Applied Pavement Technology, Inc. (APTech) And Lacy Love, Volkert, Inc. Workshop

More information

BANTAY LANSANGAN: ROAD SECTOR REPORT CARD (09 Nov 06)

BANTAY LANSANGAN: ROAD SECTOR REPORT CARD (09 Nov 06) BANTAY LANSANGAN: ROAD SECTOR REPORT CARD (09 Nov 06) CLUSTER / INDICATOR A. SYSTEM/NETWORK DESCRIPTION 1. Overall Philippine Road Network (For information): National Roads 28,805 km Provincial Roads 27,076

More information

Introduction. The Assessment consists of: Evaluation questions that assess best practices. A rating system to rank your board s current practices.

Introduction. The Assessment consists of: Evaluation questions that assess best practices. A rating system to rank your board s current practices. ESG / Sustainability Governance Assessment: A Roadmap to Build a Sustainable Board By Coro Strandberg President, Strandberg Consulting www.corostrandberg.com November 2017 Introduction This is a tool for

More information

Review of the Federal Transit Administration s Transit Economic Requirements Model. Contents

Review of the Federal Transit Administration s Transit Economic Requirements Model. Contents Review of the Federal Transit Administration s Transit Economic Requirements Model Contents Summary Introduction 1 TERM History: Legislative Requirement; Conditions and Performance Reports Committee Activities

More information

Prioritisation Methodology

Prioritisation Methodology Prioritisation Methodology March 2014 PRIORITISATION METHODOLOGY Table of contents 1 Introduction... 5 2 The Projects Prioritisation Process... 7 3 The Methodological Assumptions... 8 3.1 Background...

More information

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996 LIFE YLE Good Practice Guide ASSET MANAGEMENT Project Management Overview March 1996 Department of Energy Office of Field Management Office of Project and Fixed Asset Management ontents 1. INTRODUTION...1

More information

Life-Cycle Cost Analysis: A Practitioner s Approach

Life-Cycle Cost Analysis: A Practitioner s Approach Life-Cycle Cost Analysis: A Practitioner s Approach FHWA Office of Performance Management 1 Topics Fundamentals of Economic Analysis Tools and resources What to do now 2 Learning Objectives By the end

More information

Submission by State of Palestine. Thursday, January 11, To: UNFCCC / WIMLD_CCI

Submission by State of Palestine. Thursday, January 11, To: UNFCCC / WIMLD_CCI Submission by State of Palestine Thursday, January 11, 2018 To: UNFCCC / WIMLD_CCI Type and Nature of Actions to address Loss & Damage for which finance is required Dead line for submission 15 February

More information

The 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012

The 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012 The 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012 THE PLANNING-PROGRAMMING-BUDGETING SYSTEM LTC Valentin PÎRVUŢ Land Forces Academy

More information

OPTIMIZATION OF ROAD MAINTENANCE AND REHABILITATION ON SERBIAN TOLL ROADS

OPTIMIZATION OF ROAD MAINTENANCE AND REHABILITATION ON SERBIAN TOLL ROADS Paper Nº ICMP123 8th International Conference on Managing Pavement Assets OPTIMIZATION OF ROAD MAINTENANCE AND REHABILITATION ON SERBIAN TOLL ROADS Goran Mladenovic 1*, Jelena Cirilovic 2 and Cesar Queiroz

More information

City of Glendale, Arizona Pavement Management Program

City of Glendale, Arizona Pavement Management Program City of Glendale, Arizona Pavement Management Program Current Year Plan (FY 2014) and Five-Year Plan (FY 2015-2019) EXECUTIVE SUMMARY REPORT December 2013 TABLE OF CONTENTS TABLE OF CONTENTS I BACKGROUND

More information

Government of Peru Peru. PROVIAS Departamental Peru

Government of Peru Peru. PROVIAS Departamental Peru Project Name Region Sector Project ID Borrower(s) Implementing Agency Environment Category Safeguard Classification PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB827 Regional Transport

More information

ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK

ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK ANNEXURE A ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK CONTENTS 1. Enterprise Risk Management Policy Commitment 3 2. Introduction 4 3. Reporting requirements 5 3.1 Internal reporting processes for risk

More information

Working Paper #1. Optimizing New York s Reforming the Energy Vision

Working Paper #1. Optimizing New York s Reforming the Energy Vision Center for Energy, Economic & Environmental Policy Rutgers, The State University of New Jersey 33 Livingston Avenue, First Floor New Brunswick, NJ 08901 http://ceeep.rutgers.edu/ 732-789-2750 Fax: 732-932-0394

More information

Transportation Improvement Program and Incentives for Local Planning

Transportation Improvement Program and Incentives for Local Planning Capital District November 9, 2004 Transportation Committee Transportation Improvement Program and Incentives for Local Planning CDTC has been successful in funding 36 Linkage Program planning studies since

More information

1.0 CITY OF HOLLYWOOD, FL

1.0 CITY OF HOLLYWOOD, FL 1.0 CITY OF HOLLYWOOD, FL PAVEMENT MANAGEMENT SYSTEM REPORT 1.1 PROJECT INTRODUCTION The nation's highways represent an investment of billions of dollars by local, state and federal governments. For the

More information

Hazim M Abdulwahid, MSC, MBA Hazim Consulting

Hazim M Abdulwahid, MSC, MBA Hazim Consulting Road Map for Establishing Pavement Maintenance Management System on the Strategic Level 13 th International O&M Conference in the Arab Countries,17-19 Nov 2015 Hazim M Abdulwahid, MSC, MBA Hazim Consulting

More information

Prioritising bridge replacements

Prioritising bridge replacements Prioritising bridge replacements Andrew Sonnenberg, National Bridge Engineering Manager, Pitt&Sherry ABSTRACT Road and Rail managers own a variety of assets which are aging and will need replacement. There

More information

September Preparing a Government Debt Management Reform Plan

September Preparing a Government Debt Management Reform Plan September 2012 Preparing a Government Debt Management Reform Plan Introduction Preparing a Government Debt Management Reform Plan The World Bank supports the strengthening of government debt management

More information

Using Asset Management Planning to Make Roadway Improvements

Using Asset Management Planning to Make Roadway Improvements Using Asset Management Planning to Make Roadway Improvements 1 Presentation Overview Status of Municipal Infrastructure Asset Management 101 15+ Year Pavement Life cycle Data, M,R&R, Prediction Models,

More information

A PROCEDURAL DOCUMENT DESCRIBING THE PROCESS OF DEVELOPING THE 4-YEAR PLAN

A PROCEDURAL DOCUMENT DESCRIBING THE PROCESS OF DEVELOPING THE 4-YEAR PLAN 5-9035-01-P8 A PROCEDURAL DOCUMENT DESCRIBING THE PROCESS OF DEVELOPING THE 4-YEAR PLAN Authors: Zhanmin Zhang Michael R. Murphy TxDOT Project 5-9035-01: Pilot Implementation of a Web-based GIS System

More information

Transportation Improvement Program Project Priority Process White Paper

Transportation Improvement Program Project Priority Process White Paper Transportation Improvement Program Project Priority Process White Paper Pierce County Public Works- Office of the County Engineer Division Introduction This paper will document the process used by the

More information

Initial Transportation Asset Management Plan

Initial Transportation Asset Management Plan Initial Transportation Asset Management Plan Table of Contents Acronym Table Introduction.................. 1 Act 51 Michigan Public Act 51 of 1951 Program Development Call For Projects Process...........5

More information

2017 Strategic Financial Plan Executive Summary

2017 Strategic Financial Plan Executive Summary Executive Summary Introduction The County of Orange is committed to long-term strategic financial planning to ensure its ability to respond to economic changes and unanticipated events in a way that allows

More information

Transportation Asset Management Webinar Series Webinar 28: Financial Plans

Transportation Asset Management Webinar Series Webinar 28: Financial Plans Transportation Asset Management Webinar Series Webinar 28: Financial Plans Sponsored by FHWA and AASHTO Webinar 28 October 11, 2017 1 FHWA-AASHTO Asset Management Webinar Series This is the 28 th in a

More information

Multi-Year, Multi-Constraint Strategy to

Multi-Year, Multi-Constraint Strategy to Multi-Year, Multi-Constraint Strategy to Optimize Linear Assets Based on Life Cycle Costs Keivan Neshvadian, PhD Transportation Consultant July 2016 2016 AgileAssets Inc All Rights Reserved Pavement Asset

More information

A Multi-Objective Decision-Making Framework for Transportation Investments

A Multi-Objective Decision-Making Framework for Transportation Investments Clemson University TigerPrints Publications Glenn Department of Civil Engineering 2004 A Multi-Objective Decision-Making Framework for Transportation Investments Mashrur Chowdhury Clemson University, mac@clemson.edu

More information

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade. Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding

More information

Texas Department of Transportation Page 1 of 42 Planning and Development of Transportation Projects

Texas Department of Transportation Page 1 of 42 Planning and Development of Transportation Projects Texas Department of Transportation Page of Proposed Preamble The Texas Department of Transportation (department) proposes amendments to.,.,. -.,.0 -.0, new.0, and amendments to. -.,.,.0, and.0 -.0, all

More information

THE MANAGEMENT OF ROAD PROJECTS IN PAPUA NEW GUINEA

THE MANAGEMENT OF ROAD PROJECTS IN PAPUA NEW GUINEA THE MANAGEMENT OF ROAD PROJECTS IN PAPUA NEW GUINEA Roy Harry MUMU, John Belly Kelly KAIO PNG National Roads Authority Boroko, National Capital District, Papua New Guinea roymumu@daltron.com.pg, johnkaio@datec.net.pg

More information

Genesee-Finger Lakes Regional Bridge Network Needs Assessment and Investment Strategy

Genesee-Finger Lakes Regional Bridge Network Needs Assessment and Investment Strategy Genesee-Finger Lakes Regional Bridge Network Needs Assessment and Investment Strategy prepared for Genesee Transportation Council prepared by Cambridge Systematics, Inc. February 2015 GTC s Commitment

More information

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN Terms of Reference for Consultants 1. BACKGROUND INFORMATION Government of Vanuatu has requested TA support in the formulation and preparation of a national infrastructure

More information

Strategy for the Development of Investment Decision-Making Framework for Road Asset Management for Queensland Department of Main Roads

Strategy for the Development of Investment Decision-Making Framework for Road Asset Management for Queensland Department of Main Roads Strategy for the Development of Investment Decision-Making Framework for Road Asset Management for Queensland Department of Main Roads By: Noppadol Piyatrapoomi, Arun Kumar, Neil Robertson and Justin Weligamage

More information

Presented by: Christy A. Hall, P.E. Interim Secretary of Transportation. January 2016

Presented by: Christy A. Hall, P.E. Interim Secretary of Transportation. January 2016 Presented by: Christy A. Hall, P.E. Interim Secretary of Transportation January 2016 Overall Assessment of the System Pavements: Most South Carolinian s are riding on poor pavements. Bridges: Most bridges

More information

Making the case for road preservation to meet social expectations

Making the case for road preservation to meet social expectations Making the case for road preservation to meet social expectations JEAN-FRANÇOIS CORT É Past Secretary General of the World Road Association 2016 - National Pavement Preservation Conference Continuing the

More information

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management 0470_022817_03_chap01.fm Page 11 Wednesday, September 8, 2004 3:29 PM Part I The basics of project risk management 0470_022817_03_chap01.fm Page 12 Wednesday, September 8, 2004 3:29 PM 0470_022817_03_chap01.fm

More information

Term. Explanation. Benefit Sharing

Term. Explanation. Benefit Sharing Note on Benefit Sharing for Emission Reductions Programs Under the Forest Carbon Partnership Facility and BioCarbon Fund Initiative for Sustainable Forest Landscapes January 2019 Version Introduction Benefit

More information

Public Private Partnerships. Alberta Infrastructure Guidance Document

Public Private Partnerships. Alberta Infrastructure Guidance Document P3 Public Private Partnerships Alberta Infrastructure Guidance Document P3 Public Private Partnerships Alberta Infrastructure Guidance Document Excerpt from the February 18, 2003 Speech from the Throne

More information

An Easy to Implement Sustainability Index for Flexible Pavements

An Easy to Implement Sustainability Index for Flexible Pavements Journal of Civil Engineering and Architecture 11 (2017) 1123-1129 doi: 10.17265/1934-7359/2017.12.007 D DAVID PUBLISHING An Easy to Implement Sustainability Index for Flexible Pavements Gregory Kelly,

More information

Building a Better Tomorrow

Building a Better Tomorrow Building a Better Tomorrow Investing in Ontario s Infrastructure to Deliver Real, Positive Change A Discussion Paper on Infrastructure Financing and Procurement February 2004 2 BUILDING A BETTER TOMORROW

More information

Improving public investment efficiency for infrastructure development

Improving public investment efficiency for infrastructure development National Workshop on Infrastructure Financing Strategies for Sustainable Development in Viet Nam Hanoi, 3 October 2017 Improving public investment efficiency for infrastructure development Mr Mathieu Verougstraete

More information

Maricopa County DOT. Transportation Asset Management (TAM) Planning. March 1, 2018 DYE MANAGEMENT GROUP, INC.

Maricopa County DOT. Transportation Asset Management (TAM) Planning. March 1, 2018 DYE MANAGEMENT GROUP, INC. Maricopa County DOT Transportation Asset Management (TAM) Planning March 1, 2018 DYE MANAGEMENT GROUP, INC. Transportation Asset Management (TAM) A strategic and systematic process of operating, maintaining,

More information

Applying Risk-based Decision-making Methods/Tools to U.S. Navy Antiterrorism Capabilities

Applying Risk-based Decision-making Methods/Tools to U.S. Navy Antiterrorism Capabilities Applying Risk-based Decision-making Methods/Tools to U.S. Navy Antiterrorism Capabilities Mr. Charles Mitchell ABSG Consulting Inc. Alexandria, VA (703) 519-6387 cmitchell@absconsulting.com Commander Chris

More information

Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System

Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System M. Arif Beg, PhD Principal Consultant, AgileAssets Inc. Ambarish Banerjee, PhD Consultant, AgileAssets

More information

Connected Vehicle Pooled Fund Study Program to Support the Development and Deployment of Connected Vehicle Applications

Connected Vehicle Pooled Fund Study Program to Support the Development and Deployment of Connected Vehicle Applications Connected Vehicle Pooled Fund Study Program to Support the Development and Deployment of Connected Vehicle Applications Partnership and Operating Policies Background A connected vehicles environment holds

More information

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Corridors of Commerce DRAFT Scoring and Prioritization Process Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Project Purpose To develop and implement a scoring and project

More information

Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION

Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION Maintenance Funding & Investment Decisions STACEY GLASS, P.E. STATE MAINTENANCE ENGINEER ALABAMA DEPARTMENT OF TRANSPORTATION Funding Allocations Routine State $ 166 Million Resurfacing Federal $ 260 Million

More information

COMPONENT 4. programming may differ from what is included in this chapter.

COMPONENT 4. programming may differ from what is included in this chapter. COMPONENT 4 PERFORMANCE- BASED PROGRAMMING This chapter provides assistance to transportation agencies with the Performance- Based Programming component of Transportation Performance Management (TPM).

More information

2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION

2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION 2017 UNIFIED TRANSPORTATION PROGRAM AND HB 20 IMPLEMENTATION TEMPO Meeting July 21, 2016 Current Initiatives On-going efforts to address performance-based planning and programming processes as required

More information

OCCUPATIONAL HEALTH & SAFETY THE CARING CLIENT IMPLEMENTATION OF THE NATIONAL OHS STRATEGY

OCCUPATIONAL HEALTH & SAFETY THE CARING CLIENT IMPLEMENTATION OF THE NATIONAL OHS STRATEGY Implementation of the National OHS Strategy 2002 2012 Wayne Artuso OCCUPATIONAL HEALTH & SAFETY THE CARING CLIENT Case Study IMPLEMENTATION OF THE NATIONAL OHS STRATEGY 2002-2012 Wayne Artuso Executive

More information

LOCAL MAJOR BRIDGE PROGRAM

LOCAL MAJOR BRIDGE PROGRAM LOCAL MAJOR BRIDGE PROGRAM The Local Major Bridge Program provides federal funds to counties and municipal corporations for bridge replacement or bridge major rehabilitation projects. A Local Major Bridge

More information

2018 Annual Report. Highway Department Accomplishments

2018 Annual Report. Highway Department Accomplishments 2018 Annual Report Highway Department The vision of the Eau Claire County Highway Department is to provide services to the taxpayer that, to the best of our ability, provides safe and efficient travel

More information

CATEGORY 8 PLANNING CONTINUOUS IMPROVEMENT

CATEGORY 8 PLANNING CONTINUOUS IMPROVEMENT INTRODUCTION The College s processes related to Planning Continuous Improvement are very mature. JC s key planning processes are aligned. Clear processes are in place for strategic planning and the College

More information

Corporate and Financial restructuring of the road sector Context

Corporate and Financial restructuring of the road sector Context Corporate and Financial restructuring of the road sector The Croatian Government (the Government) is committed to optimizing the debt held by public companies in the road sector, and wants to achieve a

More information

Performance-based Planning and Programming. white paper

Performance-based Planning and Programming. white paper white paper May 2012 white paper Performance-based Planning and Programming date May 2012 NOTICE This document is disseminated under the sponsorship of the U.S. Department of Transportation in the interest

More information

INSURANCE AFFORDABILITY A MECHANISM FOR CONSISTENT INDUSTRY & GOVERNMENT COLLABORATION PROPERTY EXPOSURE & RESILIENCE PROGRAM

INSURANCE AFFORDABILITY A MECHANISM FOR CONSISTENT INDUSTRY & GOVERNMENT COLLABORATION PROPERTY EXPOSURE & RESILIENCE PROGRAM INSURANCE AFFORDABILITY A MECHANISM FOR CONSISTENT INDUSTRY & GOVERNMENT COLLABORATION PROPERTY EXPOSURE & RESILIENCE PROGRAM Davies T 1, Bray S 1, Sullivan, K 2 1 Edge Environment 2 Insurance Council

More information

Quantitative Management vs. Traditional Management

Quantitative Management vs. Traditional Management FOR PROFESSIONAL INVESTORS ONLY Quantitative Management vs. Traditional Management February 2014 Quantitative Management vs. Traditional Management I 24/02/2014 I 2 Quantitative investment in asset management

More information

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing

People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Consultant s Report Project Number: 49166-001 People s Republic of China TA 8940: Municipality-Level Public Private Partnership (PPP) Operational Framework for Chongqing Public Private Partnerships: Management

More information

RESEARCH RESULTS DIGEST March 2001 Number 252

RESEARCH RESULTS DIGEST March 2001 Number 252 National Cooperative Highway Research Program RESEARCH RESULTS DIGEST March 2001 Number 252 Subject Area: IA Planning and Administration Responsible Senior Program Officer: Charles W. Niessner Development

More information

SERC Reliability Corporation Business Plan and Budget

SERC Reliability Corporation Business Plan and Budget SERC Reliability Corporation 3701 Arco Corporate Drive, Suite 300 Charlotte, NC 28273 704.357.7372 Fax 704.357.7914 www.serc1.org SERC Reliability Corporation 2018 Business Plan and Budget FINAL June 28,

More information

VIRGINIA S STATE OF THE STATE ADDRESS

VIRGINIA S STATE OF THE STATE ADDRESS VIRGINIA S STATE OF THE STATE ADDRESS TRB ADC40 Summer Session July 27, 2009 Paul M. Kohler Noise Abatement Program Manager AGENDA 1. Economic Status of Virginia 2. Reorganization of VDOT 3. Projects of

More information

THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 )

THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 ) THE OFFICE OF TRANSPORTATION PUBLIC PRIVATE PARTNERSHIPS ( OTP3 ) VIRGINIA DEPARTMENT OF TRANSPORTATION ( VDOT ) VIRGINIA DEPARTMENT OF RAIL AND PUBLIC TRANSPORTATION ( DRPT ) RESPONSE TO REQUEST FOR INFORMATION

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Bihar New Ganga Bridge Project (RRP IND 48373) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The proposed project is to build a new six-lane bridge across the Ganges River near Patna in the state

More information

ANNUAL PUBLIC ROADS PROGRAMME FOR THE FINANCIAL YEAR 2008/2009

ANNUAL PUBLIC ROADS PROGRAMME FOR THE FINANCIAL YEAR 2008/2009 ANNUAL PUBLIC ROADS PROGRAMME FOR THE FINANCIAL YEAR 2008/2009 1.1 INTRODUCTION 1.1.1 Introduction Clause 31 of the Kenya Roads Board (KRB) Act No. 7 of 1999 establishes the Kenya Roads Board Fund (KRBF)

More information

Fonds de Compensation FDC SICAV Obligations EUR Actif 3

Fonds de Compensation FDC SICAV Obligations EUR Actif 3 Fonds de Compensation FDC SICAV Obligations EUR Actif 3 Sustainable Approach March 2018 Amundi Sustainable Approach Sustainable and Responsible Investing has been a long standing and essential part of

More information

Asset Management Plan 2016 Township of King

Asset Management Plan 2016 Township of King Asset Management Plan 206 Township of King GHD Allstate Parkway Suite 30 Markham Ontario L3R 9T8 T 905 752 4300 F 905 752 430 5432 Table of Contents. 2. 3. 4. 5. 6. Executive Summary. Introduction.2 State

More information

Presented by: Christy A. Hall, P.E. Secretary of Transportation

Presented by: Christy A. Hall, P.E. Secretary of Transportation Presented by: Christy A. Hall, P.E. Secretary of Transportation General Comments Agree with the vast majority of the agency-specific recommendations. Recognize that SCDOT needs to continue to improve its

More information

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 1698 SESSION MAY HM Treasury and Cabinet Office. Assurance for major projects

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 1698 SESSION MAY HM Treasury and Cabinet Office. Assurance for major projects REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 1698 SESSION 2010 2012 2 MAY 2012 HM Treasury and Cabinet Office Assurance for major projects 4 Key facts Assurance for major projects Key facts 205 projects

More information

EXCELLENCE INNOVATION SERVICE VALUE

EXCELLENCE INNOVATION SERVICE VALUE Incorporation of Geotechnical Elements as an Asset Class within Transportation Asset Management and Development of Risk Based and Life Cycle Cost Performance Strategies by Mark Vessely, P.E. Shannon &

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN)

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) Second Jharkhand State Road Project (RRP IND 49125) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) A. Sector Performance, Problems, and Opportunities 1. State context. The state of Jharkhand was

More information

Combining Financial Management and Collections to Increase Revenue and Efficiency

Combining Financial Management and Collections to Increase Revenue and Efficiency Experience the commitment SOLUTION BRIEF FOR CGI ADVANTAGE ERP CLIENTS Combining Financial Management and Collections to Increase Revenue and Efficiency CGI Advantage ERP clients have a unique opportunity

More information

1. Define risk. Which are the various types of risk?

1. Define risk. Which are the various types of risk? 1. Define risk. Which are the various types of risk? Risk, is an integral part of the economic scenario, and can be termed as a potential event that can have opportunities that benefit or a hazard to an

More information

Business Plan. BC Oil and Gas Research and Innovation Society. April 1, 2017 to March 31, 2020 Version Harbour Road Victoria, BC V9A 0B7

Business Plan. BC Oil and Gas Research and Innovation Society. April 1, 2017 to March 31, 2020 Version Harbour Road Victoria, BC V9A 0B7 Business Plan April 1, 2017 to March 31, 2020 Version 1 300-398 Harbour Road Victoria, BC V9A 0B7 Tel: 220-1418 info@bcogris.ca BC OGRIS Business Plan (2017/20) Table of Contents Executive Summary...

More information