Economic Analysis Concepts

Size: px
Start display at page:

Download "Economic Analysis Concepts"

Transcription

1 Economic Analysis Concepts

2 Questions & Decisions (1) Is the project justified?- Are benefits greater than costs? Which is the best investment if we have a set of mutually exclusive alternatives? If funds are limited, how should different schemes be ranked? When should the road be built or upgraded? 2

3 Questions & Decisions (2) What standard of construction should be used? What standard and frequency of road maintenance is optimal? Should staged construction be used? Are complementary investments required? 3

4 Appraisal Framework All appraisals need a framework or model for: a) Forecasting changes b) Evaluating those changes 4

5 Components of Economic Analysis (1) Costs and benefits are measured in money terms Road construction and maintenance costs are compared with estimates of the direct primary benefits going to road users and road agency Secondary benefits are usually ignored Economic prices are used in constant terms 5

6 Components of Economic Analysis (2) Costs and Benefits are forecast over the planning time horizon (usually between 10 and 20 years) Future Benefits are valued less as time progresses using the planning discount rate Costs and Benefits are compared using decision criteria such as NPV, IRR, etc. 6

7 Economic and Financial Prices The cost to the economy of road rehabilitation and maintenance may differ from the financial cost because of : taxes and duties shortage of foreign exchange under-employment The Government will usually be concerned with ECONOMIC costs. Contractors will usually be concerned with FINANCIAL costs. 7

8 Use of Economic Prices In an Economic Appraisal we use ECONOMIC (or SHADOW) prices NOT FINANCIAL prices Adjust financial prices as follows: Exclude all taxes and duties and subsidies Use the planning discount rate not financial market rate If overvalued exchange rate then value imports and exports more highly Use the opportunity cost of labor Standard Conversion Factors are now widely used for road construction costs 8

9 Benefits from Road Investment Changes in transport costs occur because of : Lower road roughness Shorter trip distance Faster speeds Reduced chance of impassability Reduced traffickability problems Change in mode 9

10 Project Costs Management (including design and supervision) Labor Equipment Materials Land, Resettlement, Environment 10

11 Primary Effects (1) Reduced vehicle operating costs (VOC) fuel and lubricants vehicle maintenance depreciation and interest Tire wear Crew time overheads Reduced journey time drivers, passengers and goods 11

12 Primary Effects (2) Changes in road maintenance costs Changes in accident rates Increased travel Environmental effects Change in value of goods moved 12

13 Secondary Effects Changes in agricultural output Changes in services Changes in industrial output Changes in consumers behavior Changes in land values Changes in income 13

14 Consumers Surplus Approach Captures primary benefits Advantages: Simple, cost based, traffic approach dependent on predicting changes in traffic Disadvantages: May not address critical factors promoting either rural development or social access 14

15 Normal and Generated Traffic Benefits Total Benefits = Transport cost savings to Normal traffic and growth Cost C1 + Additional benefits to Generated traffic C2 Demand Curve (Price Elasticity of Demand) T1 T2 Traffic Normal Generated 15

16 Generated Traffic Benefits Traffic induced by the road investment are traditionally valued at: Half the difference in transport costs Hence total generated transport cost benefits = Generated Traffic Volume x Change in Transport Costs per km x Distance x 1/2 16

17 Producers Surplus Approach Captures secondary benefits Advantages: Draws attention to changes in agricultural output (key economic activity in rural areas) Disadvantages: No reliable way of predicting response - impact studies give widely different answers - it could be based on agricultural supply price elasticities but this is almost never done; it requires very careful examination to use. For most projects benefits are just invented! 17

18 Producers Surplus P2 P1 Price & Costs per Unit of Output Increased Farmgate Price Lower Input Costs Output O1 O2 18

19 Coverage and Double Counting Any economic analysis should be designed to give maximum coverage of benefits But we must avoid double counting. Do not add primary and secondary benefits (e.g. changes in land values added to changes in transport costs) In a competitive economy the consumers surplus approach (used in HDM) should be adequate 19

20 Economic Comparisons Economic analysis involves a comparison of With and Without project cases Forecasts are made of traffic, road condition, VOC and road maintenance effects for BOTH scenarios An unrealistic Without case (i.e. with little maintenance) can give a false result A range of With investment cases should be analyzed to find the best solution 20

21 Traffic Categories Normal traffic: Existing traffic and growth that would occur on road, with and without the investment Diverted traffic: Traffic diverted from another road with same origin and destination to as the project road as a result of the investment Generated traffic: Traffic associated with existing users of the road driving more frequently or driving further than before Induced traffic: Traffic attracted to the project road due to increased economic activity in the road s zone of influence brought about by the project 21

22 Benefits from Road Investment Transport cost savings for existing (or normal) traffic = Normal Traffic Volume x Change in Transport Costs per km x Distance Main changes in cost from: a) change in transport MODE b) reduced journey TIME c) reduced VOCs 22

23 Benefits of Upgrading to a Motorable Track Headloading C1 Costs Track Improved road C2 C3 T1 T2 T3 Traffic 23

24 Cost Effectiveness Against Standard of Road 95% of year, access established Marginal productivity 99% of year, access established Maintenance for roughness reduction 0 Maintenance expenditure $/km 24

25 Development Benefits Development benefits arise from a combination of increased traffic and reduced transport costs. Benefits may also include : Increased agricultural production Increased service provision Increased industrial activity 25

26 Estimating Benefits Normal traffic benefits: trips N * d 1 * (VOC 1 -VOC 2 ) Diverted traffic benefits: trips D * ((d 1 * VOC 1 )-(d 2 *VOC 2 )) Generated and Induced traffic benefits: trips G * d 2 * (VOC 1 -VOC 2 )/2 d 1 = existing road length d 2 new road length VOC 1 = vehicle operating costs per km without investment VOC 2 = vehicle operating costs per km with investment VOC data relates to each road section and its condition at the time 26

27 Economic Decision Criteria (1) Net Present Value NPV = (B 1 -C 1 )/(1 + r) + (B 2 -C 2 )/ (1 + r) (B n -C n )/(1 + r ) n Internal Rate of Return To calculate IRR, solve for r, such that NPV = 0 B 1, B 2 Bn = Benefits in years 1, 2 n C 1, C 2 Cn = Costs in years 1, 2. n r = Planning discount rate n = Planning time horizon 27

28 Economic Decision Criteria (2) Net Present Value/ Investment Cost NPV/ C = NPV/C i First Year Rate of Return FYRR B 1, C 1 C i = (B 1 -C 1 ) / C i = Benefits and Costs in year 1 after construction = Road investment costs Payback Period 28

29 Economic Decision Criteria (3) NPV IRR 3 NPV/C FYRR Project economic validity V.Good V.Good V.Good Poor Mutually exclusive projects V.Good Poor Good Poor Project timing Fair Poor Poor Good Project screening 1 Poor V.Good Good Poor Under budget constraint 2 Fair Poor V.Good Poor Notes: 1. check for robustness to changes in key variables (sensitivity analysis) 2. with incremental analysis 3. IRR may be indeterminate with NONE or MANY solutions. 29

30 Present Value Calculation Period Flow A0 A5 PV(A0) = A0 PV(A5) = A5 / (1 + i ) ^ 5 PV(Aj) = Aj / (1+ i ) ^ j PV(Aj) = Present Value of Aj Aj = Amount at year j i = Discount rate j = Year 30

31 Present Value at 12.0% Discount Rate 1.00 in Year 1 = Year 2 Year 3 Year in Year 5 = Year 6 Year 7 Year 8 Year in Year 1 0 = in Year 1 in Year 1 in Year in Year 15 = 0.20 in Year in Year 20 = 0.12 in Year 1 31

32 Discount Rate The discount rate is opportunity cost of capital in the public sector, ie the rate of return on marginal public sector investments The discount rate to be used will be given by the planning authority responsible for the project The World Bank traditionally has not calculated a discount rate for each project but has used 10 to 15 percent as a notional opportunity cost of capital in developing countries 32

33 Discount Rate Versus Interest Rate US discount rate around 4% 33

34 NPV and IRR The Net Present Value (NPV) of a project alternative relative to the without project alternative is the sum of the discounted annual net benefits. The Internal Rate of Return (IRR) is the discount rate at which the NPV is zero. 34

35 NPV Decision Rule 1. If the NPV is positive, for the chosen discount rate, then the alternative is acceptable. 2. If the NPV is negative, for the chosen discount rate, then the alternative is unacceptable. 3. If the NPV is zero, for the chosen discount rate, then the alternative is indifferent to the without project alternative. 35

36 NPV and IRR Calculation (1) Discount Net Rate (i) Discount Present 12.0% Rate (i) Present Investments Profits Present 0.0% 7500 or or Net Value Present 3.0% 6326 Year Costs Benefits Benefits Factor Value 6.0% 5281 a b c d = c-b e = 1/(1+i)^a f = d*e 9.0% % % % % % % % % -544 Total % % NPV = % % IRR = 29.3% 48.0%

37 NPV and IRR Calculation (2) NPV at 12% Discount Rate Net Present Value (M$) Internal Rate of Return 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% Discount Rate (%) 37

38 NPV Versus IRR Net Present Value (M$) NPV at 12% Discount Rate Internal Rate of Return 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% Discount Rate (%) - The IRR and NPV will not necessarily rank the alternatives by the same order - Always use NPV to compare project alternatives 38

39 Multiples Rates of Return Net Year Benefits NPV at 12% 0.64 IRR #1 10% IRR #2 20% Discount Rate NPV 0% % % % % % % % % % % % % % % % -5.9 Net Present Value (M$) Multiple Rates of Return % 5% 10% 15% 20% 25% 30% 35% Discount Rate (%) 39

40 No Rate of Return Year Net Benefits NPV at 12% 747 IRR #NUM! No Rate of Return Discount Rate NPV 0% % % % % % % % % % % % % % % % Net Present Value (M$) % 5% 10% 15% 20% 25% 30% 35% Discount Rate (%) 40

41 Same Rate of Return Net Benefits Project Project Year NPV at 12% IRR (%) 25% 25% Discount Project Project Rate 1 2 1% % % % % % % % % % % % % % % % Net Present Value (M$) Same Rate of Return % 5% 10% 15% 20% 25% 30% 35% Discount Rate (%) Project 1 Project 2 41

42 Incremental Rate of Return Alternative A - Base Investments Profits Present or or Net Value Present Year Costs Benefits Benefits Factor Value NPV = IRR = 100.0% MIRR = 100.0% B/C = 1.79 Alternative B - Base Investments Profits Present or or Net Value Present Year Costs Benefits Benefits Factor Value NPV = IRR = 20% MIRR = 20% B/C = 1.07 Alternative B - Alternative A Investments Profits Present or or Net Value Present Year Costs Benefits Benefits Factor Value NPV = IRR = 13% MIRR = 13% B/C =

43 IRR Reinvestment Assumption IRR IMPLICIT ASSUMPTION: ALL CASH FLOW VALUES WILL EARN THE IRR INTEREST RATE Discount Rate (i) 12.0% Future Value in Year 4 Investments Profits If You If You Receive or or Net Invest at and Invest at Year Costs Benefits Benefits 29.3% 29.3% a b c d = c-b Interest Interest = NPV= 3508 IRR= 29.3% Total

44 Modified Internal Rate of Return Modified Internal Rate of Return Calculation Financing Reinvestment Rate (i) Rate (i) 12.0% 12.0% Present Future Modified Net Value Value Cash Year Benefits of Costs of Benefits Flow a d = c-b Costs at Year 0 Benefits at Year TOTAL NPV = IRR = 29.3% 20.7% MIRR = 20.7% 44

45 Benefits X Cost Alternative B 80 Benefits Alternative A Costs 45

46 Net Benefits X Costs (Efficiency Frontier) Alternative B Net Benefits (NPV) Alternative A Costs 46

47 Comparison of Alternatives When comparing project-alternatives, the Net Present Value (NPV) is used to select the optimal project-alternative (alternative with highest NPV) The Internal Rate of Return (IRR) or the B/C ratio are not recommended to compare alternatives of a given project Project Alternatives NPV Optimal Alternative: Highest NPV

48 Projects Ranking Projects When comparing the economic priority of different projects, a recommended economic indicator is the NPV per Investment ratio Selected Alternative Overlay Reseal Overlay 48 NPV/Investment P R I O R I T Y

49 Budget Constraints Simple Methodology Projects Selected Alternative NPV Investment NPV per Investment Available Budget Overlay Reseal Overlay P R I O R I T Y Reseal Budget Constraint Cut Off Overlay

50 Budget Constraints Optimization Projects Alternatives Available Budget NPV Evaluates all possible combinations of projectalternatives to find the combination that maximizes the NPV of the overall network for the given budget constraint. P = Number of projects A = Number of alternatives C = Number of possible combinations C= A ^P

51 HDM-4 Optimization Example (1) Section 1 Option Cost NPV A 2 4 B 5 7 C 7 8 Section 2 Option Cost NPV A 1 3 B 3 6 C 5 8 What is the recommended program for a budget of 5? 51

52 HDM-4 Optimization Example (2) B C B C A A dnpv/dcost Cost Section 1 Section 2 52

53 HDM-4 Optimization Example (3) A, 2-B 1-A, 2-C 1-B, 2-C 1-C, 2-C A, 2-A Combination of project alternatives that maximizes the NPV of the network 53 Cost Network

54 Appraisals & Post Evaluations (1) An Appraisal is carried out before an investment is made. Everything is uncertain. A Post evaluation may be made say 5 years after the investment. The investment is known and 5yrs of with case are known. The without case is unknown as is the remainder of the with case. 54

55 Appraisals & Post Evaluations (2) In Both Cases forecasting and evaluation models are required to come to an answer. Hence we can never be certain about the viability of an investment! 55

56 Sensitivity Analysis Consequences of changes on inputs Investment Costs (e.g. +15%) Traffic Growth Rate (e.g. = zero) Generate Traffic (e.g. = zero) Value of Time (e.g. = zero) A = Investment Costs Increase (e.g. +15%) B = Road User Benefits Decrease (e.g. - 15%) C = A and B together 56

57 Switching Values Analysis Inputs that yield a NPV equal to zero Investments Costs Normal Traffic Traffic Growth Rate Generate Traffic Investment Cost Road User Benefits 57

58 Risk Analysis Inputs vary at the same time following some defined distributions Normal Traffic Frequency Distribution 35% 30% 25% 20% 15% 10% 5% Country Africa Region Project Road Management Initiative Road Road from Point A to Point B Option 2 Upgrade to ST Internal Rate of Return Upgrade Road to Surface Treatment Standard Minimum 4.2% Maximum 22.7% Average 11.9% Standard Deviation 3.5% Median 11.7% Percentile 25% 9.4% Percentile 50% 11.7% Percentile 75% 14.1% Probability that IRR is less than 12% 50% Probability that IRR is greater than 12% 50% 0% Multiplier Factor Upgrade Road to Surface Treatment Standard 8% 7% Frequency Distribution 14% 12% 10% 8% 6% 4% Project Investment Costs Frequency Distribution 6% 5% 4% 3% 2% 1% 2% 0% 0% Multiplier Factor % 6.0% 7.1% 8.1% 9.1% 10.1% 11.2% 12.2% 13.2% 14.2% 15.3% 16.3% 17.3% 18.3% Internal Rate of Return 19.4% 20.4% 21.4% 22.4% 23.5% 24.5%

59 Rural Transport Infrastructure Farm Household/ Village Sub-village Typical Transport Infrastructure Path Path/Track Track/ Earth Road Market Center Earth Road/ Gravel Road District Headquarters 1-2 lane Gravel / ST Road Regional Headquarters 2 lane AC** Road Capital/ Port Typical Traffic Porterage NMT NMT 0-5VPD 5-50VPD 1-5 km 1-10 km 5-20 km Share of Asset Value Share of Network Length 40% 20% 0% NMT >100VPD >1500VPD VPD km km km 40% 20% 0% Responsability Type of Network Community Local Government Rural Transport Infrastructure Provincial/Central Government Trunk or Provincial Road Tracks Roads Highways 59

60 Rural Transport Infrastructure Rural Transport Infrastructure Primary, Secondary and Municipal Roads Road Network Tertiary Secondary Primary Functional Classification Access Collector Arterial Responsibility Community Local Government Regional & National Municipal % of Road Network N.A % +- 10% +- 10% 1 to 2 earth or gravel 1.5 to 2 gravel or paved Physical Characteristics tracks lanes lanes 2 or more paved lanes Normally sections with 1 to 5 kms Normally sections with 5 to 20 kms Normally sections with 20 to 100 kms Normally sections with 50 to 200 kms Traffic Characteristics Mostly NMT < 50 AADT + NMT AADT > 500 AADT Economic Evaluation No No Yes Yes Social Evaluation Yes Yes Complimentary No Financial Evaluation No No No Tolls Technical Evaluation No Yes Yes Yes Environmental Evaluation No Yes Yes Yes Safety Evaluation No Yes Yes Yes Focus on social evaluation (cost effectiveness indices, community priorities and multi-criteria analysis) 60

61 Social Benefits: Why the Concern? There is unease with conventional appraisal based primarily on transport cost savings to traffic There is a strong desire at community and national levels for better access and mobility which is frequently not matched by standard measured economic benefits The rich world governments subsidise rural transport. Should the same happen for developing countries? Isolation is a recognised characteristic of poverty There is a feeling that a minimum degree of access and mobility is a basic human right Development has moved away from a narrow definition of economic development towards concern with livelihoods and meeting Millennium Development Goals The issue is particularly important when roads are impassable to motor traffic 61

62 Economic & Social Benefits Consumers and producers surplus approaches are very economic in orientation. Yet roads provide social benefits including improved access to health and education facilities and improved social mobility that cannot be easily translated into conventional economic benefits. Although they may have important long term economic consequences. Improved health and education and more secure social networks increase long term earning capabilities but so far the economic forecasting framework does not include this. When roads are impassable to motorized traffic we know that the quality of health care and schooling falls. Drug supply and supervision drops. Likewise no NGO, government agency or commercial enterprise will establish or support a service which cannot guarantee all year round access. 62

63 Indices and Ranking Widely used for feeder road planning; there are many different approaches e.g. i) cost of improvement / population ii) estimated trips / cost Advantages: Speed, simplicity, transparency, many factors can be incorporated Disadvantages: How do we value widely different factors? (adding up apples and pears); weightings are not stable ; cannot easily address questions of road standards, timing etc, ; possible double counting 63

64 Example of Two Indices i) Andhra Pradesh (India) cost effectiveness = cost of upgrading/ population served But no measure of condition change and no importance to traffic ii) Airey & Taylor 1st for impassable roads rank = cost per head of establishing basic access 2nd when access is there: estimated trips x access change prioritization index = rehabilitation cost per km 64

65 Community Priorities Community priorities now often form an important part of feeder road appraisal. It is possible just to ask communities to rank the investments they prefer- both within the road sector or between roads and other investments. Advantages: Community acceptability, use of community knowledge Disadvantages: Sectional interest groups may dominate voting, community knowledge of area or road impact may be poor 65

66 Cost Effectiveness Analysis (CEA) Compares the cost of interventions with its predicted impacts and it is used where the benefits cannot be measured in monetary terms, or where the measurement is difficult It includes provisions that (a) the objectives of the intervention are indicated and are clearly part of a ampler program of objectives (such as reduction of the poverty); and (b) the intervention represents the smaller cost alternative of obtaining the indicated objectives It produces effectiveness indicators, such as Total Beneficiary Population per Investment or Investment per Beneficiary Population 66

67 CEA Comparison of Alternatives To compare project-alternatives, the investment cost is used to select the optimal alternative The selected alternative is the one with the lowest investment cost that will achieve the objective of the program Project Alternatives Investment Optimal Alternative: Lower Investment 67

68 Projects Eligibility with CEA To assess if a project is eligible, an acceptable effectiveness indicator threshold is defined Projects Investment per Population (U$/person) 50 Effectiveness Indicator Threshold Example 150 Eligible Not Eligible

69 Effectiveness Indicator Threshold Frequency of Projects Reasonable ? Investment per Population (US$/person) 69 Non Reasonable? Evaluate Universe of Projects and Available Budget

70 Possible CEA Indicators Investment Cost per Total Beneficiary Population 100 US$ per person Total Beneficiary Population per Investment Cost 0.01 persons per US$ Total Beneficiary Population per Investment Cost in thousands of dollars 10 persons per 1,000 US$ Etc. 70

71 Options for Beneficiary Population Rural beneficiary population o Effectiveness = (rural beneficiary population) / Investment Poor beneficiary population o Effectiveness = (poor beneficiary population) / Investment Mixed beneficiary population Etc. o Effectiveness = (poor persons non poor persons) / Investment 71

72 Total Beneficiary Population (1) Total Beneficiary Population = Directly Benefited Population + Indirectly Benefited Population The Directly Benefited Population is the one that lives next on the road, defined for example to 2.0 km at each side of the road, and the population in the ends of the road, depending on its characteristics and the use of the road The Indirectly Benefited Population is the population that lives in other roads near the road in consideration, who use the project road to arrive at the main population center of the region or at a main road 72

73 Total Beneficiary Population (2) D Main Population Center B C E F A Village For example, for the road section B-C: Directly Benefited Population = Population along section B-C plus on towns B and C Indirectly Benefited Population = Population along section A-B plus on town A 73

74 Multi Criteria Analysis (MCA) (1) It adopts criteria such as traffic, proximity to educative, health, and economic centers, etc. To each section, a number of the points is assigned to each criteria that correspond to the fulfillment of the criteria The added number of the points that each section receives is computed simply adding the points assigned for each criteria, or with the use of a more complex formula, for example, weighting the criteria by their perceived importance 74

75 Multi Criteria Analysis (2) It produces a priority indicator The indicators used in a MCA reflect implicit economic and subjective evaluations If the weights and the points are decided and assigned on a participative way, the MCA has the potential to be a good participative method for planning based on implicit a socioeconomic estimates Nevertheless, it tends to be applied by planning consultants or in isolation without the consultation with the users and communities affected by the project 75

76 Multi Criteria Analysis (3) The result of the MCA, is often, unfortunately, not transparent, specially if many factors are considered and a complicated formula is also applied Therefore, if it is adopted, this method must be used very carefully and to be maintained simple, transparent, and participative 76

77 Multi Criteria Analysis Example (1) Level of poverty of the influence area (Low, Medium, High) Potential for economic development of the influence area (Low, Medium, High) Importance of the road given by local consultation process (Low, Medium, High) Provision of access of social services of the road (Low, Medium, High) Problems of transitability of the road (Low, Medium, High) Functional classification level of the road (Low, Medium, High) Existence of public transport (Low, Medium, High) 77

78 Multi Criteria Analysis Example (2) Population Poverty Agricultural Area Traffic Functional Classification Priority Index Location on Basic Network Beneficiary Population per km Factor Poverty Percent Factor Percent of Area of Influence Factor Daily Traffic (AADT) Factor A=4 B=3 C=2 D=1 Factor Yes = 1 No = 0 Factor 9, % % % % , % % % % % % % % Health Centers Schools Public Transport Environment Feasibility Yes = 1 No = 0 Factor Yes = 1 No = 0 Factor Yes = 1 No = 0 Factor Yes = 1 No = 0 Factor Priority Index Factor = Value / Maximum Value 78

Roads Economic Decision Model (RED)

Roads Economic Decision Model (RED) Roads Economic Decision Model (RED) March 2006 Rodrigo Archondo-Callao The World Bank RED Objectives Simplify the economic evaluation of unpaved roads Better capture the economic benefits of a project

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Bihar New Ganga Bridge Project (RRP IND 48373) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The proposed project is to build a new six-lane bridge across the Ganges River near Patna in the state

More information

ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2

ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2 Appendix 6 ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2 1. Background. The Second Rural Connectivity Investment Program will support the Government of India in improving rural connectivity through the

More information

HDM-4 Applications. Project Appraisal. Project Formulation. Maintenance Policy Optimization. Road Works Programming. Network Strategic Analysis

HDM-4 Applications. Project Appraisal. Project Formulation. Maintenance Policy Optimization. Road Works Programming. Network Strategic Analysis HDM-4 Applications HDM-4 Applications Project Appraisal Project Formulation Maintenance Policy Optimization Road Works Programming Network Strategic Analysis Standards & Policies 2 Project Appraisal Concerned

More information

ECONOMIC ANALYSIS. Table 1: Vehicle Fleet Characteristics Four- Medium Car. Light Bus. Wheel Drive

ECONOMIC ANALYSIS. Table 1: Vehicle Fleet Characteristics Four- Medium Car. Light Bus. Wheel Drive Western Regional Road Corridor Investment Program (RRP MON 41193) A. Project Costs and Benefits ECONOMIC ANALYSIS 1. Project Costs. The project s capital costs include the costs of the road works, design,

More information

DEVELOPING A LOCAL GOVERNMENT TRANSPORT MASTERPLAN: CASE STUDY

DEVELOPING A LOCAL GOVERNMENT TRANSPORT MASTERPLAN: CASE STUDY DEVELOPING A LOCAL GOVERNMENT TRANSPORT MASTERPLAN: CASE STUDY Objectives of the case study J. Lebo, World Bank (1999) National or state rural planning processes are often top down, technically sophisticated

More information

Community-Based SME For Road Maintenance

Community-Based SME For Road Maintenance Community-Based SME For Road Maintenance Insights from the W.B and IADB-Peruvian Rural Roads maintenance contracts Project & Poverty Reduction Presented by Jacob Greenstein (EGAT) Scope of Presentation

More information

THE ROAD TO ECONOMIC GROWTH

THE ROAD TO ECONOMIC GROWTH THE ROAD TO ECONOMIC GROWTH Introduction 1. As in many countries, the road sector accounts for the major share of domestic freight and inter-urban passenger land travel in Indonesia, playing a crucial

More information

ECONOMIC ANALYSIS. A. Introduction

ECONOMIC ANALYSIS. A. Introduction Bridge Replacement for Improved Rural Access Sector Project (RRP PNG 43200) ECONOMIC ANALYSIS A. Introduction 1. The economic analysis of the proposed project has been carried out in accordance with ADB

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Khyber Pakhtunkhwa Provincial Roads Improvement Project (RRP PAK 47360) A. Background ECONOMIC AND FINANCIAL ANALYSIS 1. The province of Khyber Pakhtunkhwa in northwest Pakistan covers almost six degrees

More information

Chapter 8: Lifecycle Planning

Chapter 8: Lifecycle Planning Chapter 8: Lifecycle Planning Objectives of lifecycle planning Identify long-term investment for highway infrastructure assets and develop an appropriate maintenance strategy Predict future performance

More information

COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD

COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD COST BENEFIT ANALYSIS OF CHENNAI PERIPHERAL ROAD 1 Introduction The objective of the cost benefit economic analysis is to identify and quantify the benefits and costs associated with the project. This

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Additional Financing of National Motorway M-4 Gojra Shorkot Khanewal Section Project (RRP PAK 48402) ECONOMIC AND FINANCIAL ANALYSIS A. General 1. Roads are the main mode of transport in Pakistan, accounting

More information

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP

TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP Public Disclosure Authorized TRANSPORT NOTES TRANSPORT ECONOMICS, POLICY AND POVERTY THEMATIC GROUP 33930 THE WORLD BANK, WASHINGTON, DC January 2005 Notes on the Economic Evaluation of Transport Projects

More information

SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR. 1. Sector Performance, Problems, and Opportunities Chhattisgarh State Road Sector Project (RRP IND 44427) Sector Road Map SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR 1. Sector Performance, Problems, and Opportunities 1. The state of Chhattisgarh

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Chittagong-Cox s Bazar Railway Project, Phase 1 (RRP BAN 46452-002) A. Introduction ECONOMIC AND FINANCIAL ANALYSIS 1. The proposed project will construct 102

More information

Effectiveness of Rural Road Improvement Using the Do-nou Method in Developing Countries: Economic Analysis with RED Model

Effectiveness of Rural Road Improvement Using the Do-nou Method in Developing Countries: Economic Analysis with RED Model Effectiveness of Rural Road Improvement Using the Do-nou Method in Developing Countries: Economic Analysis with RED Model Koichiro TAMURA 1, Yoshiya NAKAGAWA 2, Seiji KADOOKA 3 and Makoto KIMURA 4 1 Member

More information

Draft Environmental Impact Statement. Appendix G Economic Analysis Report

Draft Environmental Impact Statement. Appendix G Economic Analysis Report Draft Environmental Impact Statement Appendix G Economic Analysis Report Appendix G Economic Analysis Report Economic Analyses in Support of Environmental Impact Statement Carolina Crossroads I-20/26/126

More information

Capital Budgeting Process and Techniques 93. Chapter 7: Capital Budgeting Process and Techniques

Capital Budgeting Process and Techniques 93. Chapter 7: Capital Budgeting Process and Techniques Capital Budgeting Process and Techniques 93 Answers to questions Chapter 7: Capital Budgeting Process and Techniques 7-. a. Type I error means rejecting a good project. Payback could lead to Type errors

More information

Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS

Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS 10-1 a. Capital budgeting is the whole process of analyzing projects and deciding whether

More information

CBA of transport infrastructure projects in Germany

CBA of transport infrastructure projects in Germany CBA of transport infrastructure projects in Germany Dr. Catharina Horn Federal Transport Infrastructure Planning, Investment Policy Paris, 27th of February 2014 www.bmvi.de 1. The Federal Transport Infrastructure

More information

Highway Engineering-II

Highway Engineering-II Highway Engineering-II Chapter 7 Pavement Management System (PMS) Contents What is Pavement Management System (PMS)? Use of PMS Components of a PMS Economic Analysis of Pavement Project Alternative 2 Learning

More information

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million)

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million) Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) ECONOMIC ANALYSIS A. Project Costs 1. This chapter outlines the methodology and results of the economic analysis for the project, comprising

More information

Project Evaluation. Carl D. Martland Senior Research Associate Dept. of Civil & Environmental Engineering

Project Evaluation. Carl D. Martland Senior Research Associate Dept. of Civil & Environmental Engineering Courtesy of Carl Martland. Used with permission. Project Evaluation Carl D. Martland Senior Research Associate Dept. of Civil & Environmental Engineering Outline Introduction (Lecture 1) Financial assessment

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP Advantages of PPP A key advantage of having the private sector provide public services is that it allows public administrators to concentrate on planning, policy and regulation. The private sector, in

More information

Public vs. Private Projects

Public vs. Private Projects 1.011 Project Evaluation Public vs. Private Projects Carl D. Martland Project Evaluation in the Private Sector Analysis focuses on financial issues NPV based upon incremental costs and benefits and the

More information

Government of Peru Peru. PROVIAS Departamental Peru

Government of Peru Peru. PROVIAS Departamental Peru Project Name Region Sector Project ID Borrower(s) Implementing Agency Environment Category Safeguard Classification PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB827 Regional Transport

More information

PRINCIPLES OF FINANCIAL APPRAISAL

PRINCIPLES OF FINANCIAL APPRAISAL LOWER MEKONG PUBLIC POLICY INITIATIVE Technical Training in Project Appraisal for the Lower Mekong Basin PRINCIPLES OF FINANCIAL APPRAISAL Ho Chi Minh City Nov 28 - Dec 09, 2016 Financial Analysis: Basic

More information

India: Public Private Partnerships in Highways Sector

India: Public Private Partnerships in Highways Sector India: Public Private Partnerships in Highways Sector Prepared by World Bank as input for IDA paper, 2008 (provided by Tarun Sankar, PPIAF office, South Asia) India s transport program is one of the most

More information

A cost is anything that reduces an objective and a benefit is anything that contributes to an objective.

A cost is anything that reduces an objective and a benefit is anything that contributes to an objective. McPeak Lecture 5 PAI 897 Costs and Benefits. A cost is anything that reduces an objective and a benefit is anything that contributes to an objective. One measure we may use of social welfare is national

More information

THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA. Contents. Chapter. 1. The COBA Method. 2. The Do-Minimum and Do-Something Options

THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA. Contents. Chapter. 1. The COBA Method. 2. The Do-Minimum and Do-Something Options THE COBA 2018 USER MANUAL PART 1 ECONOMIC CONCEPTS IN COBA Contents Chapter 1. The COBA Method 2. The Do-Minimum and Do-Something Options 3. The Fixed Trip Matrix 4. Discounting and the Price Basis 5.

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT A. Sector Road Map Road Improvement and Institutional Development Project (RRP PHI 41076) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems and Opportunities 1. Roads provide

More information

2016 Simplified Methodology for Economic Appraisal of Road- Transportation Projects in the Kurdistan Region

2016 Simplified Methodology for Economic Appraisal of Road- Transportation Projects in the Kurdistan Region 2016 Simplified Methodology for Economic Appraisal of Road- Transportation Projects in the Kurdistan Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public

More information

PRIORITIZATION OF ROAD INTERVENTIONS IN NAMPULA AND ZAMBEZIA, MOZAMBIQUE UNDER CHANGING FLOOD RISK

PRIORITIZATION OF ROAD INTERVENTIONS IN NAMPULA AND ZAMBEZIA, MOZAMBIQUE UNDER CHANGING FLOOD RISK PRIORITIZATION OF ROAD INTERVENTIONS IN NAMPULA AND ZAMBEZIA, MOZAMBIQUE UNDER CHANGING FLOOD RISK AND OTHER DEEP UNCERTAINTIES Xavier Espinet & Julie Rozenberg GGKP Conference - November 2017 Objective:

More information

Capital Budgeting Decision Methods

Capital Budgeting Decision Methods Capital Budgeting Decision Methods Everything is worth what its purchaser will pay for it. Publilius Syrus In April of 2012, before Facebook s initial public offering (IPO), it announced it was acquiring

More information

Vladimir Ramirez Soberanis Unidad de Inversiones SHCP October 21, 2010

Vladimir Ramirez Soberanis Unidad de Inversiones SHCP October 21, 2010 ITF-OECD Round Table on Improving the Practice of Cost- Benefit Analysis in Transport THE PRACTICE OF COST BENEFIT ANALYSIS IN THE TRANSPORT SECTOR MEXICO PERSPECTIVE Vladimir Ramirez Soberanis Unidad

More information

ECONOMIC ANALYSIS. Table 1: Economic costs by project component

ECONOMIC ANALYSIS. Table 1: Economic costs by project component Jiangxi Fuzhou Urban Integrated Infrastructure Improvement Project (RRP PRC 44007) A. Project Costs and Benefits ECONOMIC ANALYSIS 1. The project s capital costs include the civil works, land acquisition

More information

LIFE CYCLE MANAGEMENT OF ROAD ASSETS (Emphasis on Long Life Pavements)

LIFE CYCLE MANAGEMENT OF ROAD ASSETS (Emphasis on Long Life Pavements) 14 th INTERNATIONAL FLEXIBLE PAVEMENTS CONFERENCE LIFE CYCLE MANAGEMENT OF ROAD ASSETS (Emphasis on Long Life Pavements) Prepared for Master Class / Workshops In Sydney, Melbourne and Brisbane September

More information

The Implementation of Engineering Economy in the Transport Development - A Case Study of Road Transport

The Implementation of Engineering Economy in the Transport Development - A Case Study of Road Transport Abstract The Implementation of Engineering Economy in the Transport Development - By Winner Yousman The engineering economy is a part of skill and knowledge of cost engineering could be applied in many

More information

Project Appraisal and Selection

Project Appraisal and Selection Project Appraisal and Selection Project Appraisal Objectives Dr. DNS Dhakal Duke University Leadership for Results Program for Mid-Level Officers in the Nepalese Civil Service Kathmandu, Nepal 2 September

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN)

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) Second Jharkhand State Road Project (RRP IND 49125) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) A. Sector Performance, Problems, and Opportunities 1. State context. The state of Jharkhand was

More information

The Cost of Pavement Ownership (Not Your Father s LCCA!)

The Cost of Pavement Ownership (Not Your Father s LCCA!) The Cost of Pavement Ownership (Not Your Father s LCCA!) Mark B. Snyder, Ph.D., P.E. President and Manager Pavement Engineering and Research Consultants, LLC 57 th Annual Concrete Paving Workshop Arrowwood

More information

OPTIMIZATION OF ROAD MAINTENANCE AND REHABILITATION ON SERBIAN TOLL ROADS

OPTIMIZATION OF ROAD MAINTENANCE AND REHABILITATION ON SERBIAN TOLL ROADS Paper Nº ICMP123 8th International Conference on Managing Pavement Assets OPTIMIZATION OF ROAD MAINTENANCE AND REHABILITATION ON SERBIAN TOLL ROADS Goran Mladenovic 1*, Jelena Cirilovic 2 and Cesar Queiroz

More information

Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System

Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System M. Arif Beg, PhD Principal Consultant, AgileAssets Inc. Ambarish Banerjee, PhD Consultant, AgileAssets

More information

Capital investment decisions: 1

Capital investment decisions: 1 Capital investment decisions: 1 Solutions to Chapter 13 questions Question 13.24 (i) Net present values: Year 0% 10% 20% NPV Discount NPV Discount NPV ( ) Factor ( ) Factor ( ) 0 (142 700) 1 000 (142 700)

More information

City of Glendale, Arizona Pavement Management Program

City of Glendale, Arizona Pavement Management Program City of Glendale, Arizona Pavement Management Program Current Year Plan (FY 2014) and Five-Year Plan (FY 2015-2019) EXECUTIVE SUMMARY REPORT December 2013 TABLE OF CONTENTS TABLE OF CONTENTS I BACKGROUND

More information

Chapter 7: Investment Decision Rules

Chapter 7: Investment Decision Rules Chapter 7: Investment Decision Rules -1 Chapter 7: Investment Decision Rules Note: Read the chapter then look at the following. Fundamental question: What criteria should firms use when deciding which

More information

ECONOMIC ANALYSIS. A. Introduction

ECONOMIC ANALYSIS. A. Introduction North Pacific Regional Connectivity Investment Project (RRP PAL 46382) ECONOMIC ANALYSIS A. Introduction 1. Project summary. The Asian Development Bank (ADB) will support Palau to develop a fiber optic

More information

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Corridors of Commerce DRAFT Scoring and Prioritization Process Patrick Weidemann Director of Capital Planning and Programming November 1, 2017 Project Purpose To develop and implement a scoring and project

More information

Implementing the MTO s Priority Economic Analysis Tool

Implementing the MTO s Priority Economic Analysis Tool Implementing the MTO s Priority Economic Analysis Tool presented at 6th National Conference on Transportation Asset Management presented by Alison Bradbury Ontario Ministry of Transportation November 2,

More information

Session 1.2 Discounting and Project Alternatives. Introductory Course on Economic Analysis of Investment Projects

Session 1.2 Discounting and Project Alternatives. Introductory Course on Economic Analysis of Investment Projects Session 1.2 Discounting and Project Alternatives Introductory Course on Economic Analysis of Investment Projects Project statements Comparison of benefits and costs Typically investment costs (equipment,

More information

Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO END-OF-CHAPTER QUESTIONS

Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO END-OF-CHAPTER QUESTIONS Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO END-OF-CHAPTER QUESTIONS 11-1 a. Project cash flow, which is the relevant cash flow for project analysis, represents the actual flow of cash,

More information

The Role of the Public and Private Sector in Transport Infrastructure

The Role of the Public and Private Sector in Transport Infrastructure The Role of the Public and Private Sector in Transport Infrastructure Infrastructure Finance and the Challenges of Improving Transport Infrastructure and Services Transport Forum 2005 Washington DC, March

More information

2. Basic Concepts In Project Appraisal [DoF Ch. 4; FP Ch. 3, 4, 5]

2. Basic Concepts In Project Appraisal [DoF Ch. 4; FP Ch. 3, 4, 5] R.E.Marks 2003 Lecture 3-1 2. Basic Concepts In Project Appraisal [DoF Ch. 4; FP Ch. 3, 4, 5] 1. Which Investment Criterion? 2. Investment Decision Criteria 3. Net Present Value Annual User Charge / Value

More information

Capital Budgeting Decisions

Capital Budgeting Decisions May 1-4, 2014 Capital Budgeting Decisions Today s Agenda n Capital Budgeting n Time Value of Money n Decision Making Example n Simple Return and Payback Methods Typical Capital Budgeting Decisions n Capital

More information

Ibrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing)

Ibrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing) Ibrahim Sameer (MBA - Specialized in Finance, B.Com Specialized in Accounting & Marketing) Introduction A long term view of benefits and costs must be taken when reviewing a capital expenditure project.

More information

SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM. Frequently Asked Questions

SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM. Frequently Asked Questions SMEC PAVEMENT MANAGEMENT AND ROAD INVENTORY SYSTEM Frequently Asked Questions SMEC COMPANY DETAILS SMEC Australia Pty Ltd Sun Microsystems Building Suite 2, Level 1, 243 Northbourne Avenue, Lyneham ACT

More information

ECONOMIC AND SOCIAL RESEARCH FOUNDATION (ESRF)

ECONOMIC AND SOCIAL RESEARCH FOUNDATION (ESRF) ECONOMIC AND SOCIAL RESEARCH FOUNDATION (ESRF) Policy Dialogue Seminar on POST BUDGET (2007/08) DISCUSSION FORUM A QUICK REVIEW OF THE IMPLICATIONS OF THE 2007/08 GOVERNMENT BUDGET ON TRANSPORT INFRASTRUCTURE

More information

CAPITAL BUDGETING AND THE INVESTMENT DECISION

CAPITAL BUDGETING AND THE INVESTMENT DECISION C H A P T E R 1 2 CAPITAL BUDGETING AND THE INVESTMENT DECISION I N T R O D U C T I O N This chapter begins by discussing some of the problems associated with capital asset decisions, such as the long

More information

University 18 Lessons Financial Management. Unit 2: Capital Budgeting Decisions

University 18 Lessons Financial Management. Unit 2: Capital Budgeting Decisions University 18 Lessons Financial Management Unit 2: Capital Budgeting Decisions Nature of Investment Decisions The investment decisions of a firm are generally known as the capital budgeting, or capital

More information

Impact of Next Generation Infrastructure on Australian Cities

Impact of Next Generation Infrastructure on Australian Cities Impact of Next Generation Infrastructure on Australian Cities ISNGI 2017 Institution of Civil Engineers, London 13 September 2017 Dr. Fariba Ramezani Associate Research Fellow SMART Infrastructure Facility

More information

KEY QUESTIONS FOR CONSULTANTS ECONOMIC ANALYSIS OF PROJECTS. Project Economic Evaluation Division Economics and Development Resource Center

KEY QUESTIONS FOR CONSULTANTS ECONOMIC ANALYSIS OF PROJECTS. Project Economic Evaluation Division Economics and Development Resource Center KEY QUESTIONS FOR CONSULTANTS ECONOMIC ANALYSIS OF PROJECTS Project Economic Evaluation Division Economics and Development Resource Center Copies of the Guidelines for the Economic Analysis of Projects

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 14-Jul-2014

More information

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade. Glossary GLOSSARY Advanced Construction (AC): Authorization of Advanced Construction (AC) is a procedure that allows the State to designate a project as eligible for future federal funds while proceeding

More information

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E.

in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. Life Cycle Cost Analysis in Pavement Design In Search of Better Investment Decisions Northwest Pavement Management Association 2016 Conference Jim Powell, P.E. What is it? Economic procedure That uses

More information

BFC2140: Corporate Finance 1

BFC2140: Corporate Finance 1 BFC2140: Corporate Finance 1 Table of Contents Topic 1: Introduction to Financial Mathematics... 2 Topic 2: Financial Mathematics II... 5 Topic 3: Valuation of Bonds & Equities... 9 Topic 4: Project Evaluation

More information

Rating criteria for toll road projects. February 2018

Rating criteria for toll road projects. February 2018 Rating criteria for toll road projects February 2018 Criteria contacts Pawan Agrawal Chief Analytical Officer CRISIL Ratings Email: pawan.agrawal@crisil.com Sameer Charania Director Rating Criteria and

More information

CHAPTER 2 LITERATURE REVIEW

CHAPTER 2 LITERATURE REVIEW CHAPTER 2 LITERATURE REVIEW Capital budgeting is the process of analyzing investment opportunities and deciding which ones to accept. (Pearson Education, 2007, 178). 2.1. INTRODUCTION OF CAPITAL BUDGETING

More information

Transportation Economics and Decision Making. Lecture-11

Transportation Economics and Decision Making. Lecture-11 Transportation Economics and Decision Making Lecture- Multicriteria Decision Making Decision criteria can have multiple dimensions Dollars Number of crashes Acres of land, etc. All criteria are not of

More information

What Is a Project? How Do We Justify a Project? 1.011Project Evaluation: Comparing Costs & Benefits Carl D. Martland

What Is a Project? How Do We Justify a Project? 1.011Project Evaluation: Comparing Costs & Benefits Carl D. Martland MIT Civil Engineering 1.11 -- Project Evaluation Spring Term 23 1.11Project Evaluation: Comparing Costs & Benefits Carl D. Martland Basic Question: Are the future benefits large enough to justify the costs

More information

All In One MGT201 Mid Term Papers More Than (10) BY

All In One MGT201 Mid Term Papers More Than (10) BY All In One MGT201 Mid Term Papers More Than (10) BY http://www.vustudents.net MIDTERM EXAMINATION MGT201- Financial Management (Session - 2) Question No: 1 ( Marks: 1 ) - Please choose one Why companies

More information

Project Evaluation and Programming I Project Evaluation

Project Evaluation and Programming I Project Evaluation Project Evaluation and Programming I Project Evaluation presented to MIT 1.201 Class presented by Lance Neumann Cambridge Systematics, Inc. November 20, 2008 Transportation leadership you can trust. Outline

More information

India: National Highway Sector II Project

India: National Highway Sector II Project Validation Report October 2017 India: National Highway Sector II Project Reference Number: PVR-517 Project Number: 35335-013 Loan Number: 2154 ABBREVIATIONS ADB Asian Development Bank CSC construction

More information

Economic Impact of Public Transportation Investment 2014 UPDATE

Economic Impact of Public Transportation Investment 2014 UPDATE Economic Impact of Public Transportation Investment 2014 UPDATE May 2014 Acknowledgements This study was conducted for the American Public Transportation Association (APTA) by Economic Development Research

More information

Review of the Federal Transit Administration s Transit Economic Requirements Model. Contents

Review of the Federal Transit Administration s Transit Economic Requirements Model. Contents Review of the Federal Transit Administration s Transit Economic Requirements Model Contents Summary Introduction 1 TERM History: Legislative Requirement; Conditions and Performance Reports Committee Activities

More information

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014 Methodology for Quantitative Procurement Options Analysis Discussion Paper Partnerships British Columbia Updated April 2014 Table of Contents Part 1: Overview... 1 1. Purpose... 1 1.1 Policy Context...

More information

1.133 M.Eng. Concepts of Engineering Practice Fall 2007

1.133 M.Eng. Concepts of Engineering Practice Fall 2007 MIT OpenCourseWare http://ocw.mit.edu 1.133 M.Eng. Concepts of Engineering Practice Fall 2007 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project

More information

Capital Budgeting CFA Exam Level-I Corporate Finance Module Dr. Bulent Aybar

Capital Budgeting CFA Exam Level-I Corporate Finance Module Dr. Bulent Aybar Capital Budgeting CFA Exam Level-I Corporate Finance Module Dr. Bulent Aybar Professor of International Finance Capital Budgeting Agenda Define the capital budgeting process, explain the administrative

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Railway Rolling Stock Project (RRP BAN 49094) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The project involves procurement of 214 meter gauge (MG) passenger carriages, 50 broad gauge (BG) passenger

More information

CA. Sonali Jagath Prasad ACA, ACMA, CGMA, B.Com.

CA. Sonali Jagath Prasad ACA, ACMA, CGMA, B.Com. MANAGEMENT OF FINANCIAL RESOURCES AND PERFORMANCE SESSIONS 3& 4 INVESTMENT APPRAISAL METHODS June 10 to 24, 2013 CA. Sonali Jagath Prasad ACA, ACMA, CGMA, B.Com. WESTFORD 2008 Thomson SCHOOL South-Western

More information

House Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2.

House Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2. House Bill 20 Implementation Tuesday,, 1:00 P.M. Capitol Extension E2.020 INTRODUCTION In response to House Bill 20 (HB 20), 84 th Legislature, Regular Session, 2015, and as part of the implementation

More information

I-75 at Overpass Road Interchange

I-75 at Overpass Road Interchange Benefit-Cost Analysis Supplementary Documentation TIGER Grant Program I-75 at Overpass Road Interchange Pasco County, FL October 16, 2017 0 Benefit-Cost Analysis Supplementary Documentation 1. Introduction

More information

The NPV profile and IRR PITFALLS OF IRR. Years Cash flow Discount rate 10% NPV 472,27 IRR 11,6% NPV

The NPV profile and IRR PITFALLS OF IRR. Years Cash flow Discount rate 10% NPV 472,27 IRR 11,6% NPV PITFALLS OF IRR J.C. Neves, ISEG, 2018 23 The NPV profile and IRR Years 0 1 2 3 4 5 Cash flow -10000 2000 2500 1000 4000 5000 Discount rate 10% NPV 472,27 IRR 11,6% 5 000,00 NPV 4 000,00 3 000,00 2 000,00

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN])

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN]) CAREC Corridors 1 and 6 Connector Road (Aktobe Makat) Reconstruction Project (RRP KAZ 48424) SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN]) 1. Sector Performance, Problems, and Opportunities

More information

Disclaimer: This resource package is for studying purposes only EDUCATION

Disclaimer: This resource package is for studying purposes only EDUCATION Disclaimer: This resource package is for studying purposes only EDUCATION Chapter 6: Valuing stocks Bond Cash Flows, Prices, and Yields - Maturity date: Final payment date - Term: Time remaining until

More information

Mind the Maintenance Gap: Framework, Global Trends, and Maintenance in OIC Member States

Mind the Maintenance Gap: Framework, Global Trends, and Maintenance in OIC Member States Mind the Maintenance Gap: Framework, Global Trends, and Maintenance in OIC Member States Dr Adnan Rahman Director General, IRF www.irfnet.ch THE INTERNATIONAL ROAD FEDERATION Promoting the development

More information

CHALLENGES IN FINANCING ROAD MAINTENANCE IN SUB-SAHARA AFRICA.

CHALLENGES IN FINANCING ROAD MAINTENANCE IN SUB-SAHARA AFRICA. CHALLENGES IN FINANCING ROAD MAINTENANCE IN SUB-SAHARA AFRICA. By F Y Addo-Abedi,Ph D Chief Executive, TANROADS International seminar on sustainable road financing & 1 investment. Introduction (The role

More information

MGT201 Financial Management All Subjective and Objective Solved Midterm Papers for preparation of Midterm Exam2012 Question No: 1 ( Marks: 1 ) - Please choose one companies invest in projects with negative

More information

PROJECT CRITERIA: ECONOMIC VIABILITY AND PROJECT ALTERNATIVES

PROJECT CRITERIA: ECONOMIC VIABILITY AND PROJECT ALTERNATIVES SESSION 1.2 PROJECT CRITERIA: ECONOMIC VIABILITY AND PROJECT ALTERNATIVES Introductory Course on Economic Analysis of Investment Projects Economics and Research Department (ERD) Discounted Cash Flow: Measures

More information

Long-Term Monitoring of Low-Volume Road Performance in Ontario

Long-Term Monitoring of Low-Volume Road Performance in Ontario Long-Term Monitoring of Low-Volume Road Performance in Ontario Li Ningyuan, P. Eng. Tom Kazmierowski, P.Eng. Becca Lane, P. Eng. Ministry of Transportation of Ontario 121 Wilson Avenue Downsview, Ontario

More information

CHAPTER 11. Depreciation, Impairments, and Depletion 1, 2, 3, 4, 5, 6, 10, 13, 19, 20, 28 7, 8, 9, 12, 30

CHAPTER 11. Depreciation, Impairments, and Depletion 1, 2, 3, 4, 5, 6, 10, 13, 19, 20, 28 7, 8, 9, 12, 30 CHAPTER 11 Depreciation, Impairments, and Depletion ASSIGNMENT CLASSIFICATION TABLE (BY TOPIC) Topics Questions Brief Exercises Exercises Problems Concepts for Analysis 1. Depreciation methods; meaning

More information

Economic Risk and Decision Analysis for Oil and Gas Industry CE School of Engineering and Technology Asian Institute of Technology

Economic Risk and Decision Analysis for Oil and Gas Industry CE School of Engineering and Technology Asian Institute of Technology Economic Risk and Decision Analysis for Oil and Gas Industry CE81.98 School of Engineering and Technology Asian Institute of Technology January Semester Presented by Dr. Thitisak Boonpramote Department

More information

Sample Questions for Chapters 10 & 11

Sample Questions for Chapters 10 & 11 Name: Class: Date: Sample Questions for Chapters 10 & 11 Multiple Choice Identify the letter of the choice that best completes the statement or answers the question. 1. Sacramento Paper is considering

More information

Chapter What are the important administrative considerations in the capital budgeting process?

Chapter What are the important administrative considerations in the capital budgeting process? Chapter 12 Discussion Questions 12-1. What are the important administrative considerations in the capital budgeting process? Important administrative considerations relate to: the search for and discovery

More information

Topic 1 (Week 1): Capital Budgeting

Topic 1 (Week 1): Capital Budgeting 4.2. The Three Rules of Time Travel Rule 1: Comparing and combining values Topic 1 (Week 1): Capital Budgeting It is only possible to compare or combine values at the same point in time. A dollar today

More information

HRTPO Strategic Campaign and Vision Plan for Passenger Rail

HRTPO Strategic Campaign and Vision Plan for Passenger Rail Presentation To HRTPO Steering Committee Agenda Item #1 HRTPO Strategic Campaign and Vision Plan for Passenger Rail Presentation By March 17, 2010 Transportation Economics & Management Systems, Inc. Study

More information

REPORT TO THE CAPITAL REGIONAL DISTRICT BOARD MEETING OF WEDNESDAY, SEPTEMBER 8, 2010

REPORT TO THE CAPITAL REGIONAL DISTRICT BOARD MEETING OF WEDNESDAY, SEPTEMBER 8, 2010 REPORT TO THE CAPITAL REGIONAL DISTRICT BOARD MEETING OF WEDNESDAY, SEPTEMBER 8, 2010 SUBJECT City of Victoria Request for General Strategic Priorities Funding Application Support Johnson Street Bridge

More information

Cost-benefit analysis in the context of EU Cohesion funding - tools, methodology and available support

Cost-benefit analysis in the context of EU Cohesion funding - tools, methodology and available support Cost-benefit analysis in the context of EU Cohesion funding - tools, methodology and available support Massimo Marra JASPERS Networking and Competence Centre IPA Conference Impact Assessment What can we

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Country Partnership Strategy: Viet Nam, 2012 2015 SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Investment in the transport sector in Viet

More information

Project 06-06, Phase 2 June 2011

Project 06-06, Phase 2 June 2011 ASSESSING AND INTERPRETING THE BENEFITS DERIVED FROM IMPLEMENTING AND USING ASSET MANAGEMENT SYSTEMS Project 06-06, Phase 2 June 2011 Midwest Regional University Transportation Center College of Engineering

More information