Cost Estimation for Regional Transmission Overlay Study (RTOS)

Size: px
Start display at page:

Download "Cost Estimation for Regional Transmission Overlay Study (RTOS)"

Transcription

1 Cost Estimation for Regional Transmission Overlay Study (RTOS)

2 Purpose & Key Takeaways Purpose: To provide detail for MISO s cost estimation approach Key Takeaways: Planning-Level and Scoping-Level MISO cost estimate approach Generic Cost Estimation Data

3 Cost Estimates: Overview Planning-Level cost estimates will be used to compare long-term indicative overlay roadmaps Why does MISO develop cost estimates Prior to FERC Order 1000, Transmission Owners or stakeholders provided cost estimates for regional projects FERC Order 1000 introduced competition to who constructs, owns, and operates regionally cost shared projects Project cost is one area that Transmission Owners and Developers compete Stakeholders sought MISO s involvement to develop cost estimates MISO Staff Expertise 3

4 Cost Estimates: Planning-Level and Scoping-Level MISO estimates project cost in two stages Planning and Scoping A Planning-Level cost estimate is a high level cost estimate for facilities in studies based on overall facility characteristics A Scoping-Level cost estimate is a preliminary cost estimate based on information derived from further research on particular project requirements in terms of assumed transmission line routing and construction details of line and substation 4

5 RTOS Study Cost Estimates: Regional Needs Identification Long term Indicative Overlay Roadmaps Development MISO Planning-Level cost estimate Preliminary Regional Plan Identification Candidate Regional Plan Evaluation MISO Scoping-Level cost estimate 5

6 Planning-Level Cost Estimate: Transmission Line Length; Voltage; Conductor; Structure, New or Re-Conductor Terrain Type Right-of-Way Cost Construction Cost Estimate AFUDC; Overhead; Contingency Project Implementation Cost Estimate 6

7 Planning-Level Cost Estimate: Transmission Line Inputs Transmission Estimate Inputs Definition Source: Straight Line Length + 20% Straight line between two interconnecting substations +20% Geography Voltage and Circuits Determined by the Voltage level and the number of circuits on the proposed line Planning Solution Idea Conductor Type ACSR, ACSS, or HTLS Planning Solution Idea Structure Type New or Re-Conductor Terrain Type Right-of-Way Width Lattice, or Tubular structure - determined to match existing structure types in the project area. Whether the proposed line is new, or re-conductoring an existing line. Farmland, Desert, Wetland, Suburban, Rolling Hill, Urban, Mountain, Forested. Value is determined by the Voltage level and the number of circuits on the proposed line. Planning Solution Idea Planning Solution Idea Geography Estimate Input Data AFUDC Allowance for Funds Used During Construction Estimate Input Data Overhead Contingency Services needed to complete the project, such as: Construction Management; Project Management; Permits; Legal Fees; and any other indirect costs. Additional funds included in estimate to account for unknown conditions at the time of completing the estimate Estimate Input Data Estimate Input Data 7

8 Planning-Level Cost Estimate: Substation # of New Positions; Arrangement; Voltage; New/Existing site Major Equipment (Transformer, Shunt Reactor, Series Capacitor) Construction Cost Estimate AFUDC; Overhead; Contingency Project Implementation Cost Estimate 8

9 Planning-Level Cost Estimate: Substation Inputs Substation Estimate Inputs Definition Source: # of New Positions Number of new line and/or major equipment positions added with the proposed project Planning Solution Idea Arrangement Ring Bus or Breaker-and-a-Half Bus Arrangement. Planning Solution Idea New Substation Adder If Substation is new, general facilities are needed such as land cost, grading, fencing, grounding, and a control enclosure. Planning Solution Idea Shunt Reactor MVA If a shunt reactor is required, the MVA will be specified. Planning Solution Idea Series Capacitor MVA If a series capacitor is required, the MVA will be specified. Planning Solution Idea Transformer MVA If a transformer is required, the MVA at the voltages of the transformer will be specified. Planning Solution Idea AFUDC Allowance for Funds Used During Construction Estimate Input Data Overhead Contingency Services needed to complete the project, such as: Construction Management; Project Management; Permits; Legal Fees; and any other indirect costs. Additional funds included in estimate to account for unknown conditions at the time of completing the estimate Estimate Input Data Estimate Input Data 9

10 Planning-Level Base Cost Transmission Line 230kV Single 345kV Single 345kV Double 500kV Single 765kV Single Circuit Circuit Circuit Circuit Circuit Base cost ($/mile) in 2017$, M=Million Conductor Type $1.2M $2.0M $3.3M $2.1M $2.45M Assumptions for Base cost as mentioned below ACSS ACSS ACSS ACSR ACSR Structure Type Tubular Steel Tubular Steel Tubular Steel Lattice Steel Lattice Steel Length Greater than 10 Miles Greater than 10 Miles Greater than 10 Miles Greater than 10 Miles Greater than 10 Miles Terrain Flat Farmland Flat Farmland Flat Farmland Flat Farmland Flat Farmland Base Costs do not include AFUDC, Overhead, or Contingency 10

11 Planning-Level Base Cost Substation 230 kv Substation 345 kv Substation 500 kv Substation 765kV Substation* New line position Existing Substation Ring Bus New line position Existing Substation Breaker-and-a-Half Bus New Substation 4 positions Ring Bus New Substation 4 positions Breaker-and-a-Half Bus $1.6M $2.4M $3.3M $11.4M $2.4M $3.7M $4.9M $13.8M $8.4M $12.1M $15.8M $50.1M $11.7M $17.0M $22.4M $59.9M *765kV Line Positions include one 300MVAr Reactor per line position 2017 Dollars, M = Million Base Costs do not include AFUDC, Overhead, or Contingency 11

12 Planning-Level Base Cost Substation Transformers Transformer 300 MVA 500 MVA 700 MVA 750 MVA 1200 MVA 2250 MVA 115kV/345kV $3.3M $5.6M $7.8M 138kV/345kV $3.3M $5.6M $7.8M 161kV/345kV $3.3M $5.6M $7.8M 230kV/500kV $9.2M $14.7M 345kV/500kV $10.9M $17.4M 345kV/765kV $40.7M 500kV/765kV $40.7M 2017 Dollars, M = Million 12

13 Feedback MISO presented Cost Estimation Data in the February Planning Subcommittee meeting, and the February Economic Planning Users Group meeting and requested feedback Feedback was received on March 9, 2017 MISO will provide responses to the feedback received at upcoming Planning Subcommittee, and Economic Planning Users Group meetings 13

14 Contact Information Devang Joshi, PE Principal Transmission Design Engineer MISO Alex Monn, PE Senior Substation Design Engineer MISO 14

15 15 END

16 16 APPENDIX

17 Scoping-Level Estimate: Transmission Line Planning-Level Estimate Straight Line Length +20% Voltage & # of Circuits Conductor Type Scoping-Level Estimate Google Earth Line Routing Voltage & # of Circuits Conductor Type Conductor Size Fittings & Accessories Shield Wire 17

18 Scoping-Level Estimate: Transmission Line Planning-Level Estimate Structure Type Scoping-Level Estimate Structure Type # of Structures New or Re-conductor Right-of-Way Foundation Details New or Re-conductor Right-of-Way Terrain Type Terrain Type 18

19 Scoping-Level Estimate: Transmission Line Planning-Level Estimate AFUDC Overhead Contingency Scoping-Level Estimate AFUDC Construction Management Project Management Permits & Legal Fees Indirect Costs Contingency 19

20 Scoping-Level Estimate: Substation Planning-Level Estimate # of New Positions Scoping-Level Estimate Mobilization & Demobilization All Equipment, Bus & Fittings Steel Stands Foundations Conduit & Control Cable Relay Panels 20

21 Scoping-Level Estimate: Substation Planning-Level Estimate Arrangement New Substation Adder Scoping-Level Estimate Arrangement Land Cost Clearing & Grubbing Grading, Fence & Grounding Control Enclosure 21

22 Scoping-Level Estimate: Substation Planning-Level Estimate Shunt Reactor MVA Series Capacitor MVA Transformer MVA Scoping-Level Estimate Shunt Reactor MVA Series Capacitor MVA Transformer MVA 22

23 Scoping-Level Estimate: Substation Planning-Level Estimate AFUDC Overhead Contingency Scoping-Level Estimate AFUDC Construction Management Project Management Permits & Legal Fees Indirect Costs Contingency 23

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 Attachment GG Projected Proportion Actual True Up Revenue of Revenues Revenue Interest allocated

More information

Information Document FAC-008-AB-3 Facility Ratings ID # RS

Information Document FAC-008-AB-3 Facility Ratings ID # RS Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

PROJECT COST TASK FORCE. June 2, 2011

PROJECT COST TASK FORCE. June 2, 2011 PROJECT COST TASK FORCE June 2, 2011 Table of Contents Introduction...3 RSC Motion 1...3 Problem Summary...3 RSC Motion 4...3 Problem Summary...3 Project Tracking Current Process...4 PCTF Recommendations...4

More information

IMPORTANT INFORMATION Invitation to Bid No. TS12-S-10 Kindly acknowledge important revisions to the terms and conditions under the bidding documents in details as follows: Volume I of IV 1. TC-SUB-01 Data

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- A SCE-0, Vol. 0 R A E. Takayesu (U -E) 01 General Rate Case rd Errata ERRATA Transmission & Distribution (T&D) Volume R System Planning Before the Public

More information

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) :

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) : TGST 1-1: Refer to PNM S 2014 FERC Form 1 page 207, line 50, Account 353 Station Equipment, please provide a description of significant projects ($5 million or more) contributing to the increase of approximately

More information

Volume 2A. Direct Testimony and Supporting Schedules: Kyle Sem. Rate Base. 1/5 Tab

Volume 2A. Direct Testimony and Supporting Schedules: Kyle Sem. Rate Base. 1/5 Tab Volume A Direct Testimony and Supporting Schedules: Kyle Sem Rate Base 1/ Tab Before the Minnesota Public Utilities Commission State of Minnesota In the Matter of the Application of Otter Tail Power Company

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 92 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 101 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

Nelson Electricity Ltd Asset Management Plan Update

Nelson Electricity Ltd Asset Management Plan Update Nelson Electricity Ltd Asset Management Plan Update April 2017 March 2027 April 2017 Nelson Electricity Ltd central Nelson city view In accordance with the Commerce Act Electricity Distribution Information

More information

PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP TRANSMISSION

PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP TRANSMISSION PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP REGIONALLY FUNDED TRANSMISSION Presented on behalf of SPP s Transmission Owners SPP Strategic Planning Committee Meeting December 3, 2010 REGIONALLY

More information

Before the Minnesota Public Utilities Commission. State of Minnesota

Before the Minnesota Public Utilities Commission. State of Minnesota Direct Testimony and Schedules Christopher E. Fleege Before the Minnesota Public Utilities Commission State of Minnesota In the Matter of the Application of Minnesota Power for Authority to Increase Rates

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.16-09- Exhibit No.: SCE-0, Vol. 08 Witnesses: J. R. Goizueta M. Flores A (U 338-E) 018 General Rate Case Transmission & Distribution (T&D) Volume 8 - Infrastructure Replacement Before

More information

ARKANSAS PUBLIC SERVICE COMMISSION

ARKANSAS PUBLIC SERVICE COMMISSION 2 nd Revised Sheet No. 61.0.1 Schedule Sheet 1 of 18 Replacing: 1 st Revised Sheet No. 61.0.1 61.0. TARIFF GOVERNING THE INSTALLATION OF ELECTRIC UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS AND UNDERGROUND

More information

MainPower New Zealand Limited. Asset Management Plan

MainPower New Zealand Limited. Asset Management Plan MainPower New Zealand Limited. Asset Management Plan 2015 2025 MAINPOWER NEW ZEALAND LIMITED ASSET MANAGEMENT PLAN UPDATE 2015-2025 MainPower New Zealand Limited Asset Management Plan Update 2015-2025

More information

T-D Interconnections: Best Value Planning White Paper January 2016

T-D Interconnections: Best Value Planning White Paper January 2016 T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and

More information

Title Page Southern California Edison Company Tariff Title: Rate Schedule Tariff Record Title: Rate Schedule FERC No. 425 FERC FPA Electric Tariff AMENDED AND RESTATED ELDORADO SYSTEM OPERATINGAGREEMENT

More information

Connection and Use of System Charge Methodology Statement ("Condition 25 Statement")

Connection and Use of System Charge Methodology Statement (Condition 25 Statement) Connection and Use of System Charge Methodology Statement ("Condition 25 Statement") Revised Effective Date: 1 st January 2016 Approved by the Authority for Electricity Regulation, Oman Connection and

More information

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g 2012 SERTP Welcome SERTP 2012 First RPSG Meeting & Interactive Training Session 1 2012 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for

More information

MISO Planning Process. May 31, 2013

MISO Planning Process. May 31, 2013 MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board

More information

FERC Order 890 APS Attachment E SRP Attachment K

FERC Order 890 APS Attachment E SRP Attachment K APS/SRP 2 nd Quarter Stakeholder FERC Order 890 APS Attachment E SRP Attachment K APS Deer Valley Facility Phoenix, Arizona June 14, 2018 9 AM -12 PM Agenda 1. Welcome, Introductions, and Stakeholder Meeting

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Irma Wind Power Project Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission

More information

PCTF. April 27 & 28, Tulsa, OK. Attendees

PCTF. April 27 & 28, Tulsa, OK. Attendees PCTF April 27 & 28, Tulsa, OK Attendees In Person 4/27: Bruce Cude, Xcel Energy Cary Frizzell, SPP Terri Gallup, AEP Thomas Hestermann, Sunflower Tom Littleton, OMPA Katherine Prewitt, SPP Mitchell Williams,

More information

Power Workers' Union (PWU) INTERROGATORY #1. Ref (a): Participant Information Package: Exhibit C1-2-1, Page 5 of 6, Table 2 (OM&A Expenditures)

Power Workers' Union (PWU) INTERROGATORY #1. Ref (a): Participant Information Package: Exhibit C1-2-1, Page 5 of 6, Table 2 (OM&A Expenditures) Filed: 0-0- 0-0 Tx Rates Schedule Page of Power Workers' Union (PWU) INTERROGATORY # Ref (a): Participant Information Package: Exhibit C--, Page of, Table (OM&A Expenditures) Table : 0 Board Approved versus

More information

Settlements and ADR Time Bars. Market Subcommittee February 8, 2018

Settlements and ADR Time Bars. Market Subcommittee February 8, 2018 Settlements and ADR Time Bars Market Subcommittee February 8, 2018 Purpose and Key Takeaways Purpose Update stakeholders on proposed Tariff revisions establishing time limits for disputes, corrections

More information

Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630

Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630 Ms. Roni Reese January 10, 2008 Page 1 January 10, 2008 Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630 Re: Startrans IO,

More information

SUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES. The following summary explanations of Statements and Schedules are intended as a general guide.

SUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES. The following summary explanations of Statements and Schedules are intended as a general guide. Black Hills Power, Inc. South Dakota Revenue Requirement Model Description SUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES The following summary explanations of Statements and Schedules are intended as

More information

Wanganui - Stratford Investment Proposal. Attachment B Costing report

Wanganui - Stratford Investment Proposal. Attachment B Costing report Wanganui - Stratford Investment Proposal Attachment B Costing report September 2009 Document Revision Control Document Number/Version Description Date 001/ A Wanganui-Stratford Investment Proposal Attachment

More information

SPP-AECI Joint Projects

SPP-AECI Joint Projects SPP-AECI Joint Projects 1 Morgan Transformer Project Addition of a new 400 MVA 345/161 kv Transformer at AECI s Morgan substation and an uprate of the 161 kv line between Morgan and Brookline Located in

More information

Submission to the Economic Regulation Authority

Submission to the Economic Regulation Authority Submission to the Economic Regulation Authority NEW FACILITIES INVESTMENT TEST PRE-APPROVAL APPLICATION Mid West Energy Project (southern section) Neerabup to Three Springs Terminal via Eneabba Published

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,

More information

Information Disclosure

Information Disclosure Electricity Ashburton Limited trading as EA Networks Information Disclosure Prepared according to subpart 3 of the Part 4A Commerce Act 1986 Assessment Period: 1 April 2011 31 March 2012 Date: 11 December

More information

TRANSMISSION CHARGING STATEMENT

TRANSMISSION CHARGING STATEMENT TRANSMISSION CHARGING STATEMENT 1 September 2016 1 September 2016 TABLE OF CONTENTS Page 1 Introduction... 1 2 General System Charges... 4 3 Site Specific Charges... 5 4 Connection Assets... 8 5 Least

More information

IMPORTANT INFORMATION Invitation to Bid No. RTS2-S-17 Kindly acknowledge important revisions to the terms and conditions under the bidding documents in details as follows: 1. According to Article F-15.

More information

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects

SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects SPP s Regional Review of SPP-MISO Coordinated System Plan Recommended Interregional Projects January 4, 2016 SPP Interregional Relations Table of Contents Executive Summary... 2 Introduction... 5 Stakeholder

More information

DIRECT TESTIMONY OF PAUL E. HAERING (CAPITAL PLAN)

DIRECT TESTIMONY OF PAUL E. HAERING (CAPITAL PLAN) BEFORE THE NEW YORK STATE PUBLIC SERVICE COMMISSION ----------------------------------------------------------------------------x Proceeding on Motion of the Commission as to the Rates, Charges, Rules

More information

Information Disclosure Reports prepared according to Part 4 of the Commerce Act 1986

Information Disclosure Reports prepared according to Part 4 of the Commerce Act 1986 Information Disclosure Reports prepared according to Part 4 of the Commerce Act 1986 For the Year Ended CONTENTS INTRODUCTION REPORTS DESCRIPTION 1 ANALYTICAL RATIOS 2 REPORT ON RETURN ON INVESTMENT 3

More information

Whirlwind AA-Bank RAS Modifications

Whirlwind AA-Bank RAS Modifications Whirlwind AA-Bank RAS Modifications Edison Team Members: Adrian Franco Electric System Planning Bill Zhang - Protection Engineering Obinna Obah - Power System Controls Hans Bakker - Communications Presentation

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Economic Impacts on New Jersey of Upgrading PSE&G s Susquehanna-Roseland Transmission System

Economic Impacts on New Jersey of Upgrading PSE&G s Susquehanna-Roseland Transmission System Economic Impacts on New Jersey of Upgrading PSE&G s Susquehanna-Roseland Transmission System Dr. Joseph J. Seneca Dr. Michael L. Lahr Dr. James W. Hughes Will Irving May 2009 Table of Contents EXECUTIVE

More information

Substation Engineering. 5 DAY COURSE (5 CPD Credits) Presented by leading TAP and ESKOM professionals. joint venture company. and

Substation Engineering. 5 DAY COURSE (5 CPD Credits) Presented by leading TAP and ESKOM professionals. joint venture company. and Substation Engineering 5 DAY COURSE (5 CPD Credits) Presented by leading TAP and ESKOM professionals a and joint venture company About the Course COURSE DESCRIPTION The course provides an in-depth overview

More information

EEI Survey of Transmission Investment. Historical and Planned Capital Expenditures ( )

EEI Survey of Transmission Investment. Historical and Planned Capital Expenditures ( ) EEI Survey of Transmission Investment Historical and Planned Capital Expenditures (1999-2008) Published by: Edison Electric Institute May 2005 2005 by the Edison Electric Institute (EEI). All rights reserved.

More information

Electricity Distribution (Information Disclosure) Requirements October 2008

Electricity Distribution (Information Disclosure) Requirements October 2008 Electricity Distribution (Information Disclosure) Requirements 2008 31 October 2008 ELECTRICITY DISTRIBUTION (INFORMATION DISCLOSURE) REQUIREMENTS 2008 1. Title, commencement, and application Contents

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an

More information

Q&A Distribution equipment and materials

Q&A Distribution equipment and materials Q&A Distribution equipment and materials ITB-223/17 Establishing Long Term Agreement (LTA) in Two Lots for purchasing various capacities Transformers and Electricity supplies under Funding Facility for

More information

Enbridge Battle Sands 594S Substation Connection Needs Identification Document

Enbridge Battle Sands 594S Substation Connection Needs Identification Document APPENDIX C AESO PIP Enbridge Battle Sands 594S Substation Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to October 2015, the AESO conducted a Participant

More information

2012 Budget. Customer Presentation October 10, Helping to keep the lights on, businesses running and communities strong

2012 Budget. Customer Presentation October 10, Helping to keep the lights on, businesses running and communities strong 2012 Budget Customer Presentation October 10, 2011 Helping to keep the lights on, businesses running and communities strong Welcome & Overview Welcome! Introductions Tom Finco Budget Overview Kevin Szalacinski

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the ATCO Power Heartland Generating Station Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Addendum I. The price payable shall be subject to adjustment, up or down, in accordance with the following formula:

Addendum I. The price payable shall be subject to adjustment, up or down, in accordance with the following formula: Addendum I Sr No. 1: Price Variation Clause 1.1 Price quoted by the Bidder shall be fixed throughout the performance of the Contract and not subject to variation on any account except for 25kV Switchgears,

More information

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT (NERC Standard TPL-007-1) Revision 1 February 1, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503)

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Al Rothbauer 321S Substation And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act, S.A.

More information

The Breakdown and Mitigation of Technical Losses on Distribution Power Systems

The Breakdown and Mitigation of Technical Losses on Distribution Power Systems The Breakdown and Mitigation of Technical Losses on Distribution Power Systems Bo Yang - GE Energy James Weiss - Ameren Corporation Reigh Walling - GE Energy Lavelle Freeman - GE Energy Mike Marshall Presented

More information

Revised Cal. P.U.C. Sheet No E Cancelling Original Cal. P.U.C. Sheet No E. ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS

Revised Cal. P.U.C. Sheet No E Cancelling Original Cal. P.U.C. Sheet No E. ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS Revised Cal. P.U.C. Sheet No. 20093-E Cancelling Original Cal. P.U.C. Sheet No. 15575-E ELECTRIC RULE NO. 15 Sheet 1 APPLICABILITY: This rule is applicable to extension of electric Distribution Lines*

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

Q4 FY Presentation 26 th May 2016

Q4 FY Presentation 26 th May 2016 Q4 FY 2016- Presentation 26 th May 2016 1 Disclaimer This presentation and the discussion that follows may contain certain words or phrases that are forward - looking statements, based on current expectations

More information

Expenditure Forecast Methodology

Expenditure Forecast Methodology Forecast Methodology Regulatory Control Period 2018-19 to 2022-23 Version 1.0 Security Classification: Public ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box

More information

Information Disclosure prepared in accordance with the. Electricity Distribution Information Disclosure Determination 2012

Information Disclosure prepared in accordance with the. Electricity Distribution Information Disclosure Determination 2012 Information Disclosure prepared in accordance with the Electricity Distribution Information Disclosure Determination 2012 For the Year Ended 31 March 2013 COUNTIES POWER LIMITED Information Disclosure

More information

CAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA

CAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA CAWG MEETING July 25, 2007 Marriott Country Club Plaza Kansas City, MO 11:00 am 5:00 pm AGENDA 1. Introductions 11:00-11:10 2. STEP Screen to Portfolio Transition 11:10 12:00 Discussion lead by Charles

More information

Load and Resource Transmission Analysis 2011 through 2020

Load and Resource Transmission Analysis 2011 through 2020 Load and Resource Transmission Analysis through June, Prepared by: Joe Costello, Igor Kormaz and Mark Stout Background Pursuant to the provisions of Tri-State s Network Operating Agreements with its network

More information

Results of Operations Volume 03 Depreciation Study

Results of Operations Volume 03 Depreciation Study Application No.: A.16-09- Exhibit No.: SCE-09, Vol. 03 A3 Witnesses: P. Joseph A. Varvis R. White (U 338-E) 3rd ERRATA Results of Operations Volume 03 Depreciation Study Before the Public Utilities Commission

More information

ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M

ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M TABLE OF CONTENTS Schedule Schedule Name Page Sch 1 Summary

More information

Information Disclosure by Aurora Energy Ltd for the year ended 31 March 2008

Information Disclosure by Aurora Energy Ltd for the year ended 31 March 2008 Information Disclosure by Aurora Energy Ltd for the year ended 31 March 2008 Pursuant to the ELECTRICITY DISTRIBUTION (INFORMATION DISCLOSURE) REQUIREMENTS 2008 INDEX Page A Statutory Declaration for Publicly

More information

EDB Information Disclosure Requirements Information Templates for Schedules 1 10

EDB Information Disclosure Requirements Information Templates for Schedules 1 10 EDB Information Disclosure Requirements Information Templates for Schedules 1 10 Disclosure Date 31 August 2016 Disclosure Year (year ended) Templates for Schedules 1 10 excluding 5f 5g Template Version

More information

CUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS

CUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS CUSC - SECTION 14 CHARGING METHODOLOGIES CONTENTS 14.1 Introduction Part I -The Statement of the Connection Charging Methodology 14.2 Principles 14.3 The Calculation of the Basic Annual Connection Charge

More information

WISCONSIN PUBLIC SERVICE CORPORATION. C4. Standard Rules & Regulations Construction Policy RIIIM

WISCONSIN PUBLIC SERVICE CORPORATION. C4. Standard Rules & Regulations Construction Policy RIIIM Original Sheet No. C-48.01 EFFECTIVE IN All territory served. 1. DEFINITIONS a. Extension An extension is defined to include right-of-way, permits, easements, poles, conductors and appurtenances used in

More information

QUALITY CONTROL Prepared: D. Vree Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: D. Vree Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.6 Protection Filename ONL 15-080-T6_Protection_PP_v1 Version 1 - release for Expert

More information

Before the Minnesota Public Utilities Commission State of Minnesota. Docket No. E002/GR Exhibit (KAB-1) Distribution

Before the Minnesota Public Utilities Commission State of Minnesota. Docket No. E002/GR Exhibit (KAB-1) Distribution Direct Testimony and Schedules Kelly A. Bloch Before the Minnesota Public Utilities Commission State of Minnesota In the Matter of the Application of Northern States Power Company for Authority to Increase

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: J. Billingsley (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume 0 Transmission Construction & Maintenance Before the Public

More information

System Impact Study Report Generation Interconnection Request # GI

System Impact Study Report Generation Interconnection Request # GI System Impact Study Report Generation Interconnection Request # GI-2015-1 Executive Summary 250 MW Wind Generation Facility Comanche Daniels Park 345kV Line (L7015) Elbert County, Colorado Transmission

More information

ASSESSMENT TECHNICAL LOSSES IN DISTRIBUTION SYSTEM

ASSESSMENT TECHNICAL LOSSES IN DISTRIBUTION SYSTEM ASSESSMENT TECHNICAL LOSSES IN DISTRIBUTION SYSTEM AHMED HAMZAH KADHIM Electrical Power Engineering, Universiti Tenaga Nasional (UNITEN), Selangor, Malaysia Email: Ahmed_hamza546@yahoo.com ABSTRACT This

More information

Submitted by Western Power

Submitted by Western Power Final Determination on the New Facilities Investment Test for a 66/11 kv Medical Centre Zone Substation Expansion and Voltage Conversion of the Distribution Network Submitted by Western Power 19 February

More information

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 I. - Conditions and Definitions A. Contracts Before building an Extension, the Company may require the Applicant to sign a contract.

More information

KANSAS CITY POWER & LIGHT COMPANY P.S.C. MO. No. 2 Fourth Revised Sheet No Canceling P.S.C. MO. No. 2 Third Revised Sheet No. 1.

KANSAS CITY POWER & LIGHT COMPANY P.S.C. MO. No. 2 Fourth Revised Sheet No Canceling P.S.C. MO. No. 2 Third Revised Sheet No. 1. P.S.C. MO. No. 2 Fourth Revised 1.30 2 Third Revised 1.30 9. EXTENSION OF FACILITIES SECTIONS 9.01 THROUGH 9.11 SHALL BE APPLICABLE TO FACILITY EXTENSION AGREEMENTS EXECUTED ON AND AFTER JANUARY 1, 2018.

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 1 (Appendix) Witnesses: R. Woods (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume 1 Appendix to Operational Overview and Risk-Informed

More information

Q50 Facility Study. By Tucson Electric Power Company Transmission Planning March 7, Proposed Point of Interconnection: Vail Fort Huachuca 138kV

Q50 Facility Study. By Tucson Electric Power Company Transmission Planning March 7, Proposed Point of Interconnection: Vail Fort Huachuca 138kV Q50 Facility Study Proposed Point of Interconnection: Vail Fort Huachuca 138kV By Tucson Electric Power Company Transmission Planning March 7, 2018 PREPARED BY: FACILITY STUDY PREPARED FOR: TUCSON ELECTRIC

More information

Standard FAC Facility Ratings. A. Introduction

Standard FAC Facility Ratings. A. Introduction A. Introduction 1. Title: Facility Ratings 2. Number: FAC-008-3 3. Purpose: To ensure that Facility Ratings used in the reliable planning and operation of the Bulk Electric System (BES) are determined

More information

Regulation Director FERC Rates & Regulation. March 16, 2012

Regulation Director FERC Rates & Regulation. March 16, 2012 Regulation Director FERC Rates & Regulation March 16, 2012 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to Section

More information

DECISION AND ORDER ON PHASE 1

DECISION AND ORDER ON PHASE 1 Commission de l énergie de l Ontario DECISION AND ORDER ON PHASE 1 HYDRO ONE NETWORKS INC. Leave to construct a new transmission line and facilities in the Windsor-Essex Region, Ontario. Before: Ken Quesnelle

More information

OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986

OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986 OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986 FOR THE YEAR ENDED 31 MARCH 2010 CONTENTS 1. Introduction... 3 2. Disclaimer... 3

More information

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DE

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION Liberty Utilities (Granite State Electric) Corp. d/b/a Liberty Utilities Distribution Service Rate Case DIRECT TESTIMONY OF CHRISTIAN P. BROUILLARD

More information

Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection. November 7, :00pm CST

Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection. November 7, :00pm CST Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection November 7, 2018 2:00pm CST Agenda Introduction GridLiance West LLC (GridLiance) Background Transmission Formula Rate Template

More information

TRANSGRID PRICING METHODOLOGY 2015/ /18. Contents

TRANSGRID PRICING METHODOLOGY 2015/ /18. Contents Pricing Methodology TRANSGRID PRICING METHODOLOGY 2015/16 2017/18 Contents Pricing Methodology 1 Introduction 3 2 Duration 3 3 Which services are subject to this pricing methodology? 4 4 Overview of the

More information

4.1 Transmission Owners that maintain the transmission paths in Attachment B.

4.1 Transmission Owners that maintain the transmission paths in Attachment B. A. Introduction 1. Title: Transmission Maintenance 2. Number: FAC-501-WECC-2 3. Purpose: To ensure the Transmission Owner of a transmission path identified in Attachment B, Major WECC Transfer Paths in

More information

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With

More information

Information Disclosure prepared according to. subpart 3 of the Part 4A Commerce Act 1986

Information Disclosure prepared according to. subpart 3 of the Part 4A Commerce Act 1986 Information Disclosure prepared according to subpart 3 of the Part 4A Commerce Act 1986 For the Assessment Period: 1 April 2007-31 March 2008 I. Contents I. Introduction... 4 II. Structure of Eastland

More information

XXXXX. Skookum Creek Power Project. Interconnection Facilities Study and Project Plan

XXXXX. Skookum Creek Power Project. Interconnection Facilities Study and Project Plan XXXXX Skookum Creek Power Project Interconnection Facilities Study and Project Plan June 29, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights

More information

Project Administration Manual. India: Green Energy Corridor and Grid Strengthening Project. Project Numbers: October 2015

Project Administration Manual. India: Green Energy Corridor and Grid Strengthening Project. Project Numbers: October 2015 Green Energy Corridor and Grid Strengthening Project (RRP IND 44426) Project Administration Manual Project Numbers: 44426-016 October 2015 India: Green Energy Corridor and Grid Strengthening Project Contents

More information

APS/SRP Stakeholder Meeting For Transmission Planning

APS/SRP Stakeholder Meeting For Transmission Planning APS/SRP Stakeholder Meeting For Transmission Planning FERC Order 890 SRP Attachment K APS Attachment E SRP Facility Scottsdale, AZ December 15 th, 2017 9:00 11:00 A.M. Agenda 1. Welcome, Introductions,

More information

HVDC Inter-Island Link Upgrade Project. Investment Proposal. Part V Project Costs

HVDC Inter-Island Link Upgrade Project. Investment Proposal. Part V Project Costs HVDC Inter-Island Link Upgrade Project Investment Proposal Part V Project Costs Transpower New Zealand Limited 2005. All rights reserved 1 SUMMARY... 3 2 BACKGROUND... 4 3 APPROACH TO ESTIMATING COSTS...

More information

OtagoNet Joint Venture

OtagoNet Joint Venture OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986 FOR THE YEAR ENDED 31 MARCH 2011 CONTENTS 1. Introduction... 3 2. Disclaimer... 3

More information

REISSUED JUNE 1, 1988

REISSUED JUNE 1, 1988 REVISED SHEET NO. 29 Effective: October 28, 1966 RULE NO. 14 REISSUED JUNE 1, 1988 Service Connections and Facilities on Customer's Premises A. METER INSTALLATIONS AND MISCELLANEOUS SERVICE EQUIPMENT ON

More information

REQUEST FOR PROPOSALS FOR CITY OF LAGUNA BEACH

REQUEST FOR PROPOSALS FOR CITY OF LAGUNA BEACH REQUEST FOR PROPOSALS FOR CITY OF LAGUNA BEACH Cost Study for Citywide Undergrounding, Laguna Canyon Road and El Toro Road Undergrounding, & Electric Utility Distribution System Acquisition June 3, 2016

More information

RIIO T1 Business Plan. Section 5 Non-Load Related Expenditure

RIIO T1 Business Plan. Section 5 Non-Load Related Expenditure RIIO T1 Business Plan Section 5 Non-Load Related Expenditure Formal Issue: 28 July 2011 File Ref: 2011_SPT_Narrative_5 Non-Load Related Expenditure Non Load Narrative Page 1 of 151 Executive Summary The

More information

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018

Lower Voltage Interregional Economic Projects. RECBWG April 18, 2018 Lower Voltage Interregional Economic Projects RECBWG April 18, 2018 Interregional Gaps & Inconsistencies 1. No tariff defined cost allocation for sub 345 kv economic projects with PJM 2. Economic projects

More information

ELECTRA LIMITED 2010 INFORMATION FOR DISCLOSURE. Pursuant to Secton 57T of the Commerce Act 1986

ELECTRA LIMITED 2010 INFORMATION FOR DISCLOSURE. Pursuant to Secton 57T of the Commerce Act 1986 ELECTRA LIMITED 2010 INFORMATION FOR DISCLOSURE Pursuant to Secton 57T of the Commerce Act 1986 - - Table of contents Certificate for Disclosed Information 2 Statutory Declaration for Publicly Disclosed

More information

WECC Criterion TPL-001-WECC-CRT-3.1

WECC Criterion TPL-001-WECC-CRT-3.1 WECC Criterion TPL-001-WECC-CRT-3.1 A. Introduction 1. Title: Transmission System Planning Performance 2. Number: TPL-001-WECC-CRT-3.1 3. Purpose: To facilitate coordinated near-term and long-term transmission

More information

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Public Disclosure Copy

Public Disclosure Copy EAST ASIA AND PACIFIC Solomon Islands Energy & Extractives Global Practice IBRD/IDA Investment Project Financing FY 2009 Seq No: 14 ARCHIVED on 16-May-2018 ISR32246 Implementing Agencies: Ministry of Finance

More information