The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) :

Size: px
Start display at page:

Download "The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) :"

Transcription

1 TGST 1-1: Refer to PNM S 2014 FERC Form 1 page 207, line 50, Account 353 Station Equipment, please provide a description of significant projects ($5 million or more) contributing to the increase of approximately $34.2 million, or 12%, above the 2013 balance. For the increase to FERC Account Station Equipment, only one project meets the $5 million threshold indicated in the Information Request. However, to provide a more responsive answer, PNM has listed the projects greater than $2 million in the table below. PNM notes that these project totals can include multiple individual asset additions. For a listing of individual asset additions greater than $1 million to FERC Account 353, please see PNM Exhibit Western Project Number Project Name Amount JA Nation Trans IA $ 10,629, Alamo 115kv Static Var Compensator $ 4,350, Rio Puerco-Progress 115 kv Line $ 3,881, Replace OJO 345/115kv Transformer $ 2,789, kV Breaker Replace Fault Current $ 2,508, kv Relay Replacement $ 2,061,497 Description Transmission system enhancement/upgrade project associated with the construction of a transmission system interconnection (i.e., the wires-to-wires interconnection) Required to maintain a set voltage schedule at the Alamogordo 115 kv switching station to maintain acceptable system performance. System reliability improvements that will provide an additional transmission source into the fast growing area of northern Rio Rancho. Replacement of the existing Ojo 345/115 kv transformer with a new 300 MVA 345/115 kv transformer, to ensure safety, continued system reliably and adequate northern New Mexico import capability. Replace 115 kv circuit breakers that currently could be exposed to fault current greater than the breaker rating or within 94.5% of the breaker rating. Remove EM relay panels from control houses and replace panels equipped with new electronic relays. $ 26,221,957 1

2 TGST 1-2: Refer to PNM S 2014 FERC Form 1 page 207, line 52, Account 355 Poles and Fixtures, please explain and provide supporting documentation for the increase of approximately $13.2 million, or 9%, above the 2013 balance. The increase to Account 355 Poles and Fixtures of approximately $13.2 million is driven by the addition of a new substation, system upgrades, and replacement projects. Please see electronic file labeled PNM Exhibit TSGT 1-2 for the detailed listing of 2014 additions to Account

3 TGST 1-3: Refer to PNM S 2014 FERC Form 1 page 321, line 97, Account 566 Miscellaneous Transmission Expenses, please provide a detailed tabulation of every entry booked to this account during 2014, including name, description of cost item and amount. Please see electronic file labeled PNM Exhibit TGST 1-3 for a detailed breakdown of costs charged to Account

4 TGST 1-4: Please identify any regulatory assets reported in the 2014 Form 1 that now or in the future are expected to affect the charges under the Attachment H-1 Formula as a result of amortization through expenses, if and when approved by the appropriate regulatory body. Regulatory Assets are listed on Page 232 of PNM's 2014 FERC Form 1, and the only item that now or in the future is expected to affect the charges under the Attachment H-1 Formula as a result of amortization through expenses, if and when approved by the appropriate regulatory body, are costs related to the Alvarado Square Abandonment. 4

5 TGST 1-5: Please identify the FERC Account where NERC Fees are recorded and the total amount booked for In addition, please indicate whether the NERC Fees have been excluded from the transmission revenue requirement under the Formula. PNM pays fees to NERC annually based on NERC s allocation of its operating costs and those of the Regional Entities to load-serving entities based on the net energy needed to meet their users energy requirements. These fees are recorded to FERC Accounts 556 and The amount booked to FERC Account 556 in 2014 was $127,523. These costs are included in Attachment H-1 consistent with the settlement agreement filed on March 20, 2015 in Docket Nos. ER , et al. ( Settlement Agreement ). The amount booked to FERC Account in 2014 was $137. These costs are not included in Attachment H-1 consistent with the Settlement Agreement. 5

6 TGST 1-6: Please specify the FERC account number(s) in which PNM S records monetary penalties for violations of NERC Reliability Standards, and explain whether these accounts and the costs of any such monetary penalties are included in the Formula rates. To the extent there were any monetary penalties for violations of NERC Reliability Standards during 2014, please provide the following information for each year: a. the amount of the penalties; b. the FERC accounts where such penalties were recorded; c. the nature of the alleged violation that gave rise to the penalty; and d. the amount of the penalties included in the Formula. PNM records monetary penalties to FERC for violations of NERC Reliability Standards. These accounts and the costs of any such monetary penalties are not included in the Formula rates consistent with the agreed upon methodology. a. The amount of paid penalties in 2014 was $144,000. b. Penalties in 2014 were recorded to FERC 426. c. The 2014 NERC compliance violations were associated with self-identified violations of the Critical Infrastructure Protection Standards. d. No penalties were included in Attachment H-1. 6

7 TGST 1-7: Refer to Schedule 9 O&M, Line 57 of PNM S 2015 Annual Update Formula, FERC 421 Miscellaneous Non-operating income, please explain and provide supporting documentation for the decrease of approximately $4.0 million, or 62%, below the 2013 costs. In preparing the response to this Information Request, PNM identified that the inputs on Schedule 9 O&M, beginning with excel line 55 (FERC 416 M&J), were input in the incorrect account descriptions for both 2013 and Table 1 below shows the inputs in the corrected account descriptions for 2014 and Table 2 below shows the inputs in the corrected account descriptions for PNM notes that this change does not affect the ATTR or allocation to any rate as defined in Schedule 16 of Attachment H-1. After making these corrections, the decrease of approximately $4.0 million is related to FERC Account 426 Other deductions. The decrease is driven by one-time donations made in 2013 that were not made in Table 1 (2014 Corrected Schedule 9 O&M): Details of FERC Administrative Expenses Transferred Credit Source Current Year Expense FERC Administrative Expenses Transferred Credit company records (11,560,779) line 109, Attachment H-1 Corporate Allocation Expenses, by FERC account from PNMR Services Company, reported in FERC 922: FERC 403 Depreciation Expense company records 3,387,078 line 132, Attachment H-1 FERC 404 Amortization Expense company records 5,937,773 line 133, Attachment H-1 FERC 408 Taxes other than income company records 2,896,088 see Schedule 10 FERC 416 M&J company records - FERC 418 Nonoperating rental income company records (3,222) FERC 421 Misc Nonoperating income company records (23,751) FERC 426 Other deductions company records 2,484,095 FERC 427 Interest on long term debt company records (331,284) FERC 454 Rent from electric property company records (111,531) Misc 361 Total Corporate Allocation Expenses reported in FERC ,235,607 Total FERC Administrative Expenses Transferred Credit Page 323, line 183, column b 2,674,828 line 105, Attachment H-1 7

8 Table 2 (2014 Corrected Schedule 9 O&M): Details of FERC Administrative Expenses Transferred Credit Source Current Year Expense FERC Administrative Expenses Transferred Credit company records (9,349,484) line 107, Attachment H-1 Corporate Allocation Expenses, by FERC account from PNMR Services Company, reported in FERC 922: FERC 403 Depreciation Expense company records 3,234,876 line 131, Attachment H-1 FERC 404 Amortization Expense company records 5,714,473 line 132, Attachment H-1 FERC 408 Taxes other than income company records 3,576,410 see Schedule 10 FERC 416 M&J company records 32 FERC 421 Misc Nonoperating income company records (236,434) FERC 426 Other deductions company records 6,481,960 FERC 427 Interest on long term debt company records (326,452) FERC 454 Rent from electric property company records (110,429) Misc Alvarado Square Abandonment company records (77,914) Misc (78,269) Total Corporate Allocation Expenses reported in FERC ,178,253 Total FERC Administrative Expenses Transferred Credit Page 323, line 183, column b 8,828,769 8

9 REGARDING PNM s 2015 ANNUAL UPDATE TGST 1-8: Refer to Schedule 10 TOTI, Line 23 of PNM S 2015 Annual Update Formula, Property Related Costs, please explain and provide supporting documentation for the increase of approximately $2.0 million, or 9%, above the 2013 costs.. The increase in property tax expense for 2014 is a result of increased property values, changes in tax rates, and a corrected Maricopa County billing for 2013 received in Please see detail below. Line No. Property Tax Expense Change 1 Arizona Property Tax Expense 2 Assessed Value $379,099,000 $393,632,000 $14,533,000 3 Composite Tax Rate 1.11% 1.26% 0.15% 4 Tax Before Adjustments (Line 2 * Line 3) 4,219,249 4,954, ,330 5 Adjustments: Corrected Tax Bill Received in , ,987 7 Less: Tax on Leased Assets Recorded as Lease Expense (2,355,252) (2,848,709) (493,457) 8 Total Arizona Property Tax Expense (Line 4 + Line 6 + Line 7) 1,863,997 2,431, , New Mexico Property Tax Expense 11 Assessed Value 644,612, ,811,331 42,199, Composite Tax Rate 3.22% 3.22% 0.01% 13 Total New Mexico Property Tax Expense (Line 11 * Line 12) 20,749,507 22,148,046 1,398, Total Property Tax Expense (Line 8 + Line 13) $22,613,504 $24,579,903 $1,966,399 9

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 Attachment GG Projected Proportion Actual True Up Revenue of Revenues Revenue Interest allocated

More information

Southwestern Public Service Company. Attachment O - Transmission Formula Rate 2014 True-Up. Golden Spread Information Request No. 1.

Southwestern Public Service Company. Attachment O - Transmission Formula Rate 2014 True-Up. Golden Spread Information Request No. 1. The following questions pertain to the spreadsheet file 07-2015---Attachment_O- 2014_SPS_Transmission_Formula_Rate_True-Up_rv1 : GSEC 1-1. Refer to SPS s 2014 FERC Form 1 page 207, line 48 Account 350

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-239-3300 Fax: 202-239-3333 www.alston.com September 1, 2016 To: Re: Parties to FERC Docket No. ER08-386-000 Potomac-Appalachian

More information

Public Service Company of New Mexico Attachment H 1 Current Year Formula Rate

Public Service Company of New Mexico Attachment H 1 Current Year Formula Rate Attachment H 1 Formula Rate Allocators 1 Wages and Salary Allocation Factor 2 Transmission Wages Expense page 354, line 21, column b 5,229,728 3 4 Total Wages Expense page 354, line 28, column b 118,475,166

More information

Appendix 1 Duquesne Light Company Attachment H -17A Page 1 of 25 Formula Rate - Appendix A True-Up Notes FERC Form 1 Page # or Instruction 2017 Shaded cells are input cells Allocators 1 Transmission Wages

More information

T-D Interconnections: Best Value Planning White Paper January 2016

T-D Interconnections: Best Value Planning White Paper January 2016 T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and

More information

Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection. November 7, :00pm CST

Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection. November 7, :00pm CST Stakeholder Meeting for GridLiance West LLC 2019 Annual Formula Rate Projection November 7, 2018 2:00pm CST Agenda Introduction GridLiance West LLC (GridLiance) Background Transmission Formula Rate Template

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

IMPORTANT INFORMATION Invitation to Bid No. TS12-S-10 Kindly acknowledge important revisions to the terms and conditions under the bidding documents in details as follows: Volume I of IV 1. TC-SUB-01 Data

More information

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FERC FPA Electric Tariff INTERCONNECTION FACILITIES AGREEMENT

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount

More information

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015 2014 Attachment O True-Up Presentation Presenter: David Grover Manager, Transmission Pricing July 8, 2015 Presentation Purpose Discuss the 2014 Annual True-Up posting Walk through the timeline and mechanics

More information

Formula Rate - Appendix A Estimate Notes FERC Form 1 Page # or Instruction 2015 Shaded cells are input cells Allocators

Formula Rate - Appendix A Estimate Notes FERC Form 1 Page # or Instruction 2015 Shaded cells are input cells Allocators Page 1 of 25 Formula Rate - Appendix A Estimate Notes FERC Form 1 Page # or Instruction 2015 Shaded cells are input cells Allocators 1 Transmission Wages Expense p354.21.b 5,926,573 2 Total Wages Expense

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data Northern Indiana Public Service Company LLC Line Allocated No.

More information

APPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF

APPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF APPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF Appendix X sets forth the formula for calculating the Citizens Border

More information

2012 Budget. Customer Presentation October 10, Helping to keep the lights on, businesses running and communities strong

2012 Budget. Customer Presentation October 10, Helping to keep the lights on, businesses running and communities strong 2012 Budget Customer Presentation October 10, 2011 Helping to keep the lights on, businesses running and communities strong Welcome & Overview Welcome! Introductions Tom Finco Budget Overview Kevin Szalacinski

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- A SCE-0, Vol. 0 R A E. Takayesu (U -E) 01 General Rate Case rd Errata ERRATA Transmission & Distribution (T&D) Volume R System Planning Before the Public

More information

Potomac Electric Power Company ( Pepco ), Docket No. ER Informational Filing of 2017 Formula Rate Annual Update; Notice of Annual Meeting

Potomac Electric Power Company ( Pepco ), Docket No. ER Informational Filing of 2017 Formula Rate Annual Update; Notice of Annual Meeting Amy L. Blauman Assistant General Counsel Edison Place 701 Ninth Street NW Washington, DC 20068-0001 Office 202.872.2122 Fax 202.331.6767 pepco.com alblauman@pepcoholdings.com May 12, 2017 Ms. Kimberly

More information

1 GROSS REVENUE REQUIREMENT (page 3, line 31, column 5) $ 121,165,696

1 GROSS REVENUE REQUIREMENT (page 3, line 31, column 5) $ 121,165,696 Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/14 Utilizing FERC Form 1 Data Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line

More information

Office Fax pepco.com

Office Fax pepco.com Amy L. Blauman Assistant General Counsel EP1132 701 Ninth Street NW Washington, DC 20068-0001 Office 202.872.2122 Fax 202.331.6767 pepco.com alblauman@pepcoholdings.com May 16, 2016 Ms. Kimberly D. Bose

More information

Cost Estimation for Regional Transmission Overlay Study (RTOS)

Cost Estimation for Regional Transmission Overlay Study (RTOS) Cost Estimation for Regional Transmission Overlay Study (RTOS) Purpose & Key Takeaways Purpose: To provide detail for MISO s cost estimation approach Key Takeaways: Planning-Level and Scoping-Level MISO

More information

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER Gary A. Morgans 202 429 6234 gmorgans@steptoe.com 1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com The Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

First Revised Sheet No. 2758L. Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/10 Utilizing FERC Form 1 Data VECTREN

First Revised Sheet No. 2758L. Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/10 Utilizing FERC Form 1 Data VECTREN Midwest ISO FERC Electric Tariff, Fourth Revised Volume No. 1 First Revised Sheet No. 2758L Superseding Original Sheet No. 2758L Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended

More information

May 28, Southwest Power Pool, Inc., Docket No. ER15- Submission of Notice of Cancellation of Interconnection Agreement

May 28, Southwest Power Pool, Inc., Docket No. ER15- Submission of Notice of Cancellation of Interconnection Agreement May 28, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 RE: Southwest Power Pool, Inc., Docket No. ER15- Submission of Notice

More information

Southwestern Public Service Company ( SPS ) Transmission Formula Rate 2015 Projection

Southwestern Public Service Company ( SPS ) Transmission Formula Rate 2015 Projection 1-1. With reference to the file Attachment O-SPS Variance Analysis Projected 2015vs2014 with explanations page 8 of 14, lines 23-24, please provide a description of the general criteria that SPS uses for

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019)

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

July 30, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

July 30, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Regulation James A. Cuillier Director FERC Rates & Regulation July 30, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose:

More information

BES Definition Implementation Guidance

BES Definition Implementation Guidance BES Definition Implementation Guidance August 25, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 NERC BES Definition Implementation Guidance June 23, 2014 404-446-2560 www.nerc.com

More information

Energy Bar Association

Energy Bar Association Energy Bar Association EBA Energizer: Section 205/206 Fundamentals and Insights November 17, 2016 David DesLauriers, Director Black & Veatch Management Consulting, LLC Jason T. Gray Esq., Shareholder Duncan,

More information

Before the Minnesota Public Utilities Commission. State of Minnesota

Before the Minnesota Public Utilities Commission. State of Minnesota Direct Testimony and Schedules Christopher E. Fleege Before the Minnesota Public Utilities Commission State of Minnesota In the Matter of the Application of Minnesota Power for Authority to Increase Rates

More information

Standard PRC-004-3(x) Protection System Misoperation Identification and Correction

Standard PRC-004-3(x) Protection System Misoperation Identification and Correction Standard PRC-004-3(x) Protection System Misoperation Identification and Correction Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

Index. Rate Formula Template. For the 12 months ended 12/31/ New York Transco LLC

Index. Rate Formula Template. For the 12 months ended 12/31/ New York Transco LLC Index Rate Formula Template Utilizing FERC Form 1 Data New York Transco LLC Projected Annual Transmission Revenue Requirement For the 12 months ended 12/31/ Appendix A Main body of the Formula Rate Attachment

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an

More information

Southwestern Public Service Company Attachment O SPS Transmission Formula 2017 Projection Material Accounting Changes since January 1, 2016

Southwestern Public Service Company Attachment O SPS Transmission Formula 2017 Projection Material Accounting Changes since January 1, 2016 1 The Company has listed below any material changes that have taken effect since January 1, 2016. For additional information, please refer to the Southwestern Public Service Company FERC Form 1 for Q4

More information

WECC Criterion PRC-003-WECC-CRT-1.3

WECC Criterion PRC-003-WECC-CRT-1.3 WECC Criterion PRC-003-WECC-CRT-1.3 A. Introduction 1. Title: Analysis, Reporting, and Mitigation of Transmission and Generation Protection System and Remedial Action Scheme Misoperations Procedure 1 2.

More information

SUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES. The following summary explanations of Statements and Schedules are intended as a general guide.

SUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES. The following summary explanations of Statements and Schedules are intended as a general guide. Black Hills Power, Inc. South Dakota Revenue Requirement Model Description SUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES The following summary explanations of Statements and Schedules are intended as

More information

(1) (2) (3) (4) (5) 1 GROSS REVENUE REQUIREMENT (page 3, line 47) $

(1) (2) (3) (4) (5) 1 GROSS REVENUE REQUIREMENT (page 3, line 47) $ page 1 of 5 Attachment H Formula Rate NonLevelized Rate Formula Template For the 12 months ended 12/31/2018 Utilizing FERC Form 1 Data (1) (2) (3) (4) (5) Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT

More information

Submitted by Western Power

Submitted by Western Power Final Determination on the New Facilities Investment Test for a 66/11 kv Medical Centre Zone Substation Expansion and Voltage Conversion of the Distribution Network Submitted by Western Power 19 February

More information

I. FERC Uniform System of Accounts Changes

I. FERC Uniform System of Accounts Changes 1 The Company has listed below any material changes that have taken effect since January 1, 2012. For additional information, please refer to the Public Service Company of Colorado FERC 2012 Form No. 1,

More information

June 13, Informational Filing Public Service Electric and Gas Company, Annual True-Up Adjustment Docket No. ER

June 13, Informational Filing Public Service Electric and Gas Company, Annual True-Up Adjustment Docket No. ER Hesser G. McBride, Jr. Associate General Regulatory Counsel Law Department 80 Park Plaza, T5G, Newark, NJ 07102-4194 tel: 973.430.5333 fax: 973.430.5983 email: Hesser.McBride@pseg.com June 13, 2016 VIA

More information

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015

45-day Comment and Initial Ballot day Final Ballot. April, BOT Adoption. May, 2015 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Public Service Company of Colorado ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Public Service Company of Colorado ) Docket No. Page of UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Public Service Company of Colorado ) Docket No. ER- -000 PREPARED TESTIMONY OF Deborah A. Blair XCEL ENERGY SERVICES INC.

More information

Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630

Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630 Ms. Roni Reese January 10, 2008 Page 1 January 10, 2008 Ms. Roni Reese Senior Contracts Analyst California Independent System Operator Corporation 151 Blue Ravine Road Folsom, CA 95630 Re: Startrans IO,

More information

SUMMARY OF CAPITAL EXPENDITURES

SUMMARY OF CAPITAL EXPENDITURES Filed: May, 00 EB-00-000 Exhibit D Tab Schedule Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL BUDGET The proposed capital expenditures result from a rigorous business planning and work prioritization

More information

Applications for Participating Transmission Owner Status Attachment C - Transmission Revenue Requirement

Applications for Participating Transmission Owner Status Attachment C - Transmission Revenue Requirement Applications for Participating Transmission Owner Status Attachment C - Transmission Revenue Requirement The Transmission Revenue Requirement (TRR) for each Participating TO reflects the Participating

More information

TECHNICAL PAPER PRESENTATION

TECHNICAL PAPER PRESENTATION 1 W E L C O M E T O C O M E T 2 0 1 7 TECHNICAL PAPER PRESENTATION 2 ASSET MANAGEMENT ANALYTICS FOR A SUSTAINABLE GRID BY QASIM AZIZ P.E., & GAUTAM SONDE A B O U T T H E A U T H O R S C O M E T 2 0 1 7

More information

IMPORTANT INFORMATION Invitation to Bid No. RTS2-S-17 Kindly acknowledge important revisions to the terms and conditions under the bidding documents in details as follows: 1. According to Article F-15.

More information

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION Idaho Power Company Second Revised Sheet No. 72-1 I.P.U.C. No. 29, Tariff No. 101 First Revised Sheet No. 72-1 PUBLIC UTILITIES COMMISSION AVAILABILITY Service under this schedule is available throughout

More information

POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES

POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES POWER SYSTEM NOT IN A SECURE OPERATING STATE IN VICTORIA ON 15 JUNE 2016 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: November 2016 INCIDENT CLASSIFICATIONS Classification

More information

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014 Transmission Cost of Service Utilizing Historic Cost Data for 2013 and Projected Net Plant at YearEnd 2014 Projected TCOS Page 1 of 37 Line Transmission No. Amount 1 REVENUE REQUIREMENT (w/o incentives)

More information

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015

AEPTCo subsidiaries in PJM Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015 AEPTCo subsidiaries in PJM Transmission Cost of Service Utilizing Historic Cost Data for 2014 and Projected Net Plant at YearEnd 2015 Projected TCOS Page 1 of 75 AEP OHIO TRANSMISSION COMPANY Line Transmission

More information

Before the Minnesota Public Utilities Commission State of Minnesota. Docket No. E002/GR Exhibit (KAB-1) Distribution

Before the Minnesota Public Utilities Commission State of Minnesota. Docket No. E002/GR Exhibit (KAB-1) Distribution Direct Testimony and Schedules Kelly A. Bloch Before the Minnesota Public Utilities Commission State of Minnesota In the Matter of the Application of Northern States Power Company for Authority to Increase

More information

Wages & Salary Allocation Factor 1 Transmission Wages Expense p b 18,901,839

Wages & Salary Allocation Factor 1 Transmission Wages Expense p b 18,901,839 Page 1 of 29 Arizona Public Service Company Formula Rate Appendix A Notes Instruction 2014 Shaded cells are input cells Allocators Wages & Salary Allocation Factor 1 Transmission Wages Expense p354.21.b

More information

In addition to this transmittal letter and associated records for the etariff database, this filing includes:

In addition to this transmittal letter and associated records for the etariff database, this filing includes: 1050 Thomas Jefferson Street, NW Seventh Floor Washington, DC 20007 (202) 298-1800 Phone (202) 338-2416 Fax SUBMITTED VIA E-TARIFF FILING January 4, 2017 Kimberly D. Bose Secretary Federal Energy Regulatory

More information

September 1, Southern California Edison Company/ Docket No. ER

September 1, Southern California Edison Company/ Docket No. ER Anna J. Valdberg Senior Attorney anna.valdberg@sce.com September 1, 2011 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Southern California

More information

FERC Issued Order No. 773-A on Rehearing and Clarification of NERC Bulk Electric System Definition and Exceptions Process under Rules of Procedure

FERC Issued Order No. 773-A on Rehearing and Clarification of NERC Bulk Electric System Definition and Exceptions Process under Rules of Procedure To: From: Winston & Strawn Clients Raymond B. Wuslich Roxane E. Maywalt Date: Subject: FERC Issued Order No. 773-A on Rehearing and Clarification of NERC Bulk Electric System Definition and Exceptions

More information

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C McGuireWoods LLP 2001 K Street N.W. Suite 400 Washington, DC 20006-1040 Phone: 202.857.1700 Fax: 202.857.1737 www.mcguirewoods.com Julia Dryden English Direct: 202.857.1706 jenglish@mcguirewoods.com Fax:

More information

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015 I & M Projected TCOS Page 1 of 48 AEP East Companies Transmission Cost of Service Utilizing Historic Cost Data for 2014 and Projected Net Plant at YearEnd 2015 Line Transmission No. Amount 1 REVENUE REQUIREMENT

More information

Rate Formula Template Utilizing FERC Form 1 for the 12 months ended 12/31/2011. Oklahoma Gas and Electric Company. Index of Worksheets

Rate Formula Template Utilizing FERC Form 1 for the 12 months ended 12/31/2011. Oklahoma Gas and Electric Company. Index of Worksheets Rate Formula Template Utilizing FERC Form 1 for the 12 months ended 12/31/2011 (Enter whether "Projected Data" or "Actual Data") Projected Data Attachment H Addendum 2A Oklahoma Gas and Electric Company

More information

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2014 and Projected Net Plant at Year-End 2015 KPCo Projected TCOS Page 1 of 34 AEP East Companies Transmission Cost of Service Utilizing Historic Cost Data for 2014 and Projected Net Plant at YearEnd 2015 Line Transmission No. Amount 1 REVENUE REQUIREMENT

More information

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014 KPCo Projected TCOS Page 1 of 34 AEP East Companies Transmission Cost of Service Utilizing Historic Cost Data for 2013 and Projected Net Plant at YearEnd 2014 Line Transmission No. Amount 1 REVENUE REQUIREMENT

More information

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2012 and Projected Net Plant at Year-End 2013

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2012 and Projected Net Plant at Year-End 2013 Transmission Cost of Service Utilizing Historic Cost Data for 2012 and Projected Net Plant at YearEnd 2013 APCo Projected TCOS Page 1 of 36 Line Transmission No. Amount 1 REVENUE REQUIREMENT (w/o incentives)

More information

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014

AEP East Companies Transmission Cost of Service Formula Rate Utilizing Historic Cost Data for 2013 and Projected Net Plant at Year-End 2014 KGPCo Projected TCOS Page 1 of 34 AEP East Companies Transmission Cost of Service Utilizing Historic Cost Data for 2013 and Projected Net Plant at YearEnd 2014 Line Transmission No. Amount 1 REVENUE REQUIREMENT

More information

Workpapers. Transmission & Distribution Grid Operations SCE-03 Volume General Rate Case APPLICATION. An EDISON INTERNATIONAL Company

Workpapers. Transmission & Distribution Grid Operations SCE-03 Volume General Rate Case APPLICATION. An EDISON INTERNATIONAL Company An EDISON INTERNATIONAL Company (U 338-E) 215 General Rate Case APPLICATION Workpapers Transmission & Distribution Grid Operations SCE-3 Volume 7 N ovem ber 213 1 Workpaper - Southern California Edison

More information

Office Fax delmarva.com

Office Fax delmarva.com Amy L. Blauman Assistant General Counsel EP1132 701 Ninth Street NW Washington, DC 20068-0001 Office 202.872.2122 Fax 202.331.6767 delmarva.com alblauman@pepcoholdings.com May 16, 2016 Ms. Kimberly D.

More information

BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. ANDREW W. TUNNELL t: (205) 226-3439 f: (205) 488-5858 e: atunnell@balch.com BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

4.1 Transmission Owners that maintain the transmission paths in Attachment B.

4.1 Transmission Owners that maintain the transmission paths in Attachment B. A. Introduction 1. Title: Transmission Maintenance 2. Number: FAC-501-WECC-2 3. Purpose: To ensure the Transmission Owner of a transmission path identified in Attachment B, Major WECC Transfer Paths in

More information

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Before the Minnesota Public Utilities Commission State of Minnesota. Docket No. E002/GR Exhibit (IRB-1) Transmission

Before the Minnesota Public Utilities Commission State of Minnesota. Docket No. E002/GR Exhibit (IRB-1) Transmission Direct Testimony and Schedules Ian R. Benson Before the Minnesota Public Utilities Commission State of Minnesota In the Matter of the Application of Northern States Power Company for Authority to Increase

More information

DIRECT TESTIMONY OF PAUL E. HAERING (CAPITAL PLAN)

DIRECT TESTIMONY OF PAUL E. HAERING (CAPITAL PLAN) BEFORE THE NEW YORK STATE PUBLIC SERVICE COMMISSION ----------------------------------------------------------------------------x Proceeding on Motion of the Commission as to the Rates, Charges, Rules

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION SAN DIEGO GAS & ELECTRIC COMPANY ) DOCKET NO.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION SAN DIEGO GAS & ELECTRIC COMPANY ) DOCKET NO. UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION SAN DIEGO GAS & ELECTRIC COMPANY ) DOCKET NO. ER13-941-000 TRANSMISSION OWNER TARIFF FOURTH RATE FORMULA VOLUME NO. 11 FEBRUARY

More information

post such Annual Update on PJM s Internet website via link to the Transmission Services page or a similar successor page; and

post such Annual Update on PJM s Internet website via link to the Transmission Services page or a similar successor page; and 701 Ninth Street, NW Suite 1100 Washington, DC 20068 Amy L. Blauman Associate General Counsel 202-872-2122 202-331-6767 Fax alblauman@pepcoholdings.com May 14, 2012 Ms. Kimberly D. Bose Secretary Federal

More information

GridLiance West Transco LLC (GWT) Formula Rate Index

GridLiance West Transco LLC (GWT) Formula Rate Index (GWT) Formula Rate Index Appendix III Main Body of the Formula Attachment 1 Revenue Credit Worksheet Attachment 2 Cost Support Attachment 2a Cost Support Attachment 2b Cost Support Attachment 3 Incentives

More information

FAC Facility Interconnection Studies

FAC Facility Interconnection Studies A. Introduction 1. Title: Facility Interconnection Studies 2. Number: FAC-002-2 3. Purpose: To study the impact of interconnecting new or materially modified Facilities on the Bulk Electric System. 4.

More information

UNIFORM SYSTEM OF ACCOUNTS ACCOUNT LISTING BALANCE SHEET CHART OF ACCOUNTS ASSETS AND OTHER DEBITS

UNIFORM SYSTEM OF ACCOUNTS ACCOUNT LISTING BALANCE SHEET CHART OF ACCOUNTS ASSETS AND OTHER DEBITS BALANCE SHEET CHART OF ACCOUNTS ASSETS AND OTHER DEBITS 1. UTILITY PLANT 101 Electric plant in service (Major only). 101.1 Property under capital leases. 102 Electric plant purchased or sold. 103 Experimental

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line No. Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR

More information

GridLiance West Transco LLC (GWT) Formula Rate Index

GridLiance West Transco LLC (GWT) Formula Rate Index (GWT) Formula Rate Index Appendix III Main Body of the Formula Attachment 1 Revenue Credit Worksheet Attachment 2 Cost Support Attachment 2a Cost Support Attachment 2b Cost Support Attachment 3 Incentives

More information

STATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ ) ) ) ) ) ) ) ) )

STATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ ) ) ) ) ) ) ) ) ) STATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ I/M/O the Verified Petition of Rockland Electric Company For Approval of Changes in Electric Rates, Its Tariff For Electric

More information

Overview. Overview of SCE Retail Base TRR. SCE's retail Base Transmission Revenue Requirement is the sum of the following components:

Overview. Overview of SCE Retail Base TRR. SCE's retail Base Transmission Revenue Requirement is the sum of the following components: Table of Contents Worksheet Name Overview BaseTRR IFPTRR TrueUpAdjust TUTRR ROR PlantInService PlantStudy AccDep ADIT CWIP PHFU AbandonedPlant WorkCap IncentivePlant IncentiveAdder PlantAdditions Depreciation

More information

American Electric Power

American Electric Power American Electric Power 801 Pennsylvania Ave. NW, Suite 320 Washington, DC 20004-2615 AEP.com September 12, 2016 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E.,

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2018 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2018 Utilizing FERC Form 1 Data page 1 of 5 Thirteen Monthly Balances Composite Depreciation Rates Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line 31) $ 601,791,927 REVENUE CREDITS (Note T) Total Allocator 2 Account

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2015 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2015 Utilizing FERC Form 1 Data page 1 of 5 Thirteen Monthly Balances Composite Depreciation Rates Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line 31) $ 565,724,391 REVENUE CREDITS (Note T) Total Allocator 2 Account

More information

Southwestern Public Service Company. Transmission. Formula Rate Template. and Supporting Worksheets. Schedule 1 Annual Revenue Requirement

Southwestern Public Service Company. Transmission. Formula Rate Template. and Supporting Worksheets. Schedule 1 Annual Revenue Requirement Transmission Formula Rate Template and Supporting Worksheets Schedule 1 Annual Revenue Requirement For the 2014 TrueUp For the Period January 1, 2014 through December 31, 2014 Rate Formula Template Table

More information

ONCOR ELECTRIC DELIVERY COMPANY LLC

ONCOR ELECTRIC DELIVERY COMPANY LLC Tariff for Transmission Service Oncor Electric Delivery Company LLC 1616 Woodall Rodgers Fwy Dallas, Texas 75202-1234 Contents Sheet 1 Revision: Nine Effective Date: November 27, 2017 Page 1 of 2 CONTENTS

More information

EXCERPTS from the SAMS-SPCS SPS Technical Reference

EXCERPTS from the SAMS-SPCS SPS Technical Reference Problem Statement The existing NERC Glossary of Terms definition for a Special Protection System (SPS or, as used in the Western Interconnection, a Remedial Action Scheme or RAS) lacks clarity and specificity

More information

April 28, Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template

April 28, Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 Re: Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template Honorable Secretary Bose: Pursuant

More information

139 FERC 61,003 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

139 FERC 61,003 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 139 FERC 61,003 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. International Transmission

More information

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data

Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data page 1 of 5 Thirteen Monthly Balances Composite Depreciation Rates Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line 31) $ 575,738,213 REVENUE CREDITS (Note T) Total Allocator 2 Account

More information

Dkt. No. ER Draft Informational Filing. Table of Contents

Dkt. No. ER Draft Informational Filing. Table of Contents Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs. IFPTRR 2 Calculation of the Incremental Forecast Period TRR

More information

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows:

RECITALS. Now, Therefore, in consideration of the mutual covenants and agreements herein set forth, the Parties do hereby agree as follows: LEE COUNTY ELECTRIC COOPERATIVE STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED RENEWABLE GENERATION SYSTEMS GREATER THAN 100 KW AND LESS THAN OR EQUAL TO 1 MW TIER 3 This Interconnection Agreement

More information

Title Page Southern California Edison Company Tariff Title: Rate Schedule Tariff Record Title: Rate Schedule FERC No. 425 FERC FPA Electric Tariff AMENDED AND RESTATED ELDORADO SYSTEM OPERATINGAGREEMENT

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE

More information

Dkt. No. ER Draft Informational Filing. Table of Contents

Dkt. No. ER Draft Informational Filing. Table of Contents Table of Contents Worksheet Name Schedule Purpose Overview Base TRR Components. BaseTRR 1 Full Development of Retail and Wholesale Base TRRs. IFPTRR 2 Calculation of the Incremental Forecast Period TRR

More information

BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION

BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AND BINDING RATEMAKING TREATMENT FOR NEW WIND

More information

NERC TPL Standard Overview

NERC TPL Standard Overview NERC TPL-001-4 Standard Overview Attachment K Quarter 3 Stakeholder s Meeting September 29, 2016 1 Background New NERC TPL Standard 2016 TPL Plan and Status Update 2015 Planning Assessment Results Compliance

More information

Index. Rate Formula Template. For the 12 months ended 12/31/18. New York Transco LLC

Index. Rate Formula Template. For the 12 months ended 12/31/18. New York Transco LLC Index Rate Formula Template Utilizing FERC Form 1 Data New York Transco LLC Projected Annual Transmission Revenue Requirement For the 12 months ended 12/31/18 Appendix A Main body of the Formula Rate Attachment

More information