2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

Size: px
Start display at page:

Download "2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning"

Transcription

1 Application No.: Exhibit No.: Witnesses: A.1-0- A SCE-0, Vol. 0 R A E. Takayesu (U -E) 01 General Rate Case rd Errata ERRATA Transmission & Distribution (T&D) Volume R System Planning Before the Public Utilities Commission of the State of California Rosemead, California September, 01

2 Figure IV- Combined Distribution Circuit Upgrades and New Distribution Circuits 0 WBS Elements CET-ET-LG-PF, CET-ET-LG-NI Recorded 0-01/Forecast C (CPUC-Jurisdictional Constant 01 and Nominal $000) Nominal 01=,0 01=, 00=, 1 Constant 1. Distribution Plant Betterment, WBS Element CET-PD-LG-PB 01=, The Distribution Plant Betterment forecast expenditures include work required 01=, to meet 00=, anticipated load growth causing voltage violations, requiring neutral conductors to serve new customers, and to meet contingency scenarios. Work in this category improves voltage profiles to better serve customers by installing voltage regulators or increasing the size of conductor or cable. Neutral conductors, or fourth wires, are required on existing three-wire distribution circuits to serve new residential load. SCE also identifies areas where new cable, conductor, and switches are needed to improve reliability during contingency scenarios allowing the distribution system to keep as many customers energized as possible. Due to the diverse project scope, SCE does not forecast costs based on unit cost. A detailed discussion of how SCE plans for this category is explained in the Distribution & Subtransmission Planning Programs and Projects Section III.B. Figure IV-1 below shows 0 01 recorded and forecast expenditures 1 for the Distribution Plant Betterment budget. Recorded expenditures in 0 and 01 are higher compared to expenditures in surrounding years due to the inclusion of upgrades completed to meet 0 Refer to WP SCE-0 T&D-Vol., Book A, pp. (Tables IV- and IV- Expenditure Summary). 1 Id. --

3 Figure IV-1 Distribution Circuit Upgrades WBS Element CET-ET-LG-PF Recorded 0-01/Forecast (CPUC-Jurisdictional Constant 01 and Nominal $000) Nominal 01=0, 01=, 00=, 1 Constant Forecast expenditures for displayed in Figure IV-1 are calculated 01=,0 year-by- 01=, year and driven by forecast load growth and generation. Expenditures for both drivers are 00=, developed separately and combined to develop the forecast in Figure IV-1. In the 01 GRC, we described how SCE has modified its planning process to expand its ability to leverage capacity from neighboring circuits and substations to maximize the use of existing infrastructure. We also described that SCE must increase the upgrades in distribution circuit upgrades to build in more flexibility, as we build less new circuits. The increases in 01 through 00 are a continued reflection of increasing upgrades in this category, and declining expenditures for new distribution circuits. The load growth portion of the expenditure forecast is calculated using three main variables: capital expenditure forecast for previous years, DSP load growth, and planned DSP circuit additions, all of which indicate the need to construct Distribution Circuit Upgrades on the SCE distribution system. Expenditures for this category consider historical and existing expenditure and scope because project scope for this category is not typically created more than one to two years prior to the distribution need. The majority of projects in this category solves distribution needs identified in the Id. -1-

4 1 DER solutions will meet the current need associated with one or more of the projects, SCE will refund the balance to customers. However, should the projects be determined to be needed at or sooner than expected due to increased load growth not met by DERs, then SCE will have recovered the revenue requirements associated with these expenditures as part of this request. IV. $, $,1 CAPITAL EXPENDITURE FORECASTS SCE is forecast to spend $, million in total capital expenditures from 01 00, of which $,1 million is CPUC-jurisdictional. Table IV- shows the total company (FERC and CPUCjurisdictional) capital expenditure summary and Table IV- shows the CPUC-jurisdictional capital expenditures only. SCE s System Planning work is managed through four primary categories: 1. Transmission & Interconnection Planning Projects, described in Section A;. Distribution & Subtransmission Planning Programs and Projects, described in Section B;. System Improvement Programs, described in Section C; and 1. Customer-Requested Projects, described in Section D. The System Improvement change is already filed in June 01=, 01=,0 Table IV- 01=, System Planning Capital Expenditure Summary 01=,0 01 (Total Company Nominal $000) 00=, Total=1,1 01=, 01=0, 00=, Total=,, 01=,01 01=, 01=1,0, 01=0,1 00=,0 Total=,1,0 Note that the cost recovery for the DERs will not be collected through the GRC. 0 Refer to WP SCE-0 T&D-Vol., Book A, pp. (Tables IV- and IV-). 1 The following capital expenditures for projects with operating dates prior to 01 are not included in the table above: $1. M in 01, $.M in 01, and $.M in 01. Refer to WP SCE-0 T&D-Vol., Book A, pp. (In-Service Projects with CapEx in this GRC). -0-

5 SCE in 0, the analysis performed in reviewing how DERs impact the distribution system found that clustered DERs will drive more upgrades. 0 1 The study assumed. percent 1 of the allocated DERs were generating during minimum loading for each distribution circuit, versus 0 percent as often considered for impact studies. By comparing the forecast power flow to the rated capacity of the circuit conductors, the study identified approximately 1 circuit-miles of cable and conductor requiring replacement from on SCE s kv, 1 kv, and kv distribution circuits. Of the circuit-miles, 1 circuit-miles will be overhead conductor and 1 circuit-miles will be underground cable. The total estimated cost to replace miles of overhead conductor and underground cable due to DER exceeding loading limits is approximately $. million (nominal dollars) from The forecast expenditures driven by load growth represent our baseline forecast for distribution circuit upgrades for The expenditure was reduced by $. million to account for energy storage pilots planned to meet distribution needs. Last, forecast expenditure for DER driven upgrades are added to the cost for These three aspects were combined to develop the final expenditure for this category. We forecast capital expenditures to increase by approximately $.0 million per year (in constant 01 dollars) from compared to historical 0 01 expenditures; as referenced before, 0 expenditure was omitted from the comparison due to changes in accounting. From SCE expects to slowly increase spending in this category to better utilize existing distribution asset capacity and address needs on the kv system.. New Distribution Circuits, WBS Element CET-ET-LG-CI As part of our DSP Program, SCE identifies new distribution circuits as part of three types of projects: new substation projects, substation capacity increase projects, and projects with unique drivers. Figure IV-1 shows the historical 0 costs for these three categories of new distribution circuits while future expenditure only includes standalone circuit projects. This is due to recent accounting changes to avoid overlap in capital expenditure requests. New distribution circuits are required to provide new capacity outside the substation fence in areas where multiple distribution circuits in the same geographical region are expected to exceed capacity; to serve new residential or 0 The Impact of Localized Energy Resources on SCE s Distribution and Transmission System, SCE, May 0. 1 Refer to WP SCE-0 T&D-Vol., Book A, pp. 1 (DER Driven Circuit Upgrades Methodology). Id. Refer to WP SCE-0 T&D-Vol., pp. (Cost of Overhead Conductor Rebuilds). See SCE-0 T&D-Vol. Distributed Energy Storage Integration (DESI) Pilot Program. --

6 01=, 01=,0 01=, 01=,0 00=, Total=1,1 The System Improvement change is already filed in June Table IV- System Planning Capital Expenditure Summary (CPUC-Jurisdictional Nominal $000) 01=, 01=0,1 00=, Total=,0, 01=, 01=, 01=0,1 A. Transmission & Interconnection Planning Projects 01=, As described in the Transmission & Interconnection Planning Process Section III.A, SCE s 00=1,1 Total=,1, Transmission & Interconnection Planning Projects fall into three categories: 1 1 (1) Grid Reliability Projects needed to support grid reliability; () Transmission System Generation Interconnection Projects needed to interconnect individual generation customers; and () Policy-driven Projects must support state and federal policy to deliver energy to SCE s transmission system. While the majority of work for these transmission projects fall under FERC-jurisdiction, some of these projects include components under CPUC jurisdiction such as upgrades to the underlying subtransmission system or equipment supporting telecommunications, automation, and controls. Both the total project and CPUC-jurisdictional forecast expenditures for these three project categories are shown in Table IV- and Table IV- respectively. The total company cost for all three categories of transmission work is $1,0. million. The CPUC-jurisdictional cost for these projects is $01. million. The tables also include the Generation Interconnection RAS, which has no forecast CPUC-jurisdictional capital expenditures and will not be discussed further in this testimony. Id. See SCE-0, Vol. 1 for SCE s methodology for separating capital expenditures between FERC and CPUC jurisdiction. -1-

7 Table IV- Distribution & Subtransmission Planning Capital Expenditure Summary (Total Company Nominal $000) 01=0, 01=, 00=, Total=, 01=, 01=0, 00=, Total=,, Line No. Program/Project Category Total 1 Distribution Plant Betterment 1,,0 1, 1, 1,0 1,01 Distribution Circuit Upgrades 0,11,, 1,0,1, New Distribution Circuits, 1,,0,01 0,00 1,0 Substation Expansion Projects, 1,,,,, kv Systems, 1,1 1,1 0,0 1,, Subtransmission Lines Plan,10, 1,1,1 1,00, Transmission Substation A-Bank Plan,,,,,, Subtransmission VAR Plan 1,0 1,0 1,0 1,, Various Rights of Way, Total Distribution & Subtransmission,,01,0 1,,,,0 Table IV- Distribution & Subtransmission Planning Capital Expenditure Summary (CPUC-Jurisdictional Nominal $000) Line No. Program/Project Category Total 1 Distribution Plant Betterment 1,,0 1, 1, 1,0 1,01 Distribution Circuit Upgrades 0,11,, 1,0,1, New Distribution Circuits, 1,,0,01 0,00 1,0 Substation Expansion Projects, 1,,,,, kv Systems, 1,1 1,1 0,0 1,, Subtransmission Lines Plan,, 1,1,1 1,00,0 Transmission Substation A-Bank Plan,,0,,,, Subtransmission VAR Plan 1,0 1,0 1,0 1,, Various Rights of Way, Total Distribution & Subtransmission 0,0 0,01, 1,1,,, 01=0, 01=, 00=, Total=, 01=, 01=0,1 1 Consistent with the objective of increasing the utilization of SCE s existing distribution assets, 00=, Total=,0, we have increasingly focused on upgrading distribution circuits instead of building new ones. The overall spend on circuit capacity has declined over the past few years, and we forecast an average of approximately $0 million in 01 constant dollars in as seen in Figure IV- below. Refer to WP SCE-0 T&D-Vol., Book A, pp. (Tables IV- and IV-). Id. --

2018 General Rate Case

2018 General Rate Case Application No.: A.16-09- Exhibit No.: SCE-0, Vol. 08 Witnesses: J. R. Goizueta M. Flores A (U 338-E) 018 General Rate Case Transmission & Distribution (T&D) Volume 8 - Infrastructure Replacement Before

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: J. Billingsley (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume 0 Transmission Construction & Maintenance Before the Public

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: SCE-0, Vol. 0, Part 1 Witnesses: M. Stark K. Trainor (U -E) 01 General Rate Case Transmission And Distribution (T&D) Volume, Part 1 Distribution Maintenance Before the Public

More information

2018 General Rate Case Rebuttal Testimony

2018 General Rate Case Rebuttal Testimony Application No.: A.16-09-001 Exhibit No.: SCE-18, Vol. 08 Witnesses: M. Flores J. Goizueta (U 338-E) 2018 General Rate Case Rebuttal Testimony Transmission & Distribution (T&D) Volume 8 - Infrastructure

More information

Workpapers. Transmission & Distribution Grid Operations SCE-03 Volume General Rate Case APPLICATION. An EDISON INTERNATIONAL Company

Workpapers. Transmission & Distribution Grid Operations SCE-03 Volume General Rate Case APPLICATION. An EDISON INTERNATIONAL Company An EDISON INTERNATIONAL Company (U 338-E) 215 General Rate Case APPLICATION Workpapers Transmission & Distribution Grid Operations SCE-3 Volume 7 N ovem ber 213 1 Workpaper - Southern California Edison

More information

TURN DATA REQUEST TURN-SEU-004 SDG&E 2019 GRC A SDG&E RESPONSE DATE RECEIVED: 5, 2018 DATE RESPONDED: 25, 2018

TURN DATA REQUEST TURN-SEU-004 SDG&E 2019 GRC A SDG&E RESPONSE DATE RECEIVED: 5, 2018 DATE RESPONDED: 25, 2018 The following questions relate to SDG&E-15, electric distribution operations and maintenance costs. Workpapers refer to the relevant workpapers for this chapter ( SDG&E-15-WP WSpeer ). 1. Please provide

More information

First Quarter 2017 Financial Results

First Quarter 2017 Financial Results First Quarter 2017 Financial Results May 1, 2017 Forward-Looking Statements Statements contained in this presentation about future performance, including, without limitation, operating results, capital

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: R. Ramos J. Smolk R. Swartz S. Tran A (U -E) 01 General Rate Case ERRATA Administrative & General (A&G) Volume 0 Legal (Law, Claims, and Workers

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 93 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

Exhibit A Affidavit of Alan Varvis

Exhibit A Affidavit of Alan Varvis Affidavit of Alan Varvis Page 1 of 9 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER16- -000 AFFIDAVIT OF ALAN VARVIS FOR SOUTHERN

More information

EDISON An EDISON INTERNATIONAL Company

EDISON An EDISON INTERNATIONAL Company SOUTHERN CALIFORNIA EDISON An EDISON INTERNATIONAL Company (U 338-E) 2015 General Rate Case APPLICATION Workpapers Transmission & Distribution Customer Driven Programs and Distribution Construction SCE-03

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 9 - Poles

2018 General Rate Case. Transmission & Distribution (T&D) Volume 9 - Poles Application No.: A.1-0- Exhibit No.: SCE-0, Vol. Witnesses: C. Fanous (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume - Poles Before the Public Utilities Commission of the State of

More information

Southern California Edison Company s Supplemental Exhibit in Response to Administrative Law Judge s May 6, Ruling

Southern California Edison Company s Supplemental Exhibit in Response to Administrative Law Judge s May 6, Ruling Application No.: Exhibit No.: Witnesses: A.1-11-00 SCE- Douglas Snow Melvin Stark (U -E) Southern California Edison Company s Supplemental Exhibit in Response to Administrative Law Judge s May, 01 Email

More information

Third Quarter 2017 Financial Results

Third Quarter 2017 Financial Results Third Quarter 2017 Financial Results October 30, 2017 Forward-Looking Statements Statements contained in this presentation about future performance, including, without limitation, operating results, capital

More information

Results of Operations Volume 03 Depreciation Study

Results of Operations Volume 03 Depreciation Study Application No.: A.16-09- Exhibit No.: SCE-09, Vol. 03 A3 Witnesses: P. Joseph A. Varvis R. White (U 338-E) 3rd ERRATA Results of Operations Volume 03 Depreciation Study Before the Public Utilities Commission

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 1 (Appendix) Witnesses: R. Woods (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume 1 Appendix to Operational Overview and Risk-Informed

More information

Business Update Supplement SCE 2015 General Rate Case Decision

Business Update Supplement SCE 2015 General Rate Case Decision Business Update Supplement SCE 2015 General Rate Case Decision November 9, 2015 Forward-Looking Statements Statements contained in this presentation about future performance, including, without limitation,

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. Witnesses: M. Childs D. Gunn P. Hunt D. Lee J. McCarson (U -E) 01 General Rate Case Public Version Before the Public Utilities Commission of the State of

More information

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 I. - Conditions and Definitions A. Contracts Before building an Extension, the Company may require the Applicant to sign a contract.

More information

Cost Estimation for Regional Transmission Overlay Study (RTOS)

Cost Estimation for Regional Transmission Overlay Study (RTOS) Cost Estimation for Regional Transmission Overlay Study (RTOS) Purpose & Key Takeaways Purpose: To provide detail for MISO s cost estimation approach Key Takeaways: Planning-Level and Scoping-Level MISO

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 57965-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 52531-E PRELIMINARY STATEMENT Sheet 1 Safety and Reliability Investment

More information

MISO Planning Process. May 31, 2013

MISO Planning Process. May 31, 2013 MISO Planning Process May 31, 2013 MISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that meets reliability needs, policy needs, and economic needs MISO Board

More information

Prepared Remarks of Edison International CEO and CFO Third Quarter 2018 Earnings Teleconference October 30, 2018, 1:30 p.m. (PDT)

Prepared Remarks of Edison International CEO and CFO Third Quarter 2018 Earnings Teleconference October 30, 2018, 1:30 p.m. (PDT) Prepared Remarks of Edison International CEO and CFO Third Quarter 2018 Earnings Teleconference October 30, 2018, 1:30 p.m. (PDT) Pedro Pizarro, President and Chief Executive Officer, Edison International

More information

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) :

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) : TGST 1-1: Refer to PNM S 2014 FERC Form 1 page 207, line 50, Account 353 Station Equipment, please provide a description of significant projects ($5 million or more) contributing to the increase of approximately

More information

Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan

Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan Supplemental Report on the NCTPC 2006 Collaborative Transmission Plan 04/26/07 Table of Contents I. Executive Summary...3 II. Introduction...4 III. 1,200 MW Resource Supply Option Study Increased Imports

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 25. Interconnection of Generating Units and Facilities... 2 25.1 Applicability... 2 25.1.1 Interconnection Request and Generating Unit Requirements... 2 25.1.2 Affidavit Requirements...

More information

2018 General Rate Case

2018 General Rate Case Application No.: Exhibit No.: Witnesses: A.16-09-001 SCE-59 B. Anderson D. Bernaudo T. Cameron M. Childs D. Gunn T. Guntrip G. Henry C. Jacobs D. Kempf S. Menon D. Tessler (U 338-E) 2018 General Rate Case

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: SCE-0, Vol. 01, Pt. 1 Witnesses: A. Herrera G. Huckaby (U -E) 01 General Rate Case Financial, Legal, and Operational Services (FL&OS) Volume 1, Part 1 Financial Services Department

More information

Second Quarter 2017 Financial Results

Second Quarter 2017 Financial Results Second Quarter 2017 Financial Results July 27, 2017 Forward-Looking Statements Statements contained in this presentation about future performance, including, without limitation, operating results, capital

More information

STATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ ) ) ) ) ) ) ) ) )

STATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ ) ) ) ) ) ) ) ) ) STATE OF NEW JERSEY OFFICE OF ADMINISTRATIVE LAW BEFORE HONORABLE IRENE JONES, ALJ I/M/O the Verified Petition of Rockland Electric Company For Approval of Changes in Electric Rates, Its Tariff For Electric

More information

FAC Transmission Vegetation Management. A. Introduction

FAC Transmission Vegetation Management. A. Introduction A. Introduction 1. Title: Transmission Vegetation Management 2. Number: FAC-003-4 3. Purpose: To maintain a reliable electric transmission system by using a defensein-depth strategy to manage vegetation

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.-0- Exhibit No.: SCE-0, Vol. A Witnesses: M. Bennett G. Henry C. Hernandez J. Trapp R. Worden (U -E) 0 General Rate Case ERRATA Human Resources (HR) Volume Benefits And Other Compensation

More information

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast

Decision D FortisAlberta Inc PBR Capital Tracker True-Up and PBR Capital Tracker Forecast Decision 20497-D01-2016 FortisAlberta Inc. 2014 PBR Capital Tracker True-Up and 2016-2017 PBR Capital Tracker Forecast February 20, 2016 Alberta Utilities Commission Decision 20497-D01-2016 FortisAlberta

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 101 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

Fourth Quarter and Full Year 2017 Financial Results

Fourth Quarter and Full Year 2017 Financial Results Fourth Quarter and Full Year 2017 Financial Results February 22, 2018 Forward-Looking Statements Statements contained in this presentation about future performance, including, without limitation, operating

More information

Excerpt of D On Test Year 2012 General Rate Case For Southern California Edison Company (Pages 1-5, 13-14, , & )

Excerpt of D On Test Year 2012 General Rate Case For Southern California Edison Company (Pages 1-5, 13-14, , & ) Application No.: Exhibit No.: Witnesses: A.13-11-003 SCE-45 T. Godfrey (U 338-E) Excerpt of D.12-11-051 On Test Year 2012 General Rate Case For Southern California Edison Company (Pages 1-5, 13-14, 209-211,

More information

SDG&E 2019 GRC A TURN Data Request TURN-SEU-077 SDG&E RESPONSE DATE RECEIVED: June 29, 2018 DATE RESPONDED: July 11, 2018

SDG&E 2019 GRC A TURN Data Request TURN-SEU-077 SDG&E RESPONSE DATE RECEIVED: June 29, 2018 DATE RESPONDED: July 11, 2018 TURN Question 1: 1. In the rebuttal testimony in SDG&E-214, p. AFC-59, lines 25-26, SDG&E states it utilized some initial assumptions from SCE s 2012 pole loading study to create initial baselines for

More information

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018

Decision D FortisAlberta Inc Performance-Based Regulation Capital Tracker True-Up. January 11, 2018 Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based Regulation Capital Tracker True-Up January 11, 2018 Alberta Utilities Commission Decision 22741-D01-2018 FortisAlberta Inc. 2016 Performance-Based

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. Witnesses: S. Kempsey (U -E) 01 General Rate Case PUBLIC VERSION Administrative & General (A&G) Volume - Property & Liability Insurance Before the Public

More information

Exhibit B SCE General Rate Case Decision CPUC D (Relevant Portions)

Exhibit B SCE General Rate Case Decision CPUC D (Relevant Portions) Exhibit B SCE General Rate Case Decision CPUC D.15-11-021 (Relevant Portions) statistics justify ASLs up to 69 years. Finally, TURN suggests that aluminum conductor can last far longer than the ASLs considered

More information

ORA DATA REQUEST ORA-SDG&E-DR-007-CL8 SDG&E 2019 GRC A SDG&E RESPONSE DATE RECEIVED: OCTOBER 26, 2017 DATE RESPONDED: NOVEMBER 8, 2017

ORA DATA REQUEST ORA-SDG&E-DR-007-CL8 SDG&E 2019 GRC A SDG&E RESPONSE DATE RECEIVED: OCTOBER 26, 2017 DATE RESPONDED: NOVEMBER 8, 2017 Exhibit Reference: SDG&E-36 and SDG&E-36-WP-C SDG&E Witness: Steven P. Dais Subject: Working Cash Please provide the following: 1. Referring to page SPD-12, lines 11-14: a. Please explain whether or not

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 92 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS 1. Purpose This rule establishes procedures and defines respective cost responsibilities to provide a Line Extension to a builder, developer,

More information

Pacific Gas and Electric Company. Statement of Estimated Cash Flows April 20, 2001

Pacific Gas and Electric Company. Statement of Estimated Cash Flows April 20, 2001 Pacific Gas and Electric Company Statement of Estimated Cash Flows April 20, 2001 This document provides the latest forecast of cash flows for Pacific Gas and Electric Company (the Company ). The purpose

More information

Residential Line and Service Extension Allowance Testimony. Application No.: Witnesses: C. Silsbee S. Reed J. Schichtl L. Vellanoweth (U 338-E)

Residential Line and Service Extension Allowance Testimony. Application No.: Witnesses: C. Silsbee S. Reed J. Schichtl L. Vellanoweth (U 338-E) Application No.: Exhibit No.: Witnesses: SCE-1 C. Silsbee S. Reed J. Schichtl L. Vellanoweth (U -E) Residential Line and Service Extension Allowance Testimony Before the Public Utilities Commission of

More information

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 Attachment GG Projected Proportion Actual True Up Revenue of Revenues Revenue Interest allocated

More information

MainPower New Zealand Limited. Asset Management Plan

MainPower New Zealand Limited. Asset Management Plan MainPower New Zealand Limited. Asset Management Plan 2015 2025 MAINPOWER NEW ZEALAND LIMITED ASSET MANAGEMENT PLAN UPDATE 2015-2025 MainPower New Zealand Limited Asset Management Plan Update 2015-2025

More information

Benefits Determination and Cost Allocation

Benefits Determination and Cost Allocation Benefits Determination and Cost Allocation Johannes Pfeifenberger Transmission Executive Forum West 2012 Meeting Public Policy Objectives through Transmission Investment San Diego, CA October 22, 2012

More information

DIRECT TESTIMONY OF PAUL E. HAERING (CAPITAL PLAN)

DIRECT TESTIMONY OF PAUL E. HAERING (CAPITAL PLAN) BEFORE THE NEW YORK STATE PUBLIC SERVICE COMMISSION ----------------------------------------------------------------------------x Proceeding on Motion of the Commission as to the Rates, Charges, Rules

More information

APPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF

APPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF APPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF Appendix X sets forth the formula for calculating the Citizens Border

More information

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION

ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: Southern California Edison Utility Number/Type: U 338-E AL Number(s):3620-E/3620-E-A/3620-E-B Date AL(s) Filed: 6/16/17, 7/28/17, 9/11/17

More information

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION PECO ENERGY COMPANY STATEMENT NO. BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION DOCKET NO. R-01-0001 DIRECT TESTIMONY

More information

Testimony of Southern California Edison Company in Support of Its 2018 Energy Storage Procurement and Investment Plan

Testimony of Southern California Edison Company in Support of Its 2018 Energy Storage Procurement and Investment Plan Application No.: Exhibit No.: Witnesses: A.18-03- SCE-01 G. Chinn M. Dresti J. Edwards G. Flores L. Gaillac M. Irwin B. Landry J. Lim M. Sheriff B. Tolentino (U 338-E) Testimony of Southern California

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Jenner Wind Energy Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act,

More information

Fourth Quarter and Full Year 2018 Financial Results. February 28, 2019

Fourth Quarter and Full Year 2018 Financial Results. February 28, 2019 Fourth Quarter and Full Year 2018 Financial Results Forward-Looking Statements Statements contained in this presentation about future performance, including, without limitation, operating results, capital

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (U338-E) PUBLIC VERSION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (U338-E) PUBLIC VERSION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application Of Southern California Edison Company (U 338E) For Authority To Increase Its Authorized Revenues For Electric Service In 2018,

More information

2018 General Rate Case Rebuttal Testimony

2018 General Rate Case Rebuttal Testimony Application No.: A.1-09-001 Exhibit No.: -, Vol. 01 A Witnesses: D. Daigler D. McMullen T. Guntrip D. Neal P. Jeske S. Schuffels K. Landrith (U 8-E) 018 General Rate Case Rebuttal Testimony ERRATA Operational

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016

AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 10 Krey Boulevard Rensselaer, NY 12144 AC TRANSMISSION PUBLIC POLICY TRANSMISSION NEEDS PROJECT SOLICITATION Response due April 29, 2016 Dear NYISO Stakeholder or Interested Party: February 29, 2016 With

More information

SUMMARY OF CAPITAL EXPENDITURES

SUMMARY OF CAPITAL EXPENDITURES Filed: May, 00 EB-00-000 Exhibit D Tab Schedule Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL BUDGET The proposed capital expenditures result from a rigorous business planning and work prioritization

More information

REBUTTAL TESTIMONY OF NEIL MILLAR ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

REBUTTAL TESTIMONY OF NEIL MILLAR ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Application No.: --00 Exhibit No.: Witness: Neil Millar In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (UE) for a Certificate of Public Convenience and Necessity for the West of

More information

Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP)

Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP) Application Nos.: Exhibit No.: Witnesses James A. Cuillier Gary L. Allen (U -E) Southern California Edison Company s Testimony on Tehachapi Renewable Transmission Project (TRTP) Cost Recovery And Renewable

More information

2018 General Rate Case Rebuttal Testimony

2018 General Rate Case Rebuttal Testimony Application No.: A.16-09-001 Exhibit No.: SCE-23, Vol. 01 Witnesses: D. Daigler D. McMullen T. Guntrip D. Neal P. Jeske S. Schuffels K. Landrith (U 338-E) 2018 General Rate Case Rebuttal Testimony Operational

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: A.13-11-003 SCE-73 T. Cameron R. Fisher G. Henry C. Hu M. Marelli D. Snow P. Wong (U 338-E) 2015 General Rate Case PUBLIC VERSION Update Testimony Before the Public

More information

WISCONSIN PUBLIC SERVICE CORPORATION. C4. Standard Rules & Regulations Construction Policy RIIIM

WISCONSIN PUBLIC SERVICE CORPORATION. C4. Standard Rules & Regulations Construction Policy RIIIM Original Sheet No. C-48.01 EFFECTIVE IN All territory served. 1. DEFINITIONS a. Extension An extension is defined to include right-of-way, permits, easements, poles, conductors and appurtenances used in

More information

Nelson Electricity Ltd Asset Management Plan Update

Nelson Electricity Ltd Asset Management Plan Update Nelson Electricity Ltd Asset Management Plan Update April 2017 March 2027 April 2017 Nelson Electricity Ltd central Nelson city view In accordance with the Commerce Act Electricity Distribution Information

More information

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DE

STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION. Docket No. DE STATE OF NEW HAMPSHIRE BEFORE THE PUBLIC UTILITIES COMMISSION Liberty Utilities (Granite State Electric) Corp. d/b/a Liberty Utilities Distribution Service Rate Case DIRECT TESTIMONY OF CHRISTIAN P. BROUILLARD

More information

The second effective date allows entities time to comply with Requirements R1, R2, R4, R5, R6, and R7.

The second effective date allows entities time to comply with Requirements R1, R2, R4, R5, R6, and R7. Effective Dates Generator Owners There are two effective dates associated with this standard. The first effective date allows Generator Owners time to develop documented maintenance strategies or procedures

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

Testimony of Southern California Edison Company in Support of Its 2014 Energy Storage Procurement Plan

Testimony of Southern California Edison Company in Support of Its 2014 Energy Storage Procurement Plan Application No.: Exhibit No.: Witnesses: A.14-02-XXX SCE-01 M. Nelson M. Irwin M. Wallenrod J. Bryson R. Singh D. Snow (U 338-E) Testimony of Southern California Edison Company in Support of Its 2014 Energy

More information

Information Disclosure Reports prepared according to Part 4 of the Commerce Act 1986

Information Disclosure Reports prepared according to Part 4 of the Commerce Act 1986 Information Disclosure Reports prepared according to Part 4 of the Commerce Act 1986 For the Year Ended CONTENTS INTRODUCTION REPORTS DESCRIPTION 1 ANALYTICAL RATIOS 2 REPORT ON RETURN ON INVESTMENT 3

More information

Submitted by Western Power

Submitted by Western Power Final Determination on the New Facilities Investment Test for a 66/11 kv Medical Centre Zone Substation Expansion and Voltage Conversion of the Distribution Network Submitted by Western Power 19 February

More information

Southern California Edison Company s Tehachapi Renewable Transmission Project (TRTP) -- Application Appendices. Application Nos.: Exhibit No.

Southern California Edison Company s Tehachapi Renewable Transmission Project (TRTP) -- Application Appendices. Application Nos.: Exhibit No. Application Nos.: Exhibit No.: Witnesses: Various (U 338-E) Southern California Edison Company s Tehachapi Renewable Transmission Project (TRTP) -- Application Appendices Before the Public Utilities Commission

More information

Supplemental Information

Supplemental Information Application No: Exhibit No: Witnesses: A.1-0-01 SCE- P. T. Hunt D. Snow (U -E) Supplemental Information Before the Public Utilities Commission of the State of California Rosemead, California June, 01 01

More information

FAC Facility Interconnection Studies

FAC Facility Interconnection Studies A. Introduction 1. Title: Facility Interconnection Studies 2. Number: FAC-002-2 3. Purpose: To study the impact of interconnecting new or materially modified Facilities on the Bulk Electric System. 4.

More information

SAFETY MODEL ASSESSMENT

SAFETY MODEL ASSESSMENT Application No.: Exhibit No.: Witnesses: A.1-0- SCE-01 M. Marelli S. Menon N. Woodward (U -E) SAFETY MODEL ASSESSMENT Before the Public Utilities Commission of the State of California Rosemead, California

More information

COST-OF-SERVICE ALLOCATION METHOD

COST-OF-SERVICE ALLOCATION METHOD COST-OF-SERVICE ALLOCATION METHOD Page 1 of 1 Page of 1 TABLE OF CONTENTS 1. CONTEXT.... ALLOCATION METHOD....1 Allocation by Function.... Allocation by Component.... Allocation by Service... Page of 1

More information

Appendix 1 Duquesne Light Company Attachment H -17A Page 1 of 25 Formula Rate - Appendix A True-Up Notes FERC Form 1 Page # or Instruction 2017 Shaded cells are input cells Allocators 1 Transmission Wages

More information

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019)

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

Electricity Distribution (Information Disclosure) Requirements October 2008

Electricity Distribution (Information Disclosure) Requirements October 2008 Electricity Distribution (Information Disclosure) Requirements 2008 31 October 2008 ELECTRICITY DISTRIBUTION (INFORMATION DISCLOSURE) REQUIREMENTS 2008 1. Title, commencement, and application Contents

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) James A. Cuillier Director FERC Rates & Regulation Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate Annual

More information

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER II SUMMARY OF AMI BUSINESS CASE

SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER II SUMMARY OF AMI BUSINESS CASE Application No.: A.0-0-0 Exhibit No.: SCG Date: March, 00 Witness: Edward Fong SOUTHERN CALIFORNIA GAS COMPANY ADVANCED METERING INFRASTRUCTURE CHAPTER II SUMMARY OF AMI BUSINESS CASE Errata to Prepared

More information

Reinventing. an Enduring Franchise. Paul Steece Vice President and General Manager Electrical Markets Division. September 9, 2008

Reinventing. an Enduring Franchise. Paul Steece Vice President and General Manager Electrical Markets Division. September 9, 2008 Paul Steece Vice President and General Manager Electrical Markets Division Reinventing an Enduring Franchise September 9, 2008 1 Electrical Markets Division The Re-invention of One of 3M s Enduring Franchises

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for 138 kv and 240 kv Transmission System Development in the Red Deer Region And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1,

More information

REISSUED JUNE 1, 1988

REISSUED JUNE 1, 1988 REVISED SHEET NO. 29 Effective: October 28, 1966 RULE NO. 14 REISSUED JUNE 1, 1988 Service Connections and Facilities on Customer's Premises A. METER INSTALLATIONS AND MISCELLANEOUS SERVICE EQUIPMENT ON

More information

Electricity Distribution Information Disclosure Determination 2012 (consolidated in 2015)

Electricity Distribution Information Disclosure Determination 2012 (consolidated in 2015) ISBN 978-1-869454-39-5 Project no. 14.09:15.01/14700:14699 Public version Electricity Distribution Information Disclosure Determination 2012 (consolidated in 2015) Date of consolidation: 24 March 2015

More information

ENERGY DIVISION DATA REQUEST REGARDING COST OF OWNERSHIP CALCULATIONS R RULE 21 WORKING GROUP 3 SDG&E RESPONSE

ENERGY DIVISION DATA REQUEST REGARDING COST OF OWNERSHIP CALCULATIONS R RULE 21 WORKING GROUP 3 SDG&E RESPONSE QUESTION 1: What are your existing policies and cost accounting practices related to COO? Please be specific and detailed. For example, when replaced items get zeroed out in GRC, is depreciation included

More information

EEI Survey of Transmission Investment. Historical and Planned Capital Expenditures ( )

EEI Survey of Transmission Investment. Historical and Planned Capital Expenditures ( ) EEI Survey of Transmission Investment Historical and Planned Capital Expenditures (1999-2008) Published by: Edison Electric Institute May 2005 2005 by the Edison Electric Institute (EEI). All rights reserved.

More information

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD IN RE: MIDAMERICAN ENERGY IN RE: DOCKET NOS. E-22269, E-22270, AND E-22271 DOCKET NO. E-22279 (consolidated) ITC MIDWEST LLC BRIEF BY THE MIDCONTINENT

More information

TAC FIX IMPACT MODEL DETAILED OVERVIEW

TAC FIX IMPACT MODEL DETAILED OVERVIEW TAC FIX IMPACT MODEL DETAILED OVERVIEW Contents Goal of Spreadsheet... 2 Drivers of transmission investment... 2 Note About Terminology... 3 Core Assumptions... 3 Load served locally for an example IOU,

More information

Revised Cal. P.U.C. Sheet No E Cancelling Original Cal. P.U.C. Sheet No E. ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS

Revised Cal. P.U.C. Sheet No E Cancelling Original Cal. P.U.C. Sheet No E. ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS Revised Cal. P.U.C. Sheet No. 20093-E Cancelling Original Cal. P.U.C. Sheet No. 15575-E ELECTRIC RULE NO. 15 Sheet 1 APPLICABILITY: This rule is applicable to extension of electric Distribution Lines*

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: SCE-0, Vol. Witnesses: E. Jennerson R. Ramos J. Smolk R. Swartz (U -E) 01 General Rate Case Financial, Legal, and Operational Services (FL&OS) Volume - Legal (Law, Claims,

More information

SDG&E DIRECT TESTIMONY OF JOHN D. JENKINS ELECTRIC DISTRIBUTION CAPITAL. November 2014

SDG&E DIRECT TESTIMONY OF JOHN D. JENKINS ELECTRIC DISTRIBUTION CAPITAL. November 2014 Company: San Diego Gas & Electric Company (U 0 M) Proceeding: 01 General Rate Case Application: A.1-- Exhibit: SDG&E-0 SDG&E DIRECT TESTIMONY OF JOHN D. JENKINS ELECTRIC DISTRIBUTION CAPITAL November 01

More information

July 30, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

July 30, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Regulation James A. Cuillier Director FERC Rates & Regulation July 30, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose:

More information

EDB Information Disclosure Requirements Information Templates for Schedules 1 10

EDB Information Disclosure Requirements Information Templates for Schedules 1 10 EDB Information Disclosure Requirements Information Templates for Schedules 1 10 Disclosure Date 31 August 2016 Disclosure Year (year ended) Templates for Schedules 1 10 excluding 5f 5g Template Version

More information

2018 General Rate Case

2018 General Rate Case Application No.: Exhibit No.: Witnesses: A.16-09-001 SCE-60 M. Childs J. McCarson S. Menon D. Tessler (U 338-E) 2018 General Rate Case Tax Update Before the Public Utilities Commission of the State of

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59898-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57292-E Sheet 1 GENERATING FACILITY INTERCONNECTION AGREEMENT (3 RD PARTY

More information

Steps/Process. <COOPERATIVE NAME> 10 kw INVERTER PROCESS Page 1

Steps/Process. <COOPERATIVE NAME> 10 kw INVERTER PROCESS Page 1 10 kw INVERTER PROCESS Page 1 Application, Procedures, and Terms and Conditions for Interconnecting a Certified Inverter-Based Generation Facility No Larger than 10 kw ("10 kw Inverter Process") Steps/Process

More information

General Discussion of System-wide DER Forecasting Assumptions. April 17, 2017

General Discussion of System-wide DER Forecasting Assumptions. April 17, 2017 General Discussion of System-wide DER Forecasting Assumptions April 17, 2017 Presentation Purpose/Overview Purpose: Explain how the IOUs arrived at the proposed framework and highlight the trade-offs between

More information