Size: px
Start display at page:

Download ""

Transcription

1

2

3

4

5

6

7

8 Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 92 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN AV SOLAR RANCH 1, LLC AND SOUTHERN CALIFORNIA EDISON COMPANY AV SOLAR RANCH ONE PROJECT Contract Effective Date: Tariff Record Proposed Effective Date: Version Number: TOT345 Option Code: A

9 November 19, 2010 AV Solar Ranch 1, LLC 353 Sacramento Street, Suite 2100 San Francisco, CA Attn: Frank De Rosa Re: Engineering, Design and Procurement Letter Agreement for the AV Solar Ranch One Project Dear Mr. De Rosa: AV Solar Ranch 1, LLC ( AV Solar ) proposes to construct a 250 MW solar photovoltaic generation facility to be located in Kern County, California (the AV Solar Ranch One Project ), and interconnect the AV Solar Ranch One Project to Southern California Edison Company s ( SCE ) new Whirlwind Substation via a generation tie-line for the purpose of delivering Energy and/or Ancillary Services to the California Independent System Operator ( CAISO ) Controlled Grid. A Phase II Interconnection Study report containing the scope of work, estimated cost and estimated completion schedule for the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades was completed for the AV Solar Ranch One Project, and tendered to AV Solar by the CAISO, on July 8, All capitalized terms used herein, and not otherwise defined, shall have the meaning ascribed to that term in the CAISO Tariff. AV Solar and SCE are hereinafter sometimes referred to individually as Party and collectively as Parties. SCE and AV Solar intend to execute a Large Generator Interconnection Agreement ( LGIA ) to provide for the interconnection of the AV Solar Ranch One Project. SCE has begun construction of the Whirlwind Substation, a new 500/220 kv substation which includes a 220kV switchyard with positions 1 though 4. The Parties agree that construction of this portion of the Whirlwind Substation must be coordinated with the work done pursuant to this Agreement on the Whirlwind Substation Expansion (consisting of 220 kv positions 5 though 17, one of which will be used to interconnect the AV Solar Ranch One Project), since positions 1 through 4 must be in service to allow for positions 5 though 17 to be placed in service. AV Solar originally requested an In-Service Date of January 1, 2011, but due to delays in the construction of SCE s Whirlwind Substation, AV Solar has deferred the targeted In-Service Date to March 1, SCE currently estimates that Whirlwind Substation will be in service by Page - 1 -

10 May 3, 2012, and that the Whirlwind Substation Expansion will be completed soon thereafter. Thus, AV Solar has requested that SCE complete the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades necessary to support AV Solar s requested In-Service Date of May 3, SCE estimates that the in-service date of the Participating TO s Interconnection Facilities and Reliability Network Upgrades necessary for Interconnection Customer to interconnect to the Whirlwind Substation is within twenty-one months after execution by all parties of the LGIA. In the interest of timely completion of the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades, the Parties enter into this letter agreement ("Agreement") to agree upon an interim arrangement pursuant to which SCE will, as soon as practicable, perform the engineering and design of, and procurement of material and equipment for, the Participating TO s Interconnection Facilities and the Participating TO s Reliability Network Upgrades specified in Exhibit A, as follows: 1. SCE will perform the engineering and design of, and procurement of material and equipment for, the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades as specified in Exhibit A hereto. 2. AV Solar shall pay all of SCE s actual charges and expenses for the engineering and design of, and procurement of material and equipment for, the Participating TO s Interconnection Facilities and the Participating TO s Reliability Network Upgrades specified in Exhibit A. The charges and expenses incurred pursuant to this Agreement shall include, without limitation, SCE s costs of SCE employees and contractors, including all related overheads. Such charges and expenses are estimated to be $6,372,600, as identified in Exhibit B hereto. SCE estimates the income tax liability associated with such charges and expenses to be $480,410, as shown in Exhibit B. 3. Payments a. Upon execution of this Agreement, AV Solar shall initially pay to SCE a deposit of $2,842,600 ( Initial Deposit ) for SCE to commence work under the terms of this Agreement. AV Solar shall make additional payments to continue the work, in accordance with the schedule set forth in Exhibit C of this Agreement. The payments are to be paid quarterly in advance for charges and expenses SCE believes it will incur during the following quarter. The Initial Deposit and payments shall be applied exclusively toward SCE s charges and expenses incurred under this Agreement. Additionally, AV Solar shall post security to secure for any potential tax liability (the Tax Security Instrument ) in a form acceptable to SCE, in accordance with Section 9 herein and the schedule attached as Exhibit C hereto. Unless otherwise agreed in writing, this Tax Security Instrument shall be a letter of credit which AV Solar shall amend to increase the amount posted in accordance with the schedule attached as Page - 2 -

11 Exhibit C hereto. b. In accordance with the requirements of the CAISO Large Generator Interconnection Procedures ( LGIP ), AV Solar is required to maintain Interconnection Financial Security pursuant to LGIP Section 9.4. The Parties agree that the Initial Deposit and the additional payments made under this Agreement will be considered an acceptable form of security towards satisfying AV Solar s Interconnection Financial Security requirements under the LGIP. Therefore, upon receipt of the Initial Deposit and as any additional payments are made, SCE agrees to reduce any existing letter of credit posted by AV Solar as Interconnection Financial Security by an amount equal to the payments made under this Agreement. The amounts from each of the Initial Deposit and the additional payments to be applied as the Interconnection Financial Security for Participating TO s Interconnection Facilities and for Network Upgrades are shown in Exhibit C. The Parties also agree that, pursuant to LGIP Sections and , any amounts posted as Interconnection Financial Security for Network Upgrades or Participating TO s Interconnection Facilities is an acceptable form of collateral for securing AV Solar s obligations under this Agreement. c. If AV Solar does not make any of the payments or provide a Tax Security Instrument in the required amount by the due dates specified in Exhibit C of this Agreement, SCE shall tender a cure notice to AV Solar of such non-payment or failure to provide a Tax Security Instrument in the proper amount and a final deadline for making such payment or providing a Tax Security Instrument in the proper amount, which shall be fifteen (15) Business Days from the receipt of the notice. Subject to the foregoing sentence, if AV Solar does not pay the amounts and provide the Tax Security Instrument in the proper amount by the due dates specified in this Agreement, SCE may immediately draw upon any letter of credit posted as Interconnection Financial Security any amounts due, but not yet paid under this Agreement. If the amounts of the existing letters of credit are insufficient, upon written notice by SCE to AV Solar, SCE may stop work and terminate this Agreement, subject to acceptance or approval by FERC. d. SCE shall notify AV Solar in writing within a reasonable time if SCE learns that charges and expenses are likely to exceed the total estimated cost set forth in Exhibit B, which notification shall provide updated cost estimates in the form of Exhibit B and a new payment schedule in the form of Exhibit C. In such notification, SCE shall specify any additional payment amounts required to be paid by AV Solar and the amount by which the payments and Tax Security Instrument postings shall be increased for SCE to continue work under the terms of this Agreement. Upon agreement by both Parties, AV Solar shall pay any additional payment amounts and amend the Tax Security Instrument to conform with the revised Exhibit B and revised Exhibit C, subject to acceptance or approval by FERC. Page - 3 -

12 If AV Solar does not pay any additional payment amounts within thirty (30) calendar days of receipt of notification, AV Solar agrees that SCE will be entitled to immediately draw upon Interconnection Financial Security to the extent that SCE s estimated costs for the following ninety (90) calendar days exceed AV Solar s payments for the following ninety (90) calendar days. If the amount of the Interconnection Financial Security is insufficient, upon written notice by SCE to AV Solar, SCE may stop work once the Interconnection Financial Security has been exhausted and terminate this Agreement, subject to acceptance or approval by FERC. 4. SCE shall use commercially reasonable efforts to complete the engineering and design of, and procurement of materials and equipment for, the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades in accordance with Good Utility Practice within nine (9) months of the Effective Date (as defined in Section 21 of this Agreement) and on a schedule which is intended to allow for completion of construction of the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades by the time Whirlwind Substation commences operation; however, SCE does not warrant that such work will be completed within such time. AV Solar understands and acknowledges that such date is only an estimate and that various events could delay the actual completion of the engineering and design of, and procurement of materials and equipment for, the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades. SCE shall not be liable for any cost or damage incurred by AV Solar because of any delay in the work provided for in this Agreement. On or before the last day of each month, SCE shall provide an update to AV Solar on the status and estimated completion date of its work under this Agreement. 5. SCE and AV Solar intend to enter into an LGIA that will state the terms for payment of SCE's costs incurred for performing the work included in this Agreement. AV Solar s Initial Deposit and additional payments under the terms of this Agreement shall be credited to amounts due under the LGIA. AV Solar and SCE understand that the AV Solar Ranch One Project is a Transition Cluster project subject to the Large Generator Interconnection Procedures for Clusters, Appendix Y of the CAISO Tariff; and as such, the costs of certain Participating TO s Reliability Network Upgrades have been allocated in the Phase II Interconnection Study to both AV Solar and other members of the Transition Cluster in accordance with the requirements of the LGIP. AV Solar and SCE further understand that Exhibit A sets forth Participating TO s Reliability Network Upgrades identified in the Phase II Interconnection Study which AV Solar will fund pursuant to this Letter Agreement. Exhibit B shows AV Solar s allocated share of the costs of these Participating TO s Reliability Network Upgrades. Exhibit B also sets forth additional costs that AV Solar will fund pursuant to this Letter Agreement for facilities in addition to AV Solar s allocated share of these Participating TO s Reliability Network Upgrades ( Additional Facilities ), such as for shares of the Participating TO s Reliability Network Upgrades allocated to other members of the Transition Cluster and for other Participating TO s Page - 4 -

13 Reliability Network Upgrades that have been assigned to members of the Serial Group, which preceded the Transition Cluster. If SCE enters into an agreement with a third party under which the third party is to pay for some or all of the Additional Facilities, then SCE shall credit AV Solar for any payments AV Solar has made for the Additional Facilities under this Agreement as SCE is paid for the Additional Facilities by the third party. In any event, AV Solar shall pay no more than $5,000,000 for the cost of the Participating TO s Reliability Network Upgrades under this Agreement. SCE shall apply credit for payments made under this Agreement toward the amount AV Solar is required to finance by LGIP Section (b) as set forth in the Phase II Interconnection Study, provided, however, that the amount of the credit will be reduced by the amount of any reimbursement provided to AV Solar for payments made under this Agreement. Upon termination of this Agreement, if the payments made under this Agreement for Participating TO s Reliability Network Upgrades plus the security posted by AV Solar for Network Upgrades exceed AV Solar s Interconnection Financial Security obligations for Network Upgrades, SCE shall reimburse the amount in excess within thirty (30) calendar days after termination of this Agreement. 6. Subject to Section 7 below, this Agreement shall terminate upon the earliest of the following to occur: (i) notice that this Agreement is not accepted for filing by FERC; (ii) acceptance by FERC of the LGIA as filed or, if FERC conditions acceptance upon making a compliance filing, upon acceptance by FERC of the compliance filing; (iii) written notice of termination from AV Solar to SCE at any time; or (iv) written notice of termination by SCE and acceptance of said notice by FERC, pursuant to Section 3 of this Agreement. In the event that AV Solar terminates this Agreement pursuant to this Section 6; such termination will become effective two (2) business days after SCE s receipt of AV Solar s notice of termination. 7. AV Solar s obligations to pay charges and expenses incurred or irrevocably committed to be incurred pursuant to this Agreement as of the termination date of this Agreement and SCE s obligations to provide credit or reimbursement shall survive termination of this Agreement, except insofar as payment of such charges and expenses is provided for in an LGIA that is accepted for filing by FERC and becomes effective. In the event of termination of this Agreement in the absence of an effective LGIA between the Parties, SCE shall submit an invoice to AV Solar for all incurred and irrevocably committed to be incurred unpaid charges and expenses as soon as reasonably practicable but within twelve (12) months from the date of termination of this Agreement. AV Solar shall have the same audit rights as would be afforded under Article 25 of the pro forma LGIA (currently Appendix Z of the CAISO Tariff) ( Pro Forma LGIA ). a. In the event that AV Solar s Initial Deposit and payments in accordance with Section 3 of this Agreement exceed the amount of SCE s charges and expenses incurred or irrevocably committed to be incurred pursuant to this Agreement, SCE shall return the excess amount to AV Solar, without interest, within thirty (30) calendar days after Page - 5 -

14 the date of the invoice provided in accordance with this Section 7 hereof, without offset for any amount which may be in dispute. In the event of any such dispute, the Parties shall promptly meet and attempt in good faith to resolve the dispute. In the event the Parties determine that AV Solar did not owe SCE the full amount paid, then SCE shall refund to AV Solar, without interest, the amount overpaid by AV Solar within thirty (30) calendar days of such determination. b. In the event that AV Solar s Initial Deposit and payments in accordance with Section 3 of this Agreement are less than the amount of SCE s charges and expenses incurred or irrevocably committed to be incurred pursuant to this Agreement, then AV Solar shall pay the difference, without interest, as reflected in the invoice, within thirty (30) calendar days of receipt of the invoice provided in accordance with this Section 7 hereof, without offset for any amount which may be in dispute. In the event of any such dispute, the Parties shall promptly meet and attempt in good faith to resolve the dispute. In the event the Parties determine that AV Solar did not owe SCE the full amount paid, then SCE shall refund to AV Solar, without interest, the amount overpaid by AV Solar within thirty (30) calendar days of such determination. c. With respect to the Participating TO s Interconnection Facilities, upon termination of this Agreement, SCE shall to the extent possible and with AV Solar's authorization cancel any pending orders of, or return, any materials or equipment for such facilities; provided that in the event AV Solar elects not to authorize such cancellation, AV Solar shall assume all payment obligations with respect to such material and equipment and SCE shall deliver such materials and equipment to AV Solar as soon as practicable, at AV Solar s expense. To the extent that AV Solar has already paid SCE for any or all such costs of materials or equipment not taken by AV Solar, SCE shall promptly refund such amounts to AV Solar, less any costs, including penalties, incurred by SCE to cancel any pending orders of or return such materials and equipment. SCE may, at its option, retain any portion of such materials, equipment or facilities that AV Solar chooses not to accept delivery of, in which case SCE shall be responsible for all costs associated with procuring such materials, equipment or facilities. d. In the event that AV Solar and SCE enter into an LGIA subsequent to the termination of this Agreement, then any applicable work product generated by SCE and any associated payments made by AV Solar pursuant to this Agreement not already credited or refunded shall be reflected in the scope of, and the amount due under, such LGIA. 8. For the purposes of this Agreement, Force Majeure shall mean any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other cause beyond a Party s control. A Force Majeure event does not include acts of negligence or intentional wrongdoing by the Party claiming Force Majeure. Economic hardship is not considered a Force Majeure event. Page - 6 -

15 9. The Parties intend that the Initial Deposit and payments made by AV Solar to SCE under this Agreement for the Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades shall be non-taxable, either as contributions to capital or as a refundable advance, in accordance with the Internal Revenue Code and any applicable state income tax laws, and shall not be taxable as contributions in aid of construction or otherwise under the Internal Revenue Code and any applicable state income tax laws. AV Solar shall provide a Tax Security Instrument for payment of possible tax obligations in the manner provided for in Paragraph 2 and Section of the Pro Forma LGIA. The obligation to post a Tax Security Instrument pursuant to this Agreement may be superseded by provisions of the LGIA. 10. No Party shall be considered to be in Default with respect to any obligation hereunder, other than the obligation to pay money when due, if prevented from fulfilling such obligation by Force Majeure. For the purposes of this Agreement, Default shall mean the failure of a breaching Party to cure its breach. A Party unable to fulfill any obligation hereunder (other than an obligation to pay money when due) by reason of Force Majeure shall give notice and the full particulars of such Force Majeure to the other Party in writing or by telephone as soon as reasonably possible after the occurrence of the cause relied upon. Telephone notices given pursuant to this Section shall be confirmed in writing as soon as reasonably possible and shall specifically state full particulars of the Force Majeure, the time and date when the Force Majeure occurred and when the Force Majeure is reasonably expected to cease. The Party affected shall exercise due diligence to remove such disability with reasonable dispatch, but shall not be required to accede or agree to any provision not satisfactory to it in order to settle and terminate a strike or other labor disturbance. 11. Each Party shall at all times indemnify, defend and hold the other Party harmless, from any and all Losses arising out of or resulting from the other Party s action or inactions of its obligations under this Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party. For the purposes of this Agreement, Losses shall mean any and all damages, losses, and claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties. 12. In no event shall any Party be liable under any provision of this Agreement for any losses, damages, costs or expenses for any special, indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided, however, that damages for which a Party may be liable to another Party under another agreement will not be considered to be special, indirect, Page - 7 -

16 incidental, or consequential damages hereunder. 13. This Agreement constitutes the complete and final expression of the agreement between the Parties and is intended as a complete and exclusive statement of the terms of their agreement which supersedes all prior and contemporaneous offers, promises, representations, negotiations, discussions, communications, and other agreements which may have been made in connection with the subject matter of this Agreement. Nothing in this Agreement is intended or shall be deemed to require SCE or AV Solar to enter into any other agreement, including without limitation, any interconnection agreement. 14. Any waiver at any time by either Party of its rights with respect to a default under this Agreement, or with respect to any other matter arising from this Agreement, shall not be deemed a waiver with respect to any subsequent default or other matter arising in connection therewith. Any delay, with the exception of the statutory period of limitation in assessing or enforcing any right, shall not be deemed a waiver of such right. 15. The covenants, obligations, and liabilities of the Parties are intended to be several and not joint or collective, and nothing contained in this Agreement shall ever be construed to create an association, joint venture, trust or partnership, or to impose a trust or partnership covenant, obligation, or liability on or with regard to either Party. Each Party shall be individually responsible for its own covenants, obligations, and liabilities as provided in this Agreement. Neither Party shall be under the control of the other Party. Neither Party shall be the agent of or have a right or power to bind the other Party without such other Party s express written consent. 16. The Parties do not intend to create rights in, or to grant remedies to, any third party as a beneficiary either of this Agreement or of any duty, covenant, obligation, or undertaking established herein. 17. This Agreement shall be interpreted by and in accordance with the laws of the State of California, without regard to the principles of conflict of laws thereof, or the laws of the United States, as applicable, as if executed and to be performed wholly within the United States. 18. This Agreement shall be binding upon the Parties and their successors and assigns. Either Party may assign this Agreement subject to the conditions set forth in Article 19 of the Large Generator Interconnection Agreement. 19. SCE will file this Agreement for acceptance by FERC. Upon request by SCE, AV Solar shall support acceptance of this Agreement as filed, including waiver of any necessary filing and notice requirements. Such support shall include a written statement of concurrence with such filing, if requested by SCE. 20. Ambiguities or uncertainties in the wording of this Agreement shall not be construed for or against any Party, but shall be construed in the manner that most accurately reflects the Page - 8 -

17 Parties intent as of the date they executed this Agreement. 21. This Agreement shall become effective on the date the Agreement is fully executed by both Parties and the Initial Deposit pursuant to Section 3 of this Agreement is received by SCE ("Effective Date"). If SCE does not receive the fully executed Agreement and Initial Deposit within thirty (30) calendar days of AV Solar s receipt of this Agreement, then the offer reflected in this Agreement will expire and this Agreement will be of no effect. 22. This Agreement may be executed in one or more counterparts, each of which shall be deemed to be an original and all of which together shall be deemed to be one and the same instrument. SOUTHERN CALIFORNIA EDISON COMPANY By /s/ David L. Mead David Mead Vice President of Engineering and Technical Services Agreed to this 19th day of November, 2010 AV SOLAR RANCH 1, LLC By /s/ Frank De Rosa Name: Frank De Rosa Title: President Agreed to this 22nd day of November, 2010 Page - 9 -

18 EXHIBIT A DESCRIPTION SUMMARY FOR ENGINEERING, DESIGN AND PROCUREMENT WORK Description of Work: The engineering, design and procurement work to be performed under this Agreement are for the following Participating TO s Interconnection Facilities and Participating TO s Reliability Network Upgrades to accommodate the AV Solar Ranch One Project: Transmission (Participating TO s Interconnection Facilities): AV Solar One-Whirlwind 220 kv Transmission Line One 220 kv dead-end structure, two spans of conductors and OPGW and twelve dead end insulator / hardware assemblies between the last AV Solar owned structure on the AV Solar One-Whirlwind 220 kv Transmission Line and the Whirlwind Substation s dead-end rack at the 220 kv switchyard. Whirlwind Substation Line Drop (Participating TO s Interconnection Facilities) A new 220 kv switchrack position to terminate the AV Solar Ranch One Project s 220 kv generation tie-line. This work includes: (a) One 65 ft. high by 50 ft. wide dead-end structure (b) Three 0.003MDF coupling capacitor voltage transformers with steel pedestal support structures (c) Three 60 ft. line tie-downs with KCMIL ACSR conductors Protection relays as follows: (a) One GE L90 line current differential relay with telecommunications channel to the Generating Facility via the AV Solar One-Whirlwind 220 kv Transmission Line s OPGW (b) One SEL-311L line current differential relay Whirlwind Substation Line Position (Plan of Service Participating TO s Reliability Network Upgrades) One 220 kv position at Whirlwind Substation to be equipped to terminate the gen-tie, including the following equipment at the 220 kv Switchyard: (a) One 80 foot high by 45 foot wide dead-end structure (b) Two 3000 A 63 ka circuit breakers (c) Four 3000 A 80 ka horizontal-mounted group-operated disconnect switches (d) One grounding switch attachments (for lines grounding) (e) Two GE C60 relays (f) Eighteen bus supports with associated steel pedestal Page

19 Whirlwind Substation - Extend the 220kV Bus (Positions 5-8) (Additional Participating TO s Reliability Network Upgrades) Expansion of the bus four (4) positions to the east with includes the following equipment: (a) Two (2) 45 foot high by 45 foot wide bus dead-end structures and foundations. (b) One (1) 210 foot segment of north bus equipped with KCMIL ACSR conductors per phase (c) One (1) 210 foot segment of south bus equipped with KCMIL ACSR conductors per phase (d) Extend the three cable trenches 250 feet to the east Whirlwind Substation - Extend the 220kV Bus (Positions 9-17) (16.13% Assigned Share of Participating TO s Reliability Network Upgrades 1 ) Expansion of the bus eight (8) additional positions to the east which includes the following equipment: (a) Six (6) 45 foot high by 45 foot wide bus dead-end structures and foundations. (b) Forty-eight (48) bus dead end insulator assemblies. (c) Two (2) 210 foot segments of north bus equipped with KCMIL ACSR conductors per phase (approximately 2,600 feet total length) (d) Two (2) 210 foot segments of south bus equipped with KCMIL ACSR conductors per phase (approximately 2,600 feet total length) (e) Two (2) 230 kv, 3000 A, 63 ka sectionalizing circuit breakers and foundations. (f) Four (4) sets of 230 kv, 3000 A disconnect switches with support structures (one on each side of the sectionalizing circuit breakers) (g) Extension of the three cable trenches 500 feet to the east (approximately 1,500 feet of cable trench) (h) Two GE C60 relays Telecommunications (100% Assigned Share of Participating TO s Reliability Network Upgrades) All required light-wave, channel and related terminal equipment to support the SPS. Power Systems Control (Participating TO s Reliability Network Upgrades) Relay protection status alarms. Power Systems Control (Participating TO s Interconnection Facilities) 1 The allocation percentages provided for the assigned share of the Participating TO s Reliability Network Upgrades are those provided in the Phase II Interconnection Study report. Page

20 ne (1) RTU at the AV Solar Ranch One Project to monitor the customer s generation data such as low side MW, MVAR, kv, circuit breaker status, auxiliary load MW and MVAR. Corporate Environment, Health and Safety (Participating TO s Interconnection Facilities) Review the Draft Environmental Impact Report and Final Environmental Impact Report in order to identify the extent of SCE scope of work and impact analysis incorporated into the document and identify applicable mitigation measures. Review California Natural Diversity Data Base maps for biological resources and Record Search for Cultural Resources, and conduct a site visit to identify potential overrides. Identify California Public Utilities Commission Licensing requirements for SCE scope of work Licensing (Participating TO s Interconnection Facilities) Perform all required activities related to the SCE portion of the AV Solar Ranch One Project gen-tie line and telecom route. Page

21 Element AV Solar One-Whirlwind 220 kv Transmission Line Whirlwind Substation Line Drop Whirlwind Substation Line Position (Plan of Service Upgrade) EXHIBIT B ESTIMATED COST SUMMARY FOR ENGINEERING, DESIGN AND PROCUREMENT WORK Estimated Participating TO s Interconnecti on Facilities Cost Estimated Assigned Participating TO s Reliability Network Upgrades Cost Estimated Additional Participating TO s Reliability Network Upgrades Cost Estimated Engineering, Design & Procurement Cost Estimated Tax Liability (1) $884,000 $703,600 $246,260 $699,000 $550,000 $192,500 $2,661,000 $1,649,000 Whirlwind Substation - Extend the 220kV Bus $610,000 $250,000 (Positions 5-8) (2) Whirlwind Substation - Extend the 220kV Bus (Positions 9-17) $688,000 $3,577,000 $2,986,000 Telecommunications $150,000 $100,000 Environmental Health and Safety (limited scope) $1,485,000 $50,000 $17,500 Power Systems Control (Participating TO s Interconnection Facilities) $87,000 $69,000 $24,150 Power Systems Control (Network Upgrades) $26,000 $15,000 Total Cost $6,372,600 $480,410 (1) The estimated tax liability is based on a tax rate of 35% of the payments under this Agreement regarding Participating TO s Interconnection Facilities only. (2) These upgrades are assigned to project in the CAISO s interconnection queue ahead of the Transition Cluster. AV Solar s share of these costs under the LGIA will be 0.0%. Page

22 EXHIBIT C SCHEDULE FOR INITIAL DEPOSIT AND PAYMENTS AND POSTING OF TAX SECURITY Period Initial Deposit and Payments for Participating TO s Interconnection Facilities Initial Deposit and Payments for Participating TO s Reliability Network Upgrades Combined Initial Deposit and Payment Amounts Tax Security Posting Amounts 1 $592,600 $2,250,000 $2,842,600 $207,410 Due Date for Initial Deposit and Payments and Tax Security Postings With return of the executed Agreement 2 $400,000 $1,500,000 $1,900,000 $140,000 February 1, $380,000 $1,250,000 $1,630,000 $133,000 May 1, 2011 Total $1,372,600 $5,000,000 $6,372,600 $480,410 Page

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 101 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

Regulation Director FERC Rates & Regulation. March 16, 2012

Regulation Director FERC Rates & Regulation. March 16, 2012 Regulation Director FERC Rates & Regulation March 16, 2012 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to Section

More information

June 21, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Letter Agreement.

June 21, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Letter Agreement. Karen Koyano Principal Manager FERC Rates & Compliance June 21, 2017 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant

More information

Southern California Edison Company Tariff Title: Transmission Owner Tariff Tariff Record Title: Service Agreement No. 93 FERC FPA Electric Tariff ENGINEERING, DESIGN AND PROCUREMENT LETTER AGREEMENT BETWEEN

More information

September 8, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

September 8, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Karen Koyano Principal Manager FERC Rates & Compliance September 8, 2016 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose:

More information

Solar Generator Interconnection Agreement

Solar Generator Interconnection Agreement Solar Generator Interconnection Agreement THIS AGREEMENT is made and entered into as of the last date of signature provided below, by and between Fort Collins Utilities ( FCU ) and ( Generator ), an electric

More information

ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT

ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT ATTACHMENT H: Large Generator Interconnection Agreement (LGIA) STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT THIS STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT ( Agreement ) is made and entered

More information

Town of Highlands Board Approved as of May 17, 2012

Town of Highlands Board Approved as of May 17, 2012 TOWN OF HIGHLANDS INTERCONNECTION AGREEMENT FOR SMALL PHOTOVOLTAIC GENERATION FACILITY OF 10 kw OR LESS This PHOTOVOLTAIC INTERCONNECTION AGREEMENT FOR SMALL GENERATION 10 kw or less (the Agreement ),

More information

Customer s Name: Address: Contact Person: Telephone Number: Service Point Address: (Name and Address) Signature

Customer s Name: Address: Contact Person: Telephone Number: Service Point Address: (Name and Address) Signature APPLICATION FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION WITH THE UTILITY SYSTEM Return Completed Application to: Fannin County Electric Coop, INC. Attention: Colton Whisenhunt

More information

BC Hydro Open Access Transmission Tariff Effective: 09 December 2010 OATT Attachment M-1 Appendix 5 Page 1

BC Hydro Open Access Transmission Tariff Effective: 09 December 2010 OATT Attachment M-1 Appendix 5 Page 1 APPENDIX 5 to SGIP BC Hydro OATT Attachment M-1 Appendix 5 Page 1 Standard Generator Interconnection Agreement (SGIA) Project Name Table of Contents BC Hydro OATT Attachment M-1 Appendix 5 Page 2 Article

More information

STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission

STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission STANDARD INTERCONNECTION AGREEMENT Fayetteville Public Works Commission This STANDARD INTERCONNECTION AGREEMENT, (the Agreement ), is entered into this day of, 20 by and between, hereinafter called Customer

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff CAISO TARIFF APPENDIX CC

California Independent System Operator Corporation Fifth Replacement Electronic Tariff CAISO TARIFF APPENDIX CC CAISO TARIFF APPENDIX CC Large Generator Interconnection Agreement for Interconnection Requests in a Queue Cluster Window that are tendered a Large Generator Interconnection Agreement on or after July

More information

LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) AMONG [INTERCONNECTION CUSTOMER] AND [PARTICIPATING TO] AND

LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) AMONG [INTERCONNECTION CUSTOMER] AND [PARTICIPATING TO] AND (LGIA) AMONG [INTERCONNECTION CUSTOMER] AND [PARTICIPATING TO] AND CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION PROJECT: Project Name (Q#) TABLE OF CONTENTS LARGE GENERATOR INTERCONNECTION AGREEMENT...

More information

ABSTRACT Interconnection agreement for net energy billing DER systems or DER systems up to 100 kw that are compensated at avoided cost.

ABSTRACT Interconnection agreement for net energy billing DER systems or DER systems up to 100 kw that are compensated at avoided cost. ABSTRACT Interconnection agreement for net energy billing DER systems or DER systems up to 100 kw that are compensated at avoided cost. Roseau Electric Cooperative s 10 kw Demonstration Solar System Roseau,

More information

Recitals: Whereas, Interconnection Customer is the State of Maryland ( State ) or a local governmental entity of the State of Maryland;

Recitals: Whereas, Interconnection Customer is the State of Maryland ( State ) or a local governmental entity of the State of Maryland; MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW FOR MARYLAND STATE AND LOCAL GOVERNMENT ENTITIES This Agreement

More information

MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT

MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT APPENDIX A (insert date) MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT This Interconnection Agreement ( Agreement ) is

More information

Now, therefore, in consideration of and subject to the mutual covenants contained herein, the Parties agree as follows:

Now, therefore, in consideration of and subject to the mutual covenants contained herein, the Parties agree as follows: Interconnection Agreement for Small Generator Facility Tier 1, Tier 2, Tier 3 or Tier 4 Interconnection (Small Generator Facilities with Electric Nameplate Capacities or 10 MW or smaller) Form 8 This Interconnection

More information

STANDARD AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES WITH A CAPACITY LESS THAN OR EQUAL TO 10 MW

STANDARD AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES WITH A CAPACITY LESS THAN OR EQUAL TO 10 MW STANDARD AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION FACILITIES WITH A CAPACITY LESS THAN OR EQUAL TO 10 MW This Agreement is made and entered into this day of, by and between, a organized

More information

February 29, Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter Agent Services Agreement

February 29, Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter Agent Services Agreement February 29, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 RE: Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter

More information

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 10 kw BUT LESS THAN OR EQUAL TO 10 MW This Agreement is made and entered into this day of, by

More information

EL PASO ELECTRIC COMPANY SCHEDULE NO. DG INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION

EL PASO ELECTRIC COMPANY SCHEDULE NO. DG INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION AVAILABILITY This rate schedule is applicable to Customers with facilities consisting of one or more on-site generating units operating in parallel with the Company s system (Distributed Generation) as

More information

AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION

AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION This Interconnection Agreement ( Agreement ) is made and entered into this day of, 20, by Egyptian Electric Cooperative Association,

More information

December 22, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

December 22, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 James A. Cuillier Director FERC Rates & Regulation December 22, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: FERC Docket No.

More information

February 25, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the LGIA.

February 25, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the LGIA. Regulation James A. Cuillier Director FERC Rates & Regulation February 25, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

ATTACHMENT AM METER AGENT SERVICES AGREEMENT FOR SPP MARKET BETWEEN CITY OF INDEPENDENCE, MISSOURI (MARKET PARTICIPANT) AND

ATTACHMENT AM METER AGENT SERVICES AGREEMENT FOR SPP MARKET BETWEEN CITY OF INDEPENDENCE, MISSOURI (MARKET PARTICIPANT) AND ATTACHMENT AM METER AGENT SERVICES AGREEMENT FOR SPP MARKET BETWEEN CITY OF INDEPENDENCE, MISSOURI (MARKET PARTICIPANT) AND WESTAR ENERGY, INC. (METER AGENT) OCTOBER 1, 2009 This Agreement made and entered

More information

CORE GAS AGGREGATION SERVICE AGREEMENT

CORE GAS AGGREGATION SERVICE AGREEMENT Distribution: PG&E Program Administrator (original) CTA PG&E Gas Contract Administrator PG&E Credit Manager For PG&E Use Only CTA Group No.: Billing Account No.: Date Received: Effective Service Date:

More information

INTERCONNECTION AND OPERATING AGREEMENT

INTERCONNECTION AND OPERATING AGREEMENT INTERCONNECTION AND OPERATING AGREEMENT This Interconnection and Operating Agreement ( Agreement ) for the facility located at, in the City of, Michigan, is entered into this day of, 200 by and between

More information

KOOTENAI ELECTRIC COMMUNITY SOLAR PROGRAM APPLICATION & AGREEMENT

KOOTENAI ELECTRIC COMMUNITY SOLAR PROGRAM APPLICATION & AGREEMENT Thank you for your interest in the Kootenai Electric Community Solar Program (Program). By completing this Application (Application), you have an opportunity to participate in the Program. You agree to

More information

COMMUNITY SOLAR PARTICIPATION AGREEMENT

COMMUNITY SOLAR PARTICIPATION AGREEMENT COMMUNITY SOLAR PARTICIPATION AGREEMENT Thank you for your interest in Tacoma Power s Community Solar Program ( Program ). By completing this Agreement, you have an opportunity to participate in and facilitate

More information

December 10, Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter Agent Services Agreement

December 10, Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter Agent Services Agreement The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 December 10, 2014 RE: Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter

More information

KOSCIUSKO REMC AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION

KOSCIUSKO REMC AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION KOSCIUSKO REMC AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION This Interconnection Agreement ( Agreement ) is made and entered into this day of, 20, by Kosciusko Rural Electric Membership Corporation,

More information

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER

Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FER Title Page Southern California Edison Company Tariff Title: Transmission Owners Tariff Tariff Record Title: First Revised Service Agreement No. 39 FERC FPA Electric Tariff INTERCONNECTION FACILITIES AGREEMENT

More information

INTERCONNECTION AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF CERTIFIED INVERTER-BASED EQUIPMENT 10 kw OR SMALLER

INTERCONNECTION AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF CERTIFIED INVERTER-BASED EQUIPMENT 10 kw OR SMALLER INTERCONNECTION AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF CERTIFIED INVERTER-BASED EQUIPMENT 10 kw OR SMALLER THIS INTERCONNECTION AGREEMENT ( Agreement ) is made and entered into this day

More information

Rate Code: L L-16 SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (SANTEE COOPER) LARGE LIGHT AND POWER SCHEDULE L-16

Rate Code: L L-16 SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (SANTEE COOPER) LARGE LIGHT AND POWER SCHEDULE L-16 SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (SANTEE COOPER) LARGE LIGHT AND POWER SCHEDULE L-16 Section 1. Availability: (A) Service hereunder is available at Delivery Points on or near the transmission facilities

More information

CLAIMS ADMINISTRATION SERVICES AGREEMENT

CLAIMS ADMINISTRATION SERVICES AGREEMENT CLAIMS ADMINISTRATION SERVICES AGREEMENT This Claims Administration Services Agreement (the "Agreement") is made and entered into by and between XYZ School District ("Client") and Keenan & Associates ("Keenan").

More information

CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY

CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY Otter Tail Power Company Original Sheet No. 1 CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY Otter Tail Power Company Substitute Original Sheet No. 2 Superseding Original Volume No.

More information

STANDARD GENERATION INTERCONNECTION AGREEMENT BETWEEN CITY OF ANAHEIM AND

STANDARD GENERATION INTERCONNECTION AGREEMENT BETWEEN CITY OF ANAHEIM AND STANDARD GENERATION INTERCONNECTION AGREEMENT BETWEEN CITY OF ANAHEIM AND This Standard Generation Interconnection Agreement ( Interconnection Agreement ), dated, for purposes of identification only, is

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 62200-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 61862-E Sheet 1 TIME-OF-USE BASE INTERRUPTIBLE PROGRAM AGGREGATOR AGREEMENT

More information

The Cincinnati Gas & Electric Company Certified Supplier Service Agreement

The Cincinnati Gas & Electric Company Certified Supplier Service Agreement The Cincinnati Gas & Electric Company Certified Supplier Service Agreement This CERTIFIED SUPPLIER SERVICE AGREEMENT (Agreement) dated as of, 200 is between and among Cinergy Services, Inc. on behalf of

More information

WHITBY HYDRO CONNECTION AGREEMENT FOR A GENERATOR WITH MOMENTARY CLOSED TRANSITION OPERATION

WHITBY HYDRO CONNECTION AGREEMENT FOR A GENERATOR WITH MOMENTARY CLOSED TRANSITION OPERATION WHITBY HYDRO CONNECTION AGREEMENT FOR A GENERATOR WITH MOMENTARY CLOSED TRANSITION OPERATION This Connection Agreement ( Agreement ) is made and entered into this day of, 20, by Whitby Hydro ( the Distributor

More information

Project J290. AMENDED AND RESTATED FACILITIES CONSTRUCTION AGREEMENT by and among. Border Winds Energy, LLC, Otter Tail Power Company.

Project J290. AMENDED AND RESTATED FACILITIES CONSTRUCTION AGREEMENT by and among. Border Winds Energy, LLC, Otter Tail Power Company. SA 2678 BORDER WINDS-OTTER TAIL POWER FCA EFFECTIVE 07/19/2014 SUBSTITUTE ORIGINAL SERVICE AGREEMENT NO. 2678 PUBLIC VERSION Project J290 AMENDED AND RESTATED FACILITIES CONSTRUCTION AGREEMENT by and among

More information

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 20 kw

MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 20 kw MARYLAND STANDARD AGREEMENT FOR INTERCONNECTION OF SMALL GENERATOR FACILITIES WITH A CAPACITY GREATER THAN 20 kw This Maryland Standard Agreement For Interconnection Of Small Generator Facilities With

More information

NAVARRO COUNTY ELECTRIC COOPERATIVE, INC. Distributed Generation Short Form Contract & DG Rider

NAVARRO COUNTY ELECTRIC COOPERATIVE, INC. Distributed Generation Short Form Contract & DG Rider NAVARRO COUNTY ELECTRIC COOPERATIVE, INC. Distributed Generation Short Form Contract & DG Rider November 1, 2015 Page 1 COOPERATIVE AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION SHORT FORM CONTRACT

More information

APPENDIX A. Name: Address:

APPENDIX A. Name:   Address: Adopted from Appendix A of the New York State Standardized Interconnection Requirements and Application Process for New Distributed Generators 2 MW or Less Connected in Parallel with Utility Distribution

More information

TERMS AND CONDITIONS OF SALE

TERMS AND CONDITIONS OF SALE TERMS AND CONDITIONS OF SALE WHEREAS, Cascade is a supplier of used and refurbished computer equipment; and WHEREAS, Purchaser desires to purchase from Cascade, and Cascade desires to sell to Purchaser,

More information

August 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

August 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Regulation Karen Koyano Principal Manager FERC Rates & Compliance August 25, 2017 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

Standard Form of CAWCD Wheeling Contract

Standard Form of CAWCD Wheeling Contract EXHIBIT B DRAFT 11/9/16 Standard Form of CAWCD Wheeling Contract WHEELING CONTRACT BETWEEN THE CENTRAL ARIZONA WATER CONSERVATION DISTRICT AND [ENTITY] This CAWCD Wheeling Contract ("Contract") is made

More information

Residential Electricity Terms of Service

Residential Electricity Terms of Service Residential Electricity Terms of Service Commonwealth Edison ( Utility ) The following Residential Electricity Terms of Service ( TOS ) will apply to residential customers who choose Champion Energy (

More information

Name: Niagara Mohawk Power Corporation d/b/a National Grid. Address: 1125 Broadway Albany, NY Telephone: Telephone: (518)

Name: Niagara Mohawk Power Corporation d/b/a National Grid. Address: 1125 Broadway Albany, NY Telephone: Telephone: (518) FORM K APPENDIX A NIAGARA MOHAWK POWER CORPORATION d/b/a NATIONAL GRID NEW YORK STATE STANDARDIZED CONTRACT FOR INTERCONNECTION OF NEW DISTRIBUTED GENERATION UNITS WITH CAPACITY OF 2 MW OR LESS CONNECTED

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator ) Docket No. ER14-2824-000 Corporation ) ) MOTION TO INTERVENE, LIMITED PROTEST AND COMMENTS

More information

Man Lift Standard Terms and Conditions of Sale Page 1 of 5

Man Lift Standard Terms and Conditions of Sale Page 1 of 5 Man Lift Standard Terms and Conditions of Sale Page 1 of 5 1. Definitions. Unless otherwise defined herein, all terms which appear in these Man Lift Standard Terms and Conditions of Sale in initial capital

More information

SUPPLEMENTAL INTERCONNECTION APPLICATION INSTRUCTIONS. for COMMUNITY SOLAR ENERGY GENERATING SYSTEM ( CSEGS ) (Maryland s CSEGS Pilot Program)

SUPPLEMENTAL INTERCONNECTION APPLICATION INSTRUCTIONS. for COMMUNITY SOLAR ENERGY GENERATING SYSTEM ( CSEGS ) (Maryland s CSEGS Pilot Program) SUPPLEMENTAL INTERCONNECTION APPLICATION INSTRUCTIONS for COMMUNITY SOLAR ENERGY GENERATING SYSTEM ( CSEGS ) (Maryland s CSEGS Pilot Program) Pepco will accept Interconnection Applications for Community

More information

SAMPLE FORMS - CONTRACTS Compression Services Agreement (Form 8100) (See Attached Form)

SAMPLE FORMS - CONTRACTS Compression Services Agreement (Form 8100) (See Attached Form) SOUTHERN CALIFORNIA GAS COMPANY Revised CAL. P.U.C. SHEET NO. 51176-G LOS ANGELES, CALIFORNIA CANCELING Original CAL. P.U.C. SHEET NO. 49858-G SAMPLE FORMS - CONTRACTS Compression Services Agreement (Form

More information

RESIDENTIAL TERMS & CONDITIONS ( Agreement )

RESIDENTIAL TERMS & CONDITIONS ( Agreement ) RESIDENTIAL TERMS & CONDITIONS ( Agreement ) TERM GENERATION SERVICE CHARGES CANCELLATION FEE CONTRACT RENEWAL OTHER 12 N/A monthly billing cycles ("Term"). 5.10 cents per kwh for Generation Service. Price

More information

Metal Works Standard Terms and Conditions of Sale Page 1 of 5

Metal Works Standard Terms and Conditions of Sale Page 1 of 5 Metal Works Standard Terms and Conditions of Sale Page 1 of 5 1. Definitions. Unless otherwise defined herein, all terms which appear in these Metal Works Standard Terms and Conditions of Sale in initial

More information

WITNESSETH: WHEREAS, This Agreement does not address the sale of electricity to or from Consumers; and

WITNESSETH: WHEREAS, This Agreement does not address the sale of electricity to or from Consumers; and GENERATOR INTERCONNECTION & OPERATING AGREEMENT FOR CATEGORY 3 5 PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF GREATER THAN 150 kw BETWEEN CONSUMERS ENERGY COMPANY AND (PROJECT DEVELOPER NAME) GENERATOR

More information

Title Page Southern California Edison Company Tariff Title: Rate Schedule Tariff Record Title: Rate Schedule FERC No. 425 FERC FPA Electric Tariff AMENDED AND RESTATED ELDORADO SYSTEM OPERATINGAGREEMENT

More information

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex Southern Companies Attachment J (LGIP), Page 1 ATTACHMENT J STANDARD LARGE GENERATOR INTERCONNECTION PROCEDURES (LGIP) including STANDARD LARGE GENERATOR INTERCONNECTION AGREEMENT (LGIA) Southern Companies

More information

Major Energy Terms and Conditions (MD BGE)

Major Energy Terms and Conditions (MD BGE) Major Energy Terms and Conditions (MD BGE) 1.Agreement to Sell and Purchase Energy. This is an agreement between Major Energy Services, LLC for natural gas and/or Major Energy Electric Services, LLC for

More information

January 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

January 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms. Regulation James A. Cuillier Director FERC Rates & Regulation January 31, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms.

More information

State of Minnesota Interconnection Agreement For the Interconnection of Extended Parallel Distributed Generation Systems With Minnesota Power

State of Minnesota Interconnection Agreement For the Interconnection of Extended Parallel Distributed Generation Systems With Minnesota Power State of Minnesota Interconnection Agreement For the Interconnection of Extended Parallel Distributed Generation Systems With Minnesota Power This Generating System Interconnection Agreement is entered

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59898-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57292-E Sheet 1 GENERATING FACILITY INTERCONNECTION AGREEMENT (3 RD PARTY

More information

SMALL RENEWABLE GENERATION INTERCONNECTION AGREEMENT BETWEEN

SMALL RENEWABLE GENERATION INTERCONNECTION AGREEMENT BETWEEN SAMPLE TEMPLATE December 3, 2014 SMALL RENEWABLE GENERATION INTERCONNECTION AGREEMENT BETWEEN PUBLIC UTILITY DISTRICT NO.1 OF SNOHOMISH COUNTY, WASHINGTON AND TABLE OF CONTENTS Article 1. Scope and Limitations

More information

Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating)

Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating) Up Front Incentive Renewable Energy Credit Purchase Agreement (Residential Solar Water Heating) This Up Front Incentive Renewable Energy Credit Purchase Agreement ( Agreement ) is hereby made and entered

More information

SCHEDULE SGI : SMALL GENERATOR INTERCONNECTIONS OTHER THAN NET METERING

SCHEDULE SGI : SMALL GENERATOR INTERCONNECTIONS OTHER THAN NET METERING ~A BARC ELECTRIC COOPERATIVE SCHEDULE SGI : SMALL GENERATOR INTERCONNECTIONS OTHER THAN NET METERING A. APPLICABILITY This Schedule SGI is applicable to Interconnection Customers who own and operate, or

More information

Regulation Director FERC Rates & Regulation. January 27, 2012

Regulation Director FERC Rates & Regulation. January 27, 2012 Regulation Director FERC Rates & Regulation January 27, 2012 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to

More information

Tampa Electric Company FERC Electric Tariff First Revised Service Agreement No. 5

Tampa Electric Company FERC Electric Tariff First Revised Service Agreement No. 5 Tampa Electric Company TAMPA ELECTRIC COMPANY AGREEMENT FOR PARTIAL REQUIREMENTS ELECTRIC SERVICE FOR RESALE TO FLORIDA POWER CORPORATION UNDER RATE SCHEDULE AR-1WHOLESALE REQUIREMENTS TARIFF Tampa Electric

More information

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) 1. Overview:

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) 1. Overview: SOUTH CAROLINA COOPERATIVES Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) 1. Overview: This Standard contains the requirements, in addition to applicable

More information

Internet Services and Central Link Broadband Agreement

Internet Services and Central Link Broadband Agreement Central Link Broadband 155 N League Ranch RD Waco, TX 76705-4917 Internet Services and Central Link Broadband Agreement This Internet Services and Central Link Broadband Agreement (the Agreement ) is between

More information

Dear Oklahoma Electric Cooperative member:

Dear Oklahoma Electric Cooperative member: Dear Oklahoma Electric Cooperative member: Thank you for requesting information about interconnecting a small wind generator to OEC s system. To assist our members, we have developed a streamlined process

More information

SALEM CITY. NET METERING LICENSE AGREEMENT For Customer-Owned Electric Generating Systems of 100kW or Less

SALEM CITY. NET METERING LICENSE AGREEMENT For Customer-Owned Electric Generating Systems of 100kW or Less SALEM CITY NET METERING LICENSE AGREEMENT For Customer-Owned Electric Generating Systems of 100kW or Less This NET METERING LICENSE AGREEMENT ( Agreement ) is between ( Customer ) and Salem City ( Salem

More information

General Purchase Order Terms and Conditions (Pro-buyer)

General Purchase Order Terms and Conditions (Pro-buyer) 1. Applicability. General Purchase Order Terms and Conditions (Pro-buyer) (a) This purchase order is an offer by GT Exhaust, Inc. (the "Buyer") for the purchase of the goods specified on the face of this

More information

06/22/2017. acceptance by Provider. The terms of this Order also apply to any Corrective Action required by Company pursuant to Section 3 hereof.

06/22/2017. acceptance by Provider. The terms of this Order also apply to any Corrective Action required by Company pursuant to Section 3 hereof. 06/22/2017 1. Terms of Order This purchase order is an offer by the company identified on the face of this purchase order ("Company") for the procurement of the services specified (the "Services") from

More information

AUTOTOOL, INC. TERMS AND CONDITIONS OF SALE

AUTOTOOL, INC. TERMS AND CONDITIONS OF SALE AUTOTOOL, INC. TERMS AND CONDITIONS OF SALE The following terms and conditions of sale as they appear at www.autotoolinc.com at the time of sale (the Terms and Conditions ) govern the sale of all materials,

More information

DIGITRUST ID SERVICES AGREEMENT

DIGITRUST ID SERVICES AGREEMENT DIGITRUST ID SERVICES AGREEMENT This DIGITRUST ID SERVICES AGREEMENT, dated as of, 2018 (the Effective Date ), is by and between IAB Technology Laboratory, Inc. ( Tech Lab ) and ( Subscriber ), individually

More information

REP ENERGY, LLC MASSACHUSETTS OPERATIONS BUSINESS ELECTRICITY AUTHORIZATION

REP ENERGY, LLC MASSACHUSETTS OPERATIONS BUSINESS ELECTRICITY AUTHORIZATION REP ENERGY, LLC MASSACHUSETTS OPERATIONS BUSINESS ELECTRICITY AUTHORIZATION Version REP030415 Business Name Utility Account # Service Address Suite/ Unit # City State Zip Utility BILLING ADDRESS (if different

More information

Berkeley Electric Cooperative, Inc. Standard for Interconnecting Distributed Resources Up To 500 KVA with the Cooperative s Electric Systems (CES)

Berkeley Electric Cooperative, Inc. Standard for Interconnecting Distributed Resources Up To 500 KVA with the Cooperative s Electric Systems (CES) Berkeley Electric Cooperative, Inc. Standard for Interconnecting Distributed Resources Up To 500 KVA with the Cooperative s Electric Systems (CES) 1. Overview: This Standard sets forth the requirements,

More information

Transmission Association, Inc. Fourth Revised Sheet No. 140

Transmission Association, Inc. Fourth Revised Sheet No. 140 Transmission Association, Inc. Fourth Revised Sheet No. 140 ATTACHMENT K GENERATOR INTERCONNECTION PROCEDURES (GIP) including GENERATOR INTERCONNECTION AGREEMENT (GIA) (Effective January 1, 2016) Effective

More information

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59895-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57290-E GENERATING FACILITY INTERCONNECTION AGREEMENT (Non-Exporting)

More information

Frontier Utilities Northeast, LLC Ohio Supply Agreement Residential & Small Commercial Terms of Service

Frontier Utilities Northeast, LLC Ohio Supply Agreement Residential & Small Commercial Terms of Service Frontier Utilities Northeast, LLC Ohio Supply Agreement Residential & Small Commercial Terms of Service Competitive Retail Electric Service (CRES) Provider Certification No. 14-795E (2) Version Date: 3/13/2017

More information

TERMS AND CONDITIONS OF SALE MEDICAL EQUIPMENT

TERMS AND CONDITIONS OF SALE MEDICAL EQUIPMENT FUJIFILM Medical Systems U.S.A., Inc. (Endoscopy Division) Web Version: 03 (October 10, 2013) TERMS AND CONDITIONS OF SALE MEDICAL EQUIPMENT 1. Each quotation provided by FUJIFILM Medical Systems U.S.A.,

More information

RECITALS. NOW, THEREFORE, in consideration of the mutual agreements and covenants herein set forth, it is agreed as follows:

RECITALS. NOW, THEREFORE, in consideration of the mutual agreements and covenants herein set forth, it is agreed as follows: AGREEMENT FOR FIRE CHIEF, DUTY CHIEF, AND ADMINISTRATIVE SERVICES Between PLACER HILLS FIRE PROTECTION DISTRICT and NEWCASTLE FIRE PROTECTION DISTRICT DRAFT 2 THIS AGREEMENT FOR FIRE CHIEF, DUTY CHIEF,

More information

Standard Tariff for Electricity Purchases From And Sales to Qualifying Facilities. Applicant: Dated 20

Standard Tariff for Electricity Purchases From And Sales to Qualifying Facilities. Applicant: Dated 20 Applicant: Dated 20 Form of Standard Contract Standard Interconnection Agreement For Qualifying Facilities with a design Capacity of 25 Kilowatts or Less Preamble This Agreement is made as of the day of,

More information

OH Frontier Online Premier-6 AEP Ohio Electric Supply Product Disclosure Summary Document Effective Date: 7/18/2017. Contract Term/Length 6 months

OH Frontier Online Premier-6 AEP Ohio Electric Supply Product Disclosure Summary Document Effective Date: 7/18/2017. Contract Term/Length 6 months Frontier Utilities Northeast, LLC 5161 San Felipe Suite 320 Houston, TX 77056 1-877-636-3450 www.frontierutilities.com Customer Service Hours: Monday Friday 7am 6pm CT, Saturday 8am 2pm CT OH Frontier

More information

CLEAR MEMBERSHIP TERMS AND CONDITIONS

CLEAR MEMBERSHIP TERMS AND CONDITIONS CLEAR MEMBERSHIP TERMS AND CONDITIONS By clicking the I AGREE button that follows these Terms and Conditions, or otherwise enrolling in any of the programs offered by Alclear, LLC or its affiliates ( CLEAR

More information

STANDARD LIGHTING CONTRACT (COMPANY OWNED) FORM 548

STANDARD LIGHTING CONTRACT (COMPANY OWNED) FORM 548 Page 1 of 5 STANDARD LIGHTING CONTRACT (COMPANY OWNED) FORM 548 Contract Number: Notification Number: Part I Effective date of agreement: Company: CONSUMERS ENERGY COMPANY A Michigan Corporation ONE ENERGY

More information

Palmetto Electric Cooperative, Inc. Standard for Interconnecting Distributed Resources Less Than 2 MVA With Cooperative s Electric Systems (CES)

Palmetto Electric Cooperative, Inc. Standard for Interconnecting Distributed Resources Less Than 2 MVA With Cooperative s Electric Systems (CES) 1. Overview: Palmetto Electric Cooperative, Inc. Standard for Interconnecting Distributed Resources Less Than 2 MVA With Cooperative s Electric Systems (CES) This Standard sets forth the requirements,

More information

SAMPLE CONTRACT BETWEEN THE BOARD OF COMMISSIONERS OF THE PORT OF NEW ORLEANS AND CONTRACTOR NAME FOR SERVICES

SAMPLE CONTRACT BETWEEN THE BOARD OF COMMISSIONERS OF THE PORT OF NEW ORLEANS AND CONTRACTOR NAME FOR SERVICES SAMPLE CONTRACT BETWEEN THE BOARD OF COMMISSIONERS OF THE PORT OF NEW ORLEANS AND CONTRACTOR NAME FOR SERVICES On this day of, 2017, the Board of Commissioners of the Port of New Orleans hereinafter sometimes

More information

AccessHosting.com TERMS OF SERVICE

AccessHosting.com TERMS OF SERVICE AccessHosting.com TERMS OF SERVICE 1. Legally binding agreement. By ordering and/or using any service offered or provided by Access Hosting LLC, dba AccessHosting.com ( AccessHosting.com), the individual

More information

This Agreement will start on a meter-read date set by your EDC ( Start Date ). See Paragraph 4 for details. Section 7 for details.

This Agreement will start on a meter-read date set by your EDC ( Start Date ). See Paragraph 4 for details. Section 7 for details. Electric Generation Supplier (EGS) Information ELECTRIC GENERATION SUPPLIER CONTRACT SUMMARY ( Contract Summary ) RESIDENTIAL - FIXED PRICE PENNSYLVANIA AEP Energy, Inc. 225 West Wacker Drive, Suite 700,

More information

Holden Municipal Light Department Interconnection Agreement for Net Metering Service

Holden Municipal Light Department Interconnection Agreement for Net Metering Service This agreement dated the day of, 20, ( Agreement ) is by and between Holden Municipal Light Department ( Department ), and, ( Customer ) (Department and Customer referred to as Parties ). Whereas, Customer

More information

Fixed-to-Mobile satellite services

Fixed-to-Mobile satellite services Fixed-to-Mobile satellite services Terms and conditions of service The following terms and conditions ( Terms and Conditions ) apply to fixed-to-mobile Inmarsat services provided to the customer ( Customer

More information

4. Supply Rewards 5. Renewable Energy Certificates.

4. Supply Rewards 5. Renewable Energy Certificates. New Jersey Spring Power & Gas Variable Terms and Conditions Spring Energy RRH, LLC d/b/a Spring Power & Gas 2500 Plaza 5, Harborside Financial Center, Jersey City, NJ 07311 Tel No. 1.888.710.4782 springpowerandgas.us

More information

PAYROLL SERVICE AGREEMENT

PAYROLL SERVICE AGREEMENT PAYROLL SERVICE AGREEMENT YOUR NAME: DATE: This Payroll Services Agreement (this Agreement ) is made as of the day of, 20 for the effective service commencement date of, between Client identified above

More information

United Silicon Carbide, inc. Standard Terms and Conditions of Sale

United Silicon Carbide, inc. Standard Terms and Conditions of Sale United Silicon Carbide, inc. Standard Terms and Conditions of Sale 1. APPLICABILITY. These terms and conditions (these Terms and Conditions ) shall apply to all sales by United Silicon Carbide, inc. (

More information

Contract and Disclosure Statement Summary Pennsylvania Residential Contract

Contract and Disclosure Statement Summary Pennsylvania Residential Contract Contract and Disclosure Statement Summary Pennsylvania Residential Contract Electric Generation Supplier Information: Price Structure: Generation/Supply Price: Statement Regarding Savings: Deposit Requirement

More information

United Tool & Mold, Inc. Jungwoo USA, LLC Terms and Conditions of Sale

United Tool & Mold, Inc. Jungwoo USA, LLC Terms and Conditions of Sale United Tool & Mold, Inc. Jungwoo USA, LLC Terms and Conditions of Sale Unless United Tool & Mold, Inc. or Jungwoo USA, LLC (as the case may be, we or similar references) has entered into a written agreement

More information

BZS TRANSPORT INC. BROKER-SHIPPER TERMS AND CONDITIONS

BZS TRANSPORT INC. BROKER-SHIPPER TERMS AND CONDITIONS 1. APPLICABILITY These Terms & Conditions and agreed upon pricing documents apply to all broker services (the Services ) provided by BZS Transport Inc. (hereafter BROKER ) to SHIPPER. These Terms & Conditions

More information

LATITUDE ENGINEERING - GENERAL TERMS OF SALE

LATITUDE ENGINEERING - GENERAL TERMS OF SALE 1. General Scope LATITUDE ENGINEERING - GENERAL TERMS OF SALE These General Terms of Sale ( Terms ), together with the terms and conditions set forth on the purchase order form ( Order Form ) (collectively

More information

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT

RENEWABLE MARKET ADJUSTING TARIFF POWER PURCHASE AGREEMENT [This contract has been approved by the California Public Utilities Commission in Decision 13-05-034. Modification of the terms and conditions of this contract will result in the need to obtain additional

More information