Economic Impacts on New Jersey of Upgrading PSE&G s Susquehanna-Roseland Transmission System

Size: px
Start display at page:

Download "Economic Impacts on New Jersey of Upgrading PSE&G s Susquehanna-Roseland Transmission System"

Transcription

1 Economic Impacts on New Jersey of Upgrading PSE&G s Susquehanna-Roseland Transmission System Dr. Joseph J. Seneca Dr. Michael L. Lahr Dr. James W. Hughes Will Irving May 2009

2 Table of Contents EXECUTIVE SUMMARY... i INTRODUCTION... 1 Project Background... 1 Analytical Approach... 1 Organization of the Report... 2 ECONOMIC IMPACT ANALYSIS... 3 Expenditures Considered in the Analysis... 3 R/ECON Input-Output Model... 3 Transmission Line and Towers (Monopole Structures)... 4 Expenditure Assumptions... 4 Economic Impacts... 6 Transmission Line and Towers (Lattice Structures) Expenditure Assumptions Economic Impacts East Hanover/Roseland Switching Station Expenditure Assumptions Economic Impacts Jefferson Switching Station Expenditure Assumptions Economic Impacts Combined Economic Impacts (Monopole Towers) Combined Economic Impacts (Lattice Towers) CONCLUSION APPENDIX A: ECONOMIC AND DEMOGRAPHIC PROFILES AND DYNAMICS APPENDIX B: INPUT-OUTPUT ANALYSIS APPENDIX C: ECONOMIC IMPACTS OF COMBINED LATTICE-MONOPOLE SCENARIO... 74

3 EXECUTIVE SUMMARY This report presents the estimated economic impacts in New Jersey of the approximately $649 - $750 million in expenditures required for construction of the New Jersey portion of the proposed upgrade to PSE&G s Susquehanna-Roseland Transmission Network. The economic impacts estimated are only those associated with the expenditures to be made on construction of the network upgrade, and do not reflect any of the potential ongoing economic impacts of the increased transmission capacity once the upgrade is complete. The proposed upgrade would add 500 kv of additional power transmission capacity to the existing 230 kv network. This analysis examines the economic impacts of the construction of two switching stations and of the transmission line and towers required to accommodate the increased transmission capacity. Alternative scenarios are presented to reflect the two different types of tower structures that may be used. If all 249 towers were lattice structures, the estimated total expenditures for the project would be approximately $649 million, whereas if all the towers were monopole structures, the estimated expenditures would total $750 million. (Appendix C at the end of the report provides the aggregate expenditures and economic impacts for a 50%-50% split between the two types of towers.) The estimated economic impacts include both direct impacts and indirect impacts. Direct impacts are those directly associated with the project expenditures, such as the construction employment required for the project and purchases of material to be used in construction of the switching station and towers. Indirect impacts are those generated by the multiplier effects of the initial expenditures, as the salaries paid to workers and the business revenue generated by the expenditures made on materials in New Jersey are then re-spent throughout the economy, generating further economic activity and impacts in the form of employment, gross domestic product, compensation (income) and tax revenues. Based on the two expenditure scenarios associated with the different types of towers and on the associated range of project expenditures to be made in New Jersey, the following economic impacts were estimated: i

4 Employment. It is estimated that construction of the switching stations and transmission line and towers will generate from 3,415 to 3,931 total job-years (one job-year is equal to one job lasting one year). This includes from 2,258 to 2,646 direct job-years, including construction employment, as well as design work, consulting services and other Gross Domestic Product. It is estimated that the construction of the upgrade will generate between $396.1 and $428.1 million in gross domestic product for New Jersey. Compensation. It is estimated that the total compensation generated by both the direct and the indirect employment generated by the construction of the upgraded network will be between $307.5 million and $333.8 million. State Tax Revenues. It is estimated that the construction phase of the project will generate between $8 and $9 million in state taxes. Local Tax Revenues. It is estimated that the construction phase of the project will generate between $7.9 and $9.9 million in local taxes. ii

5 INTRODUCTION This report presents the findings of an economic impact analysis of the approximately $649-$750 million in expenditures required for construction of the New Jersey portion of the proposed upgrade to PSE&G s Susquehanna-Roseland Transmission Network. Project Background PJM Interconnection, the regional authority overseeing electricity transmission in all or part of 13 states, including New Jersey and Pennsylvania, has determined that the existing 230 kv capacity of the transmission line running from Susquehanna, Pennsylvania to Roseland, New Jersey is not sufficient to accommodate projected demand growth in coming years. As a result, PJM has directed PSE&G of New Jersey and PPL of Pennsylvania to upgrade the network by adding a new 500 kv capacity transmission line to the existing network. The upgrade will require not only the addition of the new power line itself, but also construction of new towers to accommodate both the new 500 kv, as well as the existing 230 kv line, and the construction of two new switching stations along the transmission route, one in Jefferson, New Jersey and one near the line s terminus in Roseland, New Jersey. This economic impact analysis covers the estimated $649-$750 million of expenditures required for construction of the New Jersey portion of the new line, including the two switching stations to be built in New Jersey. Analytical Approach The economic impacts of the construction of the new transmission line in New Jersey are estimated using the R/ECON Input-Output model developed and maintained by the Center for Urban Policy Research at Rutgers University s Edward J. Bloustein School of Planning and Public Policy. The model provides estimates of a broad and detailed range of economic impacts, including employment, gross domestic product, income and tax revenues. A detailed description of the model and its methodology is provided with the analysis. 1

6 The construction of each component of the new transmission infrastructure is analyzed individually. That is, the transmission line and towers are analyzed separately, as are each of the two switching stations. In addition, two separate analyses of the transmission line and tower infrastructure are provided. Because the existing towers currently carrying the 230 kv line do not meet the specifications required to handle two lines of the given capacities discussed, an additional 249 new towers are required in New Jersey. Some of these towers will be monopole structures (i.e., a single pole with branches holding the transmission lines), while others will be wider lattice-type structures. Because each of these tower types requires a different mix of material and labor inputs, two separate analyses are provided, one assuming that all towers are monopole, and the other assuming that all towers are lattice. Organization of the Report The report begins with a brief overview of the expenditures considered in the analysis. This is followed by a description of the R/ECON Input-Output Model and its application. Next, the analyses of the separate components of the transmission network are presented. These analyses consist of the all-monopole transmission line and towers, the all-lattice transmission line and towers, the Jefferson Switching Station, and the Roseland/East Hanover Switching Station. Each analysis consists of a review of the input expenditures used in the R/ECON Input-Output Model and a detailed presentation of the estimated economic impacts of those expenditures. A final section presents the combined impacts of the total investment in New Jersey for both the allmonopole and all-lattice tower scenarios. This is followed by a brief summary and conclusions. An appendix presents a brief economic profile of the areas in New Jersey where the new transmission line would be built. 2

7 ECONOMIC IMPACT ANALYSIS Expenditures Considered in the Analysis Because of the highly specialized nature of the power transmission materials and equipment needed for construction of the upgraded network, almost all the required material will be purchased outside of New Jersey. As such, the majority of the impacts measured in this analysis are generated via the employment of construction workers and the purchase of specialized services associated with the project. The majority of these workers and services are expected to come from New Jersey. Detailed explanations of the specific expenditures made in New Jersey are provided for each component of the analysis. R/ECON Input-Output Model The R/ECON Input-Output Model at the Center for Urban Policy Research at the Bloustein School of Planning and Public Policy was used to measure the economic impacts of the proposed expenditures for the Susquehanna-Roseland network upgrade. The R/ECON model consists of 515 individual sectors of the New Jersey economy and measures the effect of changes in expenditures in one industry on economic activity in all other industries. Thus, the expenditures made on labor, materials, legal and design services, and other inputs for the transmission line have both direct economic effects as those expenditures become incomes and revenues for workers and businesses, and subsequent indirect effects as those workers and businesses, in turn, spend those dollars on other things consumer goods, business investment expenditures, which, in turn, become income for other workers and businesses. This income gets further spent, and so on. In summary, the R/ECON Input-Output model estimates both the direct economic effects of the initial expenditures (in terms of jobs and income) and the indirect (or multiplier) effects (in additional jobs and income) of the subsequent economic activity that occurs following the initial expenditures. The model also estimates the gross domestic product for New Jersey and the tax revenues generated by the combined direct and indirect new economic activity caused by the initial spending. 3

8 Transmission Line and Towers (Monopole Structures) Expenditure Assumptions This estimate of the economic impacts for construction of the transmission line and towers for the Susquehanna-Roseland network assumes that all towers are monopole structures. 1 In order to reflect the full scope of the expenditures included in PSE&G s cost estimates for construction of the transmission line and towers portion of the upgraded network, it was necessary to make several assumptions and adjustments to the various expenditure items included in PSE&G s initial cost estimates. Following is an explanation of this process. PSE&G s estimated total cost for construction of the transmission line and monopole towers is $497.9 million. The base cost of construction estimated by PSE&G for the all-monopole transmission line and towers, including labor, materials, third party professional services and PSE&G support, was $380.4 million, with an additional 11% in estimated inflation costs ( escalation ) and an additional 20% in contingency. In order to incorporate all potential expenditures into the analysis, the escalation (11%) and contingency (20%) estimates were distributed proportionately between the costs of labor and material and the other costs (professional services, PSE&G support, etc.) according to their respective shares of the $380.4 million base cost. In addition, the OH&P on labor (25% of base labor and material costs) and material (10% of base labor and material costs), the Scope Modifications on labor (15% of base labor and material costs) and material (15% of base 1 Scenarios assuming all monopole and all lattice tower structures are presented in the body of the report. A spreadsheet indicating the aggregate impacts of using 50% of each type of tower structure is presented in Appendix C. 4

9 labor and material costs), and the Inefficiencies on labor (18% of base labor and material costs) were also distributed proportionately across the labor and material components of the base construction cost structure. The separate expenditures on labor and materials for the laying of tower foundations were not broken out in PSE&G s cost specifications. For purposes of the analysis, 65% of the $59.4 million in expenditures on foundations was allocated to labor, and the remaining 35% to material. These various adjustments resulted in total allocations of $247.8 million for transmission line construction labor and $171.9 million for material. All direct construction labor was assumed to come from North Jersey. All specialty materials (conductors, insulators, field wire, tower structures, etc.) are assumed to be purchased from outside of New Jersey. As such, of the material expenditures, only the concrete and other material used for construction of the tower foundations was incorporated into the impact estimate. Of the Other Costs (i.e., professional services, PSE&G support, etc.) associated with construction of the transmission line, the costs for consulting services provided by Louis Berger, the cost of soil borings, the costs of appraisals, title and mapping costs, and the costs of PSE&G legal fees were incorporated into the economic impact estimate. These expenditures totaled approximately $8 million. In addition, PSE&G s support costs were allocated according to the shares reflected in the itemized cost breakdowns of PSE&G support in the cost estimates for the two switching stations. All of these costs were incorporated into the economic impact estimate, with the exception of 5

10 Licensing/Permits/Bonds/Builder s Risk. Of this last category, approximately $3.8 million in builder s risk insurance was incorporated into the expenditure estimates. As a result of these assumptions and adjustments, $337.5 million of the total $497.9 million estimate for construction of the transmission line and towers (or 67.8%) was allocated to expenditures on labor, material and services in New Jersey. Economic Impacts Based on the R/Econ Input-Output model, Table 1 lists the estimates of the economic impacts of the expenditures made in New Jersey for construction of the Transmission Line and Towers Table 1 Indicator Direct Indirect Total Multiplier Employment (job-years) 1,600 1,000 2, GDP ($ 000) 256,252 63, , Compensation ($ 000) 206,970 42, , State Tax Revenue ($000) - - 6,943 - Local Tax Revenue ($000) - - 5,332 - As noted in the preceding section, these impacts are based on estimated in-state expenditures on labor, material and services of approximately $337.5 million. They do not reflect the impacts of the remaining $160.4 million in transmission line-related expenditures to be made outside of New Jersey. Explanatory notes for each indicator follow Table 2. Table 2 lists estimates of the total employment generated in New Jersey by the Transmission Line expenditures by business sector. 6

11 Table 2 Sector Employment (job-years) Natural Resources & Mining 16 Construction 1,185 Manufacturing 306 Transportation & Public Utilities 83 Wholesale Trade 101 Retail Trade 276 Financial Activities 159 Services 472 Government 2 Total 2,600 Indicator Explanations: Employment Employment impacts are measured in job-years (i.e., one job lasting one year). The all-monopole transmission line and towers component of the project is estimated to generate a total of 2,600 jobs in New Jersey. Based on salary and benefit estimates for the employment required to upgrade the transmission line, approximately 1,185 direct construction jobs are estimated to be created. Note also from Table 1 that the direct employment associated with the construction of the transmission line (1,600 jobs) exceeds the total construction employment (1,185 jobs) listed in Table 2. The additional direct employment (415 jobs) associated with the project is generated in the New Jersey-based wholesale and manufacturing sectors that produce and distribute the non-specialized materials used in laying foundations, building access roads, etc., as well as the various PSE&G internal functions associated with project management and support, and outside services (e.g., legal) provided by New Jersey firms. Significant additional indirect employment (1,000 jobs, Table 1) is generated across various sectors, including services, financial activities, and retail trade. 7

12 GDP Note that the total GDP generated in the state ($320.1 million, Table 1) is close to the total expenditures estimated for New Jersey. By explicitly excluding those material expenditures that are to be made outside of New Jersey, the model minimizes the economic leakage that would normally be reflected were they to have been included. That is, were the excluded $160.4 million in expenditures to be included, the relative proportion of impacts leaked from the New Jersey economy would be higher. This leakage is reflected in the per-million dollar impacts reported below. Compensation Compensation represents the total wages, salaries and supplements to wages and salaries (i.e., employer contributions to government and private pension funds) paid for all direct and indirect jobs generated as a result of the project expenditures made in New Jersey. The transmission line and monopole towers component is estimated to generate $249.8 million in compensation in New Jersey. State Tax Revenues State tax revenues are comprised of the income taxes associated with the salaries paid to the workers in the direct and indirect jobs associated with the project, and with the sales associated with the economic output generated by the project. The transmission line and monopole towers component is estimated to generate $6.9 million in state tax revenues. Local Tax Revenues The estimates of the increase in local tax revenues are for the entire state. The increase represents a long-run estimate of property tax revenues generated by payment of residential and commercial property taxes from the personal and business incomes generated by the project and/or resulting from improvements 8

13 made to property caused by the increased economic activity generated by the project. Local tax revenues increase because the additional economic activity from the transmission line project generates income for workers and revenues for business 2. The increases in personal incomes and in business revenues are, in part, used to pay property taxes and to improve properties (both residential and commercial). Thus, households benefitting from the additional jobs and resulting incomes acquire and/or improve residential properties, and are able to pay rents and mortgages and the associated property taxes. Similarly, business income and profits also increase as a direct result of higher sales and output caused by the project. Businesses subsequently acquire and/or improve their properties. Historical New Jersey fiscal and economic data are used to measure the relationship between business revenues and the amount of commercial property tax revenues collected, and between household incomes and the amount of residential property tax revenues collected. 3 Given the increases in both household income and the business revenues caused by the expenditures made on the transmission line, the R/ECON Input-Output Model invokes the known statistical relation of local property tax revenues to both household income and business revenues in order to estimate the addition to local tax revenues attributable to the transmission line project. It is important to note that this additional tax revenue occurs over a period of time. It is not an immediately generated impact. The economic sequence is as follows. The additions/improvements to residential and commercial property financed by the higher household incomes and higher business revenues are, in time, captured by higher property assessments, which, in turn, generate higher local tax 2 For businesses, the revenue increase is measured in terms of value-added, and it is the change in valueadded in the business sector that is the basis for the estimated change in property tax revenues. 3 For the entire state, approximately 76% of total local property tax revenues are attributable to residential property; with approximately 21% derived primarily from commercial and industrial property. 9

14 revenues. There are time lags between the increase in incomes and revenues, the improvements to property, and the increase in assessed values. Thus, the local tax revenue impacts estimated in this analysis are the outcome of a long-run adjustment process. This process occurs over the entire state based on the geographical dispersal within New Jersey of the households and businesses that benefit from the expenditures on the transmission line. Table 3 provides the per-million dollar spending impacts for the transmission line. Note that these impacts are calculated per million dollars of total transmission line expenditures that is, on the basis of the $497.9 million to be spent both inside and outside of New Jersey. Table 3 Indicator Impacts per $1 million of total project expenditures Employment (job-years) 5.2 GDP $642,864 Income $501,616 State Tax Revenues $13,944 Local Tax Revenues $10,709 10

15 Transmission Line and Towers (Lattice Structures) Expenditure Assumptions This estimate of the economic impacts for construction of the transmission line and towers for the Susquehanna-Roseland network assumes that all towers are lattice structures. In order to reflect the full scope of the expenditures included in PSE&G s cost estimates for construction of the transmission line and towers portion of the upgraded network, it was necessary to make several assumptions and adjustments to the various expenditure items included in PSE&G s initial cost estimates. Following is an explanation of this process. PSE&G s estimated total cost for construction of the transmission line and lattice towers is $397.1 million. The base cost of construction estimated by PSE&G for the all-lattice transmission line and towers, including labor, materials, third party professional services and PSE&G support, was $303.2 million, with an additional 11% in estimated inflation costs ( escalation ) and an additional 20% in contingency. In order to incorporate all potential expenditures into the analysis, the escalation (11%) and contingency (20%) estimates were distributed proportionately between the costs of labor and material and the other costs (professional services, PSE&G support, etc.) according to their respective shares of the $303.2 million base cost. In addition, the OH&P on labor (25% of base labor and material costs) and material (10% of base labor and material costs), the Scope Modifications on labor (15% of base labor and material costs) and material (15% of base labor and material costs), and the Inefficiencies on labor (18% of base labor and material costs) were also distributed proportionately across the labor and material components of the base construction cost structure. 11

16 The separate expenditures on labor and materials for the laying of tower foundations were not disaggregated in PSE&G s cost specifications. For purposes of the analysis, 65% of the $20.2 million in expenditures on foundations was allocated to labor, and the remaining 35% to material. These various adjustments resulted in total allocations of $239.2 million for transmission line construction labor and $74.4 million for material. All direct construction labor was assumed to come from North Jersey. All specialty materials (conductors, insulators, field wire, tower structures, etc.) are assumed to be purchased from outside of New Jersey. As such, of the material expenditures, only the concrete and other material used for construction of the tower foundations was incorporated into the impact estimate. Of the Other Costs (i.e., professional services, PSE&G support, etc.) associated with construction of the transmission line, the costs for consulting services provided by Louis Berger, the cost of soil borings, the costs of appraisals, title and mapping costs, and the costs of PSE&G legal fees were incorporated into the economic impact estimate. These expenditures totaled approximately $8.1 million. In addition, PSE&G s support costs were allocated according to the shares reflected in the itemized cost breakdowns of PSE&G support in the cost estimates for the two switching stations. All of these costs were incorporated into the economic impact estimate, with the exception of Licensing/Permits/Bonds/Builder s Risk. Of this last category, approximately $3.1 million in builder s risk insurance was incorporated into the expenditure estimates. 12

17 As a result of these assumptions and adjustments, $292.3 million of the total $397.1 million estimate for construction of the transmission line and towers (or 73.6%) was allocated to expenditures on labor, material and services in New Jersey. Economic Impacts Based on the R/ECON Input-Output model, Table 1 lists the estimates of the economic impacts of the expenditures made in New Jersey for construction of the alllattice transmission line and towers Table 1 Indicator Direct Indirect Total Multiplier Employment (job-years) 1, , GDP ($ 000) 233,318 54, , Compensation ($ 000) 186,827 36, , State Tax Revenue ($000) - - 5,932 - Local Tax Revenue ($000) - - 7,329 - As noted in the preceding section, these impacts are based on estimated in-state expenditures on labor, material and services of approximately $292.3 million. They do not reflect the impacts of the remaining $104.8 million in lattice-tower transmission linerelated expenditures to be made outside of New Jersey. Explanatory notes for each indicator follow Table 2. Table 2 lists estimates of the total employment generated in New Jersey by the all-lattice structure transmission line expenditures by business sector. 13

18 Table 2 Sector Employment (job-years) Natural Resources & Mining 7 Construction 996 Manufacturing 155 Transportation & Public Utilities 72 Wholesale Trade 53 Retail Trade 249 Financial Activities 140 Services 412 Government 0 Total 2,084 Indicator Explanations: Employment Employment impacts are measured in job-years (i.e., one job lasting one year). The all-lattice transmission line and towers component of the project is estimated to generate a total of 2,084 jobs in New Jersey. Based on salary and benefit estimates for the employment required to upgrade the transmission line, approximately 996 direct construction jobs are estimated to be created. Note also from Table 1 that the direct employment associated with the construction of the transmission line (1,212 jobs) exceeds the total construction employment (996 jobs) listed in Table 2. The additional direct employment (216 jobs) associated with the project is generated in the New Jersey-based wholesale and manufacturing sectors that produce and distribute the non-specialized materials used in laying foundations, building access roads, etc., as well as the various PSE&G internal functions associated with project management and support, and outside services (e.g., legal) provided by New Jersey firms. Significant additional indirect employment (872 jobs, Table 1) is generated across various sectors, including services, financial activities, and retail trade. 14

19 GDP Note that the total GDP generated in the state ($288.1 million, Table 1) is close to the total expenditures estimated for New Jersey. By explicitly excluding those material expenditures that are to be made outside of New Jersey, the model minimizes the economic leakage that would normally be reflected were they to have been included. That is, were the excluded $104.8 million in expenditures to be included, the relative proportion of impacts leaked from the New Jersey economy would be higher. It is important to note that this leakage is reflected in the per-million dollar impacts reported below. Compensation Compensation represents the total wages, salaries and supplements to wages and salaries (i.e., employer contributions to government and private pension funds) paid for all direct and indirect jobs generated as a result of the project expenditures made in New Jersey. The transmission line and lattice towers component is estimated to generate $223.5 million in compensation in New Jersey. State Tax Revenues State tax revenues are comprised of the income taxes associated with the salaries paid to the workers in the direct and indirect jobs associated with the project, and with the sales associated with the economic output generated by the project. The transmission line and lattice towers component is estimated to generate $5.9 million in state tax revenues. Local Tax Revenues Local tax revenues are comprised of increased property tax revenues resulting from improvements associated with the increased business activity generated by the project. The transmission line and lattice towers component is estimated to generate $7.3 million in local tax revenues. 15

20 Table 3 provides the per-million dollar spending impacts for the transmission line. Note that these impacts are calculated per million dollars of total transmission line expenditures that is, on the basis of the $373.2 million to be spent both inside and outside of New Jersey. Table 3 Indicator Impacts per $1 million of total project expenditures Employment (job-years) 5.2 GDP $725,533 Income $562,797 State Tax Revenues $14,940 Local Tax Revenues $18,457 16

21 East Hanover/Roseland Switching Station Expenditure Assumptions In order to reflect the full range of expenditures incorporated into PSE&G s cost estimates for construction of the East Hanover/Roseland switching station portion of the upgraded Susquehanna-Roseland network, the following assumptions and adjustments were made to the various construction expenditures. The total cost of construction for the East Hanover/Roseland switching station was estimated at $166.6 million, including $125.6 million in base costs and $41 million in contingency. The contingency and escalation (32.6%) estimates were distributed proportionately between the contractor s labor and material costs, the professional services costs, and the PSE&G support costs according to their respective shares of the $125.6 million base cost. Expenditures on transformers, circuit breakers, disconnect switches, and other electronic equipment were assumed to be made outside of New Jersey. All direct construction labor was assumed to come from North Jersey. As a result of these assumptions and adjustments, $57.1 million of the total $166.6 million estimate for construction (or 34.3%) of the East Hanover/Roseland Switching Station, was allocated to expenditures on labor, material and services in New Jersey. 17

22 Economic Impacts Table 1 shows the economic impacts of the East Hanover/Roseland switching station expenditures described above. Table 1 Indicator Direct Indirect Total Multiplier Employment (job-years) GDP ($ 000) 42,267 8,847 51, Compensation ($ 000) 33,822 5,954 39, State Tax Revenue ($000) Local Tax Revenue ($000) - - 1,200 - As noted in the preceding section, these impacts are based on estimated in-state expenditures on labor and material of approximately $57.1 million. They do not reflect the impacts of the remaining $109.5million in expenditures to be made outside of New Jersey. Explanatory notes regarding each indicator follow Table 2. Table 2 shows the total employment generated in New Jersey by the East Hanover/ Roseland switching station expenditures by business sector. 18

23 Table 2 Sector Employment (job-years) Natural Resources & Mining 1 Construction 411 Manufacturing 27 Transportation & Public Utilities 12 Wholesale Trade 9 Retail Trade 29 Financial Activities 23 Services 79 Government 0 Total 592 Employment Employment impacts are measured in job-years (i.e., one job lasting one year). The East Hanover/Roseland switching station portion of the project is estimated to generate a total of 592 jobs in New Jersey. Based on salary and benefit estimates for the employment required to construct the stations, approximately 411 direct construction jobs are estimated to be created. Note also from Table 1 that the direct employment associated with the construction of the switching station (462 jobs) exceeds the total construction employment (411 jobs) listed in Table 2. The additional direct employment (51 jobs) associated with the project is generated in the New Jersey-based wholesale and manufacturing sectors that produce and distribute the non-specialized materials used in laying foundations, building access roads, etc., as well as the various PSE&G internal functions associated with project management and support, and outside services (e.g., legal) provided by New Jersey firms. Significant additional indirect employment (130 jobs, Table 1) is generated across various sectors, including services, financial activities, and retail trade. GDP As with the expenditures on construction of the transmission line, the GDP generated in the state ($51.1 million) is close to the total expenditures estimated for New Jersey due to the exclusion from the model of those material 19

24 expenditures that are to be made outside of New Jersey. The per-million-dollar impacts reported below reflect the impact on New Jersey per million dollars of total expenditures, including those expenditures made outside of the state. Compensation Compensation represents the total wages, salaries and supplements to wages and salaries (i.e., employer contributions to government and private pension funds) paid for all direct and indirect jobs generated as a result of the project expenditures made in New Jersey. The construction of the East Hanover/Roseland switching station is estimated to generate $39.8 million in compensation in New Jersey. State Tax Revenues State tax revenues are comprised of the income taxes associated with the salaries paid to the workers in the direct and indirect jobs associated with the project, and with the sales associated with the economic output generated by the project. The construction of the East Hanover/ Roseland switching station is estimated to generate $.968 million in state tax revenues. Local Tax Revenues Local tax revenues are comprised of increased property tax revenues resulting from improvements associated with the increased business activity generated by the project. The construction of the East Hanover/Roseland switching station is estimated to generate $1.120 million in local tax revenues. Table 3 provides the per-million-dollar spending impacts for the East Hanover/Roseland switching station. Note that these impacts are calculated per million dollars of total expenditures that is, on the basis of the $166.6 million to be spent both inside and outside of New Jersey. 20

25 Table 3 Indicator Impacts per $1 million of total expenditures Employment (job-years) 3.6 GDP 306,785 Compensation 238,730 State Tax Revenues 5,811 Local Tax Revenues 7,202 21

26 Jefferson Switching Station Expenditure Assumptions In order to reflect the full range of expenditures incorporated into PSE&G s cost estimates for construction of the Jefferson switching station portion of the upgraded Susquehanna-Roseland network, it was necessary to make several assumptions and adjustments to the various expenditure items listed for construction of the station. Following is an explanation of this process. The total cost of construction for the East Hanover/Roseland switching station was estimated at $77 million, including $57.8 million in base costs, $6.1 million in escalation costs and $13.1 million in contingency. The escalation (10.5%) and contingency (22.7%) estimates were distributed proportionately between the contractor s labor and material costs. The Professional Services costs and the PSE&G Support costs were distributed according to their respective shares of the $57.8 million base cost. The Scope Assessment and Fees on the labor portion of the contractor s costs (34% of base costs) were combined with the labor costs. Expenditures on circuit breakers, disconnect switches, and third party professional services were assumed to be made outside of New Jersey. Of the approximately $6.5 million in bulk material expenditures, 60% was assumed to be electrical material, and 40% civil material, with 90% of the electrical bulk being purchased outside New Jersey. The majority of civil bulk material associated with site work, access roads, foundations, etc., was assumed to be purchased in New Jersey. 22

27 All direct construction labor was assumed to come from North Jersey. As a result of these assumptions and adjustments, $62.1 million of the total $77 million estimate for construction (or 80.5%) of the Jefferson Switching Station was allocated to expenditures on labor, services and material in New Jersey. Economic Impacts Table 1 shows the economic impacts of the Jefferson Switching Station expenditures described above. Table 1 Indicator Direct Indirect Total Multiplier Employment (job-years) GDP ($ 000) 47,145 9,784 56, Compensation ($ 000) 37,654 6,574 44, State Tax Revenue ($000) - - 1,080 - Local Tax Revenue ($000) - - 1,333 - As noted in the preceding section, these impacts are based on estimated in-state expenditures on labor and material of approximately $62.1 million. They do not reflect the impacts of the remaining $14.9 million in expenditures to be made outside of New Jersey. Explanatory notes regarding each indicator follow Table 2. Table 2 shows the total employment generated in New Jersey by the Jefferson Switching Station expenditures by business sector. 23

28 Table 2 Sector Employment (job-years) Natural Resources & Mining 1 Construction 538 Manufacturing 26 Transportation & Public Utilities 12 Wholesale Trade 10 Retail Trade 47 Financial Activities 24 Services 80 Government 0 Total 739 Employment Employment impacts are measured in job-years (i.e., one job lasting one year). The Jefferson Switching Station of the project is estimated to generate a total of 739 jobs in New Jersey. Based on salary and benefit estimates for the employment required to construct the stations, approximately 538 direct construction jobs are estimated to be created. Note also from Table 1 that the direct employment associated with the construction of the Switching Stations (584 jobs) exceeds the total construction employment (538 jobs) listed in Table 2. The additional direct employment (46 jobs) associated with the project is generated in the New Jersey-based wholesale and manufacturing sectors that produce and distribute the non-specialized materials used in laying foundations, building access roads, etc., as well as the various PSE&G internal functions associated with project management and support, and outside services (e.g., legal) provided by New Jersey firms. Significant additional indirect employment (154 jobs, Table 1) is generated across various sectors, including services, financial activities, and retail trade. GDP As with the expenditures on construction of the transmission line, the GDP generated in the state ($56.9 million) is close to the total expenditures estimated for New Jersey due to the exclusion from the model of those material 24

29 expenditures that are to be made outside of New Jersey. The per-million-dollar impacts reported below reflect the impact on New Jersey per million dollars of total expenditures, including those expenditures made outside of the state. Compensation Compensation represents the total wages, salaries and supplements to wages and salaries (i.e., employer contributions to government and private pension funds) paid for all direct and indirect jobs generated as a result of the project expenditures made in New Jersey. The construction of the Jefferson Switching Station is estimated to generate $44.2 million in compensation in New Jersey. State Tax Revenues State tax revenues are comprised of the income taxes associated with the salaries paid to the workers in the direct and indirect jobs associated with the project, and with the sales associated with the economic output generated by the project. The construction of the Jefferson Switching Station is estimated to generate $1.1 million in state tax revenues. Local Tax Revenues Local tax revenues are comprised of increased property tax revenues resulting from improvements associated with the increased business activity generated by the project. The construction of the Jefferson Switching Station is estimated to generate $1.3 million in local tax revenues. Table 3 provides the per-million-dollar spending impacts for the Jefferson Switching Station. Note that these impacts are calculated per million dollars of total transmission line expenditures that is, on the basis of the $77 million to be spent both inside and outside of New Jersey. 25

30 Table 3 Indicator Impacts per $1 million of total expenditures Employment (job-years) 9.6 GDP $739,340 Compensation $574,392 State Tax Revenues $14,022 Local Tax Revenues $17,315 Note that these per-million-dollar impacts are significantly higher than those of the East Hanover and Roseland stations. This is largely due to the fact that $70 million dollars of expenditures on transformers and circuit breakers for the East Hanover and Roseland stations is assumed to be spent out of state, while there are no comparable expenditures for the Jefferson switching station. Thus, there is less economic leakage assumed as a proportion of the total costs of construction. 26

31 Combined Economic Impacts (Monopole Towers) Following are the combined impacts for all components of the project, including the transmission line and towers (assuming monopole towers) and all switching stations. Table 1 shows the aggregate economic impacts of the entire $741.5 million construction project (the total project budget is $750 million when the management reserve is included). The total expenditures estimated to be made in New Jersey are $497.9 million (or 66.1%) Table 1 Indicator Direct Indirect Total Multiplier Employment (job-years) 2,646 1,284 3, GDP ($ 000) 345,664 82, , Compensation ($ 000) 278,446 55, , State Tax Revenue ($000) - - 8,991 - Local Tax Revenue ($000) - - 7,865 - As noted in the preceding section, these impacts are based on estimated in-state expenditures on labor and material of approximately $456.7 million. They do not reflect the impacts of the remaining $284.8 million in expenditures to be made outside of New Jersey or the $8.5 million management reserve. Explanatory notes regarding each indicator follow Table 2. Table 2 shows the total employment generated in New Jersey by the total combined project expenditures. Table 2 Sector Employment (job-years) Natural Resources & Mining 18 Construction 2,134 Manufacturing 359 Transportation & Public Utilities 107 Wholesale Trade 120 Retail Trade 352 Financial Activities 206 Services 631 Government 2 Total 3,931 27

32 Employment Total employment generated by the project is estimated at 3,931 jobs, with the majority of those jobs occurring in the construction industry (2,143 jobs). Other sectors with large direct and indirect job gains include the aggregate services sector (631 jobs), the retail trade sector (352 jobs), and the manufacturing sector (359 jobs). GDP The GDP generated in the state ($428.1 million) is close to the total expenditures estimated for New Jersey due to the exclusion from the model of those material expenditures that are to be made outside of New Jersey. The per-million-dollar impacts reported below reflect the impact on New Jersey per million dollars of total expenditures, including those expenditures made outside of the state. Compensation Compensation represents the total wages, salaries and supplements to wages and salaries (i.e., employer contributions to government and private pension funds) paid for all direct and indirect jobs generated as a result of the project expenditures made in New Jersey. The project is estimated to generate $333.8 million in compensation in New Jersey. State Tax Revenues State tax revenues are comprised of the income taxes associated with the salaries paid to the workers in the direct and indirect jobs associated with the project, and with the sales taxes associated with the economic output generated by the project. The project is estimated to generate $9 million in state tax revenues. Local Tax Revenues Local tax revenues are comprised of increased property tax revenues that are generated over time because of property improvements associated with the increased business activity generated by the project. The value of these property 28

33 improvements is, in time, included in assessments and hence in property tax revenues. The project is estimated to generate $7.9 million in local tax revenues. Table 3 provides the per-million-dollar spending impacts for the full project. Note that these impacts are calculated per million dollars of total expenditures that is, on the basis of the $741.5 million to be spent both inside and outside of New Jersey and including the additional $8.5 million management reserve. Table 3 Indicator Impacts per $1 million of total expenditures Employment (job-years) 5.2 GDP $570,829 Compensation $445,007 State Tax Revenues $11,988 Local Tax Revenues $10,487 29

34 Combined Economic Impacts (Lattice Towers) Following are the combined impacts for all components of the project, including the transmission line and towers (assuming lattice towers) and all switching stations. Table 1 shows the aggregate economic impacts of the entire $640.7 million construction project (the total project budget is $649.2 million when the management reserve is included). The total expenditures estimated to be made in New Jersey are $411.5 million (or 64.2%) Table 1 Indicator Direct Indirect Total Multiplier Employment (job-years) 2,258 1,156 3, GDP ($ 000) 322,730 73, , Compensation ($ 000) 258,303 49, , State Tax Revenue ($000) - - 7,980 - Local Tax Revenue ($000) - - 9,862 - As noted previously, these impacts are based on estimated in-state expenditures on labor and material of approximately $411.5 million. They do not reflect the impacts of the remaining $229.2 million in expenditures to be made outside of New Jersey. Explanatory notes regarding each indicator follow Table 2. Table 2 shows the total employment generated in New Jersey by the total combined project expenditures. Table 2 Sector Employment (job-years) Natural Resources & Mining 9 Construction 1,945 Manufacturing 208 Transportation & Public Utilities 96 Wholesale Trade 72 Retail Trade 325 Financial Activities 187 Services 571 Government 0 Total 3,415 30

35 Employment Total employment generated by the project is estimated at 3,415 jobs, with the majority of those generated in the construction industry (1,945 jobs). Other sectors with large direct and indirect job gains include the aggregate services sector (571 jobs), the retail trade sector (325 jobs), and the manufacturing sector (208 jobs). GDP The GDP generated in the state ($396.1 million) is close to the total expenditures estimated for New Jersey due to the exclusion from the model of those material expenditures that are to be made outside of New Jersey. The per-million-dollar impacts reported below reflect the impact on New Jersey per million dollars of total expenditures, including those expenditures made outside of the state. Compensation Compensation represents the total wages, salaries and supplements to wages and salaries (i.e., employer contributions to government and private pension funds) paid for all direct and indirect jobs generated as a result of the project expenditures made in New Jersey. The project is estimated to generate $307.5 million in compensation in New Jersey. State Tax Revenues State tax revenues are comprised of the income taxes associated with the salaries paid to the workers in the direct and indirect jobs associated with the project, and with the sales taxes associated with the economic output generated by the project. The project is estimated to generate $8 million in state tax revenues. Local Tax Revenues Local tax revenues are comprised of increased property tax revenues that are generated over time because of the improvements associated with the increased business activity generated by the project. The value of these improvements is, in 31

36 time, included in assessments and hence in property taxes. The project is estimated to generate $9.9 million in local tax revenues. Table 3 provides the per-million-dollar spending impacts for the full project, assuming all lattice tower structures are used for the transmission line. Note that these impacts are calculated per million dollars of total expenditures that is, on the basis of the $640.7 million to be spent both inside and outside of New Jersey and including the additional $8.5 million management reserve. Table 3 Indicator Impacts per $1 million of total expenditures Employment (job-years) 5.3 GDP $610,220 Compensation $473,639 State Tax Revenues $12,292 Local Tax Revenues $15,191 32

37 CONCLUSION This report presents an economic impact analysis of the proposed upgrade of PSE&G s Susquehanna-Roseland transmission network. Using the Edward J. Bloustein School s R/ECON Input-Output model, impact estimates were generated for construction of two switching stations and the transmission line and towers, including separate analyses for two different types of tower. Based on the proposed employment and other project expenditures to be made in New Jersey, we estimate that the $649.2 million (all lattice towers) to $750 million (all monopole towers) in project expenditures ($425.2 million to $467.7 million to be made in New Jersey), including management reserves, will generate: between 3,415 (lattice) and 3,931 (monopole) job-years for workers in New Jersey; between $396.1 million (lattice ) and $428.1 million (monopole) in gross domestic product for the state; between $307.5 million (lattice) and $333.8 million in compensation for workers in the jobs generated by the project in New Jersey; between $8 million (lattice) and $9 million (monopole) in state taxes; and between $7.9 million (monopole) and $9.9 million (lattice) in local taxes. 33

Contribution of the Life Sciences Industry to the New Jersey Economy

Contribution of the Life Sciences Industry to the New Jersey Economy Contribution of the Life Sciences Industry to the New Jersey Economy Submitted to: Debbie Hart President, BioNJ This study was supported by a research contract with BioNJ. June 2014 Joseph J. Seneca, Michael

More information

APPENDIX 7.0-B BC Stats BC Input - Output Model Report

APPENDIX 7.0-B BC Stats BC Input - Output Model Report KITSAULT MINE PROJECT ENVIRONMENTAL ASSESSMENT APPENDICES APPENDIX 7.0-B BC Stats BC Input - Output Model Report VE51988 Appendices KITSAULT MINE PROJECT ENVIRONMENTAL ASSESSMENT - APPENDICES BC INPUT-OUTPUT

More information

September The Economic Impact of the Atlantic Coast Pipeline in West Virginia, Virginia, and North Carolina. Prepared for. Dominion Resources

September The Economic Impact of the Atlantic Coast Pipeline in West Virginia, Virginia, and North Carolina. Prepared for. Dominion Resources September 2014 The Economic Impact of the Atlantic Coast Pipeline in West Virginia, Virginia, and North Carolina The one-time construction activity of the Atlantic Coast Pipeline can inject an annual average

More information

Economic Impact of the Commercial Construction Industry on the Economy of the State of Alabama

Economic Impact of the Commercial Construction Industry on the Economy of the State of Alabama Economic Impact of the Commercial Construction Industry on the Economy of the State of Alabama Prepared by: M. Keivan Deravi, Ph.D. Dean & Professor of Economics Auburn University at Montgomery May 2017

More information

Economic impact of NHS spending in the Black Country. 21 July 2017

Economic impact of NHS spending in the Black Country. 21 July 2017 Economic impact of NHS spending in the Black Country 21 July 2017 Economic impact of NHS spending in the Black Country Final report A report submitted by ICF Consulting Limited Date: 21 July 2017 Job Number

More information

Pacific Gas and Electric Company. Statement of Estimated Cash Flows April 20, 2001

Pacific Gas and Electric Company. Statement of Estimated Cash Flows April 20, 2001 Pacific Gas and Electric Company Statement of Estimated Cash Flows April 20, 2001 This document provides the latest forecast of cash flows for Pacific Gas and Electric Company (the Company ). The purpose

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS 1. Purpose This rule establishes procedures and defines respective cost responsibilities to provide a Line Extension to a builder, developer,

More information

Economic Benefits of the Proposed Casa Diablo Geothermal Power Plant, Wahlstrom & Associates 2012

Economic Benefits of the Proposed Casa Diablo Geothermal Power Plant, Wahlstrom & Associates 2012 Appendix G Comment Letters ATTACHMENT G2 Economic Benefits of the Proposed Casa Diablo Geothermal Power Plant, Wahlstrom & Associates 2012 This exhibit contains an economic benefit report provided by the

More information

Tax Code Connections: How Changes to Federal Policy Affect State Revenue Technical appendix

Tax Code Connections: How Changes to Federal Policy Affect State Revenue Technical appendix A methodology from Feb 2016 Tax Code Connections: How Changes to Federal Policy Affect State Revenue Technical appendix Overview of the tax model The tax model used in this analysis calculates both federal

More information

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) This Standard contains the requirements, in addition to applicable

More information

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) :

The following Information Requests pertain to the spreadsheet file Attachment_H- 1_Formula_Rate_2015_-Run_1_posted_ _(effective_ ) : TGST 1-1: Refer to PNM S 2014 FERC Form 1 page 207, line 50, Account 353 Station Equipment, please provide a description of significant projects ($5 million or more) contributing to the increase of approximately

More information

ASSET RISK MANAGEMENT Asset Health Framework

ASSET RISK MANAGEMENT Asset Health Framework ASSET RISK MANAGEMENT Asset Health Framework 15 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D Preface This document has been prepared to

More information

Cost Estimation for Regional Transmission Overlay Study (RTOS)

Cost Estimation for Regional Transmission Overlay Study (RTOS) Cost Estimation for Regional Transmission Overlay Study (RTOS) Purpose & Key Takeaways Purpose: To provide detail for MISO s cost estimation approach Key Takeaways: Planning-Level and Scoping-Level MISO

More information

Economic Impact Assessment Nova Scotia Highway Construction Program

Economic Impact Assessment Nova Scotia Highway Construction Program Economic Impact Assessment Nova Scotia Highway Construction Program Prepared by: Canmac Economics Limited Prepared for: Nova Scotia Road Builders Association June, 2016 Contents Executive Summary... 3

More information

Economic Impacts of Oregon Energy Tax Credit Programs in 2006 (BETC/RETC) Final Report

Economic Impacts of Oregon Energy Tax Credit Programs in 2006 (BETC/RETC) Final Report Economic Impacts of Oregon Energy Tax Credit Programs in 2006 (BETC/RETC) Final Report ECONOMICS FINANCE PLANNING 888 SW Fifth Avenue, Suite 1460 Portland, Oregon 97204 503-222-6060 May 30, 2007 Acknowledgements

More information

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 63 SOUTH CAROLINA Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition

More information

Cautionary Statements and Factors That May Affect Future Results

Cautionary Statements and Factors That May Affect Future Results Cautionary Statements and Factors That May Affect Future Results Any statements made in this presentation about future operating results or other future events are forward looking statements under the

More information

South Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard)

South Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard) South Carolina Standard for Interconnecting Small Generation 100 kw or Less With Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition

More information

Revised Cal. P.U.C. Sheet No E Cancelling Original Cal. P.U.C. Sheet No E. ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS

Revised Cal. P.U.C. Sheet No E Cancelling Original Cal. P.U.C. Sheet No E. ELECTRIC RULE NO. 15 Sheet 1 DISTRIBUTION LINE EXTENSIONS Revised Cal. P.U.C. Sheet No. 20093-E Cancelling Original Cal. P.U.C. Sheet No. 15575-E ELECTRIC RULE NO. 15 Sheet 1 APPLICABILITY: This rule is applicable to extension of electric Distribution Lines*

More information

The Economic Impact of the Constitution Pipeline

The Economic Impact of the Constitution Pipeline The Economic Impact of the Constitution Pipeline June, 2013 The Economic Impact of the Constitution Pipeline June, 2013 Prepared for: Constitution Pipeline, LLC Prepared By: Kent Gardner, Ph.D. Scott Sittig,

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an

More information

Economic Impact Assessment Study Ontario Rental Housing Sector

Economic Impact Assessment Study Ontario Rental Housing Sector Economic Impact Assessment Study Ontario Rental Housing Sector December 2013 Federation of Rental Housing Providers of Ontario KPMG Canada kpmg.ca Table of Contents 1. Executive Summary 1 2. Introduction

More information

2016 HERNANDO COUNTY SCHOOL DISTRICT ECONOMIC IMPACT STUDY

2016 HERNANDO COUNTY SCHOOL DISTRICT ECONOMIC IMPACT STUDY 2016 HERNANDO COUNTY SCHOOL DISTRICT ECONOMIC IMPACT STUDY Tampa Bay Regional Planning Council Economic Analysis Program Authors Randy Deshazo Principal Economic Planner Avera Wynne Planning Director Contact

More information

SSE s Economic Contribution to the UK, Scotland, and the Republic of Ireland Financial Year 2014/15

SSE s Economic Contribution to the UK, Scotland, and the Republic of Ireland Financial Year 2014/15 www.pwc.co.uk/sustainability SSE s Economic Contribution to the UK, Scotland, and the Republic of Ireland Financial Year 2014/15 June 2016 Contents 1 Introduction 2 2 SSE s contribution to UK GDP and employment

More information

XXXXX. Skookum Creek Power Project. Interconnection Facilities Study and Project Plan

XXXXX. Skookum Creek Power Project. Interconnection Facilities Study and Project Plan XXXXX Skookum Creek Power Project Interconnection Facilities Study and Project Plan June 29, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights

More information

The Economic Impact of Aged Care Facilities in New Zealand

The Economic Impact of Aged Care Facilities in New Zealand Final Report 23 June 2011 The Economic Impact of Aged Care Facilities in New Zealand Prepared for NZ Aged Care Association Authorship This document was written by Fraser Colegrave Fraser.colegrave@covec.co.nz

More information

Accounting Documents. For the year ended 31 December Sure (Guernsey) Limited

Accounting Documents. For the year ended 31 December Sure (Guernsey) Limited For the year ended 31 December 2014 Sure (Guernsey) Limited Introduction... i 1. Regulatory Accounting Principles... 1 2. Businesses... 2 3. Attribution Methods... 5 3.1 Introduction... 5 3.2 Attribution

More information

T-D Interconnections: Best Value Planning White Paper January 2016

T-D Interconnections: Best Value Planning White Paper January 2016 T-D Interconnections: Best Value Planning White Paper Updated January 2016 1. Purpose This paper defines the process and criteria that together constitute joint best value planning (BVP) between ATC and

More information

SSE s Economic Contribution to the UK, Scotland and the Republic of Ireland FY18 Results

SSE s Economic Contribution to the UK, Scotland and the Republic of Ireland FY18 Results May 2018 www.pwc.co.uk SSE s Economic Contribution to the UK, Scotland and the Republic of Ireland FY18 Results Context, key notes and assumptions 2 Context and use of this data Context SSE plc ( SSE )

More information

Economic Impacts of Wind Energy Development in Iowa: Four Scenarios

Economic Impacts of Wind Energy Development in Iowa: Four Scenarios Economic Impacts of Wind Energy Development in Iowa: Four Scenarios Dave Swenson 1 Department of Economics Iowa State University June, 2015 Introduction The deployment of additional wind energy capacity

More information

CAPE HATTERAS ELECTRIC COOPERATIVE

CAPE HATTERAS ELECTRIC COOPERATIVE CAPE HATTERAS ELECTRIC COOPERATIVE INTERCONNECTION STANDARD STANDARD FOR INTERCONNECTING SMALL GENERATION 100 kw OR LESS 1. Definitions: 1.1 Area EPS: Area Electric Power System: The electric facilities

More information

Final Report. An Analysis of the Economic Impacts Associated With the Kami Iron Ore Project: A 8 Mtpa, 26 Year Project

Final Report. An Analysis of the Economic Impacts Associated With the Kami Iron Ore Project: A 8 Mtpa, 26 Year Project Final Report An Analysis of the Economic Impacts Associated With the Kami Iron Ore Project: A 8 Mtpa, 26 Year Project Prepared for: Prepared by: Dr. Wade Locke And Strategic Concepts, Inc. November 25,

More information

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION PECO ENERGY COMPANY STATEMENT NO. BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION DOCKET NO. R-01-0001 DIRECT TESTIMONY

More information

Interconnection Standards Solar Policy Survey January 2017

Interconnection Standards Solar Policy Survey January 2017 Interconnection Standards Solar Policy Survey January 2017 The NESEMC Solar Policy Survey compiles information on state-level policies that significantly influence the solar energy market. The survey was

More information

Public Utility District #1 of Ferry County Budget. December 19, 2016

Public Utility District #1 of Ferry County Budget. December 19, 2016 Public Utility District #1 of Ferry County 2017 Budget December 19, 2016 The Approved Budget for 2017 is $7,688,400 which reflects an overall decrease of 3.86% from the 2016 Budget; this is a reduction

More information

Appendix 1-2. Conference Board of Canada Report (October 2015)

Appendix 1-2. Conference Board of Canada Report (October 2015) CA PDF Page 1 of 64 Energy East Pipeline Ltd. TransCanada PipeLines Limited Consolidated Application Volume 1: Energy East Project and Asset Transfer Applications Appendix 1-2 Conference Board of Canada

More information

THE ECONOMIC IMPACTS OF THE OIL AND NATURAL GAS INDUSTRY ON THE U.S. ECONOMY IN 2009: EMPLOYMENT, LABOR INCOME, AND VALUE ADDED

THE ECONOMIC IMPACTS OF THE OIL AND NATURAL GAS INDUSTRY ON THE U.S. ECONOMY IN 2009: EMPLOYMENT, LABOR INCOME, AND VALUE ADDED www.pwc.com/us/nes THE ECONOMIC IMPACTS OF THE OIL AND NATURAL GAS INDUSTRY ON THE U.S. ECONOMY IN 2009: EMPLOYMENT, LABOR INCOME, AND VALUE ADDED May 2011 Prepared for American Petroleum Institute The

More information

Economic Impact Analysis of Fort Steele National Heritage Town. Final Report. By:

Economic Impact Analysis of Fort Steele National Heritage Town. Final Report. By: Economic Impact Analysis of Fort Steele National Heritage Town Final Report By: The Canadian Tourism Research Institute The Conference Board of Canada April 30, 2008 WHAT'S INSIDE This study reports on

More information

Project Coordination and Path Rating

Project Coordination and Path Rating Document name Category Project Coordination, Path Rating and Progress Report Processes ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter Document

More information

The economic impact of the UK Maritime Services Sector

The economic impact of the UK Maritime Services Sector The economic impact of the UK Maritime Services Sector A Report for Maritime UK (including regional breakdown) February 2013 Contents 1 Executive summary...2 2 Introduction...5 2.1 The channels of economic

More information

Economic Impact & Job Creation relative to Large-Scale, High Voltage Transmission Infrastructure

Economic Impact & Job Creation relative to Large-Scale, High Voltage Transmission Infrastructure Economic Impact & Job Creation relative to Large-Scale, High Voltage Transmission Infrastructure Dave Swenson Department of Economics Iowa State University July, 2018 Acknowledgements Special thanks to

More information

SCHEDULE SGI : SMALL GENERATOR INTERCONNECTIONS OTHER THAN NET METERING

SCHEDULE SGI : SMALL GENERATOR INTERCONNECTIONS OTHER THAN NET METERING ~A BARC ELECTRIC COOPERATIVE SCHEDULE SGI : SMALL GENERATOR INTERCONNECTIONS OTHER THAN NET METERING A. APPLICABILITY This Schedule SGI is applicable to Interconnection Customers who own and operate, or

More information

THE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer

THE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer THE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer EXECUTIVE SUMMARY Purpose and Conclusions of the Study This report presents the results of an investigative

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Al Rothbauer 321S Substation And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities Commission Act, S.A.

More information

November 16, Ms. Donna Mitchell, CPA Controller/Treasurer City of Dover 5 East Reed Street Weyandt Hall, Suite 300 Dover, Delaware 19901

November 16, Ms. Donna Mitchell, CPA Controller/Treasurer City of Dover 5 East Reed Street Weyandt Hall, Suite 300 Dover, Delaware 19901 Ms. Donna Mitchell, CPA Controller/Treasurer 5 East Reed Street Weyandt Hall, Suite 300 Dover, Delaware 19901 Re: 2015 Electric Cost-of-Service and Rate Design Study Update Project Number 84122 Dear Ms.

More information

Independent Review of Aurora Network summary of findings. Michael Van Doornik, Manager Advisory (VIC) 31 October 2018

Independent Review of Aurora Network summary of findings. Michael Van Doornik, Manager Advisory (VIC) 31 October 2018 Independent Review of Aurora Network summary of findings Michael Van Doornik, Manager Advisory (VIC) 31 October 2018 Agenda 1. Terms of reference 2. Limitations of the review 3. Our approach to undertaking

More information

CRE Loan Concentrations in 2017: What You Need To Know

CRE Loan Concentrations in 2017: What You Need To Know CRE Loan Concentrations in 2017: What You Need To Know NEW JERSEY BANKERS ASSOCIATION 113 th Annual Conference The Breakers, Palm Beach, FL May 17-21, 2017 Michael T. Rave Partner Day Pitney LLP mrave@daypitney.com

More information

Distribution of Crossrail Benefits. 1 delivering a world-class, affordable railway

Distribution of Crossrail Benefits. 1 delivering a world-class, affordable railway Distribution of Crossrail Benefits 1 Crossrail Benefits Crossrail delivers: A robust Economic Appraisal approved by DfT (Benefit Cost Ratio = 2)* Wider Economic Benefits (WEBs) worth around 15bn The following

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- A SCE-0, Vol. 0 R A E. Takayesu (U -E) 01 General Rate Case rd Errata ERRATA Transmission & Distribution (T&D) Volume R System Planning Before the Public

More information

Economic Impact Analysis of Physicians Offices in New Jersey. Submitted to: Medical Society of New Jersey. May 2011

Economic Impact Analysis of Physicians Offices in New Jersey. Submitted to: Medical Society of New Jersey. May 2011 Economic Impact Analysis of Physicians Offices in New Jersey Submitted to: Medical Society of New Jersey May 2011 Dr. Joseph J. Seneca Dr. Michael L. Lahr Will Irving Julia Friedman Table of Contents EXECUTIVE

More information

THE NARRAGANSETT ELECTRIC COMPANY POLICY 1 LINE EXTENSION POLICY FOR INDIVIDUAL RESIDENTIAL CUSTOMERS

THE NARRAGANSETT ELECTRIC COMPANY POLICY 1 LINE EXTENSION POLICY FOR INDIVIDUAL RESIDENTIAL CUSTOMERS THE NARRAGANSETT ELECTRIC COMPANY POLICY 1 LINE EXTENSION POLICY FOR INDIVIDUAL RESIDENTIAL CUSTOMERS When an individual residential customer ( Customer ) requests that a distribution line be extended

More information

Loudoun 2040 Fiscal Impact Analysis Report Loudoun County, Virginia

Loudoun 2040 Fiscal Impact Analysis Report Loudoun County, Virginia Loudoun 2040 Fiscal Impact Analysis Report Loudoun County, Virginia Submitted to: Loudoun County, Virginia July 6, 2018 4701 Sangamore Road Suite S240 Bethesda, Maryland 20816 800.424.4318 www.tischlerbise.com

More information

Multipliers: User s guide

Multipliers: User s guide Federal Planning Bureau Economic analyses and forecasts Multipliers: User s guide Final demand multipliers are a standard application of Leontief s traditional input output model. They measure the response

More information

Public Utility District #1 of Ferry County Budget. December 17, 2018

Public Utility District #1 of Ferry County Budget. December 17, 2018 Public Utility District #1 of Ferry County 2019 Budget December 17, 2018 The Approved Budget for 2019 reflects an overall reduction of approximately 3.2 percent from the 2018 Budget. The District is predicting

More information

Economic Impact of Tennessee HOUSE Grants

Economic Impact of Tennessee HOUSE Grants I. Introduction Economic Impact of Tennessee HOUSE Grants Overview. The HOUSE (Housing Opportunities Using State Encouragement) program was a State funded program administered by the Tennessee Housing

More information

ROCKLAND ELECTRIC COMPANY B.P.U. NO. 3 - ELECTRICITY. 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 GENERAL INFORMATION

ROCKLAND ELECTRIC COMPANY B.P.U. NO. 3 - ELECTRICITY. 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 GENERAL INFORMATION 1st Revised Leaf No. 18 Superseding Original Leaf No. 18 No. 15 IDENTIFICATION OF EMPLOYEES Company employees or agents authorized to enter upon its customers premises are provided with photo identification

More information

THE ECONOMIC IMPACTS OF THE OIL AND NATURAL GAS INDUSTRY ON THE U.S. ECONOMY: EMPLOYMENT, LABOR INCOME AND VALUE ADDED

THE ECONOMIC IMPACTS OF THE OIL AND NATURAL GAS INDUSTRY ON THE U.S. ECONOMY: EMPLOYMENT, LABOR INCOME AND VALUE ADDED THE ECONOMIC IMPACTS OF THE OIL AND NATURAL GAS INDUSTRY ON THE U.S. ECONOMY: EMPLOYMENT, LABOR INCOME AND VALUE ADDED Prepared for American Petroleum Institute September 8, 2009 National Economics & Statistics

More information

Alberta Utilities Commission

Alberta Utilities Commission Alberta Utilities Commission In the Matter of the Need for the Grizzly Bear Creek Wind Power Plant Connection And in the matter of the Electric Utilities Act, S.A. 2003, c. E-5.1, the Alberta Utilities

More information

Ohio Ethanol Producers Association

Ohio Ethanol Producers Association Economic Impact Analysis of the Ethanol Industry in Ohio for the Ohio Ethanol Producers Association October 2012 Prepared by: Greg Davis, Ph.D. Professor Nancy Bowen, CEcD Field Specialist Ohio State University

More information

The Economic Impact of Legal Aid Services in the State of Florida. Florida TaxWatch February 2010

The Economic Impact of Legal Aid Services in the State of Florida. Florida TaxWatch February 2010 The Economic Impact of Legal Aid Services in the State of Florida Florida TaxWatch February 2010 Contents I. Executive Summary... 3 II. Introduction... 6 III. The Economic Impact of 2008 Legal Aid Services

More information

Nelson Electricity Ltd Asset Management Plan Update

Nelson Electricity Ltd Asset Management Plan Update Nelson Electricity Ltd Asset Management Plan Update April 2017 March 2027 April 2017 Nelson Electricity Ltd central Nelson city view In accordance with the Commerce Act Electricity Distribution Information

More information

Better Buildings Neighborhood Program: An Economic Impact Analysis of a Whole-Building Retrofit Program

Better Buildings Neighborhood Program: An Economic Impact Analysis of a Whole-Building Retrofit Program Better Buildings Neighborhood Program: An Economic Impact Analysis of a Whole-Building Retrofit Program Matthew Koson, Evergreen Economics, Portland, OR Stephen Grover, Evergreen Economics, Portland, OR

More information

Calculating the economic contribution of Beatrice Offshore Windfarm Limited

Calculating the economic contribution of Beatrice Offshore Windfarm Limited Calculating the economic contribution of Beatrice Offshore Windfarm Limited Methodology document Contents Background... 2 Input-Output Model methodology... 3 Direct, indirect and induced impacts... 3 Gross

More information

Cost Allocation Method

Cost Allocation Method Cost Allocation Method November 2013 Expenditure Forecasting Methods casting approach Contents 1. Background 3 2. Nature, Scope and Purpose 4 3. Responsibility for the Cost Allocation Method 5 4. Corporate

More information

A New Construction Price Comparison Methodology for. The International Comparison Program: Concept Note

A New Construction Price Comparison Methodology for. The International Comparison Program: Concept Note Public Disclosure Authorized I n t e r n a t i o n a l C o m p a r i s o n P r o g r a m Public Disclosure Authorized Public Disclosure Authorized A New Construction Price Comparison Methodology for The

More information

PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP TRANSMISSION

PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP TRANSMISSION PROPOSAL FOR COST ESTIMATION REVIEW PROCESS FOR SPP REGIONALLY FUNDED TRANSMISSION Presented on behalf of SPP s Transmission Owners SPP Strategic Planning Committee Meeting December 3, 2010 REGIONALLY

More information

A. INTRODUCTION B. METHODOLOGY

A. INTRODUCTION B. METHODOLOGY Chapter 14: Economic Conditions A. INTRODUCTION This chapter evaluates potential effects that the Proposed Project may have on economic conditions. The chapter provides a profile of the current population

More information

SOLAR PV INSTALLATION AT USC BASEBALL STADIUM

SOLAR PV INSTALLATION AT USC BASEBALL STADIUM AMENDMENT NO. 7 TO SOLICITATION TO: ALL VENDORS FROM: Charles Johnson, Procurement Manager SUBJECT: SOLICITATION NUMBER: USC-RFP-1761-CJ SOLAR PV INSTALLATION AT USC BASEBALL STADIUM DATE: June 30, 2010

More information

SP Transmission successfully fast-tracked

SP Transmission successfully fast-tracked 2 RIIO-T1 Transmission Price Control January 2012 SP Transmission successfully fast-tracked SP Transmission is pleased to announce that it has reached agreement with the Government energy regulator Ofgem

More information

TECHNICAL PAPER PRESENTATION

TECHNICAL PAPER PRESENTATION 1 W E L C O M E T O C O M E T 2 0 1 7 TECHNICAL PAPER PRESENTATION 2 ASSET MANAGEMENT ANALYTICS FOR A SUSTAINABLE GRID BY QASIM AZIZ P.E., & GAUTAM SONDE A B O U T T H E A U T H O R S C O M E T 2 0 1 7

More information

Otahuhu Sub-Station Conference. Graeme Everett 23 rd July 2007

Otahuhu Sub-Station Conference. Graeme Everett 23 rd July 2007 Otahuhu Sub-Station Conference Graeme Everett 23 rd July 2007 The World of Norske Skog Europe - 100% Skogn Follum Union Saubrugs Parenco Walsum Steti Golbey Bruck Chongwon Hebei Chonju Pan Asia - 100%

More information

TRANSMISSION TARIFF METHODOLOGY FOR THE WEST AFRICAN POWER POOL

TRANSMISSION TARIFF METHODOLOGY FOR THE WEST AFRICAN POWER POOL AUTHORIDADE REGIONAL REGULADORA DE ELETRICIDADE DA CEDEAO ECOWAS REGIONAL ELECTRICITY REGULATORY AUTHORITY AUTORITÉ DE RÉGULATION RÉGIONALE DU SECTEUR DE L ÉLECTRICITÉ DE LA CEDEAO TRANSMISSION TARIFF

More information

PROJECT COST TASK FORCE. June 2, 2011

PROJECT COST TASK FORCE. June 2, 2011 PROJECT COST TASK FORCE June 2, 2011 Table of Contents Introduction...3 RSC Motion 1...3 Problem Summary...3 RSC Motion 4...3 Problem Summary...3 Project Tracking Current Process...4 PCTF Recommendations...4

More information

Power Workers' Union (PWU) INTERROGATORY #1. Ref (a): Participant Information Package: Exhibit C1-2-1, Page 5 of 6, Table 2 (OM&A Expenditures)

Power Workers' Union (PWU) INTERROGATORY #1. Ref (a): Participant Information Package: Exhibit C1-2-1, Page 5 of 6, Table 2 (OM&A Expenditures) Filed: 0-0- 0-0 Tx Rates Schedule Page of Power Workers' Union (PWU) INTERROGATORY # Ref (a): Participant Information Package: Exhibit C--, Page of, Table (OM&A Expenditures) Table : 0 Board Approved versus

More information

Council for Education Policy, Research and Improvement

Council for Education Policy, Research and Improvement Introduction Council for Education Policy, Research and Improvement Review of Public Postsecondary Centers and Institutes Economic Impact of Centers and Institutes in Florida s Public Universities-DRAFT

More information

Fiscal Impact Analysis of the North Carolina Rural Job Creation Fund

Fiscal Impact Analysis of the North Carolina Rural Job Creation Fund Fiscal Impact Analysis of the North Carolina Rural Job Creation Fund Prepared for: Stonehenge Capital Company, LLC. Copyright 2017 All Rights Reserved Economic Impact Group, LLC. Dacula, GA 30019 March

More information

COLORADO FILM INCENTIVES

COLORADO FILM INCENTIVES COLORADO FILM INCENTIVES Economic and Fiscal Impact Analysis of Actual Film Budget Scenario on Colorado Conducted by: BUSINESS RESEARCH DIVISION Leeds School of Business University of Colorado at Boulder

More information

Section 24 COGENERATION AND SMALL POWER PRODUCTION

Section 24 COGENERATION AND SMALL POWER PRODUCTION Section 24 COGENERATION AND SMALL POWER PRODUCTION Cooperative is a member of Corn Belt Power Cooperative and Northwest Iowa Power Cooperative, generation and transmission cooperatives ("G&T" or "Corn

More information

GEORGIA STATE UNIVERSITY ANDREW YOUNG SCHOOL OF POLICY STUDIES FISCAL RESEARCH CENTER ATLANTA, GA FEBRUARY 2, 2005

GEORGIA STATE UNIVERSITY ANDREW YOUNG SCHOOL OF POLICY STUDIES FISCAL RESEARCH CENTER ATLANTA, GA FEBRUARY 2, 2005 GEORGIA STATE UNIVERSITY ANDREW YOUNG SCHOOL OF POLICY STUDIES FISCAL RESEARCH CENTER ATLANTA, GA FEBRUARY 2, 2005 SUBJECT: Analysis of a Tradable Motion Picture Credit for Georgia Prepared by: William

More information

EEI Survey of Transmission Investment. Historical and Planned Capital Expenditures ( )

EEI Survey of Transmission Investment. Historical and Planned Capital Expenditures ( ) EEI Survey of Transmission Investment Historical and Planned Capital Expenditures (1999-2008) Published by: Edison Electric Institute May 2005 2005 by the Edison Electric Institute (EEI). All rights reserved.

More information

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1

ROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 I. - Conditions and Definitions A. Contracts Before building an Extension, the Company may require the Applicant to sign a contract.

More information

Submitted by Western Power

Submitted by Western Power Final Determination on the New Facilities Investment Test for a 66/11 kv Medical Centre Zone Substation Expansion and Voltage Conversion of the Distribution Network Submitted by Western Power 19 February

More information

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY The Northeastern ISO/RTO Planning Coordination Protocol among PJM Interconnection, L.L.C. ( PJM ), the New York Independent

More information

THE ECONOMIC IMPACT OF FEARRINGTON PLACE

THE ECONOMIC IMPACT OF FEARRINGTON PLACE THE ECONOMIC IMPACT OF FEARRINGTON PLACE PREPARED FOR JESSE FEARRINGTON PREPARED BY COLUMBIA, SOUTH CAROLINA RESEARCH TRIANGLE PARK, NORTH CAROLINA APRIL 17, 2006 1 INTRODUCTION This report evaluates the

More information

UK Power Networks. Overall Cost Benefit Analysis

UK Power Networks. Overall Cost Benefit Analysis UK Power Networks Overall Cost Benefit Analysis Contents 1 Executive Summary 3 1.1 Analysis Conclusions 3 1.2 Summary Table 4 2 Introduction 5 2.1 Scope 5 2.2 Input Parameters 6 2.3 Asset Replacement/Refurbishment

More information

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

june 07 tpp 07-3 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper june 07 Service Costing in General Government Sector Agencies OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Contents: Page Preface Executive Summary 1 2 1 Service Costing in the General Government

More information

Alberta H. Charney, Ph.D. Marshall Vest, Director

Alberta H. Charney, Ph.D. Marshall Vest, Director Economic and Revenue Impact of $1 Million in Su s ta i n e d Ca n c e r Research Funds 1 Cancer Research Funds Impact Study By: Alberta H. Charney, Ph.D. Marshall Vest, Director Economic and Business Research

More information

EDISON An EDISON INTERNATIONAL Company

EDISON An EDISON INTERNATIONAL Company SOUTHERN CALIFORNIA EDISON An EDISON INTERNATIONAL Company (U 338-E) 2015 General Rate Case APPLICATION Workpapers Transmission & Distribution Customer Driven Programs and Distribution Construction SCE-03

More information

DECISION AND ORDER ON PHASE 1

DECISION AND ORDER ON PHASE 1 Commission de l énergie de l Ontario DECISION AND ORDER ON PHASE 1 HYDRO ONE NETWORKS INC. Leave to construct a new transmission line and facilities in the Windsor-Essex Region, Ontario. Before: Ken Quesnelle

More information

Maryland Offshore Wind Technical Conference

Maryland Offshore Wind Technical Conference Maryland Offshore Wind Technical Conference Process Overview, Application Checklist, and OREC Bid Forms presented by Seth Parker and Diane Rigos LAI Michael Drunsic DNV GL January 8, 2015 Overview Introductions

More information

Reinventing. an Enduring Franchise. Paul Steece Vice President and General Manager Electrical Markets Division. September 9, 2008

Reinventing. an Enduring Franchise. Paul Steece Vice President and General Manager Electrical Markets Division. September 9, 2008 Paul Steece Vice President and General Manager Electrical Markets Division Reinventing an Enduring Franchise September 9, 2008 1 Electrical Markets Division The Re-invention of One of 3M s Enduring Franchises

More information

Table 1 Economic Impact of the Local Healthcare System on Jefferson County. Multiplier Type Direct Impact Multiplier Total Impact

Table 1 Economic Impact of the Local Healthcare System on Jefferson County. Multiplier Type Direct Impact Multiplier Total Impact The Economic Impact of the Local Healthcare System On the Jefferson County Economy Executive Summary The healthcare industry is often one of the largest employers in a rural community and serves as a significant

More information

CA-NLH-59 Depreciation Methodology and Asset Service Lives Page 1 of 3

CA-NLH-59 Depreciation Methodology and Asset Service Lives Page 1 of 3 CA-NLH-59 and Asset Service Lives Page 1 of 3 1 2 3 Q. Re: Calculation Procedure: Please state all reasons the Company did not propose a change to the Equal Life Group calculation procedure. To the extent

More information

Let s Look at the Broad Picture Macroeconomics in Credit Risk

Let s Look at the Broad Picture Macroeconomics in Credit Risk Let s Look at the Broad Picture Macroeconomics in Credit Risk Hristiana Vidinova 30 November 2016 Experian and the marks used herein are service marks or registered trademarks of Experian Limited. Other

More information

Minnesota Printing Industry Economic & Fiscal Contribution

Minnesota Printing Industry Economic & Fiscal Contribution Demonstrating the Importance of the Printing Industry to the Minnesota State and Local Governments Minnesota Printing Industry Economic & Fiscal Contribution The printing industry in Minnesota contributes

More information

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014

NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 NORTHERN INDIANA PUBLIC SERVICE COMPANY Attachment GG True-Up Adjustment For the Year Ended December 31, 2014 Attachment GG Projected Proportion Actual True Up Revenue of Revenues Revenue Interest allocated

More information

State of Wisconsin Department of Administration Division of Energy

State of Wisconsin Department of Administration Division of Energy State of Wisconsin Department of Administration Division of Energy Focus on Energy Public Benefits Evaluation Low-income Weatherization Assistance Program Evaluation Economic Development Benefits Final

More information

Rating Criteria for Power Distribution Utilities. February 2018

Rating Criteria for Power Distribution Utilities. February 2018 Rating Criteria for Power Distribution Utilities February 2018 Criteria contacts Pawan Agrawal Chief Analytical Officer CRISIL Ratings Email: pawan.agrawal@crisil.com Ramesh Karunakaran Director Rating

More information

THE ECONOMIC IMPACT OF THE 2013 GENERAL OBLIGATION BONDS FOR AFFORDABLE HOUSING IN AUSTIN NOVEMBER 2016

THE ECONOMIC IMPACT OF THE 2013 GENERAL OBLIGATION BONDS FOR AFFORDABLE HOUSING IN AUSTIN NOVEMBER 2016 THE ECONOMIC IMPACT OF THE 2013 GENERAL OBLIGATION BONDS FOR AFFORDABLE HOUSING IN AUSTIN NOVEMBER 2016 INTRODUCTION Civic Economics and HousingWorks are pleased to present this analysis of the economic

More information

The Centre for Spatial Economics

The Centre for Spatial Economics The Centre for Spatial Economics The Economic and Fiscal Impacts of the New Prosperity Mine on British Columbia Prepared for Taseko Mines by Ernie Stokes The Centre for Spatial Economics October 2011 TABLE

More information